Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Dimaporo failing to complywith his obligations under par. 6 of the contract andplaintiff corporation liable
for installing machineryand equipment that are basically defective andinadequate. As to who was the first
infractor in pointof time, it was not determined by the trial court.Rescission of the contract was granted but
held that
parties should bear his/its own damages, applyingarticle i 192 of the New Civil Code which provides:In
case both parties have committed abreach of the obligation, the liability of thefirst infractor should be
equitably temperedby the Courts. If it cannot be determinedwhich of the parties first violated thecontract,
the same should be deemedextinguished, and each shall bear his owndamages.From the judgment of
the Court below, Dimaporodirectly appealed to this Court imputing seven (7)assignments of errors
committed by the trial court,which may be synthesized into four (4) main issues:a) whether he was guilty
of breach of contract.b) whether he was liable to return the machineryand equipment subject matter of the
contract.c) whether he was liable to pay appellee Corporationthe amount of P19,628.93 with interest.d)
whether he was entitled to the award of damagesin his favor.Appellant Dimaporo maintained that he has
notcommitted any breach of contract, Exh. A,particularly par. 6 thereof that it was appelleeCorporation
who was guilty thereof, and points in hisappellant's brief testimonial and documentaryevidence in support
of the same. Upon the otherhand, the trial court, in its decision, makes thefollowing findings:From the
entire evidence presented, itappears that defendant had failed to complywith his obligations under
the contract, Exh.A, more particularly with the provisions of par. 6 thereof. He was unable to
furnishsufficient laborers needed to complete theoperations of the mill, food, foundationmaterials and
effective water systems (Exhs.G, G-1, I, I-1, J-1, K, R, CC, KK LL NN-1). UnderExh. MM, a daily work
progress report dulycertified correct by defendant, the hammermill and flash drier were
alreadycommercially operated on December 11,1954 (Exh. MM-3). This necessarily gives theimpression
that the installation of the millhas been completed in accordance with thecontract and the subsequent
failure of theproject is due to defendant's fault. ... Takinginto consideration defendant's failure tocomply
with this obligation, plaintiff's delayin the complete installation of the machineryand equipment seems
reasonable andunderstandable. ...
3
The foregoing is a conclusion of fact of the trialcourt. The rule is well-settled that factual findings of the
trial court, supported by substantial evidence,are generally binding on the Supreme Court. Theyare
entitled to great respect, the lower court havinghad the opportunity of weighing carefully what wastestified
to and did so without oversight or neglect.
4
Hence the rule that when a party appeals directly tothis Court, he is deemed to have waived the right
todispute any finding of fact made by the court below.
5
It is next argued for appellant Dimaporo, that thetrial court erred in ordering the return of themachinery
and equipment subject matter of thecontract to appellee corporation and maintainedthat although a
rescission of the contract is in order,he has no obligation, however, to return themachinery and
equipment, much less pay thetransportation expenses thereof to the port of Cotabato, since the
machinery and equipmentshipped by appellee corporation were neverdelivered to appellant. He
contended that byreference to the contract, Exh. A, it is clear that theobligation of the appellee did not
end with theshipment of the machinery and equipment to the allsite; it must also install the machinery
andequipment in such a manner that they wouldproduce at least 6 tons of cassava flour per 24 hoursof
operations so much so that until such machineryand equipment were installed and shown to becapable of
producing at the warranted rate, therecould be no delivery of such machinery andequipment
to appellant. This contention is in Our opinion, not sustained bythe terms of the contract or by the facts
appearingin evidence. It is true that under par. 8 of thecontract, E Exh. A, the "SELLER warrants that it
willdeliver all the machinery and equipment as agreedin par. 4, guaranteed to process at least 6 tons
of cassava flour or starch per 24-hour day operation."However in said paragraph it was also stipulatedthat
"this warranty of capacity shall be attained onlywhen properly coordinated to the necessary manuallabor
required for the purpose." And according tothe trial court, "the delay of the completion of theinstallation as
well as the incapacity of the mill toproduce the desired amount of flour/starch aswarranted by the plaintiff
under the contract areattributable to defendant's non-compliance with hisobligation to furnish
food, materials, and watersystem."Even assuming that there is some degree of plausibility in appellant's
position, still the lowercourt did not commit any error in ordering appellantto return the machinery and
equipment to appelleecorporation, for when the former, as defendant inthe lower court, filed his Answer to
the complaint of appellee corporation, he prayed for the rescission of the contract between him and the
plaintiff and formutual restitution by the parties.
