Sei sulla pagina 1di 10

Table of Contents

1. Project Data................................................................................................................ 2
2. Project Scope and Site Description.........................................................................2
2.1. Location and General Composition...................................................................2
2.2. Scope of Works..................................................................................................... 3
2.2.1. Roads & Site Clearance................................................................................3
2.2.2. Site access and traffic management..........................................................5
2.2.3. Road Markings and Signs.............................................................................5
2.2.4. Pavements...................................................................................................... 6
2.2.5. Utilities............................................................................................................ 6
2.2.6. Street Lighting............................................................................................... 8
2.2.7. Intelligent Transport System (ITS).............................................................8
2.2.8. Surface water Drainage.............................................................................. 10
2.2.9. Environmental.............................................................................................. 10
2.2.10.

Foul Sewerage.......................................................................................... 10

2.2.11.

Treated Sewerage Effluent (TSE)...........................................................10

2.2.12.

Landscape.................................................................................................. 11

2.2.13.

Public Utility Services..............................................................................13

2.2.14.

Inspection of Site..................................................................................... 13

2.2.15.

Protection of Underground Services and Traffic Diversion...............13

2.2.16.Coordination with other Contractors.......................................................13


3. Planning Methodology............................................................................................. 13
4. Construction Approach:.......................................................................................... 14
4.1. Package 1............................................................................................................ 15
4.2. Package 2............................................................................................................ 67
5. Assumptions for the Baseline programme:.......................................................104
6. Baseline Programme Description:.......................................................................104
6.1. General.............................................................................................................. 104
6.1.1. Construction milestone:...........................................................................104
6.1.2. Mobilisation................................................................................................ 104
6.1.3. Permits/Approvals :................................................................................... 105
6.1.4. Provisional Sum Instruction.....................................................................105
Baseline Schedule
Page No: 1

Design and construction of lateral interceptor sewers, Al Wakra

6.2. Engineering....................................................................................................... 105


6.2.1. General Submittals: ................................................................................105
6.2.2. Material Submittal & Approval: ............................................................105
6.2.3. Method Statement Submittal & Approval : .........................................105
6.2.4. Subcontractor Submittal & approval:....................................................105
6.3. Procurement:.................................................................................................... 105
6.4. Construction..................................................................................................... 105
6.4.1. Part-1........................................................................................................... 105
6.4.2. Part 2........................................................................................................... 106
6.5. Project Close Out............................................................................................. 107
6.6. Working hours:................................................................................................. 107
6.7. Programme Requirements:............................................................................ 107
6.8. Critical Path :.................................................................................................... 107
7. Risk Assessment:................................................................................................... 146

Contract:

1. Project Data

Baseline Schedule
Page No: 2

Design and construction of lateral interceptor sewers, Al Wakra

DESIGN AND CONSTRUCTION OF


LATERAL INTERCEPTOR SEWERS, AL
WAKRA
(LIS-02) - (C727/2)

Client:

Public Work Authority

ENGINEER:

CH2M HLL international B.V

2.1.1 The City of Doha is experiencing significant growth, and the need for
an efficient, flexible and reliable wastewater management system is
vital. The current pace of growth is posing major challenges for the
existing drainage infrastructure. The Authority is the service provider

Consultant:

for sewerage services in Doha, including the sewerage collection

Contractor:

QBC Qatar Building Company

Project Start Date:

04th October 2015

Project Completion Date:

15th December 2018

network and associated treatment works.

2.1.2 To address the need for improvements, the Authority has embarked on
a major
programme of expansion and upgrades that consists of numerous

Contract Duration:

1,169 days

works currently in various stages of development and completion. The

Contract Value:

QR. 824,849,867.62

Inner Doha Re-sewerage

Maintenance Period:

365 days.

Implementation Strategy (IDRIS) Programme is a world-class solution


developed by the Authority to upgrade and expand the sewerage
infrastructure in order to accommodate the projected population
growth for an additional 1 million people in Dohas oldest area the
south catchment (around 680 km2).

