GOVERNMENT OF KARNATAKA

PUBLIC WORKS, PORTS & INLAND WATER TRANSPORT


DEPARTMENT
PROJECT IMPLEMENTATION UNIT
KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT - II
World Bank Funded-Loan No 8022-IN
Quarterly Progress Report
(July-September-2013)

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Quarterly Progress Report 1


(1 July 2013 to 30 September 2013)
Contents
1.

EXECUTIVE SUMMARY..................................................................................................................................1

2.

SUMMARY OF PROJECT ACTIVITIES.........................................................................................................9


2.1 COSTS AND BANK LOAN FOR PROJECT COMPONENTS.....................................................................................9
2.2 OVERALL PROJECT IMPLEMENTATION STATUS (PROGRESS AND ISSUES) BY COMPONENT AND CONTRACT.10
2.3 SUMMARY OF PROCUREMENT PACKAGES FOR WORKS, GOODS AND SERVICES...........................................18
2.4 LOAN STATUS.................................................................................................................................................18
THE REASONS FOR SLOW DISBURSEMENT ARE MAINLY DUE TO TERMINATION OF WEP-2 CONTRACTOR M/S
ROMAN TARMAT LTD, PENDING FINALIZATION OF DBFOMT PACKAGES ...............................................................18
2.5 DISBURSEMENT CLAIMS................................................................................................................................18
2.6 AUDIT OF PROJECT ACCOUNTS FOR THE FINANCIAL YEAR 2013-14............................................................19
2.7 BANK MISSIONS & RATINGS..........................................................................................................................19
2.8 MAJOR ISSUES AND PROPOSED RESOLUTIONS FOR EACH COMPONENT........................................................20
2.9 PROJECT PERFORMANCE INDICATORS............................................................................................................22
2.10 ACTIONS EXPECTED FOR NEXT QUARTERLY PERIOD....................................................................................22

3.

INTRODUCTION..............................................................................................................................................24
3.1
3.2

4.

DETAILED PROJECT IMPLEMENTATION/PROGRESS BY COMPONENT AND CONTRACT......27


4.1
4.2
4.3

5.

PROJECT BACKGROUND.................................................................................................................................24
PROJECT DATA...............................................................................................................................................25

WB-EPC PACKAGES......................................................................................................................................27
CIVIL WORKS PROGRESS...............................................................................................................................29
MAJOR ONGOING ISSUES...............................................................................................................................31

PROJECT IMPLEMENTATION MONITORING.........................................................................................39


5.1
5.2

PHYSICAL PROGRESS......................................................................................................................................40
FINANCIAL PROGRESS....................................................................................................................................44

6.

PAYMENT AND DISBURSEMENT PROGRESS..........................................................................................48

7.

SOCIAL, RESETTLEMENT & REHABILITATION....................................................................................50


7.1
7.2
7.3

8.

COVENANTS.....................................................................................................................................................53
8.1
8.2

9.

SUMMARY OF RESETTLEMENT AND REHABILITATION ACTIVITIES................................................................50


RESETTLEMENT COMPLAINTS........................................................................................................................52
HIV/AIDS EDUCATION MONITORING............................................................................................................52

LOAN COVENANTS.........................................................................................................................................53
LEGAL COVENANTS.......................................................................................................................................54

SUMMARY OF PROCUREMENT PACKAGES...........................................................................................57


9.1

PROCUREMENT PLANS FOR WORKS, GOODS, AND SERVICES........................................................................57

10. ENVIRONMENTAL MANAGEMENT ACTIVITIES...................................................................................58


10.1 CLEARANCES AND COMPLIANCE...................................................................................................................58
10.2 EMP COMPLIANCE.........................................................................................................................................60
11. PERFORMANCE MONITORING INDICATORS........................................................................................65
12. SEMINARS, WORKSHOPS AND TRAINING..............................................................................................71
13. REPORT DELIVERY SCHEDULE.................................................................................................................72

Page i

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Table of Contents
TABLE 1: CURRENT PROBLEMS & ACTIONS
TABLE 2: SUMMARY OF COST & BANK LOAN AMOUNT FOR PROJECT COMPONENTS (US$ MILLION)
TABLE 3: EPC CIVIL WORK PROGRESS
TABLE 4: R&R AND LA STATUS - EPC PACKAGES
TABLE 5: R&R AND LA STATUS-ANNUITY PACKAGES
TABLE 6: ROAD SECTOR POLICY & INSTITUTIONAL DEVELOPMENT
TABLE 7: SUMMARY OF PROCUREMENT FOR WORKS, GOODS & SERVICES
TABLE 8: LOAN STATUS
TABLE 9: DISBURSEMENT CLAIMS
TABLE 10: BANK MISSIONS AND RATINGS
TABLE 11: MAJOR ISSUES AND PROPOSED RESOLUTIONS
TABLE 12: ACTION EXPECTED FOR NEXT QUARTERLY PERIOD
TABLE 13: PROJECT DATA
TABLE 14: CIVIL WORK PROGRESS
TABLE 15: MAJOR ONGOING ISSUES
TABLE 16: PROJECT IMPLEMENTATION MONITORING
TABLE 17: PHYSICAL PROGRESS OF WEP-1
TABLE 18: PHYSICAL PROGRESS OF WEP-2A
TABLE 19: PHYSICAL PROGRESS OF WEP-3
TABLE 20: PHYSICAL PROGRESS OF WEP-4
TABLE 21: PHYSICAL PROGRESS OF WEP-5
TABLE 22: FINANCIAL PROGRESS, WEP-1
TABLE 23: FINANCIAL PROGRESS, WEP-2A
TABLE 24: FINANCIAL PROGRESS, WEP-3
TABLE 25: FINANCIAL PROGRESS, WEP-4
TABLE 26: FINANCIAL PROGRESS-WEP-5
TABLE 27: PAYMENT AND DISBURSEMENT PROGRESS
TABLE 28: STATEMENT OF RECEIPTS AND PAYMENTS
TABLE 29: PROJECTS OVERALL DISBURSEMENT PROGRESS
TABLE 30: RESETTLEMENT AND REHABILITATION ACTIVITIES FOR WEP PACKAGES.
TABLE 31: RESETTLEMENT AND REHABILITATION ACTIVITIES FOR WAP PACKAGES.
TABLE 32: RESETTLEMENT COMPLAINTS
TABLE 33: HIV-AIDS CAMPAIGNS AT WEP PACKAGES
TABLE 34: LOAN COVENANTS
TABLE 35: LEGAL COVENANTS
TABLE 36: RIGHT TO INFORMATION ACT
TABLE 37: COMPLAINT MANAGEMENT CELL (CMC) CASES FOR THE YEAR 2013(JULY TO SEPT 2013)
TABLE 38: SUMMARY OF PROCUREMENT PACKAGES
TABLE 39: ENVIRONMENTAL CLEARANCES
TABLE 40: STATUTORY COMPLIANCE STATUS
TABLE 41: STATUS OF WATER BODIES
TABLE 42: DETAILS OF FOREST LAND DIVERSION
TABLE 43: TREE CUTTING STATUS OF EPC PACKAGE
TABLE 44: TREE CUTTING STATUS OF ANNUITY PACKAGE
TABLE 45: ENVIRONMENT POLLUTION MONITORING STATUS
TABLE 46: BORROW AREAS OF THE CONTRACTORS
TABLE 47: CRUSHERS/QUARRY PRODUCTION
TABLE 48: PROJECT DEVELOPMENT OBJECTIVES MONITORING
TABLE 49: SEMINARS, WORKSHOPS AND TRAININGS CONDUCTED BY PIU
TABLE 50: SEMINARS, WORKSHOPS AND TRAININGS CONDUCTED BY CSC
TABLE 51: REPORT DELIVERY SCHEDULE

Page ii

6
9
11
15
15
17
18
18
18
19
20
22
25
27
31
39
40
41
41
42
43
44
45
45
46
47
48
49
49
50
51
52
52
53
54
56
56
57
58
59
60
61
62
62
63
63
64
65
71
71
72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Abbreviations
AIDS
BC
CAAA
CA
CDTA
CFE
CFO
CSC
DBFOMT
DBM
DBMS
DPR
EMP
EMS
EOI
EOT
EPC
FD
FMM
FPTA
GAAP
GOK
GSB
HIV
HMP
HRD
HT
IBRD
ICB
ICT
IE
IRAP
IRC
ISO
IT
IUFR
JV
KRDCL
KHSDRP
KSHIP
KSPCB
KPWD
LHS
M&E
MIS
MOEF
MS
NCB
NGO
PAD
PAF
PAP

Acquired Immune Deficiency Syndrome


Bituminous Concrete
Controller of Aid Accounts and Audit
Concession Agreement
Capacity Development &Technical Assistance
Consent for Execution
Consent for Operation
Construction Supervision Consultant
Design, Build, Finance, Operate, Maintain, and Transfer
Dense Bituminous Macadam
Data Base Management Services
Detailed Project Report
Environment Management Plan
Environmental Management System
Expression of Interest
Extension of Time
Engineering and Procurement Contract
Finance Department
Financial Management Manual
Financial Planning and Technical Advisory
Governance and Accountability Action Plan
Government of Karnataka
Granular Sub-base
Human Immunodeficiency Virus
Hot Mix Plant
Human Resource Development
High Tension
International Bank for Reconstruction and Development
International Competitive Bidding
Information and Communications Technology
Independent Engineer
International Road Assessment Program
Indian Road Congress
International Organization for Standardization
Information Technology
Interim Unaudited Financial Report
Joint Venture
Karnataka Road Development Corporation Limited
Karnataka Health System Development & Reform Project
Karnataka State Highways Improvement Project
Karnataka State Pollution Control Board
Karnataka Public Works Department
Left Hand Side
Monitoring and Evaluation
Management Information System
Ministry of Environment and Forests
Milestone
National Competitive Bidding
Non-governmental Organization
Project Appraisal Document
Project Affected Families
Project Affected People
Page iii

PIU-KSHIP

PCB
PCC
PIU
PMS
PPP
PRAMC
PWD
QM
RAP
R&R
RFP
RHS
RIS
RSM
RUSS
SCDP
SDRC
STD
TA
TD
TIMS
TOR
TPH
TRSC
VFM
VO
WMM

Quarterly Progress Report 2 (1 July to 30 September 2013)

Pollution Control Board


Project Coordinating Consultant
Project Implementation Unit
Project Management System
Public Private Partnership
Planning and Road Asset Management Centre
Public Works Department
Quality Management
Resettlement Action Plan
Resettlement and Rehabilitation
Request for Proposal
Right Hand Side
Road Information System
Road Safety Management
Road User Satisfaction Survey
Safety Corridor Demonstration Program
Social Development Research Cell
Sexually Transmitted Disease
Technical Assistant
Transport Department
Traffic Incident Management System
Terms of Reference
Tonne per Hour
Traffic & Road Safety Cell
Value for Money
Variation Order
Wet Mix Macadam

Page iv

PIU-KSHIP

1.

Quarterly Progress Report 2 (1 July to 30 September 2013)

EXECUTIVE SUMMARY

1.1 The IBRD assistance covers the following four components.

Component 1: Road Improvement Works (Total Cost: US$ 603 million; IBRD: US$ 260 million;
GOK: US$ 94 million; Developer: US$ 249 million).

Component 2: Highway Financing Modernization (Total Cost: US$ 374 million; IBRD: US$ 67
million; GOK: US$ 56 million; Developers/Financial Institutions: US$ 251 million).

Component 3: Road Safety Improvement (Total Cost: US$ 14 million; IBRD: US$ 11 million;
GOK: US$ 3 million).

Component 4: Road Sector Policy and Institutional Development (Total Cost: US$ 11.8 million;
IBRD: US$ 9.44 million; GOK: US$ 2.36 million).

1.2 The total estimated project cost is US$ 1,005 million (IBRD: US$ 350 million, GOK: US$ 155
million, and Private Sector Developers: US$ 500 million). The duration for implementation of the
project is 5 years from June 2011 to December 2016. Further information on the project components
are given in Chapter 3.
1.3 Current Loan Status
As at the end of September 2013, a sum of US$ 41.511 million representing 11.90% of the available
loan had been disbursed against the target amount of US$ 167 million as per PAD. Disbursement is
considerably behind the schedule by 75.14% because of the following reasons:

The five (6) EPC contracts failing to achieve targets due to reasons noted in Para 1.4 below.

Delay in procurement of four (4) Annuity contracts.

There are delays in the procurement of Goods and Services, but these contracts being of much
smaller value compared to the civil works do not significantly impact the overall disbursement.
1.4 Project Implementation Status:
The project implementation status for Civil Works, Goods and Services are summarized below.
a) Civil Works:
i) World Bank EPC Contracts: The physical progress achieved for the Second Quarter 2013/14 for
the six (6) EPC contracts is 4.77% compared to the programmed 3.50%. The overall physical
progress achieved since inception is 49.30% compared to the programmed 65.82%. These contracts
are running up to 13 months behind the original schedule. WEP-2A Contractor has mobilized
sufficient men & machineries and started CD works and bridge works. Procurement of Package
WEP-2B has been concluded and the 24-month Contract awarded to M/s DRN Infrastructure Pvt. Ltd
the same Contractor who won the WEP-2A Contract. The WEP-2B Accepted Contract amount is
US$ 21.75 million. The Contract Agreement was signed on 6 th July 2013. The Contractor started the
mobilization of men and machineries and PIU KSHIP paid 5% mobilization advance. Details of these
Contracts are presented in Chapter 2.

Page 1 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

The slow progress is mainly due to the following reasons:

Delay in locating suitable quarry and crusher sites due to a High Court stay order on operation of
quarries. Most of the quarries were only finalized after approximately nine months from the
commencement of implementation. Due to the delay in the mobilization of the crushers, the
Major structural works in all the Contracts were delayed and delays have also been experienced
for the pavement layers.

Delay in obtaining statutory clearances for quarries and the operation of stone crushers due to
Supreme Court and High Court directives on operation of stone crushers in the State. Contractors
for WEP-3, WEP-4, and WEP-5 have got quarry approval and clearance for establishment of
crushers. In WEP-1, the application for establishment of a crusher has been filed in this regard
PIU-KSHIP official requested District Commissioner, Bangalore to clear the application of the
Contractor which is pending from long time.

Due to insufficient cash inputs from JV partners in WEP-3 and shortage of funds and shortage of
key experienced staff in WEP-5 leads to the slow progress.

In package WEP-3 no proper coordination between JV partners still persists, and no


improvement after several meeting with the Management and PIU KSHIP.

ii) Annuity Contracts: The Project Governing Board (PGB) decided to rejection of bids for not
having Value for Money (VFM). During the June 2013 mission, the Bank suggested reviewing the
DBFMOT Concession, restructuring and rebidding the four annuity packages.
b) Goods: There are nine (9) contracts for Goods to be procured out of which two already procured.
The Disbursement of Goods is delayed mainly due to delay in procurement of services.
c) Services: Out of fifty (50) contracts for Services, nineteen (19) contracts have been signed and
representing 38.0% of the total contracts. All nineteen (19) Contracts are in progress against the
twenty seven (27) planned and the balance eight (8) contracts are under procurement. An amount
of US$ 3.143 million has been disbursed.
1.5 Project Achievements during Reporting Period
a) Component 1:
Works Progress

The financial progress achieved for the second quarter of 2013/14 for the EPC contracts is 4.23%
compared to the programmed 4.13%. The overall financial progress achieved since inception is
40.19% compared to the planned 62.33%.

In WEP-1, the Contractor has completed equivalent length of Section-I (28.90 Kms) and the
Taking over Certificate is pending due to non-submission of as built drawings by the Contractor.

In WEP-5, the section between Km 17+650 to Km 17+750 where there is a court stay have been
resolved.

Procurement

WEP-2B NCB Contract: Procurement process has been completed and the contract awarded to
M/s DRN Infrastructure for US$ 21.75 million (INR 978.74 million). The Contract Agreement is
signed on 6th July 2013.
Page 2 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

For the two (2) Safe Corridor Demonstration Projects, M/s URS Scott Wilson India Pvt. Ltd was
selected for the design/documentation services under single source selection process for an
amount of USD 100,000 (INR 4.5 Million). The NOC obtained from the Bank and Contract
agreement is expected to be signed in the month of October 2013. The draft DPR for SH-20
(Yaragatti-Belgaum) is expected to be finalized by 15 thDecember-2013. The tender notification
by 31st December-2013 for SH-20 project (Belgaum to Yaragatti section).

RFP for preparation of DPR for KRDCL Co-financing: Out of ten (10) bids received five (5) met
the technical evaluation criteria. Among the five (5) bids, M/s Feedback Ventures was the lowest
quoted at USD 404,444 (18.2 INR Million). The contract duration is 12 months and the Contract
Agreement is signed on 24th August 2013. The DPR consultant has submitted inception report
and made a inception presentation along with reconnaissance survey findings on 5 th Sept 2013. It
is proposed to complete Revalidation of components essential for project structuring by
December 2013. R&R survey and land acquisition surveys will also progress concurrently since
these tasks are time consuming.

QM/Quality control capacity enhancement in PWD: Two times EOIs called, no firm has
qualified, and bank suggested KSHIP any known firm with similar services experience and
approve for hiring on Single Source Selection or to invite 3rd call of EOI.

Periodic Road User satisfaction survey-I: Contract awarded to MDRA (Marketing and
Development Research Associates, New Delhi) for USD 95,291.00. The Contract Agreement was
signed on 1st July 2013. The Consultant submitted draft report.

