Sei sulla pagina 1di 227

WS & SA DATA 2012-13

Muunicipal Allowance
0%
DATA FOR WATER SUPPLY AND SANITARY ITEMS
Description
Qty
Unit
Rate

Sl.No
1

Page-1

BMW-A

BMW-A.02

Supplying and laying, filling, jointing and testing SWG SP-1 pipe conforming to ISI 651 &
with air tight Cement joints in CM (1.5:1) prop. including excavation of trenches and socket
any soil (except rock requiring blasting) and refilling with watering and tamping to the required
including cost and conveyance of all materials to site and all labour charges , overhe
contractor profit etc., complete for finished item of work (APSS NO 1301 & 1318)
101.60mm dia upto 914.40mm (3')
depth
Rate as per SSR BMW-A.2
Add MA @ on Labour charges
Over head & Contractor profit 14%
Rate per 1 RM

BMW-A.03

152.40mm dia upto 914.40mm (3')


depth
Rate as per SSR BMW-A.4
Add MA @ on Labour charges
Over head & Contractor profit 14%

1.00 RM
0.00
0.14

408.00
216.00
408.00

1 RM

say

1.00 RM
0.00
0.14

614.00
216.00
614.00

1 RM

say

Rate per 1 RM
2

per Unit

Supplying and laying, filling, jointing and testing SWG SP-1 pipe conforming to ISI 651 w
tight Cement joints in CM (1.5:1) prop. including excavation of trenches and socket pits in an
(except rock requiring blasting) and refilling with watering and tamping to the required slope inc
cost and conveyance of all materials to site and all labour charges , overheads & contractor
etc., complete for finished item of work (APSS NO 1301 & 1318)
a) 203.20mm (8") dia upto 1524mm (5')
depth
Cost of SWG pipe BMW-A.17
labour charges for laying , jointing ,
testing
Add MA @ on Labour charges
Over head & Contractor profit 14%
Rate per 1 RM

b) 254mm (10")dia upto 1524mm (5')


depth
Cost of SWG pipe BMW-A.18
labour charges for laying, jointing,
testing
Add MA @ on Labour charges
Over head & Contractor profit 14%
Rate per 1 RM

1.00 RM

485.00

1 RM

1.00 RM
0.00

268.00
268.00

1 RM

0.14

753.00
say

1.00 RM

888.00

1 RM

1.00 RM
0.00

268.00
268.00

1 RM

0.14

1156.00
say

c) 300mm (12") dia upto 1524mm (5')


depth

296144668.xls

Page 1

WS & SA DATA 2012-13

Sl.No

Description
Cost of SWG pipe
labour charges for laying , jointing ,
testing
Add MA @ on Labour charges
Over head & Contractor profit 14%
Rate per 1 RM

Page-2

Qty
Unit
1.00 RM

Rate
1280.00

per Unit
1 RM

1.00 RM
0.00

268.00
268.00

1 RM

0.14

1548.00
say

Constructing 904.0 mm (30) dia brick masonry inspection chamber as per IS - 4111
1:1986 with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from app
source having a minimum crushing strength of 5 N/sq.mm including plastering with cement m
1:3 prop; thick both inside and outside fitted with 20 dia RCC manhole covers and f
including excavating pits up to a depth of 904 mm (3'-0") in all sorts of soils (exculding roc
laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benchin
channel 100 mm thick as per Standard specification and including cost and conveyance
materials like cement, sand, bricks, water etc., to site, cost of seigniorage charges on all ma
and all incidental and operational, labour charges like mixing cement mortar, constructing ma
lift charges, curing , overheads & contractors profit etc., complete for finished item of work
Standard specification.

Rate as per SSR BMW-B.1


Over head & Contractor profit 14%

1 No.
0.14

6530.00
6530.00

say

Rate per Each


4

Constructing 904.0 mm (30) dia brick masonry inspection chamber as per IS - 4111
1:1986 with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from app
source having a minimum crushing strength of 5 N/sq.mm including plastering with cement m
1:3 prop; thick both inside and outside fitted with 20 dia RCC manhole covers and f
including excavating pits up to a depth of 1524 mm (5'-0") in all sorts of soils (exculding
and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 ben
and channel 100 mm thick as per Standard specification and including cost and conveyance
materials like cement, sand, bricks, water etc., to site, cost of seigniorage charges on all ma
and all incidental and operational, labour charges like mixing cement mortar, constructing ma
lift charges, curing , overheads & contractors profit etc., complete for finished item of work a
Standard specification.

Rate as per SSR BMW-B.2


Overheads&Contractors Profit @14%

1 No.
0.14

10218.00
10218.00

Each

say

Rate per Each


5

Each

Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 prop. Masonry. Inspe


chamber upto 914.4 mm (3'0") and fitted with light weight 457.2 mm x 457.2 mm (1'6"x1'6
frame and cover of 20 Kg including cost and conveyance of all materials like cement, sand, b
water etc., to site, cost of seigniorage charges on all materials and all incidental and opera
labour charges like mixing cement mortar, constructing masonry, lift charges, curing , overhe
contractors profit etc., complete for finished item of work as per Standard specification.
Rate as per SSR BMW-B.06
Overheads&Contractors Profit @14%

1 No.
0.14

3672.00
3672.00

Each

say

Rate per Each


296144668.xls

Page 2

WS & SA DATA 2012-13

Sl.No
6

Description

Page-3

Qty

Unit

Rate

Supplying and fixing of SWG Gully traps 150mm x 100mm of ISI make confirming to IS
4127 with C.I grating & constructing cement brick masonry in CM (1:6) prop., intermediate ch
and fitted with 304.8 mm X 288.6 mm (12"x9") C.I Frame with hinged cover of standard ma
approved including cost and conveyance of all materials to site, labour charges, overhe
contractors profit etc., complete for finished item of work.
Rate as per SSR BMW-A.72
Deduct cost of CI frame and cover
Add for RCC Cover
Over head & Contractor profit 13.615%

1 No.
1 No.
1 No.

0.13615

568.00
101.00
100.00

say

Supplying and fixing CI Nahani traps 100 mm dia Inlet- 75 mm (3") outlet pipe - 4 Kg
quality ISI marked conforming to IS:1729-1979 with C.P. Grating fixing with white cement as p
requirements with standard practice for all floors including cost and conveyance of all mater
site, labour charges , overheads & contractors profit etc., complete for finished item of work.
Rate as per SSR BMW-c.41
Add MA @ on Labour charges

1 No.
0.00

329.00
55.00

Over head & Contractor profit 14%

0.14

329.00

1 Each

say

Rate per Each


8

1 Each
1 No.
1 No.

567.00

Rate per Each


7

per Unit

Supplying and fixing 580mm x 440mm long Orissa pan white glazed Water Closet 1st
ISI marked confirming to IS:2556-Part-3-1981 with "P" or "S" trap Hindware / Parryware / N
with brick - ISI mark and providing masonry seat, CC squatting plate and 10 litres capacity
flush PVC low level cistern Parryware or equivalent with internal components fixed on 2 Nos. o
wood blocks of size 76.20mm x 101.60mm using required size of nails, screws as approv
Engineer-in-charge, 12.70mm PVC connection with brass union nuts CP coated , 31.75mm
plumber union, P trap or S trap of Indian W.C. shall be encased on CC (1:2:4) 150mm alroun
above the joint to stop leakage at the joint etc., complete including cost and conveyance
materials to site, cost of CC bed, labour charges and seigniorage charges, overheads & contr
profit etc., complete for finished item of work.
BMW-D.04
Add MA on labour charges for fixing
Orissa pan
Cost of Brick masonry seat BMW-D.09
Cost of C C squatting plate BMW-D.10
Cost of slim line PVC flush tank 10 Ltrs.
capacity single flush BMW-G.08
12.70mm PVC connection with brass
union nuts BMW-I.48
Add MA on labour charges for fixing
PVC connection with brass union nuts
31.75mm brass plumber union BMWE.11

296144668.xls

1 No.
0.00

1440.00

1 Each

351.00

1 No.

298.00

1 Each

1 No.

89.00

1 Each

1 No.

1455.00

1 Each

1 No.

102.00

1 Each

0.00
1 No.

20.00
69.00

1 Each

Page 3

WS & SA DATA 2012-13

Sl.No

Description
Add MA on labour charges for fixing
31.75mm brass plumber union
Teak wood blocks 76.2mm x 101.6mm
BMW-I.42

Page-4

Qty

Unit

0.00
2 Nos.

Rate

per Unit

14.00
26.00

Add MA on labour charges for fixing


Teak wood blocks

0.00

9.00

Over head & Contractor profit 14%

0.14

3505.00

1 Each

Rate per Each


9

Supplying and fixing European Water Closet of 1st quality conforming to IS:2556-Part-2-1
Hindustan / Neycer or Parryware make white glazed with 'S' trap,supplying and fixing best
make plastic seat and lid for European water closets with rubber or plastic Buffers as per IS
1996 and 10 litres capacity single flush PVC low level cistern Parryware or equivalent with in
components and fixed using required size of nails and screws, 12mm PVC connections with
union nuts CP coated including cost and conveyance of all materials to site, overheads & contr
profit etc., complete for finished item of work for all floors.

Cost of EWC with 'S' trap TBSP-E.II-02


Add MA on labour charges for fixing
EWC
Supply and fixing of 10 lts. Capacity
lowdown PVC flushing tank TBSP-E.IV01

1 No
0.00

1964.00

1 Each

246.00

1 No

2534.00

1 Each

1 No

891.00

1 Each

Plastic seat and lid for European Water


Closet and rubber buffers TBSP-E.V-01
Add MA on labour charges for fixing
Plastic seat and lid for EWC and rubber
buffers
12.70mm dia PVC connection with
brass union nuts TBSP-J.I-32
Add MA on labour charges for fixing
PVC connection with brass union nuts
Cost of 76.2 x 101.60 mm teakwood
blocks TBSP-J.I-31
Add MA on labour charges for fixing
Teak wood blocks
Over head & Contractor profit 13.615%

0.00
1 No
0.00
2 Nos

71.00
102.00

1 Each

20.00
26.00

0.00

9.00

0.13615

5543.00

1 Each

Rate per Each

296144668.xls

Page 4

WS & SA DATA 2012-13

Sl.No
10

Description

Page-5

Qty

Unit

Rate

Supplying and fixing Indian make Flat Back Wash Hand Basin (HSW/Parryware/ Neyce
quality conforming to IS:2556-Part-4:1972 of size 550mm x 400mm with 32 mm nominal siz
Fitting with parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nomina
Chromium Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/Senior/Nice or equ
complete with standard CI brackets including wooden blocks ,1 No.12.70mm PVC connectio
brass union nuts CP coated , 1 No.12.70mm NP bib tap 400 gms Seiko or equivalent , 31.75m
PVC flexible waste pipe 914.4mm length of 1st quality including cost and conveyance of all ma
to site, labour charges , overheads & contractors profit for finished item of work with single pilla