6
To sustainappellant's contention that he is not liable for thereturn of machinery and equipment would
befundamentally contradicting the very notion of rescission. The first paragraph of article 1385 of theNew
Civil Code provides:
Rescission creates the obligation to returnthe things which were the object of thecontract, together with
their fruits, and theprice with its interest; consequently, it canbe carried out only when he
who demandsrescission can return whatever he may beobliged to restore.Furthermore, when a contract
is resolved orrescinded, it is the duty of the court to require theparties to surrender that which they have
severallyreceived and to place each as far as practicable inhis original situation; and when a resolution
isgranted, it has the effect of abrogating the contractin all parts. The party seeking resolution cannot
ask"performance as to part and resolution as toremainder.
7
The last two issues are both centered on thequestion of who is liable for the payment of damages and
interests as a result of the breach of contract. The trial court, in resolving the issues,applied Article 1192
of the New Civil Code, which asaforestated, enunciated the rule if both partiescommitted a breach of
obligation. The trial courtfind the following facts: "Both parties have failed tocomply with what
is respectively encumbent uponthem to do, and the object of the contract isconsequently defeated;
defendant failed to complywith his obligations under the contract, Exh. A; thatfurther scrutiny of the
evidence shows that themachinery and equipment sold and installed byplaintiff were all along,
by themselves, defectiveand inadequate. As to who was the first infractor inpoint of time, under said
circumstances, cannot bespecifically delineated. Hence, parties should bearhis/its own damages.Based
on these findings, the trial court ruled, asaforestated in the dispositive portion, that appellantDimaporo
must pay appellee corporation the totalamount of P19,628.93 which the latter had spent byway of
advances to the former with which topurchase the necessary materials and supplies atthe rate of 6% per
annum; that appellee corporationmust return to appellant the amount of P15,750.00representing the
partial payment made by it toappellant for the purchase price of said machineryand equipment. The trial
court, however, made nopronouncement as to damages and costs.But appellant would contend that the
amount of P19,628.93 should be offset by the damages thatare due to him by reason of the violations by
theappellee corporation of its obligation under thecontract; that appellee must be required to payinterests
on the amount of P15,750.00 since thisamount paid has already been used by it; and thatsince the first
infractor was the appellee'scorporation, therefore, damages should be paid bythat party to the
appellant. The findings of fact of the trial court that bothappellant Dimaporo and appellee
corporation havecommitted a breach of obligation are fully supportedby the evidence on record. As We
have stated, Weare not in a position to disturb the same. Therefore,it correctly applied Article 1192 of the
New CivilCode to the effect that in case both parties havecommitted a breach of obligation and it cannot
bedetermined who was the first infractor, the contractshall be deemed extinguished and each shall
bearhis/its own damages. Consequently, the trial courtcommitted no reversible error when
it orderedappellee corporation to pay appellant the amount of P15,570.00 representing partial payment of
thepurchase price of the machinery and equipment. This is but a consequence of the decree of
rescissiongranted by the trial court. Neither did it commit anyerror when it refused to grant any interest
on theaforesaid amount of P15,570.00. This is also but aconsequence of the enunciated rule that each
partyshould bear his/its own damages. For the samereasons, We hold that although appellant is liable
topay the amount of P19,628.93 which appelleecorporation had spent by way of advances withwhich to
purchase the necessary materials andsupplies, however, he is not liable to pay interestthereon at the rate
of 6% per annum until fullpayment of the same, as held by the lower court.Otherwise, to hold so would be
in conflict with theabove-mentioned rule that each party must bearhis/its own damages.PREMISES
CONSIDERED, with the only modificationthat the sum of P19,628.93 be paid by appellantDimaporo to
appellee Grace Park Engineering, Inc.,without interest, the judgment appealed from isaffirmed in all
other respects. No pronouncement asto costs.SO ORDERED.
Teehankee (Chairman), Makasiar, Fernandez,Guerrero and Melencio-Herrera, JJ., concur