Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
OPERATING MANNUAL
FOR
STEAM GENERATION PLANT
INDEX
ITEM
Page
1.
2.
3.
Introduction
Brief of description of the process
Equipment specification and design operating datas
VU-40
Boiler
Package Boilers
1
1
7
4.
30
30
30
32
32
36
38
39
42
5.
46
6.
7.
8.
9.
Diagram
54
54
57
59
61
65
72
94
94
94
94
95
95
INTRODUCTION
The Steam Generation Plant comprises of three identical pulverized coal fired boilers
with oil support, having a maximum continuous rating (MCR) of 150 T/Hr steam at a
pressure of Kgs/cm2g and 4950C. The normal rate of steam generation (NCR) is
84T/Hr. The boilers are tangentially fired, balanced draught, Natural circulation,
radiant dry bottom and provided with bow mills.
1.2
MAJOR EQUIPMENT:
i)
Bowl Bills- 3 Nos per boller.
ii)
Fuel firing system
iii) Furnance Ash hopper
iv) Furnance chamber
v)
Forced draft fan
vi) Induced draft fan
vii) Regenerative type of Air-heater
viii) Steam/air pre-heater
ix) Economiser
x)
Electrostatic Precipitation for fly ash
xi) Water drum, steam drum and boiler, tubes
xii) Steam desuperheater and super-heater
A common chimney is provided for final disposal of flue gases for all the
three boilers.
DESCRIPTION OF THE PROCESS
1.3
FEED WATER
Boiler feed water at a temperature of 131 0C and a pressure of 141Kg/cm2g is
pumped from the Deaerator by boiler feed water pumps AGA-701AB. This feed water
passes through a synthesis economizer and goes to boiler house at a temp of 200 0C. It
boiler house it is distributed to each boiler through an 8 individual feed water line.
1.4
1.5
Plant
Ammonia
Urea
NH3 Compressor
Ammonia
De-aerator
FO Storage Tank
Boiler FO day
Tank
Qty.
Source
60.0
80.0
N2 Compressor
Syn. Compressor
70.0
15.0
20.0
8.0
Syn. Compressor
NH3 Compressor
Ammonia
NH3 Plant
0.1
-do-
8.
9.
10.
11.
1.7
LPG Vaporizer
Caustic Soda
Caustic soda
Unloading
Miscellaneous
3 Kg/cm2/187oC
-do-do-
0.1
0.2
0.7
Ammonia
----do-------do----
-do-
3.0
----do----
1.8
START UP FACILITIES:
i)
During start up, the boilers use HSDO upto 10% of the normal load, then fuel oil
upto 30% and coal above 30% of the normal load suitable. Firing facilities are
provided for each boiler.
ii)
One electric motor driven feed water pump is provided in Ammonia Plant to
pump boiler feed water to the boiler until enough steam is generated and the
turbo feed pump is put into operation.
Feed water is supplied to the Steam drum from economizer outlet header. After
side of the steam drum is connected with the furnance bottom ring header through boiler bank
tubes. Lower water drum and two 406 mm OD down comers.
The furnace front wall tubes slope forward to form the roof of the furnance and routed in such
a way that the super heater penetrations is possible. The furnance front roof tubes are
expanded to the steam drum.
The rear water wall tubes slope forward to form the furnance rear arch. Half of the rear wall
tubes are joining the lower drum and remaining tubes form furnance screen tubes and are
connected to the upper part of the furnance to permit passage of the flue gas with uniform
velocity.
Both side walls are crowned with side outlet header. The side wall outlet headers
are connected with steam drum by a system of riser tubes.
The water in the furnance wall absorbs heat. The resulting steam water mixture is discharged
into steam drum directly from front and rear whereas the steam water mixture from side walls
are collected by the outlet headers and discharged in the steam drum by means of a system of
steam risers. Those discharged steam from the riser tubes and furnance wall is collected in
the chamber formed by the vertical buffle panels in the drum. Here the primary separation of
steam water is made. Most of water drops down after impact and passes around the ends of
the panels to mix with the incoming feed water.
A portion of the water is tapped off through the perforated continuous blow down pipe
at this point of high solid concentration. The steam and some water are released over the top
ends of the panels and cascades into the main part of the drum. From here, wet steam rises
and passes through the primary screen where much of the water is removed. Then the steam
enters the screen dryer, consisting of several layers of screens, where the last entertained
moisture is removed. This water is returned to the water side of the drum through the drain
pipes. Dry steam leaves the drum through the top outlet nozzles. Dry steam after separation
from the drum enters into the primary or platon super heater where it is super-heated to about
390oC to 460oC by both radiant and convection heat of the furnance. Steam from platon
super heater enters to the final super heat via desuperheater where required amount of water
is injected in it to monitor the final superheater inlet temperature. In final superheater, steam
is further superheated to 495oC +- 50oC by conversion heat of flue gas. Then, this superheated
steam at 495oC +- 5oC and 105 Kg/cm2 is supplied to NH3 Plant through SX common header
for further use.
FUELS COMBUSTION :
Each boiler is designed for steaming with two mills supported with FO guns.
Pulverized cool is supplied to the furnance at the four corners of the boiler in three elevations
A.B and C. Each mill suppliers PF coal in all the four corners of one elevation only. There
are two types of FO guns in between elevation AB and BC in all the four corners of the
boilers. As such, there are 12 Nos. of pulverized cool burners and 8 Nos of FO guns. There
is provision to burn HSD in lower tyre FO guns as and when required.
The coal from unloading bay comes to the raw coal bunkers passing through crusher
houses conveyed by a system of conveyer belts. Coal coming from raw coal bunkers comes
to raw cola feeder and then supplied to the mill Quantity of coal supplied to the mill is
controlled by changing the speed of raw coal feeder. This coal is crushed in between bowl
and bull ring segments of mill. Hot air is introduced to mill, which is coming from RHS and
LHS wind boxes of the boiler. There is provision to supply cold air to maintain the
temperature of coal dust and air mixture from 70oC to 90oC. This coal dust and air mixture is
passing via classifier vanes and exhauster of the mills, supplied to all the four corners of the
boiler furnance through distributor. Size of the coal dust is 200 m of 70% passing Regulating
of the fireness of grinding is done by changing the angle of the vanes of classifier of the mill.
In order to ensure safety against explosion hazards are provided peepholes in furnace
and explosion diaphragms in flue gas path at different placed on flue gas ducts after Air Preheater.
This cola dust and air mixture burns in the furnace with the support of fuel oil. Adequate
quantity of secondary air supplied to the furnace to boost up ignitions by both side wind
boxes, regulated by aux.air dampers in each corner. Heat liberated due to combustion of fuel
in furnace is absorbed by water walls for steaming inside tube water and remaining heat goes
with flue gas for further use. This flue gas heat is used in superheaters to superheat steam
temperature in bank tubes and economizer for further heating up water temperature in air preheatet to raise the temperature of air coming from FD fans.
70 to 80% of the ash particles are driven out with flue gas and remaining are collected
in bottom ash hoppers. More than 99% of ash particles are liberated in electro-static
precipitators from flue gas. This flue gas, temp, about 140 oC goes to chimney through 2 Nos.
of ID fans, and then to atmosphere. The ashes of bottom ash hoppers and electrostatic
precipitators hoppers transferred to the ash ponds, out side of factory by ashing system
equipment.
C+O2
S+O2
If excess air is used for combustion, Sulphur trioxide(SO2) may also be formed
as combustion product.
Boiler Designation:Furnace:-
5766mm with
Fusion welded
Depth 6070mm
Radiant dry bottom
Superheater:-
Platen
Spaced Final
Heating surface
------do--------
Economiser:-
Type
Continuous
Finned
Total heating
Surface in m2
1425
Air Heater:-
Type
Regenerative 20-5-VIR-62
Volume 858 m3
378 m3
635m3
No. of stages
One
H S in m2
4582
No. of Block
One
2.2 Te/Hr
3.2 Te/Hr.
Type
12
48
Location
Corners of
furnace
Mills
Type
XRS603
System
Suction
Type
Capacity
145 Te/Hr
Motor
280 KW for Coal 51 grindability 75%
through a 200 mesh
10
Exhauster
Type
Speed
Drive
2974 V-25 990 R.P.M Driven by
Motor
Fans
Fan
Type
F.D. NDF
186
I.D NDE
246
No.
Gf/Blr
2
2
DESIGN CONDITION
29 3
m3/Sec
41
m3/Sec
383
40 oC
Kg/m2
290
135 oC
Kg/m2
Motor
KW RPM
135 145
Control
145 740
Inlet Vane
Soot Blower
Type
Furnace
Wall Blowers
Rw SE
Platens
Long Retractable
Convection Zone Model T-30 Make IE
Qty/Blr
24
Medium
SH Steam
SH Steam
Safety Valves
Location Make
&Type
Drum
Dresser
1738-WA
Dresser
1738-WA
SuperDresser
heater
1728-WD
No. off
Per Blr
1
Relieving
Capacity
118.8
Te/Hr.
