Report No: ISR8724

The World Bank


Implementation Status & Results

Public Disclosure Copy

Bosnia and Herzegovina


Sarajevo Waste Water Project (P090675)
Operation Name: Sarajevo Waste Water Project (P090675)

Product Line: IBRD/IDA

Project Stage:

Implementation

Seq.No: 5

Status: ARCHIVED

Country: Bosnia and Herzegovina

Approval FY:

Region: EUROPE AND CENTRAL ASIA

Lending Instrument: Specific Investment Loan

Archive Date:

27-Dec-2012

2010

Implementing Agency(ies):

Key Dates
Board Approval Date

22-Dec-2009

Original Closing Date 30-Nov-2015

Planned Mid Term Review Date 14-Jun-2013

Effectiveness Date

15-Jul-2010

Revised Closing Date 30-Nov-2015

Actual Mid Term Review Date

Last Archived ISR Date 19-Jun-2012

Project Development Objectives


Project Development Objective (from Project Appraisal Document)

Improve the living conditions of populations in the areas covered by the Sarajevo Water and Waste Water Company and in downstream riverside communities by: (a)
reducing the population's exposure to, and reliance on highly polluted water from the Miljacka and Bosna Rivers; and (b) improving the efficiency of the waste water
collection network in the Sarajevo Canton.
Has the Project Development Objective been changed since Board Approval of the Project?

Yes

No

Component(s)
Component Name

Component Cost

Component A: High Priority Infrastructure Rehabilitation

36.00

Component B: Institutional Development Support

0.50

Component C: Project management

0.50

Public Disclosure Copy

Overall Ratings
Previous Rating

Current Rating

Progress towards achievement of PDO

Satisfactory

Satisfactory

Overall Implementation Progress (IP)

Moderately Satisfactory

Moderately Satisfactory

Overall Risk Rating

Moderate

Moderate

Implementation Status Overview


The Project is proceeding satisfactorily toward meeting its Project Development Objectives. Overall, 24 contracts with an aggregate contract value of US$8 million are under
implementation with 17% of the project financing disbursed to date. Of these,13 contracts for priority investments to improve and rehabilitate the primary and secondary wastewater
networks of Sarajevo have been awarded, of which 10 have been completed. In terms of results, 9.6 km of sewage network has been repaired or rehabilitated of the 16 km. end of
project target. The Project is performing well against most result indicators. More than 20,000 household connections have benefited from sewage network rehabilitation, against an

Page 1 of 5

Report No: ISR8724

Public Disclosure Copy

The World Bank

CY 2012 target of 10,000. Sewage networks blockages have been reduced and exceed end of Project targets. Over 20,000 connections are benefiting from improved sanitation
network services. However, the Project still lags behind on the wastewater treatment results since this contract has not been awarded to date. Preliminary designs have been
completed, prequalification of contractors is nearly completed and bidding documents have been submitted for review. This contract is expected to be awarded by April 2013.
Substantial progress has been made under Component B in strengthening institutional systems, including improvements to the Sarajevo Water Utility Management Information
System. This is expected to improve the processing time for financial transactions and improved reporting across departments of the Utility.
Locations
Country

First Administrative Division

Location

Bosnia and Herz

Federation of Bosnia and Herzegovina

Sarajevo

Bosnia and Herz

Not Entered

Bosnia and Herzegovina

Bosnia and Herz

Federation of Bosnia and Herzegovina

Butila

Bosnia and Herz

Federation of Bosnia and Herzegovina

Kanton Sarajevo

Actual

Planned

Results
Project Development Objective Indicators
Indicator Name

Reduction in river pollution measured by


amount of BOD5 removed at the WWTP

Core Unit of Measure

Number

Baseline

Current

End Target

Value

0.00

0.00

8640.00

Date

22-Dec-2009

15-Dec-2012

30-Nov-2015

Comments

Public Disclosure Copy

Volume of waste water collected treated at


primary level (m3/day)

Cubic Meter(m3)

Preliminary design work


completed. Prequalification
process is close to finalized
and bidding documents have
been submitted and are being
revised based on Bank
comments.

