1 Name of Work
:-
2 Cost of Estimate
:-
3 Authority
:-
4 Budget Provision
:-
5 Necessity
:-
B.I.No. 2314 Grant No. 24/5054 (1222) with budget provision of Rs.35.00 Lakhs.
for year 2015-16.
The Administrative approval of Harinbhatta nalla Bridge is accorded by Govt.of
C.G. vide letter no. F - 17-18/2015/19/tech-2 Dated 22-05-15 for amounting
Rs.513.61 lacs.Hence technical sanction from competent authority is necessary
as per norms of PWD C.G..,estimate has been framed for Rs. 490.23 Lacs.
Provisions
A.
370.01 Lacs
Bridge Proper
1 Type of bridge
:-
High level
2 Length of bridge
:-
3 Overall width
:-
8.40m.
4 Clear Roadway
:-
7.50 m.
5 Type of foundation
:-
Open foundation
6 Type of Sub-structure
:-
1. Pier
:-
8 Fixed Items
:-
Crash Barrier Railing, wearing coat, Strip seal expansion joint, Name plate etc
complete as per MORT & H Std. Drg.
B.
Approaches
i)
Patewa Side
139.00 M
Darra Side
134.00 M
Total length
273.00 M
ii)
:-
8.400 M.
iii)
Width of crust
:-
7.50 M
iv)
Thickness of crust
:-
300 mm.
W.M.M.
250 mm
B.M.
S.D.B.C
v)
Patewa Side
Darra Side
Total
Sub Engineer
25 mm
= 2 x 233.00 m.
Specification
:-
MORT&H and IRC specification will be followed for the construction of the bridge.
Rates
:-
Executive Engineer
P.W.D. Bridge Const. Division
Raipur (C.G.)
GENERAL ABSTRACT
Name of work- Construction of H.L. Bridge across Sarar Nalla
on Darra Patewa Road.
Circle
Division
Length of Bridge
Width of bridge
8.40m
(A)
Bridge proper
(i) Foundation
Rs.
5581025.00
(ii) Sub-Structure
Rs.
4684517.00
(iii) Super-Structure
Rs.
16460971.00
Rs.
26726513.00
Total of (A)
(B)
Approaches
Rs.
3448909.00
(ii)B.T. work
Rs.
1239660.00
Rs.
5586230.00
Total of (B)
Rs.
10274799.00
Grand Total
Rs.
37001312.00
Rs.
Say
370.01 Lacs
Executive Engineer
P.W.D. Bridge Const. Division
Raipur (C.G.)
ABSTRACT
Name of work- Construction of H.L. Bridge across Sarar Nalla on Darra Patewa Road.
s.n
o.
1
1
S.O.R.
ITEM
2
3
CH-2 / Excavation for Structures Earth work in
2.1 / excavation of foundation of structures as
P-13
per drawing and technical specification,
including setting out,
construction of
shoring and bracing, removal of stumps
and other deleterious matter, dressing of
sides and bottom and backfilling with
approved material including dewatering
etc. complete.
I
(i)
II
Descriptions
Ordinary Soil
Upto 3 m depth
Ordinary Rock (not requiring blast)
Quantity
Unit
Rate
Amount
856.073
575.947
cum
cum
175.20
295.20
149984.00
170020.00
155.636
333.097
cum
cum
4613.00
5992.00
717951.00
1995917.00
mt 68693.00
2288143.00
33.310
CH-2 /
10
40
100
each
m
m
5951.00
1300.00
1475.00
total
59510.00
52000.00
147500.00
5581025.00
s.n
o.
1
5
S.O.R.
ITEM
Descriptions
3
SUB STRUCTURE
and
laying
Plain/Reinforced
Quantity
Unit
Rate
Amount
CH-3 / Providing
3.6/ cement concrete in sub-structure complete
P-20
as per drawing and technical specifications
section 1500, 1700 and 2200 (Newly laid
concrete shall be covered by gunny bags).
A
(d)
(iii)
CH-3 /
3.7/
P-21
Height upto 5m
Using concrete mixer
R.C.C. Grade M-30
Supplying, fitting and placing HSD (High
Strength
Deformed
Steel)
bars
reinforcement in sub-structure complete as
per drawing and technical specifications
section 1600 and 2200.