IT/ICT/MIS enhancement services and action plan preparation and implementation: Shortlist
along with RFP submitted to the Bank for clearance.

QM ISO certification (Phase II): The eight (8) consultants submitted the Expression of Interest
(EOI) and evaluation is under process. The shortlisted evaluation report will be submitted to the
bank by 5th December 2013.

Consultancy services for collection of Non-CRN Road condition data for population and
operationalization of Road Information System (RIS) and Payment Management System (PMS):
EOI evaluation completed and evaluation report along with draft RFP shall be sent to Bank by
end of December 2013.

Recruitment of GAAP Consultant: Task to be assigned to Project Management System (PMS)


consultant (M/s. Backend Services as additional scope of services. Additional VO of USD 33333
(INR 1.5 million) issued to the PMS Consultant. KSHIP website under development. Complaint
Handling System (CHS) at UAT stage.

Extended Core Road Network (CRN): Extended Core Road Network report is under
consideration in Government of Karnataka. Issue of Government order is expected by end of
December 2013.

Management of HIV Aids along the Roads: This Consultancy is awarded to Karnataka State Aids
Prevention Society and Agreement signed on 27th March 2013 for USD 34,896 (INR 1.57
Million). The Contract duration is one year. During the first half of the contract period, the
project roads under EPC packages will be covered and in the second half the roads under annuity
packages will be covered.

Page 3 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

An updated Procurement Plan with agreed new activities will be submitted to Bank for No
Objection in November 2013.

Environmental

In all packages except WEP-1 (crusher license awaited). In this regard, PIU KSHIP official
requested the District Commissioner of Bangalore rural, to clear the application of the Contractor
which is pending from long time. In WEP-2B package, identification of quarry and crusher
locations is in progress.

Archeological Department Clearance: Application seeking prior permission from ASI in link
M7B and M7C has been forwarded to the National Monument Authority, New Delhi, with
recommendations by the Department of Kannada and Culture, GOK. Further on 21st May 2013,
KSHIP along with Project Coordinating Consultants attended a meeting in the National
Monument Authority office at New Delhi and Project Coordinating Consultants gave a power
point presentation on each application. The NMA has cleared application pertaining to link M7B.
M7C permission is awaited. NMA is reminded on this issue.

Re-use of Scarified Bitumen: A pilot project has been undertaken in WEP-1 for the re-use of
scarified materials has been identified for re-surfacing using scarified bitumen in WEP-1(Link
67A) package. In this regard a proposal/estimate from KSHIP division of Tumkur of USD 11,044
(INR 0.49 Million) has been approved. Subject to the success of the pilot project, it will be
extended to other packages.

ISO 14001 Service for Operationalising in KPWD: Contract Signed with M/s.Allied Boston
India Pvt.Ltd. New Delhi. The consultants have submitted their Inception Report in February
2013 as per their Task I activity. The Inception Report is accepted by PIU. A three-day training
program from 28th Oct 2013 to 30th Oct 2013 on EMS and internal audit is organized in
Bangalore by the Consultant. All the 14 designated concerned officers have been requested to
attend the training.

Resettlement and Rehabilitation (R&R) and Land Acquisition (LA)

In all the five WEP packages, as many as 313 PAPs were identified and all of them are issued
with Identity Cards. Of them, 170 are commercial squatters and 113 are encroachers. The
commercial squatters have been assisted with shifting allowance, subsistence allowance and
assistance for income generation asset as provided in the Entitlement Matrix and they have been
shifted outside the ROW. The Land acquisition is 99% completed in EPC packages.

Implementation RAP in WAP packages have already been taken up. Joint Verification of affected
structures has been completed in all the packages except the town limits of Shimoga, Shikaripura
and Hangal where 4 lane roads are proposed. A total number of 844 PAPs, consisting of 505
commercial squatters, 60 residential squatters, 271 encroachers and 8 tenants, have been
identified and out of them 519 PAPs (61%) have been issued ID Cards. So far, 137 PAPs
16.23% (83 commercial squatters and 54 encroachers) have received full assistance. Issue of ID
Cards and release of assistance to the remaining PAPs are under. The Land acquisition progress is
slow in Annuity packages (0.51%).

Other

NGOs services extended up to Dec, 2013 and M&E consultant service extended up to 31 st March
2014.
Page 4 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

The internal audit of the PIU-KSHIP and KRDCL accounts for the quarter ending 31 st March
2013 has been completed. The internal auditor is yet to submit the Draft Report to PIU-KSHIP.
Based on Banks comments on Aide Memoire 17th -25th June 2013 regarding internal audit, a
letter has been addressed to the Internal Auditor to submit the pending audit reports and to
comply with the terms of contract.

Vacancy of the position of Assistant Commissioner (Land Acquisition). Appointed two Assistant
Commissioner Post (Land Acquisition) in the month of July 2013.

Page 5 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

1.6 Issues Identified in the Previous Quarter that Still Exist in the Current Quarter
Table 1: Current Problems & Actions
Sl No
Component-1

Current Problems

Action Taken
In the Management meeting held on 22nd May 2013, it was agreed that the
Contractor will infuse at least INR 100 Million of working capital in July
2013 to start improving progress to about 5% per month from
August/September, failing which stringent Contractual measures including
Contract termination could be resorted to.
WEP-2A, WEP-3 WEP-4 and WEP-5 Contractors have established their
quarries and crushers. In WEP-1 the quarry license has been approved and
crusher application submitted to KSPCB for approval. In this regard PIUKSHIP is official requested DC, Bangalore to clear the application of the
Contractor,
The sites have been allotted to 11 families who are eligible. The payment of
compensation is in progress.

Poor co-ordination between JV partners on WEP-3 affecting


progress.

Delay in getting quarry and crusher operation approvals on WEP


Contracts.

Delays in completing compensation on WEP Contracts.

Clearance under Forest (Conservation) Act

KSHIP has complied all conditions except alternate land to be provided by


the DC Shimoga. Land identified, handing over process to forest
department is in progress.

Completion of evaluation and award process for DBFMOT


Annuity.

The Project Governing Board (PGB) decided to rejection of bids for not
having Value for Money (VFM). During the June 2013 mission, the Bank
suggested reviewing the DBFMOT Concession, restructuring and rebidding
the four annuity packages.

Component-1B

Selection of Independent Engineer (IE) for DBFOMT Annuity.

EOIs were Evaluated and a shortlist and RFP submitted to the Bank and the.
Bank had already provided no objection. Further action will depend on the
Govt decision on rebidding the four annuity packages.

Component-3
8

Completion of Staffing for the Road Safety Cell.

GO regarding formation of Road Safety Cell is issued and posting of staff to


the cell is being pursued with Transport Department.

Page 6 of 72

PIU-KSHIP

Sl No

Quarterly Progress Report 2 (1 July to 30 September 2013)

Current Problems

Delay in the starting the SCDP designs.

10

Safe corridor program consultancy services for monitoring and


evaluation

Action Taken
M/s URS Scott Wilson India Pvt. Ltd is selected under single source process
for an amount of USD 100,000 (INR 4.5 Million). NOC obtained from the
Bank and Contract agreement is expected to be signed in the month of
October 2013. The draft DPR for SH-20 (Yaragatti-Belgaum) is expected to
be finalized by 15th December-2013. It is expected to be issued tender
notification by 31st December-2013 for SH-20 project (Belgaum to Yaragatti
section).
The scope of the consultancy is already covered under RSM consultancy
services, already staffs have been mobilized.

11

Clearance for revised D-Code to be obtained from Finance


Department

The proposal for revision of D-Code is in the Finance Department. To be


cleared before 15th December 2013.

12

Submission of disbursement projection.

The estimated disbursement projection for the quarter ended July-Sept 2013
is US $ 5.0 Million. The report has been sent to the Bank in the month of
August 2013.

Component-4

Page 7 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

1.7 Summary of the Main Problems Affecting the Civil work progress:
The package-wise key issues which caused delays in achieving the target values are given below.
WEP-1
Crusher license pending with District Collector. In respect of this, PIU KSHIP official requested
DC, Bangalore to clear the application of the Contractor which is pending from long time.
WEP-2A
Contractor not yet started the crusher production and highway activities as the completion date
for Section-I, is already over and Section-II is on 1st January 2014.
WEP-2B
The completion date of Section-I is 19 th December 2013, still Contractor not yet deployed the
machinery, manpower, not identified the quarry sites.
WEP-3
Shortage of key staff.
Insufficient cash flow from the JV partners adversely impacts work progress.
No proper co-ordination between JV partners.
No motivation or interest towards the work from the Contractor.
Identification of source approval is in progress.
Poor Safety and road maintenance of Diversion roads by the Contractor.
WEP-4
Delay in construction of Major Bridge and Diversion road.
WEP-5
Insufficient Cash flow on site resulting in slow progress.
Shortage of Key staff.

Page 8 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

2.

SUMMARY OF PROJECT ACTIVITIES

2.1 Costs and Bank Loan for Project components


Table 2: Summary of Cost & Bank Loan Amount for Project Components (US$ million)

Component

1 - Road Improvement Works


a) Item-Rate Contracts*

Project
Costs
Including
Contingenc
y
602.6
166

Bank
Loan
Amount

GOK
Financing

Developer
/ Private
Sector
Banks

Contracted
Value

259.8
119.6

197.26
40.03

180.86
0

132.8
132.7

b) DBFOMT Annuity Concession**

436.6

140.2

157.23

180.86

0.1

2 - Highway Financing Modernization


a) TA Services for KRDCL
b) Civil Works under Co-financing Pilot
c) Consultancy Services-NGO &
Environment/Social Audit
3 - Road Safety Improvement
4 - Policy and Institutional
Development
Incremental Operating Costs
Total Project Cost
Front-end Fee
Total Financing Required
Total Cumulative Disbursement till
September

373.9
5
368.9

67.3
4
63.3

60.52
1
59.46

269.18
0
269.18

1.1
1.1
0

0.06

13.8

11

1.98

1.9

11.8

9.4

1.71

0.3

2
1004.1
0.9
1005

1.6
349.1
0.9
350

0.45
261.92
0
261.92

0
450.04
0
450.04

1.6
137.7
0.9
138.6

Balance Loan (Bank Loan Amount)

41.511
308.489

Note- Exchange rate Rs. 45 per dollar as per Loan agreement.


*

The amount US$ 132.8 million is exclusive of WEP-2 terminated amount of US$ 27.12 million (INR
1220.2million). However, the awarded WEP-2A Contract amount of US$ 20.5.million (INR 925.4)
and WEP-2B Contract amount of US$ 21.75 million is included.

Initially five (5) Works Packages had been contracted in Mar, 2011. Package WEP-2 was terminated
in Nov, 2012 and re-procured in two packages WEP-2A and WEP-2B. Package WEP-2A was
procured and a Contract signed in Feb, 2013. Package WEP2B is also procured and the Contract is
signed on 6th July 2013. The total contracted value is inclusive of civil works of WEP-1, WEP-2A,
WEP-2B, WEP-3, WEP-4, WEP-5, CSC, NGO and EMP services.

** Bids evaluated and placed before Project Governing Board recommending rejection of bids for not
having VFM. Bank suggested reviewing the DBFMOT Concession, restructuring and rebidding for
the four annuity packages.

Page 9 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

2.2

Overall Project Implementation Status (Progress and Issues) by


Component and Contract

a) Component 1: Road Improvement Works


Component 1 comprises two parts, namely Civil Works under traditional Item-Rate Contracts (EPC
Contracts, 266 km) and Civil Works under Design Build Finance Operate Maintain and Transfer
(DBFOMT) Annuity Concessions (565 km).
i) Component 1A: EPC Works
Out of the five (5) EPC contracts, WEP-2 was terminated in Nov, 2012 due to consistently poor
performance of the Contractor. After the termination of WEP-2, the works have been split into two NCB
packages namely WEP-2A (Haveri-Hanagal) of length 31.784Km (Link T8) and WEP-2B (Hanagal to
Tadasa) of length 43.459Km (Link M7D) in order to save construction time. WEP-2A has been awarded
to M/s DRN Infrastructure for an amount of US$20.5.million (INR 925.4) and the Contract Agreement
were signed on 22nd Feb, 2013. The Contract Duration is 21 months. WEP-2B has also been tendered
under NCB and Contract was awarded to M/s DRN Infrastructure for an amount of US$ 21.75 million.
The Bank NOC has been received and the Contract was signed on 6 th July 2013.
For the six (6) EPC contracts including WEP-2A and WEP-2B, the physical progress achieved for the
Second Quarter of 2013/14 is 4.77% against the programed 3.50%. The overall physical progress
achieved since inception is 49.30% against the programmed 65.82%. The 12.63km (both lanes) of road
was blacktopped in the present quarter against a programmed length of 10.13 km. Total 114.33km (both
lanes) has been completed against a programmed length of 145.00 km.
The package-wise civil works progress is summarized in the Table below.

Page 10 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Upgradation
of Road
From
Tinthini-

*13-May13
52.4

31.78

43.45

36

73.8

M/s Lanco
Infratech Ltd.

12Apr11

M/s DRN
Infrastructure,
Engineers &
Contractor

22Feb13

M/s DRN
Infrastructure,
Engineers &
Contractor

6Jul13

M/s RVCPLRIDL JV

7Apr11

M/s Patel
Engineering
Ltd.

31Mar11

21.83

20.56

28.90

28.90

Actual, %

Overall
Financial
Progress

Planned, %

Actual, %

Financial
Progress in
Current
Quarter

Planned, %

Actual, %

Overall
Physical
Progress

Planned, %

Actual, %

Physical
Progress in
Current
Quarter

Planned, %

Advance
Payment,
US$ Million

Duration Elapsed, Months

Achieved Length, (SectionI/Section-II)Km

Planned Length, (SectionI/Section-II)Km

Completion Date (SectionI/Section-II), Km

Milestones (Section-I / SectionII)


Date of Commencement

Contract Value,
US$ Million

Contract Signing Date

Upgradation
of Road
from
DharwadSaundatti

Name of Contractors

Description of Contract

WEP-2B

Upgradation
of Road
From
Hanagal to
Tadasa

Length, Km

Packages
WEP-1
WEP-2A

Upgradation
of Road
From
Haveri
(NH-4) to
Hanagal

WEP-4

Upgradation
of Road
from
Hoskote to
Chintamani
Bypass)

WEP-3

Table 3: EPC Civil Work Progress

13-Aug-11
12-Feb-14

23.50

2.04

1-Aug-13

3.00

1-Jan-14

7.00

19-Dec-13

4.00

19-May-14

12.00

*24-Oct-12

20

7.63

11

22-Feb-13

1.09

9.29

4.28

66.17

61.16

10.14

5.34

54.64

49.83

1.03

1.59

1.62

1.59

1.62

Major
Issues
that led to
Delays

Insufficient
cash flow.
Crusher
license
pending
with
District
Collector

21.75

18.76

28-Jul-11

35.71

13-Aug-11

27-Mar-13

18.5

*12-June-13

32.45

32.45

0.94

10.35

3.78

38.41

33.11

12.63

2.56

40.4

28.34

Insufficient
cash flow
from JV
partners

3.43

8.23

10.47

62.95

60.55

8.9

7.3

55.41

48.24

Page 11 of 72

Actual, %

23.83

Advance
Payment,

Duration Elapsed, Months

Achieved Length, (SectionI/Section-II)Km

Planned Length, (SectionI/Section-II)Km


28.63

Planned, %

*18-Apr-13

Actual, %

19-Jul-11

Planned, %

13.68

Actual, %

31Mar11

Overall
Financial
Progress

Planned, %

M/s SRKKCl JV

7.86

Financial
Progress in
Current
Quarter

Actual, %

28.63

41.35

Overall
Physical
Progress

Planned, %

Upgradation
of Road
From
ChowdapurGulbarga

12-Aug-14

Physical
Progress in
Current
Quarter

US$ Million

WEP-5

Kalmala

Completion Date (SectionI/Section-II), Km

Milestones (Section-I / SectionII)


Date of Commencement

Contract Value,
US$ Million

Contract Signing Date

Name of Contractors

Quarterly Progress Report 2 (1 July to 30 September 2013)

Length, Km

Description of Contract

Packages

PIU-KSHIP

1.37

7.60

5.32

94.74

91.71

11.19

4.35

78.12

72.91

Major
Issues
that led to
Delays

*Note: EOT approved for Section-I for packages WEP-1, 3, 4, and 5 for 3 months.