Cost of Wash hand basin TBSP-E.VI04


Add MA on labour charges for fixing
Wash hand basin
12.70mm NP bib tap (400gms) BMWE.07
Add MA on labour charges for fixing bib
tap
12.70mm dia PVC connection with
brass union nuts BMW-I.45
Add MA on labour charges for fixing
PVC connection with brass union nuts
Deduct cost of NP chain and rubber
plug BMW-I.18
31.75mm dia. PVC flexible waste pipe
BMW-G.05
Over head & Contractor profit 13.615%

1 No.
0.00
1 No.
0.00
1 No.
0.00

1782.00

407.00

1 Each

29.00
102.00

1 Each

20.00

1 No.

42.00

1 Each

1 No.

26.00

1 Each

0.14

2275.00
say

Supplying and fixing NP soap dish heavy type of approved make ISI quality with NP screw
complete including cost and conveyance of all materials, labour charges for fixing , overhe
contractors profit for finished item of work in all floors
Cost of NP soap dish BMW-I.28
Add MA @ on Labour charges

1 No.
0.20

243.00
12.00

Overheads&Contractors Profit @14%

0.14

245.40

1 Each

say

Rate per Each


12

1 Each

351.00

Rate per Each


11

per Unit

Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x 457.2mm , pl
back with NP screws 1st quality including cost and conveyance of all materials, labour cha
overheads & contractors profit for finished item of work in all floors.
Rate as per SSR BMW-I.105
Add MA @ on Labour charges

1 No.
0.00

513.00
116.00

Over head & Contractor profit 14%

0.14

513.00

Each

say

Rate per Each

296144668.xls

Page 5

WS & SA DATA 2012-13

Sl.No
13

Description

Page-6

Qty

Unit

Rate

Supplying and fixing of 25.4mm dia , 609.6mm long aluminium anodized towel rod
brackets and aluminium screws including cost and conveyance of all materials, labour cha
overheads & contractors profit for finished item of work.
Rate as per SSR BMW-I.20
Add MA @ on Labour charges

1 No.
0.00

164.00
44.00

Over head & Contractor profit 14%

0.14

164.00

Supplying and fixing 12.70mm dia NP push cock as approved by the Engineer-In-C
including cost and conveyance of all materials, labour charges , overheads & contractors
complete for finished item of work in all floors.
Rate as per SSR BMW-E.29
Over head & Contractor profit 14%

1 No.
0.14

271.00
271.00

Supplying and fixing NP bib taps of size 12.70mm dia of Indian make heavy
Seiko/Senior/Nice as approved by the Engineer-In-Charge including cost and conveyance
materials, labour charges , overheads & contractors profit complete for finished item of work
floors.
Rate as per SSR BMW-E.07
Add MA @ on Labour charges

1 No.
0.00

407.00
29.00

Over head & Contractor profit 14%

0.14

407.00

Supplying and fixing NP bib taps of size 12.70mm dia of Indian make heavy duty as app
by the Engineer-In-Charge including cost and conveyance of all materials, labour cha
overheads & contractors profit complete for finished item of work in all floors.
Rate as per SSR bmw-E.09
Add MA @ on Labour charges

1 No.
0.00

258.00
29.00

Over head & Contractor profit 14%

0.14

258.00

Each

say

Rate per Each


17

Each

say

Rate per Each


16

Each

say

Rate per Each


15

Each

say

Rate per Each


14

per Unit

Supplying and fixing Chrome plated bib cock cum health faucet with 1m long flexible tub
wall hook of Jaquar make queen series/Jupiter Aqua Lines-JAL or equivalent series as approv
Engineer-In-Charge with 7 years warranty with necessary fittings etc., complete including co
conveyance of all materials, labour charges , overheads & contractor profit complete for fin
item of work in all floors.
Rate as per SSR BMW-I.141
Over head & Contractor profit 14%

1 No.
0.14

4360.00
4360.00

Each

say

296144668.xls

Page 6

WS & SA DATA 2012-13

Sl.No

Description

18

Page-7

Qty

Unit

Rate

per Unit

Supplying and fixing of CI pipes Class "LA" for water, gas, sewage conforming to specif
No. IS : 1536/1989(Third revision) with amendment No.1&2 in standard lengths of 3.66m, 4
4.50m, 5.00m, 5.50m & 6.00m with lead joints and fixing all specials such as plug bends, of
single junctions, double junctions as per site requirement including painting black with Japan
including fixing of MS clamps if necessary with required number of Bombay nails including co
conveyance of all materials to site, labour charges etc., complete for finished item of work at a
levels. (APSS No. 1302 1319 & 1326)

a)

80mm dia. Pipe


Cost analysis for 8.00 RM
Cost of 80mm dia. CI pipe
Transportation
charges,
loading,
unloading and stacking @ 0.70%
Cost of specials (1.5%)
Lowering charges
Jointing charges
Rate per 8 RM
Over head & Contractor profit 14%

8.00 RM

760.00

1 RM

0.007
0.015
136.80 Kgs
1 Joint

6080.00
6080.00
1.02
595.07

1 Kgs
1 Joint

0.14

6948.37

Rate per 1 RM

b)

Say

100mm dia. Pipe


Cost analysis for 8.00 RM
Cost of 100mm dia. CI pipe
Transportation
charges,
loading,
unloading and stacking @ 0.70%
Cost of specials (1.5%)
Lowering charges
Jointing charges
Rate per 8 RM
Over head & Contractor profit 14%

8.00 RM

944.00

1 RM

0.007
0.015
173.87 Kgs
1 Joint

7552.00
7552.00
1.02
729.13

1 Kgs
1 Joint

0.14

8624.62

Rate per 1 RM

c)

Say

125mm dia. Pipe


Cost analysis for 8.00 RM
Cost of 125mm dia. CI pipe
Transportation
charges,
loading,
unloading and stacking @ 0.70%
Cost of specials (1.5%)
Lowering charges
Jointing charges
Rate per 8 RM
Over head & Contractor profit 14%

8.00 RM

1193.00

1 RM

0.007
0.015
226.13 Kgs
1 Joint

9544.00
9544.00
1.02
845.51

1 Kgs
1 Joint

0.14

10830.13

Rate per 1 RM

d)

Say

150mm dia. Pipe


Cost analysis for 8.00 RM
Cost of 150mm dia. CI pipe

296144668.xls

8.00 RM

1447.00

1 RM

Page 7

WS & SA DATA 2012-13

Sl.No

Description
Transportation
charges,
loading,
unloading and stacking @ 0.70%
Cost of specials (1.5%)
Lowering charges
Jointing charges
Rate per 8 RM
Over head & Contractor profit 14%

Page-8

Qty

Unit

0.007
0.015
283.20 Kgs
1 Joint
0.14

Rate
11576.00
11576.00
1.02
1068.30

Say

200mm dia. Pipe


Cost analysis for 8.00 RM
Cost of 200mm dia. CI pipe
Transportation
charges,
loading,
unloading and stacking @ 0.70%
Cost of specials (1.5%)
Lowering charges
Jointing charges
Rate per 8 RM
Over head & Contractor profit 14%

8.00 RM
0.007
0.015
411.73 Kgs
1 Joint
0.14

2113.00
16904.00
16904.00
1.02
1562.38

1 Kgs
1 Joint

Say

250mm dia. Pipe


Cost analysis for 8.00 RM
Cost of 250mm dia. CI pipe
Transportation
charges,
loading,
unloading and stacking @ 0.70%
Cost of specials (1.5%)
Lowering charges
Jointing charges
Rate per 8 RM
Over head & Contractor profit 14%

8.00 RM

2847.00

1 RM

0.007
0.015
556.27 Kgs
1 Joint

22776.00
22776.00
1.02
1896.04

1 Kgs
1 Joint

0.14

25740.51

Rate per 1 RM

A)

1 RM

19258.23

Rate per 1 RM

f)

1 Kgs
1 Joint

13187.84

Rate per 1 RM

e)

per Unit

Say

Lowering charges of CI pipes


PHE-LCIS-1(Page 864)
Assumption 10m
200mm dia. CI PIPES 5m long(Class - A)
Weight : 514 Kgs
Labour
Plumber 1st Class
Plumber 2nd Class
Man Mazdoor

Add MA @ on Labour charges

0.102 Nos.
0.238 Nos.
1.33 Nos.
0.20

350.00
285.00
250.00
436.03

1 Each
1 Each
1 Each

Rate per 1 Kg
B)

Jointing charges of CI pipes


PHE-JCIS-1(Page 868)

296144668.xls

Page 8

WS & SA DATA 2012-13

Sl.No

Description
a)

80mm dia. Pipe


Details of cost for 10 joints

i)

Labour
Plumber 1st Class
Plumber 2nd Class
Man Mazdoor

ii)

Add MA @ on Labour charges


Material
Fuel wood
Kerosene
Spun yarn (Page - 397, S.No.5)
Pig lead (Page - 397, S.No.1)

Page-9

Qty

Unit

Rate

per Unit

350.00
285.00
250.00
438.45

1 Each
1 Each
1 Each

600.00
40.00
105.00
264.00

1 quintal
1 Ltr
1 Kg
1 Kgs

350.00
285.00
250.00
603.05

1 Each
1 Each
1 Each

600.00
40.00
105.00
264.00

1 quintal
1 Ltr
1 Kg
1 Kgs

350.00
285.00
250.00
603.05

1 Each
1 Each
1 Each

600.00
40.00
105.00
264.00

1 quintal
1 Ltr
1 Kg
1 Kgs

0.270 Nos.
0.630 Nos.
1.65 Nos.
0.00

350.00
285.00
250.00
686.55

1 Each
1 Each
1 Each

0.420 quintal

600.00

1 quintal

0.135 Nos.
0.320 Nos.
1.20 Nos.
0.00
0.190
0.330
1.00
20.00

quintal

Ltr
Kg
Kgs

Rate per joint


b)

100mm dia. Pipe


Details of cost for 10 joints

i)

Labour
Plumber 1st Class
Plumber 2nd Class
Man Mazdoor

ii)

Add MA @ on Labour charges


Material
Fuel wood
Kerosene
Spun yarn (Page - 397, S.No.5)
Pig lead (Page - 397, S.No.1)

0.220 Nos.
0.530 Nos.
1.50 Nos.
0.00
0.250
0.330
1.80
24.00

quintal

Ltr
Kg
Kgs

Rate per joint


c)

125mm dia. Pipe


Details of cost for 10 joints

i)

Labour
Plumber 1st Class
Plumber 2nd Class
Man Mazdoor

ii)

Add MA @ on Labour charges


Material
Fuel wood
Kerosene
Spun yarn (Page - 397, S.No.5)
Pig lead (Page - 397, S.No.1)

0.220 Nos.
0.530 Nos.
1.50 Nos.
0.00
0.370
0.700
2.00
28.00

quintal

Ltr
Kg
Kgs

Rate per joint


d)

150mm dia. Pipe


Details of cost for 10 joints

i)

Labour
Plumber 1st Class
Plumber 2nd Class
Man Mazdoor

ii)