27.654
cum
6370.00
1761565.00
mt 69002.00
1908187.00
276.541
704.450
cum
905.00
637527.00
86.520
cum
1926.00
166638.00
210600.00
cucm
1.00
Total
210600.00
4684517.00
CH-3 /
CH-3 /
and
Technical
Specifications
s.n
o.
1
S.O.R.
ITEM
Descriptions
3
SUPER STRUCTURE
10 CH-4 / Furnishing
and
Placing
4.1/ Reinforced/Prestressed cement concrete in
P-24 super-structure as per drawing and
Technical Specification sections 1500, 1600
and 1700 (Newly laid concrete shall be
covered by gunny bags).
B
(i)
(a)
(ii)
Height 5m to 10m
Quantity
Unit
Rate
Amount
885.603
cum
7263.00
6432135.00
106.272
mt 70101.00
7449799.00
82.688
cum 11847.00
979599.00
294.00
rm
600.00
176400.00
54
no
2007.00
108378.00
7.519
cum
4437.00
33362.00
25.200
cum
9467.00
238568.00
15 CH-4 /
16 CH-4 /
s.n
o.
S.O.R.
ITEM
Descriptions
1
2
17 CH-4 /
3
Strip Seal Expansion Joint (Providing and
laying of a strip seal expansion joint
4.18/ Pcatering to maximum horizontal movement
29
upto 70 mm, complete as per approved
drawings and standard specifi cations to be
installed by the manufacturer/supplier or
their authorized representative ensuring
compliance
to
the
manufacturer's
instructions for installation.)
Quantity
Unit
Rate
Amount
84.000
Rm 11124.00
934416.00
18 CH-4 /
294.000
sqm
56.00
16464.00
no
6600.00
26400.00
77
tonne
Sub
Engineer
850.00
65450.00
TOTAL 16460971.00
Grand total 26726513.00
Executive Engineer
P.W.D. Bridge Const. Division
Raipur (C.G.)
DETAILED ESTIMATE
Name of work- Construction of H.L. Bridge across Sarar Nalla on Darra
Patewa Road.
Length of bridge
Width of bridge
8.40 m
Formation level
R.L. 104.425 m
Soffit level
R.L. 103.500 m
R.L. 102.000 m
R.L.
99.880 m
R.L.
99.425 m
R.L.
96.985 m
R.L. 95.000 m
R.L. 95.000 m
P4 & P5
R.L. 94.500 m
P6,P7&P8
R.L. 95.500 m
A1 & A2
P1,P2 & P3
s.n
o
S.O.R.
ITEM
CH-2 /
2.1 /
P-13
I
(i)
Descriptions
No.
H/D
Quantity
Unit
Ordinary Soil
Upto 3 m depth
Av. Ground level R.L.99.880 m
Abutment A1& A2 (Patewa& Darra side)
(R.L.99.880 m to R.L.96.985 m)
6.850
8.700
2.895
345.055
cum.
(5.3)2
2.895
Total
511.018
856.073
cum.
cum.
8.700
1.985
236.592
cum.
Pier P1 to P8
(R.L.99.880 m to R.L.96.985 m)
II
3.14/4
6.850
Pier P1 to P3
(R.L.96.985 m to R.L.95.000 m)
3.14/4
(5.3)2
1.985
131.395
cum.
3.14/4
(5.3)2
2.485
109.662
cum.
3.14/4
(5.3)2
1.485
Total
98.298
575.947
cum.
cum.
2
8
6.850
3.14/4
8.700
(5.3)2
0.150
0.150
17.879
26.478
cum.
cum.
2
8
30.500
3.14/4
0.300
(5.3)2
1.500
1.500
( - )
27.450
264.776
-172.802
cum.
cum.
cum.
Pier P4 to P5
(R.L.96.985 m to R.L.94.500 m)
Pier P6 to P8
(R.L.96.985 m to R.L.95.500 m)
CH-2 /
2.6/
P-13
A
(i)
P1 to P8
Trench filling
A1 & A2
P1 to P8
Deduct footing
s.n
o
S.O.R.
