Sei sulla pagina 1di 6

I.E.M.S.

Code

VISUAL
INSPECTION
PROCEDURE

UAN (for QMHA)

Page

11-3090

1 of 6

VISUAL INSPECTION
PROCEDURE
Owner
: ENPC
Main contractor : Uhde
Project name
: AMMONIA UREA PROJECT

00
Rev

Status

CC Category Code:
1 = for approval
2 = for review
3 = for information
4 = for internal use
AC Acceptance Code:
1 = approved / reviewed
2 = approved / reviewed as
noted
3 = not accepted
4 = received

First Issue

11/6/2010

Emad Omar

11/6/2010

Hassan Basha

Description

Date

Prepared

Date

Checked

Status Code:
A = Issued for Design
D = Issued for Inquiry
E = Issued for Order
F = Issued for Prefabrication
G = Issued for Construction /
Fabrication
H = Issue for Work
Preparation
I = As- built

Date

Approved

Acc.

Space for Bar Code label

M = General Issue

Copyright 2007 Uhde GmbH

Doc. ID-Code
PT-BM-183-DC-00005

Category
1

Code

I.E.M.S.A

VISUAL INSPECTION
PROCEDURE

CONTENTS
1
2
3
4
5
6
7
8
9

ENPC
UAN (for QMHA)

Page

11-3090

2 of 6

PAGE
3
3
3
3
4
4
5
5
6

Scope
Equipment
Personnel
Examination condition
Visual inspection technique
Acceptance criteria &tolerance
Visual examination for repair welds
Examination records
Reporting

1- SCOPE
This visual inspection procedure has been established in accordance with the
respective Project specification UD-BM-G00-EC-00016- ESD - Y4 - pipe welding on
Copyright 2007 Uhde GmbH

Doc. ID-Code
PT-BM-183-DC-00005

Rev.

00

Code

I.E.M.S.A

VISUAL INSPECTION
PROCEDURE

ENPC
UAN (for QMHA)

Page

11-3090

3 of 6

site. For piping to control the quality of weld joints during the execution of the
project

2- EQUIPMENT
By means of some measuring tools such as :

Cambridge Gauge
HI-LO Gauge
Fillet Weld Adjustment Size Gauge
Meters, Calipers,------------------ETC.

3- PERSONNEL
Personnel who carry out examination in accordance with this procedure shall be:
(a) Familiar with relevant standards, rules and specifications.
(b) Informed about the welding procedure to be used.
(c) Have good vision in accordance with the requirements of EN-970 ( ISO
17637), or equivalent which shall be checked every 12 months.

4- EXAMINATION CONDITIONS
(a) The illuminance at the surface shall be a minimum of 350 Lx. ( 500 Lx is
recommended)
(b) For performance of direct inspection, access shall be sufficient to place the
eye within 600 mm of the surface to be examined and at an angle not less than
approximately 30 (fig. 1 )
Range of eye Position

30o

30o

Fig. (1 ) Access for examination

5-VISUAL INSPECTION TECHNIQUE


I. VISUAL INSPECTION DURING PREPARATION &FIT UP:Copyright 2007 Uhde GmbH

Doc. ID-Code
PT-BM-183-DC-00005

Rev.

00

Code

I.E.M.S.A

VISUAL INSPECTION
PROCEDURE

ENPC
UAN (for QMHA)

Page

11-3090

4 of 6

1- Check material type ,heat no., thickness


2- Check joint configuration: edge preparations, angle of grooves (if found),
root gap, root face, working points position, hi-lo, alignment, dim., level, etc.
3- Review welding consumables certificate, type &sizes according to
approved W.P.S.
4- Review welders ID or certificates and assure they are suitable for
specified welding or not
5- Check supports distribution & temporary attachments
6- Review the tents (covers around area of welding) & safety precautions
7II- VISUAL INSPECTION DURING WELDING:-

1- Check all W.P.S. parameters such as: consumable type, size, current
characteristics, preheat temp, interpass temp, welding sequence, cleaning
between passes,-------------------etc.
2- Monitor distribution & reduce it by welding sequence & welder
distribution
III- VISUAL INSPECTION AFTER COMPLETE WELDING JOINTS:-

1- Check the weld cleaning from arc strikes, dirt's, spatters, etc.
2- Detect any discontinuity can be appeared on surface & affects service
performance such as porosity, under cut, over lap, cap height, crack,
under run, etc.
3- Determine sizes of defects by measuring tools available
4- Check dim., alignment, level, weld profile& size
6. ACCEPTANCE CRITERIA & TOLERANCE :
I-VISUAL INSPECTION DURING PREPARATION & FIT UP:-

Using tolerance mentioned within construction, drawings and W.P.S. for:


joint configuration , dim., tolerances, level, alignment, taking into
consideration shrinkage & longitudinal, angular and transverse distortion
expected

II- VISUAL INSPECTION DURING WELDING:-

Welding shall be according to ranges found in the approved W.P.S.& suitable


welder qualification

Copyright 2007 Uhde GmbH

Doc. ID-Code
PT-BM-183-DC-00005

Rev.

00

Code

I.E.M.S.A

VISUAL INSPECTION
PROCEDURE

ENPC
UAN (for QMHA)

Page

11-3090

5 of 6

Any change in essential variable needs to stop welding & to qualify


new W.P.S.

III- VISUAL INSPECTION AFTER COMPLETE WELDING JOINTS:1- Check the weld cleaning from strikes, dirts, spatter..etc
2- Detect any discontinuity can be appeared on surface & affects service
performance such as porosity , under cut , over lap, cap height crack, crack,
under run, .etc
3- Determine sizes of defects by measuring tools available .
4- Check dim, alignment, level, weld profile & size.
7- VISUAL EXAMINATION OF REPAIRE WELDS
7.1 GENERAL
When welds fail to comply wholly or in part with the acceptance criteria, and repair
is necessary, the checks detailed in 7.2 and 7.3 shall made during repair operation.
7.2 PARTIALLY REMOVED WELD

It shall be checked that the excavation is sufficiently deep and long to remove all
defects.
It shall also be ensured that there is a gradual taper from the base of the cut to
the surface of the weld metal at the ends and sides of the cut, the width and
profile of the cut being such that there is adequate access for re-welding
7.3 COMPLETELY REMOVED WELD

It shall be checked that, when a cut has been made through a faulty weld and there
has been no serious loss of material, or when a section of materials containing a
faulty weld has been removed and a new section is to be inserted, the shape and
dimensions of the weld preparation meet the specified requirements.
7.4 EXAMINATION

Every repaired weld shall be examined to the same requirements as the original
weld, as specified in section 5
8- EXAMINATION RECORD:Visual inspection report (copy attached) will be prepared and signed by QA/QC
inspector, containing the visual inspection test results and interpretation of
indication if found.

Copyright 2007 Uhde GmbH

Doc. ID-Code
PT-BM-183-DC-00005

Rev.

00

Code

I.E.M.S.A

VISUAL INSPECTION
PROCEDURE

Owner : ENPC
Main contractor : Uhde
Drawing no. :
Application code :EN970 :1997
Item no.:
Filler metal:
Part
no.

Weld no.

IEMSA

Welder no.

ENPC
UAN (for QMHA)

Page

11-3090

6 of 6

Report no.:
Date :
QA/QC drawing no. :
Material :

Evaluatio
n

PETROJT

Remarks

UHDE

ENPC

Name
Sign
date
ABRIVIATION :

Acc. : accept

Copyright 2007 Uhde GmbH

Rep.: repair

Doc. ID-Code
PT-BM-183-DC-00005

Rev.

00