Page 12 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

WEP-1: In package WEP-1 the Contractor was able to finish 7.94Km of BC against the 10.14Km in
current quarter and cumulative length completed is 30.94Km against the 33.14 Km till the end of this
quarter, which is 93.36% to the targeted value. Completed 2 culverts against planned 4 nos and overall
35 culverts completed against 55 and 1 Major Bridge completed against planned 1 no and overall 8
Major Bridges completed against the 17 nos till the end of this quarter.
The Contractor has achieved 5.34%financial progress for this quarter against the planned 10.14%, the
cumulative financial progress is 49.83% against the planned 54.64% till the end of this quarter.
Contractor is lagging 4.81 % behind the schedule. The Contractor already completed equivalent length of
Section-I and requested for taking over certificate and Taking Over Certificate is pending due to nonsubmission of As Built drawings by the Contractor. The Contractor has to complete the Section-II length
(23.50Km) by end of 12th Feb 2014, based on the Contractor past performance, the Contractor seems to
be complete the Section-II within scheduled target date. PIUKSHIP cleared all pending IPCs till August
2013 and September month IPC is under review. All encumbrances are cleared in Section-I & Section-II.
All design issues have been resolved. Work zone safety arrangements and traffic management measures
have been taken care and no accidents reported in this quarter.
WEP-2A: In package WEP-2A, the Contractor completed 20 nos cross drainage structures against
planned 38 nos. The MOEF cleared the operation of quarry which was pending from the last quarter. The
Contractor has to start the crusher production and highway activities as the completion date of Section-I
(3.00Km) is 19th December 2013. On 16th July Contractor submitted EOT proposal for 8 months due to
delay in approval of his crusher and quarry license; this was rejected by the Engineer. The Mobilization
and equipment advance paid to the Contractor. The Contractor has achieved 1.62%financial progress for
this quarter against the planned 1.59%.
WEP-2B: The contract is awarded to M/s DRN Infrastructure Pvt. Ltd and the Contract is agreement was
signed on 6th July 2013. Letter to proceed with the works was issued on 20 th July 2013 and site was
handed over on 20th July 2013. Identification of quarry and borrow areas is in progress.
WEP-3: In package WEP-3, the progress is poor due to lack of proper planning and inadequate
resources. In this quarter there was no progress on construction of BC layer, the Contractor was able to
finish 7.63 Km against the 36.00Km which is 21.19% to the targeted value. No progress on construction
of culverts in current quarter and overall 27 culverts completed against 41 nos. The Contractor finished
the 2 Major Bridges in current quarter against the total 8 nos.
The Contractor has achieved 2.56% of financial progress for this quarter against the planned 12.63%. The
cumulative financial progress is 28.34% against the planned 40.40% till the end of this quarter. Three
month EOT has been given by the Engineer. The original completion date of Section -I (20.00 Km) was
27th July 2012 and the revised completion date of Section -I is 24 th October 2012. The contract
completion date for Section -II has also expired on 27 th March 2013. The contractor has to achieve
balance length of Section -I along with work on Section -II. Proper planning must be done with additional
resources mobilization. The JV partner M/s RIDL is not working and there is no coordination with Lead
partner M/s RVCPL. This contract is being closely monitored by PIUKSHIP holding periodic
management meetings. Further Contractor proposed new km-wise Section-I from Km 2+500 to Km
22+500 and Section-II from Km 22+500 to Km 38+500 with the completion date as December 2013 for
Section-I and June 2014 for Section-II, the Engineer instructed Contractor to submit the revised work
Programme. All encumbrances cleared (Shifting of Electric Poles & Tree felling work completed). The
PIU KSHIP cleared July month IPC, August and September months IPCs not submitted by the
Contractor.

Page 13 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

WEP-4: The performance of this contract is better although the Contractor is not fully meeting the
targeted quantities. The contractor is able to finish 17.31 Km of BC against the 13.68 Km in the current
quarter and cumulative length completed is 40.31 Km against the 44.58 Km till the end of this quarter
which is 90.40% to the targeted value. Completed 16 culverts against planned 15 nos and overall 72
culverts completed against 110 nos. Eleven (11) Major Bridges completed against planned 4 nos and
total 24 major bridges completed against the total 38 nos till the end of this quarter.
The Contractor has achieved 7.3%financial progress for this quarter against the planned 8.90%, the
cumulative financial progress is 48.24% against the planned 55.41% till the end of this quarter.
Contractor is lagging 7.17 % behind the schedule. The Contractor already completed equivalent length of
Section -I, traffic signs & road marking works are pending in Section -I. As per the contract, actual date
for completion of Section - I (32.45 Km) is 12 th March 2013. An EOT of three months with revised
completion date of 12th June 2013 has been granted for Section -I. PIU KSHIP cleared Contractor IPCs
of July, August 2013 and September month IPC is under preparation. The two quarries and two crusher
licenses has been approved by KSPCB. All encumbrances are cleared in Section -I & Section -II. All
design issues have been resolved. Work zone safety arrangements and traffic management measures have
been taken care and no accidents reported in this quarter.
WEP-5: The progress of this package is very slow, running 5 months behind the schedule. The contractor
was able to finish 6.53 Km of BC against the 11.33 Km in the current quarter and cumulative length
completed is 23.83 Km against the planned 28.63 Km till the end of this quarter which is 83.23% to the
targeted value. There is no progress on construction of Culverts and finished 1 Major Bridge work in
current quarter. So for thirty eight (38) culverts out of forty (40) have been completed. Five (5) bridges
out of seven (7) have been completed.
The Contractor has achieved 4.35%financial progress for this quarter against the planned 11.19%. The
cumulative financial progress 72.91% against the planned 78.12% till the end of this quarter and
Contractor is lagging 5.21 % behind the schedule. As per the Contract the completion period of the
project ends on 18th January 2013 and Engineer granted an EOT of three months with revised completion
date is 18th April 2013. The contractor has applied for a further EOT up to October 2013 which is not
accepted by the Engineer. Contractor further claimed the EOT up to December 2013, due to delay in
approval of quarry licenses, which was rejected by the Engineer.
The Contractor has not submitted IPC from April to August 2013 and recently submitted IPCs are under
review. The quarry and crusher licenses have been approved. All obstructions cleared. Work zone safety
arrangements and traffic management measures have been taken care in this quarter and no accidents
reported in this quarter.
Environmental Management
Environmental Clearance has been obtained by KSHIP for project roads.
Environmental clearances obtained by KSHIP Contractors for all WEP Packages, except WEP-2A,
where contractor is yet to identify locations for establishing camp and crusher installations
Environmental Management Plan (EMP) implementation is satisfactory and covers enhancement of
water bodies, construction of noise barriers, borrow area management, construction materials
management etc.
Independent Environment Pollution Monitoring (air quality, water quality, noise levels, and soil
quality) for WEP packages has been carried out as per the EMP during June-July 2013. The results are
satisfactory.
Page 14 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

R&R and Land Acquisition (LA) Status: The status of R&R and LA for EPC Packages is given in the
table below.
Table 4: R&R and LA Status - EPC Packages
Description

ID Card
Issued, %

No of PAPs
received all
benefits, %

Subsidence
& Shifting
allowance
paid, %

Non-Title Holders

Completed

Completed

Completed

Title Holders

99

12.5

R&R Status

LA Status

R&R Completed
in all EPC
packages except
13 families in
WEP-2

The total Land


Acquisition
completed is 99%

ii) Component 1B: Annuity Works


The Project Governing Board (PGB) decided to rejection of bids for not having Value for Money (VFM).
During the June 2013 mission, the Bank suggested reviewing the DBFMOT Concession, restructuring
and rebidding the four annuity packages.
Environmental Management
Environmental clearances obtained by KSHIP for all four (4) Annuity package roads.
Environmental Management Plan (EMP) covers enhancement of water bodies, construction of noise
barriers, construction materials management etc. Above measures except noise barriers which have
already been executed by KSHIP, are part of the civil works under the Annuity concessions.
R&R and Land Acquisition (LA) Status: The status of R&R and LA for EPC Packages are given in the
table below.
Table 5: R&R and LA Status-Annuity Packages
Descriptio
n

Non-Title
Holders

ID Card Issued, %

Out of the 844 PAPs


identified in the WAP
packages, 519 PAPs
(61.49%) have been
issued ID cards. Issue
of ID cards to the
remaining PAPs is in
progress.

No of
PAPs
received
all
benefits,
%

16.70

Subside
nce &
Shifting
allowan
ce paid,
%

70.51

R&R Status

LA Status

The R&R work is


progressing, Joint
verification completed in
all links, except town limit
of Shimoga, Shikaripura
and Hanagal where four
lanes is proposed. Out of
362 commercial squatters
36 squatters are assisted
with shifting and
subsidence allowance, 83
commercial squatters are
assisted with IGA, 54
encroachers have received
reconstruction cost.
Release of assistance to
other is in progress.

Progress is slow due


to delay in
conducting of price
fixation meetings.

Page 15 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

The Independent Engineer (IE)


The Transaction Advisory Consultant has assisted PIU KSHIP in procurement process of IE for the
Annuity packages. EOIs were Evaluated and a shortlist and RFP submitted to the Bank on 27 th September
2012, and the Bank had already provided no objection. However, further action will be subject to the
Government decision on rebidding the four Annuity Contracts.

b) Component 2: Highway Financing Modernization


The details of Contract status for roads developed under KRDCL given below.
The DPR preparation of roads developed under co-financing Contract awarded to M/s Feedback
Ventures and Contract agreement signed on 24th of August 2013. The DPR consultants have been
mobilized on 22nd Aug 2013. The DPR consultant has submitted inception report and made a inception
presentation along with reconnaissance survey findings on 5 th Sept 2013. It is proposed to complete
Revalidation of components essential for project structuring by end of December 2013. R&R survey
and land acquisition surveys will also progress concurrently since these tasks are time consuming.
Strategic presentation has been prepared by FPTA and has been presented to MD, KRDCL in
September 2013. FPTA Consultants submitted the White Paper on Financial policy and White Paper
will be finalized after meeting with Finance department of GoK.
KRDCL OMT roads, tender notification was issued on 28 th Feb 2013. The RFP issued to bidders and
last date for submission of bids is on 17 th June 2013. There is no response received from bidders,
decided to modify the bid document and invite tender in second call.

c) Component 3: Road Safety Improvement


Road safety capacity building consultants M/s Vic Roads have been mobilized. The inception stage
almost completed, awaiting FD/TD outcome on RSC establishment to finalize Inception Report.
Safe Corridor Demonstration Program (SCDP): This covers road safety pilot of two corridors,
Maddur to Mysore (53.8km) and Belgaum to Yaragatti (61.85km section). CDTA Consultant has
finalized the iRAP recommendations on road safety measures for these roads. M/s URS Scott Wilson
(Project coordinating consultants) is selected under single source lump sum contract, Contract amount is
USD 100,000, and NOC from Bank is received. The Contract Agreement is expected to be signed in the
month of October-2013. The draft DPR for SH-20 (Yaragatti-Belgaum) is expected to be finalized by
15th December-2013. It is expected to be issued tender notification by 31 st December-2013 for SH-20
project (Belgaum to Yaragatti section).
Capacity Building for Lead Agency: Contract Road safety capacity building consultants M/s Vic
Roads have been mobilized. The inception report was reviewed by all the stake holder departments and
accepted. The consultant is submitting the final Inception Report soon. The consultant will cover other
procurement for goods and services in co- ordination with the respective stake holder departments.
Road Safety Cell: GO regarding formation of Road Safety Cell is issued and posting of staff to the cell
is being pursued with Transport Department.

Page 16 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

d) Component 4: Road Sector Policy and Institutional Development


Table 6: Road Sector Policy & Institutional Development
Sl
No
1
2

Items
D-Code Clearance
Formalize the Core
Road Network

IT-ICT

PWD-wide QM /ISO
certification program

Road User Satisfaction


Surveys (RUSS)

GAAP Implementation
Support

Black-Spot
Rectification program

Status
Awaiting approval of the GOK. To be cleared before 15th December 2013.
Proposal is under consideration of Government. Issue of Government
order is expected by end of December 2013.
Shortlist along with RFP submitted to Bank for no objection. Bank
clearance is awaited.
Second call request for Expression of Interest (REOI) was advertised on
1st of Feb 2013 and only two firms were shortlisted. Further Bank during
its mission to KSHIP in the month of June 2013 instructed to issue letters
to the various interested consultants who have ISO operationalizing
background and experiences. Thus letters with REOI have been sent to
various consultants. Eight (8) consultants submitted the Expression of
Interest (EOI) and evaluation is under process. The shortlisted evaluation
report will be submitted to the bank by 5th December 2013.
Contract awarded to MDRA (Marketing and Development Research
Associates New Delhi). Contract amount is USD 95291.00 and Contract
agreement signed on 1st July 2013.
Task to be assigned to Project Management System (PMS) consultant
(M/s. Backend Services as additional scope of services. Additional VO of
USD 33333 (INR 1.5 million) issued to the PMS Consultant. KSHIP
website under development. Complaint Handling System (CHS) at UAT
stage.
It is proposed to improve 35+33 Black spots on SH-23 and SH-25 by
KSHIP for 2013 and 2014. Approval of Steering committee is accorded in
the 59th Steering committee on 16th August 2013.

Page 17 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

2.3

Summary of Procurement Packages for Works, Goods and Services


Table 7: Summary of Procurement for Works, Goods & Services

Sl No
1
2

Procurement
Package
Works

Total
Nos
10*

Contracts
Completed
No's
-Nil-

Contracts
Under Progress
No's
5

Contracts Not Yet


Awarded
No's
5

Services

50**

19

23

3
Goods
9
2
-Nil7
Note:
* WEP-2 Contract is terminated and WEP-2 package is split in to two packages, WEP-2A & WEP-2B.
WEP-2A & WEP-2B procurement is completed.
** 4 procurement packages for services (Procurement of IDSAP consultant, Monitoring consultants for
BOT-toll O&M packages under KRDCL, Consultancy services for statutory audit, KRDCL and
Consultancy services for procurement and training of automated traffic count equipment) have been
dropped.

2.4

Loan Status
Table 8: Loan Status

Loan
Amount in
Million US$

Loan
Effective
Date

Loan
Closing
Date

Cumulative
Disbursement
amount up to June
2013, in US$
million

Cumulative
Disbursement
amount up to
September 2013,
in US$ million

Cumulative
Disbursement
Planned during
Year 2013-14, in
US$ million

350

1, June
2011

31st ,
December
2016

38.209

41.511

167
(As per PAD)

The reasons for slow disbursement are mainly due to termination of WEP-2 contractor M/S Roman
Tarmat Ltd, pending finalization of DBFOMT packages

2.5

Disbursement Claims
Table 9: Disbursement Claims
Projects Overall Disbursement

Up to September 2013
(Million US$)

Planned
167
Actual
41.511
Percentage (%)
11.90%
Note: Actual Disbursement includes Front-End Fee and Advance

2.6

Audit of Project Accounts for the Financial Year 2013-14

The Project has submitted the Interim Unaudited Financial Report (IUFR) for the Quarter ended
30th September 2013 with a claim of US$ 4.778 million..

Page 18 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

2.7

The Audit Report for the financial year 2012-13 has already submitted to Bank during September
2013.

Bank Missions & Ratings

The World Bank mission last visited Karnataka for the third Implementation Support Mission, during the
period of 17th -22nd June 2013. The Key Performance Ratings by the Bank for the Project are as follows:
Table 10: Bank Missions and Ratings
Key Project Data
Board Date
Signing Date
Effectiveness Date
Closing Date

March 24, 2011


May 30, 2011
July 19, 2011
December 31, 2016

Project Age
Disbursement

13 months
US$20.6 M (5.8 % of
Loan)
2 (Financial Management
and Safeguard Compliance)

Flag Risks

Key Performance Rating


Last
Development Objective (DO)
S
Implementation Progress
MS
Procurement Compliance
MS
Financial
Management
MS
Compliance
Safeguards compliance
MU
Legal Covenants Compliance
S
Project Management

Now
MU
MU
MS
S
MU
MU
MU

Counterpart Fund
S
S
M&E
S
MS
S = satisfactory; MS = moderately satisfactory; MU = moderately unsatisfactory; U = unsatisfactory

Page 19 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

2.8

Major Issues and Proposed Resolutions for each Component


Table 11: Major Issues and Proposed Resolutions
Major Issues

Accelerating of work execution on ItemRate Contracts (WEP-3 ) to INR 5


crores/month

DBFOMT Annuity

KRDCL OMT roads

Proposed Resolution

Time Line

In the management meeting held on 22nd


May 2013, it was agreed that the Contractor
will infuse at least INR 100 Million of
working capital in July 2013 to start
improving progress to about 5% per month
from August/September, failing which
stringent Contractual measures including
Contract termination could be resorted to.

31-Dec-13

Reviewing the DBFMOT Concession,


restructuring and rebidding for four annuity
contracts.
Tender notification was issued on 28th Feb
2013. The RFP issued to bidders and last
date for submission of bids is on 17 th June
2013. There is no response received from
bidders, decided to modify the bid
document and invite tender in second call.

Developed alternate sites have been


provided to the 11 PAPs. Construction cost
in respect of 11 PAPs has been released and
Develop and allot alternative sites with placed with the Executive Engineer,
construction grants and moving allowance Shimoga with instruction to release the
to 14 families in WEP-2
same in installments to the PAPs based on
construction progress.
Release of
compensation and other R&R assistance is
under process.
Joint Verification has been conducted in all
packages except in the town limits of
Shimoga, Shikaripura and Hangal. 844
PAPs (505 commercial squatters, 60
Issue of ID cards to eligible Non-Title
residential squatters 8 tenants and 271
Holders in Annuity packages
encroachers) have been identified and out of
them 544 (64.45%) have been issued ID
cards. Issue of ID cards to the remaining
PAPs is in progress.
Staffing completion for the Road safety
Cell as per the agreed covenant

GO regarding formation of Road Safety Cell


is issued and posting of staff to the cell is
being pursued with Transport Department.

