Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
ON
Design of Earthquake
Resistant Structure
Submitted to:
Mr. Sahil Garg
Submitted by:
Arjun
Diksha Jindal (8014220)
Jyoti Mandhani (801423006)
Harjinder Kaur (801423004)
Level of Building
Wi
Roof
rd
3 floor
2nd floor
1st floor
Level
Roof
rd
3 floor
2nd floor
1st floor
Wi
2843.75
3062.5
3062.5
3062.5
hi (from base)
14.5
11
7.5
4
Wihi2
5,97,898
3,70,562
1,72,266
49,000
Wihi2 =
11,89,726
Wihi2/ Wihi2
0.503
0.311
0.145
0.041
Qi = VB Wihi2/ Wihi2
353.86
218.79
102.01
28.84
S.No.
1
2
3
4
5
6
7
8
9
10
11
12
13
Load Combination
1.5DL+1.5LL
1.2(DL+LL*+EQX)
1.2(DL+LL*-EQX)
1.2(DL+LL*+EQY)
1.2(DL+LL*-EQY)
1.5(DL+EQX)
1.5(DL-EQX)
1.5(DL+EQY)
1.5(DL-EQY)
0.9DL+1.5 EQX
0.9DL-1.5 EQX
0.9DL+1.5 EQY
0.9DL-1.5 EQY
DL
1.5
1.2
1.2
1.2
1.2
1.5
1.5
1.5
1.5
0.9
0.9
0.9
0.9
LL
1.5
0.25/0.5*
0.25/0.5*
0.25/0.5*
0.25/0.5*
-
Various Checks
(a) Check for Axial Stress
EQ
+1.2
-1.2
+1.2
-1.2
+1.5
-1.5
+1.5
-1.5
+1.5
-1.5
+1.5
-1.5
ck
fy
0.24 20
415
= 0.26%.
= 0.26 x 250 x 432/100
= 280.8 mm2
(Clause 6.2.1(b) of IS 13920: 1993)
Maximum reinforcement = 2.5%
= 2.5 x 250 x 432 /100
= 2700 mm2
(Clause 6.2.2 of IS 13920: 1993)
Left end
-203.123
4.35
1.425%
0.507%
Top reinforcement
Center
Right end
-90.4
1.93
3.21%
1.6%
Sagging
Moment (kNm)
Ast at bottom
Asc at top
< 1.42/2
Hence revise to 0.71%
(Clause 6.2.3; IS13920:
1993)
Bottom reinforcement
203.12
92.2
Ast required = 1500 mm2
Ast required = 1500 mm2
= 0.94%
= 3.21%
> 1.42/2 i.e. 0.71
(Clause 6.2.1(b) and 6.2.4
ok
of IS13920: 1993)
0.35/2 = 0.175 %
0.39/2 = 0.195 %
< 0.26%
< 1.47/4=0.37%
< 1.47/4=0.37%
Hence, revise to 0.37%.
Hence, revise to 0.37%
Summary of required reinforcement
Top = 1.425%
Top = = 3.21%
Bottom = 0.94%
Bottom = 3.2%
Mu = 203.123 kN-m
M
203.12 106
bd 2
250 432 432
= 4.35
Referring to Table-50 of SP: 16,
For d/d = 68 / 432 = 0.15, we get
90.4
Ast required = 1500
mm2
= 3.21%
ok
0.8/2 = 0.4%
> 0.26%
> 1.47/4=0.37% ok
Top = 3.21%
Bottom = 3.21%
= 1,583 mm or 4,000 mm
= 1,583 mm (lowest of the above)
(Clause 23.1.2 of IS 456: 2000)
Substituting the values and solving the quadratic equation, we get
Ast at bottom = 1,500mm2 > 415 mm2
< 3,990 mm2
It is necessary to check the design assumptions before finalizing the reinforcement.
xu = 0.87fyAst / 0.36fckbf
= (0.874151500) / (0.36 20 1583)
= 48.93 mm
< df
ok
Details of Reinforcement
Table 05 shows summary of reinforcement provided at left end, at centre, and at right end of
the beam AB.
A total of 3-16 straight bars each are provided throughout the length of the beam at both top
and bottom. 5-20+1-16 extra at top (i.e., a total of 1.487 %) and 3-20 extra at bottom (i.e., a
total of 0.97%) are provided at the left end. At the right end, i.e., over the central support, 5-20
+ 1-16 extra at top (i.e. a total of 1.487%) and 1-20 + 2-16 extra at bottom (i.e. a total of
0.83%) bars are provided.
In an external joint, both the top and bottom bars of the beam shall be provided with an
anchorage length beyond the inner face of the column equal to the development length in tension
+ 10 times bar diameter minus the allowance for 90 degree bend (Clause 6.2.5 of IS 13920:1993)
as shown in Fig 03.
Table 05 Summary of reinforcement for beam AB
Beam AB
Top Reinforcement
Bottom
Reinforcement
Longitudinal Reinforcement
Left end
Center
Right end
3-16 straight + 53-16 straight Steel
3-16 straight + 520 +1-16 extra
Provided = 603 mm2
20 +1- 16 extra
Steel Provided =
i.e. 0.378%
Steel Provided =
2,374 mm i.e. 1.487%
2,374 mm2 i.e.
1.487%
3-16 straight + 33-16 straight Steel
3-16 straight + (220 extra Steel
Provided = 603 mm2
16+1-20) extra
2
Provided = 1,545 mm
i.e. 0.378%
Steel Provided =1,319
i.e. 0.97%
mm i.e. 0.83%
In this case, for Fe415 steel and M20 grade concrete, from Table 65 of SP: 16,
ld = 47 + 10 - 8 = 49
= 980 mm for 20 bar
= 784 mm for 16 bar
1.4(M u As + M u Bh )
L
Vswaytoleft =
As
Bh
1.2(DL + LL) 1.4(M u + M u )
2
L
1.2 x (103 + 36) /2 - 186
103 kN
Ah
Bs
1.2(DL+ LL) 1.4(M u + M u )
+
2
L
1.2 x (103 + 36) /2 + 175
259 kN
Vu,b =
Ah
Bs
1.2(DL + LL) 1.4(M u + M u )
2
L
1.2 x (103 +36) /2 - 175
92 kN
Vu,b =
Figure shows the shear force diagram for the beam considering plastic hinge formation at ends.
As per Clause 6.3.3 of IS 13920:1993, the design shear force to be resisted shall be the
maximum of:
i) Calculated factored shear forces as per analysis
ii) Shear forces due to formation of plastic hinges at both ends of the beam plus factored gravity
load on the span (as calculated above)
Hence, design shear force (Vu) will be 259 kN (maximum of 195 kN from analysis and 259 kN
corresponding to hinge formation) for left end of the beam and 270 kN (maximum of 207 kN and
270 kN) for the right end.
From analysis, the shear at the mid-span of the beam is 125 kN. However, shear due to
formulation of plastic hinges at both the ends of the beams has been calculated as 186 kN and
175 kN. Hence, the design shear at centre of the span is taken as 186 kN.
The required capacity of shear reinforcement at the left end of the beam is:
Vus = Vu Vc
= 259-114
= 145 kN
Similarly the, required capacity of shear reinforcement at the right end and at mid-span is 156
and 117 kN, respectively.
Referring to Table 62 of SP:16, we get the required spacing of 2 legged 8 stirrups as 145 mm,
165 mm and 135 mm respectively at left end, centre and right end.
As per Clause 6.3.5 of IS 13920:1993, the spacing of stirrups in the mid-span shall not exceed
d/2 = 532/2 = 266 mm.
Minimum shear reinforcement as per Clause 26.5.1.6 of IS 456:2000 is given by:
Sv = Asv x 0.87 fy /(0.4 b)
= 2 x 50 x 0.87 x 415 / (300 x 0.4)
= 300 mm.
Spacing of links over a length of 2d at either end of beam as per Clause 6.3.5 of IS13920: 1993
shall be the least of:
i) d/4 = 532 /4 = 133 mm
ii) 8 times diameter of smallest bar
= 8 x 16 = 128 mm
However, it need not be less than 100 mm.
Hence, provide 2 Legged - 8 stirrups @125mm c/c at left and at right end over a length of 2d =
2 x 532 = 1,064 mm.
Elsewhere, provide stirrups at 165 mm centers.
In case of splicing of reinforcement, the spacing of links shall be limited to 150 mm centers as
per clause 6.2.6 of IS 13920:1993.
The reinforcement detailing is shown in Fig 04.
Design Checks
(a) Check for Axial Stress
Factored axial force = 850 kN
(Lowest at At or Bb among all load combination is considered)
Factored axial stress = 850,000 /500 x 500 =3.40 MPa
Hence, for the load combination 0.9DL + 1.5 EQY, the member needs to be checked as flexural
member. For all other load combinations design is done as a Column member.
(Clause 7.1.1; IS 13920:1993)
(b) Check for Member Size
Width of column, B = 500 mm 300 hence, ok.
13920:1993)
(Clause 7.1.2; IS
Span, L = 3,500 mm
The effective length of column can be calculated using Annex E of IS 456: 2000. In this example
as per Table 28 of IS 456: 2000, the effective length is taken as 0.85 times the unsupported
length, which is in between that of fixed and hinged case.
L = (3500 500) 0.85
D
500
Hence, ok.
Design of Column
(a) Sample Calculation for Column Reinforcement at AB End
First approximate design is done and finally it is checked for all force combinations.
(i) Approximate Design
In this case, the moment about one axis dominates and hence, the column is designed as an
uniaxially loaded column in that direction.
The column is oriented in such a way that depth of column is 500 mm for X direction earthquake
and 500 mm for Y direction earthquake force.
Design for Earthquake in X-Direction
Pu = 850 kN , Mu2 = 84.89 kN-m
P
3
850 10
fck bD = 20 500 500
u
u2
= 0.17
84.9 106
5000 mm2
Provide 12-25 bars with total Asc = 5,892 mm2 i.e., 5,892 x 100 / (500 x 500) = 2.35%.
Pu
For
f ck bD
Mu
fck bD 2
Mu,2,1 = 0.2 20 500 500 500 /(1106 )
= 500 kN-m
Mu,3,1 = 0.2 20 500 500 500 /(1106 )
= 500 kN-m
Puz = 0.45 fckAg + (0.75fy - 0.45fck) Asc
= 0.45 x 20 x 500 x 500 +
u3 n
162
1.216
20.8 1.216
u 2,1
180
u3,1
= 0.88 + 0.039
= 0.92 < 1.00
300
Hence o.k.
3Pu
A f
g ck
Fig 07: Column shear due to plastic hinge formation in transverse beams
br
Vu = 1.4 (M u )
h
st
= 1.4(377)/3.5 = 189 kN
(d) Design Shear
The design shear force for the column shall be the higher of the calculated factored shear force as
per analysis and the shear force due to plastic hinge formation in either of the transverse or
longitudinal beams.
(Clause7.3.4; IS 13920: 1993)
From Section (c) above, the design shear in X direction is 195 kN which is the higher of 112 kN
and 195 kN. Similarly the design shear in Y direction is 176 kN, which is the higher of 123 kN
and 176 kN.
1,05,600
300 / 4 = 75 mm
But need not be less than 75 mm nor more than 100 mm.
(Clause 7.4.6 of IS 13920: 1993).
Provide 10 confining links @ 75 c/c for a distance Lo (Refer figure 4.5), which shall not be less
than:
a) Larger lateral dimension = 500 mm
b) 1/6 of clear span = (3,500 500)/6 = 467 mm c. 450 mm
(Clause 7.4.1 of IS 13920: 1993).
Provide confining reinforcement for a distance of Lo = 500 mm on either side of the joint. (Refer
Fig 08)