1
1
29 7
Te/Hr
Size
Set Pressure
120 4 Kg/cm2
123 9 Kg/cm2
109 2 Kg/cm2
Inlet Vane
11
Pipe Line
Size
No. off/Boiler
Main Steam
273X32
One
Feed Water
219X20
One
12
PREDICTED PERFORMANCE
Evaporation
Te/Hr
Te/Hr
o
C
o
C
o
C
100% MCR
150
200
C
C
320
495
STEAM PRESSURE
Drum design
Operating
Super heater outlet
atg
atg
atg
121.0
113.4
105.0
PRESSURE DROP
Economiser
Final super heater
atg
atg
0.5
8.4
C
C
o
C
o
C
o
C
1052
1052
497
327
142
mmwc
mmwc
mmwc
mmwc
mmwc
mmwc
mmwx
Total mmwc
4
21
20
20
105
20
20
210
mmwc
mmwc
mmwc
mmwc
110
82
30
15
254
13
Total mmwc
HEAT LOSS
Dry gas
H2O in air & H2 in fuel
Carbon
Radiation
Unaccounted & manufacturing
Margin
Total
Efficiency
Excess air leaving
Economizer
Coal
Fixed carbon
Volatile matter
Moisture
Ash
Hydrogen
Grindability
High heating valve
Lower heating valve
Size of mill
%
%
%
%
4.45
5.29
2.00
0.32
%
%
%
%
%
%
0.50
13.56
86.44
%
%
%
%
%
Hardgroore
Kcal/Kg
Kcal/Kg
mm
25
Bituminous
Coal
30.0
24.5
6.5
39.0
3.05
50
4271
4100
20
PERFORMANCE
Total coal fired
Number of mills operating
Coal/ mill
Maximum mill capacity
Air flow through mill
Temp of air/fuel mixture after
classifier
Temp. of air at inlet to mill
Temp. of tempering air
Hot air temp. available
Total tempering air to mills
Total hot air to mills
Te/Hr
Te/Hr
Te/Hr
Kg/hr per mill
0
C
0
C
C
0
C
Kg/hr
Kg/hr
0
24.38
Two
12.19
14.50
25855
77
149
40
288
27345
24365
14
Sl. Description
N.
1.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10
.
11
12
13
14
H.T.Motors
Mill Motors
L.T. Motors
F.D.Fan Motor
I.D. Fan motor
Light oil pump motor
Fuel Oil pump Motor
Igniter fan motor
Scanner fan Motor
Raw Coal feeder
motor
Air heater drive
motor
Rapping mechanism
for collecting
Rapping mechanism
for discharge
HP dosing pump
motor
Mixing tank motor
Long retractable soot
blower traverse
Rotary
Wall blower
Transverse
Rotary
Air heater blower
15
.
16 Ash
.
water pump
Valve Drivers
Quantity
/Per Blr
3
Quantity Capacity
per
Project
9
280 KW
Full load
current/voltage
RPM
3.3. KV
990
150 KW
415V/258A
990
2
1
1
3
6
2
2
3
3
9
160 KW
5.5 KW
15 KW
2.2KW
2.2KW
2.2/
415V/275A
415V110A
415V/275A
415V/4.65A
415V/5,65A
990
1460
1460
2850
2850
3.7 KW
3.7KW
415V/7.6A
415V/6.86A
950
1480
18
0.25KW
415V
1390
18
0.25KW
415V
1390
1.5KW
415V/3.2A
2900
2
18
0.75KW
0.37KW
415V
415V/1.36
1440
1500
6
24
18
72
0.45KW
0.56KW
415V/0.44
415V/0.8
1500
1500
24
1
72
3
0.05KW
0.18KW
415V/1.26
415V
1500
250KW
3300V/55.0
1488
15
S.No. Description
1.
2.
3.
4.
5.
6.
7.
16
33
16
66
54
5
Counter
Staggered
44.5X4.5
SA-210Gr
A1
Platen
superheater
(Panel type)
Pendant
Radiant
18
Parallel
Inline
44.5
SA-213T11
SA-213T22
(4.5)
(5)
4
Parallel
Inline
44.5
SA209T1BS3059
P2S2 620 SA213T22
(44.5X4.6)
(44.5X4.5)
(44X5)
96
304.8
No. of loops
Flow type
Arrangement
Tube size out side dia in mm
Material of construction
Material thickness(mm)
1
219.1 X
28
SA-106Gr
B
323.9+32
219.1X28
No. off
Size mm
SA 335 P12
SA-106Gr B
Material
1
219.1 X 28
SA-106Gr
B
1
323.9X36
SA 335 P12
12
329.9X32
SA 330 P12
No. off```
Size mm
Material
Outlet
header
1 (each)
212.1X20
SA-106
GrB
1
273X32
SA-335 P12
12
108X10
SA-106 Gr2B
No. off
Size mm
SA-106 G2B
Transfer
tubes
Longitudinal mm
Transverse mm
96
Alternatively
139.7X165.1
Main
Steam Line
124
78
17
METALURGY COMPONENT
Metal
Grade
1
2
3
4
5
BS 3059
P2S2 620
Grinding
Roll
Bullring
segment,
Periphery
liner
Carbon
C
0.10 0.10
To
To
0.15 0.35
3.0
2.0
to
8.0
0.40
To
0.70
0.040 0.040
Chro Molibd
mium enum
Cr
MO
0.44
0.65
1.00
1.50
0.44
0.65
1.90
2.60
0.87
1.13
0.96
Nitro
gen
0.008
7
0.70
To
1.10
2.0
0.54
Copp Nic
er-Cu keL
Nl
0.45
To
0.65
0.75
7.5 to Nil
9.5
0.25
Tin
Sn
0.30 0.0
30
4.0
to
5.0
5.0
to
6.0
18
ELECTRASTATIC PRECIPITATOR
DESIGN CONDITION :
i)
ii)
iii)
iv)
v)
vi)
vii)
viii
)
ix)
i)
ii)
iii)
iv)
ii)
iii)
98.5 %.
15 mmwc.
0.87m/sec.
12.41 sec.
COLLECTION ELECTRODES
68 M3/Sec.
150oC.
3.61 gm/sec.
160 mm WC.
2 FAA-3x36-6560-2.
1.
2.
3.
27.
243 (9x27).
1458 (6x243).
6 Mtrs
400 mm.
99.10 m8/4/sec.
5616.
5391.36 m.
125mm.
19
6.
iv)
i)
9
ii)
iii)
i)
iv)
ii)
iii)
Type
RECTIFIER CONTROL PANEL
No. of happers
Capacity
Type of control
Heating
Number
Location
10
i)
ii)
Number
Equipment control
iii)
Location
11
MOTOR
i)
ii)
Rapping of electrode
Rating
iii)
Location
12
HEATING ELEMENT
i)
ii)
iii)
Hoppers
Shaft insulation
Support insulation in the insulators
houring
iv)
v)
v)
5.
7.
i)
i)
ii)
ii)
iii)
8
iv)
i)
ii)
v)
iii)
By ramididical.
6 (one per field).
8Transducer
hr storage.
Electrical
heating provided for the
3.
bottom
of happers
E P control
room.
6+6.
Gear motor 33KW/1.1 Rpm at 3 ph,
415 V, 50 c/s.
On the side panels of casing.
20
iv)
Control
a)
Used for
b)
c)
d)
e)
f)
Flash point
Kinematic viscosity at 50 oC max m
Sulphur total by weight
A P I gravity
Gross heating value
LIGHT OIL
a)
Used for
b)
c)
d)
e)
f)
g)
Flash point
Kinematic viscosity at 38 oC
Carbon residue rams bottom by weight max m
Sulphur total by weight
A P I gravity
Gross heating value
IGNITERS GUN
a)
b)
Application
Type
c)
d)
No. off
Heated at
21
e)
f)
g)
h)
i)
Capacity each
Oil firing rate
Oil pressure at control cabinet
Atomizing air quantity
Atomizing air consumption
j)
k)
l)
i)
ii)
Application
Type
iii)
iv)
v)
vi)
vii)
viii)
Ix)
x)
No. off
Location at
Capacity
Turn-down
Oil firing rate
Oil pressure at gun
Atomizing air quantity
Atomizing air consumption
22
xi)
xii)
4.90kg/cm2g
1.00 kg/cm2 air pressure to be
more than oil pressure.
xiii) Atomising nozzle assembly designation Mixing platon 41A spray plate60N41
HEAVY FUEL OIL GUNS
Application
Type
No. off
Located at
Capacity
Turn down
Oil firing rate
Oil Pressure at the gun
Oil leiseasity at the gun
Steam consumption
Steam pressure at the gun
Defferial pressure betn oil & steam
Atomizer nozzle assembly designation
Above said figures and designa value corresponding to normal operating conditions
23
Type
2.
3.
4.
5.
6.
7.
No. off
Heater area each
Oil flow rate
Oil temperature range
Steam pressure
Design pressure
24
LIGHT OIL
PUMP
-do-
MOTOR DOE
HEAVY OIL
PUMP
Bharat Bijlee
4.
MOTOR FOR
HEAVY OIL
PUMP
Kirloskar
Type/Size particulars
Multiscrew, position
displacement with
built in relief valve
165 Ltrs/min at 150 C
at, discharge pressure
22 kg/cm2g 1450 rpm
Multiscrew, positive
displacement with
built in relief valve
65 ltrs/min at 1.50
CST and discharge
pressure 22.00
kg/cm2g 2920 rpm
Horizontal foot
mounted squirrel
cage flave proof
motor KW-15, rpm1460,
volts-415
Horizontal foot in
mounted squirrel
cage flame proof
motor KW-5 5, rpm3000, volts-415
Remakrs
25
MILLS
1)
2)
3)
4)
Type of Pulverisation
Size
No. of Mills
Capacity
5)
6)
Motor
Coupling
7)
Cooling System
8)
Wear Surfaces
9)
10)
11)
12)
Feeders
Capacity
Speed
Drive
3.7 KW
6:1
Lower control
3.7 KW,3 phage, Induction motor flange
type directly mounted
26
5)
6)
7)
8)
9)
27
TYPE VU BOILERS
DATA OF ID & FD FANS
S.No. Particulars
1.
Type
2.
Fan Orientation
3
4.
5.
7
8.
9.
10.
11.
12.
13.
Medium handled
Non of fans/bir
Fan designating
i)
Capacity M3/Sec.
ii)
Total head developed
mmwc
iii)
Temperature of medica
oC
iv)
Sp. Wt of medium
v)
Speed rpm
Drive coupling
Drive motor supplier
i)
Frame size
ii)
Rating KW
iii)
Voltage KV
iv)
Frequency cps
v)
Phase
Fan weight in kg
Type of fan regulation
Bearing
Thrust bearing
Coupling side
FD Fan
NDFY 186
Style 01 left
bottom 55o to
vertical view
from drive end
Atmosphere air
2
ID Fan
NDFY 246
Style 01 left up
wards view from
drive end
29.3
383
41
290
40
1.128
990
Pin type
Siemens
400 M
150
415
50
3
6888
Inlet guide vane
NU332C3
7234 BVA
N234C3
0.882
740
Pin type
Flanges
2
400 M
160
415
50
3
9696
Inlet guide vane
NU332C3
7234 BVA
N234C3
28
S. No.
1
2
3
4
5
6
Tag No.
PS-27.4
PS-27.5
PS-27.6
PS-49.4
TIA-58.2
TS-66.4
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
TRA-52.2
PS-4.5
PS-4.6
PS-4.8
PS-13.4
PS-13.5
PS-13.6
PS-13.8
TRA-63.3
PS-7.4
PS-41.4
PS-5.4
PS-5.5
LS-10.1
PS-10.4
PS-90.4
PS-94.5
PS-95.4
TICA-93.1
S. No.
26
27
28
29
Tag No.
PS-91.3
PS-92.3
PS-BAH-102-A
PS-BAL-102-A
Service
Inset air PR low
Compressed air PR low
BFP Discharge PR high
BFP Discharge PR low
Setting
270 mm WG
35 mm WG
280 mm WG
900 C
800 C
760 C
840 C
2.5 M3 / Sec
0.0 M3 / Sec
10.0 M3 / Sec
+40.0 mm WG
+15 mm H2O
-25 mm H2O
-5 mm H2O
5700 C
108 kg/cm2
5050 C
+100 mm H2O
-100 mm H2O
-200 mm H2O
8 kk/Cm2
8 kg/Cm2
2.0 kg/Cm2
8 kg/Cm2
1200 C
Setting
1.0 kg/Cm2
5.5 kg/Cm2
145 kg/Cm2
120 kg/Cm2
29
30
TS-70.2 A
31
TS-70.2 B
S.No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
LUBRICATION CHART
Lubrication Chart
Type of Lube Oil
Mill gear box
257/40
Mill exh. Bearing
533
Mill Roller
533
ID Fan
317
FD Fan
317
Ash water pump bearing housing
317
(both sides)
Air heater gear box
533
Clinker grinder gear box
533
Clinker grinder fluid coupling
314
Soot blower gear box
317
Phosphate dosing pump
553
Air heater bearing (top/bottom)
c-100
Rapping motors
553
MSSV (MCV)
317
MSSV by pass (MCV)
317
Start up vent (MOV)
317
RCF GEAR BOX
533
Lr Soot blowers
317
LDO unloading
pumpWORK
317
WESTER
900 C
600 C
Quantity in Liters
500
2
11-12
15
15
2
30
15
4-5
1
20-25
10-15
5-7
5-7
2-4
4-6
15-20
2
1
PACKAGE BOILER
DETAILED SPECIFICATION SHEET
1
2
3
4
5
6
7
8
9
10
30
11.
Feed Pumps
Capacity
Motor
Head
R.P.M.
Oil Pump
Capacity
Head
R.P.M.
FD Fan
Capacity
Pressure
Motor HP/kw
R.P.M.
2 Nos.
33.32 M3 Lts
HP/Kw 50/37
18.29 kg/cm2
3000
2 Nos.
3000
30 kg/cm2
1500
2 Nos.
12000 NM3/Hrs
515 MM/wg
50/37
1500
1576 kg/hrs
TDR 5:1
7. Electric Power Requirement
voltage 415 cycles-50/5/3 PH
4 wire system -160 KW
8. Feed water line from left water service tank to pump -4 NB Dia
31
32
The following steps outline the procedure for bringing cold boiler up to working
pressure & temperature. It is assumed that boiler has been boiled out and prepared for
operation. The boiler should be filled up with treated feed water. The water level in steam
drum should be at normal operating level.
PREPARATIONS
1.
2.
3.
Drum vents
Water gauge glass valves (Locked open)
Superheater header drains and vents and main steam line drain
All instrument and control connections to the boiler
Including valves on both side of desuperheater control valves.
33
NOTE: -Close all superheater drains when headers are free of water except the
superheater outlet header drain which remains open.
4.
CHECK:
-
Following equipments for adequate lubrication, cooling water flow and ready
for service.
Air heater and drive (if rotary air heater is provide)
Fans and drive
Boiler feed pump and drive
Slag removing systems
All servo/Pneumatic drive for valve and dampers.
5.
6.
It is presumed that pulverized equipment has been checked for proper functioning
and ready for service recheck.
1)
2)
3)
4)
7.
8.
It is presumed that wind boxes have been checked for proper damper positioning,
burner is in horizontal position etc.
9.
34
10.
Put all automatic control equipment on manual control and see that all control
equipment is ready for service. Manually operate all sequential trips and see that the
emergency fuel trips function property.
FILLING OF BOILER WITH WATER:Before start filling up open all the vent valves on
economizer, boiler drums platen and final superheater. It is also possible to fill the
economizer simultaneously through drain valves or through the main feed line. The boiler is
filled up to top of drum.
LIGHTING: i)
(Included draft-ID)
(Forced draft-FD)
It is necessary that during start up initial firing be done by means of the warm
up oil guns which are rated to give 15% of boiler MCR, at which point the
35
load carrying heavy oil guns can be placed in service or oene mill can operate
continuously at minimum rati g
xiii) To prepare a mill for service, proceed as follows:
-
Check to see that all the classifier vanes setting are identical
Check coal supply and open the coal gates to mill feeder.
Fully open the exhauster discharge valve. Make sure that tampering air damper
has freedom movement.
Hot air gates closed. Hot air control dampers closed.
xiv) Before placing the mill in service, check the associated burner windbox
dampers.
xv) Start the mill, open the hot air gate. Operate without coal to warm up the mill
with hot air to required temperature make sure that warm up oil guns to must
in stable condition. When ready to fire coal, start the mill feed at minimum
rating. It the ignition of pulverized coal does not take place, immediately
stops the feeder.
xvi) When the mill is not empty (in emergency fuel trip case) when other mills are
loaded,.
the furnace draft must be raised sufficiently to prevent- getting aq pressure in the furnace and
thus blowing hot furnace gases back into idle mill and coal pipings. The exhauster discharge
valves of other mill (idle mills) shall be closed
xvii) If the coal ignition of coal in furnace not occurs within 5 seconds, stop the
feeder of purge the furnace, cause for failing to lighting of load may be due
totoo much secondary air.
Too lean a coal primary mixture.
Loss of warm up oil gun flame.
xviii) When the ignition of coal has become stable on preparation, cut the fuel rate
to minimum. Watch the fire:xix) Main coal/Air temperature leaning the pulveriser, regulate hot air damper
manually to hold between 74 to 80oC for high volatile coal and 80 to 85oC for
low volatile coal at outlet of pulveriser.
36
The lamp should not exceed 90oC. If it should 90oC, the hot air gate must
closed. Check the pulveriser oil temperature of turn on the water to oil cooler
when temperature approaches 65oC at any time.
Note: Pulveriser start up will cause a sudden and sharp increase of steam pressure. This
will level out rapidly as load is increased.
xx)
Place the second pulveriser in same way when feeder rating of first pulveriser
has reached approx 80% of maximum.
The warm up guns of ignitors must remain in service until the feeder rating of
each of two pulverisers exceeds 50% of maximum or otherwise during single
mill operating conditions.
xxi) The boiler inter locks and secondary air damper controls or the operator
should close the auxiliary air dampers serving compartments adjacent to coal
nozzles which are out of service when the boiler reaches 301. of full load and
increases the windbox to furnace differential pressure to approximately 100
MMWC.
xxii) It is essential that air flow to the furnace is sufficient for the firing rate at all
times Automatic control is normally preferred for maintaining such a
balanced condition. The O2 measuring devices which are often tried in with
the air flow control should be checked periodically to assure continuous and
dependable operation.
xxiii) Place the desuperheater spray control and combustion control on Auto when
firing conditions are stable and temperature & pressure controls set point
have been reached before refers to control equipment.
xxiv) Adjust the feed water supply to boiler as necessary to maintain normal water
level. Feed water control should be placed on automatic as soon as possible
& practicable when continuous feed water flow is established.
xxv) If the setting of safety in drum and superheater has not been checked
previously this should be done prior to going on the line.
37
NORMAL OPERATION- UNIT LOAD CHANGES:During normal operation, with the unit on the line, changes in pulveriser loading and/or
the number of pulverisers in service may be required to accommodate unit load changes. A
wide range of load control can be achieved with the pulverisers on automatic.
a)
Decreasing load:If the unit load decreased to a point when the feeder rating off the pulverisers in
service is reduced below 50% of maximum, stabilization fuel oil firing should be
introduced and if so desired one pulveriser be taken out of service and the load on the
other pulveriser increases
.
To remove the pulveriser from service proceed as follows:
38
If the unit load is reduced to a point where no pulveriser are required, auxiliary support
oil guns can be used to carry the boiler load.
NOTE:- Auxiliary supporting fuel should be used at any time and under any condition
in which in the operators judgment, stabilization of ignition is necessary.
INCREASING LOAD:- If after a load decrease, where one pulveriser has been taken
out of service, the unit load should increase to a point where the feeder rating of the
pulverized in service exceeds 80% of maximum, the second pulveriser could be placed in
service as follows:
i)
ii)
iii)
Start the pulveriser feeder, the feeder control should be on Manual at minimum
feeder rating.
iv)
When the pulveriser is grinding and coal ignition has been established, gradually
increase the feeder rating until the pulveriser loading equals that of the other
pulverisers in service. Then place the pulverisers on auto control.
39
v)
The auxiliary supporting fuel may be taken out of service when furnace conditions
have established and both the pulverisers are in service each with a feeder rating of
at least 50%
40
feeder when the coal air temperature drops to 45 oC. Run the pulveriser until empty
and stop the pulveriser.
3. After all fires are out, keep the fans in service for at least five minutes (at 30% air
flow) to purge the unit close all gas duct, secondary air duct and wind box dampers
after the fans are shut down.
