Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1
Key Design Parameters for Rail Bridges
During the course of interaction with various Railways, I have
come across some design parameters adopted for construction of
important bridges like one over Ganga at Mungheyr, Kosi and
Brahmaputra at Boghibeel, which are not at all in consonance with
Railways own codes. Indian Railways have been pioneers in design and
construction of important bridges and have the unique distinction of
bridging all the important rivers of the country for over 150 years. The
design of well foundation is so well known and construction methodology
is so well established that it should have been possible to design and
construct them with much more confidence.
(a)
Using
Laceys
(Cumecs)
formula
for
Design
discharge
{DL=0.47 (Q/f)}
f is silt factor
scourable depth).
The value is generally taken as 1.00 which is in itself quite
conservative.
Scour depth
(b)
sinking
effort
available
may
be
calculated
by
simple
H1 + (w-) X H2 + (w-)
H3
w
H3
w
in (m)
H1
___________
___________
H2
xxxxxxxxxxxxxx
xxxxxxxxxx
_____
H3
formula:-
This is calculated below LWL. But empirical values are also safely used
with fair degree of confidence.
Stiff and soft
Clay
Dense sand
Dense gravel
Design of Steining:
The normal Railway practice is to provide plain cement concrete.
sectional area and ties of about 0.04% of the volume per unit length is
found to be adequate and should be adopted.
F= M - P
Z
A
F = tensile stress in t/m2
M = Moment in t m
A = Cross Section area in sq.m
Z = Sectional modules of well in m3
q = Density of soil = 1.5 t/m3
P = Total lateral pressure in t/m2
The above was used in checking stresses in Mokamah bridge over
River Ganga. Details in Technical Paper No.336 Ganga Bridge at
Mokamah by Shri H.K.L.Sethi.
Check for Bearing Capacity:
Most of deep foundations are on sandy beds at foundation
level. The allowable bearing capacity can be calculated by
q = 5.4 N2B + 16 (100 + N2 ) D
q = Allowable soil pressure in kg/sq.m.
N = SPT value.
B = Smaller dimension of well cross section in metre.
D = Depth of foundation level below scour level in metre.
For calculating Bending moment both active and passive soil
pressures around the well should be considered.
A factor of safety usually of 3 is taken.
4.
It is
customary to place the bottom of the well cap at LWL. This is done in
order to enable inspection of the well cap.
Low water level is determined from gauge levels of the river for as large
period as possible particularly from consideration of as long working
period as possible. From the available charts, LWL adopted should give
ideally 150/180 days for working. Of course in river like Bramhaputra
this is not available where maximum time available is 130/140 days.
Thus LWL is not necessarily the lowest gauge level.
This is also
important so that the well cap can be cast without use of coffer dams etc.
5.
Well Curb:
Most important element of well curb is the cutting edge. This is
between 2.8/3.0 metres, which will give the sinking effort of over 5t/m3.
Steining concrete could be of M20 (200 kg/cm2) to be treated as
plain concrete although ordinary M15 (1:2:4) concrete has served very
well in the past.
The well curb is usually of M25 (250 kg/cm2)
6.
Pier Shaft:
The pier is designed as column subjected to vertical forces and
where Z = 2c
.
.ka
(ii)
c =
Density of soil.
Cohesion
of
has served successfully for over 100 years, is to use crated boulders in
alluvium deposits for launching aprons. The size of crate is determined
on the basis of water velocity to prevent it being swept and lifted away.
The basic principle of the launching apron is best described as the one of
a carpet which takes the shape of the scoured bed. The bottom of the
apron is normally placed at LWL.
In such
cases
also,
it
is
customary to
secure
these
blocks by
proper
methods(chains anchored in the shore). They are very costly and may be
impossible to execute, if quantities are large both from the point of view
of casting and handling of concrete blocks.
smoothly and being flexible, easily take the shape of the scoured beds
and are not lost as in case of concrete blocks.
For pitching guide bunds, slopes also, boulders in the form of grids
are used.
The usual
( R.R.Jaruhar )
Member Engineering
06.06.2005.