Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
BUILDING COMMISSIONING
Ad\:ctrrrtrgc,.v of Bfrildirt
Cf~ftifrri,s,siijfiifi~
Tetrrti
..
.......................
..................................
Corrrrrrissioriirig Arrtlio
......................................
Co.sr F(r(.ror,s............................................................................
C o f f f f f ~ i , s . s ; ~Ohjectilu!,s
~ f l i f l ~ ............................................
PJugr(IffIN f l d Predesigrl CorrrrffissiorrirlgPhcrse ...........
41 . I
41. I
4I.1
4 I .2
41.2
41.2
41.3
41.4
41.4
...........................
41.5
41.6
Commissioning Team
Tlie size and maheup of tlie commissioning team depends on the
size antl complexity of tlie project aiid the owners desire to invest
i n quality assurance. The responsibility of each member of the commissioning team is tlocumented in the commissioning plan.
All participants i n the construction project have a commissioning
responsibility. Participants include the commissioning authority,
owner, design professionals, construction manager, general contractor, subcontractors. operation and maintenance manager, suppliers,
and equipment manufacturers. The project building operation, production. aiid maintenance managers need to be brought into the commissioning process early. preferably during the predesign phase.
Their knowledge of occupancy. special lighting. anticipated equipment loads. aiid other factors should influence the design and set performance objectives. Adtlitionally. the early participation of both the
TAB ant1 HVAC controls coiitrilctors is also important because their
experience can provide guidance on space requirements. balancing
devices. probe antl control locations, and accessibility to equipment.
Commissioning Authority
The commissioning authority is a qualified professional, company. or agency that iinpleriieiits the overall commissioning process
i n cooperation with the commissioning team as specified in the contract docunients. Tlie commissioning authority has a significant
41.2
impact on the project and must be able to take responsibility for acting on or verifying the performance aspects of the project. However,
the appointment of a commissioning authority does not alter other
professional or contractual obligations. The owner should select a
qualified commissioning authority who has proven experience and
is registered as a professional in a recognized organization.
The commissioning authority, should understand all building
systems being commissioned. The authority should also be familiar
with applicable design and building standards, use of test instruments and equipment for functional testing, and interaction of the
various systems. Additional qualifications of the commissioning
authority may be found in ASHRAE Guideline 1.
Responsibility. The primary responsibility of the commissioning authority is to inform the owner of the status, integration, and
performance of all tested systems in the facility.
Information. The commissioning authority should function as a
catalyst and initiator to disseminate information and assist the
design and construction teams in verifying satisfactory completion
of construction. The authority verifies system completeness, performance, and adequacy to meet intended performance standards. The
authority may provide such services as design review, establishing
commissioning specifications. construction observation, spot testing, verification, and functional performance testing. Turnover
information services may include providing performance and operating information (i.e., operating and maintenance manuals, training) to the responsible parties.
Quality Assurance. The commissioning authority assists all
parties in achieving a high level of installation quality and system
performance. Through an effective turnover process, the personnel
responsible for the facility should be able to maintain that high level
of systems performance.
Observation of Tests. The commissioning authority should
observe and coordinate testing as required to ensure the performance meets design intent and contract documents.
Documentation of Tests. The commissioning authority should
document or witness the results of the performance testing. The
authority should provide or approve test forms to be used by representative parties to ensure a consistent format and to specify the type
of information to be recorded.
Resolution of Disputes. The commissioning authority should
remain an objective party, present on the project, with specific
project knowledge. Should disputes arise, the authority should be
available to determine the scope and extent of the problem and educate the involved parties as to the nature and extent of the problem.
The owner or their designate should preside over resolution of problems as specified in the contract documents.
Deficiencies. The commissioning authority should verify that
deficiencies found during the commissioning process are corrected.
Acceptance. The commissioning authority should determine
and advise the owner of the date of acceptance for each component
and system. Acceptance may extend to representing the owner with
respect to warranty start data, substantial completion, certificate of
occupancy, assembling or coordinating turnover documents. and
scheduling training.
'Ibrnover. The commissioning authority participates in the successful transfer of control of the facility from the construction team
to the owner.