Caution:
It oils has been fired and it is knower suspected that combustible particles
deposits are present in air heater, the air heater has inlet temperature must be reduced to 180
o
C before shutting down the F.D. fans, I.F fans.
4. Keep the water level insight in gauge glass. As the unit cools and the water shrinks
make up should be added intermittently to prevent water from dropping out of sight
in gauge glass.
The operator should observe the gauge glass periodically so that he is always aware of the
actual drum level and can take appropriate action to reestablish water level when the unit
is being restarted.
HOT RESTART
Assuming the boiler has been down for a comparatively short period of time and
considerable drum pressure was maintained by the following procedure should be used in
restarting the Unit.
1.
2.
3.
4.
41
5.
and temperature limits required by the process. The working period should
be long enough to allow complete boiling out of superheater.
Establish he firing conditions to maintain the maximum furnace exit gas
temperatures without exceeding it.
EMERGENCY PROCEDURES:1.
2.
3.
1.
MASTER FUEL TRIP:Under conditions requiring a master fuel trip through normal interlocks or operators
action(manual trip), all fuel should be tripped instantaneously. If coal was being
fired the pulverisers should be tripped immediately. Tripping the pulverisers will
automatically trip the feeders and close the hit air shut off gates.
If oil was being fired, the oil and ignitor trip valves and individual nozzle shut off
should be closed immediately.
Maintain the unit airflow at pre-trip value for at least 5 minutes to purge the system. If
a hot restart is anticipated the airflow may be gradually reduced to light-off air flow
(30% of full load air flow) during the purge period.
b)
If oil guns were in service when the fuel trip occurred, check to ensure that all
individual nozzles shut off valves are closed. Oil guns should be retracted, removed,
cleaned and reinstalled to be ready for restart of the Unit.
c)
42
d)
Close the exhauster discharge valves on pulverisers that contain coal. This will
prevent hot furnace gases from being carried back into these pulverisers.
If the pulveriser will attained in service, start its feeder when the pulveriser
amps begin to fall off. When the feeder is started, open the hot air shut off gate
and bring the pulveriser upto normal operating temperature.
If the pulveriser will not be retained in service, stop the pulveriser after it is
completely cleared of coal. The exhauster discharge valve should remain open
to allow a flow of coming air through the empty pulveriser.
b)
c)
d)
If pressure parts damage is suspected, reduce the steam pressure gradually byt
opening the superheater start up drains. Open the drum vents when the pressure
drops below 2 Kg/cm2 (gauge). As the boiler cools reduce the air flow. Shut
down the air heaters and fans as soon as the unit is cool enough for a man to
enter. Drain the boiler when drum metal temperature is 90 oC following normal
draining procedure. Determine the cause of low water and examine the boiler
43
for the effects of possible overheating such as leaks and distortion of pressure
parts.
Repair any leak etc.
e)
f)
Hydrostatically test the boiler at working pressure before putting the unit back in
service.
Reduce the water level immediately by throttling the feed supply and opening
waterwall system drain valves.
b)
Reduce the steaming rate, if necessary, and place feed water control on manual. If
priming should occur, as indicated by rapid fluctuations in outlet steam temperature,
Proceed as follows-
GENERAL:
During the failure of direct water gauge, the boiler can be left in operation only
when the remote water gauges is in perfect condition. Repair of the direct water gauges must
be carried out as quickly as possible i.e. within 24 Hrs. The remote water gauge must be
observed with greater attention prolonged operation with one disconnected water gauge is not
permissible.
-
In the case the safety valves blow up because of exceeding the maximum of
design pressure, it is necessary to bring down the pressure by reducing the firing
increasing the feeding and steam extraction and blowing down the boiler.
44
after the individual superheater is exceeding it is necessary to limit the firing and
to check up the feed water temperature.
-
In case the quality of feed water of boiler water gets worse which might cause
dangerous pollution or damage to the tube walls it is necessary to reduce the
boiler output or to shut down the same if the condition does not improve.
Water level in indicator continuously drops even after blowing & closure of
steam supply.
b)
c)
d)
e)
f)
g)
h)
Deformation of pressure parts which might cause explosion and endanger the
personnel.
i)
j)
45
Gradually reduce the load on the unit, reduce the firing rate in line with the
decreasing steam flow. Allow the pressure to drop with the reduction in load to
accelerate cooling. Reduce the steam temperature at the rate prescribed.
46
Steam temperature control may be left on automatic until the point is reached
where better control can be obtained on manual.
ii)
When the feeder rating on pulverisers is reduced to below50% put the fuel oil
gun in service. Place the pulveriser supplying the upper coal elevation on manual control
Gradually reduce the feeder rating. When minimum rating is reached close the hot air shut
off gate. Stop the feeder when the coal air temperature has dropped to 45 oC. It is advisable
to close the coal shut off gates above the feeder and run the spouts and feeders empty before
stopping the feeder. Keep the pulveriser running for about 2 minutes or until it is completely
empty. Then stop the pulveriser.
iii) As pulveriser are taken out of service, the secondary air damper control system
should close the associated wind box dampers and throttle other dampers as required to
compensate for the reduction in firing rate.
iv)
Take the second pulveriser out of service when the feeder rating on this
pulveriser reaches 40%
v)
vi)
Reduce the airflow in line with fuel reduction until 30% of maximum air
flow is reached. Do not reduce the air flow below this rating until all fires are
out and the unit is off the line. To avoid firing instability during this period of
high relative air flow, the auxiliary air dampers at all elevations should open and
reduce the wind box to furnace differential pressure to its lower setting.
vii)
viii) After the last pulveriser has been shut down, remove the fuel oil guns and the
ignitors from the service shut off cooling water to pulverisers. All fires should be
removed when the unit is off the line.
ix)
Immediately after the boiler is off the line, open wide the superheater outlet
vents and drains. Open other drains in the superheater system as required for
further pressure reduction.
x)
Close desuperheater-isolating valves.
xi)
47
a)
Purge the unit by running the induced draft and forced draft fans for at least five
minutes (30% air flow) after the fires are extinguished.
b)
Reduce the airflow through the unit to a minimum; Keep the fans in service until
the unit has cooled to the desired temperature.
c)
Keep the water level near normal in the gauge glass and make up as required.
d)
Open the drum vents when the unit pressure has decayed to 2 Kg/cm2/gauge.
xii)
a)
b)
c)
d)
xiii)
It is desirable to accelerate the cooling process in order to permit entry into the
unit for maintenance proceed as follows:
Purge the unit by running the induced draft and forced draft fans for at least five
minutes (at a minimum of 30% air flow after the fires are extinguished.
Continue running the fans to cool the unit at the desired rate.
Maintain the water level near normal in the gauge glass.
Open the drum vents when unit pressure has been reduced to 2Kg/cm2g.
If the boiler is to be emptied, the boiler water temperature should be reduced at
least 95oC before draining.
When the water level in the drum falls down below 10 to 200mm and level cannot be
seen in gauge glass while closing the steam VIV of G.I.G
2.
When water level rises beyond visible level in the gauge glass.
48
3.
4.
5.
6.
7.
8.
When there is a break in the heating surfaces and impossible to maintain proper water
level.
When all gauge glasses fails.
When drum pressure rises beyond 124 atm (If safety valves had not opened and pressure
could not be reduced)
When boiler frame beams gets red hot and there is danger that livings will fall.
When soot and fuel particles start to burn in the boiler gas flues.
When there are cracks, break in pipes leaks in welding joints riveted joints in main
elements of the boiler (drum, header and piping) main steam pipeline.The boiler must be
shut down in all emergency cases that required shutting down boiler.
DIRECTION AND LIQUIDATION OF TYPICAL EMERGENCY IN BOILER
1.
III)
IV)
49
II)
III)
IV)
V)
B)
I)
II)
III)
IV)
V)
VI)
C)
Electrical motors are switched off and shut the dampers of FD fans, hot air
line to mill, and partially ID fans, so as not to over load during further
starting up.
Close injection to de-superheater.
Drive manually APH motor.
Take out partially scanner guns of all the corners.
Close manually main steam line valves to check further reduction of steam
or. Of B/r.
To follow boiler box-up operations.
iii)
iv)
v)
Steam and gaseous coming out of feed holes and cracks in boiler linings
etc.
B)
4.
Shut down the furnace stop RCFs, mirls, fuel oil to furnace. FD fans and
leave ID fans in service until the main mass of steam and flows of furnace
removed.
iii) Stop feeding the boiler with water.
SIGN OF BREAK IN WATER WALL OR SUPER HEATER PIPE:
i)
50
ii)
iii)
The water issuing out of the water wall and steam from super heater tubes can
damage the neighboring tubes in short time. Hence damage and increasing time
eliminated by immediate shutdown.
5.
A)
B)
Immediate information should reach to chief of shift of boiler house and get the
instruction from him. In case, it is necessary to continue running the boiler, only
permissible in small leakages.
i)
Carefully watch the water level in boiler and feed liner pressure. If
feed line pressure dropping and large difference in flow of water meter and steam flow
meter, then demand to start stand by feed pump.
ii)
If water level is dropping even intersity the feeding and gets lower the mark and
signal a water escaped from the drum. If protection fails, shut down the boiler and stop
feeding. I.D fan is left in service till steam and gas flues are removed.
iii) Open super heat blow down and after 15-20 minutes, close the superheater blow
down.
6.
51
iv)
v)
vi)
vii)
B)
SIGN OF WATER ESCAPMENT
If water level gets down the limit level then (a) water level low (b) water level very
low (boiler trip) (c) water level dangerously low indications will appear. Boiler will trip
in interlock if it is in service.
C)
i)
ii)
iii)
iv)
a)
7.
ii)
Water level gauge glasses and control room instruments are out of order.
iii)
iv)
Foaming and forcing of the boiler when increasing the phosphate valve.
If water goes to the steam line then it is dangerous to steam line and steam driven
compressors and turbine.
SIGN OF OVER FEEDINGS
i)
52
ii)
8.