31-Dec-13

31-Dec-13

31-Dec-13

31-Dec-13

31-Dec-13

Page 20 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

Major Issues

Identify and Procure Certifying agency for


ISO 14001 certification

Design the RSCDP program and the M &


E framework and start commencing the
bidding for civil works

Proposed Resolution
Bank during its mission to KSHIP in the
month of June 2013, instructed to issue
letters to the various interested consultants
who have ISO operationalizing background
and experiences, the letters along with EOI
have been sent to various consultants. The
last date for receiving EOI is 31st August
2013. Eight (8) consultants submitted the
Expression of Interest (EOI) and evaluation
is under process. The shortlisted evaluation
report will be submitted to the bank by 5th
December 2013.
For the two (2) Safe Corridor
Demonstration Project, M/s URS Scott
Wilson India Pvt. Ltd is selected under
single source process for an amount of USD
100,000 (INR 4.5 Million). The NOC from
Bank is received. The Contract Agreement
is expected to be signed in the month of
October-2013. The draft DPR for SH-20
(Yaragatti-Belgaum) is expected to be
finalized by 15th December-2013. It is
expected to be issued tender notification by
31st December-2013 for SH-20 project
(Belgaum to Yaragatti section).

Revised D-Code clearance to be obtained


from Finance Department

Awaiting approval of the GOK. To be


cleared by 15th December 2013.

Submission of Quarterly Disbursement


Projection for FY 14 by July 15,2013

The disbursement projection for the quarter


ended July to Sept 2013 was estimated at
US $ 5.0 Million. The report sent to the
Bank during August 2013.

Time Line

5-Dec-13

2-Dec-13

15-Dec-13

Page 21 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

2.9

Project Performance Indicators

For details on project performance indicators please refer Table-48 of Chapter-11.

2.10 Actions Expected For Next Quarterly Period


Table 12: Action expected for Next Quarterly Period
Activity
Responsibly
Formalize the Core Road
PWD
Network
Consultancy
services
for
Collection of Non-CRN Road
condition data for Population and
PWD
operationalisation
of
Road
information
system
and
pavement management system.
Clearance under Forest
(Conservation) Act

PIU

PWD-wide QM /ISO
certification program

PIU

EOI/TOR of OMT concession


issued for KSHIP-I and KRDCL
roads (following government
approval)
Consultancy services and
training for traffic police (Also
includes Safe corridor program capacity building for police
enforcement)
Safe corridor program consultancy services for
development of safety campaigns
Safe corridor program consultancy services for capacity
building for post impact care
Safe corridor program
consultancy services for
monitoring and evaluation

KRDCL

Timeline
A final proposal is under Government and
decision expected by end of December 2013.
EOI short listing completed. RFP is under
preparation and will be submitted to WB
shortly.
KSHIP has complied all conditions except
alternate land to be provided by the DC
Shimoga. Land identified. Handing over
process to forest department is in progress.
In second call request for Expression of
Interest (EOI) was advertised on 1st of Feb
2013 and only two firms were shortlisted.
Further Bank during its last mission to KSHIP
in June 2013 instructed to issue letters to the
various interested consultants who have ISO
operationalizing background and experiences.
The letters along with EOI have been sent to
various consultants. Eight (8) consultants
submitted the Expression of Interest (EOI) and
evaluation is under process. The shortlisted
evaluation report will be submitted to the bank
by 5th December 2013.
KRDCL OMT roads, tender notification was
issued on 28th Feb 2013. The RFP issued to
bidders and last date for submission of bids is
on 17th June 2013. There is no response
received from bidders, decided to modify the
bid document and invite tender in second call.

RSM consultant is taking up procurement of


services and goods under road safety
TRSC/POLICE/PIU component in coordination with all stake
holder departments under road safety cell,
appropriate VO has to be approved in
consultation with WB.
PIU/RSM-TA
PIU/KSHRDP
PIU/TRSC/RSMTA

Page 22 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

Activity
Consultancy services and
software development for Traffic
Incident Management System
(TIMS)
Road safety consultant for
DBFOMT (Annuity) contracts(Road Safety Audit)

Responsibly
PIU/TRSC/RSMTA
PIU

Delay in the starting the SCDP


designs and the Monitoring and
Evaluation (M&E) framework,
and thus the procurement for
civil works.

Selection of TA for enhanced


PWD core skills training
Suite(Conducting Training)
Appointment of Project
Management Consultancy
(PMC)

Timeline

PIU

RFP and shortlist of consultant is ready.


Further process will be undertaken on decision
of award of DBFOMT Annuity Contract.
M/s URS Scott Wilson India Pvt. Ltd is
selected under single source process for an
amount of USD 100,000 (INR 4.5 Million).
The NOC from Bank is received. The Contract
Agreement is expected to be signed in the
month of October-2013. The draft DPR for
SH-20 (Yaragatti-Belgaum) is expected to be
finalized by 15th December-2013. It is
expected to be issued tender notification by
31st December-2013 for SH-20 project
(Belgaum to Yaragatti section).

PIU/PWD

To be finalized in discussion with the Bank.

PIU

Draft TOR is prepared and will be submitted


by 30th December 2013.

Page 23 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

3.

INTRODUCTION

3.1

Project Background

The Karnataka State Highways Improvement Project (KSHIP) is an initiative of the Public Works
Department (PWD) of the Government of Karnataka (GOK) for improvement of the road network of the
State. Previously, the improvement of 2,414 km of State Highways (SH) and Major District Roads
(MDR) in Karnataka was completed under KSHIP-I with World Bank (WB) assistance. Following on
from the success of KSHIP-I, a further 3,414 km of SHs roads have been prepared for implementation
under KSHIP-II. The Detailed Project Report (DPR) was completed by the Consultant (Scott Wilson) in
December 2009.
The GOK through Government of India (GOI) has obtained a loan (signed on 30 May 2011) from the
International Bank for Reconstruction & Development (IBRD) as financial assistance towards the
implementation of KSHIP-II. Key references of the Loan are given below.
Financing Agency
Loan no.
Project Number
Loan Signing Date
Effective Date
Closing Date
Total Loan Amount

IBRD
8022 IN
P107649
30th May 2011
19 July 2011
31 December 2016
US$ 350 million

The financing plan amounts to US$ 1,005 million comprising US$ 155 million by GOK, US$ 500
million by private sector developers, and US$ 350 million by IBRD.
The IBRD assistance covers the following four components.

Component 1: Road Improvement Works (Total Cost: US$603 million; IBRD: US$260 million;
GOK: US$94 million; Developer: US$249 million). This component will support capital
improvement and maintenance works of selected priority Core Road Network through a combination
of traditional Item Rate contracts and PPP concessions.

Component 2: Highway Financing Modernization (Total Cost: US$374 million; IBRD: US$67
million; GOK: US$56 million; Developers/Financial Institutions: US$251 million). This component
will assist KRDCL in implementing the concept of co-financing with private financial institutions
through technical assistance and pilot transactions.

Component 3: Road Safety Improvement (Total Cost: US$14 million; IBRD: US$11 million; GOK:
US$3 million). This component will assist the GOK to respond to the growing road safety problems
in Karnataka with comprehensive strategic and institutional measures, consistent with the main
thrusts of the 2007 Sundar Committee report and the findings of the road safety management
capacity review.

Component 4: Road Sector Policy and Institutional Development (Total Cost: US$11.8 million;
IBRD: US$9.44 million; GOK: US$2.36 million).This component will support implementation of a
Page 24 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

new medium-term Institutional Development and Strengthening Action Plan (IDSAP) for the period
2010-2016.
The PWD has established a Project Implementation Unit (PIU) to implement three of the four project
components, namely Components 1, 3 and 4. The Karnataka Road Development Corporation Limited
(KRDCL) using its main organizational setup is responsible for implementing Component 2.
This Quarterly Progress Report is submitted to the Bank as per the reporting requirements under IBRD
assistance which call for quarterly progress reports covering the physical and financial progress for
project components to be submitted by the PIU-KSHIP. The Report, which has been reviewed by PIUKSHIP, is prepared by the Project Coordinating Consultant (PCC), URS Scott Wilson, based on PCC
activities and necessary inputs by PIU-KSHIP.

3.2

Project Data
Table 13: Project Data

Project Data
Project Title:
Project Number:
Project Report Number:
Report Start Date:
Report End Date:
Exchange Rate (Local to
US$)
Grant
Original Grant Amount:
Revised Grant Amount:
Bank Board Approval Date:
Grant Signing Date:
Effectiveness Date:
Expected Date of Completion:
Original Closing Date:
Revised Closing Date:
Project Funding

Karnataka State Highways Improvement Project-II


P107649
1/6/2011
30/12/2012
45
US$350 million
24/03/2011
30/5/2011
19/7/2011
31/12/2016

Institution
Government Contribution:
Co-Financing:
Missions
During the Reporting Period:
Next Expected Mission:
Bank Contact
Task Team Leader
Transport Specialist
Sr. Transport Specialist

GOI/GOK

Amount
US$ 155 million (GOI/GOK)
US$ 500 million
(Developers/ Financial Institutions)
US$ 350 million

Third Implementation Support Mission: June 17-22, 2013


December 2013
Name
Email
Phone/Fax
+1-202 458 5630
Dr. Binyam Reja
Breja@worldbank.org
Radia Benamghar
rbenamghar@worldbank.org
abandyopadhyay@worldbank +91-11-49247768
Arnab
+91-11-49247643
Bandyopadhyay
.org

Page 25 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

Procurement

ArunKolsur

akolsur@worldbank.org

+91-11-4363 6629
+91-11-4363 6651

Sr. Financial Management


Specialist

S. Krishnamurthy

skrishnamurthy@worldbank.o
rg

+91-11-41479605
+91-11-24652230

Implementing Agency
Name of Executing Agency:
Name of Implementation
Agency:

PWD, Government of Karnataka

Address:

Project Implementation Unit, KSHIP, PWD Offices, Annexe Building,


KR Circle, Bangalore - 560 001

Project Management
Contact Person:
Phone/Fax:
Email:
Executing Agency

Mr Ramesh N.S, Project Director, PIU-KSHIP


Phone: 91-80-22226262. Fax: 91-80-22229666
piukship@gmail.com

Contact Person:
Phone/Fax:
Email:
Address:

KSHIP & KRDCL

Mr E. Venkataih, Principal Secretary, Public Works Ports& Inland


Water Transport Department
Phone: 91-80-22251449/22034912. Fax: 91-80-22353988
prs-pwd@karnataka.gov.in
Vikasa Soudha, Bangalore

Page 26 of 72

PIU-KSHIP

4.

Quarterly Progress Report 2 (1 July to 30 September 2013)

DETAILED PROJECT IMPLEMENTATION/PROGRESS BY COMPONENT AND CONTRACT

4.1

WB-EPC Packages

The WB-EPC packages, all of which have been awarded and where works are in progress, are listed in the table below.
Table 14: Civil Work Progress

Contract
Name

WEP-1

WEP-2A

WEP-2B

WEP-3

WEP-4

Contract No

KSHIPII/STG1/ICB/WEP-1
(Hoskote to
Chinthamani Bypass)

KSHIPII/STG1/NCB/WEP2A (Haveri (NH-4) to


Hanagal )

KSHIPII/STG1/NCB/WEP2B (Hanagal (NH-4)


to Tadasa )

KSHIPII/STG1/ICB/WEP-3
(Dharwad-Saundatti)

KSHIPII/STG1/ICB/WEP-4
(Tinthini-Kalmala)

Proc
Method

ICB

NCB

NCB

ICB

ICB

Signing
Date

12th Apr
2011

22nd
Feb
2013

6th July
2013

07th Apr
2011

31st Mar
2011

Contract
Amount
US$
Million

21.83

20.56

21.75

18.76

35.71

Length
(Km)

Jan-Mar

Apr-Jun

July-Sept

Planned

21.47

19.3

9.29

66.17

28.69

10.14

54.64

Actual

11.24

9.89

4.28

61.16

8.51

5.34

49.83

Difference

10.23

9.41

5.01

5.01

20.18

4.80

4.81

Planned

12.58

13.59

1.59

1.59

Actual

1.62

1.62

Difference

12.58

13.59

-0.03

-0.03

Planned

Actual

Difference

Planned

23.11

8.48

10.35

38.41

12.63

40.40

Name of the
Contractor

2013-14
Progress

52.4

31.78

43.459

36

73.8

M/s Lanco
Infratech Ltd.

M/s DRN
Infrastructure,
Engineers &
Contractor

M/s DRN
Infrastructure,
Engineers &
Contractor

M/s RVCPLRIDL JV

M/s Patel
Engineering
Ltd.

Overall
Financial
Progress
till end of
30th Sept
2013, %

Overall
Physical
Progress
till end of
30th Sept
2013, %

Quarterly Physical Progress, %

Financial Progress, %
2013-14
Apr-Jun

July-Sept

22.9

Actual

11.58

5.97

3.78

33.11

6.02

2.56

28.34

Difference

11.53

2.51

6.57

5.30

16.88

10.07

12.06

Planned

14.09

11.43

8.23

62.95

12.82

8.90

55.41

Actual

17.67

8.78

10.47

60.55

6.47

7.30

48.24

Difference

-3.58

2.65

-2.24

2.40

6.35

1.60

7.17

Page 27 of 72

PIU-KSHIP

Contract
Name

WEP-5

Quarterly Progress Report 2 (1 July to 30 September 2013)

Contract No

KSHIPII/STG1/ICB/WEP-5
(ChowdapurGulbarga)

Proc
Method

ICB

Signing
Date

31st Mar
2011

Contract
Amount
US$
Million

13.68

Length
(Km)

Apr-Jun

July-Sept

Planned

20.7

7.60

94.74

25.61

11.19

78.12

Actual

16.9

3.96

5.32

91.71

2.29

4.35

72.91

Difference

3.8

-3.96

2.28

3.03

23.32

6.84

5.21

Progress

28.63

July-Sept

Jan-Mar

Name of the
Contractor

M/s SRKKCl JV

Apr-Jun

Overall
Financial
Progress
till end of
30th Sept
2013, %

Overall
Physical
Progress
till end of
30th Sept
2013, %

Quarterly Physical Progress, %


2013-14

Financial Progress, %
2013-14

Page 28 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

4.2

Civil Works Progress

For the five WB-EPC contracts, the civil works physical progress in the quarter in terms of percentage
(based on physical quantities) achieved are summarized below.
WEP-1
The physical progress of pavement layers is found satisfactory. The percentage completion of earthworks
is 23.96%; GSB 61.80%, WMM 61.80%, DBM & BC are 58.52 % against the planned 100% have been
reported.
The overall physical progress achieved till this quarter is 61.16% against planned 66.17 % and overall
financial progress is 49.83% against the planned of 54.64%.
Progress on bridges, culverts & drains is inadequate to meet the scheduled target. Thirty Five (35) cross
drainage structures have been completed out of a total of fifty five (55). Eight (8) bridges have been
completed out of seventeen (17).
Still Crusher license is pending with District Collector. In respect of this, PIU KSHIP official requested
DC, Bangalore to clear the application of the Contractor which is pending from long time
WEP-2A
The contractor has completed twenty (20) cross drainage structures have been completed out of sixty four
(64). The quarry license and crusher license CFE and CFO issued on 24 th May 2013, the Contractor
obtained MOEF clearance for quarry operations. The Contractor not yet started the any earthwork
activities as per Programme.
WEP-2B
Regarding WEP-2B Contract, the contract awarded to M/s DRN Infrastructure, Engineers & Contractor
and Contract signed on 6th July 2013. On 20th July site handing over and notice to proceed with the work
has been issued.
WEP-3
The progress is still lagging far behind the schedule. The physical progress of earthwork is 43.04%, GSB
39.21%, WMM 35.63%, DBM and BC are 25.52% against the planned 100% as reported.
The overall physical progress achieved up to this quarter is 29.90% against planned 100 % and overall
financial progress is 25.64% against the planned of 100%.
Twenty seven (27) culverts have been completed out of a total forty one (41). Two (2) Major Bridges
completed out of total eight (8).
The Contractor has received KSPCB approval for crusher, quarry and HMP plants. The insufficient cash
flow and lack of proper co-ordination between JV partners have resulted in slow progress of this
Contract. Frequent management meetings have been conducted to monitor the work and also achieve
better co-ordination between the JV partners. Further Contractor proposed new km-wise Section-I from
Km 2+500 to Km 22+500 and Section-II from Km 22+500 to Km 38+500 with the completion date as
December 2013 for Section-I and June 2014 for Section-II, the Engineer reviewed the milestone
proposal, work Programme and recommended to the Employer the revised dates for Section-I and
Section-II with possible delay and damages.
Page 29 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

WEP-4
The physical progress of pavement layers is found satisfactory. The physical progress of earthworks is
51.64%, GSB is 58.47%, WMM 56.48% and DBM & BC are 56.62% against the planned 100% as
reported.
The overall physical progress achieved up to this quarter is 60.55% against planned 62.95 % and overall
financial progress is 48.24% against planned of 55.41%.
Progress on bridges, culverts & drains is very slow. Seventy two (72) cross drainage structures out of one
hundred and ten (110) have been completed. Only twenty four (24) bridges have been completed out of
thirty eight (38).
WEP-5
The progress is still lagging far behind the schedule. The Contractor is not performing based on the
Programme which was submitted by him. The physical progress of earthworks is 48.94%; GSB 88.74%,
WMM 85.91%, DBM and BC are 81.76% against the planned 100% as reported.
The overall physical progress achieved up to this quarter is 91.71% against planned 94.74% and overall
financial progress is 72.91% against the planned 78.12%.
There is no progress on construction of CD works and Major Bridge work in current quarter. So far
thirty eight (38) culverts out of forty (40) have been completed. Five (5) bridges out of seven (7) have
been completed.
The key issue in the reporting period is shortage of key and experienced staff and shortage of funds.
As per the Contract project completion date is 18 th January 2013, based on EOT the project completion
date is 18th April 2013. The Contractor submitted the EOT Programme stating the completion time as
October 2013, which is rejected by the Engineer. On 25 th July, the Contractor claimed that, he needed up
to December as the completion date due to delay in approval of licenses, change in scope etc., which was
rejected by Engineer. The Contractor is not performing based on the Programme which was submitted by
him.

