Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Unit-VI
Prof Nitesh P. Tantarpale
Assistant Professor
PRMCEAM, BADNERA
Contents
water way, scour depth, depth of foundation, Afflux, clearance and free
board.
Critical combination.
2
PROF NITESH TANTARPALE, PRMCEAM BADNERA
One of the essential data for the bridge design is fair assessment of the
maximum flow which could be expected to occur at the bridge site during the
design period of the bridge.
Discharge
By a rational method.
Empirical Method
Rational Method
Waterway
The area through which water flows under a bridge structure is known as
waterway.
While fixing the waterway of a bridge, the following guiding principles must
be kept in mind to ensure safety of the bridge structures:
The increased velocity due to obstructed waterway should not exceed the
permissible velocity under the bridge.
The free board for high level bridges should not be less than 600 mm.
The maximum permissible velocity of flow (V) depends upon the nature of the
river bed as in Table
The velocity of flow of stream or river water should not be more than the
values mentioned in this table.
10
Afflux
The phenomenon of heading up of water on the upstream site of the bridge is called afflux
When a bridge is constructed, its components like abutments and piers, cause the reduction of the
natural waterway.
Due to this reduction in natural waterway, the velocity under bridge increases so as to carry the
maximum flood discharge.
This increased velocity gives to a sudden heading up of water on the upstream side of the stream or
river. The phenomenon of this heading up water is known as afflux.
Thus, greater the afflux greater will be velocity under down stream side of the bridge and greater will
be the depth of scour consequently greater will be the depth of foundation required.
Hence, determination afflux is necessary for the safe design of the bridge.
11
12
Determination of Afflux
Marriman's equations.
Molesworth's equations
13
14
CLEARANCES
To avoid any possibility of traffic striking any structural part clearance are
specified.
The horizontal clearance should be the clear width and the vertical clearance
the clear height, available for the passage of vehicular traffic as shown in the
clearance diagram
15
FREEBOARD
Free board is the vertical distance between the designed high flood level,
allowing for afflux, if any, and the level of the crown of the bridge at its
lowest point.
It is essential to provide the free board in all types of bridges for the
following reasons:
Free board is required to allow floating debris, fallen tree trunks and approach
Free board is also required to allow for the afflux during the maximum flood
discharge due to contraction of waterway.
Free board is required to allow the vessels to cross the bridge in case of navigable
rivers. The value of the free-board depends upon the type of the bridge.
17
S. No.
Type of bridge
Free board
600 mm
Arch bridges
300 mm
Girder bridges
600 to 900 mm
Navigational streams
2400 to 3000 mm
18
After determining waterway and economic span the length of bridge can be
determined by following relation
L = Nl + (N - 1) b
where
19
Scour Depth
The process of cutting or deeping of river bed due to action of water is called
scouring.
When the velocity of stream water exceeds the limiting velocity it causes
vertical cutting of the river bed, which is known as scouring.
It differs from erosions which causes horizontal widening of the river bed.
The normal scour depth is the depth of water in the middle of stream when it
is carrying the maximum flood discharge.
Case -1: When linear waterway of the bridge is equal to the regime width: In
this case, the normal scour depth is equal to the regime depth given by the
following Lacey regime equation.
20
Case -2: When linear waterway of the bridge is less than regime width
21
Maximum scour depth is the depth of water at the round obstruction to the
flow of water when the river carries maximum flood discharge.
It usually occurs at bends, pier noses and on the under stream noses of guide
banks provided for a bridge.
In case of a bridge on a straight reach of the stream having single span, the
maximum depth of scour should be taken as 1.5 times the normal scour depth of
water.
For bridge sites on curves or where cross current exists or when the bridge is a
multi-span structure, the maximum depth of scour should be taken as 2 times the
normal depth of scour.
In case of bridge causing construction, the maximum scour depth should not be less
than the value obtained by the following equations
22
23
Prevention of Scouring
At the site of bridge, the river bed soil should be such as to resist the
maximum velocity of water.
The shape of the piers should be designed in such a way that it may not cause
eddies and currents in water.