2.1.3 IDRIS is strategic in nature and was developed to convert the foulsewer drainage in the Doha South Catchment from a pumped network
to a gravity sewer network. The IDRIS Programme both supports and
contributes to achieving the Qatari National Vision 2030 to transform
Qatar into an advanced country capable of sustaining its own
development and providing a high standard of living for its people. The
Authoritys vision calls for the delivery of state-of-the-art, sustainable,
world-class buildings and infrastructure that can fulfil this vision.
2. Project Scope and Site Description
2.1.

Project Background

2.1.4 The IDRIS scheme is comprised of a number of Lateral Interceptor


Sewers (LIS) that will be used to intercept flows in the existing high-

Baseline Schedule
Page No: 3

Design and construction of lateral interceptor sewers, Al Wakra

level system and transfer them into a new deep-trunk sewer; thereby,
relieving the existing overloaded system. The deep-trunk sewer, known
as the Main Trunk Sewer (MTS), has an internal diameter (ID) ranging
between 3.0 and 4.5 meters (m) and will transfer the flows by gravity
for a distance of over 40 kilometres (km) south to a Terminal Pump
Station (TPS) located at the downstream end of the MTS. The flows will

Project Location

then be lifted into the New Doha South (NDS) Sewage Treatment Works
(STW) for treatment. The reclaimed Treated Sewage Effluent (TSE) will
be suitable for irrigation purposes and will be returned to Doha
metropolitan area.

2.2.

Scope of Works

The works include, but are not limited to, the following:
2.2.1.

Roads & Site Clearance

DW013 will require approximately 23.075 km of road to be built,


consisting of the
3. Planning Methodology
QBC will start the work with the submission and approval of necessary permits for
various pre-construction plans, work method statements, material submittal for
Procurement & Traffic management Plan etc., in this stage the mobilization of the
site offices, the required Manpower & machinery will be carried out.
After receiving the approval of RO, Excavation Permits and the traffic Management
Plan & Road diversions approved by traffic police & other authorities and also with
approval from Atkins, QBC will execute the work without disrupting the traffic flow
and temporary diversion will be provided to fulfil the necessary traffic diversion.
The construction work is majorly divided in to different stages for package 1 &
Package 2. Package 1 divided in to 27 stages & Package 2 divided into 16 stages.
Baseline Schedule
Page No: 4

Design and construction of lateral interceptor sewers, Al Wakra

The work sequences are elaborately explained in the Baseline Programme


substantiated with optimum Resources and fully cost loaded work programme.
(Refer the details in the Baseline Program of this Submission). While each item of
the scope of works will be executed and completed then as built drawing also will
be done in parallel to the Project Progress.
The Project will be closed out with the snagging after addressing of all snagging
works demobilisation and Handing over will be done.

4. Construction Approach:
QBC will divide the road section to part 1 and part 2 as represented in (Figure
1), and for part 1 the following utilities & road work will be carried out:
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.

TSE (Pipeline, Chamber) if any


Ground water (Pipeline, Manhole, Gully)
Foul sewer (Pipeline, Manhole, House connection)
Potable Water (Pipeline, Chamber, House connection), if any
Electricity works, if any
Telecommunication works (Duct, Chambers), if any
Qatar National Broadband Network (QNBN) (Duct, Chambers), if any
Road Works (Earth works, sub base, Kerb, Base course etc)
ITS (Ducts, Chambers), if any
Street light (Cable, Base, Poles, Feeder Pillar)
Irrigation works
Landscaping works

Part 2 will be carried out after completion of base course of part 1 and diversion of
traffic on part 1, following utilities & road work will be carried out:
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.

Surface water (Pipeline, Manhole, Gully), if any


Foul sewer (House connection)
Potable Water (Pipeline, Chamber, House connection), if any
Electricity works, if any
Telecommunication works (Duct, Chambers), if any
Qatar National Broadband Network (QNBN) (Duct, Chambers), if any
Road Works (Earth works, sub base, Kerb, Base course etc)
ITS (Ducts, Chambers), if any
Street light (Cable, Base, Poles, Feeder Pillar)
Irrigation works
Landscaping works

Baseline Schedule
Page No: 5

Figure 1

As stated earlier whole project of DW013 consists of two packages (Package 1 &
Package 2), QBC will carry out the work under DW013 as follows:

4.1.