Cost Factors
No reliable data are available to determine the cost or cost-contributing factors of building commissioning. The number of costcontributing factors depends on the size and complexity of the
project and the willingness of the owners to invest in the appropriate
commissioning process.
A wide range of professional services, comprehensive documentation, system testing, and operator training are available to be
included in the scope of commissioning. One intent of commissioning
is to fully recover its own capital investinent over the life of the system
through improved management antl owner satisfaction.
Commissioning Objectives
The owner should expect the following results from
commissioning:
requirements
Retlucetl risk exposure because problem are identified earlier
Improved knowledge for use in future designs and installations
Benefit of supporting professional input, leutling to the most costeffective design and operation
Reduced number of interference drawings during construction,
clue to improved coininunication antl coordination
Contractors can expect tlie following benefits:
This phase should begin ;IS close to project inceptioo ;IS possible. The information gathered is used to develop the tlesigii of the
system and establish a method to evaluate its performance.
Owner's Program. This program outlines the owner's overall
vision for the facility antl expectations as to how it will be used and
operated. The owner's program should contain known performance
Building Commissioning
go:ils antl objectives along with budget constraints, schedules, antl
orher litnitations. Typically, the rechnicnl aspects of the owner's
prograin incltitles use of the facility, user needs. occupancy requirenieiits, type of construction, systeiii functions, as well as energy, air
quality. power quality, antl environmental performance criteria. Tlie
prograin should tlefiiie the scope of the coiiiiiiissioiiiiig process and
the preferred organizational structure. It should contain a11 requirenieiirs needed to develop the initial design intent document. This
critical tlocuriient forms the basis froiii which all other documentation is developed.
'leani Selection. The commissioning authority and the design
te;iiii should be selected at this rime. Tlie operations antl inainteii:iiice (O&Mj personnel should be identified antl encouraged to
leiitl their knowledge to ensure that iin~)ortantO&M issues are coiisidered iii tlesigii antl during coiiimissioning.
Coniniissioning Plan. This tlocument or group of tlocunients
tlefiiies the cominissioning process or schetlule at the various stages
of project development. It continually evolves and is updated as the
design antl construction of the building progresses.
As tlie design concepts evolve from tlie initial design intent tlocuiiieiit, a preliminary coiniiiissioning plan is developed that outlines
the process required to coinmission the building systems. Tziis plan
should develop the extent of the commissioning process aiid coininunicote it to a11 project participants. It llittst include the scope of
the process. the time required for coiiipletion. and an organizational
c1i:irt indic:iting reporting relationships. The scope antl potential
cost :IS outliiietl in tlie preliininnry coiiiinissioning plan then should
be evaluated aiid approved.
Tlie roles antl responsibilities of each project participant with
respect to cominissioning are itleiitifietl i n the preliminary corntiiissioning plan. This plan should recognize the owner, coniiiiissioiiiiig
authority. design professional(s). operation and iiiaiiiteiiaiice staff,
coiitractors, vendors, and other specialists as appropriate. Tlie teani
inny be expantled or motlifietl as the project progresses.
Systenis Rlanual. Material for the systems niaiiual should begin
to be compiled. The manual provides tlie information neetletl to
uiitlerstxitl, operate. and inaintain each systein. In this phase. tlie
iiiaiiu:il will contain a stateiiietit tliat conveys the required functional
oper:ition i n all norinal antl eiiiergeiicy modes of operation, The initial tlesigii iiitent tlocuriient shall be iiiclutletl in the systerlis rnanual.
which is uptlated tluough all phases of the project.
41.3
When approved, the design intent document should be used as
the starting point for the tlevelopment of the contract documents
antl referred to in case of aiiibiguities or uncertainties about project
design. Changes to the design intent occurring during the course of
the project should be documented, reviewed, and approved. The
design intent docuiiieiit iiiay be included in the contract documents
as a reference. The final design intent document becomes part of the
systems manual.
Conceptual designs for HVAC systems and other building systenis should be prepared to provide options to the owner that meet
the owner's program.
Tlie design intent is updated and defines design assumptions,
building energy perforniance. perforinance standards of the proposed systeins, the iiiost appropriate conceptual approach, space
requirements. zoning, and other requireinents that affect building
use aiid aesthetics.
