Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Industrial Operations
GROUPE DANONE
CUTE
Page 1
Rev B April 24
Introduction
CUTE aims to provide a common terminology for the definition and control of
Utilization and Efficiencies of our Lines and Factories.
Our goals for sustainable growth whilst continuing to improve margin and yields,
will not be achieved without improving the utilization and the efficiencies of our
Factories and related Capital Assets.
The definitions and indices in CUTE shall be implemented in all our factories and
the respective CBUs should use them to monitor their assets performance.
It is essential that all CBUs apply CUTE in a consistent way so that data is
comparable within our operations. Only in this way can the effectiveness of the
various Manufacturing Performance Improvement programs be seen.
CUTE will provide consistent data to be used by GROUPE DANONE Divisions in
analyzing sourcing scenarios.
This reference handbook has been agreed by the Operations Directors of the
three WWBU and the Group Operations Committee.
Prepared by:
CUTE
Luis Larracoechea
Page 2
Rev B April 24
1. Background
Within GROUPE DANONE Divisions, different factories and CBUs use different
terminology and criteria for the definition and measurement of utilization and
performance indices. CUTE specifies terms and indices for harmonized
measuring and reporting on the performance of machines, lines and WW
factories in GROUPE DANONE.
CUTE definitions are intended to ensure that any communication on aspects of
time allocation, line utilization and efficiencies means the same to everyone
involved.
- Specifies Machine Time Definitions (CUTE is meant to define machine operation,
not labour utilization) for the analysis of Packing Lines, Plant or Processes*
* The term machine is used in a very general sense, and the same analysis is applicable to
a group of machines in a line, any process or plant.
CUTE
Page 3
Rev B April 24
2. CUTE (Capacity,
C
A
Calendar Time
Unavailabl
e Time
Available time
Availabl
e
Unused
Time
Disposable Time
Planned
non
Operational
Time
Operational Time
Production Time
Net
Production
Time
NP
Routine
Productio
n
Activities
Unexpecte
d
Stoppages
Calendar Time
Calendar Time defines the maximum time within a reporting period, such as:
-
CUTE
52 weeks in a year
168 hours in a week
24 hours in a day
8760 hours in a year
Page 4
Rev B April 24
C
A
Calendar Time
Unavailabl
e Time
Available time
Available Time is the time during which the machine/line could operate within
the limits of local or industry working conventions. This means that it will
effectively be the normal working pattern of the site (although overtime must be
added to it when worked).
Unavailable Time is the time during which the machine is not normally
operated, owing to:
Bank Holidays:
- The time in which factory is planned to be closed due to bank holidays.
Other Traditional or Enforced Closures:
- Weekends not worked, if the local regulations don't allow working on Sunday and (or)
Saturday.
- Local holidays, specific to the region of the country,
- Traditional closures. For example: afternoon and night shift on Christmas Eve,
religious holidays.
- Closures enforced by Union of Workers or Local Authorities.
- Shift working restrictions
- Enforced factory shutdowns
These days are planned for the whole year during budgeting time.
Unavailable Time is effectively the time that is agreed within the CBU
management to be outside the control of the factory management. (Note that:
negotiating overtime operation could reduce it.)
CUTE
Page 5
Rev B April 24
Available time
Disposable Time
Available
Unused
Time
Disposable Time is the time during which the machine is actually used by
production and engineering, whether or not the machine is actually producing.
Available unused Time is the time in which the machine/line could be used but
production is not scheduled because there are no production orders planned
from Supply Chain. (Note that: a Machine upgrade, overhauls or other types of Planned NonOperational activities, are not considered as unavailable time.)
Calculation of Available Unused Time: The amount of time in this category cannot be
calculated directly but has to be derived from the difference between the Available Time and the
Disposable Time.
Available Unused Time = Available Time Disposable Time
Where the Disposable Time is the calculated time that would be required to
produce the actual or estimated volume of production when the machine is
operating at its Operational Efficiency plus any Planned Non-Operational Time.
