Sei sulla pagina 1di 7

JOY E.

PECHET, PMP
Ms. Pechet is a Senior Executive Consultant with Long International and
has nearly 30 years of experience in cost and schedule analysis, project
controls, and claims preparation and negotiation for large domestic and
international construction projects. Her expertise includes schedule delay
analysis, loss of productivity studies, budget and cost variance analysis,
and cash flow studies. She has prepared damage and lost profits analyses
for breach of contract, business interruption, and wrongful termination
disputes.
In addition, Ms. Pechet has successfully evaluated and
negotiated extension of time, loss of productivity, and acceleration claims
for petrochemical, oil refining, coal and gas-fired power plants,
commercial, educational, medical and correctional facilities, and large
infrastructure projects throughout the world ranging in size from
US$100,000 to over US$1 billion.
Ms. Pechet is an expert in delay claims, forensic planning, contract management, dispute resolution and
avoidance, project controls, disruption and productivity analysis, Primavera software, and FIDIC
contracts. She has prepared both assertive and defensive claims for owners, contractors and
subcontractors, applying various delay claim techniques including Time Impact Analysis, Windows
Analysis, Impacted-As-Planned, and Collapsed-As-Built to quantify delay. She has produced loss of
productivity analyses to quantify the schedule impact.
EDUCATION
B.S., Civil Engineering, Massachusetts Institute of Technology (MIT), 1977
PROFESSIONAL REGISTRATIONS
Project Management Professional (PMP)
Member of Chartered Institute of Arbitrators, (MCIarb)
PROJECT EXPERIENCE
Ms. Pechet has prepared and negotiated delay and disruption claims for over 20 years, for projects ranging
in size from US$100,000 to over US$1 billion. Much of this work has been performed on large industrial
and infrastructure projects located throughout the world. She has managed and directed internal claims
teams and supported external legal counsel. Ms. Pechet has evaluated project schedules, contract documents,
and project records to determine the cause and effect of construction delays and cost overruns, attributing
responsibility for cost and schedule impacts to the various contracting parties. She has prepared delay and
quantum claims and successfully negotiated equitable adjustments with Owners, Contractors and Subcontractors. She has prepared both assertive and defensive claims for a wide variety of clients spanning a
number of industries. Representative claims include the following:
Petrochemical, Oil Refining and Power Plant Facilities

Engaged by Contractor to evaluate cost and schedule delays and to prepare Requests for Equitable
Adjustment for a US$1.3 billion petrochemical plant in UAE. The project consisted of two separate
contracts, one for the EPC of a Cross-Linked Polyethylene plant (XLPE), and the other for the provision of
utilities and offsite structures, including Marine Facilities and a Sea Water Intake/Outfall Structure, for
Ethylene and Polypropylene plants being constructed at the same time by other contractors. Negotiations

Resume of Joy Pechet, PMP

Page 2

with client on the REAs totaling over US$250 million have begun. Also responsible for responding to and
negotiating $50 million of claims against the Contractor by subcontractors.

Evaluated cost and schedule impacts to a US$460 million Lube oil process plant constructed in a 20-year
old refinery in the UAE. The project consisted of the EPC of a Base Oil Unit using Unconverted Oil form a
hydrocracker as a feedstock.

Assisted with the preparation of assertive and defensive claims on a $1.2 billion coal-fired power plant
project in the UAE. Responsibilities included forensic schedule analysis, loss of productivity calculations,
and cost overrun analyses. Reviewed project correspondence, schedule updates, status reports and cost
reports to evaluate the cause and effect of delays, disruption, loss of productivity and cost overruns.
Analyzed contractual provisions to assess a Partys entitlement to additional costs and extension of time.

Prepared and successfully negotiated a 4.75 month extension of time to the completion date of a gas fired
power plant as a result of Owners delay in providing access to site.

Prepared disruption claim due to Owners failure to finalize design requirements for a gas-fired power plant
prior to Notice to Proceed. This had the effect of transforming a Lump-Sum Turnkey Project into a designbuild project. Also argued that disruptions caused by a supplier are recoverable under German law.

Demonstrated entitlement to a 5.75 month extension of time as a result of transportation delays, cladding
delays (not within Contractors control), and poor performance by Owners contractors on a gas-fired
power plant.

Prepared claim for 8-month extension of time and $40 million in additional costs as a result of unforeseen
ground conditions. Showed that total delay to the gas-fired power plant would have been 12 months but for
mitigation and acceleration by Contractor.

Successfully argued for a 9-month extension of time as a result of unforeseeable growth in lead times of
key power plant components due to extraordinary market conditions. Justification was based on the fact
that tender was made in 2006, but Notice to Proceed was not issued until 2008.

