Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
To: sam99@eim.ae
Date: Wed, 09 Mar 2011 12:29:42 -0800 (PST)
Subject: CESMM3 Diameter Range
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Thank you,
Best Regards,
Chandika
----- Original Message ----From: Abdullah
To: "sam99@eim.ae" <sam99@eim.ae>
Date: Thu, 10 Feb 2011 15:40:51 +0400
Subject: Question
Dear Professor,
I am one of your Alumni,
Can you please explain the following:
1-
Method of building up Star Rates, When and for what purpose are
these rates required? These are required either, to value an item of
work shown in the drawings but not measured in the BOQ of a remeasurement contract or, to value a variation for which an existing
BOQ rate is inapplicable. They are either, built-up from first principles
(i.e. cost/likely cost of resources plus OH&P), or derived from existing
rates. Star Rates is a colloquial expression.
2-
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
factors priced within the original rates should remain unchanged and the OH&P should be allowed
proportionately.
(No attachments should be sent with this short Q&A queries)
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Best regards,
George John,
Senior Quantity Surveyor
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Sincerely,
Nameer Yaseen
----- Forwarded Message ---From: "ramlalprk@yahoo.com" <ramlalprk@yahoo.com>
To: sma99@eim.ae
Sent: Sat, January 22, 2011 11:08:43 AM
Subject: Regarding clerification of doubt
Please clear for me the question,
1.If our contract value 105 M and 13M removed partially or fully, after total positive and negative
assessment,
The revised value of the contact is 97M
Professor please clear for me the following,
1. Do I have right to claim Over head? No. If however the 105 M includes any Provisional Sums
and Dayworks exceeding 18.34 M, then you may be able to claim the OH under-recovery.
2. Under which clause we can claim OH Sub-Clause 52.3 in FIDIC 4th Edition.
3.Is any clause state that if activity
removed
is less than 15 percent ,contractor
doesn't have right to claim Office over
Head, is it true It is inferred from 52.3. Also see handout of SCA Session 5 for more details.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Thanks professor ,
Ram Lal Pareek
Student
--- Original Message ----From: Jaseer
To: "Prof. Sam" <sam99@eim.ae>
Date: Sun, 02 Jan 2011 11:22:40 +0400
Subject: CA-Advanced class and one clarification related to SCA october class
will be same as that you forwarded through the flyer for the cancelled class in November.
If you have a revised copy of the flyer for the February class, please forward to me.
Apart from the above I would like to ask a question regarding last SCA class related to
the module Variation and Valuation of varied work. You have explained it very detail
and clear regarding the valuation of these works in the October SCA class. However just
for my better understanding I would like to ask one question that, can you give me a
very simple definition for Varied work and variation separately? So that I can
distinguish between them very easily
Variations are additions to, omissions from or alterations of the original scope of work.
"Varied work" includes Variations as well as other additional work which are named in
FIDIC-4th as "varied work", which are instructed under 17.1, 20.3, 31.2, 49.3 and 65.3
most of which are rectification/searching nature for defects etc. and providing facilities.
Since it is somewhat difficult to call them additions/omissions/alterations of the original
scope, this specific expression is used in FIDIC-4th.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Jasseer.E.P
Planning Engineer
GECO Mechanical & Electrical Ltd.
-----Original Message----From: thirimadura ariyaratna [mailto:ariyaratnat@yahoo.com]
Sent: Thursday, December 02, 2010 7:00 PM
To: sam99@eim.ae
Subject: Questions
Dear Professor,
Good evening, I am one of your student followed by the Sound Contract
Administration Course and also in between I have attended your SLQS
Seminars.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Contract
Sum
Contract
Period
x Delay
Allocable OH
8,171.
56
= 200,000,00
0.00
=
467days
=
1.77%
7.80%
200,000,00
0.00
467
Contract
Sum
Contract
Period
100
/
day
Delay
Allocable
Overhead
= 200,000,00
0.00
=
467days
=
7.80%
200,000,00
0.00
467
= 33,404
.71
As we learned during SCA session 6 Emden formula is used for both head office OH
and Profit in one formula which is,
/day
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder