Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
DE DAVIES
Section Manager
TauTona Mine, AngloGold Ashanti South African Operations
SYNOPSIS
The paper describes the extraction of reef adjacent to geological structures in the
Carbon Leader Reef Section at TauTona Mine. Traditionally long wall mining
has left feasible and economical blocks of ground adjacent to structures when
negotiating major geological features. This meant that mining through an upthrow fault, rolling to the reef elevation on the displaced side of the fault left reef
in the long wall. High grade areas were abandoned and gold was sterilized.
In these tight economic times and with the need to continuously improve safety
standards the need arose to develop a technique to extract these blocks
economically and safely. It was believed that the structures in these abandoned
areas were de-stressed and could now be mined in small volumes at a high
grade.
The term RATS is an acronym derived from reef adjacent to structures and
aptly describes the process of identifying and extracting these blocks. The
viability of this method was addressed in terms of the mine design, underground
investigations and financial risks.
The paper concludes with an analysis of the successes achieved to date.
INTRODUCTION
TauTona Mine is one of the AngloGold Ashanti Southern Africa operations. It is
close to the town of Carletonville in the province of Gauteng and about 70km
south-west of Johannesburg. TauTona is 46 years old and employs 4 000
people. Mining operations are conducted at depths ranging from 1,800m to
3,500m at which the worlds deepest stoping sections are found.
TauTona
Savuka
Mponeng
Ergo
Western Ultra
Deep Levels
Tau Lekoa
Kopanang
Moab Khotsong
Great Noligwa
Safety is our first value: We place people first and correspondingly put
the highest priority on safe and healthy practices and systems of work.
We are responsible for seeking out new and innovative ways to ensure
that our workplaces are free of occupational injury and illness. We live
each day for each other and use our collective commitment, talents,
resources and systems to deliver on our most important commitment to
care.
Our objective is to mine gold safely at the correct profit margin. We are a team
that produces gold by believing that the workplace can be injury free. We are
achieving our targets through people, we want to maximise TauTonas
contribution to AGA shareholders by exploring and managing life of mine
extension opportunities and striving for continual improvement. As depicted in the
following graph, safety statistics for the RATS operations from 2005 to 2008
proofs that mining reef adjacent to structures at depth was done safely.
Injury Statistics for RATS 2005 - 2008
5
4
Dressing Cases
Loss Time Injuries
Serious Injuries
Fatalities
3
2
1
0
2005
2006
2007
2008
At TauTona Mine gold production declined from 2005 to 2008 by 27% to 9 332kg,
owing to a greater-than-scheduled decrease in volumes of ore mined. This was
a result of increased seismic activity in the vicinity of the CLR shaft pillar which is
being mined. Both face length and face advance were negatively affected by
seismicity during 2008. (AngloGold Ashantis Report to Society, 2008, South
Africa: Johannesburg.)
At TauTona Mine we believe in continuous improvement and therefore it is of
utmost importance to review all our current processes, to find ways to make it
even more effective and value creating.
The concern we have is that TauTona mine traditionally used the longwall mining
method. Our gold production has decreased and a need to create additional face
length arose in order to create flexibility. Because of increased seismicity, we had
to change our mining strategy. To remain sustainable we decided to develop a
method of extracting gold from the reef adjacent to structures without interfering
with the current operations, thus enhancing our gold profile.
4
Reef band
Fa
ult
RATS
OOOOOOOOOOOOOOOOOOOOOOOOOOOOOO
Reef band
Figure 5: Sketch indicating reef displaced between 5 and 10 metres leaving reef adjacent
to structures
METHODOLOGY
Support design:
The support design was based on the Fall of Ground Management Process
(FOGM) with specific reference to mine wide design guidelines FOGM 1 and
the Local area design guidelines FOGM 2. FOGM 1 is aimed at the prevention
of rock burst and FOGM 2 is aimed at the prevention of rock bursts and fall of
ground.
FOGM 1: Mine wide design guidelines used
Both modelling and seismic trends must indicate that the planned RATS
mining are sufficiently removed from current working places not to have
any interaction.
No mining into the stressed abutments at the top or bottom of a long wall
including pillars.
All access ways must be positioned under mined out ground where no
stress changes will occur due to the new mining activity.
In order not to mine into existing excavations all stoping and development
must be clearly indicated and avoided.