Add MA @ on Labour charges


Material
Fuel wood

296144668.xls

Page 9

WS & SA DATA 2012-13

Sl.No

Description
Kerosene
Spun yarn (Page - 397, S.No.5)
Pig lead (Page - 397, S.No.1)

Page-10

Qty

Unit

Rate

per Unit

0.760 Ltr
2.00 Kg
36.00 Kgs

40.00
105.00
264.00

1 Ltr
1 Kg
1 Kgs

0.270 Nos.
0.630 Nos.
1.65 Nos.
0.00

350.00
285.00
250.00
686.55

1 Each
1 Each
1 Each

600.00
40.00
105.00
264.00

1 quintal
1 Ltr
1 Kg
1 Kgs

350.00
285.00
250.00
733.25

1 Each
1 Each
1 Each

600.00
40.00
105.00
264.00

1 quintal
1 Ltr
1 Kg
1 Kgs

Rate per joint


e)

200mm dia. Pipe


Details of cost for 10 joints

i)

Labour
Plumber 1st Class
Plumber 2nd Class
Man Mazdoor

ii)

Add MA @ on Labour charges


Material
Fuel wood
Kerosene
Spun yarn (Page - 397, S.No.5)
Pig lead (Page - 397, S.No.1)

0.560
0.756
3.00
54.00

quintal

Ltr
Kg
Kgs

Rate per joint


f)

250mm dia. Pipe


Details of cost for 10 joints

i)

Labour
Plumber 1st Class
Plumber 2nd Class
Man Mazdoor

ii)

Add MA @ on Labour charges


Material
Fuel wood
Kerosene
Spun yarn (Page - 397, S.No.5)
Pig lead (Page - 397, S.No.1)

0.280 Nos.
0.650 Nos.
1.80 Nos.
0.00
0.650
1.140
3.50
66.00

quintal

Ltr
Kg
Kgs

Rate per joint


19

Supplying and fixing of SWR PVC pipes (Prince/Sudhakar/Kisan/Supreme or any ISI bra
Kg/Sq.cm. and fixing all special such as plain bends, off sets, door bends, single junctions, d
junctions as per site requirement, fixing with PVC clamps if necessary with required num
Bombay nails including cost and conveyance of all materials to site, labour charges, overhe
contractors profit complete for finished item of work at all floor levels. (APSS No. 1302 1
1326)
a) 75mm dia
Data for 6 RM
Cost of 75mm dia pipe BMW-G.10
Cost of PVC clamps BMW-I.101
Labour charges BMW-G.152
Rate per 1 RM
Over head & Contractor profit 14%

6.00 RM
3 Nos.
6.00 RM

255.00
25.00
65.00

0.14

162.50

3 RM
Each
1 RM

say

296144668.xls

Page 10

WS & SA DATA 2012-13

Sl.No

Description
b) 90mm dia
Data for 6 RM
Cost of 90mm dia pipe BMW-G.21
Cost of PVC clamps BMW-I.101
Labour charges BMW-G.152
Rate per 1 RM
Over head & Contractor profit 14%

Page-11

Qty

Unit

Rate

6.00 RM
3 Nos.
6 RM

405.00
25.00
65.00

0.14

212.50

per Unit

3 RM
Each
1 RM

say
c) 110mm dia
Data for 6 RM
Cost of 110mm dia pipe BMW-G.13
Cost of PVC clamps BMW-I.101
Labour charges
Rate per 1 RM
Over head & Contractor profit 14%

6.00 RM
3 Nos.
6 RM

484.00
25.00
58.00

0.14

231.83

3 RM
Each
1 RM

say
20

Supplying & fixing GI pipe Medium Grade properties & weight as per IS 1239 ISI m
ground or on wall including cost of tees, elbows, bends, reducers, couplings, running joints,
flanges, unions etc. with necessary excavation in all types of soils except rock requiring bla
refilling, chiselling masonry walls and making good the walls & floors to the original surfac
fixing MS clamps on TW blocks on walls including cost and conveyance of all materials and
charges , overheads & contractors profit complete for finished item of work.
a) 15mm Nominal bore
Rate as per SSR BMW-F.79
Add MA @ on Labour charges
Over head & Contractor profit 14%

1.00 RM
0.00

185.00
41.00

0.14

185.00

1 RM

say

Rate per 1 RM
b) 20mm Nominal bore
Rate as per SSR BMW-F.81
Add MA @ on Labour charges
Over head & Contractor profit 14%

1.00 RM
0.00

206.00
41.00

0.14

206.00

1 RM

say

Rate per 1 RM
c) 25mm Nominal bore
Rate as per SSR BMW-F.83
Add MA @ on Labour charges
Over head & Contractor profit 14%

1.00 RM
0.20

270.00
41.00

0.14

278.20

1 RM

say

Rate per 1 RM
d) 32mm Nominal bore

296144668.xls

Page 11

WS & SA DATA 2012-13

Sl.No

Description
Rate as per SSR BMW-F.85
Add MA @ on Labour charges
Over head & Contractor profit 14%

Page-12

Qty
Unit
1.00 RM
0.00
0.14

Rate
379.00
41.00
379.00

say

Rate per 1 RM
e) 40mm Nominal bore
Rate as per SSR BMW-F.87
Add MA @ on Labour charges
Over head & Contractor profit 14%

1.00 RM
0.00

424.00
44.00

0.14

424.00

f) 50mm Nominal bore


Rate as per SSR BMW-F.89
Add MA @ on Labour charges
Over head & Contractor profit 14%

1.00 RM
0.00

457.00
67.00

0.14

457.00

1 RM

say

Rate per 1 RM

Supplying and fixing 65 mm Nominal Bore GI pipe Medium Grade properties & weight
IS 1239 in ground or on wall with GI fittings such as elbows tees couplings, nipples, plugs inc
excavation for trenches and refilling the trenches ,chiselling masonry walls and making goo
walls & floors to the original surface and fixing MS clamps on TW blocks on walls including co
conveyance of all materials and labour charges , overheads & contractors profit comple
finished item of work except for GI bends union and GI connectors with checkout and socket T
Zenith make or equivalent
Rate as per SSR BMW-F.91
Over head & Contractor profit 14%

1.00 RM
0.14

811.00
811.00

1 RM

say

Rate per 1 RM
22

1 RM

say

Rate per 1 RM

21

per Unit
1 RM

Supplying and fixing Gunmetal Gate ( GM peet ) valve as per IS-778 Class - I , Indian
heavy type including cost and conveyance of all materials , labour charges , overhea
contractors profit complete for finished item of work.
a) 15mm Nominal bore
Rate as per SSR BMW-F.21
Add MA @ on Labour charges
Over head & Contractor profit 14%

1 No.
0.00

459.00
44.00

0.14

459.00

Each

say

Rate per Each


b) 20mm Nominal bore
Rate as per SSR BMW-F.19
Add MA @ on Labour charges
Over head & Contractor profit 14%

1 No.
0.00

621.00
44.00

0.14

621.00

Each

say

Rate per Each

296144668.xls

Page 12

WS & SA DATA 2012-13

Sl.No

Description
c) 25mm Nominal bore
Rate as per SSR BMW-F.17
Add MA @ on Labour charges
Over head & Contractor profit 14%

Page-13

Qty

Unit

Rate

1 No.
0.20

914.00
44.00

0.14

922.80

Each

say

Rate per Each


d) 32mm Nominal bore
Rate as per SSR BMW-F.23
Add MA @ on Labour charges
Over head & Contractor profit 14%

1 No.
0.00

1368.00
44.00

0.14

1368.00

Each

say

Rate per Each


e) 40mm Nominal bore
Rate as per SSR BMW-F.25
Add MA @ on Labour charges
Over head & Contractor profit 14%

1 No.
0.00

1864.00
67.00

0.14

1864.00

Each

say

Rate per Each


f) 50mm Nominal bore
Rate as per SSR BMW-F.27
Add MA @ on Labour charges
Over head & Contractor profit 14%

1 No.
0.00

2692.00
90.00

0.14

2692.00

Each

say

Rate per Each


g) 65mm Nominal bore
Rate as per SSR BMW-F.29
Add MA @ on Labour charges
Over head & Contractor profit 14%

1 No.
0.00

5135.00
112.00

0.14

5135.00

Each

say

Rate per Each


h) 80mm Nominal bore
Rate as per SSR BMW-F.31
Add MA @ on Labour charges
Over head & Contractor profit 14%

1 No.
0.00

7268.00
133.00

0.14

7268.00

Each

say

Rate per Each


23

per Unit

Providing and placing on terrace (at all floor levels)polyetheylene water storage tank
double layer approved brand and manufacture with cover and suitable locking arrangemen
making necessary holes for inlet and outlets and over flow pipes but without fittings and
support for tanks including cost and conveyance of all materials and labour charges , overhe
contractors profit complete for finished item of work.

296144668.xls

Page 13

WS & SA DATA 2012-13

Sl.No

Description
Rate as per SSR BMW-G.01
Over head & Contractor profit 14%

Page-14

Qty

Unit
1 Lt
0.14

Rate
6.00
1.00

say

Rate per 1 Ltr


24

Supplying and fixing of stainless steel sink of size 508.00mm x 457.2mm x 203.20mm,
thick of Indian make fixed on cantilever brackets including supply and fixing 31.75mm C.P.
coupling, 31.75 mm dia PVC flexible waste pipe of 914.4 mm length of Ist quality ncluding chi
brick masonry wall and making good & restoring to original surfaces , overheads & contractors
complete for finished item of work in all floors
Rate as per SSR BMW-I.123
Add MA @ on Labour charges

1 No
0.00

4905.00
449.00

Over head & Contractor profit 14%

0.14

4905.00

Supplying and fixing of stainless steel sink of size 914.4 mm x457.2mm, 1mm thick of
make fixed on cantilever brackets including supply and fixing 31.75mm C.P. waste coupling,
mm dia PVC flexible waste pipe of 914.4 mm length of Ist quality ncluding chiselling brick ma
wall and making good & restoring to original surfaces overheads & contractors profit compl
finished item of work in all floors.
Rate as per SSR BMW-I.119
Add MA @ on Labour charges

1 No
0.00

6865.00
506.00

Over head & Contractor profit 14%

0.14

6865.00

Each

say

Rate per Each


25

Each

say

Rate per Each


24

per Unit
1 Lt

Supplying and fixing white glazed flat back Bowl urinals of size 440 mm x 265 mm x 31
with integral flushing rim fixed with screws complete Indian make (HSW/Parry/Neycer) conform
IS:2556-1995 as approved by Engineer-in-charge, including supply and fixing 12.7mm
connection with brass plumber union nuts CP coated, 12.70mm push cock 1st quality of app
make , 31.75 mm dia PVC flexible waste pipe of 914.4 mm length of Ist quality including co
conveyance of all materials to site, labour charges , overheads & contractors profit comple
finished item of work for all floors.
Rate as per SSR BMW-D.33
Add MA @ on Labour charges BMWD.36
12.7mm PVC connections with brass
plumber union nuts bmw-i.48
Add MA @ on Labour charges
12.70mm NP push cock BMW-E.29
31.75mm dia. PVC flexible waste pipe
BMW-G.05
Over head & Contractor profit 14%

