Sei sulla pagina 1di 14

Dokument-Nr:

Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10

Repair Procedure

Germany

1 02 123-81-14-D4
Seite
Page

von
of

14

Repair of tubes to tubesheet weld at inlet side and outlet side of


Fire Tube Boiler
General
At the tube to tubesheet welds on the gas inlet and outlet side of the fire tube boiler
leakages occurred in the weld.
Grinding of surface and PT have been performed. Most likely location of pores is at
the welding end craters.
As conclusion it was decided that all welds shall be removed and rewelded acc. to this
procedure.
Repairing tools and repairing material are described in Appendix 3.
The work will be done acc. to NBIC, which will be used due to the fact that the boiler
was already in operation.
Preconditions
Tube sheet and tubes should be clean and dry. The tubes should be dried and cleaned
with compressed air.
The following tasks should be confirmed before the repair:
AI approval of repair procedure is mandatory
Tube sheet is clean and dry
All electrical equipment of boiler has connected with safety protectors.
Axial-flow fans have been installed on the inlet and outlet of the boiler and the
boiler is ventilated.
Kick-off meeting to the participants of each procedure. Work may proceed after
release from Outotec.
The required welders must have the satisfied TIG qualifications and the welding job
should be strictly done according to WPS A148Re offered by ALSTOM.

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10

Repair Procedure

Germany

1.

1 02 123-81-14-D4
Seite
Page

von
of

14

Preparation of the tube sheet for repair

Two different repair methods are applied for the repair of tube to tubesheet welds.
Para. 1 a. describes the procedure for a local area which was already repaired
whereas para 1 b. describes the repair for all other tube to tube sheet welds.
1. a. repair in the 2 areas which showed leakage during hydrotest on
9.9.11

Both of the leaking tubes shall be cut for testing purposes. Detailed cutting
procedure still has to be agreed on. For repair please refer to 1 02 123-81-13D4-01.

Sketch 1: repaired area acc to procedure 1021213-81-13-D4

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10

1 02 123-81-14-D4

Repair Procedure

Germany

Seite
Page

von
of

14

1. b. check and repair of all other welding seams


-

Repair of tube sheet welds will be performed in clusters of 9 tubes each.

Distance between clusters are maximized. The minimum distance between 2


clusters is 5 x tube pitch (see sketch 2 and 3)

As maximum 4 clusters at one time will be ground and rewelded

Remove inner layer of refractory at a length of 500 mm if needed for working


space of milling machine

Cut and remove Pos. no. 51 on drawing 102123-33-11-Z0-01

Grind back the tube projection to 4,5 mm for tubes 60,3 x4,5 mm

Grind back the tube projection to 6 mm for tubes 101,6 x 8 mm mm

Grind back the total weld by using milling machine. Cutting tool should be used
to prepare the original J-groove acc. drawing no. 05685 (Fire tube boiler
details 1).

After removing of welds 100% VT and 100% PT inspection should be done at the
machined area

Welding of tube to tube sheet acc. drawing no 05685 and WPS A148Re.

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10
Germany

Sketch 2: Repair - Clusters

Repair Procedure

1 02 123-81-14-D4
Seite
Page

von
of

14

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10
Germany

Sketch 3: Repair - Clusters

Repair Procedure

1 02 123-81-14-D4
Seite
Page

von
of

14

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10

Repair Procedure

Germany

1 02 123-81-14-D4
Seite
Page

von
of

2. Welding and Testing

Preheating of a min. surface of 250 mm around the repair place at a


temperature of min. 150 C 220 C

Root pass welding acc. to WPS A148Re


-

Testing: 10% PT, 100% VT of root pass (only for the first 200 welds)

Build up welding acc. to WPS A148Re


-

Maximum interpass temperature is 232 C

Testing 100% PT, 100% VT

Referring NBIC, part 3, sect. 2 para. 2.5.3 and 2.5.3.1 the welding method
without PWHT will be applied

NOTE:

Hydrotest: After completion of all welds


after root pass testing of the first 200 welds it needs to be agreed if the
remaining welds can be welded completely without root pass testing.

3.

(deleted, see 2)

4.

Reinstallation of Pos. 51 and refractory


Reweld pos. no. 51 acc. To WPS A356

14

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10

Repair Procedure

Germany

Appendix 1 WPS and PQR for Tube to Tubesheet Welding

1 02 123-81-14-D4
Seite
Page

von
of

14

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10
Germany

Repair Procedure

1 02 123-81-14-D4
Seite
Page

von
of

14

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10
Germany

Repair Procedure

1 02 123-81-14-D4
Seite
Page

10

von
of

14

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10

Repair Procedure

Germany

Appendix 2: WPS and PQR for welding of Pos. No. 51

1 02 123-81-14-D4
Seite
Page

11

von
of

14

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10
Germany

Repair Procedure

1 02 123-81-14-D4
Seite
Page

12

von
of

14

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10
Germany

Repair Procedure

1 02 123-81-14-D4
Seite
Page

13

von
of

14

Dokument-Nr:
Document-No.:

ALSTOM Power Energy Recovery GmbH


34123 Kassel, Ellenbacher Str. 10

Repair Procedure

Germany

1 02 123-81-14-D4
Seite
Page

14

von
of

14

Appendix 3: Required Tools and Materials


Material
- TIG wire DMO IG
- CM2- IG

2,4 mm,
2,4 mm,

200 Kg
4 Kg

Tools
-

1 x rolling machine for inner 51,3 mm (not planned, just as precaution)

1 x bevelling machine for inner 51,3 mm (not planned, just as precaution)

1 x drift punch outer 60 mm, inner 51,3 mm, length400 mm (not planned,
just as precaution)

2 x milling machine (rotary speed ~ 20.000 rpm) with 8 and 6 mm adaptor

various milling cutter tree shape 8 mm

1 x hammer ~ 2.000 gr

2 x TIG welding machine with tungsten electrodes 2,4 mm

2 x argon 99,8%

various nos. of cleaner

2 x grinding machine for grinding disc 115 mm

various grinding discs 115 mm

various cutting discs 115 mm

various serrated grinder grain size 40

various grinding paper grain size medium

Potrebbero piacerti anche