To leave crush pillars against major faults.
To consider preconditioning of prominent dykes.
Design considerations
We assumed that shallow mining conditions would prevail as the area had been
de-stressed with the original mining. Due to the regeneration of stress in the
back areas, the stress would now be zero. Careful modelling shed some light on
the expected stress conditions. The initial elastic modelling indicated stresses of
approximately 7 MPa. It was thus assumed that the back area stress would be
between 0 MPa and 10 MPa.
Stope closure is a combination of elastic convergence and in-elastic bed
separation especially in the hanging wall. This bed separation is at maximum
close to the stope face and decreases in magnitude further away (into the
hanging wall). It was unknown how much of this bed separation would be visible
and what affect it would have on the planned mining.
Ideally, the support installed must prevent the first bed from falling, thereby
supporting the additional layers in the hanging wall. The first layer is however
unknown, but drilling support into the hanging wall will improve the integrity of the
initial support system design. If drilling is impossible, the support design may
have to be adjusted as soon as the stoping has commenced and new information
becomes available.
Low closure rates were expected, thus stiff active support had to be designed.
Because the expected closure rates could not be determined, yielding support
was considered. Low seismic rates were probable, but close to abutments the
seismic risks increased.
The possibility of back break conditions on large spans could not be disregarded.
As proven by the platinum mines breaker lines of packs were often used to
prevent back break from forming up to the face area. With packs on the gullies
and limited panel spans, these breaker lines would not be required.
Support design
The standard approach is to use the accident statistics for the applicable
geotechnical settings at the mine for the past 5 years to determine the fallout
thickness to be supported. From this the support resistance and energy
absorption criteria can be calculated. The support standard is then designed to
meet these criteria.
In this case the accident statistics is not applicable as the geotechnical setting is
totally different. There are no accident statistics available for this geotechnical
setting on TauTona.
With so many unknowns and a new geotechnical setting, a different approach
to support design was required. Without accident statistics the next option was
to try and pre-determine a likely fallout thickness. The most likely fallout
thickness is up to the first well defined bedding plane consisting of quartzite.
The bottom contact between the Greenbar and the quartzite has practically no
cohesion and can be assumed to determine a likely thickness (2m above the reef
contact). This relates to a support resistance criterion of 53 kN. The next
bedding plane is the top contact of the Greenbar, a further 2m above the bottom
contact, relating to a support resistance criterion of 106 kN.
The current support standard of elongates (Profile props) spaced 1m by 1,6m
gives a support resistance capability of 125 kN and can therefore support at least
up to the top contact of the Greenbar.
On a larger scale, including the packs in the equation and assuming 20 metre
long panels, the same support standard gives a support resistance capability of
200 kN and can support up to 7,5 metres of dead weight (wedge).
Fallout thickness: Maximum of
3.5 metres?
Reef left behind
2m
2m
Fault
Greenbar
Quartzite Beam
<5m
In-stope pillars against
the major fault
5m
2m
2m
After considering all the above and careful modelling the following support design
was established:
2m max
Dip
1.5m max
3.0m max
7m max
4.5m max
1.6m
1.0m
1.8m
1.6m
Legend:
Pre-stressed pack (75cm x 150 cm)
Pre-stressed Profileprop (180mm)
Splitset (1.5m)
Camloc prop
Figure 9: Support standard for RATS mining (face length less than 20m)
2m max
Dip
1.5m max
6m max
3.0m max
7m max
4.5m max
1.6m
1.0m
1.8m
1.6m
Legend:
Pre-stressed pack (75cm x 150 cm)
Pre-stressed Profile prop (180mm)
Splitset (1.5m)
Camloc prop
Figure 10: Support standard for RATS mining (face length in excess of 20m)
10
Financial Risks:
Blocks were identified and prioritized according to the set criteria for inclusion in
the Business Unit Plan. The reef adjacent to structures was identified by the
Mineral Resources Department and each one was allocated with a specific block
number. These blocks were prioritized according to their volume and grade, their
current infrastructure utilisation and their proximity to current working places. A
multi disciplinary risk assessment followed after a financial evaluation was done.