ITEM
(vii)
Descriptions
No.
(1.800)2
0.400
Total
6.550
Unit
33.012
cum.
0.300
4
8.400
0.250
2
8.400
0.300
4
5.700
0.250
4
5.700
(5.00)2
8 3.14/4
8x1/2 3.14/4*(5.0*5.0+
2.0*2.0)
3.500
3.500
3.500
3.500
35.280
14.700
23.940
19.950
cum.
cum.
cum.
cum.
0.600
94.260
cum.
0.500
45.530
cum.
Pier P1 to P8
3.14/4
Quantity
0.300
Side
Inter
H/D
cum.
cum.
-8
-8.144
155.636
Pier Soft
(R.L.95.400 m to R.L.98.900 m)
8.400
Pier shaft P1 to P3
(R.L.96.100 m to R.L.99.425 m)
3.14/4
(1.80)2
3.325
25.387
cum.
3.14/4
(1.80)2
3.825
19.469
cum.
3.14/4
(1.80)2
2.825
Total
Pier P4 & P5
(R.L.95.600 m to R.L.99.425 m)
Pier P6 to P8
(R.L.96.600 m to R.L.99.425 m)
CH-2 /
2.24/ P18
CH-2 /
2.25/ P18
(i)
(ii)
(iii)
CH-3 /
3.6/
P-20
A
(b)
(iii)
21.569
cum.
333.097
10
10
1
4
10
40
5
2
3
5
5
5
Total
25
10
15
100
nos.
m.
m.
m.
m.
m.
SUB STRUCTURE
Providing and laying Plain/Reinforced
cement concrete in sub-structure complete
as per drawing and technical specifications
section 1500, 1700 and 2200 (Newly laid
concrete shall be covered by gunny bags).
Height upto 5m
Using concrete Mixer
R.C.C. Grade M-30
Abutment A1 & A 2 wall
(R.L.99.880 m to R.L.102.600 m)
4
2
4
4
8.400
8.400
5.700
5.700
0.300
0.250
0.300
0.250
2.720
2.720
2.720
2.720
27.418
11.424
18.605
15.504
cum.
cum.
cum.
cum.
2
6
2
8.400
0.700
8.400
1.150
0.550
0.300
0.400
0.461
1.100
7.728
1.065
5.544
cum.
cum.
cum.
(R.L.102.600 m to R.L.104.100 m)
Cap
pedestal
Dirt wall
s.n
o
S.O.R.
ITEM
Descriptions
No.
back
inner
Side
Inter
2
2
4
4
Pier P1 to P8
8.400
8.400
5.150
5.150
H/D
Quantity
Unit
0.300
0.250
0.300
0.250
1.500
1.500
1.500
1.500
7.560
6.300
9.270
7.725
cum.
cum.
cum.
cum.
(1.80)2
1.675
34.103
cum.
1.800
1.800
1.800
0.550
0.400
0.600
0.900
0.461
10.368
53.568
51.840
8.519
cum.
cum.
cum.
cum.
276.541
cum.
Pier Shaft
(R.L.99.425 m to R.L.101.100 m)
(R.L.99.300 m to R.L.101.700 m)
Squarehead
Cap
8
8
8
48
pedestal
3.14/4
1.800
6.200
4.000
0.700
Total
6
CH-3 /
3.7/
P-21
CH-3 /
3.9/
P-22
A1 & A2
(R.L.102.600 m to R.L.104.000 m)
A1 & A2
CH-3 /
3.10/ P22
CH-3 /
3.14/ P22
2.850
2.850
2.450
2.400
7.200
7.200
402.192
196.992
cum.
cum.
4
2
4
2
2.850
2.850
2.300
2.300
2.450
2.400
2.450
2.400
1.400
1.400
1.400
1.400
Total
39.102
19.152
31.556
15.456
704.450
cum.
cum.
cum.
cum.
cum.
17.500
0.600
4.120
Total
86.520
86.520
cum.
cum.
54
40.000
25.000
3.900
210600.000
cucm.
8
4
s.n
o
S.O.R.