1 No

845.00

Each

0.00

140.00

1 No
0.00
1 No

102.00
20.00
271.00

Each

1 No

26.00

Each

0.14

Each

1244.00
Say

Rate per Each

296144668.xls

Page 14

WS & SA DATA 2012-13

Sl.No
26

Description

Page-15

Qty

Unit

Rate

Supplying and fixing white glazed flat back half stall urinals of size 590 mm x 375 mm
mm with integral flushing rim fixed with screws complete Indian make (HSW/Parry/N
conforming to IS:2556-1995 as approved by Engineer-in-charge, including supply and fixing 12
PVC connection with brass plumber union nuts CP coated, 12.70mm push cock 1st qua
approved make , 31.75 mm dia PVC flexible waste pipe of 914.4 mm length of Ist quality inc
cost and conveyance of all materials to site, labour charges etc., overheads & contractors
complete for finished item of work for all floors.
Rate as per SSR bmw-d.35
Add MA @ on Labour charges
12.7mm PVC connections with brass
plumber union nuts bmw-i.48
Add MA @ on Labour charges
12.70mm NP push cock BMW-E.29
31.75mm dia. PVC flexible waste pipe
BMW-G.05

1 No
0.00

2818.00
140.00

Each

1 No
0.00
1 No

102.00
20.00
271.00

Each

1 No

26.00

Each

Over head & Contractor profit 14%

0.14

Say

Supplying and fixing of 16mm to 20 mm thick polished marble slab partitioins of size 4' 0
0" for urinals including full rounding the edges , fixing in position, polishing, including cos
conveyance of all materials and labour charges , overheads & contractors profit comple
finished item of work for all floors.
Rate as per SSR BMW-B.14
Chiselling the brick masonry wall BMWI.05
Add MA @ on Labour charges
Rounding the edges of marble BMMV.11
Labour charges for fixing ( dadooing
labour charges )
Add MA @ on Labour charges
Over head & Contractor profit 14%

0.72 Sqm

999.00

1 Sqm

1.20 RM

28.00

1 RM

0.00

33.60

2.40 RM

348.00

1 RM

0.72 Sqm
0.00

446.00
32.11

10 Sqm

0.14

1620.19
Say

Rate per Each


28

Each

3217.00

Rate per Each


27

per Unit

Supplying and fixing of 101.60mm x 609.60mm white glazed porcelain channels 1st
fixed in brick masonry to the required slopes , white cement pointing including cost and conve
of all materials and labour charges , overheads & contractors profit complete for finished it
work for all floors.
Rate as per SSR BMW-I.125
Rate for 1 RM
Over head & Contractor profit 14%

1 No
(1/0.6096)
0.14

495.00
495.00
812.01

1 Each

Say
29

Construction of brick masonry support for GI pipe of size 304.80mm x 228.60mm x 228.6
in CM (1:8) prop including plastering and finishing with 12mm thick in CM (1:5) including co
conveyance of all materials and all labour charges, overheads & contractors profit comple
finished item of work for all floors.
Rate as per SSR BMW-I.63

296144668.xls

1 No

73.00

1 Each

Page 15

WS & SA DATA 2012-13

Sl.No

Page-16

Description

Qty
Unit
0.14

Over head & Contractor profit 14%

Rate
73.00

per Unit

Say

Rate per Each

S & Fixing of 50.8 GI union including all charges


Rate as per SSR 217
Add over head charges & contractor profit

14%
say

S & Fixing of 25.40 mm GI union including all charges


Rate as per SSR 214
Add over head charges & contractor profit
14%
say
S & Fixing of 12.70mm GI union including all charges
Rate as per SSR 212
Add over head charges & contractor profit
14%
say
Cutting holes in stone masonary including all charges
Rate as per SSR 639
Add over head charges & contractor profit

14%
say

Providing PVS SWR pipes of 75 mm dia including all accessories for Air Pipes
(per 3.00 Rm)
3.05
1.00
1.00
1.00
3.00
6.00

Rm
nos
nos
nos
nos
nos

Cost of PVC SWR


PVC SWR plain B
PVC SWR DOOR
Vent Cowl 432
clamps 438
Nails
Labour charges 486

Add over head charges & contractor profit

85
50
67
14
15
1

per Rm
Each
Each
Each
Each
Each

14%
say

3.05
1.00
1.00
1.00

Providing PVS SWR pipes of 110 mm dia including all accessories for Air pipes
(per 3.00 Rm)
Rm
Cost of PVC SWR
484 per Rm
nos
PVC SWR plain B
83 Each
nos
PVC SWR DOOR b
107 Each
nos
Vent Cowl 434
19 Each

296144668.xls

Page 16

WS & SA DATA 2012-13

Sl.No

Description
3.00 nos
6.00 nos

Page-17

Qty
Unit
Rate
per Unit
clamps 440
18 Each
Nails
1 Each
Labour charges 486

Add over head charges & contractor profit

14%
say

Supplying and fixing of SWR pipe of 75mm outer dia for drainage system including all charges with
excavation ( Cost per 3 RM)
1
1
1
1

Rm
nos
nos
nos

Cost of PVC SWR


77.33 per Rm
single Y 413
67 each
Double T 407
114 each
coupler 425
32 each
labour charges as per SWG pipe fixing rate

Add over head charges & contractor profit

14%
say

Supplying and fixing of SWR pipe of 110 mm outer dia for drainage system including all charges with
excavation
1
1
1
1

Rm
nos
nos
nos

Cost of PVC SWR


146.66 per Rm
single Y 418
155 each
Double T 409
236 each
coupler 427
52 each
labour charges as per SWG pipe fixing rate

Add over head charges & contractor profit

14%
say

Supplying and fixing PVC low level system with internal components 10 lits of white glazed
Rate as per SSR 342
Add over head charges & contractor profit

14%
say

Supply , Installation and commissioning approved make EWC CASCADE model P or S trap with porcelin cistern on E
with all components with matching colour seat cover of approved make with rubber byffer and cap 14 mm angle stop
450 mm long PVC inter
Rate as per SSR 151
Add over head charges & contractor profit

14%
say

Supplying and fixing of Oval Shape Basin white 520 x 410 mm parry or equivalent

296144668.xls

Page 17

WS & SA DATA 2012-13

Sl.No

Description

Page-18

Qty

Rate as per SSR 723


Add over head charges & contractor profit

Unit

Rate

per Unit

14%
say

Supplying and fixing Europeon type Hindustan / nycer type / Parry ware with S trap
Rate as per SSR 146
Add over head charges & contractor profit

14%
say

S & Fixing of 1/2 " dia piller cocks Jaquar make queen series 7 years warantly icluding all charges
chrome plated
Rate as per SSR item no 737
Add over head charges & contractor profit

14%
say

Supplying and fixing of Pedastal(with matching colour) for Wash Hand Basin (HSW/Parry/Earthenware)
Rate as per SSR item no 161
Add over head charges & contractor profit

14%
say

Supplying and fixing of 31.75 mm CP Bottle trap to the wash hand basin
Rate as per SSR item no 163
Add over head charges & contractor profit

14%
say

Supplying and fixing of soap dish Jaquar make queen series with 7 years warantly Ivory gold
Rate as per SSR item no 754
Add over head charges & contractor profit

14%
say

S & fixing of 1/2 " Angle Stop Cock includingall charges


Rate as per SSR item no 178
Add over head charges & contractor profit

14%
say

S & fixing of PVC whaste pipe of 38.10 mm including all charges


Rate as per SSR item no 340

296144668.xls

Page 18

WS & SA DATA 2012-13

Sl.No

Description
Add over head charges & contractor profit

Page-19

Qty

Unit
14%

Rate

per Unit

say
S & Fixing of 1/2 " Stop cocks
Rate as per SSR 186
Add over head charges & contractor profit

14%
say

S & fixing of PVC pipe with brass union nut


Rate as per SSR 642
Add over head charges & contractor profit

14%
say

Assistant Engineer
(R&B) Section, Sirsilla.

Execuitve Engineer
(R&B) Division Karimnagar

296144668.xls

Deputy Executive Engineer


(R&B) Sub - Division Sircilla

Suprentending Engin
(R&B) Circle, Karimn

Page 19

WS & SA DATA 2012-13

Page-20

296144668.xls

Page 20

Amount

ming to ISI 651 & 4127


ches and socket pits in
ng to the required slope
harges , overheads &
318)

408.00
0.00
57.12
465.12
465

614.00
0.00
85.96
699.96
700

ming to ISI 651 with air


socket pits in any soil
required slope including
eads & contractor profit

485.00
268.00
0.00
753.00
105.42
858.42
858

888.00
268.00
0.00
1156.00
161.84
1317.84
1318

WS & SA DATA 2012-13

Page-21

296144668.xls

Page 21

Amount
1280.00
268.00
0.00
1548.00
216.72
1764.72
1765

as per IS - 4111: Partmm thick from approved


ring with cement mortar
ole covers and frames
oils (exculding rock) and
C.C. 1:2:4 benching and
and conveyance of all
charges on all materials
r, constructing masonry,
hed item of work as per

6530.00
914.20
7444.20
7444

as per IS - 4111: Partmm thick from approved


ring with cement mortar
ole covers and frames
of soils (exculding rock)
d P.C.C. 1:2:4 benching
t and conveyance of all
charges on all materials
r, constructing masonry,
ed item of work as per

10218.00
1430.52
11648.52
11649

. Masonry. Inspection
57.2 mm (1'6"x1'6") C.I
e cement, sand, bricks,
dental and operational,
s, curing , overheads &
cification.
3672.00
514.08
4186.08
4186

WS & SA DATA 2012-13

Page-22

296144668.xls

Page 22

Amount

confirming to IS 651 &


., intermediate chamber
er of standard make as
charges, overheads &
568.00
-101.00
100.00
567.00
77.20
644.20
644

utlet pipe - 4 Kgs 1st


white cement as per site
yance of all materials to
d item of work.
329.00
0.00
329.00
46.06
375.06
375

Water Closet 1st quality


e / Parryware / Neycer
10 litres capacity single
s fixed on 2 Nos. of teak
screws as approved by
oated , 31.75mm brass
:4) 150mm alround well
and conveyance of all
overheads & contractors

1440.00
0.00
298.00
89.00
1455.00
102.00
0.00
69.00

WS & SA DATA 2012-13

Page-23

296144668.xls

Page 23

Amount
0.00
52.00
0.00
3505.00
490.70
3995.70
3996

IS:2556-Part-2-1973 of
and fixing best Indian
Buffers as per IS 2548equivalent with internal
connections with brass
overheads & contractors

1964.00
0.00

2534.00

891.00

0.00
102.00
0.00
52.00
0.00
5543.00
754.68
6297.68
6298

WS & SA DATA 2012-13

Page-24

296144668.xls

Page 24

Amount

Parryware/ Neycer) 1st


2 mm nominal size C.P.
h 15 mm nominal bore
enior/Nice or equivalent
m PVC connection with
uivalent , 31.75mm dia.
veyance of all materials
rk with single pillar cock