INFLAMATION UNBRUNT CARRIED AWAY FUEL IN GAS FUELS OF
THE BOILER:
REASONS:- Incomplete burning of fuel will cause formation of shoot (during
Combustion of fuel oil) and carried away unburnt particles (cool dust) causes
deposits of dry easy to in flame components in gas fuels of boilers ,wants
economizers, an air heater elements and ducts ,
Deposits of carried away combustibles may catch fire under definite conditions and
causes serious damage to boiler and elements.
SIGN OF INFLAMATION OF CARRIED AWAY FUELS
I) Sharp increase of exhaust flue gasses temperature of the boiler.
II)Flame and smoke coming out of boiler parts and black smoke from chimney
III) Rise in temp. of furnace.
IV) Heating up of causing exhaust flue gas ducts.
In case of rapid increase of temperature of flue gasacus by instruments and
visible inspection at site necessary.
a)
Open the valves to supply steam through Fuel oil burners and fill the gas flue
with steam.
53
The droughts left and air supply to inflamed placed contribute burning and will
damage the equipments.
9.
1.
a)
b)
c)
d)
e)
2. Extinction of flame and its subsequent firing up with oil burner with out
preliminary ventilation of furnace and with uninterrupted coal dust supply may
cause to explosion in the furnace chamber. It is practically important wran
burning coal with high volatile contents.
3.
4.
If the flame dies out in he furnace and protection is switch on position (timing 5
seconds) protection gives out on impulse to shut-down the boiler.
If the protection failed. If form to shit-In charge and ammonia plant personnel to
unload compressors to desired to maintain steam pressure quantity.
a) Stop immediately fuel to furnace, switched off coal feeders, mills, oil
b) Take out boiler from steam common header
c) Interlock the furnace 5-10 seconds.
d) Boiler control charge over from auto to remote control.
e) If the explosion takes place in the furnace and gas flow makes round the
furnace check the condition of the furnace cl when its condition found O.K.
then close man holes and explosion doors that have got opened during
explosion. After that fire up the, then start pulverisers and charge over to coal
dust keeping oil support in service.
It should be kept in mind that, when fire dies out in furnace, sharp drop of water level
takes place but do not force feeding the boiler as water level may increase beyond limit
when the flame fires up again.
54
When spry line valves, nozzle etc. got checked or valves seat may get alomdamaged. Then adequate quantity of spray water could not be supplied.
7)
Sharp increase in amount of saturated stream from the boiler, taken for auxiliary
steam and soot blowing etc.
8)
55
7.
If above measures do not effect to decrease the SH Steam temp and reaches to
515oC and above and keeps during 3 to 5 minutes and continue to rise. The boiler
should be emergently stopped as per instructions.
8.
II)
III)
IV)
Uncontrollable of coal flow from Rek and coal dust from mill to furnace
ACTION:1.
Find out the reason for increase of pressure of steams and act accordingly.
2.
3.
Vent steam thro 710 valve to control pressure but practice to venting of steam
should be avoided so for as possible, due to reason of saving of raw materials and
cost.
4.
5.
6.
If we are unable to control increasing of pressure and safety devices (drums & SH
safety VIV3 & venting system of SH Steam) fails to operate to control pre. Then
emergently shut down boiler.
56
OPERATION OF MILLS
PRINCIPLES
The coal-enters to the center of the revolving bow Centrifugal force causes the material
to travel toward the outer perimeter of the bowl where it comes between the grinding ring in
the revolving bow and the mills. The mills, which are spring loaded, impart the pressure
necessary for grinding. The partially pulverised material continuous up over the edge of the
bowl.
Air enters the mill housing below the bowl, in directed upward part the bowl passes
through the classifier vanes at the top of the iner cone. The air picks up P.F. and heavier
particles striking against the deflectors return the bowl and get crushed. Lighter particles
through classifier vanes is sucked by exhauster fan and goes to burner through distributor
pipes.
Any tramps iron or difficult to grind foreign material in the feed is carried over the top
of the bowl where it drops out through the air stream to the lower part of the mill housing.
Pivoted scrapers attached to the bowl hub sweep the tramp iron into rejecting sport.
Mill type-603 XRS-X-Capacity 26.8 T (Moro) 33KV Motor KW amps Fineness 70%
through 200 mesh screen.
MILL OPERATION
CHECKINGS:
1.
Get sure that the maintenance work on mill-exhauster Coal feeder or any of its motors
are not going on and work permits if any has been surrendered by the respective department
viz B/M, P/M & I/M.
2.
Make sure that power is available in mill motor and coal feeder motor.
3.
Make sure that interlock system of hot air gate mill feeder is O.K.
4.
Make sure that feeder control-Hot air control & exhauster control drives are O.K.
5.
Make sure about lubrication in mill gear housing and Roller journals housing PIV
gear housing and exhauster bearing etc.
6.
7.
Make sure about cooling water flow through mill gear housing oil cooler.
Make sure that adequate supporting flame is there in the furnace.
57
C.
D.
1.
Mill temperature high: Increase temperature air and decrease hot air. Also increase
coal feeding watch on mill amps.
2.
Mill fire: Feed coal to the maximum extent possible by keeping watch on mill amps.
Open coal air damper now and reduce hot air. The fire should decrease or lost
otherwise shut down the mill and isolate the mechanically. Charge foam extinguishers
through manhole inside. Let the mill get cooled gradually.
3.
High motor amps: Reduce coal loading. Observe for any unusual sound,
for any foreign material and check rejection gate to be clear.
vibration
58
4.
Mill puffing: Due to low air flow maintain minimum air flow to get required coal
air velocity.
5.
Poor grindability: Due to warm out roller parts in bull ring, ring housing. Reducing
mill loading.
Excess rejection: Due to minimum air through the mill deracted capacity of the mill.
6.
MILL INTERLOCKS:
1.
There is an interlock system for protection of the mill groups and associated boiler.
a)
b)
c)
e)
Either exhauster isolating gate or exhauster vent valve will open or close
alternative.
2.
3.
4.
Check/operate the rejection gate and remove the rejection time to time.
5.
6.
7.
59
Superheater steam
Before reduction
After reduction
24
Soot blowers
60
9.
Do not operate the soot blower with excessive steam leakage through pecking.
10.
The hand cranks provided for emergency operation should be removed after their use
on the blower.
Blower No.
Type
25.26
T-30MKIE
11
27 to 30
T-30 NKIE
1 to 24
RWSE
10.5
WALL BLOWER
INSTRUCTIONS:1.
2.
Donot operate the blowers adjacent to burner at loads less than 60% MCR.
3.
Check nozzle position an alignment with respect to water wall after each shut-down of
the boiler.
4.
When adjusting limit switches, switch off the power to the unit to avoid any injuries.
5.
Before operating the blower made sure the drain holes in the motor frames point
downwards and are open.
6.
61
1.
2.
3.
Check up for starting current and normal running current of motor viz-a-viz the
manufacturing specification.
4.
5.
Check for the lubrication of bearing housing and inlet guide vanes etc.
6.
7.
Check up the wire mesh provided forwards the suction side of FD fan and arrange
for the cleaning of the same periodically.
8.
9.
In case any leakages are noticed from oil seals or level indicator, inform the shift in
charge to get the same attended.
62
10.
11.
12.
Before starting of the fan make sure that the man holes of the fan, drain cover are
closed. No water traces should be there in the FD fan duct.
In case of ID fan any erosion notice in the inlet duct or caring should be properly
recorded and informed to the concerned supervisor for necessary action,.
Keep the inlet guide vanes and its actuating level clean and free from accumulation
of ash for smooth operation.
DONTS:1.
2.
3.
4.
5.
6.
63
AIR PREHEATER
The regenerative type of air heater absorbs waste heat from flare gas, then transfers to
incoming cold air by means of continuously rotating heat transfer elements of specially
formed metal plates. Thousands of these high efficiency elements are speed and completely
arranged with twelve sector shaped compartment of gradually divided cylindrical shell called
the rotor. The housing surrounding the motor is provided with duct connections at both ends
and is adequately sealed by radial and circumferential sealing members-forming an air
passage through one half of the preheater and a gas passage through the other.
As the motor slowly revolves the mass of elements alternatively through the gas and air
passage, heat is absorbed by the element surfaces raising through the hot gas stream, then as
these same surfaces are carried through the air stream, then release the stored up
heat.thus greatly increasing the temperature of the incoming combustion process air.
The complete rotor is supported by a thrust bearing(spherical rotor bearing. To guide
the upper end of the rotor, a guide tornion is bolted to the face of the rotor post. The position
of this trunnion is maintained by a radial guide bearing assembly. The bearing is water
cooled.
The oil level of the support bearing is to be maintained such that the rolling elements of
the bearing are submerged in the oil.
An auxiliary drive through an oil turbine is provided to keep the air heater running in
case of failure of motor. The air passes through solenoid operated valve.
The air heater is provided with soot blowing arrangement at the bottom part of the
rotor towards the flue path.
Water washing arrangement through nozzle is provided for cleaning during shut down.
64
65
highest possible voltage initials random flash over between the electrodes. Too high a flash
over ( spark) rate will not hnlp result in reduction of useful power and interruption
of precipitation process but will also cause rapture of emitting electrode, due to electrical
erosion. A recommended flash over rate for optimum performance is found to be in the range
of 5 to 10 flash over per minute.
A fraction of the dust also gets deposited on the emitting wires, resulting in the
enlargement of the effective size of the wire which would inform suppress irrigation of gases
recovery for charging the dust particles. The effect is maintained by periodically dislodging
the dust particles by separate rapping mechanisms.
The performance of a precipitator is also closely related to even distribution of gas over
the cross section of the field. In order to minimize the re-entrainment of collected dust a gas
distribution system is provided in the inlet.
IMPORTANT INSTRUCTIONS ABOUT EPS
DOS
1.
MECHANICAL PARTS:1)
Check up draining of ash from the hoppers at least once a shift of duration not
exceeding 8 hours.
Ensure that ash flows freely and the heaters and associated thermostats are
functioning properly.