Feasible
Blocks
X
XX
X
Not Feasible
11
Greenfield
BME
x
=
x
=
x
x RD =
+
+
=
+/=
+/=
+/=
x
x
=
Plan
FACE LENGTH
FACE ADVANCE
TOTAL m2
ON REEF PERCENTAGE
REEF m2
ON REEF cmg/t
kg GOLD EX STOPES
VAMPING kg
REEF DEVELOPMENT kg
TOTAL kg BROKEN
U/G INVENTORY
GOLD HOISTED
SURFACE INVENTORY (SHAFT)
GOLD DELIVERED TO PLANT
PLANT INVENTORY
GOLD CALLED FOR
MINE CALL FACTOR
RECOVERY FACTO
GOLD RECOVERED
12
m
m
m
%
m
cmg/t
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
%
%
Kg
1 300
4.50
29 497
50.80%
14 984
3 481
1 413.517
0
0
1 413.517
0
1 413.517
0
1 413.517
0
1 413.517
74.00%
97.57%
1 020.585
cm
cm
t
t
g/t
R3 481
100.0
40 607
40 607
25.1
The next step was to determine whether these blocks would be financially viable
to mine. Due to the mining risk this model allowed us to use variable parameter
values to determine feasibility. Firstly the total incline square meters were used.
A 50% discount was added to establish the available square meters to be mined.
This allowed us to group blocks together according to accessibility and locality.
Tonnages and contents of these blocks were calculated.
Stoping and
development costs were determined by using rand/m and rand/m cost. This
variable model allowed us to use different units: gold price, rand/m, or rand/m to
determine profits or losses in the different blocks or group of blocks.
The initial financial evaluation indicated that these blocks would be feasible to
mine and could be extracted at a profit, thus enhancing the current gold profile.
PILLAR NO
SECTION 7 - FINRISK
0.0271
FINAL
DATE
% M
MINED
% M
FLTING
DEVELOPMENT SHEET
LINE
LEVEL
PANELS
STOPE SHEET
MCF
%
Plant REC.
%
GOLD PRICE
R / Kg.
85.03
97.57
80,000
FINAL
BLOCK No.
ALL
STOPING TO BE DONE
CW
INCLINED M
BLOCK No.
BLOCK
26
28
36
70
100%
13027
4290
40875
11855
60%
7816
2574
24525
7113
0%
7816
2574
24525
7113
TOTAL
70047
42028
23.0
42028
SW Full Width
SW
(MRIS)
% GROUNDGROUND
AVAILABLE
AVAILABLE - FLT DISCOUNT
cm.
100
100
100
100
cm.
23.0
23.0
23.0
23.0
VALUE
(MRIS)
cm.g/t
3333
3829
4205
4421
REEF DIP
22.5
22.5
22.5
22.5
GRADE
g/m
90.32
103.77
113.96
119.81
4056
22.5
109.93
100.0
100.0
H
3.4
3.4
3.2
3.0
1.2
2.4
W
3.0
3.0
3.0
1.8
2.4
3.0
SG
2.78
2.78
2.78
2.78
2.78
2.78
TONS
851
0
2802
6755
961
0
11369
0
#DIV/0!
CONTENTS
Kilograms Au
706
267
2795
852
113896
113896
R/m *Dev
7500
Plant REC.
%
Total REC.
%
R / Kg.
85.03
97.57
82.96
80,000
4620
7500
7500
7500
*Standard VR
16.13
COST
225000
0
787500
3375000
900000
0
R/ton
M2
COST (R/M2
264
42028
2094
5,287,500
465
REVENUE
88,007,051
R/rec.gm.
281
500
COSTS
937
STOPING COSTS
DEVELOPMENT COSTS
TREATMENT COSTS
AVG Tons / M
R/rec.gm.
PROFIT / LOSS
STOPING,
DEVELOPMENT,
TOTAL ENGINEERING
FLAT RE-EQUIPPING,
DIAMOND DRILLING
DIRECT COST
UNIT COST
TOT.STOPE TREAT.
0
0
0
TOT.DEV. TREAT.
0
0
TOTAL TREATMENT
0
0
TONS
(R/ton)
(R/ton)
(Rand)
113896
6755
(R/ton)
(Metres)
AS PER
NOW
IN 6
MTHS
IN 12
MTHS
IN 18
MTHS
Date :
m./mth.:
No.:
m.:
m / mth.:
m.:
Mths.:
13
R/rec.gm.