1782.00
0.00
407.00
0.00
102.00
0.00
-42.00
26.00
2275.00
318.50
2593.50
2594

ity with NP screws etc.,


or fixing , overheads &
243.00
2.40
245.40
34.36
279.76
280

m x 457.2mm , plywood
erials, labour charges ,
513.00
0.00
513.00
71.82
584.82
585

WS & SA DATA 2012-13

Page-25

296144668.xls

Page 25

Amount

dized towel rods with


erials, labour charges ,
164.00
0.00
164.00
22.96
186.96
187

he Engineer-In-Charge
ds & contractors profit
271.00
37.94
308.94
309

an make heavy duty


and conveyance of all
shed item of work in all
407.00
0.00
407.00
56.98
463.98
464

eavy duty as approved


rials, labour charges ,

258.00
0.00
258.00
36.12
294.12
294

m long flexible tube and


t series as approved by
plete including cost and
it complete for finished
4360.00
610.40
4970.40
4970

WS & SA DATA 2012-13

Page-26

296144668.xls

Page 26

Amount

forming to specification
ngths of 3.66m, 4.00m,
as plug bends, off sets,
black with Japan paint
nails including cost and
item of work at all floor

6080.00
42.56
91.20
139.54
595.07
6948.37
972.77
7921.14
990.14
990

17.1

85.5

21.734

108.67

28.266

141.33

7552.00
52.86
113.28
177.35
729.13
8624.62
1207.45
9832.07
1229.01
1229

9544.00
66.81
143.16
230.65
845.51
10830.13
1516.22
12346.35
1543.29
1543

11576.00

WS & SA DATA 2012-13

Page-27

296144668.xls

Page 27

Amount
81.03
173.64
288.86
1068.30
13187.84
1846.30
15034.13
1879.27
1879

35.4

177

51.466

257.33

69.534

347.67

16904.00
118.33
253.56
419.96
1562.38
19258.23
2696.15
21954.38
2744.30
2744

22776.00
159.43
341.64
567.40
1896.04
25740.51
3603.67
29344.18
3668.02
3668

35.70
67.83
332.50
87.21
523.24
1.02

WS & SA DATA 2012-13

Page-28

296144668.xls

Page 28

Amount

47.25
91.20
300.00
0.00
114.00
13.20
105.00
5280.00
5950.65
595.07

77.00
151.05
375.00
0.00
150.00
13.20
189.00
6336.00
7291.25
729.13

77.00
151.05
375.00
0.00
222.00
28.00
210.00
7392.00
8455.05
845.51

94.50
179.55
412.50
0.00
252.00

WS & SA DATA 2012-13

Page-29

296144668.xls

Page 29

Amount
30.40
210.00
9504.00
10682.95
1068.30

94.50
179.55
412.50
0.00
336.00
30.24
315.00
14256.00
15623.79
1562.38

98.00
185.25
450.00
0.00
390.00
45.60
367.50
17424.00
18960.35
1896.04

me or any ISI brand) 4


single junctions, double
ith required number of
r charges, overheads &
PSS No. 1302 1319 &

510.00
75.00
390.00
975.00
162.50
22.75
185.25
185

WS & SA DATA 2012-13

Page-30

296144668.xls

Page 30

Amount

810.00
75.00
390.00
1275.00
212.50
29.75
242.25
242

968.00
75.00
348.00
1391.00
231.83
32.46
264.29
264

er IS 1239 ISI mark in


gs, running joints, union
rock requiring blasting,
he original surface and
all materials and labour

185.00
0.00
185.00
25.90
210.90
211

206.00
0.00
206.00
28.84
234.84
235

270.00
8.20
278.20
38.95
317.15
317

WS & SA DATA 2012-13

Page-31

296144668.xls

Page 31

Amount
379.00
0.00
379.00
53.06
432.06
432

424.00
0.00
424.00
59.36
483.36
483

457.00
0.00
457.00
63.98
520.98
521

erties & weight as per


nipples, plugs including
s and making good the
walls including cost and
ors profit complete for
kout and socket Tata or
811.00
113.54
924.54
925

Class - I , Indian make


harges , overheads &

459.00
0.00
459.00
64.26
523.26
523

621.00
0.00
621.00
86.94
707.94
708

WS & SA DATA 2012-13

Page-32

296144668.xls

Page 32

Amount

914.00
8.80
922.80
129.19
1051.99
1052

1368.00
0.00
1368.00
191.52
1559.52
1560

1864.00
0.00
1864.00
260.96
2124.96
2125

2692.00
0.00
2692.00
376.88
3068.88
3069

5135.00
0.00
5135.00
718.90
5853.90
5854

7268.00
0.00
7268.00
1017.52
8285.52
8286

ater storage tank with


cking arrangement and
thout fittings and base
charges , overheads &

WS & SA DATA 2012-13

Page-33

296144668.xls

Page 33

Amount
6.00
0.14
6.14
6.14

mm x 203.20mm, 1mm
ng 31.75mm C.P. waste
uality ncluding chiselling
ads & contractors profit
4905.00
0.00
4905.00
686.70
5591.70
5592

m, 1mm thick of Indian


waste coupling, 31.75
chiselling brick masonry
ctors profit complete.for
6865.00
0.00
6865.00
961.10
7826.10
7826

m x 265 mm x 315 mm
y/Neycer) conforming to
d fixing 12.7mm PVC
1st quality of approved
uality including cost and
tors profit complete for

845.00
0.00
102.00
0.00
271.00
26.00
1244.00
174.16
1418.16
1418

WS & SA DATA 2012-13

Page-34

296144668.xls

Page 34

Amount

0 mm x 375 mm x 390
ke (HSW/Parry/Neycer)
upply and fixing 12.7mm
ush cock 1st quality of
h of Ist quality including
ads & contractors profit
2818.00
0.00
102.00
0.00
271.00
26.00
3217.00
450.38
3667.38
3667

itioins of size 4' 0" x 2'


ing, including cost and
ors profit complete for
719.28
33.60
0.00
835.20
32.11
0.00
1620.19
226.83
1847.02
1847

n channels 1st quality


ng cost and conveyance
ete for finished item of
495.00
812.01
113.68
925.69
926

28.60mm x 228.60 mm
1:5) including cost and
tors profit complete for
73.00

WS & SA DATA 2012-13

Page-35

296144668.xls

Page 35

Amount
10.22
83.22
83

137
19.18
156.18
156
Rm
75
10.5
85.5
86
Rm
41
5.74
46.74
47
Rm

67
9.38
76.38
76
Each

259.25
50
67
14
45
6
58
499.25
166.42
23.30
189.72
190
Rm

1476.20
83
107
19

WS & SA DATA 2012-13

Page-36

296144668.xls

Page 36

Amount
54
6
58
1803.20
601.07
84.15
685.22
685
Rm

77.33
67
114
32
58
348.33
48.77
397.10
397
Rm

146.66
155
236
52
58
647.66
90.67
738.33
738
Rm

1323
185.22
1508.22
1508
Each

celin cistern on EWC


4 mm angle stop cock

10925
1529.50
12454.50
12455
Each

WS & SA DATA 2012-13

Page-37

296144668.xls

Page 37

Amount
2105
294.70
2399.70
2400
Each

1438
201.32
1639.32
1639
Each

1533
214.62
1747.62
1748
Each

932
130.48
1062.48
1062
Each

368
51.52
419.52
420
Each

2088
292.32
2380.32
2380
Each

403
56.42
459.42
459
Each

81

WS & SA DATA 2012-13

Page-38

296144668.xls

Page 38

Amount
11.34
92.34
92
Each
196
27.44
223.44
223
Each
85
11.90
96.90
97
Each

ecutive Engineer
- Division Sircilla

prentending Engineer
B) Circle, Karimnagar

WS & SA DATA 2012-13

Page-39

296144668.xls

Page 39

WS & SA DATA 2012-13

Page-40

296144668.xls

Page 40

WS & SA DATA 2012-13

Page-41

296144668.xls

Page 41

WS & SA DATA 2012-13

Page-42

296144668.xls

Page 42

WS & SA DATA 2012-13

Page-43

296144668.xls

Page 43

WS & SA DATA 2012-13

Page-44

296144668.xls

Page 44

WS & SA DATA 2012-13

Page-45

296144668.xls

Page 45

WS & SA DATA 2012-13

Page-46

296144668.xls

Page 46

WS & SA DATA 2012-13

Page-47

296144668.xls

Page 47

WS & SA DATA 2012-13

Page-48

296144668.xls

Page 48

WS & SA DATA 2012-13

Page-49

296144668.xls

Page 49

WS & SA DATA 2012-13

Page-50

296144668.xls

Page 50

WS & SA DATA 2012-13

Page-51

296144668.xls

Page 51

WS & SA DATA 2012-13

Page-52

296144668.xls

Page 52

WS & SA DATA 2012-13

Page-53

296144668.xls

Page 53

WS & SA DATA 2012-13

Page-54

296144668.xls

Page 54

WS & SA DATA 2012-13

Page-55

296144668.xls

Page 55

WS & SA DATA 2012-13

Page-56

296144668.xls

Page 56

WS & SA DATA 2012-13

Page-57

296144668.xls

Page 57

BLD-CSTN

Andhra Pradesh Standard Data


Buildings
Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

659

BLD-CSTN

Index-code

S No Description
1

BLD-CSTN-1
BLD-CSTN-1-1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

MORTARS
1

Cement Mortar (1 : 1)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

kg.

1440.00

4848.76

6982.22

cum

1.05

134.23

140.94

cum

1.05

0.00

day

0.20

310.00

Add 25% for MC on Labour charges


Grand Total

BLD-CSTN-1-2

BLD-CSTN-1-4

BLD-CSTN-1-5

62.00

62.00

7185.15

7185.15

7185.15

7185.15

4654.81
140.94

Cement Mortar (1 : 1.5)


Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

BLD-CSTN-1-3

6982.22
140.94

Grand Total
Add 25% for MC on Labour charges
Grand Total
Cement Mortar (1 : 2)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Add 25% for MC on Labour charges
Grand Total
Cement Mortar (1 : 3)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Add 25% for MC on Labour charges
Grand Total
Cement Mortar (1 : 4)
Unit : 1cum
A. MATERIALS:
Cement

kg.

960.00

4848.76

4654.81

cum

1.05

134.23

140.94

cum

1.05

0.00

day

0.20

310.00

62.00

62.00

4857.75

4857.75

4857.75

4857.75

3491.11
140.94

kg.

720.00

4848.76

3491.11

cum

1.05

134.23

140.94

cum

1.05

0.00

0.00

0.20

310.00

62.00

62.00

3694.04

3694.04

3694.04

3694.04

day

kg.

480.00

4848.76

2327.41

2327.41

cum

1.05

134.23

140.94

140.94

cum

1.05

0.00

0.00

0.20

310.00

62.00
2530.34

2530.34

2530.34

2530.34

1745.55

1745.55

day

kg.