ITEM
10
CH-4 /
4.1/
P-24
B
(i)
(a)
(ii)
Descriptions
CH-4 /
4.2/
P-27
H/D
15.000
6.000
0.888
719.280
18
15.000
1.200
0.188
74.448
147.000
0.450
0.300
39.690
147.000
0.350
0.250
25.725
147.000
0.225
0.400
26.460
CH-4 /
4.4/
P-27
Total
885.603
concrete
including
drawing
as per
9
2
15.000
6.000
147.000
7.500
7.500
0.075
0.075
Total
Total
14
CH-4 /
4.9/
P-27
15
CH-4 /
16
CH-4 /
4.11/ P28
17
CH-4 /
4.18/ P29
cum.
106272.3600
106.2724 M.T.
on Approach
4.10/ P27
Unit
12
Quantity
Furnishing
and
Placing
Reinforced/Prestressed cement concrete in
super-structure as per drawing and
Technical Specification sections 1500, 1600
and 1700 (Newly laid concrete shall be
covered by gunny bags).
cantiveler
11
No.
75.938 cum.
6.750 cum.
82.688 cum.
294.000 Rm
294.000 m.
54
nos.
7.300
5.150
0.100
7.519 cum.
7.519 cum.
8.400
6.000
0.250
25.200 cum.
10
8.400
s.n
o
18
S.O.R.
ITEM
CH-4 /
4.20/ P29
19
CH-4 /
4.23/ P29
20
CH-4 /
4.24/ P30
Descriptions
No.
H/D
Quantity
Unit
147.000 -
2*2
294.000 m.
nos.
Sub
Engineer
77.000
77.000 MT
S.O.R.
ITEM
Descriptions
1
2
3
1 CH-3 /
Construction of embankment with Material
3.12 / P- Obtained from Borrow Pits/Borrow Area
12
(Construction of embankment with approved
material/selected soil having C.B.R.>5 (unless
specified otherwise in the contract) obtained
from borrow pits with all lifts and leads,
transporting to site, spreading, grading to
required slope and compacting to meet
requirement of table 300-2)
on
Quantity
Unit
Rate
Amount
7531.278
cum.
223.00
1679475.00
614.250
cum.
460.00
282555.00
1036.875
cum.
1434.00
Total
1486879.00
3448909.00
2047.500
sqm
64.00
131040.00
2 CH-4 /
Granular Sub-base as per Table:- 400-1
4.1/ P-15
Construction
of
granular
sub-base
by
providing graded Material, , carriage of mixed
Material to work site, spreading in uniform
layers with motor grader on prepared surface
watering, rolling and compacting with
vibratory power roller at OMC to achieve the
desired density, complete as per clause 401
S.
n
o.
S.O.R.
ITEM
6 CH-5 /
5.3 (ii)/
P-21 19
Descriptions
Quantity
Unit
Rate
Amount
3
(ii) Granular surfaces treated with primes @
0.30 kg /Sqm
2047.500
sqm
17.00
34808.00
102.375
cum.
6255.00
640356.00
51.188
cum.
8468.000
433456.00
Total
1239660.00
2173183.00
B
(iii)
900.615
cum.
2413.000
450.307
cum.
2079.000
Total
Total
Sub
Engineer
936189.00
3109372.00
7797941.00
Executive Engineer
P.W.D. Bridge Const. Division
Raipur (C.G.)
S.O.R.
ITEM
Descriptions
CH-3 /
3.12 / P12
CH-4 /
4.1/ P15
No.
on
H/D
Sheet attached
2
CH-4 /
4.10/ P20
CH-5 /
5.1/ P19
7531.278
Cum
312.750
301.500
614.250
cum.
cum.
139.000
134.000
7.500
7.500
0.300
0.300
Total
1
1
224.000
329.000
7.500
7.500
0.250
0.250
Total
1
1
139.000
134.000
7.500
7.500
Unit
Patewa side
Darra side
3
Quantity
420.000
616.875 cum.
1036.875 cum.
1042.500
1005.000 cum.
Total 2047.500 cum.
s
no
.
5
S.O.R.
ITEM
Descriptions
CH-5 /
5.2 (ii)/
P-19
No.