Profit/Revenue %
TOT.DEV. COST
IN 24
MTHS
3rd
YEAR
3,832.965
306,637,216
FINANCIALS
Item
COST
GOLD PRICE
MCF
%
STOPING COSTS
DEVELOPMENT COSTS
METRES
WORKING PLACE
30
HLGE
RAW / CON.X/C
105
CROSSCUT
450
RAISE + SLUSHER
120
BOXHOLE
TRAVELLINGWAY
705
TOTAL
PLANNED DEV.RATE; m / mth
ESTIMATED TIME TO COMPLETION: mths
FACTORS
STOPE STATS
TONS
ORE
21182
6976
66463
19276
4th
YEAR
IN RANDS
306,637,216
80.00
88,007,051
5,287,500
0
0
93,294,551
24
213,342,665
55.7
69.57
IMPLEMENTATION
PILLAR INVESTIGATION PROCESS:
In the implementation process certain steps are critical to ensure all possible
constraints are addressed prior to allocation of resources. A flow sheet as
described in appendix 1 was used to ensure involvement of all the role players.
See Appendix 1 for process flow sheet, section 1 to 10, were detailed and signed
off plans was used for inclusion into the mining schedule.
14
Reef adjacent to structures blocks were identified by using the volume, grade
and kilograms allocated to the blocks. This was determined by using Krige
values.
4 839m @ 3 804cmgt
498.895kg
1 454m @ 2 964cmgt
116.791kg
610m @ 2822cmgt
40.882kg
2 354m @ 4 167cmgt
265.753kg
10 583m @ 3 648cmgt
913.691kg
15
PROCESS:
From the pillar investigation process all relevant information was used to
determine and prioritize blocks according to their volume and grade, their current
infrastructure utilisation and their proximity to current working places. A multi
disciplinary risk assessment was conducted and the blocks were scheduled in
terms of availability, equipping and resource requirements.
For the initial blocks identified no development was required to access the
blocks. Resources were allocated in terms of equipment (winches, locos,
loaders, switches, rails, box fronts, miscellaneous stores) and labour. The 111
employees allocated to the project included stoping, equipping, horizontal
transport, haulage maintenance and supervision labour. The implementation of
this mining method commenced with four crews doing the equipping, ventilation,
support and establishment of the blocks. Each crew consisted of a Stope Team
Leader, Miners Assistant, four Rock Drill Operators - Stope and four Stope Multi
Task Crew members.
A crew movement and section build-up schedule was drawn up and
implemented. Stoping of the reef adjacent to structures commenced in June
2005.
Due to the fact that the throw of the faults determined the face length short
panels were designed with a face length between 10 and 20 metres. Most of
these structures generally strike North East. The reef at TauTona Mine dips from
North to South at 22 degrees and strikes from East to West. Current box holes
were used as the initial attacking point. A diagonal wide gully was mined in a
western direction through the old stope until reef was intersected and continued
up to the fault position. After this establishment a north gully was positioned in
the centre of the block and in the direction of the fault. This establishment
created the face length and opened the block for extraction according to the
support design specifications. All blocks were extracted without night shift, thus
doing both cleaning and blasting on day shift.
16
94
96/97
7 36C
6 36B
4055
3982
1724
2678
93/94
11 36G
4742
1918
97
Gang March April May June July Aug Sept Oct Nov Dec Jan ' 06 Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan ' 07 Feb
1
2
3
4
5
6
7
8
9 10
11 12 13 14 15 16 17 18 19 20 21 22
23 24
A
25
50 75 100 120 120 120
120 120 120
B
50 50 75 100 120 120
120 120 120 120
C
D
50
50
50
0
25
0
50 100
50 75
50 100 120
0
50 100 120
0
25
50 100
14 H
11
11 I
8
8
25
50
120 120
120
120 120
100 100
120 120
120 120
120 120
120 120
40 50
120 120
120
100 120
120 120
50
70 120 120 120 120 120 120
70 100
120
40
0
50
0
36
GRANDTOTAL
30247
TOTAL GANGS
TOTAL GOLD KG' s @ 4056 cmgt
0
0
0
0
0
0
0
0
0
17
8000
7000
6000
5000
4000
3000
2000
1000
Act Total m2
2005
2006
2007
2008
2009 YTD
1646
4698
8950
6579
1991
800
700
600
500
400
300
200
100
2005
2006
2007
2008
2009 YTD
112
348
713
592
173
18
CONSTRAINTS
It was foreseeable that ventilation and cooling would be the biggest constraint.