Page 30 of 72

PIU-KSHIP

4.3

Quarterly Progress Report 2 (1 July to 30 September 2013)

Major Ongoing Issues

Major ongoing issues in the current quarter are given in table below.
Table 15: Major ongoing Issues

Other LA and R&R related


actions

Component 1A.: Road Improvement Works


(Item-rate contract 6 packages)

Area

Action Required

Responsibi
lity

WEP 3: Supplementary agreement with revised


work program/targets, along with indication of
resources

PIU

WEP 2: Develop and allot alternative sites with


construction grants and moving allowance to 14
families in WEP-2

Action Taken

Due Date

Revised Program obtained from the contractor

Complied

PIU/LAQ

The sites have been allotted to 11 families who are eligible. The payment of
compensation is in progress.

Complied

WEP 2A: Resolution on satisfactory assessment


and payment of compensation to affected structures

PIU/LAQ

Compensation has been paid.

Complied

WEP 2B and 3: Streamline the signage and


measures for safety for workers and other road
users during construction

PIU/Enviro
nment

Instructions have been issued in the form of letters to all contractors and
periodic informal trainings conducted at work places. Improvements observed
in WEP 1, WEP 2A and WEP-3 packages. In the remaining packages
contractors are being pursued.

30-Sep-13

WEP 5: Prepare estimate of fallow land under


cultivation

PIU/Enviro
nment

An estimated 94Sqm of borrow area land under WEP 5 package is being


developed into cultivation land under the borrow area management program.
Similar plan for the remaining packages is under preparation.

complete

Completion of mid-term LA and R&R Impact


Evaluation

PIU/R & R

Modified Check list is ready. Compliances to the World Bank observations


from the check list will be sent.

Nov. 2013

Extend assistance to all vulnerable people in EPC


contracts

PIU/R & R

Vulnerable people identified. Except 3, all other are getting pension from
Govt. Report is being sent to WB.

15.11.2013

In all WEP contracts, finalize Encumbrance


Removal Plan

PIU/R & R

Encumbrance removal plan for all packages except WEP5 will be sent to WB
by end of the month.

30-11-2013

Page 31 of 72

PIU-KSHIP

Component 1B: DBFOMT


Annuity Concessions

Other Environmental Management Issues

Area

Quarterly Progress Report 2 (1 July to 30 September 2013)


Action Required

Responsibi
lity

Action Taken

Due Date

Pay difference in amount between depreciated and


without depreciation for structure compensation

PIU/LAQ

Details are being collected from AC. Status report will be finalized and shared
with the Bank shortly.

Dec, 2013.

Provide update and plan of action for reuse of


scarified material from WEP roads following pilot
along WEP1

PIU/Enviro
nment

A project on pilot basis has been undertaken in WEP-1 for the recycling of
scarified materials to resurface PWD village road for a length of about 500
meters. The work is under progress and is expected to be completed by 15 th
December 2013. The findings will be shared with the WB for taking further
action in the matter.

15-Dec-13

Obtain consent to operate for plants used for the


project

PIU/Enviro
nment

Except WEP1 and WEP2B, in all other contract packages contractors have
obtained consents from the DC and Pollution Control Board. WEP2B
Contractor identified the location for establishing camp and identification of
quarry is under process.

Mar,15, 2014

Submit compliance with stage 1 conditions of


clearance and follow up for stage II clearances
under forest Act, especially for M7A

PIU/Enviro
nment EE
Shimoga/A
CF

KSHIP has complied all conditions except alternate land to be provided by the
DC Shimoga. Land identified. Handing over process to forest dept is in
progress.

30-Nov-13

Complete enhancement works for all ponds as per


revised design

Environme
nt EE
Tumkur,
Shimoga,
Raichur

Four water bodies along the project roads have been taken up of which one
pond in WEP-3 package is completed, in the remaining WEP-1, WEP-2 and
WEP-4 will be completed.

April, 30th
2014.

Response to additional information/clarifications


w.r.t. BER, as requested by the Bank

PIU

The additional information has been submitted to WB. Further suggestions of


WB are under review by KSHIP and GOK.

30-Nov-13

Independent Engineer - $9.5 million

PIU

Action will be taken after decision on award of annuity works.

31-Dec-13

Page 32 of 72

PIU-KSHIP

Other Environmental
Management Issues

LA and R&R related actions

Area

Quarterly Progress Report 2 (1 July to 30 September 2013)


Action Required

Responsibi
lity

Action Taken

Due Date

Complete LA process and identify alternative house


sites for all packages

PIU/LAQ
R&R

60 PAPs NTHs in WAP packages have to be provided alternate house sites.


Location of sites to 33 PAPs in the progress

31st Dec 2013

Complete issue of pending section 15 of LA notices


in WAP pack ages (Kortagere, Solur,
RannaBelagale, and Kunigal)

PIU/LAQ
R&R

Section 15 notifications issued for all balance expect Koratagere bypass which
is under litigation.

15-Dec-13

Complete consultations in all WAP packages as per


RIP disclosure

PIU/LAQ
R&R

Public consultations completed in Link 63D, E, 64F & G of WAP-1; 19 C &


D of WAP-2 and M7C & T21 of WAP-3 will be completed in the remaining
links by Oct 2013

30th Nov 2013

Supplementary RIP for WAP packages

PIU/R & R

After issue of 15 Notifications, supplementary RIPs will be prepared and sent


for concurrence

30th Nov 2013

Appointment of Assistant Commissioner

PIU/LAQ

Asst Commissioners for Bangalore and Belgaum recently posted.

Complete constituting district level grievance


committees in the remaining 10 districts

PIU/R & R

Committees have been constituted in 13 districts. For Belgaum, proposals are


pending with DC. Being pursued.

30th Nov 2013

Extending Income generation assistance to PAPs in


Phase II roads

PIU/R & R

83 PAPs released IGA. For others proposals are awaited from NGOs

30th Nov 2013

Completion of Joint verification of impacts and


issue of ID cards in Phase II roads

PIU/R & R

Joint verification completed in all links except town limits of Shimoga,


Shikaripura and Hangal, where four lane is proposed.

30th Nov 2013

Update Entitlements for those residing on


Grmathna lands and ex-gratia for affected
structures to squatter families.

PIU/R & R
/LAQ

It is under examination

30th Nov 2013

Out of 2 applications 1 Application is cleared by the National Monument


Authority New Delhi. KSHIP is pursuing the NMA for approval of the 2 nd
application

30th Nov 2013

Follow up with Department of culture, GoK, to


ensure that the successful bidder is provided with
information regarding safeguards required during
construction close to temples in WAP3

PIU/Enviro
nment

Complied

Page 33 of 72

PIU-KSHIP
Area

Quarterly Progress Report 2 (1 July to 30 September 2013)


Responsibi
lity

Action Required

Component 2: Highway Financing Modernization (KRDCL)

EMP to be submitted by potential bidders and EHS


consultant completion of rejuvenation of water
bodies along the road side

PIU/Enviro
nment

Action Taken

Due Date
After
concessionaires
are mobilized

Not yet due

Activities related to roads to be financed through co-financing


Identify the list of 400km roads to be
financed under this component

KRDCL

The list of 8 co-financing packages has been already identified by KRDCL.

Before
September 30,
2013

The DPR consultants have been mobilized on 22nd Aug 2013

The DPR consultant has submitted inception report and made a inception
presentation along with reconnaissance survey findings on 5th Sept 2013.
Finalization of DPRs for the roads
identified in Step 2a)

KRDCL

Field surveys required for revalidation of DPRs will commence by 4 th week of


Sept 13. It is proposed to complete Revalidation of components essential for
project structuring by December 2013.

Before
December 31,
2013

R&R survey and land acquisition surveys will also progress concurrently
since these tasks are time consuming.
Initiation of the Bidding Process

KRDCL
It is proposed to initiate procurement in two batches. The DPR consultants
have been advised to prioritize the roads requiring minimum time for
revalidation and surveys in Batch 1.

By January 31,
2014

Based on the cost and traffic data to be provided by DPR consultant (likely by
end of Nov 2013), FPTA shall initiate the project structuring exercise.

Page 34 of 72

PIU-KSHIP
Area

Quarterly Progress Report 2 (1 July to 30 September 2013)


Responsibi
lity

Action Required

Action Taken

Due Date

In the Aide Memoire of WB dated June 17-22, 2013 it is suggested that the
contracting options need to be expanded to include lump sum EPC plus
maintenance contracts. This option will also be kept in view while structuring
the projects.

World Bank is requested to advise if Single Stage Two Cover bidding mode
will be acceptable by World Bank for the PPP contracts. This proposal was
also made before WB in KRDCL email dated 15th June 2013.
Concomitant Actions required to facilitate co-financing with support from PWC
Consultants (PWC) to submit their
inception report and strategic presentation
on KRDCLs scope of work and business
plan over next five years, to be presented
to the Government and obtain their
endorsement for (i) selection of roads for
co-financing component; (b) utilization of
revenue from OMT concessions and other
means of support from exchequer/Govt to
support co-financing roads;
Issue of OMT concessions on roads that
would mobilize revenue to support for cofinancing component

The FPTA consultant has made a presentation of the Inception Report to


Review Committee in April 2013, post which final report with suggested
modification was also submitted during the same month.
KRDCL
Strategic presentation has been prepared by FPTA and has been presented to
MD, KRDCL in September 2013.

Before
September 30,
2013

A date from Senior GoK officials is being sought currently by KRDCL.


KRDCL

IDecK is providing transaction advisory services for OMT Concessions.

Before
November 30,
2013

The documents are based on KSMCA Std. Document.


Single stage bidding process with two cover system has been adopted.
Bids for OMT contracts were invited in Feb 2013and opened in July 2013.
There was no response for all the eight OMT contracts.
Presently, the OMT documents are being restructured with the objective of
ensuring good participation. Bids will be invited once again shortly.

Page 35 of 72

PIU-KSHIP

Component3: Road Safety Component

Area

Quarterly Progress Report 2 (1 July to 30 September 2013)


Action Required

Responsibi
lity

Action Taken
The list of the roads included in proposed OMT contracts and sample bidding
documents are enclosed for Banks information.

Initiation of dialogue (before Sept 30,


2013) and then finalize co-financing
arrangements
including
through
securitization of revenues from OMT
concessions on roads that would mobilize
revenue to support this component.

KRDCL

Appointment of Procurement Advisor to


coordinate all procurement activities
related to safety

PIU

Finalize list of all procurements and


include the same in procurement action
plan

PIU

Securitization of revenues from OMT concessions for co-financing


arrangements can be decided upon the response from OMT contracts

RSM consultant is taking up procurement of services and goods under road


safety component in coordination with all stake holder departments under road
safety cell, appropriate VO has to be approved in consultation with WB.

Due Date

Before
November 30,
2013

By August
2013
By August
2013

Civil Works
Award of contracts for Maddur to Mysore

PIU

Tender Notification by 30th Dec 2013.

30th Dec 2013

Award of contracts for Belgaum to


Hungund

PIU

Tender Notification by 2nd Dec 2013.

2nd Dec 2013

Goods
Police Enforcement Equipment

Post-Impact Care
PIU
Monitoring and Evaluation Software and
Hardware

RSM consultant is taking up procurement of services and goods under Road


safety component in coordination with all stake holder departments under road
safety cell, appropriate VO has to be approved in consultation with WB.

Services
Capacity Building for Police Enforcement

Development of Safety Campaigns


Capacity building for Post-Impact Care

PIU

Consulting Services for M&E

RSM consultant is taking up procurement of services and goods under road


safety component in coordination with all stake holder departments under road
safety cell, appropriate VO has to be approved in consultation with WB.

Traffic Incident Mgt System (TIMS)


Consultant for DBFOMT

PIU

Action to be taken after decision on award of annuity works.

31-Dec-13

Page 36 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Area

Responsibi
lity

Action Required
Center of Excellence
Establishment

Study

and

PIU

Action Taken
This will be covered under RSM Consultancy.

Due Date
-

Road Asset Management System


PIU

Short listing finalized on 17-10-2013. RFP is under finalization. WB no


objection to be sought shortly.

31-Dec-13

PIU

EOI evaluation completed and evaluation report along with draft RFP shall be
sent to Bank

31-Dec-13

Procurement of Software

PIU

This is Part of the KRAMS software under PRAMC

IT-ICT-MIS Consultant

PIU

Shortlist submitted to WB for no objection.

31-Dec-13

Strategic Studies for GOK planning

PIU

TOR is under preparation.

31-Dec-13

PIU

Awaiting approval of the GOK

31-Dec-13

Study of future institutional development


and strategies

PIU

To be discussed with WB.

14-Jun-13

Finalization of D-Code

PIU

Awaiting approval of the GOK

31-Dec-13

Engagement of consultant

Component 4: Road Sector Policy and Institutions Development

Data Collection
Network

for

non-Core

Road
Establishment/operationalization

Road

Fund

Quality Management/Quality Control


QM ISO Certification program

PIU

Short listing of additional four firms is under process. EOI is under evaluation.

QC Equipment

PIU

To be procured under two stages.

QC Capacity Enhancements

PIU

In view of poor response even for the 2nd call, the Banks concurrence is
sought for selection of SSS or to go for 3rd call.

PIU / Environment

TOR approved by World Bank on 30.10.2013 and EOI will be notified in


November 2013.

Environment ISO Certification Selection


of Audit/Certification agency

31-Dec-13

13-Nov

Road User Satisfaction Survey (RUSS)

PIU

Agreement signed on 1st July 2013. The consultancy service is in progress.

RUSS II

PIU

EOI is under finalization and will be issued by end of Nov, 2013.

Nov, 2013

RUSS III

PIU

Not yet due

Not yet due

Mid-June 2013

Page 37 of 72

PIU-KSHIP

Overall Project Management Issues

Area

Quarterly Progress Report 2 (1 July to 30 September 2013)


Action Required

Responsibi
lity

Action Taken

Due Date
Immediately

Road Safety Cell to staffed

PIU

GO regarding formation of Road Safety Cell is issued and posting of staff to


the cell is being pursued with Transport Department.

Appointment of PMC (IDSAP to be


included)

PIU

Draft TOR is prepared and will be submitted by 30th December 2013.

PCC contract for phase 2

PIU

PCC contract service for Phase- 2 is currently in progress.

Project Monitoring Report (PMR)

PIU/JCA

Monthly/Quarterly Project Reports

PIU

Financial Management Report


Procurement Plan

PIU/JCA
PIU

30th December
2013.

Submitted
Submitted for 2nd quarter.

Nov, 2013

IUFR for quarter ending Sept submitted.


Updated procurement plan submitted

Page 38 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

5.

PROJECT IMPLEMENTATION MONITORING

An overall evaluation of the Project implementation in terms of planned completion as a percentage of


the total, actual completed as a percentage of the total and the difference is presented in the Table below
for key areas of the Project.
Table 16: Project Implementation Monitoring
2011-12
Area

Planned
- Year
End

Actual

8.5

8.5

2012-13

2013-14

Difference

Planned
- Year
End

Actual

Difference

17

15.1

1.9

Planned
- Year
End

Actual

Difference

Cumulative % of civil
works completed
(contract value)
Cumulative % of
equipment supplied
(contract value)
Cumulative % of
Services completed
(cost)

Procurement of IT equipment, Office equipment, and supply of almirah is completed

Cumulative % of
resettlement
completed

R&R completed in all EPC packages except resettlement and rehabilitation of 13 families in WEP-2. In
Annuity Contract, out of 844 PAPs 519 have been issued ID cards. Subsistence and shifting allowance
have been paid to 397 PAPs and replacement cost paid to 54 encroachers. Release of assistance to
other PAPs is in progress. The status of land acquisition completed in EPC package by 99% and there
is only 0.51% progress in Annuity package.

An amount of US$ 3.143 million has been disbursed under the procurement of 19 services.

Page 39 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

5.1

Physical Progress

WEP-1
The following table shows the Planned Quantity v/s Achieved Quantity during this reporting quarter. The
planned quantity is as per approved Work Program.
Table 17: Physical Progress of WEP-1
Item
Earthwork, Cum
(BOQ = 1,066,666 Cum)
GSB, Cum
(BOQ = 144,069 Cum)
WMM, Cum
(BOQ = 156,506 Cum)
DBM, Cum
(BOQ = 33,853Cum)
BC, Cum
(BOQ =23,309 Cum)
Item
Culverts (Total 55 No)
Bridges (Total 17 No)

Program

July

August

September

Total

62300

59831

183821

Planned

61690

Achieved

10310

6611

16921

Planned

5425

4438

4438

14301

Achieved

4912

2361

298

7571

Planned

6139

5003

5003

16145

Achieved

4621

3447

1809

9877

Planned

1775

1775

1212

4762

Achieved

641

856

377

1874

Planned

926

926

764

2616

Achieved
Program

625
July

130
August

737
September

1492
Total

Planned

Achieved

Planned

Achieved

WEP-2A
The following table shows the Planned Quantity v/s Achieved Quantity during this reporting quarter. The
planned quantity is as per approved Work Program.