Prepared 95-day extension of time for a power project in Brazil due to (1) Owners civil works delays, (2)
custom clearance delays, (3) shortages of sand for concreting, and (4) delays in Owner-supplied cladding.

Developed a work-around plan, with full agreement by Owner, to mitigate the impact of a Contractors
delay for gas-fired power plant in Perth. Contract completion date was achieved.

Demonstrated the impact of unforeseen soil conditions to justify request for 1.5 month extension of time
and 1 month of acceleration costs to a power plant project in the UK.

As a consequence of Polands acceptance into the EU after contract award, analyzed the impact to boiler
steel structure design due to the change in law. The requirement to harmonize the original contract with the
EU standards resulted in engineering delays. A 9.5-month extension of time claim was prepared.

Successfully argued entitlement to a 3-month extension of time as a result of the discovery of asbestos on
underground pipes that had to be removed prior to start of construction of a power plant.

Prepared a claim for 2-month extension of time for a power plant project in France. Successfully argued
that Owner failed to inform Contractor that site was classified as protected species area, thereby resulting
in a 2-month redesign effort.

Demonstrated how delays to a coal-fired project were a result of events outside the control of Contractor,
including extreme weather, slow submittal review by Owner, soil contamination, and labor shortages.
Successful in receiving a 9-month extension of time and $35 million in prolongation costs.

Demonstrated how Owners delays were concurrent with Contractors delays, to offset full assessment of
liquidated damages.

Resume of Joy Pechet, PMP

Page 3

Assessed impact of labor shortages and lower labor productivity on schedule for a power plant project in
Texas.

Responsible for preparation and negotiation of change orders and claims to recover $60 million in cost
overruns and to obtain relief from assessment of liquidated damages. Project involved 8 Distributed
Control Systems being designed, manufactured, and installed by Invensys to control 8 nuclear power plants
under construction in China. Analyzed cost overruns and schedule delays that are attributable to the client.

Industrial, Commercial, Educational, Medical and Correctional Facilities

Responsible for negotiating $54 million in claims against US government. Developed negotiating
strategies. Analyzed contractors progress to defend Government against claims by contractor. Settled
$54 million claims for $8 million.

Prepared integrated schedule for IRS Headquarters Building. Coordinated works performed by several
contractors and many governmental agencies.

Prepared time impact analysis showing entitlement to 11 weeks of compensable delay on a new
parking garage.

Project Manager for the construction of the US Consulate in Cape Town, South Africa. Responsibilities
include: day-to-day over site and interface with General Contractor; coordinating design and submittal
reviews with government; negotiating Contractor Requests for Equitable Adjustment; coordinating,
reviewing and monitoring contractor schedules and progress payments.

Analyzed impact to academic building as a result of delays to (1) switchgear design, (2) elevator
installation, (3) interior finishes, and (4) productivity loss.

Demonstrated impact to critical path of delayed permitting, stop work orders, and redesign of the piling
system. Determined compensable and non-compensable delays.

Responsible for project integration, requirements analysis, risk management, and process re-engineering for
major IT upgrade project for the US Air Force. Managed the preparation of an Integrated Network
Schedule consisting of 150 Satellite Control Network development projects, launch activities, and network
downtime schedules. Identified cross project impacts, resource conflicts, critical paths and project
interdependencies.

Prepared feasibility studies, cash flow analysis, budgets, and cost variance analyses for hotel and resort
construction projects at Euro Disney totaling over $150 million. Developed project proformas and
implemented financial reporting systems.

Project Manager for the design, fabrication and installation of elaborate multi-million dollar water features
in the US and internationally.

Performed earned value analysis of $150 million Pentagon IT network upgrade project. Prepared Budget
vs. Cost and cash flow analyses. Updated cost-loaded schedules.

Transportation Projects

Aided in the analysis, preparation and negotiation of a $90 million claim against the Massachusetts
Department of Transportation for additional costs to the client (Honeywell) for traffic control systems for
the Central Artery Tunnel project. Responsibilities included identification of cost and schedule impacts
due to scope changes.

Assisted with the development of an integrated project schedule for the Dulles Airport Expansion Project.