This was addressed through the implementation of proper ventilation layouts
utilizing the current infrastructure.
Seismicity on structures was not excluded, but by implementing the unique
support design it was proven that this risk was minimized and controlled.
Inaccessibility of the blocks prior to mining provided us with limited geological
information on the reef horizon. The structures in the blocks were modeled from
old geological mapping, thus creating a degree of uncertainty in terms of
confidence levels in some blocks. Structural changes within the blocks when
mining commenced could influence the successful extraction of the blocks.
Interference with current mining, when mining reef adjacent to structures, posed
a major risk in certain areas which could influence the volume of the current
longwall operation. Re-mining in these areas could increase the seismicity,
resulting in the loss of the access ways to the existing long walls. In addition
layouts for ventilation were critical to ensure that ventilation conditions were
conducive for mining both the areas.
A proper assessment of all existing excavations in the proposed mining area was
necessary to prevent unnecessary holing into established infrastructure.
CONCLUSION
Due to the complexity of the mining environment it is inevitable that one must be
able to adapt to change in order to ensure the viability of the system. This paper
does not seek to obscure your mind, but rather to stimulate the thinking process.
It is imperative to not only remember the basic principles of mining but to
challenge the obvious.
At TauTona Mine it was proven that mining reef adjacent to structures at depth
needed a dynamic and workable plan. The unique extraction sequence per block
was a major contributor to the success of this mining method. The reality is that
successes and failures in blocks are inevitable. The multi disciplinary risk
assessment and involvement of all services departments is imperative to ensure
the success of mining reef adjacent to structures.
The content of this paper results from approximately four years of experience in
mining reef adjacent to structures at depth. It was written with the objective of
assisting fellow mining engineers in the planning and implementation of such a
mining method.
19
ACKNOWLEDGEMENTS
The author wishes to thank the management of TauTona Mine for permission to
publish this paper and all the persons who assisted in the preparation.
In addition thanks to Great Noligwa Mine for their Pillar Investigation Process
Flow Sheet and Lourens Scheepers, Rock Engineering Manager, TauTona Mine
who assisted with the support design.
REFERENCES
AngloGold Ashanti. (2008). Report to Society. South Africa: Johannesburg.
Jager, A.J.; Ryder, J.A. (1999). A Handbook on Rock Engineering Practice for
Tabular Hard Rock Mines.
Le Roux, W.L. (1979). Mine Ventilation Notes for Beginners.
Lurie, J. (1984). South African Geology for Mining, Metallurgical, Hydrological
and Civil Engineering.
Ritson, T.P. (1997). Surveying for Mine Surveyors.
Storrar, C.D. (1987). South African Mine Valuation.
20
PILLAR No.
BLOCK No.
TAUTONA MINE
Date:
Date:
Sign:
Date:
Sign:
Date:
Sign:
Date:
Sign:
Date:
Sign:
Date:
Section Surveyor.
Section 4 completed.
WORKING PLACE
MO Old areas.
Section 5 completed.
Sign:
Date:
Sign:
Date:
Sign:
Date:
Sign:
Date:
Sign:
Date:
Sign:
Date:
Sign:
Date:
N o s.
BLOCK
SHE Department.
Section 9 completed.
Engineering Department
Section 10 completed.
Geology Manager
Section 11 completed.
Section Manager
Section 11 completed.
MRM Manager.
Section 11 completed.
21
P I L L A R N o.
Summary
WORKING PLACE
PILLAR No.
BLOCK No.
TAUTONA MINE
BLOCK
RIH/RIF
iii) Determine:
RGSW
N o s.
Hazardous conditions
v) Transfer to CAD:
Date:
22
P I L L A R N o.
Signature :-
TAUTONA
Appendix
GEOLOGICAL INVESTIGATION
MINE
Geologist:
Date:
PILLAR No.
BLOCK No.
Working place:
Plan scale 1: 1000
U/C
F/W
cmg/t.
It is proposed by Geology to
Facies type:
ORIS:
Geological comments:
INCLINED M2 :
INSERT A COPY (1: 100)
CW (cm) :
SW (cm):
GRADE (CMG/T) :
Geological Investigation
23
WORKING PLACE
PILLAR No.