Page 40 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

Table 18: Physical Progress of WEP-2A


Item
Earthwork, Cum
GSB, Cum
WMM, Cum
DBM, Cum
BC, Cum
Item
Culverts (Total 64 No)
Bridges (Total 1 No)

Program
Planned

July
-

August
-

September
-

Total
-

Achieved

Planned

Achieved

Planned

Achieved

Planned

Achieved

Planned

Achieved

Program

July

August

September

Total

Planned

15

19

Achieved
Planned

15
-

5
-

20
-

Achieved

WEP-2B
The agreement signed on 6th July 2013 and Contractor already identified land for land Base camp. The
identification of borrow areas and crusher locations is under process.
WEP-3
The following table shows the Planned Quantity v/s Achieved Quantity during this reporting quarter. The
planned quantity is as per approved Work Program.
Table 19: Physical Progress of WEP-3
Item
Earthwork, Cum
(BOQ = 12,33,106 Cum)
GSB, Cum
(BOQ = 94,120 Cum)
WMM, Cum
(BOQ = 1,01,306 Cum)
DBM, Cum
(BOQ = 25,185Cum)
BC, Cum
(BOQ =15,727 Cum)
Item
Culverts (Total 41 No)
Bridges (Total 8 No)

Program

July

August

September

Total

Planned

4168

668

53623

58459

Achieved

2040

3237

639

5916

Planned

4596

4021

2872

11489

Achieved

2660

2660

Planned

3609

3609

5413

12631

Achieved

3407

483

1291

5181

Planned

886

673

1345

2904

Achieved

374

796

205

1375

Planned

834

590

834

2258

Achieved
Program

0
July

0
August

0
September

0
Total

Planned

Achieved

Planned

Achieved

Page 41 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

WEP-4
The following table shows the Planned Quantity v/s Achieved Quantity during this reporting quarter. The
planned quantity is as per approved Work Program.
Table 20: Physical Progress of WEP-4
Item

Program

July

August

September

Total

Earthwork, Cum
(BOQ = 22,59,190 Cum)

Planned

67090

44375

42700

154165

Achieved

18581

19100

7266

44947

GSB, Cum
(BOQ = 1,90,127 Cum)

Planned

8000

7000

5320

20320

Achieved

4186

6873

4732

15791

Planned

7500

7200

5958

20658

Achieved

4974

7862

5879

18715

Planned

1150

915

900

2965

Achieved

485

1627

1422

3534

WMM, Cum
(BOQ = 2,02,241 Cum)
DBM, Cum
(BOQ = 38,121Cum)
BC, Cum
(BOQ =30,501 Cum)
Item
Culverts (Total 110 No)
Bridges (Total 38 No)

Planned

545

360

456

1361

Achieved
Program

1343
July

1841
August

391
September

3575
Total

Planned

15

Achieved

16

Planned

Achieved

11

Page 42 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

WEP-5
The following table shows the Planned Quantity v/s Achieved Quantity during this reporting quarter. The
planned quantity is as per approved Work Program.
Table 21: Physical Progress of WEP-5
Item
Earthwork, Cum
(BOQ = 22,59,190 Cum)
GSB, Cum
(BOQ = 1,90,127 Cum)
WMM, Cum
(BOQ = 2,02,241 Cum)
DBM, Cum
(BOQ = 38,121Cum)
BC, Cum
(BOQ =30,501 Cum)
Item
Culverts (Total 40 No)
Bridges (Total 7 No)

Program

July

August

September

Total

Planned

Achieved

1290

3705

142

5137

Planned

Achieved

434

200

634

Planned

Achieved

564

385

949

Planned

Achieved

98

74

172

Planned

Achieved
Program

242
July

1434
August

918
September

2594
Total

Planned

Achieved

Planned

Achieved

Page 43 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

5.2

Financial Progress

WEP-1
The Contractors Achieved v/s Planned cash flows for this Quarter are summarized in the table below.
Table 22: Financial Progress, WEP-1
Month
July
August
September
Total

Planned,
US$ million

Achieved,
US$ million

Planned

Achieved

0.68
0.84
0.85
2.37

0.55
0.44
0.14
1.13

3.10%
3.87%
3.91%
10.87%

2.50%
2.03%
0.66%
5.19%

WEP-2A
Page 44 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

The Contractors Achieved v/s planned cash flows for this Quarter are summarized in the table below.
Table 23: Financial Progress, WEP-2A
Month

Planned,
US$ million

Achieved,
US$ million

Planned

Achieved

July
August
September
Total

0.09
0.03
0.04
0.16

0.04
0.07
0.07
0.18

0.44%
0.16%
0.17%
0.78%

0.22%
0.32%
0.35%
0.89%

WEP-3
The Contractors Achieved v/s Planned cash flows for this Quarter are summarized in the table below.
Table 24: Financial Progress, WEP-3
Month
July
August
September
Total

Planned,
US$ million
0.68
0.69
1.00
2.37

Achieved,
US$ million
0.26
0.15
0.07
0.48

Planned
3.82%
3.85%
5.58%
13.25%

Achieved
1.47%
0.82%
0.40%
2.69%

Page 45 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

WEP-4
The Contractors Achieved v/s Planned cash flows for this Quarter are summarized in the table below.
Table 25: Financial Progress, WEP-4
Month
July
August
September
Total

Planned,
US$ million
1.19
1.02
0.96
3.18

Achieved,
US$ million
0.74
1.08
0.78
2.61

Planned
3.33%
2.87%
2.70%
8.90%

Achieved
2.07%
3.04%
2.19%
7.30%

WEP-5
The Contractors Achieved v/s planned cash flows for this Quarter are summarized in the table below.
Table 26: Financial Progress-WEP-5
Page 46 of 72

PIU-KSHIP
Quarterly Progress Report 2 (1 July to 30 September 2013)

Month
July
August
September
Total

Planned,
US$ million
0.38
0.36
0.79
1.53

Achieved,
US$ million
0.16
0.26
0.18
0.60

Planned
2.79%
2.65%
5.75%
11.19%

Achieved
1.17%
1.88%
1.30%
4.35%

Page 47 of 72

PIU-KSHIP

6.

Quarterly Progress Report 2 (1 July to 30 September 2013)

PAYMENT AND DISBURSEMENT PROGRESS

The summary of Package-wise payment and disbursement progress is given in the table below.
Table 27: Payment and Disbursement Progress

WEP-5

CSC-I

Upgradation
of the Road
from
Chowdapur to
Gulbarga
Construction
Supervision
Consultancy
Services(CSCI)

Works

Services

ICB

ICB

ICB

16.57

31.54

12.08

4.29

0.80%

0.80%

0.80%

0.80%

2013
July

Works

ICB

0.80%

2012
Apr

Upgradation
of the Road
from Tinthini
to Kalmala

Works

21.75

0.80%

2011

Payments

Jan

WEP-4

Upgradation
of the Road
from Dharwad
to Saundatti

ICB

20.56

0.80%

Cumulative Payments (Planned/Actual) (%) and Bank's Cumulative Disbursements (%)

Oct

WEP-3

Works

ICB

19.28

Bank
Financing
Ratio (%)

Jul

WEP-2B

Upgradation
of the Road
from Hangal
to Tadas

Works

ICB

Contract
Price
(Million
US$)

Apr

WEP-2A

Upgradation
of the Road
from Haveri
(NH-4) to
Hangal

Works

Proc.
Method

Jan

WEP-1

Upgradation
of the Road
from Hoskote
to Chintamani

Category
1/

Oct

Contract
Description

Jul

Component

Contr.
No

Planned

12.92%

11.12%

20.22%

19.51%

68.79%

54.64%

Actual

5.00%

5.00%

7.20%

11.80%

19.70%

28.70%

40.79%

48.56%

48.56%

Disbursed

4.00%

4.00%

5.80%

9.40%

14.80%

21.20%

25.33%

33.32%

38.85%

Planned

13.59%

1.59%

Actual

5.00%

5.00%

Disbursed

4.00%

4.00%

Planned

Actual

Disbursed

Planned

28.2

8.61

13.64

21.44

100%

40.40%

Actual

5.00%

5.00%

5.00%

6.80%

9.60%

11.90%

24.25%

27.63%

27.63%

Disbursed

4.00%

4.00%

4.00%

5.40%

7.40%

9.00%

12.24%

20.62%

22.10%

Planned

10.76

8.74

12.61

14.04

47.73%

55.41%

Actual

5.00%

5.00%

12.20%

15.30%

21.10%

27.90%

39.78%

48.72%

48.72%

Disbursed

4.00%

4.00%

4.00%

12.20%

16.40%

21.40%

27.71%

35.09%

38.98%

Planned

33.85

18.12

26.35

17.24

100%

78%

Actual

10.00%

10.00%

26.30%

31.60%

47.10%

57.10%

70.00%

72.54%

72.55%

Disbursed

8.00%

8.00%

16.00%

25.30%

36.40%

43.80%

45.47%

55.21%

58.04%

Planned

Actual

0.00%

16.30%

31.20%

36.00%

44.00%

51.00%

70.00%

78.54%

78.54%

Disbursed

0.00%

13.00%

13.00%

28.80%

35.20%

40.80%

49.49%

62.83%

62.83%

Page 48 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

The summary statement of receipts and payments, and the Projects overall disbursement progress are
given in the tables below.
Table 28: Statement of Receipts and Payments

Statement of Receipts and Payments

(In US$ Million)


Quarter
Last
This
Quarter
Quarter

ITEMS

Cumulative
Last
This
Quarter
Quarter

RECEIPTS
IBRD Funds

0.000

4.542

43.769

48.311

Government Funds

7.078

2.834

44.699

47.533

7.078

7.376

88.468

95.844

6.013

6.196

77.077

0.000

Road Sector Policy & Institutional Development

0.108

0.059

1.005

1.064

Incremental Operating Costs

0.090

0.162

1.164

1.327

Advances

0.000

0.958

8.354

9.312

6.210

7.376

87.600

11.703

TOTAL RECEIPTS
PAYMENTS
Road Improvement Component
Highway Financing Modernization
Road Safety Component

TOTAL PAYMENTS

Table 29: Projects Overall Disbursement Progress


Bank's Cumulative Disbursement (Million US$)
Aspect

2011
Jan

Planned
Actual

2012

2013

Apr

Jul

Oct

Jan

Apr

Jul

Oct

Jan

Apr

Jul

10

19

28

36

45

58

71

84

97

167

10

17

20

23

23

27

33.67

38.20

41.51

Oct

Page 49 of 72

PIU-KSHIP

7.
7.1

Quarterly Progress Report 2 (1 July to 30 September 2013)

SOCIAL, RESETTLEMENT & REHABILITATION


Summary of Resettlement and Rehabilitation Activities

The summary of resettlement and rehabilitation activities is given in the table below.
Table 30: Resettlement and Rehabilitation Activities for WEP Packages.
a) Non-Title Holders
Sl
No

Type of R&R Assistance

Target per
RIP

Revised
Target

Progress

Remarks

ID card issued

292

313

313 (100)

Allotment of house plots

24

30

30 (100)

8 PAPs had their own sites.

Construction grant for houses

24

30

30 (100)

8 PAPs had their own sites and the


remaining 22 PAPs provided sites. All
have completed construction of their
houses.

Subsidence allowance paid

197

200

200 (100)

Shifting allowance paid

197

200

200 (100)

IGA Support Provided


Replacement cost for
Encroachers
Shifting of CPRs

169

170

170 (100)

97

113

113 (100)

441

443

382 (86.43)

The NGO reported that Government


pension has been sanctioned to them.
Details have been sought from the
NGO.

7
8
9

Assistance to vulnerable
provided

41

Still awaited
from NGO

10

No. of PAPs received all benefits

292

313

313 (100)

Note: The figure in brackets indicates the percentage progress


b) Title Holders
Sl
No

Type of R&R Assistance

Target per
RIP

Revised
Target

Progress

Remarks
On Re-verification, revised target
comes to 823 Khathedars only

ID card issued

818

823

26 (3.15)

Subsidence allowance paid

16

14

Shifting allowance paid

16

16

2(12.50)

Allotment of house plots

14

14

No Progress

Construction grant for houses

14

14

No Progress

Compensation offered

818

823

823 (100)

Compensation Paid

818

823

817 (99)

No. of PAPs received all benefits

818

823

817 (99)

Note: The figure in brackets indicates the percentage progress

Page 50 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Table 31: Resettlement and Rehabilitation Activities for WAP Packages.


a) Non-Title Holders
Sl
No

Type of R&R Assistance

ID card issued

Target per
RIP

Revised
Target

Progress
(Numbers)

Percentage
Progress

1500

844

519

61.49

Allotment of house plots

49

61

4.91

Construction grant for houses

49

50

Subsidence allowance paid

524

563

397

70.51

5
6

Shifting allowance paid


IGA Support Provided
Replacement cost paid for
Encroachers
Tenants
Shifting of CPRs
Number of PAPs received all
benefits

524
476

563
502

397
83

70.51
16.53

152

253

54

21.34

5
1230

5
1169

0
981

0
83.92

1501

820

137

16.70

7
8
9
10

Remarks
In WAP-3 package JV was
conducted in respect of
squatters. Revised target
may vary on completion of
final JV.
NGO reports 11 PAPs have
their own Sites. Records
are awaited. Location of
sites for others is in
progress.
Released to the Executive
Engineer vide Office order
dated 3-11-2012 with
instruction to release them
to PAPs in installments
based on construction
progress.

b) Title Holders
Sl
No
1
2
3
4
5
6
7
8

Type of R&R Assistance


ID card issued
Subsistence allowance paid
Shifting allowance paid
Allotment of house plots
Construction grant paid
Compensation offered
Compensation Paid
No. of PAPs received all benefits

Target
per RIP
3179
0
0
0
0
3179
3179
3179

TITLE HOLDERS
Revised
Progress
Target
(Numbers)
2903
0
0
0
0
0
0
3
0
0
2903
33
2903
15
2903
15

Percentage
Progress
0
0
0
0
0
1.00
0.51
0.51

Remarks

Page 51 of 72

PIU-KSHIP

7.2

Quarterly Progress Report 2 (1 July to 30 September 2013)

Resettlement Complaints

As noted in the table below, no resettlement complaints have been received to date.
Table 32: Resettlement Complaints

7.3

HIV/AIDS Education Monitoring

The Karnataka State Aids Prevention Society has been appointed for creation of awareness on HIV and
AIDS among the road users in the project roads more particularly to the workers engaged in the road
works. An agreement has already been signed. The duration for implementation of this programme is
one year. During the first half of the contract period, the project roads under EPC packages will be
covered and in the second half the roads under annuity packages will be covered.
In each of the WEP Contract packages the Contractor has been advised by CSC to conduct awareness
program at their construction camp site with co-ordination of adjacent village Panchayat among the
workers and villagers through experienced service providers. The Contractors action taken report on
awareness programme at each project site will forward on receipt.
Table 33: HIV-AIDS Campaigns at WEP Packages

Contract
Package

Link ID

Description of Link

Contractors Name

Details awareness
programme held.
Date

67A

Hoskote - H Cross
(Hindgnala Cross)

67B

H Cross - Chinatmani
Bypass (Corridor 65F
Junction)

WEP2A

T8

Haveri-Hangal

M/s DRN
Infrastructure

WEP 3

21B

Dharwad - Saundatti

M/s RVCPL RIDL


(JV).

Tinthni - Chinchodi Jalhalli - Karegud Devadurga


Devadurga - Masarkal Gabbur - Kalmala

M/s Patel Engineering


Pvt. Ltd.

Chowdapur - Gulbarga

M/s SRK KCL (JV)

WEP 1

13A
WEP 4
13B
WEP 5

6C

Persondays

Tentative
Date for
next
Awareness
Programme

M/s Lanco Infratech


Pvt. Ltd.
No HIV-AIDS
awareness program
conducted in this
quarter.

Page 52 of 72

PIU-KSHIP

8.

COVENANTS

8.1

Loan Covenants

Quarterly Progress Report 2 (1 July to 30 September 2013)

The summary of covenants is given in the tables below.


Table 34: Loan Covenants
Description
Establish and maintain until completion of the Project, an
audit committee to review reports of said external and
internal auditors.
Appoint and thereafter maintain, until completion of the
project, an external auditor for KRDCL
Appoint an internal auditor for the Project in accordance
with terms of reference acceptable to the Bank.
Appoint, and thereafter maintain until completion of the
Project, finance staff with qualifications acceptable to the
Bank employed in accordance with the staffing plan
agreed upon between Karnataka and the Bank.
Prepare and furnish to the Bank not later than forty five
(45) days after the end of each calendar quarter, interim
unaudited financial reports for their Respective Parts of the
Project covering the quarter, in form and substance
satisfactory to the Bank.
Have their financial statements audited by independent
auditors acceptable to the Bank, all in accordance with
consistently applied auditing standards acceptable to the
Bank. Each audit of these financial statements shall cover
the period of one (1) Fiscal Year of the Borrower. The
audited financial statements for each period shall be
furnished to the Borrower and the Bank not later than six
(6) months after the end of such period.
Implement the Financial Management Manual
Maintain a financial management system and prepare
financial statements in accordance with consistently
applied accounting standards acceptable to the Bank, both
in a manner adequate to reflect the operations, resources
and expenditure.

Timeline

Status

30-Sep-11

complied

19-Nov-11

AG has agreed to take up


external Audit of KRDCL
project accounts.

19-Nov-11

complied

19-Nov-11

complied

Quarterly
from
Effectiveness

Complied. The latest IUFR


sent to Bank is for the QE
30th September 2013.

Annually

Complied.
AG
has
completed the audit of
project
financial
statements for the FY
2012-13 and issued the
audit report dated 30-082013. The same has been
submitted to GOI and to
WB on 7th Sept.2013 (ie
within the due date)
complied
As agreed with the Bank
computerized
accounts
have been maintained in
Tally accounting software
acceptable to the Bank.

