Khazzan Project

Commissioning Control of Work Procedure

3.0. ROLES AND RESPONSIBILITIES


3.1.

COW SINGLE POINT OF ACCOUNTABILITY (SPA)

The SPA for the Petrofac Commissioning Control of Work shall be the Petrofac Commissioning Manager
and shall:

Ensure CoW management and conformance as per this CoW Management Plan

Ensure implementation of this plan and supporting CoW processes within their area of control

Ensure the competency and capability of workforce required to conform to the requirements of this plan

Approve Hazardous Identification and Task Risk Assessment (HITRA) if within approval level or obtain a
higher level of approval if the residual risk is higher than their level of authority on the HITRA approval
matrix

Ensure compliance with Deviation approval process

Ensure self-verification, CoW audits, assurance and lessons learned processes are in place and effective

3.2.

SITE AUTHORITY (SA)

The SA has the overall accountability for the execution of CoW requirements at site
Authorization:

Authorize personnel to Area Authority (AA), and Isolating Authority (ISA) roles.

Ensure that the authorization document (Appendix **) clearly identifies the competency and authorization
for the specific discipline. For example Ground Disturbance, Lifting, WAH, CSE etc.

Ensure that the authorization document clearly identifies the discipline for which the person is authorized
as an AA, ISA and PA. For example, AA, ISA and PA for electrical work; AA, and PA for civil work, etc.

Ensure delegation of any of the roles responsibilities are documented and risk assessed if required

Authorize all Work Permits prior to commencement of work

Procedures:

Implement CoW processes and other supporting CoW requirements

Verify that CoW activities are monitored

Training and Competency:

Ensure that the task workforce is competent, which includes role specific training, experience,
certifications, qualifications and displays appropriate behaviours

Verify site CoW training and competency register

Planning/SIMOPS:

Approve break-in/unplanned tasks that are raised after the daily CoW meeting and not on the approved
schedule

Chair Daily PTW Meeting and ensure SIMOPS risk(s) are properly assessed and managed

Task Risk Assessment:

Ensure that Task Risk Assessments (TRA) are undertaken and the TRAs are approved by the required
level of authority

Approve site risk-assessed procedures and routine permits, and verify they are maintained in a central
register

Approve tasks as detailed in the Task Risk Assessment Table (TRAT)

Self-Verification:

KZ01-CG-PLN-00-XXXX

Page 7 of 24

Rev: A01
Project Internal

Khazzan Project

Commissioning Control of Work Procedure

Conduct self-verification of CoW/PTW requirements including self-verification of any other processes


associated with CoW/PTW.

Others:

Verify that crew change/shift handovers, involving CoW are in accordance with the requirements in
Section 13.2

Manage non-conformances to the CoW Plan/PTW procedure.

HWOF:

3.3.

Ensure HWOF is suitably risk assessed, authorized and controlled according to site conditions

AREA AUTHORITY (AA)

The AA role is pivotal to the CoW/PTW process for the management and control of non-routine tasks. The
AA is responsible for the day-to-day management of the PTW process, task hazard identification and risk
control measures associated with work performed within allocated area of responsibility. There may be more
than one AA at any particular site. The AA shall:
Permits:

Report to the SA and have overall responsibility for ensuring that Work Permits are issued and work
activities are carried out in accordance with the PTW System

Ensure that any cancelled permits are replaced with new ones

Issue and revalidate permits

Approve daily activity in area(s) of control

Conformance to Procedure(s):

Ensure conformance to procedural requirements

Be familiar with Khazzan Development Commissioning CoW related documents and ensure that the
protocol for permitted work, routine permits and risk assessments are practiced

Task Risk Assessment:

Manage hazards and risks associated with SIMOPS and liaise closely with the affected AAs and
Performing Authorities (PAs) when planning the work

Conduct pre-job site visits with the PA and identify all hazards and appropriate controls that need to be
included in the PTW. This may be delegated to Area Authority Designate depending on activity.

Ensure that the appropriate level of hazard identification and risk assessment has been carried out for the
task (Level 1 or 2)

Ensure that all the appropriate control measures have been put in place prior to a permit being issued,
confirming that the PA fully understands the scope of the work, tasks, hazards and controls.

Training and Competency:

Report to SA if not competent for that task and or particular discipline/area for which they are being
assigned as an AA

Ensure that the Authorization document has clear identification of the area for which the PA is competent

Ensure that the PAs, including Confined Space Attendant and Entrant understand their duties and are
competent to perform them

Isolations:

Ensure conformance with the Energy Isolation Procedure

KZ01-CG-PLN-00-XXXX

Page 8 of 24

Rev: A01
Project Internal

Khazzan Project

Commissioning Control of Work Procedure

Ensure that the isolation(s) is/are in place prior to allowing an associated permit to be issued through an
approval of isolation design, Isolation plan, and control of isolation implementation

Work site monitoring and Completion of Work:

Ensure that the worksite inspections are carried out before, during and after the performance of each task
(some of this task activity for during and after work completion may be delegated to a competent
nominated person)

Ensure that there is a walkthrough of every work site activity after completion of work to manage correct
plant re-instatement and good housekeeping

Review active permits, site conditions and implementation of hazard control measures at the work site to
determine if the proposed work can continue simultaneously with other PTW tasks

Approve reinstatement of plant and/or equipment

Responsible to manage change in permit work conditions (e.g. monitoring frequency).

Others:

Ensure that adequate handovers take place at shift change, crew change or other change out/over of
AAs, PAs, ISAs and IAs

Foster the culture to STOP any Unsafe Job and record any such event

All equipment used for any specialized activity, for example, fall arrest and rope access is subject to
adequate inspection and maintenance by competent people

3.4.

AREA AUTHORITY DESIGNATE

The Area Authority Designate (AAD) role shall serve as a delegate for the AA role. However, the
accountability for ensuring hazards are identified and the associated risks are controlled cannot be
delegated; it is only the responsibility for carrying out certain elements of the AA role that can be delegated
by the AA to the AAD. The AA cannot delegate the responsibilities listed below:

AA accountability

Approval of Level 2 TRA (requiring AA approval as per the approval Matrix)

Control of the ICC

Worksite visit for high residual risk tasks

Attendance of the daily CoW meeting

Approval of the daily activity in the AAs area

Change of permit to work conditions (e.g. monitoring frequency)

Approval to reinstate plant and/or equipment

3.5.

AFFECTED AREA AUTHORITY (AAA) FOR SIMOPS

This applies where there is more than one AA on a site or if the activities carried out in one area impinge or
impact on activities in another area (SIMOPS). In this case, the AA shall inform all affected AAs. This role is
not an additional CoW role but the AA of the affected area is called as AAA. Other responsibilities of the
AAA remain same as the AA. The AA shall ensure that all AAAs:

Countersign the Permit to Work from the adjoining area to confirm that they are aware of the activity
taking place and that the hazards can be effectively managed with the specified controls

Communicate with personnel working within his area who may be affected by the adjacent activity to
ensure that they understand the potential impact on their activities.