1. Attempt any five :

20

a) State any four purposes of estimating.


b) State different types of approximate estimates and explain any one briefly.
c) State any two situations when revised estimate and supplementary estimate
in required to be prepared.
d) Prepare approximate estimate of a building using following data :
i) Proposed built up area of the building is 135 sqm
ii) Similar type of structure is constructed with built up area 105 sqm and
the total cost of construction is 9,95,000 in nearby area last year.
iii) 10% increase in rate is observed in last twelve months.
e) Define the terms contingencies and work charged establishment.
f) Rule out the page of a standard measurement sheet and abstract sheet.
g) Prepare a face sheet for the detailed estimate of residential building with
following data :
i) Civil construction cost
ii) Contingencies

Rs. 11,65,300=00
5%

iii) Work charged establishment 2%


iv) Electrification
v) Water supply arrangement
vi) Sanitary arrangement

8%
5%
5%.

P.T.O.

12137

-2-

*12137*
MARKS

2. Attempt any four :

16

Calculate the quantities of following items of works by entering the same in


standard format of measurement sheet (Refer Fig. 1(a) and 1 (b)).

Fig. No. 1 (a)

*12137*

-3-

12137
MARKS

Fig. No. 1 (b)


a) Excavation for foundation
b) P.C.C. 1 : 4 : 8 in foundation and plinth
c) VCR masonry in CM 1 : 6 in foundation and plinth
d) Brick masonry in C.M. 1 : 6
e) R.C.C. slab in C.C. 1 : 11/2 : 3
f) 20 mm thick cement plaster in C.M. 1 : 4.
Use long wall short wall method.

12137

*12137*

-4-

MARKS
3. Attempt any two :

16

a) Work out the quantity of concrete and steel for 8 Nos. of R.C.C. footing
shown in Fig. No. 2.

Fig. No. 2
b) A simply supported beam resting on two wall supports of 300 mm thick with
clear distance between support is 4.5 m. The reinforcement provided in the
beam is as follows :
Top Bars
2 Nos. 10


Bottom bars
3 Nos. 12


Bentup bars
2 Nos. 16


Stirrups
6

Calculate the quantity of steel in the beam.


c) Analyse the rate for P.C.C. 1 : 4 : 8 in foundation and plinth.

150 mm c/c

*12137*

12137

-5-

MARKS
4. Attempt any two :

16

a) Calculate the quantity of cement and sand for the following :


i) 25 cum of P.C.C. 1 : 3 : 6
ii) 170 sqm of cement plaster 20 mm thick in C.M. 1 : 4.
b) Calculate the quantity of earthwork for road from the following data by using
mean area method :
Formation width = 10 m
Slope of banking = 2 : 1
Slope in cutting = 1.5 : 1

c) Refer Figure No. 3 and calculate the quantities of the following in respect of
under ground water tank :

12137

-6-

*12137*
MARKS

Figure No. 3
i) Excavation for foundation
ii) P.C.C. 1 : 4 : 8
iii) B.B. masonry in C.M. 1 : 6
iv) Internal cement plaster in C.M. 1 : 4.
5. Attempt any four :
16
a) Calculate the liftwise quantities of earth work for a well of 10 m diameter and
4.5 depth. The strata available from G.L. to 4.5 m depth is hard murum.
b) i) State the rules for deduction of plaster as per IS 1200.
ii) State the multiplying factors for taking the measurements of painting works
for the following :
1) A.C. Sheet corrugated
2) M.S. Grill
3) Flush door
4) Fully glazed window.
c) i) State any four factors to be considered while preparing the detailed
estimate.
ii) Define the check list and explain why the check list preparation is
necessary before the preparation of detailed estimate.
d) State any four factors affecting measurement sheet.
e) State four factors affecting task work.

*12137*

12137

-7-

MARKS
6. Attempt any four :

16

a) Enlist the data required for preparation of detailed estimate with necessity of
each.
b) State the factors affecting the rate analysis. Explain any one in details.
c) State any three methods for calculating the earth work for road. Explain any
one briefly.
d) Enlist the different types of detailed estimates and explain any one briefly.
e) Define task work. What is the task work for the following items ?
i) P.C.C. 1 : 4 : 8 in foundation
ii) B.B. Masonry in super structure
iii) R.C.C. Slab in C.C. 1 : 1.5 : 3
iv) 20 mm thick cement plaster in C.M. 1 : 6.
f) Define rate analysis and state any six purposes of rate analysis.
_________________