BLOCK No.
TAUTONA MINE
WORKING PLACE
CHECKLIST
BLOCK
N o s.
Date:
24
P I L L A R N o.
Signature :-
WORKING PLACE
PILLAR No.
BLOCK No.
TAUTONA MINE
CHECKLIST
i) Review available information:
BLOCK
Inclined M
N o s.
CW (CM)
SW (CM)
GRADE (Cmg/t)
kriged
ORIS
Signature :-
Date:
25
P I L L A R N o.
conventional
WORKING PLACE
PILLAR No.
BLOCK No.
TAUTONA MINE
MCF :PRF :-
(%)
(%)
LOW:
LOW:
All additional pegs required in place :Plans up to date :Layouts out and signed by all depts. :Old gold / Lockup :-
MOD:
MOD:
HIGH:
HIGH:
(Y/N)
(Y/N)
(Y/N)
tons @
g/t
=
0 kg Au
WORKING PLACE
CHECKLIST
BLOCK
Remarks:
N o s.
SIGNATURES:
Date:
Section Surveyor:
Date:
26
P I L L A R N o.
WORKING PLACE
PILLAR No.
BLOCK No.
TAUTONA MINE
X/Cut
_____________________________________
_____________________________________
Timber
bay
_____________________________________
_____________________________________
T/Way
_____________________________________
_____________________________________
a)Wet bulb:-
b)Dry bulb:-
N o s.
BLOCK
B/Holes _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_____________________________________
WORKING PLACE
CHECKLIST
i) State of working places:
Haulage _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_____________________________________
__ __________________
iv) Stoping layouts or pegs reqiuired:
___________________________________
_________________________
v) Equipping required:
__________________________________
R
Signature :-
Date:
27
P I L L A R N o.
TAUTONA
MINE
M/Overseer:
Date:
JUL 01
PILLAR No.
BLOCK No.
Working place:
Plan scale 1: 1000
Sleepers?:
Condition:
R
Mining comments:
This pillar
IS / IS NOT
ESH comments:
mineable.
28
PILLAR No.
WORKING PLACE
BLOCK No.
TAUTONA MINE
R
R
R
(metres)
(metres)
(metres)
(metres)
BH / Orepass required :
(metres)
WORKING PLACE
Mine Design
Provisional mining layout on CAD taking the current
Geological structure on CAD, the underground
investigation (App.) and Rock Engineering (App.) into account.
M SLUSHER + M RSE
ASSESSMENT :
This pillar
IS / IS NOT
Signature :
N o s.
BLOCK
T/Way required :
(metres)
Timberbay required :
(metres)
Flat re-equipping required :
(metres)
Total Pillar Access dev.costs : MODE
R
Total Capital development costsMODE
:
R
Total Stoping costs :
R
MODE
Total Mining costs,(excl.D/drilling)
:
MODE
R
Start date for mining
Area that can be mined per year (M2) 2400
CAD Design File No.
mineable.
Date:
P I L L A R N o.
29
TAUTONA
MINE
Date:
Working place:
Plan scale 1: 1000
Hlge.
X/Cut
T/Way
Slusher
B/Hole
TOTAL
Mine design/planning comments:
Mining comments:
Development Plan
30
BLOCK No.
Appendix F1
PILLAR No.
SECTION 7 - FINRISK
0.0271
DATE
% M
MINED
% M
FLTING
DEVELOPMENT SHEET
LINE
LEVEL
MCF
%
Plant REC.
%
85.03
97.57
PANELS
STOPE SHEET
BLOCK No.
STOPING TO BE DONE
INCLINED M
SW
CW
BLOCK No.
BLOCK
26
28
36
70
100%
13027
4290
40875
11855
60%
7816
2574
24525
7113
0%
7816
2574
24525
7113
TOTAL
70047
42028
23.0
42028
SW Full Width
(MRIS)
% GROUNDGROUND
AVAILABLE
AVAILABLE - FLT DISCOUNT
cm.
100
100
100
100
cm.
23.0
23.0
23.0
23.0
VALUE
(MRIS)
cm.g/t
3333
3829
4205
4421
REEF DIP
22.5
22.5
22.5
22.5
GRADE
g/m
90.32
103.77
113.96
119.81
4056
22.5
109.93
100.0
100.0
H
3.4
3.4
3.2
3.0
1.2
2.4
W
3.0
3.0
3.0
1.8
2.4
3.0
SG
2.78
2.78
2.78
2.78
2.78
2.78
TONS
851
0
2802
6755
961
0
11369
0
#DIV/0!
