Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Project
Project:
A special type of process / transformation
A series of related jobs directed toward some
major output
Require time and resources
Examples
MS Windows 2000, Fund raising, Preparation for a
private party, Building a new airport
Reserve
Church
(1)
Decorate
Church
(3)
Choose
Cake (2)
Get Gifts
(1)
Start
Preparatio
ns
Church
Notice
(17)
Jacks
Catering
(10)
Rehearsal
Dinner (1)
Wedding
(April 22)
Choose
Pattern
(3)
Travel
from
Guatemala
(10)
Receive
Lace (8)
Choose
Invitation
s (3)
7
Prepare
Guest List
(4)
Invitation
s (12)
Fit Dress
(2)
Sew
Dress (11)
Address
Inv. (4)
Clean &
Press (2)
6
Inv. To
Post
Office (1)
Invitation
Lead Time
(10)
Project Management
Project management
Planning, directing, and controlling resources (people,
equipment, material) to meet the technical, cost, and time
constraints of the project.
Different aspects of PM
Team work
Leadership
We focus on technical aspect
Project Manager
Responsible for:
Work
Human Resources
Communications
Quality
Time
Costs
Project Management
Statement of work (SOW)
Objectives, work to be done, a proposed
schedule, performance measures (cost, time,
quality)
Level 2
Level 3
Level 4
Project
Example 1:
Clear Ocean Bay
Motion Pictures Ltd
Activity
Immediately
Predecessor
Durations
(weeks)
11
D Cast announcement
A,C
E Stage setting
F Music Recording
7.5
D,E,F
G Film shooting
Question
How long will it take to complete the
project?
When should each activity start?
Another Representation
AOA: Activity-on-arrow
Activity A immediately precedes D.
In our class, we use AON more frequently
D
1
C,8
E,8
B,11
F,7.5
A path is a sequence from Start to Finish.
The Start and finish nodes may be omitted.
G,7
Finish
A,6
19 28
0 6
D,9
A,6
Start
0 11
B,11
11 19
19 27
28 35
C,8
E,8
G,7
19 26.5
F,7.5
Question
How long will it take to complete
the project?
When should each activity start?
A,6
0 6
LS LF
0
A,6
13
19 28
19 27
11 19
13 19
Start
0
D,9
0 11
Critical path
C,8
B,11
11 19
28 35
E,8
20 28
19 26.5
0 11
F,7.5 1.5
Slack time = LF EF = LS ES
20.5
28
G,7
28 35
Slack Time = LF EF = LS - ES
13
1.5
A
C
D
E
F
G
11
19
28
35
Time
Immediately
Predecessor
Durations (days)
A Computer programming
B Implementation
C Drafting
D Proof reading
E Final write-up
B,D
B,3
7 + 3 + 2 = 12
E,2
Start
C,6
D,3
Problem
If we need to reduce the completion time of a
project, which activities should be crashed? by
how many units of time?
Partial crash is allowed : we can use crashing
program for any part of an activity
Partial crash is not allowed: an activity should
be carried out either with normal program, or
with crashing program, but not both.
The case when Partial crash is not allowed will
not be covered here.
Normal Time
Cost/day to expedite
$100
$150
$200
$150
$250
B,3
E,2
Start
C,6
D,3
Crashing -- Step 1
A,6
B,3
E,2
Start
C,6
D,3
Crashing -- Step 2
A,5
B,3
E,2
Start
C,6
D,2
Exercise 2:
Clear Ocean Bay Motion Pictures Ltd
In Example 1, we have
found that the project
takes 35 weeks.
Now for some reason, the
project needs to be
completed in 32 weeks.
Which activities would you
crash and by how many
weeks?
Idea: start from the
cheapest critical activity.
Activity
Normal
Time
Max
Crashing
Time
Cost/week
to expedite
40
11
300
200
80
60
7.5
0.5
100
500
Time-Cost Trade-Off:
To What Extent Should a Project be Crashed?
Total
cost
Expected indirect costs
Shorten
Cumulative
cost of crashing
CRASH
Shorten
Optimum
Time/Cost Tradeoff
Goal: To reduce the project duration by crashing
on selected activities as long as the benefit is
greater than the cost.
Crashing priorities:
critical activities
more economical
on more than more critical path
Example 3
Suppose a project consists of activities A,B,C,D,E
and F. The activities crashing can take place over a
wide range of reduction time. The cost per day of
reduction is as follows:
Activity Immed. Pred. Normal time (days) Cost/day to crash Low Time Limit
A
None
3
$450
1
B
None
4
$300
2
C
A
3
$200
1
D
A,B
2
$500
1
E
D
2
$100
1
F
C,E
4
$140
3
Example 3
A,3
C,3
F,4
Finish
Start
B,4
D,2
E,2
Example 3
1. Critical path: B-D-E-F. Crash E for one day,
with cost $100. --new completion time: 11
days
2. Critical path: B-D-E-F. Crashing F for one day,
with cost $140. ---- new completion time 10
days
3. Critical path: B-D-E-F. Cost for crashing one
day is at least $300, which is greater than
$150. Stop here.
Summary: Crash E and F for one day
respectively. The project will be finished in 10
days, with a crashing cost of $240.
Example
If we use mean activity duration, we have
E[tA] = 4.5
4.5
5
A
B
E[tB] = 5
F
9.5
S
E[tC] = 9.5
C
Example
In practice, there are four possibilities: corresponding to
these cases, the project completion times are 9, 10, 10,
10 respectively
The real mean project completion time should be 9.75
4
10
9
C
10
C
Immediate Expected
Predecesors
Time
None
7
None
5.333
A
14
A
5
C
11
D
7
B
11
E,F
4
G,H
18
6
ET(A)=42/6=7
Network
Duration = 54 Days
C(14)
E(11)
H(4)
A(7)
D(5)
F(7)
I(18)
B
(5.333)
G(11)
Probability Exercise
What is the probability of finishing this project in
less than 53 days?
P(t < D)
D=53
TE = 54
Z =
D - TE
cp
Pessim. - Optim. 2
Activity variance, = (
)
6
2
Task
A
B
C
D
E
F
G
H
I
= 41
P(t < D)
TE = 54
D=53
Z =
D - TE
cp
53- 54
=
= -.156
41
TE = 54
Z =
D - TE
cp
t
D=56
56 - 54
=
= .312
41
Review Problems
Page 802 to 807, problems 1.b, 2, 5.b, 14,
15, 16, 17.