Package 1

Design and construction of lateral interceptor sewers, Al Wakra

The following sequence will be followed for the above mentioned section:
Package-01

Baseline Schedule
Page No: 6

Design and construction of lateral interceptor sewers, Al Wakra

Package-02

Baseline Schedule
Page No: 7

Design and construction of lateral interceptor sewers, Al Wakra

(iv)

Construction sequence will start from


Part 1 of the road with TSE, Foul water drainage & ground water pipeline works
(excavation, pipe laying, and backfilling). Manhole excavation will start after
excavation of pipeline and continue with following activities for manhole (blinding,
tanking, protection, base slab, wall concrete, external tanking, cover slab, DI cover
& backfilling). House connection Guiles excavation work will start after wall of
manholes and follow by (Installation of gullies, backfill and grating). Road
excavation at part 1 side will be follow the excavation of road and continue with
(ducts, kerbs, sub-base up to base course), After completion of base course at part
1, work sequence will shift to Part 2 side of the road starting with surface water,
potable water, electricity works, Foul water house connection works, QNBN works,
gully installation & pipe laying works, street light, ITS & Irrigation works if any,
simultaneously works like sub-base, base-course, wearing course, street lighting,
landscaping works will continue as shown in below picture sequence.

Baseline programme indicates the planning implementation with Major items


which covers over all scope of the Project. While developing Baseline programme
the following assumptions has been made in order to make a realistic construction
approach and executable work programme as follows but not limited to:

(ii)

(iii)

Activity durations and resource assignments& assumed daily production


& required logics and their lags for predecessors and successors will be
modified if necessary based on site obstructions/ interfaces and also
unforeseen site conditions and unavoidable changes in QBCs
Construction Methodology. If necessary, programme will be subjected to
modification due to changes in QBCs construction methodology with
information to Atkins.
After the site handing over to QBC, QBC intend to start the work as soon
as possible. Assuming that all the necessary permits and approvals from
the Government/ Ashghal/ Kharamaa/ private authorities will be issued on
time and no obstructions or delay in permits/approvals will stop QBCs
execution and work progress.
QBC assumed that all the client and Government authorities permits/
approvals will be on time without any delays, and no interruptions for the
work to start and the client will provide always necessary work front in
order to progress in execution of works.

Baseline Schedule
Page No: 8

(v)

QBC assumes that there is no electrical work at package-2 in our scope of


work as there is discrepancy in road cross section and layout provided,
which has notified by QBC through email dated 06th July 2015.
(vi) QBC assumes that there is no any requirement of dewatering.
(vii) Sewer house connection for package 2 has considered as a future house
connection as per drawing details.
(viii) Road excavation considered up to sub-grade bottom level.
6. Baseline Programme Description:
The Baseline Programme developed into activities in the following Stages &
divisions:

5. Assumptions for the Baseline programme:

(i)

QBC assumes that if any scope of the project changes, if any additional
works are incurred it will affect the end date of the project and the client
will accept the required time & cost allocation for such works as positive
variations, additional works and time extension for QBC.

1.
2.
3.
4.
5.

General
Engineering
Procurement
Construction
Handing Over

For programming and planning purpose each sub division is further divided in to
various levels based on the type of activities involved.
6.1.

6.1.1.

General

Construction milestone:

The contractual milestones are included based on the conditions of the contract.
The programme of works starts with a start milestone as Project Start Date which
represents the commencement of the project as 28 th June 2015. The finish
milestone project Completion Date represents the completion of the project as
16th February 2017 which includes the demobilization and the handing over. The
Project total duration is 600 days.

Design and construction of lateral interceptor sewers, Al Wakra

6.1.2.

Mobilisation

mainly include for Electrical works, Irrigation works, Rebar works, Survey

The Third party insurance, Contractors all risk insurance, Performance bond etc
are considered. The site office setting ups for Engineer and contractor and gradual

6.3.

works, ITS & Telecommunication works, Micro Tunnelling Works etc.