CUTE
Page 6
Rev B April 24
D
O
Disposable Time
Planned
non
Operational
Time
Operational Time
CUTE
Page 7
Rev B April 24
O
P
Operational Time
Production Time
Routine
Productio
n
Activities
Production Time is the maximum time during which the machine is expected
to effectively run and deliver finished products.
Routine Production Activities is the time taken by operational activities that are
required to enable the machine to produce. These activities normally occur whilst
the machine is staffed and are included in weekly and daily production plans:
Equipment changeovers, format changes:
- Time between last previous good product to first new good product. Measured on
packing hall.
- Time for which the line was stopped due to change of production from one recipe
or shape of product to another one.
- Also time for which the line was stopped for change of packaging without
changing of recipe or shape of the product.
Start-ups and Shutdowns:
- Time lost to start or close production.
- This is the time to prepare or finish the production while the line is staffed with
regular crew.
- Normally it will be the time from beginning of the shift to the first product packed
and from the end of packing to the end of the shift.
- Start-ups and shut-downs are preceded or followed by the period of nonproduction activities fe. Factory closure, time without the orders, planned
maintenance etc.
Sanitation & Routine cleaning:
- Cleaning necessary to preserve proper hygiene of the line. It is done on regular basis
required by hygienic condition/regime of the line. Usually once per week, every other
week, after end of a block of production, but sometimes planned in the middle of a
production run.
- It is routine planned period used for manual cleaning of production line or
automatic CIP.
- Can be done by regular or reduced number of workers.
Trials with Production:
- Time lost due to trials organized by production and linked to start-up period or
change of technical equipment.
- The product that is produced during these trials is valid for sales.
Lunch or rest breaks:
- Time for which the machine/line was stopped due to staff lunch or rest break. Note
that: CUTE defines machine/line operation, not labour and as such, if a machine/line
is stopped for meals, breaks or other rest periods, the time is recorded as a Routine
Production Activity. They may be avoided by providing with relief operators.
CUTE
Page 8
Rev B April 24
Production Time
Net
Production
Time
NP
Unexpected
Stoppages
Net Production Time is the theoretical time that a machine/line should take
to produce the good output if it runs at TMP speed. It includes no allowances for
interruptions, or any other time losses. Where a machine/line is producing a
range of products, calculation of the NP for the output of each product, enables to
report an average efficiency for the mix. (NP=Weighted average for the output of
each product)
Calculation of Net Production Time: NP is not a time that can be recorded, but
it must be calculated directly from the declared production.
Net Production Time = Output Produced / TMP
Upgrades of machines/lines
Different pack sizes and formats of the same product
Special wrappers for presentations, discounts or promotions
Local improvements to the machine/line
Local restrictions due to the quality of packing materials
Technical Downtimes
Technological Downtimes
Organizational Downtimes
Time and Waste Adjustments
CUTE
Page 9
Rev B April 24
Technological Problem
- Time lost during production, which are related to process problems.
- The cause is not clearly identified and cannot be dedicated to another line in this
section.
- Wrong size of product causing stop of the line due to problems with packing.
Unexpected need for cleaning
- Short stoppages for cleaning needed to take place during Production Time. For
example:
Cleaning of milkwashing unit
Short stoppage at the end of the shift for the machine cleaning
Time for re-heating of the Chocolate Enrober
Change of packaging portion
- Short stops of machine for loading new portion of packing material. Usually
registered only when TMP of the line is governed by the output of Packing machine.
Change of reel of packing material when Packing machine is the bottleneck of
the production line.
Defective Raw or Packaging Material
- Time lost is clearly connected to inadequate quality of Raw or Packaging Material
CUTE
Page 10
Rev B April 24
Time Adjustment
This is the time that is calculated to be lost when the machine is not running at its
specified TMP and/or due to unexpected stoppages, which are too short for manual
recording.
