T&C Procedure For Lift System

JKR/CKM/T & C :______________________

CAWANGAN KEJURUTERAAN MEKANIKAL


JABATAN KERJA RAYA

PROCEDURE T & C FOR LIFT

1.

TESTING AND COMMISSIONING


Upon completion of the installation work, the Contractor shall have checked and
adjusted all parts of the installation to ensure that each and every section of the work
is in proper working order.
When he is satisfied that everything is in operating order, he shall arrange with the
S.O. and the Inspector of Machinery for carrying out commissioning of the
installations. He shall also carry out all the acceptance tests as stipulated hereunder
and any other tests as may be deemed necessary by the Inspector of Machinery.

2.

Power supply Check Stage


During this stage the main procedure is to establish the power supply to the
respective elevator and to measure and check the power supply capacity to confirm
requirements. Volt and Amp Meter or Multi-Meters are to be used.

3.

Wiring Connection Check Stage


At this stage the Testers/Adjuster will double check all wiring connections as done
earlier in the Installation Work Procedure Assembly in accordance to Drawing. The
testing team is to ensure all wiring connection are properly tighten and insulated.

4.

Slow speed Testing Stage


During this stage the elevator will run on slow speed. Adjustment and clearance will
be check and operation inspected. Second stage cleaning will be done on sensitive
moving parts for the next procedure of high speed testing.

5.

High speed testing stage


During this stage the elevator will be running on high speed and operation inspected.
All safety switches shall be check before running high speed.

6.

Elevator test run and safety switches check stage

Page 1 of 5

T&C Procedure For Lift System

During this stage the elevator is test run to ensure smooth running without any
obstruction of moving parts. At the same time appointment is made with Department
of Occupational Safety and Health (DOSH) Inspector to inspect and commission the
elevator.
7

Commissioning Stage
During this stage the work procedure is to ensure that the inspection carried out by
the Inspector from DOSH is done smoothly and in accordance to local and overseas
statutory requirements.

I.Drop Test

i.If required, a drop test shall be applied to the fully loaded car, in order to test the
efficiency to the safety gear as specified.
II.Over speed Test
i.An over speed test shall be carried out in order to determine the efficiency of the
safety gear as specified.
III.Balance Test
i.Each lift shall be run in both direction under balanced load conditions and
instrument readings taken in order to determine whether the balance is as
specified.

IV.Load Test
i.Each lift shall be run in both directions under various load conditions from no load
to 10% overload and instrument readings taken to determine the relations
between load, current and speed.
ii.Each lift shall be subjected to a two (2) hour test with the Lift carefully loaded,
stopping at each floor on the up and down trips, during which the doors shall be
fully opened and closed. Stops at the lower terminal landing shall be of one (1)
minute duration and the other floors only of sufficient duration to permit the
opening and closing of the doors.

V.Safety Operation Tests

Page 2 of 5

T&C Procedure For Lift System

i.All safety circuits, governor trip devices, door contacts, limit switches and other
safety devices shall be simulated to show satisfactory safe operation of the lift
installations. The Contractor must submit a full report of the safety operation tests
as specified in the lift code or other further conditions as may be deem necessary
by the S.O. or Inspector of Machinery.
VI.Temperature Rise
i.Tests shall be made to ensure that the temperature rises of motors magnet
operating coils and bar resistances, conform to those submitted by the Tendered
in the Schedule of Technical Data of Equipment Offered.
VII.Insulation Tests
i.The insulation test of the whole the installation shall not be less than 1 Mega
Ohm between any phase conductors and earth when measured with 1,000 Volt
Megger.
VIII.Performance Test
i.For comparison of performance, Tenderers shall state in the Schedule of
Technical Data of Equipment Offered the time taken for the car to travel from
stop and deceleration to creep speed, leveling and closing and opening the car
and enclosure doors.
ii.Timing on this sequences of operations will be taken with various car loadings,
up to full load and in both directions of travel.
iii.A check on car speeds in both directions of travel with varying loads up to full
load will also made.
The Contractor shall provide, at his own expense, all labour, weights, apparatus
and instruments properly calibrated, required for carrying out all the tests.

Page 3 of 5

T&C Procedure For Lift System

8.

Installation verification before Testing and Commissioning

Checks the followings:


I.The cable connection at Motor Terminals
II.The wiring connection between Control Panel and Car Cage
III.FFB and Kinfe Switches cut Off and Cartridge Fuses
IV.To check for any abnormalities in Control Panel, Traction Machine and etc
V.To check proper earthing to the equipments
VI.To ensure all Hatch/ Landing Door Locked
VII.To ensure there are no obstruction to run the lift in slow speed

9.

Insulation Test
I.To ensure the incoming supply cut Off before proceeding with testing
II.Remove all Glass fuses form fuses Holder in Control Panel
III.Insulation check will be carried out by using Mega Tester and checking for the
following items:
a. Terminal of Motor
b. Main Contactor
c. Lighting Circuit
d. Control Circuit
e. Supervisory Panel Circuit
f. MG Brake Circuit

10.

Safety Device Check


I.To operate the lift and check that lift stops after any safety switch cut Off.
(governor Switch, Stop Switch, Limit Switch, Final Limit Switch and etc)

11.

Safety Catch Operation Test


I.Bring the elevator moves downwards and check the elevator stops after the
catch is activated

12.

Door Adjustment and Setting


I.To check and adjust alignment of door
II.To check and adjust clearance between door edge and sill
III.To check and adjust inclination of door in completely closed position

Page 4 of 5

T&C Procedure For Lift System

13.

Check floor to floor height measurement

13.1

High Speed Trial Operation


I.Generate call and confirm that the elevator is operated as acceleration, steady
running, deceleration and landing at the called floor level.
II.Load the cage by 50% of the test weight and check the counterweight and lift car
are in balance.

14.

Over speed Test


I.The over speed test will be done to ensure the efficiency of the safety gear are
applied

15.

Leveling Test
I.The Lift Car Leveling Device accuracy shall be tested at all floors with no load
and fuel load in the car

16.

Final Adjustment
I.Overload Setting
II.Lift car level checking and adjustment not exceeding 10mm.

17.

Group Control Operation


I.All the lift must be completed on high speed before turning on the Group
Management Panel to check the Group Control Operation. This will be included
in the Hall Button, Function Check, Hall indicator Check, Key Switch Panel
Operator Check, Fire Mode Operation and Standby Power Operation Check.

18.

JKKP Inspection
I.The JKKP Inspection will be arrange after all lifts are tested and in good
condition, it will be inspected by DOSH as per laws requirements

19.

Handover
After all the inspection by the Authority had been done / carried out successfully
then the elevator will be hand over to the Client.

Page 5 of 5