FACTORS
STOPE STATS
TONS
ORE
21182
6976
66463
19276
CONTENTS
Kilograms Au
706
267
2795
852
113896
113896
MCF
%
Plant REC.
%
85.03
97.57
R/m *Dev
7500
7500
7500
7500
*Standard VR
16.13
COST
225000
0
787500
3375000
900000
0
R/ton
M2
COST (R/M2
264
42028
2094
5,287,500
465
FINANCIALS
Item
COST
REVENUE
88,007,051
500
COSTS
937
STOPING COSTS
DEVELOPMENT COSTS
TREATMENT COSTS
AVG Tons / M
R/rec.gm.
PROFIT / LOSS
DIRECT COST
UNIT COST
TOT.STOPE TREAT.
0
0
0
TOT.DEV. TREAT.
0
0
TOTAL TREATMENT
0
0
TONS
(R/ton)
(R/ton)
(Rand)
113896
6755
(R/ton)
(Metres)
AS PER
NOW
IN 6
MTHS
IN 12
MTHS
Date :
m./mth.:
No.:
m.:
m / mth.:
m.:
Mths.:
31
IN RANDS
306,637,216
R/rec.gm.
281
Total REC.
4620
STOPING COSTS
DEVELOPMENT COSTS
METRES
WORKING PLACE
30
HLGE
RAW / CON.X/C
105
CROSSCUT
450
RAISE + SLUSHER
120
BOXHOLE
TRAVELLINGWAY
705
TOTAL
PLANNED DEV.RATE; m / mth
ESTIMATED TIME TO COMPLETION: mths
STOPING,
DEVELOPMENT,
TOTAL ENGINEERING
FLAT RE-EQUIPPING,
DIAMOND DRILLING
GOLD PRICE
IN 18
MTHS
R/rec.gm.
Profit/Revenue %
TOT.DEV. COST
IN 24
MTHS
3rd
YEAR
4th
YEAR
93,294,551
213,342,665
WORKING PLACE
PILLAR No.
BLOCK No.
TAUTONA MINE
ii) Stability:
Rating
WORKING PLACE
X/cut
T/way
B/hole
Timber bay
BLOCK
Other
b). Secondary :-Haulage
X/cut
N o s.
T/way
ASSESSMENT :
Date :
32
P I L L A R N o.
WORKING PLACE
PILLAR No.
BLOCK No.
TAUTONA MINE
ii) Temperatures:
WORKING PLACE
BLOCK
v) Escape routes:
N o s.
CH4 =
H2O (l/hr) =
Precautions :-
Special instructions ?
Date
33
P I L L A R N o.
ASSESSMENT :
WORKING PLACE
PILLAR No.
BLOCK No.
TAUTONA MINE
WORKING PLACE
BLOCK
N o s.
P I L L A R N o.
Signature :
Date:
34
SUMMARY SHEET
TAUTONA MINE
(ORIS)
#REF!
N/A
(cm)
Full C/Width
(cm)
Footwall thickness :-
(cm)
(cm)
(cm)
tons
(%)
(%)
R/Kg.
R/Kg.
R
Kg.
TO BE CALC.
g/t.=
FINAL ASSESSMENT :
COMMENTS :-
Signature :
PILLAR GEOLOGIST
35
Date:
Kg. Au
COSTS
Gold price used :Curr.Breakeven gold price:Total revenue :Total Recovered Gold :LOM DCF - Operational
PROFIT or LOSS :-
(%)
(cm.g/t.)
STORES + CORPORATE
(%)
TOTAL PRODUCTION +
From Finrisk
(70% OF TOTAL)
ASSESSMENT :
This pillar
IS / IS NOT
mineable.
Signature :-
Date:
ASSESSMENT :
This pillar
IS / IS NOT
Signature :-
mineable.
Date:
ASSESSMENT :
Signature :-
Date:
ASSESSMENT :
Signature :-
Date:
MRM comments:
FINAL ASSESSMENT :
This pillar CAN / CANNOT be mined safely and profitably.
Signature :-
Date:
36
37