Waste Adjustment
Is calculated by converting the weight of collected waste during the production run into
units of equivalent time. Note that: Concepts such as: Technological waste, Burnt
leftovers from wafer ovens and waste from cutting of wafer books are not to be
converted into time as they will not impact Line Output and Efficiency.
Calculation of Time Adjustment: The amount of time in this category cannot be calculated
directly but has to be derived from the difference between the Production Time and the Net
Production Time calculated from the TMP, plus all recorded Unexpected Downtimes.
Time Adjustments = P (NP+(Technical+Technological+Organizational+Waste))
CUTE
Page 11
Rev B April 24
CUTE
Page 12
Rev B April 24
This is a very severe measure of the assets use. It will primarily be of value for
inter-company benchmarks when assessing how a line is being utilized over the
long term.
3.2 EFFICIENCY INDICES
It is essential in ALL statements of machine/line efficiency to mention the TMP
used for calculation. The TMP will normally be set by the factory taking into
account local machine/line constraints and may vary with the products produced.
It will however be compared with centrally set reference speeds in case of key
pieces of normalized equipment
3.2.1 Production Efficiency (PE)
It is a measure of how effectively the machine/line has been run by the
production department during the time it was under their control and could have
run productively.
PE= Net Production Time (NP) x 100
Production Time (P)
Improvement in PE is normally tackled at the operating level in a factory by
reducing the causes of unexpected stoppages, by ensuring adequate supplies of
materials or clearance of product from the machine/line and by applying
preventive or corrective maintenance.
3.2.2 Operational Efficiency (OE)
Top of mind indicator for
Efficiency
This is the most commonly used indicator of efficiency at both the CBU and
GROUPE DANONE Division level, because it measures all the activities within
the control of a factory.
It is a measure of how efficiently the machine/line has been operated by the
production and engineering departments of a factory during the time it was
planned to run ( for example, how many and how well startups, changeovers
etc are handled).
OE= Net Production Time (NP) x 100
Operational Time (O)
Improvement in OE is normally tackled at the departmental level in an
organization. By reducing frequency and times for start-up, shut-down and
cleaning, by not stopping machines/lines for meal or other personnel breaks, by
designing machines and operations to simplify changeovers, loading and
unloading or by reducing causes of unexpected stoppages
Note that: When seeking to reduce Working Capital, it may sometimes not be
possible to increase the OE. This will happen when it is more beneficial to reduce
CUTE
Page 13
Rev B April 24
stock levels by shortening production runs, which will tend to increase the
number of changeovers and, hence, lower the OE.
3.3.1
GROUPE DANONE CBUs and Inter Company Sourcing, need realistic figures
showing what their factories can be expected to deliver in current circumstances.
Maximum Capacity (MC)
It measures the potential or maximum output that could be obtained from a
machine /line when operated at a stated efficiency over the total Calendar
Time (8760 hr) in a year.
MC= TMP x Operational Efficiency x Calendar Time
Available Capacity (AC)
It measures the output that can be expected from a machine /line when
operated at an estimated efficiency in a full year taking into account the
constraints for Unavailable Time, during which the machine/line will not
operate due to the limits of local or industry working conventions.
AC= TMP x Operational Efficiency x Available Time per year
Note that:
1. MC and AC will normally apply to a specific product mix, so that, need to
be calculated using their weighted average TMP.
2. When declaring machine/line capacity, the Operational Efficiency at
which it was calculated should always be stated (fe. Available Capacity @
80% OE)
3.3.2
Planners and schedulers need figures that are practically achievable; hence,
allowing them to make efficient use of installed capacity.
Operational Capacity (OC)
CUTE
Page 14
Rev B April 24
CUTE
Page 15
Rev B April 24
NB. The Avg. TMP for a line is calculated using Operational Time per SKU as a weight
kg/h.
CUTE
Page 16
Rev B April 24
CUTE
Page 17
Rev B April 24
CUTE
Page 18
Rev B April 24
CUTE
Page 19
Rev B April 24