Value

0.00

0.00

200000.00

Date

22-Dec-2009

15-Dec-2012

30-Nov-2015

Comments

Number of sewer connections benefiting from


rehabilitation works

Number

Collection is improved
through completion of 10 in
13 contracts awarded for
waste water network
rehabilitation. Treatment
plant rehabilitation expected
to commence by April 2013.

Value

0.00

20000.00

48000.00

Date

22-Dec-2009

15-Dec-2012

30-Nov-2015

Page 2 of 5

Report No: ISR8724

The World Bank

Public Disclosure Copy

Comments

Number of sewer blockages per year

Number

This figure represents the


number of connections for
which completed rehabilitation
works have been achieved to
date. There has been a
substantial increase to nearly
half the end of Project target.

Value

3300.00

2707.00

2900.00

Date

22-Dec-2009

15-Dec-2012

30-Nov-2015

Comments

People provided with access to "improved


sanitation facilities under the proj.

Number

Number of blockages
removed in 2012

Value

0.00

0.00

300000.00

Date

15-Dec-2012

15-Dec-2012

30-Nov-2015

Comments

People provided with access to improved


sanitation facilities - urban

This core indicator was just


introduced and will show
results once the rehabilitated
WWTP at Butila is in full
operation.

Number

Value

0.00

0.00

300000.00

Sub Type

Date

15-Dec-2012

15-Dec-2012

30-Nov-2015

Breakdown

Comments

Newly added sector core


indicator. All beneficiaries of
the WWTP rehabilitation are
located in the urban area.

Prequalification stage is near


completion. Bidding
documents have been
submitted and requested
revisions have been made.

Intermediate Results Indicators


Indicator Name

Public Disclosure Copy

Cumulative length of sewage collectors


repaired and/or rehabilitated (km)

Core Unit of Measure

Kilometers

Baseline

Current

End Target

Value

0.00

9.59

16.00

Date

22-Dec-2009

15-Dec-2012

30-Nov-2015

Comments

% of WWTP rehabilitation works completed

Percentage

There has been a substantial


increase in the cumulative
length of network repairs from
2.8 km to 9.59.

Value

0.00

0.00

100.00

Date

22-Dec-2009

15-Dec-2012

30-Nov-2015

Comments

Preliminary design is
completed; Prequalification is
nearly completed; Bidding

Page 3 of 5

Report No: ISR8724

The World Bank


documents have been
submitted and reviewed.
Percentage

Public Disclosure Copy

Increased revenues (in %)

Value

0.00

0.00

10.00

Date

22-Dec-2009

15-Dec-2012

30-Nov-2015

Comments

Increased revenues will be


related to assessment of new
tariff for wastewater
treatment, as well as
improved efficiency of
operations and bill collection
supported under Component
B.

Data on Financial Performance (as of 08-Nov-2012)


Financial Agreement(s) Key Dates
Project

Ln/Cr/Tf

Status

Approval Date

Signing Date

Effectiveness Date

Original Closing Date

Revised Closing Date

P090675

IBRD-78420

Effective

22-Dec-2009

17-Mar-2010

15-Jul-2010

30-Nov-2015

30-Nov-2015

Disbursements (in Millions)


Project

Ln/Cr/Tf

Status

Currency

P090675

IBRD-78420

Effective

USD

Original

Revised

35.00

Cancelled

35.00

Disbursed

0.00

Undisbursed

5.36

28.92

% Disbursed

15.00

Public Disclosure Copy

Disbursement Graph

Page 4 of 5

Report No: ISR8724

Public Disclosure Copy

The World Bank

Key Decisions Regarding Implementation


No key decisions were made

Restructuring History
There has been no restructuring to date.