Procurement:

The construction materials like

mobilisation of manpower & machineries are considered

VC & ESCV Pipes & fittings, DI pipe &

fittings, HDPE pipe & fitting, GRP Pipes, RC Pipes, LV, MV & HV cables, Gully
pots & grating, Street light cable, feeder pillar, street light poles & fittings,
6.1.3.
Permits/Approvals :
Road Opening Permits, Excavation Permit and MMUP permit and their

Potable water valves, Fire hydrants, interlock & kerbs are included in the

respective approvals are considered in order to execute the work.


6.1.4. Provisional Sum Instruction
These are the dates on or before which engineer should pass the

programme.

instruction to execute the work for the particular provisional sum items
to complete the project with in stipulated time frame.
6.2.
Engineering
6.2.1.
General Submittals: All general plans which include Project
Quality Plan, Project Safety Plan, Environment Plan, Project Baseline plan
submission and their respective approvals considered.
6.2.2.
Material Submittal & Approval: The materials for all the

programme and their respective, delivery to site etc. are considered in the
6.4.
Construction
6.4.1. Part-1
6.4.2. Part 2
6.5.

Project Close Out

It demonstrates the handing over for entire project to PWA, snagging list and
as built drawings if any.

items such as, DI pipe, VC pipe and HDPE pipe, UPVC pipes & Ducts etc.
will be submitted and will get the approval.
6.2.3.
Method Statement Submittal

The

6.6.
Working hours:
The calendars considered for the projects, DW013. The official holidays and

construction method statement for all the items are included which are

non-working days as per Qatar Labour Law were considered.. The normal

Surveying works, Dewatering Works, Earthworks, Protection of Existing

working hours will be 8 hours throughout the week except Friday as week

Underground service Utilities, Preparation and laying of sub-base,

end holidays. And the Week starts on Saturday.


6.7.
Programme Requirements:
The Baseline programme has been created according to Clause 14 of the

&

Approval

Preparation and laying of Aggregate base, Asphalting works, Traffic


Signs and Road Markings,

Kerbing & Foot way works, Street Lighting

works, Civil structure works, Surface water drainage works, Manhole for
all works ( TSE/ Sewer/ Drainage),

Ducts works &

Road Crossings

Ducts, Relocation of water pipelines, TSE works & Chambers, Irrigation


& Landscaping works and their respective submission and approvals are
considered.
6.2.4.

Subcontractor Submittal & approval: Subcontractors profile

to be submitted & obtained their respective approvals considered, which


Baseline Schedule
Page No: 9

conditions of contract DW013: Construction of Road & Infrastructure in Al Sailiya


North of Salwa road .

(This also complies according to QCS 2014 clause 7.4

section1 parts, General conditions of contract, clause 8.2.1, the frame work
contract requirement under Vol 2, Schedule 1, Part B, clause 1.18 for
Programme submissions, and Procedure for schedule management for
GEC relevant clauses for construction part).
6.8. Critical Path :
The critical path will be the activities of end stages as per
sequence of work and excavation of ground water pipeline.

Design and construction of lateral interceptor sewers, Al Wakra

Approved electrical
scheme

Approved water and


5

electrical drawings from


Kahramaa

Interface with other


contractor

The delay in approval of electrical


scheme

will

badly

affect

the

construction in site
Any delay in the approval of water
and

electrical

drawings

from

Kahramaa will have a delay in the


project
Whether there is any contractor still
working in site, will badly effect on the
progress in site
Delay in approval of dewatering work

Dewatering work

trench

7. Risk Assessment:
No.

Description

Affect
One way traffic diversion proposed by

Traffic Diversion plan

QBC may be will take long time for

approval

approval by other parties and it will


affect the start of the work at site
The connection of proposed network
to existing may be delayed if the

Connection with existing

existing

connection

consequently

will

not

effect

ready,
on

the

completion of the project


The instruction of the provisional sum
3

Instruction of provisional
sum items

items must be on time as identified in


the baseline programme and whether
there is a delay will badly affect the
construction in site

Baseline Schedule
Page No: 10

will badly affect the work in deep

Design and construction of lateral interceptor sewers, Al Wakra

Potrebbero piacerti anche