Page 53 of 72

PIU-KSHIP

8.2

Quarterly Progress Report 2 (1 July to 30 September 2013)

Legal Covenants

The summary of covenants is given in the tables below.


Table 35: Legal Covenants
Description
Meet all annuity payments to fall due under annuity concession
agreements in a timely manner in accordance with the terms of said
agreements.

Timeline

Status

31-Dec-14

Not Due
Yet

Commence undertaking comprehensive road safety interventions in the


identified safe corridor demonstration program.

1-Apr-12

Received
NOC from
Bank.
Agreement
expected to
be signed in
the month
of October
2013.

On an annual basis throughout the duration of the Project, to


develop a consolidated investment and borrowing plan to improve
selected corridors under the Core Road Network commencing
December 31, 2013, and thereafter implement such plan taking into
account the Bank's comments thereon

31-Dec-14

Not Due
Yet

1-Dec-14

Not Due
Yet

From
Effectiveness

Complied

Establish and Maintain Project Steering Committee to From Complied


be responsible for the overall coordination and Effectiveness oversight
of implementation of the Project.

From
Effectiveness

Complied

Establish and Maintain District-level Grievance Redressal


Committee to deal with grievances related From Effectiveness Partial
Complied to or arising out of the RAP.

From
Effectiveness

Partial
Complied

Establish and maintain Traffic and Road Safety Cell From Not
Complied at TD for effective implementation of Part C of the Project

From
Effectiveness

Not
Complied

30-Sep-11

Complied

19-Nov-11

Complied

19-Nov-11

Complied

Appoint, and thereafter maintain until completion of the Project,


finance staff with qualifications acceptable to the Bank
employed in accordance with the staffing plan agreed upon
between Karnataka and the Bank.

19-Nov-11

Complied

Designate and thereafter maintain a Project Coordinator for KRDCL

19-Nov-11

Fully operationalize its road asset management system to


provide inputs to prioritize its road investment and
management program.
Establish and Maintain a Project Governing Board to From Complied
be responsible for interdepartmental coordination and Effectiveness
policy matters.

Establish and maintain until completion of the Project, an


audit committee to review reports of said external and internal
auditors.
Appoint and thereafter maintain, until completion of the Project, an
external auditor for KRDCL.
Appoint an internal auditor for the Project
with terms of reference acceptable to the Bank.

in accordance

Page 54 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Description

Timeline

Status

Maintain the Project Implementation Unit (PIU) responsible for


implementing PWD's Respective Parts of the project.

From
Effective

Partially
Complied

EMP and RAPs are prepared to mitigate impacts prior from issue of
RPF for works under the project prior to effective issuance of any
request for proposals under the Project, social and environmental
screening reports, environmental management plans, and
resettlement action plans, for mitigation of any environmental and
social impacts under the Project, shall have been prepared based on
said screening report findings and in accordance with the policies and
principles of the Resettlement Policy Framework and found acceptable
to the Bank

From
Effectiveness

Partially
Complied

All land acquisition and resettlement and from


rehabilitation-related impacts shall have been Effective
satisfactorily addressed along such stretches, all in accordance with
the RAP and resettlement action plans including payment of
compensation for loss of Land and other assets, and other
assistance to Displaced Persons.

From
Effectiveness

Partially
Complied

Carry out a mid-term impact study by June 30, 2013, June 30, and
another study within one hundred and twenty 2013 (120) days
following the completion of the implementation of the RAP and
resettlement action plans in accordance with terms of reference
satisfactory to the Bank, to assess the impact of the implementation of
said RAP and resettlement action plans on changes in the living
standard of Displaced Persons, and discuss the results of each such
study with the Bank promptly after its completion and, taking into
account the recommendations of the Bank, take appropriate measures
satisfactory to the Bank.

30-Jun-13

It has been
Taken up
and report
is awaited
shortly

Monitor and evaluate the progress and prepare Project Quarterly


Reports which shall cover the period of one (I) from calendar
quarter, and shall be furnished to the Bank not later than forty-five
(45) days after the end of the period covered by such report.

Quarterly
from
Effectiveness

Being
Complied

Prepare and furnish to the Bank not later than forty- Quarterly five
(45) days after the end of each calendar quarter, from interim
unaudited financial reports for their Effectiveness Respective
Parts of the Project covering the quarter, in form and substance
satisfactory to the Bank.

Quarterly
from
Effectiveness

Being
Complied

Have their financial statements audited by Annually


independent auditors acceptable to the Bank, all in accordance with
consistently applied auditing standards acceptable to the Bank.
Each audit of these financial statements shall cover the period of one
(1) Fiscal Year of the Borrower. The audited financial statements
for each period shall be furnished to the Borrower and the Bank
not later than six (6) months after the end of such period.

Annually

Complied

Implement the Financial Management Manual

Complied

Page 55 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Table 36: Right to Information Act


Status as at end of Quarter: 1st July 2013 to 30th September 2013
No of
No .of
No. of
Land
Bidding
application application application
acquisition
Process
Received
disposed
pending
17

16

ROW
Details

Quality of
the Work

General
16

The details are attached in Appendix-D.


Table 37: Complaint Management Cell (CMC) Cases for the Year 2013(July to Sept 2013)

Month/ Year

29/7/2013

12/8/2013

Road link.

Name of the
petitioner
with
address

Name of the
petitioner
date and
subject

Action and
date of reply
sent to the
petitioner
(With file
No.)

Reply furnish from which section


in KSHIP

13A&B

Mr. V
Sharbappa,
Amarapur,
TalukDevdurga,
DistrictRaichur

Poor Quality
Construction
of Bus
Shelter and
Bridges

Reply is
awaited from
PIU KSHIP

Reply is awaited from PIU KSHIP

21B

Mr. Pralhad
Joshi,
Member of
Parliament
Loksabha
Dharwad

Poor Quality
Construction
of State
Highway
road from
Dharwad to
Savadatti of
SH-34.

Reply is
awaited from
PIU KSHIP

Reply Awaited from PIU KSHIP

Page 56 of 72

PIU-KSHIP

9.
9.1

Quarterly Progress Report 2 (1 July to 30 September 2013)

SUMMARY OF PROCUREMENT PACKAGES


Procurement Plans for Works, Goods, and Services

A summary of all the procurement packages is given in the table below.


Table 38: Summary of Procurement Packages
Contract Phase

Category
Works

Contracts
Completed
prior to the
reporting period

Goods

Services

Description
EPC Packages
Supply of IT
Equipment,
office
equipment and
Supply of
almirah
-

Sub-total
Contracts
Under Process

Works
Goods
Services

Annuity
Packages
-

Sub-total
Contracts not
yet awarded
Sub-total
Total

Works
Goods
Services

Estimated
Value
(INR
Million)
6579.0

147.0

Contracted
Value
(INR
Million)
5953.2

4.0

0.1

19
27

735.8
7318.8

16.3
163.4

523.7
6476.9

11.6
143.9

15491.0

344.0

8
12

642.30
16133.3

14.28
358.28

7
23
30
69

152.1
460.15
612.25
24064.35

3.4
10.39
13.79
535.47

0
6476.9

0
143.9

No of
Contracts

Estimated
Value
($US)

Contracted
Value
($US)
132.3

Details of the procurement plans for Works, Goods, and Services are given in Appendices A, B and C
respectively.
The WB-EPC works packages were procured in 2010-2011 and implementation is ongoing. The next
major works procurement activity will be the WB-Annuity packages to be re-procured under EPC.
The CSC services for WB-EPC have been in place since April 2011. In line with the above-noted reprocurement of Annuity packages under EPC, a fresh EOI for Construction Supervision Consultancy for
these EPC packages will be prepared.

Page 57 of 72

PIU-KSHIP

10.

Quarterly Progress Report 2 (1 July to 30 September 2013)

ENVIRONMENTAL MANAGEMENT ACTIVITIES

10.1 Clearances and Compliance


Environmental Clearances
All environmental clearances for the WB-EPC and Annuity road packages as noted below have been
obtained by PIU-KSHIP.
Table 39: Environmental Clearances
Sl
No.

Pkg No

WEP-1

WEP-2

WEP-3

WEP-4

WEP-5

State Environmental Impact Assessment


Authority (GOK)/ Environmental Appraisal
Committee, MOEF, GOI Clearances State
Environmental Impact Assessment
Authority (GOK) Clearances
No:SEIAA:80:IND:2008
dt:18/11/2008
No:SEIAA:80:IND:2008
dt:18/11/2008
No:SEIAA:7:IND:2009
dt:01/10/2009
No:SEIAA:80:IND:2008
dt:18/11/2008
No:SEIAA:7:IND:2009
dt:01/10/2009
No:SEIAA:80:IND:2008
dt:18/11/2008

Ministry of
Environment &
Forests(Govt.of
India) Clearance

Not required
Not required
Not required
Not required
Not required

Karnataka State Pollution


Control Board Clearance

No:PCB/439/CFE/08/H551
dt:22/07/2008
No:PCB/439/CFE/08/H551
dt:22/07/2008
No:PCB/05/CNP/09/558
dt:29/01/2010
No:PCB/439/CFE/08/H551
dt:22/07/2008
No:PCB/439/CFE/08/H551
dt:22/07/2008
No:PCB/439/CFE/08/H551
dt:22/07/2008

Remarks

Completed
Completed
Completed
Completed
Completed

Annuity
1

WAP-1

WAP-2

WAP-3

WAP-4

No:SEIAA:80:IND:2008
dt:18/11/2008
No:5-13/2008-IA-III, GOI, MOEF, New
Delhi dt:13/01/2009
No:SEIAA:80:IND:2008
dt:18/11/2008
No:SEIAA:7:IND:2009
dt:01/10/2009
No:SEIAA:7:IND:2009
dt:01/10/2009
No:5-6/20098-IA-III, GOI, MOEF, New
Delhi dt:22/01/2010
No:SEIAA:7:IND:2009
dt:01/10/2009

Not required

No:PCB/439/CFE/08/H551
dt:22/07/2008

Completed

Not required

No:PCB/439/CFE/08/H551
dt:22/07/2008

Completed

Not required

Not required

No:PCB/05/CNP/09/558
dt:29/01/2010
No:PCB/439/CFE/08/H551
dt:22/07/2008
No:PCB/439/CFE/08/H551
dt:22/07/2008

Completed

Completed

Statutory Compliance
All Six (6) WB-EPC packages (Note: WEP-2 package is terminated) were inspected during the period 1 st
July 2013 to 30th September 2013. The statutory compliance status is given in the table below.

Page 58 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Table 40: Statutory Compliance Status


Quarry CFO

Details of Crusher
Consent for Execution (CFE)

Package No

WEP-1
WEP-2A

Applied Date

13/4/2012
NA

Approval Date
from Mines &
Geology Dept

No of
Crushers

Applied Date

Approval Date
from DC

Hot Mix Plant CFE/CFO


Consent for Operation (CFO)

Applied Date

Applied Date

Approval Date
(KSPCB
Permission)

1/3/2012

17/11/2012

18/7/2013
CFO awaited

8/4/2013
13/12/2011

24/5/2013
16/2/2013

Approval Date
(KSPCB
Permission)

14/8/2012

Crusher-1

7-Apr-12

Permission
awaited. KSHIP is
pursuing with DC
Bangalore

18/3/2013

Crusher-1
Crusher-1

8/4/2013
12/12/2011

24/5/2013
16/2/2013

Crusher-2

9/5/2012

16/2/2013

16/9/2013

CFO awaited

9/5/2013

16/2/2013

Not Applied
31/5/2013
16/9/2013

CFE awaited

WEP-3

24/10/2011

05/03/2012

WEP-4

17/9/2011

14/3/2012

Crusher -1

03/10/2011

16/3/2012

19/6/2012

12/2/2013

5/11/2011
9/6/2012

CFE-16/3/2012
CFO-12/2/2013

WEP-5

15/4/2011

31/5/2011

Crusher -1

24/01/2012

16/4/2012

24/01/2012

16/4/2012

24/01/2012

16/4/2012

In WEP-1 package for crushers CFE pending from DC (KRSC) , Bangalore meanwhile KSPCB has visited the site and issued SHOW CAUSE NOTICE to the
Contractor for operating crushers without CONSENTS. In WEP-2A package KSPCB granted CFE and CFO for crusher establishment and operation (NO
ISSUE). In WEP-3 CFE/CFO for both crushers from KSPCB granted to establishment and operate (Separate CFO applied on 19/9/2013 with fee). Crisher-3
(RIDL) plant relocated. In WEP-4 CFO for crusher and HMP is granted by KSPCB renewed up to dated 18/06/2014 and WEP-5 total required BOQ quantity
crushed, Contractor has been instructed for submission of planning of crusher.

Page 59 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

10.2 EMP Compliance


Enhancement of Water Bodies
Administrative approval for estimates of following four water bodies are approved and awarded. The
work is in progress and the status is given in the table below.
Table 41: Status of Water Bodies
Package
No

Link no

Name of
Lake/Village

WEP-1

67B: Hindgnala
Cross - Chinatmani
Bypass

irrigation tank
/Chinthamani

WEP-2

M7D

Lake/Hosur village

WEP-3

21B:Dharwad Saundatti

lake/ Aminbhavi

WEP-4

13B:-Devadurga Kalmala

Chainage

10+600

Benchi/Gabbur

Estimated
Cost US$
million

0.111

0.084

2+100
(RHS)

28+600

Total

Progress
75% of the work is completed.
Balance work was held up due to
dispute over a portion of lake land.
A modified estimate is prepared to
complete the work leaving dispute
land with the consent from Zilla
Panchayat before 31st Dec. 2013
De-silting work was suspended due
to monsoon. The tank is now full
with water and used for irrigating
the fields. Work will be resumed as
soon as the water level in the tank
is subsided and expected to be
completed before 30th April 2014.

0.197

Works completed in June 2013.

0.007

30 % of the work is completed.


Neighboring farmers have
demanded to demarcate the lake
boundary by joint survey. Local
Tahsildar is requested to fix the
boundary. Works expected to be
completed by 30th April 2014.

0.399

Construction of Noise Barrier


The construction of solid noise barriers are completed along project roads covering sensitive locations
such as government schools/colleges/hospitals/offices in all the WB-EPC& Annuity packages.
Independent Environment Monitoring (Pollution)
M/s. Deccan Consulting Engineers Private Limited, New Delhi has been appointed by KSHIP as a
independent Environmental Monitoring consultants. They have completed 1 st quarter monitoring of the
year 2013 during June-July 2013 and reported as generally satisfactory.
Forest Land Diversion
The status of forest land diversion is given in the table below.

Page 60 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Table 42: Details of Forest Land Diversion


Package

WEP1

WEP2A

Link No

67A

T8

Name of link

Hoskote - Hindignal cross

Haveri(NH4)-Hanagal

Extent(Ha)

Status

0.24

Stage-2
MOEF

Cleared

by

0.13

Stage-2
MOEF

Cleared

by

Stage 1
MOEF
WEP2B

M7D

Hanagal Tadasa

Remarks

cleared

by

T21

Shikaripua-Anandpuram

4.106

M7A

Shimoga-Shikaripura

4.678

M7B

Shikaripura-Anavatti

0.6786

Stage 1
MOEF

Anavatti-Hangal

0.141

Cleared

GOK is expected to
submit the stage-2
proposal to MOEF by
15th December 2013.

Cleared

MOEF expected to
clear stage 2 proposals
by 31st March 2014.

by

Stage 2 Compliance to
conditions of stage I is
under process.
Stage 1
MOEF

M7C

Forest Land taken over


and handed over to the
contractor for road
construction.

0.6
Stage-2 proposal with the
State Government

WAP3

Forest Land taken over


and handed over to the
contractor for road
construction.

Expected to be cleared
by 15th Jan 2014.

by

Stage 2 Proposal is under


review at MOEF.

Expected to be cleared
by 25th Feb 2014

Tree Cutting Status


The status of Tree cutting for EPC and Annuity packages are given below:

Page 61 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Table 43: Tree Cutting Status of EPC Package


Sl
No.

Link No.

Name of Link

Length in
Km

67A

Hoskote-Hindgnala Cross

23.5

67B

Hindgnala Cross-Chinatmani
Bypass

34

T8

Haveri (NH.4)-Hangal

31.8

M7D

Hangal-Tadasa

43.5

5
6
7
8

21B
13A
13B
6C

Dharwad-Saundatti
Thinthini-Devadurga
Devadurga-Kalmala
Chowdapur-Gulbarga
Total

38.53
32.45
41.35
28.67
268.8

No of Trees No of Trees
Marked
Cut

Pkg No

WEP1

WEP-2

WEP-3
WEP-4
WEP-5

Balance no of
Trees to be
Cut

Remarks

1934

1934

4014

4014

2065

2053

10

2502

2498

416
1231
1332
2695
16189

400
1231
1332
2695
16157

16

30

WAP-4

WAP-3

WAP-2

No of Trees
Marked

Total No, of
Trees Cut

Balance

Saved Trees

Remarks

63A

(NH209) Malavalli Maddur

22.8

777

407

153

217

Work will be completed by


30th April 2014

63B

Maddur - Huliyurdurga

27.53

1441

490

377

574

Work will be completed by


31st August 2014

63C

Huliyurdurga - Kunigai

21.11

2245

1234

1011

Work will be completed by


31st August 2014

63D

Kunigal - Tumkur (NH206)

35.19

1643

531

1112

Work will be completed by


31st August 2014

63E

Tumkur - Koratagere

27.9

586

285

206

95

Work will be completed by


31st August 2014

64F

Koratagere - Madhugiri

20.03

461

260

201

Work will be completed by


30 April 2014

64G

Madliugin - Pavaaada

35.79

1249

1094

155

Work will be completed by


30 April 2014

Name of
Link

Link No.