360.00

4848.76

62.00

660

BLD-CSTN

Index-code

S No Description
1

Sand (including 5% wastage)


Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Add 25% for MC on Labour charges
Grand Total

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

cum

1.05

134.23

140.94

cum

1.05

0.00

0.00

day

0.20

310.00

140.94

62.00

62.00

1948.49

1948.49

1948.49

1948.49

661

BLD-CSTN

Index-code

BLD-CSTN-1-6

S No Description
1

Cement Mortar (1 : 5)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg.

288.00

4848.76

1396.44

cum

1.05

134.23

140.94

cum

1.05

0.00

0.00

0.20

310.00

1396.44
140.94

day

Grand Total

62.00

62.00

1599.38

1599.38

1599.38

1599.38

1163.70
140.94

Add 25% for MC on Labour charges


Grand Total

BLD-CSTN-1-7

BLD-CSTN-1-8

Cement Mortar (1 : 6)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Add 25% for MC on Labour charges
Grand Total
Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Add 25% for MC on Labour charges
Grand Total

kg.

240.00

4848.76

1163.70

cum

1.05

134.23

140.94

cum

1.05

0.00

0.00

0.20

310.00

day

62.00

62.00

1366.64

1366.64

1366.64

1366.64

872.78
140.94

kg.

180.00

4848.76

872.78

cum

1.05

134.23

140.94

cum

1.05

0.00

0.00

0.20

310.00

62.00
1075.71

1075.71

1075.71

1075.71

day

62.00

662

ROAD METAL RATES (FOR SSR 2014-15) Excluding Seigniorage charges


NAME OF WORK ::-

Construction of Community Hall Building at Chinna Mulkanur in Karimnagar District.

Conveyan
ce charges
Lead in
excluding
Kms
over head
charges

Sl.N
o

Description of Metal

Source of Supply

Mannual
loading
including
idle
charges
and
excluding
over head
charges

Unloading
charges
including
idle
charges
and
excluding
over head
charges

Conveyanc
e including
loading,unl
oading by
Material
machenary
rate as
,idle
per SSR
charge
excluding
over head
charges

Muncipal /
Blastin
Material
Machine
other
g
Initial
crushing Allowances
charge
Rate
charges
s

Toal Cost
per Cum

per unit

0%
12

13

14

40mmHBG metal SS 5

Qry in km 8/0 on
KK road

26.00

278.04

29.49

14.74

322.27

845.00

620.00

70.00

155.00

0.00

1167.27

Cum

25mmHBG metal SS 5

- DO -

26.00

278.04

29.49

14.74

322.27

1313.00

994.40

70.00

248.60

0.00

1635.27

Cum

20 mm HBG SS 5 M/C

- DO -

26.00

278.04

29.49

14.74

322.27

1365.00

1036.00

70.00

259.00

0.00

1687.27

Cum

12.5mm/13.2MM HBG
metal SS 5 M/C

- DO -

26.00

278.04

29.49

14.74

322.27

1097.00

821.60

70.00

205.40

0.00

1419.27

Cum

10mmHBG metal SS 5
M/C

- DO -

26.00

278.04

29.49

14.74

322.27

935.00

692.00

70.00

173.00

0.00

1257.27

Cum

6mmHBG metal SS 5
M/C

- DO -

26.00

278.04

29.49

14.74

322.27

735.00

532.00

70.00

133.00

0.00

1057.27

Cum

26.00

278.04

29.49

14.74

322.27

357.00

229.60

70.00

57.40

0.00

679.27

Cum

26.00
26.00
26.00
26.00

278.04
278.04
278.04
278.04

29.49
29.49
29.49
29.49

14.74
14.74
14.74
14.74

322.27
322.27
322.27
322.27

252.00
280.00
543.21
518.52

182.00
210.00
473.21
448.52

70.00
70.00
70.00
70.00

0.00
0.00
0.00
0.00

574.27
602.27
865.48
840.79
0.00

Cum
Cum
Cum
Cum
Cum

11.00

112.05

14.79

7.39

134.23

560.00

0.00

0.00

134.23

Cum

11.00

112.05

14.79

7.39

134.23

560.00

0.00

0.00

134.23

Cum

11.00

112.05

14.79

7.39

134.23

760.00

0.00

0.00

134.23

Cum

Stone crusher dust finer


than 3mm not more than
10% pass 0.075 sieve
7
8

RR Stone for Moasonry


rough Stone
CR Stone 30x30x45cm
CR Stone 30x30x60cm

Coarse Sand for concrete


Mortar
10 Coarse Sand for Filling
9

11 Fine Sand for Mortor

- DO - DO - DO - DO Mutnoor Godavary river


- DO - DO -

Gravel

12

13

14

160.21

Cum

5.00

46.03

14.79

7.39

68.21

92.00

92.00

11 Bricks 23x11x7

5.00

73.93

186.95

186.95

447.83

5000.00

5000.00

0.00

5447.83

1000 Nos

12 Modular Bricks 19x9x9


Fly Ash blocks
290x100x140
CRS stone
13 Cement
14 HYSD Steel
15 Mild Steel(6mm)

5.00

73.93

186.95

186.95

447.83

6000.00

6000.00

0.00

6447.83

1000 Nos

0.00

74.81

186.95

186.95

448.71

14000.00

0.00

14448.71 1000 Nos

26.00

278.04

29.49

14.74
48.76
58.35
58.35

322.27

332.00
4800.00
34000.00
40000.00

0.00
0.00
0.00

654.27
4848.76
34058.35
40058.35

Cum
MT
MT
MT

1122.63

Cum

Bond stone 24x24x45

Local
Local
Local
Qry in km 8/0 on
KK road

26.00

Rough Sahabad stone


1.00
0.00
110.20
55.10
41.32
25mm
Rough Sahabad stone
1.00
0.00
110.20
55.10
66.12
40mm
Note :- Mechanical loading with idle hire charges, Machnical unloading with idle hire charges is adoped.

262.00

70.00

1052.63

70.00

1650.00

1650.00

1691.32

10Sqm

1157.00

1157.00

1223.12

10Sqm

BLD-CSTN

Andhra Pradesh Standard Data


Buildings
Index-code

S No Description
1

2
Muncipal Allowance

EARTH WORK EXCAVATION

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

3
0.00

Earth work excavation and depositing on


bank with initial lead of 10m and initial lift
of 2m in Loamy & Clayey Soils like BC Soils,
Red Earth & Ordinary Gravelly Soils ( SS 20B) including shoring, strutting, sheeting,
planking and dewatering including cost of
hire charges of T & P, labour charges etc.,
complete for finished item of work for
Foundation of Building.(APSS No. 308)
Taking out put = 10 Cum
Light Mazdoor

Nos

3.64

310.00

Add 75% for excavation of foundation of cum


building

846.300

1128.40

1128.40

846.30

846.30

1974.70

1974.70

Add 20% Muncipal allowance

0.00

1974.70

Add 13.615% over heads

cum

1974.70

0.13615

0.00

268.86

Seigniorage charges

Cum

10.00

0.00

0.00

0.00

0.00
1974.70

Rate per 10 cum


Rate per 1 cum
2

2 Filling with useful available excavated earth


(excluding rock) in trenches, sides of
foundations and basement with initial lead
in layers not exceeding 15cm thick,
consolidating each deposited layer by
watering and ramming including all
operational, incidental, labour charges, hire
charges of T & P etc., complete for finished
item of work. (APSS NO. 309 & 310)
Unit =6Cum
Light Mazdoor
Nos
Add 20% Muncipal allowance
0.00

2243.56

197.00

224.00

0.31
96.10

310.00

96.10

0.13615
Total

0.00
96.10
16.02
16.00

cum
cum

6
3.12

160.21
310.00

KL

0.72

77.00

1983.92

0.13615

961.28
967.20
0.00
55.44
1983.92
270.11
2254.03
376.00

Add 13.165% over heads


Rate per 6cum
Rate per 1Cum
3

1974.70

96.10
0.00
96.10

3 Filling with Gravel in trenches, sides of


foundations and basement with initial lead
in layers not exceeding 15cm thick,
consolidating each deposited layer by
watering and ramming including all
operational, incidental, labour charges
(excluding
seignorage
charges)
hire
charges of T & P etc., complete for finished
item
ofOutput
work. (APSS
Taking
6 CumNO. 309 & 310)
Cost of Gravel
Light Mazdoor
MA
Water Charges
Total
Add 13.615% over heads
Rate per 6 Cum

cum
Rate per cum

Total

659

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Filling with Sand Cushion under footings


with initial lead in layers not exceeding
15cm thick, consolidating each deposited
layer by watering and ramming including
all operational & incidental charges, labour
charges,( excluding seignorage charge) hire
charges of T & P etc., complete for finished
item of work. (APSS NO. 309 & 310)
Cost of Sand
cum
Light Mazdoor
cum
MA
Add 14% over heads
cum
Rate per cum

1
0.31

134.23
310.00

134.23
96.10

0.14

32.25
262.57

230.33
Total

660

BLD-CSTN

Index-code

BLD-CSTN-1
BLD-CSTN-1-1

S No Description
1

MORTARS

Cement Mortar (1 : 1)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg.

1440.00

4848.76

6982.22

cum

1.05

134.23

140.94

cum

1.05

0.00

day

0.20

310.00

Add 25% for MC on Labour charges


Grand Total

BLD-CSTN-1-2

BLD-CSTN-1-4

BLD-CSTN-1-5

62.00

62.00

7185.15

7185.15

7185.15

7185.15

4654.81
140.94

Cement Mortar (1 : 1.5)


Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

BLD-CSTN-1-3

6982.22
140.94

Grand Total
Add 25% for MC on Labour charges
Grand Total
Cement Mortar (1 : 2)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Add 25% for MC on Labour charges
Grand Total
Cement Mortar (1 : 3)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Add 25% for MC on Labour charges
Grand Total
Cement Mortar (1 : 4)
Unit : 1cum
A. MATERIALS:
Cement

kg.

960.00

4848.76

4654.81

cum

1.05

134.23

140.94

cum

1.05

0.00

day

0.20

310.00

62.00

62.00

4857.75

4857.75

4857.75

4857.75

3491.11
140.94

kg.

720.00

4848.76

3491.11

cum

1.05

134.23

140.94

cum

1.05

0.00

0.00

0.20

310.00

62.00

62.00

3694.04

3694.04

3694.04

3694.04

day

kg.

480.00

4848.76

2327.41

2327.41

cum

1.05

134.23

140.94

140.94

cum

1.05

0.00

0.00

0.20

310.00

62.00
2530.34

2530.34

2530.34

2530.34

1745.55

1745.55

day

kg.

360.00

4848.76

62.00

661

BLD-CSTN

Index-code

S No Description
1

Sand (including 5% wastage)


Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Add 25% for MC on Labour charges
Grand Total

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

cum

1.05

134.23

140.94

cum

1.05

0.00

0.00

day

0.20

310.00

140.94

62.00

62.00

1948.49

1948.49

1948.49

1948.49

662

BLD-CSTN

Index-code

BLD-CSTN-1-6

S No Description
1

Cement Mortar (1 : 5)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg.