H/D
Quantity
Unit
1
1
139.000
134.000
7.500
7.500
1
1
139.000
134.000
7.500
7.500
0.050
0.050
Total
52.125
50.250
102.375
cum.
cum.
1
1
139.000
134.000
7.500
7.500
0.025
0.025
Total
26.063
25.125
51.188
cum.
cum.
CH-5 /
5.3 (ii)/
P-21 19
B(ii)
CH-5 /
5.20 A
(iii)/ P-24
B
(iii)
CH-9 /
9.11/ P40
1042.500
1005.000 cum.
Total 2047.500 cum.
cum.
s
no
.
S.O.R.
ITEM
Descriptions
Quantity as per enclosed sheed
CH-9 /
9.12/ P40
No.
H/D
Quantity
Unit
900.615
cum.
450.307
cum.
Sub
Engineer
1
1
S.O.R.
ITEM
2
3
CH-2 / Excavation for Structures Earth
2.1 work in excavation of foundation of
/ P-13 structures as per drawing and
technical specification, including
setting out,
construction of
shoring and bracing, removal of
stumps and other deleterious
matter,
dressing of sides and
bottom
and
backfilling
with
approved
material
including
dewatering etc. complete.
A
2
Descriptions
(i)
CH-2 /
2.6
/ P-14
Quantit
y
4
Rate
5
Ordinary soil
763.200 cum.
Upto 3 m depth
Plain/Reinforced cement concrete
in open foundation complete as
per
drawing
and
technical
specifications
(i)
512.775 cum.
146.000
4613.000
Total
Sub
Engineer
Executive Engineer
P.W.D. Bridge Const. Division
Raipur (C.G.)
s Sarar Nalla
ad..
Amount
7
111427.00
2365431.00
2476858.00
ve Engineer
ge Const. Division
pur (C.G.)
on
H/D
Quantity
Unit
135.00
1.20
1.20
388.80
cum
130.00
1.20
1.20
Total
374.40
763.20
cum
cum
135.00
1.20
0.30
97.20
135.00
0.450
1.35
164.03
130.00
1.20
0.30
93.60
130.00
0.450
1.35
157.95
Ordinary soil
(i)
Upto 3 m depth
Patewa Side i/c Circular portion
119.00 m + 16.00 =135.00
Darra Side i/c Circular portion
114.00 m + 16.00 =130.00
Total
Sub Engineer
512.78
cum
Name of work- Construction of H.L. Bridge across Sarar Nalla on Darra -Patewa Road.
(A) Patewa side
Chainage
Ground
level
Formation
level
Depth/
Height
Topwidth
Bottom
width
Av.Width
Area
81.00
100.230
104.425
4.195
10.000
26.780
18.390
77.146
90.00
100.00
120.00
140.00
160.00
180.00
200.00
220.00
100.205
100.180
100.030
100.880
101.080
101.380
101.500
102.000
104.425
104.239
103.867
103.495
103.123
102.751
102.379
102.000
4.220
4.059
3.837
2.615
2.043
1.371
0.879
0.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
26.880
26.236
25.348
20.460
18.172
15.484
13.516
10.000
18.440
18.118
17.674
15.230
14.086
12.742
11.758
10.000
77.817
73.541
67.815
39.826
28.778
17.469
10.335
0.000
1)
conical portion
Deduct crust
Deduct concrete block
Deduct filter media
Av. Area
-77.481
75.679
70.678
56.684
34.302
23.123
13.902
5.168
Length
Quantity
-9.000
10.000
20.000
20.000
20.000
20.000
20.000
20.000
TOTAL
697.333
756.789
1413.561
1133.674
686.041
462.470
278.046
103.353
5531.266
2x3.14x(7.2)2x4.195
4
139.000
7.500
341.426
0.625
(-)
attached sheet
attached sheet
(-)
(-)
Net Quantity
Sub Engineer
M3
M3
651.563
496.762
248.381
4475.987
M3
Name of work- Construction of H.L. Bridge across Sarar Nalla on Darra -Patewa Road.