2)
RAPPERS:Ensure that the drives of the rapping mechanism of the bolts collecting and
discharge electrodes operate as details in the operation and maintenance manual.
Failure or improper operation of the rappers will lead to wastable and pool
performance of the precipitator. Check up the oil level in the geared motor.
3)
INTERLOCKIN SYSTEMS:-
66
Ensure that the interlocks and keys provided are positioned properly for the
safety of the equipments and operating personnel.
ELECTRICAL PARTS:1) Record the readings (KV milliamps) on the rectifier panel at least once a shift.
2) Adjust the power input from each rectifier control such that the optimum voltage
and current are maintained at low spark rate not exceeding 5 sparks per minute
on average. Operation at high spark rate will lead to lowering the life of the
emitting electrodes by electrical erosion and consequent snapping.
3) Check up the operation of heating elements for hoppers, insulator housing
Etc. from the readings or the meters on the auxiliary control panels. Failure of
heating elements shall be immediately attended.
4) Ensure that all the controls meters and indicating devices on the control panels
of transformer-rectifier sets are in proper working condition. Any damage must
be set right by replacement.
The cause of failure of any field of the precipitator like snapping of wire, control
not working properly etc. must be reported to the engineer in charge of the
precipitator for timely action to set right and replaced the damaged components.
DONTS:1. Do not try to operate the rectier set at higher voltage and current when there is
excessive sparking.
2. Do not allow the hopper to get field up with ash. This may lead to eventual
shorting of the high voltage system and rendering the filed ineffective.
3. Do not energize any electrical field without the drive for the associated rapping
device functioning properly.
4. Do not fail to record faults or abnormal operations of the precipitator during shift
and bring it to the notice of the concerned engineer.
67
5. Do not fail to observe the general safety regulation pertaining to the high voltage
equipment.
The complete bottom ash system shall be manually operated from the bottom ash local
control panel, one (1) No. to be provided for each Boiler Unit. However, the complete
fly ash system for all the three Units will be controlled from a common. Fly control
Panel.
1.
BOTTOM ASH SYSTEM
The bottom ash resulting from the combustion of coal in the boiler furnace of each unit
will be collected in the respective water impounded self-supporting hopper. Once in a
cycle of eight (8) hours, the feed gate below each bottom ash hopper will be opened by
means of a 4-way manually operated valve. The ash together with stored water will be
discharged into a clinker grinder, where the larger ash lump will be ground and the
resulting ash slurry will conveyed through pipeline to disposal area via Hydraulic Jet
Pump located under respective clinker grinder.
2.
FLY ASH SYSTEM:The fly ash system of all the three boiler Unit comprised two simultaneously of
working independent and parallel fly ash stream, namely, Stream-A and Stream-B
both of which will be provided with three (3) Nos. branch lines. One branch line
from each of three boiler unit will be connected to Stream-A while the other branch
line from each unit will be connected to Stream-B. Grouping of fly ash hopper outlet
of each boiler unit for connecting to one of the two branch lines will be done as
follows:-
68
i)
Brach line to Stream-A Two ( 2 ) Nos. Economiser Hopper and three (3)
Nos. E.P. Hoppers are indicated in Single Line Flow Diagram.
ii)
Branch line to Stream-B Two ( Nos.) Air Heater Hoppers and three (3 )
Nos. E.P. Hopper are indicated in single Line flow Diagram. Below each
fly ash hopper there will be an electro pneumatically operated ash
extraction valve and at the end of a branch line there will be an air-intake
check valve.
The operation of the both fly ash conveying stream are identical. Two hydraulic
exhauster (one working and the other stand-by) is provided at the heard of each
stream. Once in a cycle of eight (8) hours shift, high pressure water supply will be
made to the hydraulic exhauster which will in turn crate necessary vacuum to establish
an air flow in the fly ash conveying pipe line. After the air flow is established, the ash
extraction valve below one hopper to the branch (with header valve open) will be
opened and ash will be discharge into the fly ash conveying air steam). The air and fly
ash mixture gets mixed with water in the exhauster and the resulting ash slurry (mixed
up with air) will be discharge in to the air separator. Air (from the ash slurry) will be
vented out in the air separator and ash slurry ( free of air) will be discharged directly
to the disposal. I are due to gravity head.
3.
ASH SLURRY DISPOSAL SYSTEM:Ash slurry disposal system comprises two ( 2 Nos) disposal pipes one of which will be
working and the other will remain as standby. The system will be such that either
bottom ash of any boiler unit or fly ash system can be operated at a time through the
same disposal pipe line. Once in a cycle of 8 hours, bottom ash cleaning of the boilers
will be carried out one after another followed by the fly ash cleaning of all boilers.
Electro-pneumatic operated butterfly valves will be provided for isolating each
individual bottom ash and fly ash disposal lines from the main disposal pipe. A
universal cross over will be provided between the disposal lines so that the slurry can
be transported into disposal area by any of the liens.
4.
69
Continuous supply of service water at required pressure shall be tapped from the
purchasers service water header to meet the requirement of bottom ash hopper, seal
through make-up and bottom ash hopper window spraying. For gland flushing of
clinker grinder during bottom ash cleaning, filtered water at specified pressure will also
be tapped from purchasers filtered water header.
5.
B.
1.
2.
Start, stop, reverse push buttons for the clinker grinder motor.
Indication lamps for above.
Indication lamps for water line M.O. valve.
Seal water line solenoid valve open/close-PB & II
B.A. cleaning over-PB:
Indication lamps for slurry line solenoid operated valve in addition
necessary relays, fuses, space heater and mimic diagram.
70
i)
ii)
iii)
iv)
v)
Header and hopper selector switches and indication lamps for all hopper
and header valves;
vi)
vii)
viii)
ix)
x)
xi)
71
xv)
C.
2.
3.
4.
5.
After above operations are carried out necessary indication lamps on both the fly ash
and local control panels will be glowing and the following operations are to be
performed from the local control panel:
i)
iii)
Now the bottom ash cleaning is started by opening the feed gate through the 4-way
manually operated air line valve. In case the clinker grinder motor trips during ash
cleaning due to jamming of clinker, the grinder motor can be Inched in reverse
direction from local control panel to remove jamming.
After the ash clearing for any B.A. hopper is over the following operations are to
be performed to stop ash cleaning.
1.
2.
3.
72
sulrry line valve for that unit will be closed and B.A. Unit Selector Switch will
be set by the next desired position. The ash cleaning for the next bottom ash
hopper will be carried out following the same sequence of operation as stated
above.
b)
73
next hopper extraction valve in sequence and closed the first hopper extraction
valve.
If during the operation, the ash is discharged into the conveyor pipe line at too fast
rate, the vacuum rises above the normal conveying vacuum which causes vacuum
(VS-3) mounted on the fly ash line to operate to close the hopper extraction valve.
When overload condition is removed, VS-3 will reset to reopen the extraction valve
and ash conveying will continue.
In the event of Plugged Hopper condition i.e., when the ash arches over the
hopper outlet and does not flow, a vacuum switch (VS-2- operates through a- time
delay (0-5 minutes approx) to energize necessary relays to give Plugged Hopper
alarm. After this alarm is annunciated the Auto-Jog-Manual
switch is to be manually indexed to Jog position. Now the system can be kept
hold for visual inspection or manual clearing of the plugged Hopper. On the other
hand if the Jog push bottom is pressed in this condition, the step switch will step
to the next position. The operation selector switc h is then again put back to Auto
position and the step switch automatically continues to sequence thereafter.
When all the hopper of one unit is cleared the step switch will step to the next unit
by passing, if necessary, any shut down unit, guided by the Unit Shutdown
Selector Switch. Then the branch header valve and corresponding hopper valve in
sequence for the next running unit will be opened after closing of the earlier branch
header valve and hopper valve.
When the hoppers of all the remaining units are cleared in sequence, the step
switch will reset itself for next manual starting.
During the fly ash clearing operation one air blower will deliver fluidizing air
through the fluidizing pads for two hoppers (one from each stream) from which ash
is being discharged to the conveying pipe line.
2. REMOTE MANUAL OPERATION:
For remote manual operation of hoppers, first the Auto-Jog-Manual Selector
Switch is set at Manual position.
74
Now the branch selection shall be done by Header Selector Switch and individual
hopper cleaning shall be carried out by setting Hopper Selector Switch to
selected positions.
Vacuum switches VS-2 &3 shall be interlocked with manual clearing in the same
manner as described above for automatic sequential operation, and vacuum switch
VS-1 gives the empty hopper indication lighting an Amber Lamp Hopper Selector
Switch is to be to the next selected position thereby closing the early operating
valve and opening the selected hopper valve.
It shall be possible to carry cut this operation for all the fly ash hoppers at random.
The fluidizing blower and the solenoids in the fluidizing air pipe line shall be
interlocked with the fly ash system operation as described in automatic operation.
D. SYSTEM INTERLOCKS:
1. INTERLOCKS BETWEEN BOTTOM ASH SYSTEM AND FLY ASH SYSTEM
AND BETWEEN BOTTOM ASH SYSTEMS OF DIFFERENT BOILER UNITS.
i) An interlocks shall be provided between Bottom ash slurry line isolating valve and
fly ash slurry line valve so that one valve cannot be opened till ht other valve is closed.
ii)
While cleaning bottom ash system of any of the boiler units depending on the
position of the Bottom Ash Unit and Fly Ash Selector Switch, it is ensured that
cleaning of other BA Units and fly ash system cannot be carried out simultaneously.
2. BOTTOM ASH SYSTEM INTERLOCKS
i) The water line motor operated valve before jet pump cannot be opened unless the
respective slurry line butterfly valve is kept open.
ii) The motor operated valve will close immediately whenever the butterfly valve in
slurry line closes.
iii) The slurry line butterfly valve can be closed only if the respective waterline motor
operated valve is kept closed.
iv)
Clinker grinder motor cannot be started unless the following requirements are
met:
75
a) Required water pressure available at the jet pump inlet, sensed via a pressure
switch PSW3.
b) Required water pressure available at the clinker grinder gland seal sensed via
a per pressure switch PSW4.
