Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
A. VARIATIONS:
Construction contracts are of such nature that it is almost impossible to design and construct a project such that the
final product is identical in every way when compared with the original design which formed the basis of contractors
bid. Changes to original design and/or details that may come about either due to:
a)
b)
c)
d)
e)
In either of these cases, the contractor is no longer obliged to execute the work unless or until these changes (which
are termed as variations) are regularized by mutual consent of the parties and the Contract Price is adjusted
accordingly.
Purpose of Variation:
i.
Valuation of variations are generally intended such that an element of profit can be recovered on the extra
costs to be incurred on executing that variation.
B. CLAIMS:
Whenever there is delay, disruption, encounter with adverse circumstances, it is followed by an effect in terms of
additional time or cost which is to be borne by either of the parties. Where there is a breach of contract or there is a
provision in the contract to claim loss or damage, one party may lodge a claim against the other one.
Purpose of claim:
i.
ii.
iii.
Basic purpose of claim is to reinstate the claimant in the same financial position in which he would have been
if the compensation event would not have occurred. Therefore, in most of the circumstances, the provisions
for claims limit reimbursement to cost / expense without inclusion of any profit
The insertion of claim provision in the contract is also intended to empower the contract administrator (which
is supposed to be a neutral entity) to make payment of damages to the contractor without a variation being
ordered.
Claims arising out of a breach of contract by one of the either parties is a remedial action (provided by law)
for the other party