Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Activities
to
be
completed before RfP
issuance
Site identification and Land Acquisition for the Power Station for captive mine and land for power station in name of
Infrastructure SPV
Environmental Clearance for the Power station
Forest Clearance (if applicable) for the land for the Power Station
Connectivity and Long Term Open Access
Compilation of requisite Hydrological, Geological, Meteorological and Seismological data and preparation of a Detailed
Project Report (DPR) for Power Station as well as the Geological Reports for the Captive Coal blocks
Activities to be
completed before
Signing of Agrement or
Transfer of Operating
SPV
Infrastructure SPV shall transfer the critical land for the Power Station on a lease basis to the Operating SPV, however,
other responsibility under Land Acquisition Act will lie with Operating SPV. All actions for the remaining area of the
land required shall be taken by Operating SPV in the name of Infrastructure SPV, which then will be leased to Operating
SPV
Infrastructure SPV shall transfer the land that is sufficient to enable the Operating SPV/Seller to source coal required to
operate the Power Station at normative availability for a period of at least five years from the COD of 1st Unit of the
Power Station, on a lease basis, however, other responsibility under Coal Bearing Act, will lie with Operating SPV. All
actions for the remaining captive coal blocks required shall be taken by Operating SPV in the name of Infrastructure SPV,
which then will be leased to Operating SPV
Environmental Clearance and Stage I-Forest Clearance shouldve been obtained in name of Operating SPV
Procurers to appoint an Independent Engineer within 6 months of the effective date of Agreement
Disclaimer: This document is personal interpretation of mine and has nothing to do with organisational view or interest
Bidding Process
Publication of RfQ
ZERO DATE
Submission of Responses of
RFQ
Within 45 DAYS
Issuance of RFP
Within 75 DAYS
Successful bidder to be selected based on Levelised tariff based on escalation rates and discounting
factor determined by CERC from time to time basis.
Entire bidding process to be completed within 300 days, however, if it takes more than 730 days,
permission from central government must be required
Bid results, PPA signed must be made public
2. Analysis
Levelised tariff regime coming back with escalation rate defined by CERC
Separation of Infrastructure SPV and Operating SPV will mitigate the transfer pricing issues and related
party transactions significantly
Infrastructure SPV takes responsibility of land acquisition and captive coal block clearances only for
critical portion. The ultimate responsibility lies with Operating SPV
It is not clear whether the LTA and connectivity will be granted at the time of PPA signing or not. Which
in present transmission congestion is the risk
It is not clear on who will determine the transfer pricing of the leasing right of Infrastructure SPV to
Operating SPV
Present Case 2 model, is plug and play model kind of for developers to come, set up, own and operate a
power station
Disclaimer: This document is personal interpretation of mine and has nothing to do with organisational view or interest