The river bed on upstream side, downstream side and the portion under the
bridge should be properly pitched with beams and long stones.
In the case of sandy beds, sheet piling may be done on under stream and
downstream sides of the bridge to prevent scouring.
Piles may also be driven in river bed, where scouring is likely to occur.
24
For bridges and culverts, the following loads, forces and stresses should be
considered where applicable. The loads and forces to be considered in
designing road bridge and culverts are listed below:
1.
Dead loads
2.
Live loads
3.
4.
Wind loads
5.
Lateral loads
6.
Longitudinal forces
7.
8.
9.
10.
Earth pressure
11.
Buoyancy
25
Temperature stresses
Deformation stresses
Secondary stresses
Erection stresses
26
Dead loads: The dead load carried by a bridge member consists of its own
weight and the portions of the weight of the superstructure and any fixed
loads supported by the member.
Live loads: Live loads are those caused by vehicles which pass over the bridge
and are transient in nature. These loads cannot be estimated precisely, and
the designer has very little control over them once the bridge is opened to
traffic. Classifications of load are:
Impact effect of live load: The impact is caused due to fact that moving
heavy vehicles over rough or uneven surfaces. The provision for impact effect
should be made by an increment of live load. The magnitude of the impact
depends not only on the span but also on the type of smoothness of the road
surface, the speed of the vehicle and the type of its tyres.
27
Wind load: Bridge structures are designed for the lateral wind forces, forces
should be considered to act horizontally and in such a direction that the
resultant stresses in the member under consideration are the maximum. The
wind force on a structure should be assumed as a horizontal force of the
intensity specified below and acting on an area calculated.
Lateral loading/loads:
(a) Force on railings and parapets : the railings and parapet should be
designed to resist a lateral force and vertical force each of 150 kg/m applied
simultaneously at the top of the railing or parapet.
(b) Force on kerbs: Kerbs should be designed for lateral loading of 750 kg/m
run of kerb applied horizontally at top of the kerb.
28
Braking effects resulting from the application of the brakes to braked wheels.
Braking force is invariably greater than tractive efforts.
29
Force due to water currents: Any part of a bridge which may be submerged
in running water should be designed to sustain safely the horizontal pressure
due to the force of the current.
30
31
Maintenance of Bridges
R.C.C. works must be inspected for the cracks and if any cracks are found,
they should be sealed as soon as possible.
32
33
Strengthening of Bridges
In the past, live load carried by a bridge was very light as compared to the
dead load. There has been a tremendous increase in the carrying capacities of
our transport vehicles. The road system however, has not sufficiently
developed to cater for such increase in payloads. There is a terrible need for
improvement of the old and out of service bridges on our roads.
34
35
To fill large voids in honey combed concrete by cement grouting so that quality of
concrete is improved and cover to reinforcement is obtained.
To impact extra shear strength to girders when shear cracks appear on the girder,
by providing shear plates.
Grouting: High pressure grouts are not useful for strengthening of R.C.C.
bridges. Therefore grouting should be done by hand operated pump with low
pressure operations for cracks more than 0.25 mm in any bad concrete, we
may employ solid suspension grout such as cement water or cement sand
water with water cement ratio 0.47 to 0.52. For finer cracks, we may employ
chemical grout as epoxy grout.
For thin cracks and pressure, epoxy should be used under pressure.
36
I-Beams: R.C.C. beam and slab bridge - In this type, the beams are
strengthened by providing steel I-beam on each side of the existing beams. In
case of longer spans the load from the existing beams are directly taken away
by steel cross girders supported on steel built-up girders.
37
Masonry Arch Bridges: They are usually strengthened by first removing the
filling above the arch and then casting R.C.C. arch slab on the top of the
roughened extrudes, the slab is securely keyed into the abutments.
When the arch is too weak to hear loud more than its own weight, then a new
R.C.C. arch must be built several centimeters above existing extrudes with
the help of removable shuttering.
38
(e) Steel Bridge: They are strengthened by providing extra steel plates or
angles or concrete encasements.
(f) Suspension Bridge: They are usually strengthened by providing additional
39