In the event of water pressure at the jet pump inlet and the clinker grinder
gland seal fall below pre-set valves the running grinder motor shall trip.
3. FLY ASH SYSTEM INTERLOCKS
i) Four (4) Nos pressure switches shall be provided in water line between
Hydraulic exhauster and the motor operated water line valve.
a)
Out of these four, two (2) pressure switches (PSW1) shall be interlocked with
the vacuum breaker such that if adequate water pressure is not there the vacuum
breaker cannot be closed to start fly ash cleaning. If the water pressure falls during
operation, the vacuum breaker will thereby stopping the fly ash cleaning operation.
b)
Other pressure switches (PSW2) shall be inter locked with the fly ash system
such that if adequate water press is not there fly ash cleaning cannot be started and
conversely the system stops automatically when pressure drops below the preset valve.
ii)
Two (2) Nos. air pressure switches PSA (one for each stream of fly ash)
connected to the compressed air line shall be so interlocked with the fly ash
system that the fly ash system cannot be started unless there is sufficient air
pressure. The fly ash clearing shall stop when the air pressure fails below set
pressure.
iii) Ash extraction valve shall open in sequence such that the ash hopper valve
nearest to the air intake valve shall/open first for each branch.
iv) Ash clearing will start from the economizer Hopper branch and end in E.P.
Hopper breach for stream A for stream B, the ash clearing will start from the Air
Heater Hopper branch and end in E.P. Hopper branch.
v)
As the extraction valve of each of the hopper having fluidizing pads opens, its
respective fluidizer air valve shall also open to inject fluidizer air to the pads.
vi) The water line motor operated valve before exhauster cannot be opened unless
the fly ash slurry line butterfly valve is kept open.
vii) The motor operated valve will close immediately whenever the slurry line
butterfly valve closes.
viii) The slurry line butterfly valve can be closed only if the motor operated valve is
kept close.
E.
ANNUNCIATION SYSTEM
76
a)
c)
2.
The Annunciation System shall remain effective even when the fly ash
system is operated manually.
3.
1.
GENERAL
This boiler is provided with 8 Nos. of oil burners, 4 Nos. of oil guns to fire light or
heavy oil in EL AB and 4 Nos. of oil guns to fire heavy oil in ELBC. The light oil is used
for cold start-up and heavy oil for flame stabilization and load carrying upto 30% of the
boiler MCR. The light oil/burners can be put into operation after starting the corresponding
ignitors and proving ignitor flame.
2.
BURNER CONTROL:
Oil burner system consists of the following field equipment. These are controlled from
the burner control panel located in the unit control room. The equipment send necessary feed
back and flame present signals to the control panel.
1.
2.
3.
4.
5.
6.
1 No.
1 No.
1 No.
8 Nos.
8 Nos.
8 Nos.
77
7.
8.
9.
8 Nos.
8 Nos.
8 Nos.
Ignitor oil, light oil and heavy oil trip valves can be individually operated from the
control panel. Ignitor trip valves/Burner trip valves and Burner scavenge valve can be
operated in pairs from the control panel.
Heavy oil manual valve, light oil manual valve, atomizing steam manual valve and atomizing
air manual valve before eadh burner in ELAB have to be operated manually as per fuel
selected in the control panel.
Burner control panel consists of 3 sections: one for common equipment. AC and DC supply
changeover system and annunciation system: second for control of individual burner
equipment in ELAB and annunciation system; third for control of individual burner
equipment in ELBC and annunciation system.
II)
(S1)
(S2)
(S3)
(PB10, PB 11)
(PB1)
(PB2)
(PB3)
(PB4)
(PB5)
(PB6)
(PB7)
(PB8)
(PB9)
(13PB1)
(24PB1)
78
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
B.
INDICATING LAMPS:
1. RED LAMPS TO INDICATE:
a.
b.
(1ACL)
(2ACL)
(57PB1)
(68PB1)
(13PB2)
(24PB2)
(57PB2)
(68PB2)
(13PB3)
(24PB3)
(57PB3)
(68PB3)
(13PB4)
(24PB4)
(57PB4)
(68PB4)
(13PB5)
(24PB5)
(57PB5)
(68PB5)
(13PB6)
(24PB6)
(13PB7)
(24PB7)
79
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
n.
o.
p.
q.
r.
(1DCL)
(2DCL)
(HL)
(HL2)
(HL3)
(L2)
(L3)
(L4)
(1L1)
(2L1)
(3L1)
(4L1)
(5L1)
(6L1)
(7L1)
(8L1)
80
2.
3.
(L1)
(L5)
(L6)
(L7)
(L8)
(L9)
(13 L1)
(24L1)
(57L1)
(68L1)
(1FL)
(2FL)
(3FL)
(4FL)
(5FL)
(6FL)
(7FL)
(8FL)
(9FL)
(13FL)
(24FL0
(57FL)
(68FL)
(1FL1)
(2FL1)
(2FL1)
(2FL1)
(2FL1)
(2FL1)
81
20
21
22
23
24
25
26
27
28
29
III
IV
Scanner 7failed
Scanner 8 failed
Burner-1 auto trip
Burner-2 auto trip
Burner-3 auto trip
Burner-4 auto trip
Burner-5 auto trip
Burner-6 auto trip
Burner-7 auto trip
Burner-8 auto trip
(2FL1)
(2FL1)
(1FL1)
(2FL1)
(3FL1)
(4FL1)
(5FL1)
(6FL1)
(7FL1)
(8FL1)
2)
3)
Running condition of ignitor fan is indicated by the burning of red lamp (L3)
4)
Running condition of scanner fan is indicated by the burning of red lamp (L4)
5)
Heavy oil (H.O.) temperature OK is indicated by the burning of green lamp (L7)
6)
Closed condition of all ignitor trip valves is indicated by the burning of green
lamp (LI)
7)
8)
9)
10)
Check-up whether the annunciation system and other operation indicating lamps
are functioning alright by pressing the system test push button PB8.
82
A.
1.
The following conditions should be satisfied to open the ignitor oil trip valve IOTV.
a)
b)
c)
d)
e)
f)
2.
B.
3.
4.
5.
6.
83
A.
B.
IGNITOR PAIR:
7.
8.
MFR de-energised
b)
c)
84
d)
e)
LOTV closed .
Ignitor pair stop push button in pressed position and elevation load greater than
30% and both burner pair selected on HO and all four BTVs of the elevation open.
f)
Ignitor pair stop push button in pressed position and corresponding scavenge trip
valves open and scavenge time elapsed or corresponding scavenge trip valves closed.
NOTE:-
1.)
in EL
2.)
For stopping ignitors under the above conditions, the corresponding burners shall be
stopped for normal shut down.
3.)
When ignitor start command is initiated, corresponding ITVs open and simultaneously
corresponding timer and ignition transformer are energized. Timer and ignition
transformer de-energise once the flame is proved within the pre-set time. If flame is not
proved within pre-set time, ignition transformer will de-energise and ITV will also
close.
4.)
85
Any of the following conditions should be present to trip the burner pair:
a)
Boiler MFR energized.
b)
Emergency trip push button in pressed position.
c)
LOTV/HOTV closed when LO/HO is fired (For EL AB only For EL
BC HOTV closed).
d)
Associate ignitors not in service and less than 2 out of 4 scanner show
flame.
e)
Associate ignitor not in service and EL load less than 30% and adjacent
less EL feeders not in service.
NOTE:
f)
g)
h)
i)
j)
k)
l)
m)
86
1)
When burner pair start push button is pressed, one of the two burners will start
and the second burner will start after a time delay of 15 secs.
2)
Burner pair start push button is common for two burner trip valves and burner
atomizing valves. When the push button is depressed, first the burner atomizing
valve will open and then the burner trip valve.
Burners in opposite corners from a pair.
If one of the ignitor fails, only the corresponding burner stopped.
3)
4)
F.
SCAVENGE:
11.
V.
OPEATION PROCEDURE:
A.
B.
SEQUENCE OF OPERATION:
1)
2)
87
3) Check-up whether all initial conditions required to open ignitor oil trip
valve (IOTV) are satisfied Press the LOTV open push button PB2 IOTV
solenoid energises through contacts of R2A (MFR energized), R3
(Ignitor fan ON) R5 ( compressed air pressure OK), PB1 (IOTV close
PB), PB2 (IOTV open
R6 (L.O pressure OK) and R19 (All ITVs closed) and holes on through contacts
of R2A, R3, R5, PB1, R4), R4OA (IOTV open) and R8 (IO pressure OK) or
R19. The open condition of the valves is indicated by the glowing of the red
lamp L5.
5) After opening IOTV, check up where all initial conditions required for starting
the ignitors are satisfied. Press ignitor pair 1 & 3 start push button 13 PB1,
13R1 and 13T1 energise. Through contacts of 13R1 (ignitor start impulse),1R1
(ignitor flame not proved) and IR3 (no trip impulse available) ignition
transformer energises. At the same time through contacts of DP switch and
13R1 (line 275 and 272) ignitor trip valve open coil gets supply and starts
opening. When ignitor trip valve starts opening, limit switch CLS changes over
and coil gets supply through 13R1 and CLS (line 269). When ITV completely
opens OLS changes over and if DP and flow are O.K. the relay IRI energises
indicating ignitor is on. Likewise ignitor 3 comes into service. Similarly any
ignitor pair can be put into service by pressing corresponding ignitor pair start
push button. If the ignitor flame proven condition does not come within the
preset time, 13 R2 energises which in turn energises trip relay 1R3. Now through
contract of 1R3 (line 270) and CLS ignitor trip valve close coil energises and
ITV starts closing. When it completely closed, limit switch CLS changes over
and relay 1R15 energises indicating ignitor trip valve closed condition.