Basis of Design. Tlie basis of design should respond to and be
coiisistent with perforiiiance criteria specified in the owner's prograin. The basis of design includes the requirements for each occupancy, activity, aiitVor physical area of the proposed facility. The
basis should reference ASHRAE or other applicable standards,
local builtliiig codes, and environmental quality objectives.
Because the design ititeiit iiiay be revised and changes may be
accepted as design concepts, tlie basis of design should be reviewed
with regard to these changes ancl updated as needed. The final versions of the design intent docutiieiit aiid its reference to the basis of
tlesigii should be included i n tlie contract documents.
Coniniissioning Plan. During the design phase, the approvedpreliminary commissioning plan may expand the planned activities for
all participaiits relative to the coiiiniissioning process. Updated inforiiiatioii iiicludes work roles aiid responsibilities, project organization
chart. antl scheduling of the process. The plan identifies which syst e m , system components. arid functions will be tested on this project.
This document also sets the scope for the testing specification.
Observations of the progress of construction are important for
updating the coinmissioning plan, particularly with respect to the
schecluling of activities. In addition to construction requirements.
observations should be conducted to ensure compliance with manufacturers' installation instructions.
Commissioning Specificatiun. The building systems commissioning specification is part of the project specification. This specification is required to contractually implement the post-design
phases of the process. Tlie commissioning specification is a detailed
description of the scope and objective of commissioning during the
construction, acceptance, and post-acceptance phases of a project. It
liiust specify the scope of work, roles, responsib
iiieiits of each commissioning teain member. and their lines of
authority. This specification is needed by contractors so that they
can include in their bid the support required by commissioning,
which includes meetings, training, testing, etc.
Tlie coiiiiiiissioiiiiig specificatioii should detail testing requirenieiits, acceptance phase procedures for verification, functional perforiiiance testing acceptance criteria, and any other required
acceptance phase procedures. It should include a list of equiptnent
aiitl system to be evaluated. along with checklist formats and sample test f o r m .
Tlie scope of work in tlie specification should identify the
required skills aiid qualifications of the commissioning team.
iiiclutliiig operation and maintenance personnel. It should include a
section for each trade involved iii the construction of the building,
detailing their scope of work iii the coiiiinissioning process. Management of turiiover docunients and training must be specified.
Contract Documents. These docunients should clearly reveal,
describe. aiid fulfil1 the requirements specified in the design intent
tlocuinents.
Design Intent Cunipliance. Tlie contract documents should be
reviewed to ensure consistency and that they correctly represent the
41.4
current design intent document. Results are reported to the owner.
The contract documents then should be accepted or rejected by the
owner or the owners designee.
System Coordination. Part of the review of drawings includes
verifying system coordination. All other specified building systems
including other mechanical, electrical, fire-safety, and life-safety
service requirements, should be coordinated with the HVAC equipment and systems.
C o n s t r u c t i o n Commissioning Phase
Objectives. During the construction phase, all systems are
installed, started. and operated. This phase includes tlie following
objectives:
Review submittals
Finalize details of the commissioning plan
Conduct periodic commissioning team meetings
Maintain documentation of all tests. observations and issues,
verify system installation
Verify equipmentkystem start-up and operation
Verify performance of temperature and building management
controls
Verify testing, adjusting, and balancing (TAB) work
Coordinate as-built drawings
Manage assembly, indexing, and turnover of all documents
Coordinate O&M training
During installation; O&M personnel should observe and monitor
the systems and testing. Through this procedure, they should
develop a better understanding of the intended operation and performance and become familiar with the location of equipment and
devices, including those that may be hidden when construction is
complete.
Procedures. During the construction phase, the following activities are part of commissioning:
Review submittals for performance parameters
Detail the commissioning plan
Create project-specific test procedures and checklists needed to
supplement the specified tests
Make necessary observations and inspections
Manage documentation of all tests/observations including
turnover documents
Report progress and deficiencies to all parties involved
Coordinate training of operations and maintenance personnel
The updated operation description should be included as part of
the systems manual. This description should be updated and combined with equipment data, including performance data, for training
of and subsequent use by the operations and maintenance staff.