Resume of Joy Pechet, PMP

Page 4

PROFESSIONAL EXPERIENCE
Long International, Inc.
Orlando, Florida (September 2014 to Present)
As a Senior Executive Consultant with Long International, Ms. Pechet provides construction claims analyses
related to schedule delays, acceleration issues, requests for time extension, assessment of liquidated damages,
productivity losses, and the quantification of damages. Other duties include proactive CPM scheduling and
schedule assurance services, cost control and monitoring services, and property damage and business
interruption claims analyses.
Hyundai Engineering and Construction
Abu Dhabi, UAE (July 2013 to September 2014)
As a Claims Consultant, Ms. Pechet was responsible for developing and implementing strategies for
resolution of claims and disputes. Tasks include the analysis, preparation, and negotiation of assertive and
defensive claims. Managed and directed internal claims teams and external legal counsel. Evaluated project
schedules, contract documents, and project records to determine the cause and effect of construction delays
and cost overruns; attributed responsibility for cost and schedule impacts to various Parties in accordance
with contractual requirements. Evaluated and quantified concurrent delays. Applied various delay claims
techniques including Time Impact Analysis, Windows Analysis, Impacted-As-Planned, and Collapsed-AsBuilt to quantify delay. Produced productivity analyses and identified construction inefficiencies.
Responsible for redefining Contract Management processes and procedures and for developing a Claims
Manual to serve as the standard guide to claims and disputes for the Company.
Hill International
Doha, Qatar (March 2013 to July 2013)
As an Associate Director, Ms. Pechet was responsible for producing independent, expert delay and disruption
analyses for settlement and arbitration purposes. Clients included Siemens, Metka, and Punj Lloyd, and
involved offshore platforms, power plants, and airport projects. Managed and directed internal and external
claims teams. Presented delay and disruption claims training seminars to clients.
Invensys Operations Management
Foxborough, Massachusetts (April 2012 to March 2013)
As a Commercial Contract Management Specialist, Ms. Pechet was responsible for preparation and
negotiation of change orders and claims to recover $60 million in cost overruns and to obtain relief from the
assessment of liquidated damages. Project involved 8 DCS systems being designed, manufactured, and
assembled by Invensys to control 8 nuclear power plants under construction in China. Analyzed cost
overruns and schedule delays attributable to delays by the client in finalizing plant engineering and design
inputs to the DCS. Compared design input delays with contractual requirements to determine schedule
impacts to Invensys by system; produced change order proposals to recover revenue; revised the internal
change management process; aided in formulating a commercial strategy for recovery of additional costs;
coordinated with Project Directors, Legal, Engineering and Project Controls to determine cause and effect of
clients design input delays.

Resume of Joy Pechet, PMP

Page 5

Siemens Energy Third-Party Contractor


Orlando, Florida (September 2010 to April 2012)
Engaged as an external consultant by Siemens to aid in the preparation of assertive and defensive claims on a
$1.2 billion coal-fired power plant project. Responsibilities included forensic schedule analysis, loss of
productivity calculations, and cost overrun analyses. Scope of services included: (1) review of project
correspondence, status reports, schedule updates, and cost reports to evaluate the cause and effect of delays,
disruptions, loss of productivity, and cost overruns, (2) preparation of assertive and defensive claims,
(3) analysis of contractual provisions to assess a Partys entitlement to additional costs and extension of time,
and (4) presentations to Owner, Partners, project team, lawyers, etc. to defend and assert positions regarding
the party responsible for cost/schedule impacts.
ALSTOM Power Systems Plant Business
Baden, Switzerland (January 2007 to July 2010)
Director Forensic Planning, responsible for schedule delay, disruption, and loss of productivity analysis.
Performed cause-and-effect and time impact analyses. Prepared negotiation strategies for cost and schedule
claims. Interpreted contract and law to identify strategies for claiming Extension of Time (EOT) and cost
entitlement opportunities. Negotiated EOT and loss of productivity claims for projects around the world.
Responsible for identifying future schedule concerns and for proposing alternative mitigation plans to prevent
further schedule deterioration; evaluated the cost/benefits of various schedule recovery options. Identified
concurrent delay situations. Ensured that client interfaces and change orders are explicitly identified in the
project schedule. Successful in recovering several months of liquidated damages assessment as well as
prolongation and disruption costs as a result of forensic schedule analysis, contract interpretation, and client
negotiation. Authored and presented training seminars on schedule delay, loss of productivity, and
acceleration claims to project teams worldwide.
US Government General Services Administration (GSA) Contractor
Washington, DC (September 2005 to January 2007)
As a Project Manager/Claims Consultant, Ms. Pechet was responsible for resolving $54 million in Requests
for Equitable Adjustments and claims against GSA by a General Contractor on a $300 million project.
Successful in getting parties to agree to settle these claims for $8 million. In addition, evaluated schedule
delays; performed resource allocation studies; calculated economic losses as result of schedule delays;
assessed impact of design/construction changes on schedule; determined negotiation strategies; and analyzed
progress, resource requirements and cost performance on several GSA projects, including an IRS Renovation
Project. Interfaced with project managers, clients, attorneys, and contractors to resolve schedule and
cost disputes.
ASRC Constructors Inc.
Beltsville, Maryland (December 2004 to August 2005)
As Project Controls Engineer, developed and monitored resource and cost-loaded schedules, performed cash
flow analysis, analyzed earned value, and developed what-if scenarios for a classified $150 million Pentagon
IT network upgrade project. Additionally, responsible for preparation and maintenance of multiple,
concurrent construction schedules for $20 million Dept of State FPSP Embassy Maintenance & Repair
Program. Utilizing Primavera P3.1, prepared and monitored cost and resource-loaded schedules in a multiproject environment; negotiated change orders; managed field staff in remote locations; and prepared cost
proposals for additional task order work.