Length in
Km

WAP-1

Pkg No

Table 44: Tree Cutting Status of Annuity Package

I9A

Mudhol - Mahalingapura

19.17

1248

1248

19B

N'lahalingapura - Kabbur

42.35

2175

2164

11

19C

Kabbur - Chikkodi

18.41

752

748

19D

Clirkkodi - Nippani (NH4)

23.97

972

972

T21

Shikaripura - Anandapuram
(NH206)

32.24

1984

1904

80

M7A

Shimoga - Shikaripura

49.8

1500

1212

288

M7B

Shikaripura - Anvatti

45.29

2585

2503

82

M7C

Anvatti - Hangal

26.22

925

909

16

61.31

4027

3927

100

48.66

1965

1680

285

557.77

26535

19803

3708

3024

10A
10B

Managuli - Basavana
Bagewadi -Talikota
Talikoia - Hunasagi
Devapur
Total

Work will be completed by


31st May 2014

Work will be completed by


31st May 2014

Pollution Monitoring

Page 62 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

For each of the Contract Packages, monitoring of Ambient Air Quality, Water Quality, Noise Quality and
Soil Quality has been carried out as per the EMP. The Contractors last quarter Environment Pollution
Monitoring Status shown below.
Table 45: Environment Pollution Monitoring Status
Number of Locations where Samples were Collected

Package
Ref

Air Quality

Water Quality

Noise Quality

Soil Quality

WEP-1

WEP-2A

WEP-3

NIL

Remarks

WEP-4

Satisfactory Results reported.


Results received. Necessary
advise issued to Contractor
Results received. Necessary
advise issued to Contractor
Satisfactory Results reported.

WEP-5

NIL

NIL

NIL

NIL

Pollution monitoring not done

Borrow Area Management


The Borrow Area status with respect to environmental management plan for embankment / sub-grade
construction of each project is as shown in the table below.

Yet to be started

Qty Balance for use

16

NIL

WEP-2A

NIL

NIL

NIL

NIL

NIL

WEP-3

37

19

NIL

WEP-4

35

30

16

10

13

WEP-5

20

20

14

NIL

WEP-1

Rehabilitated

Ongoing

32

Contract
Package

Total No. of Borrow


Areas Identified

No. of
Borrow
Areas
approved
w.r.t. EMP

Exhausted

No. of Borrow Areas

Balance for
Rehabilitation

Table 46: Borrow Areas of the Contractors

Construction Material Management


The contractors for six packages WEP-1, WEP-2A, WEP-2B, WEP-3, and WEP-4 & WEP-5 (excluding
the terminated WEP-2 package) are procuring the construction materials from their own or pre-existing
quarries only after paying the applicable royalties and getting necessary consent/permission of the
Department of Mines & Geology and District Administration.

Page 63 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Table 47: Crushers/Quarry Production

Package

WEP-1
WEP-2
WEP-2A
WEP-3

WEP-4
WEP-5

Link No &
Crusher Capacity

67B, 200TPH
M7D, 120TPH
T8
21B, 200 TPH
21B, 120 TPH
21B, 120 TPH
13B, 250TPH
13B, 250TPH
6C, 200TPH

Quantity
extracted upto
Total Qty.
end of
required, (Tonne)
previous
month,
(Tonne)
776,849
546,047
Contract terminated
460

Balance
quantity
remaining,
(Tonne)
230,443
-

5,99,508

323716.87

275791.13

1,111,000

676546.64

434,453

425,213

398500

26713

Debris Disposal
The Debris Disposal Plan, with respect to Environment Management Plan, in each of the projects is
implemented by the Contractor using identified disposal sites. The surplus material, after all in-situ
applications, is disposed suitably for filling used borrow areas and other low lying areas.
Other debris generated from dismantling the existing road is stocked on site at locations shown by the
Employer for suitable future reuse, subject to the suitability of the materials and necessary approval and
further instruction of the Employer.
Prior permission Form
Application seeking prior permission from Architectural Survey of India (ASI) in link M7B and M7C are
forwarded to National Monument Authority, New Delhi, with recommendations by the Department of
Kannada and Culture, GOK. The NMA has cleared application pertaining to link M7B. M7C permission
is awaited. NMA is reminded on this issue.
Re-use of Scarified bitumen
A project on pilot basis has been undertaken in WEP-1 for the recycling of scarified materials to
resurface neighboring PWD road for a length of about 500 meters. The work is under progress and is
expected to be completed by 15 th December 2013. The findings will be shared with the WB for taking
further action in the matter.
ISO 14001 service for operationalising in KPWD
M/s.Allied Boston India Pvt.Ltd. New Delhi consultants engaged by KSHIP for operatinalising ISO
14001 in 14 offices of KPWD have completed task 3 including training for KPWD officers on
compliance of EMS and ISO 14001 requirement for auditing from 28-30 October 2013 in Bangalore. The
balance two tasks will be completed by 30th May 2014.
KSHIP has initiated procurement of third party auditing agency for accreditation support to fourteen
offices of KPWD. In this regard TOR has been approved by the World Bank. Request for EOI is
published and it is expected to complete the hiring process by 30 th March 2014.
Page 64 of 72

PIU-KSHIP

11.

Quarterly Progress Report 2 (1 July to 30 September 2013)

PERFORMANCE MONITORING INDICATORS

The Project Monitoring will be reported when due, as per the following tables.
Table 48: Project Development Objectives Monitoring
Outcome
Indicators
for Each
Component
Achievement
by GOK in
generating
at
least US$500
million in new
private sector
capital
(debt
and equity) for
CRN
improvement
and
management by
end-of-project
(EOP).
Share of Core
Road Network
in
good
condition (IRI <
4)
increases
from 50 percent
to 65 percent by
EOP.

Uni
t of
Me
asu
re

US$
mill
ion

Km
(%)

Baseline

Year

200.00
(Currentl
y raised
by
KRDCL
)

50%

YR 1
6/ 2011

YR 2
6/
2012

YR 3
6/2013

200
(KRDCLK
SHIP II)

50%

YR 4
6/2014

YR 5
6/ 2015

500 (KRDCL
+ KSHIP II)

65%

Frequency
and
Reports

Every two
years

Every two
years

Data Collection and Reporting


Respon
Data
sibility
Description
Collecti
for
(indicator
on
Data
definition
Instru
Collecti
etc.)
ments
on

PWD
Annual
Report,
KRDCL
Annual
Report

Asset
Manage
ment
Unit

PWD,
KRDCL

PWD

Status to end of
October, 2013

The indicator
will measure
private sector
debt and equity
raised as part of
the DBFOMT
concession and
by KRDCL as
part of the cofinancing, and
by KRDCL on
its own through
parallel
transactions.

KRDCL has identified 452


kms
of
SH
for
improvement
under
Highway
Co-financing
component of KSHIP-2.

Will measure
expansion of
road quality and
expansion in the
state

Out of 269 kms taken up


under WB EPC mode, BC
has been laid for a length
of 114.33 kms with IRI<
2000. Under ADB
contracts a length of 50
kms completed. Further
under SHDP a road length
of about 2000 kms taken
up for improvement of
which the IRI is yet to
collect.

Page 65 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Outcome
Indicators
for Each
Component

Uni
t of
Me
asu
re

Baseline

Year

15
percent
reduction
in
Vehicle
Operating Costs
and 25 percent
reduction
in
Travel
Time
Cost on project
corridors
by
EOP

US$
per
vehi
cleKm
s

VOC:
US$0.26
TT:
US$0.07
4

30
percent
reduction
in
road-accident
related fatalities
on safe corridor
pilots by EOP.

Nu
mbe
r of
fatal
ities
per
year

30 (on
Belgaum
to
Yeragatti
&
Maddur
to
Mysore
corridor)
*

YR 1
6/ 2011

YR 2
6/
2012

YR 3
6/2013

YR 4
6/2014

YR 5
6/ 2015

VOC:
US$0.20
TT:US$0.06

30

27

21

Frequency
and
Reports

When the
road
construction
is completed

Every two
years

Data Collection and Reporting


Respon
Data
sibility
Description
Collecti
for
(indicator
on
Data
definition
Instru
Collecti
etc.)
ments
on

Asset
Manage
ment
Unit

M&E
Report
on safe
corridors
pilot

PWD

PWD

Will measure
the impact of the
project on road
users

Will measure
ability of the
project to show
measureable
results on road
safety

Status to end of
October, 2013

Out of 269 kms taken up


under WB EPC mode, BC
has been laid for a length
of 114.33 kms with IRI<
2000. Under ADB
contracts a length of 50
kms completed. Travel
time reduction will be
evaluated at EOP.
DPR for SH-20 (YaragattiBelgaum), agreement
signed in the month of 17th
Oct 2013. It is expected to
be issued tender
notification by December2013 for SH-20 project
(Belgaum to Yaragatti
section).

Intermediate Results
Component-1: Road Improvement Component
Completion of
upgrading and
widening
of
about 269 km.
through item
rate contracts

Km /
Proc
urem
ent
mile
ston
es.

Contracts
awarded

100 kms
road
construc
tion
substanti
ally
complet
ed

269 km road
construction
completed

Project
Progress
Report
Every Year

PWD

The road works


are in various
stages. To end of
Dec, 2012 45 kms
have been
completed up to
BC level.

The road works are in


various stages. 114.33
kms have been completed
up to BC level.

Page 66 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Outcome
Indicators
for Each
Component
Completion of
upgrading,
widening
of
about 562 km.
through
DBFOMT
(Annuity)
Concessions

Uni
t of
Me
asu
re

Km./
Proc
urem
ent
mile
ston
es

Baseline

Year

YR 1
6/ 2011

YR 2
6/
2012

YR 3
6/2013

YR 4
6/2014

YR 5
6/ 2015

Frequency
and
Reports

Data Collection and Reporting


Respon
Data
sibility
Description
Collecti
for
(indicator
on
Data
definition
Instru
Collecti
etc.)
ments
on
Project
Progress
Report

RFQ
issued

562 Km
Constructi
on
Complete
d

Develop
ers hired

O&M phase
started

Every Year

PWD

Procurement
process in
progress. The RFP
have been
received and
opened on 05-122012. The RFP is
presently under
evaluation.

Status to end of
October, 2013

As the annuity bids did not


meet the VFM the tenders
have been cancelled and
processes are underway to
re-procure under item-rate
contracts. Bank
Suggested Reviewing the
DBFMOT Concession,
restructuring and
rebidding for four annuity
contracts.

Land acquisition and resettlement Implementation


(a)
Land
acquisition
completed
(Phase I)
(b) Key R&R
assistance
provided
(alternative
housing and
livelihood
support)- Phase
I
(c)
Improve
the living
standards
(measured
percent PAFs
with
increased/restor
ed
income/assets):
Phase I

Perc
enta
ge

0%

40%

70%

100%

Perc
enta
ge

0%

20%

40%

70%

Perc
enta
ge

0%

25%

100%

80%

Every Year

Project
Progress
Report

Every Year

Project
Progress
Report

Twice in the
project period

Project
Progress
Report,
R&R
Impact
Assessme
nt Report

EPC-Payment released99%, Annuity-15


notifications issued for
100% and 19 notification
issued for all links except
one (T21).

EPC-Non title holders100%


EPC-Title holders -99%
Annuity- Non Title
holders- 18.20%
Annuity- Title holders0.51%

Page 67 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Outcome
Indicators
for Each
Component

Uni
t of
Me
asu
re

Baseline

Year

Environmental Management
a)
Implementation
No.
0
of EMP as
agreed.
(b) ISO 14001
certification
obtained for
operational
units

YR 1
6/ 2011

YR 2
6/
2012

YR 3
6/2013

YR 4
6/2014

YR 5
6/ 2015

Frequency
and
Reports

Data Collection and Reporting


Respon
Data
sibility
Description
Collecti
for
(indicator
on
Data
definition
Instru
Collecti
etc.)
ments
on

As
awarded
PIU(HQ)
certified

1 field
division
certified

Every Year

Project
Progress
Report

PWD

Component-2: Highway Financing Modernization Component


Tolling
KRDCL
KRDCL
Poli Passing
started on
issues
generates
cy
of
selected
debt or
additional road
and
Tolling
roads
develops
user revenues
Insti Policy
PPP
and commits
tutio
transacti
them for
nal
on
mobilizing debt Acti
backed
by toll
financing (via
on
revenues
securitization)
and/or making
payments for
PPP
transactions
Km / Screening
CoDPR
Completion of
Proc
commenc
financing
complet
upgrading,
arrangem
ed
widening and O urem ed
ent
ent
& M of about
mile
establishe
400 km through ston
d;
co-financing
es
Transacti
arrangements
on

Every Year

Constructi
on
Complete
d

Every Year

Project
Progress
Report

Project
Progress
Report

Status to end of
October, 2013

Contract awarded to M/s


Allied Boston Pvt. Ltd,
New Delhi for
operationalising EMS in
14 offices of PWD.
Inception Report is
accepted. Consultants are
preparing Manuals

KRDCL

KRDCL

Tolling Policy is under


review of the Government.
Consultant (M/s IDECK)
has been mobilized by
KRDCL for preparing
bidding documents for
OMT concessions.

Adviser
engaged

Component-3:Road Safety Improvement Component

Page 68 of 72

PIU-KSHIP

Quarterly Progress Report 2 (1 July to 30 September 2013)

Outcome
Indicators
for Each
Component

Uni
t of
Me
asu
re

Baseline

Year

YR 1
6/ 2011

YR 2
6/
2012

YR 3
6/2013

YR 4
6/2014

YR 5
6/ 2015

Frequency
and
Reports

Data Collection and Reporting


Respon
Data
sibility
Description
Collecti
for
(indicator
on
Data
definition
Instru
Collecti
etc.)
ments
on

Status to end of
October, 2013

Lead Agency Established2009


Pilot Corridor identified
-2010

Effective
implementation
of Safe
Corridor Pilot

Polic
y
and
Instit
ution
al
Acti
ons

Lead
Agency
Establishe
d: pilot
corridor
identified

Consultan
t services
procured

Multisector
interve
ntion
implem
entatio
n
started

Multi-sector
intervention
completed

Minimum
3 star
rating
achieved
through
iRAP
investigati
on

Every Year

M&E
Report on
Safe
Corridors
Pilot
Annual
Report of
Road
safety
Cell

PWD /
Road
Safety
Cell

Road safety Cell


constituted in TD-2010-11
but yet to be staffed
Consultant Services
procured for Institutional
Capacity Building.
Road Safety Management
Consultants Procured2012.
iRAP Completed (3 *
rating obtained)
DPR is under preparation
for Engineering
interventions.
Interventions vetted by
experts and customized to
Karnataka Roads to
achieve 3 * rating.

Component -4: Road Sector Policy and Institutional Development Component


Satisfactory
implementation
of agreed
Action Plan for
institutional
development
and governance
improvement

Polic
y
and
Instit
ution
al
Acti
ons

IDSAP
and
GAAP
Endors
ed

Key
consultant
services
procured

Studie
s
Comp
leted

Recom
mended
actions
taken

Assessment
of IDSAP
and GAAP
results made

Key consultant services


procured-ongoing
HRD Manager ProcuredApr,13
Consultant appointed for
Implementation of GAAP
aspects- Apr,13
PMS Consultants procured.Oct, 12
EMS-ISO Certification
consultants procured.-Nov,12

Page 69 of 72

PIU-KSHIP

12.

Quarterly Progress Report 2 (1 July to 30 September 2013)

SEMINARS, WORKSHOPS AND TRAINING

The schedule of seminars, workshops and training conducted is given in the tables below.

Overall Status

% of Training
Complete

Total No. ManMonths Trained

Actual Start Date

Planned Start
Date

Description

Total No. of
Man-Months

Activity

No. of Trainees/
Participants

Table 49: Seminars, Workshops and Trainings conducted by PIU

Seminars, Workshops and trainings are not conducted in this Quarter

Overall Status

% of Training
Complete

Total No.
Man-Months
Trained

Actual Start
Date

Planned Start
Date

Total No. of
Man-Months

No. of
Trainees/
Participants

Packages

Description

Activity

Table 50: Seminars, Workshops and Trainings conducted by CSC

Seminars, Workshops and trainings are not conducted in this Quarter

Page 70 of 72

PIU-KSHIP

13.

Quarterly Progress Report 2 (1 July to 30 September 2013)

REPORT DELIVERY SCHEDULE

The report delivery detail is given in the table below.


Table 51: Report Delivery Schedule

12/12
10/01/13

Q4

Q3

Q2

Q1

2016

Q4

Q3

Q2

Q1

2015

Q4

Q3

Q2

Q1

Q4

Q3

Q2

Q1

Q4

30/03/13

Interim
Unaudited
Financial Report
(IUFR)

2014

8/13

8/12
10/10/12

Training Report

5/13

CSC Quarterly
Progress Report
(CSC-QPR)

10/7/12

Q3

2013

18/09/12

Quarterly
Progress Report
PCC

Q2

Reports listed in
Project and Loan
Agreements

Q1

2012

10/04/13

Annual Progress
Report

Page 71 of 72

Potrebbero piacerti anche