(B) Darra side
Chainage
Ground
level
Formation
level
Depth/
Height
Topwidth
Bottom
width
Av.Width
Area
66.00
99.530
104.425
4.895
10.000
29.580
19.790
96.872
75.00
80.00
100.00
120.00
140.00
160.00
180.00
200.00
100.880
100.930
101.100
101.200
101.430
101.610
101.800
102.000
104.425
104.328
103.940
103.552
103.164
102.776
102.388
102.000
3.545
3.398
2.840
2.352
1.734
1.166
0.588
0.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
24.180
23.592
21.360
19.408
16.936
14.664
12.352
10.000
17.090
16.796
15.680
14.704
13.468
12.332
11.176
10.000
60.584
57.073
44.531
34.584
23.354
14.379
6.571
0.000
1)
portion
Av. Area
-78.728
58.828
50.802
39.558
28.969
18.866
10.475
3.286
Length
Quantity
-9.000
5.000
20.000
20.000
20.000
20.000
20.000
20.000
TOTAL
708.552
294.142
1016.040
791.150
579.373
377.326
209.506
65.715
4041.805
2x3.14x(9.85) x4.925
4
Deduct crust
329.000
5.500
750.202
0.625
(-)
1130.938
403.853
attached sheet
(-)
attached sheet
(-)
TOTAL
TOTAL (A+B)
Sub Engineer
M3
201.926
3055.291
7531.278
M3
Name of work- Construction of H.L. Bridge across Sarar Nalla on Darra -Patewa Road.
(A) Patewa side
Chainage
81.00
90.00
100.00
120.00
140.00
160.00
180.00
200.00
220.00
Ground Formation
level
level
100.230
104.425
100.205
104.425
100.180
104.239
100.030
103.867
100.880
103.495
101.080
103.123
101.380
102.751
101.500
102.379
102.000
102.000
Depth
4.195
4.220
4.059
3.837
2.615
2.043
1.371
0.879
0.000
Av. Depth
0.000
4.208
4.139
3.948
3.226
2.329
1.707
1.125
0.440
Sxd
0.000
8.415
8.279
7.896
6.452
4.658
3.414
2.250
0.879
Sub Engineer
=
=
slant
Length
Height
0.000
0.000
9.408
9.000
9.256
10.000
8.828
20.000
7.214
20.000
5.208
20.000
3.817
20.000
2.516
20.000
0.983
20.000
Total Area
side
Area
0
2
2
2
2
2
2
2
2
2X1/4X3.14X9.51x10.63
TOTAL AREA
2207.679 x 0.300
2207.679 x 0.150
0.000
169.349
185.124
353.120
288.542
208.312
152.679
100.623
39.310
1497.059
158.814
1655.873
496.762
248.381
Unit
--
Sq.m.
Sq.m.
Cu.m
Cu.m
Name of work- Construction of H.L. Bridge across Sarar Nalla on Darra -Patewa Road.
(B) Darra side
Chainage
66.00
75.00
80.00
100.00
120.00
140.00
160.00
180.00
200.00
Ground
level
99.530
100.880
100.930
101.100
101.200
101.430
101.610
101.800
102.000
Formation
level
104.425
104.425
104.328
103.940
103.552
103.164
102.776
102.388
102.000
Depth
Av. Depth
Sxd
4.895
3.545
3.398
2.840
2.352
1.734
1.166
0.588
0.000
0.000
4.220
3.472
3.119
2.596
2.043
1.450
0.877
0.294
0.000
8.440
6.943
6.238
5.192
4.086
2.900
1.754
0.588
Sub Engineer
=
=
=
=
slant
Length
Height
0.000
0.000
9.436
9.000
7.763
5.000
6.974
20.000
5.805
20.000
4.568
20.000
3.242
20.000
1.961
20.000
0.657
20.000
Total Area
2X1/4X3.14X11.01x4.925
side
Area
2
2
2
2
2
2
2
2
2
0.000
169.852
77.625
278.972
232.193
182.731
129.692
78.441
26.296
1175.803
TOTAL AREA
2817.967 x 0.300
2817.967 x 0.150
Quantity of Concrete block
Quantity of Filter Media
Unit
--
170.373
Sq.m.
1346.175
403.853
201.926
900.615
450.307
Sq.m.
Cu.m
Cu.m
Cu.m
Cu.m