Resume of Joy Pechet, PMP

Page 6

US Department of State OBO


Washington, DC (August 2003 to December 2004)
As a Project Controls Engineer, Ms. Pechet was responsible for the analysis of budgetary and cost
information from multiple government sources; preparation of monthly reports on project budget status;
preparation of Project Change Request and Amendments; tracking and analysis of allotments and obligations
of project funds; resolving budget disparities; establishing internal budgetary controls; and managing project
funding authorization changes.
As a Construction Manager, Ms. Pechet was responsible for managing the construction of a $35 million in
consulate in Cape Town, South Africa. Responsibilities included: day-to-day oversight and interface with
General Contractor; monitoring and analysis of cost and schedule data; coordinating design and submittal
reviews with government entities; critiquing and negotiating Contractors Requests for Equitable Adjustment;
coordinating multiple, integrated schedules; reviewing and monitoring General Contractors schedule for
critical path, logic errors, and inconsistencies with government schedules; developing risk mitigation plans;
determining impact of contract mods on schedule in anticipation of construction claims. Utilized P3 and P5.
GS-14 Step 10.
Hill International
Washington, DC (February 2002 to August 2003)
As Managing Consultant in the Construction Claims Division, responsible for the analysis, preparation, and
submittal of a $90 million claim by a subcontractor against the Massachusetts Central Artery.
Responsibilities included: identifying cost impacts of scope changes; developing a methodology for
segregating base costs from impacted and changed work costs; coordinating the financial analysis effort;
identifying key issues responsible for cost overruns; providing analysis of project metrics; coordinating
expert witness work; and preparing supporting documentation for use in negotiation. In addition, responsible
for developing an Earned Value Management System for client.
Bechtel Energy Corporation
Frederick, Maryland (January 2001 to February 2002)
As Claims Analyst, responsible for evaluating change order disputes and establishing claim strategies,
including those affecting prime contracts, subcontracts, vendors, and partners. Effort included both the direct
preparation and critiquing of offensive and defensive claims and disputes, and the direction of external
resources to perform such tasks. Specifically involved in the assessment of the commercial aspects of claims,
including interpreting cost and schedule data and preparing impact analyses. Aided in the preparation for
negotiation, mediation, arbitration, and litigation. Assisted Project Management in its efforts to minimize
risks and avoid claims situations.
Lockheed Martin Technical Operations
El Segundo, California (June 1997 to June 2000)
As Systems Engineer, responsible for project integration, requirements analysis, risk management, and
process re-engineering of a major IT upgrade project for the Air Force. Managed the preparation of an
Integrated Network Schedule consisting of 150 Air Force Satellite Control Network
development/sustainment projects, Satellite Program launch activities, and network downtime schedules.
Identified cross project impacts, resource conflicts, critical paths, and project interdependencies.
Recommended risk mitigation options and resource reallocation plans. Performed sensitivity analysis on

Resume of Joy Pechet, PMP

Page 7

schedules. Documented technical, cost, and schedule risks. Led quarterly Risk Review Forums, with
participation from contractors, AFSPC operations, and AF customer.
WET Design
Los Angeles, California (January 1995 to June 1997)
As Project Manager, directed multi-disciplinary activities leading to the successful design, engineering,
fabrication, and installation of elaborate, multi-million dollar water features within the US and abroad. As
Director of WETCare, responded to clients field service requirements by directing field, engineering and
programming staff to the site. Prepared and marketed project enhancement proposals. Resolved installation
and warranty issues.
Navigant Consulting, Inc. (formerly Peterson Consulting Limited Partnership)
Boston, Massachusetts (July 1993 to January 1995)
As Senior Consultant, provided litigation support consulting and contract disputes management. Performed
damage and lost profits analyses for breach of contract, business interruption and wrongful termination
disputes. Reviewed, analyzed, and prepared construction claims. Performed liability assessments,
schedule/cost variance analysis, construction oversight, lost profits/productivity calculations, and delay and
damage analysis.
Walt Disney Company Euro Disney
Paris, France (June 1987 to January 1992)
As Project Controller, prepared feasibility studies, cash flow analyses, budgets, and cost variance analyses for
hotel and resort construction projects totaling over $150 million; developed project proformas; designed and
implemented financial reporting systems.

Potrebbero piacerti anche