5)
Check-up whether all initial conditions required to open light oil trip valve
(LOTV) is OK. Press LOTV open push button PB4. LOTV solenoid energises
through contacts of R2A (MFR energized), PB3 (LOTV close PB), PB4 (LOTV
open PB), R6(L.O. pressure OK), 1R10 to 4R10 (BTVs closed in ELAB) or
1R12 to 4 R12 (LOMVs closed) and holds on through contacts of R2A, PB3
R17 (LOTV open) R41 and R14 (Air/oil DP OK) or R41 and 1R10 to
4R10/1R12 to 4R12 lamp PB4 glows indicating LOTV open condition.
6)
Before starting the oil burner, the respective gun to be manually brought to the
advanced position and the oil gun should be properly purged.
88
Check-up whether the initial conditions required for opening the scavenge valves
are satisfied. Press the burner scavenge pair start push button (13 PN5).
Contacts R2B (MFR energized)13R5/3R9 burner not started/Burner scavenge
not complete),1R10 (BTV closed) and 13R8(Auto/Manual scavenge start
impulse) close or remain closed depending on the initial condition of the
contracts. At this point, the circuit branches out into two, one going to energise
the atomizing valve solenoid (BaV1) and the other going to energise the
scavenge valve solenoid (BSV1). The BAV1 energises through 13R5 (burner
pair not started) and 1R6
(BTV not energized) after which the BSV is energized through 1R2 (associate ignitor
on), 1R13/1R14 (associate steam/air manual valve closed). 1R4(gun in firing position)
and 1R7 (BAV open). The scavenge and atomizing valve for Burner-3 also open
simultaneously in a similar fashion Steam/Compressed air is allowed through the oil
gun for the present time. Purge complete annunciation and lamp come on after
completion of the gun purge cycle To close the burner scavenge valve either the burner
pair start push button must be operated or the burner gun must be brought back
manually from the advanced position in case the burners are not to be put into service
immediately.
NOTE:
Burner gun should not be kept in advanced position for long time in the hot furnace
unless a cooling medium (steam/air) is available. Otherwise the burner tip will get
spoiled.
7)
Select LO firing, by pressing 13PB6. Check up whether all initial condition required to
start the burner with light oil are satisfied. Press burner pair start push button 13PB3.
Burner atomizing valve solenoid energises through the contacts of R2B. 13R12A,
13R12, R17,R22, 13R5, 13R4 and 1R8. After this burner trip valve solenoid energises
thro R2B, 13R12A, 13R12, R17, R22, 13R5, 13R4, 13R6, 1R2, 1R4, 1R7, BSV1
CLS, 13R12, 1R11, 1R13, 1R12, 1R14. The light oil is atomized as long as L.O.
pressure is OK and burner is aided by ignitor flame. After a time delay Burner-3
comes into service. Lamp 13PB4 glows indicating Burner-1 and 3 are in service.
Similarly next pair of burners can be brought into service in ELAB
8)
With 4 L.O. burners and 4 ignitors in service, steam (required for HO heating) shall be
admitted and the HO pumpoing and heating units shall be prepared for HO firing.
89
With the above, H.O. at boiler front will be available. Check-up the pressure and
temperature of H.O. be for HOTV.
Open the heavy oil re-circulation manual valve. Check up whether intial conditions
required to open HOTV are satisfied. Press HOTV open push button. HOTV open
solenoid energises through R2, PB5, PB6, R12, R9 abd 1R10 to 8R10. HOTV open
lamp PB6 glows. Allow the HO to circulate in the line till the temperature in the
temperature gauge before HOMRC valve (HOT) is observed at 100oC. Close the H.O.
manual recirculation valve.
9)
Check-up whether all initial required to start the burner in ELBC are satisfied. Press
burner pair start push button (57PB8). Burner-5 atomising valve open and
subsequently Burner-5 trip valve opens. The HO burns with the ard of ignitors. After
a time delay Burner-7 atomising valve and burner trip valve open. Lamp 57PB4 burns
indicating Burner 5 & 7 are in service.
10)
11)
When all burners are in service and if there is an indication for elevation load greater
than 30% (L8), the ignitor may be removed from service.
12)
AUTO SCAVENGING:
To stop oil burner, ignitor must be put in service if not in service. Now press burner
stop push button, BTV closes. Then burner atomizing valve and burner scavenge valve
open and admit steam/compressed air to clean the gun. The remnant oil in the gun is
burnt off by the ignitors. After preset time the ignitor is stopped, the flow of
steam/compressed air is continued through the gun and purge complete light/alarm
comes. Reset the alarm. Retract the gun manually. On retraction burner atomizing
valve and scavenge valve close.
90
Remote manual purging of the gun may be performed by pressing scavenge start PB as
under section V item 6.
INTERLOCK SYSTEM
I.
STARTING :- I.D. FAN can be started if the following conditions are satisfied.
a)
Regulating vane in minimum position.
b)
Start signal initiated.
c)
Outlet & inlet dampers are in close position.
TRIPPING :- I.D Fan can be tripped if any one of the following conditions exists
a)
Winding temp. high temp. trip setting is 1050 C
b)
Electrical protection operated :
i) Over load
ii) Instantaneous short circuit
iii) Instantaneous earth fault
iv) Instantaneous unbalance
v) Delayed under voltage
c)
LOCAL CONTROL :- I) I.D fan can be started from local if L.R. switch is selected
local by turning T-N-C switch to close position.
II) I D fan can be tripped from local by turning the T-N-C switch to
trip position.
II
91
IV
STARTING
F.D. fan can be started if the following conditions are satisfied.
a) Direct or cross connections ID fan is running.
b) Inlet and outlet dampers of corresponding ID fan are open.
c) Any one set of the flue gas dampers before and after EP are open.
d) Regulation vanes are in minm position.
e) Start signal initiated
f) F.D. fan outlet damper in close position.
II
TRIPPING
FD fan motor will be tripped if any one of the following condition exist.
a) Corresponding (selected) ID fan tripped
b) Motor winding temperature high setting 1050 c
c) Electrical protection operated.
III
92
b)
c)
d)
e)
IV
IGNITOR FAN
STARTING :a) Fan can be started from UCB by pressing start push button.
b) Fan can be started from local by pressing start push button if load operation is
selected.
TRIPPING :Motor can be tripped if any of the following conditions exists.
a) Stop push button of UCB/local pressed.
b) Overload protection acts.
c) Both FD fan tripped.
SCANNER FAN
1.
AUTO STARTING
Fan starts running automatically when any of the following conditions exists.
1) Furnace/scanner outlet DP (differential pressure) below 2.2 W.C.
2) Both FD tripped and emergency damper open.
2.
MANUAL STARTING ;-
93
B.
control at U.C.B.
i) Automatic selector switch 1 no.
ii) Open-close selection switch 1 no.
iii) Open-close indication lamp 2 no.
INTERLOCK
i) Damper can be open and close by pressing open/close PB if manual position
selected.
ii)
Damper opens automatically if both F.D. trip.
iii)
Auto closing in the event of one of the F.D. fan is running.
MFR SYSTEM
A. CONTROL AT U.C.B.
i) Purge start push button
ii) Reset push button.
iii) Emergency trip P.B.
iv) Lamps for (1) purge progress.
(2) Purge required
(3) Purge complete.
(4) M.F.R. On.
Purge interlock is O.K.
B
INTERLOCK :-
94
95
MFR de-energised to trip the boiler when any of the following conditions exists.
i) Both F.D. fan tripped or both I.D. fan tripped
ii) Drum level very low -200 M.M.W.C.
iii) Furnace draught very high
iv) All mills tripped/Heavy oil ignitor oil and light oil trip valves closed. If 3 out of 4
ignitors are proven in any elevation.
v) Emergency trip P.B. pressed.
vi) Air flow less than 30%
vii) Scanners show no flame (Both elevation scanner show min 2 out of 4 scanners. No
flame) and 3 out of 4 ignitors not in service
MILLS
D)
STARTING
Mill can be started when followed conditions are satisfied.
i)
M.F.R. energized
ii)
iii)
iv)
v)
96
TRIPPING
i)
If F.D. fan one set gets tripped, all mills tripped except selected mills
ii)
If Both I.D. and F.D. fans tripped, all mills tripped.
iii) If electrical protection operated
97
LOCAL CONTROL ;a) Feeder can be started from local by pressing start PB. If switch selected in local
position.
b) Feeder can be tripped from local by pressing stop PB.
EXHAUSTER IN LET CONDITION DAMPER
INTERLOCK ;a) To connect auto control when mill is started.
b) To disconnect auto control when mill is stopped.
c) To become stay put under all failure.
98
FUEL SPECIFICATION
COAL
1.
2.
3.
4.
5.
6.
7.
8.
9.
Carbon
Volatile Matter
Moisture
Ash
Hydrogen
Grindobility
High headers valve
Low heating value
Coal size feeding to mill
30 %
24.5 %
6.5 %
39.0 %
3.05 %
50 hard groove
4271 K cal
4100 K cal.
20 mm
C/H ratio
Sp. Gravity (150 C/40 C)
Sulphur (s) wt. %
Nitrogen wt.
Oxygen wt.
Ash wt. ppm
Sodium (Na) wt. ppm
Vonadium (Va) wt. ppm
Silica
wt. ppm as silica maxm
Calcium
wt. ppm
maxm
Magnecium wt. ppm
maxm
Nickel
maxm
Water volume
%
0
0
Viscosity (C.S.) 50 at 95 C
Viscosity (C.S.) 500 at 950 C
8:5
0.85 to 0.95
4.20 %
0.4
0.44
<500 ppm
80
160
5
40
2 ppm
50 ppm
10 % maxm
150 contistocke
30 contistocke
FUEL OIL
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
POLISH WATER
1.
2.
3.
P.H.
Turbidity
TDS
6.5 TO 6.9
<20 DEGREE
<418 PPM
99
4.
5.
6.
7.
8.
9.
10.
11.
12.
--------------------------------------
General requirement
Total hardness
PH value at 250 c
Conductivity
Oil Contains
SIO2 CONTAINS
Oxygen [ o2]
Total co2
Fe contents
Pressure
Temperature
Sio2
TDS
PO4
Fe
Al