Regularly scheduled meetings of the entire project team should
be held to communicate issues to all concerned, resolve conflicts,
report on the progress of the commissioning process, identify urgent
work, and identify and resolve deficiencies. This site coordination is
critical to ensure a quality commissioning process.
Testing and calibration of controls should begin concurrent with
and be completed prior to the completion of the TAB work. Specified TAB work must be performed prior to acceptance procedures.
Prior to functional performance testing, operational tests should be
conducted on equipment, duct, pipe, and control systems to verify
that pressures, flow rates, and control functions meet design
requirements. The training program for operations and maintenance
personnel should be coordinated with the appropriate participants.
Submittals. Submittals should be reviewed prior to systems
installation. Submittals include shop drawings, equipment submittals, and testing and balancing procedures and forms. Submittals
should also include test procedures, report forms, data sheets, and
checklists that will be used in the functional performance testing.
Equipment submittals should include full and pkt-loatl perforiiiaiice data covering the entire operating range for each piece of
equipment. The equipment operations and maintenance inforination
(including parts lists, installation instructions, and special tool
needs) should be submitted in accordance with specification
requirements and reviewed for completeness. clarity. ant1 accessibility. Commissioning submittal review is intended to verify correct
inforination on test documents. It does not supersede or stlpp1:llit
design commissioning review.
Commissioning Plan. Tlie cuinmissioning plan sliuultl be
updated tu define the on-site activities required Cur implementing
the commissioning specifications. This plan inust be project specific and reflect the actual equipment that will be insralletl. Tlie
commissioning plan should
Define each partys role in the inspections, verification, testing
and training
Detail the schedule of inspections tluring construction
Develop the schedule for verification antl functional performance
tests
Define the process for reporting and correcting any tleficieiicies
identified
Detail any training sessions for operatiolis antl iiiaiiitenmx
personnel that are to take place during this phase
Documentation. All commissioning activities that occur tluring
the construction phase should be tlocumentetl. The equipment and
control sequence documentation developed during the design phase
should be updated to match the equipment supplied on tlie project.
Acceptance Commissioning P h a s e
Objectives. During the acceptance phase, verification, functional performance tests, and other acceptance procedures takes
place. The objectives of the acceptance coniniissiuniny phase are tu
41.5
Building commissioning
The specific tests required and the order of testing will vary
tlepentling on the rype and size of system, number of systems,
sequence of construction, relationship between building systems,
and specific owner/tenant program requirements.
During functional performance testing, a failure in performance
of a part of the systeni or of a component may be revealed. Any performance deficiencies must be evaluated to determine the cause antl
whether they are part of tlie contrnctual obligations. After corrective
iiieasures are completed, tlie functional performance test that failed
inay be repeated.
Functional Perforniance Test Procedures. Testing should be
perforinell as ilefiiietl in the coininissioning specification and
t1et;iiletl in the contract tlocunients. If any test cannot be completed
because of a deficiency outsiile the scope of the systeni, the deficiency should be tlocuinented antl reported to the owner. Deficiencies should then be resolved antl corrected by appropriate parties
and the functional performance tests reschetluletl.
If the coinmissioning specification indicates that specific seasonal testing is to be contluctetl. the appropriate initial performance
tests shoultl be completed and ilocuinentetl ant1 tlie adtlitional tests
schetluled. The parties responsible for the seasonal tests should
41.6
commissioning tlocuments plus :my updates from the coininissioniiig of previous modifications.
Post-Acceptance Coniniissioning Procedures. The tllree itlentifiable levels of post-acceptance coiiimissioiiing are as follows:
Post-Acceptance C o m m i s s i o n i n g
Post-acceptance commissioning is the continued adjustment,
optimization, and modification of building systems to meet specitied requirements. It may be used on existing buildings or even on
a facility that has previously been commissioned. It includes updating documentation to reflect minor setpoint adjustment, maintenance and calibration, major modifications, and provision for
ongoing training of operations and maintenance personnel.
The objective of post-acceptance commissioning is to maintain
the performance throughout the useful life of the facility in accordance with the current design intent. The extent of post-acceptance
commissioning is determined by the scope of modifications and
occupancy changes that are made to the facility.
Post-acceptance commissioning stalts from the base of existing documents. This documentation includes all available original