288.00

4848.76

1396.44

cum

1.05

134.23

140.94

cum

1.05

0.00

0.00

0.20

310.00

1396.44
140.94

day

Grand Total

62.00

62.00

1599.38

1599.38

1599.38

1599.38

1163.70
140.94

Add 25% for MC on Labour charges


Grand Total

BLD-CSTN-1-7

BLD-CSTN-1-8

Grand Total
Add 25% for MC on Labour charges
Grand Total
Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Add 25% for MC on Labour charges
Grand Total

kg.

240.00

4848.76

1163.70

cum

1.05

134.23

140.94

cum

1.05

0.00

0.00

0.20

310.00

day

62.00

62.00

1366.64

1366.64

1366.64

1366.64

872.78
140.94

kg.

180.00

4848.76

872.78

cum

1.05

134.23

140.94

cum

1.05

0.00

0.00

0.20

310.00

62.00
1075.71

1075.71

1075.71

1075.71

1939.50
1518.55
60.40

1939.50
1518.55
60.40

0.00

0.00

0.00

0.00

day

62.00

CONCRETE, DAMP PROOF COURSE &


REINFORCEMENT

BLD-CSTN-2
BLD-CSTN-2-1

Cement Mortar (1 : 6)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

Plain Cement concrete Grade M20 - Nominal


Mix
using 20mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 20mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Water (including for curing)
Grand Total
Add 25% for MC on Labour charges
Grand Total

Kg
cum
cum

400.00
0.90
0.45

4848.76
1687.27
134.23

cum

0.90

cum

0.45

0.00

day

0.10

415.00

41.50

41.50

day

2.36

310.00

731.60

731.60

kl

1.20

103.00

123.60
4415.15
0.00
4415.00

123.60
4415.15
4415.00

663

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Add 14% over head charges

Amount
Rs.with
MA

Amount
without M.A

618.10
5033.00

618.10
5033.00

Note : For Nominal Mix : Considering table 9 IS 456 : 2000,


the quantity of cement needed is 405 kgs / cum. Hence
proposed 400 kgs of cement for cum of CC M20

664

BLD-CSTN

Index-code

BLD-CSTN-2-2

S No Description
1

10

Plain Cement concrete Grade M10 - Nominal


Mix upto Plinth level
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
MA on crew charges
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Kg

220.00

4848.76

1066.73

1066.73

cum
cum
cum

0.90
0.45
0.90

1167.27
134.23
0.00

1050.55
60.40
0.00

1050.55
60.40
0.00

cum
kl

0.45
1.20

0.00
103.00

0.00
123.60

0.00
123.60

hour

1.00

338.90

338.90

338.90

hour

0.00

204.10

0.00

day

0.10

415.00

41.50

day

1.39

310.00

Add 25% for MC on Labour charges

BLD-CSTN-2-3

11

12

430.90

430.90

3112.57

3112.57

0.00

Grand Total

3112.57

Add 14% over head charges

435.76

435.76

3548.00

3548.00

1333.41

3112.57

PCC Grade M15 - Nominal mix 1:2.5:5 (Hand


mixing)
Unit = 1cum
A) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
Water (including for curing)
B) Labour
Mason (1st Class)
Mazdoor (Unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

BLD-CSTN-2-4

41.50

kg

275.00

4848.76

1333.41

cum

0.48

134.23

64.43

64.43

cum

0.54

1167.27

630.33

630.33

cum

0.27

1687.27

455.56

455.56

cum

0.09

1257.27

113.15

113.15

kl

1.20

103.00

123.60

123.60

day

0.10

415.00

41.50

41.50

day

2.36

310.00

731.60

731.60

3493.58

3493.58

0.00
3493.58

3493.58

489.10

489.10

3983.00

3983.00

Plain Cement concrete (1:4:8) using 40 mm


metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

kg

162.00

4848.76

785.50

785.50

cum

0.90

1167.27

1050.55

1050.55

cum

0.45

134.23

60.40

60.40

cum

0.90

cum

0.45

kl

1.20

103.00

123.60

123.60

day

0.10

415.00

41.50

41.50

day

2.36

310.00

731.60

731.60

2793.15
0.00
2793.15
391.04

2793.15
2793.15
391.04

665

BLD-CSTN

Index-code

S No Description
1
13

BLD-CSTN-2-5

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

3184.00

3184.19

Plain Cement concrete (1:4:8) using 40 mm


metal with concrete mixture.
All work
upto plinth level.
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Add MA on Crew charges

kg

162.00

4848.76

785.50

785.50

cum

0.90

1167.27

1050.55

1050.55

cum

0.45

134.23

60.40

60.40

cum

0.90

cum

0.45

kl

1.20

77.00

92.40

92.40

hour
hour

1.00
0.00

338.90
204.10

338.90
0.00

338.90

666

BLD-CSTN

Index-code

S No Description
1

C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day

0.10

415.00

41.50

41.50

day

1.39

310.00

430.90

430.90

2800.15

2800.15

Add 20% for MC on Labour charges

0.00

Grand Total

2800.15

Add 13.615% over head charges

BLD-CSTN-2-6

14

15

392.02
3192.17

kg
cum

129.60
0.90

4848.76
1167.27

628.40
1050.55

628.40
1050.55

cum

0.45

134.23

60.40

60.40

cum

0.90

cum

0.45

kl

1.20

77.00

92.40

92.40

day

0.10

415.00

41.50

41.50

day

2.36

310.00

731.60

731.60

2604.85
0.00
2604.85
354.65
2959.00

2604.85
2604.85
364.68
2969.52

Plain Cement concrete (1:5:10) using 40 mm


metal with Concrete mixture. All work upto

plinth level.
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Add MA on Crew charges
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 20% for MC on Labour charges
Grand Total
Add 14% over head charges

BLD-CSTN-2-8

381.24
3181.00

Plain Cement concrete (1:5:10) using 40 mm


metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 20% for MC on Labour charges
Grand Total
Add 13.615% over head charges

BLD-CSTN-2-7

2800.15

16

Plain Cement concrete (1:6:10) using 40 mm


metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)

kg

129.60

4848.76

628.40

628.40

cum

0.90

1167.27

1050.55

1050.55

cum

0.45

134.23

60.40

60.40

cum

0.90

cum

0.45

kl

1.20

77.00

92.40

92.40

hour
hour

1.00
0.00

338.90
204.10

338.90
0.00

338.90

day

0.10

415.00

41.50

41.50

day

1.39

310.00

430.90

430.90

2643.05
0.00
2643.05
370.03
3013.00

2643.05
2643.05
370.03
3013.07

kg

129.60

4848.76

628.40

628.40

cum

0.90

1167.27

1050.55

1050.55

cum

0.54

134.23

72.48

72.48

cum

0.90

cum

0.54

kl

1.20

77.00

92.40

92.40

667

BLD-CSTN

Index-code

S No Description
1

B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

BLD-CSTN-2-9

17

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day

0.10

415.00

41.50

41.50

day

2.36

310.00

731.60
2616.93
0.00
2616.93
366.37
2983.00

731.60
2616.93
2616.93
366.37
2983.30

Plain Cement concrete (1:6:10) using 40 mm


metal with Concrete mixture upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)

kg

129.60

4848.76

628.40

628.40

cum

0.90

1167.27

1050.55

1050.55

cum

0.54

134.23

72.48

72.48

cum

0.90

cum

0.54

kl

1.20

77.00

92.40

92.40

668

BLD-CSTN

Index-code

S No Description
1

B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Add MA on Crew charges
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

BLD-CSTN-2-8

16

17

18

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

hour

1.00

338.90

338.90

338.90

hour

0.00

204.10

0.00

day

0.10

415.00

41.50

41.50

day

1.39

310.00

430.90

430.90

2655.13

2655.13

0.00
2655.13

2655.13

371.72

371.72

3027.00

3026.84

kg

216.00

4848.76

1047.33

1047.33

cum

0.90

1167.27

1050.55

1050.55

cum

0.54

134.23

72.48

72.48

cum

0.90

cum

0.54

kl

1.20

77.00

92.40

92.40

day

0.10

415.00

41.50

41.50

day

2.36

310.00

731.60
3035.86
0.00
3035.86
425.02
3461.00

731.60
3035.86
3035.86
425.02
3460.88

Plain Cement concrete (1:3:6) using 40 mm


metal with Concrete mixture upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Add MA on Crew charges
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 20% for MC on Labour charges
Grand Total
Add 13.615% over head charges

BLD-CSTN-2-10

Quantity

Plain Cement concrete (1:3:6) using 40 mm


metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

BLD-CSTN-2-9

Unit

Plain Cement concrete - Nominal Mix (1:3:6)


using 20mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 20mm
Fine aggregate (Sand)

kg

216.00

4848.76

1047.33

1047.33

cum

0.90

1167.27

1050.55

1050.55

cum

0.54

134.23

72.48

72.48

cum

0.90

cum

0.54

kl

1.20

77.00

92.40

92.40

hour

1.00

338.90

338.90

338.90

0.00

204.10

0.00

day

0.10

415.00

41.50

41.50

day

1.39

310.00

430.90

430.90

3074.06

3074.06

0.00
3074.06

3074.06

418.53

418.53

3493.00

3492.59

Kg

220.00

4848.76

1066.73

1066.73

cum

0.90

1687.27

1518.55

1518.55

cum

0.45

134.23

60.40

60.40

669

BLD-CSTN

Index-code

S No Description
1

Seigniorage charges for C.A


Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

BLD-CSTN-2-11

BLD-CSTN-2-12

19

20

Plain Cement concrete (M 20) Nominal Mix


using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
25% MA on Crew
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

92.40

92.40

cum

0.90

cum

0.45

kl

1.20

77.00

day

0.10

415.00

41.50

41.50

day

2.36

310.00

731.60

731.60

3511.17

3511.17

0.00
3511.17
491.56
4003.00

3511.17
491.56
4002.74

773.10

Kg

350.00

4848.76

1697.07

1697.07

cum

0.90

1687.27

1518.55

1518.55

cum

0.45

134.23

60.40

60.40

cum

0.90

cum

0.45

kl

1.20

77.00

92.40

92.40

hour
0.00

1.00
1.00

338.90
189.00

338.90
0.00

338.90

day

0.10

415.00

41.50

41.50

day

1.39

310.00

430.90

430.90

4179.71

4179.71

0.00
4179.71
585.16
4765.00

4179.71
585.16
4764.87

Plain Cement concrete (M 15) Nominal Mix


1:2.5:5
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm
Coarse aggregate 20mm
Coarse aggregate 10mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

Kg

275.000

4848.76

1333.41

1333.41

cum

0.540

1167.27

630.33

630.33

cum

0.270

1687.27

455.56

455.56

cum

0.090

1257.27

113.15

113.15

cum

0.480

134.23

64.43

64.43

cum

0.900

cum

0.480

kl

1.20

77.00

92.40

92.40

hour

1.000

338.90

338.90

338.90

day

0.100

415.00

41.50

41.50

day

1.390

310.00

430.90

430.90

1536.85
0.00
1536.85
215.16
1752.00

1536.85
1536.85
215.16
1752.00

670

BLD-CSTN

Index-code

S No Description
1

BLD-CSTN-2-13

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum
cum
Kgs

0.900
0.450
400.000

1687.27
134.23
4848.76

1518.55
60.40
1939.50

1518.55
60.40
1939.50

day
day
day

0.133
0.267
3.600

415.00
370.00
310.00

55.20
98.79
1116.00

55.20
98.79
1116.00

hour
hour
hour
hour
kl

1.000
0.000
1.000
0.000
1.200

338.90
204.10
175.10
146.90
77.00

338.90

0.20

1269.99

338.90
0.00
175.10
0.00
92.40
5394.84
0.00
5394.84

21 R.C.C. M-20 Nominal Mix


NEW RCC M- 20 Nominal mix (Cement:fine aggregate:

coarse aggregate) corresponding to Table 9 of IS


456 using 20mm size graded machine crushed
hard granite metal (coarse aggregate) from
approved quarry including cost and conveyance
of all materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and
labour charges such as machine mixing, laying
concrete, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished
item of work, but excluding centering, shuttering.

FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)

A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Add MA on Crew
Cost of Petrol for Vibrator
Add MA on Crew
Water (including for curing)
BASIC COST per 1 cum
Add 20% for MC on Labour charges
Grand Total
Add 13.615% over head charges

Foudation ( Footings )
Rate of RCC
Cost of centering
20% Muncipal Allowance

473.00

0.00

13.615% over head charges and controctors


pofit
Rate per Cum
Plinth Beam
Rate of RCC
Cost of centering
20% Muncipal Allowance

1141.00

0.00

13.615% over head charges and controctors


pofit
Rate per Cum
Pedastals
Rate of RCC
Cost of centering
20% Muncipal Allowance
13.615% over head charges and controctors
pofit
Rate per Cum

753.00

0.00

175.10
92.40
5394.84
5394.84

5395.00
5395.00

5394.84
5395.00

5395.00
750.00
0.00
6145.00
836.64
6981.64
6982.00

5395.00
0.00

5395.00
2476.00
7871.00
0.00
7871.00
1071.64
8942.64
8943.00

5395.00
0.00
5395.00

5395.00
1068.00
6463.00
0.00
6463.00
879.94
7342.94
7343.00

5394.84
0.00
5394.84

5395.00
755.30
6150.30

5395.00
755.30
6150.30

5394.84
755.28
6150.11

671

BLD-CSTN

Index-code

S No Description
1

COLUMNS, LINTELS, WATER TANKS, RCC WALLS


IN BUILDINGS UP TO 3.66 M HEIGHT

A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum
cum
Kgs

0.900
0.450
400.000

1687.27
134.23
4848.76

1518.55
60.40
1939.50

1518.55
60.40
1939.50

day
day
day

0.167
0.167
4.700
0.00

415.00
370.00
310.00
1588.10
1588.10

69.31
61.79
1457.00
0.00

69.31
61.79
1457.00

hour
hour
kl

1.000
0.000
1.200

338.90
204.10
77.00

338.90
0.00
92.40
5537.85
5537.85

338.90
92.40
5537.85
5537.85

5538.00

5537.85

Add 20% for MC on Labour charges


Total Labour Charges

B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Add MA on Crew
Water (including for curing)
BASIC COST per 1 cum
Grand Total
Add 13.615% over head charges
COLUMNS 1st floor
Rate of RCC
Cost of centering

5538.00

1567.00

20% Muncipal Allowance

1338.00

0.00

13.615% over head charges and controctors


pofit
Rate per Cum

7105.00
0.00
7105.00
967.35
8072.35

5537.85

1668.75
7206.60
7206.60
1008.92
8215.52

8072.00
COLUMNS 2nd floor
Rate of RCC
Cost of centering
Add 10% extra on labour charges
Lift charges beyond initial lift of 3.0M

5538.00
911.00
158.81
4.10
6611.91

LINTELS 1st floor


Rate of RCC
Cost of centering
Rate for 1 Cum
LINTELS 2nd floor
Rate of RCC
Add 10% extra on labour charges
Lift charges beyond initial lift of 3.0M
Cost of centering
Rate for 1 Cum
CHAJJAS 1st floor
Rate of RCC(1X0.75X0.063)
CEILING PLASTERING (2X1X0.75+2.5X.05)
Cost of centering
CHAJJAS 2nd floor
Rate of RCC(1X0.75X0.063)
CEILING PLASTERING (2X1X0.75+2.5X.05)
Add 10% extra on labour charges
Lift charges beyond initial lift of 3.0M
Cost of centering

Columns
RCC Concrete
Cost of Centring Charges incl MA on labour
Material Lift charges

0.05
1.63

5538.00
2755.99

10Sqm

0.05
1.63

5538.00
2649.00

10Sqm

GL-FL
Cum
5538.00
1567.00

FL-SL

Cum
5538.00
1701.00
158.81

2nd F-TF

Cum
5538.00
1835.00
317.62

5538.00
1713.00
7251.00

5537.85
0.00
5537.85

5538.00
158.81
4.10
2849.10
8550.01

5537.85
158.81
4.10
0.00
5700.76

261.67
447.85
0.00
709.52

261.66
374.42
0.00
636.08

261.67
430.46
7.94
0.21
504.31
1204.59

78.85
430.46
7.94
0.21
0.00

3rd F-FthF

Cum
5538.00
1968.00
476.43

4th F

Cum
5538.00
2102
635.24

672

BLD-CSTN

Index-code

S No Description
1

Over head charges 13.615%


Grand Total

Lintel
RCC Concrete
Cost of Centring Charges
Material Lift charges
Over head charges 13.615%
Grand Total

Sun Shades
RCC Concrete
Cost of Centring Charges
Material Lift charges
Over head charges 13.615%
Grand Total

BEAMS
RCC Concrete
Cost of Centring Charges
Material Lift charges
Over head charges 13.615%
Grand Total

Slab up to 150mm
RCC Concrete
Cost of Centring Charges
Material Lift charges
Over head charges 13.615%
Grand Total

Slab 150mm to 300mm


RCC Concrete
Cost of Centring Charges
Material Lift charges
Over head charges 14%
Grand Total

Unit

Quantity

7105.00
967.35
8072.35
Say 8072.00
per Cum
GL-FL
Cum
5538.00
1713.00
7251.00
987.22
8238.22
Say 8238.00
per Cum
GL-FL
Sqm
346.13
296.00
642.13
87.43
729.55
Say 730.00
per1Sqm
GL-FL
Cum
5538.00
2464.00
8002.00
1089.47
9091.47
Say 9091.00
per1Cum

GL-FL
Sqm
830.70
279.00
1109.70
151.09
1260.79
Say 1261.00
per1Sqm

GL-FL
Sqm
1246.05
287.00
1533.05
214.63
1747.68
Say 1748.00
per1Sqm

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

7397.81

7690.62

7982.43

8275.24

1047.08
8737.70
8738.00
per Cum

1086.81
9069.24
9069.00
per Cum

1007.21
8405.02
8405.00
per Cum
FL-SL

Cum
5538.00
1808.00
158.81
7504.81

1021.78
8526.59
8527.00
per Cum
FL-SL

Sqm
346.13
311.00
9.93
667.05

90.82
757.87
758.00
per1Sqm
FL-SL

Cum

2nd F-TF

Cum

3rd F-FthF

Cum

5538.00
1844.00
317.62
7699.62

5538.00
1934.00
476.43
7948.43

1048.30
8747.92
8748.00
per Cum

1082.18
9030.61
9031.00
per Cum

2nd F-TF

Sqm
346.13
325.00
9.93
681.05

92.73
773.78
774.00
per1Sqm
2nd F-TF

Cum

3rd F-FthF

Sqm
346.13
340.00
9.93
696.05

94.77
790.82
791.00
per1Sqm
3rd F-FthF

Cum

1126.67
9401.91
9402.00
per Cum
4th F

Cum
5538.00
2024
635.24
8197.24

1116.05
9313.29
9313.00
per Cum
4th F

Sqm
346.13
354
9.93
710.05

96.67
806.72
807.00
per1Sqm
4th F

Cum

5538.00
2576.00
158.81
8272.81

5538.00
2688.00
158.81
8384.81

5538.00
2801.00
158.81
8497.81

5538.00
2913
158.81
8609.81

1126.34
9399.15
9399.00
per1Cum

1141.59
9526.40
9526.00
per1Cum

1156.98
9654.79
9655.00
per1Cum

1172.23
9782.04
9782.00
per1Cum

FL-SL

Sqm

2nd F-TF

Sqm

3rd F-FthF

Sqm

4th F

Sqm

830.70
292.00
23.82
1146.52

830.70
304.00
23.82
1158.52

830.70
317.00
23.82
1171.52

830.70
330
23.82
1184.52

156.10
1302.62
1303.00
per1Sqm

157.73
1316.25
1316.00
per1Sqm

159.50
1331.02
1331.00
per1Sqm

161.27
1345.79
1346.00
per1Sqm

FL-SL

Sqm

2nd F-TF

Sqm

3rd F-FthF

Sqm

4th F

Sqm

1246.05
300.00
35.73
1581.78

1246.05
313.00
35.73
1594.78

1246.05
326.00
35.73
1607.78

1246.05
339
35.73
1620.78

221.45
1803.23
1803.00
per1Sqm

223.27
1818.05
1818.00
per1Sqm

225.09
1832.87
1833.00
per1Sqm

226.91
1847.69
1848.00
per1Sqm

RCC SLABS, BEAMS UP TO 3.66M HEIGHT

673

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum
cum
Kgs

0.900
0.450
400.000

1687.27
134.23
4848.76

1518.55
60.40
1939.50

1518.55
60.40
1939.50

day
day
day

0.067
0.133
2.500

415.00
370.00
310.00

27.81
49.21
775.00

27.81
49.21
775

hour
hour
kl

0.267
0.000
1.200

338.90
204.10
77.00

90.49
0.00
92.40
4553.35
0.00
4553.35
637.47
5191.00

90.49

A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Add MA on Crew
Water (including for curing)
BASIC COST per 1 cum
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

SLAB UP TO 150MM THICK 1st floor


Rate of RCC(1X1X0.15)
Cost of centering
Add 25% MC on Labour charges for centering

252.00

Rate per 1 Cum


Rate per 1 Sqm
SLAB UP TO 150MM THICK 2ND floor
Rate of RCC(1X0.75X0.063)
Add 10% extra on labour charges
Lift charges beyond initial lift of 3.0M
Cost of centering
0.00
ROOF LEVEL BEAMS 1st floor
Rate of RCC(1X0.75X0.063)
Cost of centering
ROOF LEVEL BEAMS 2ND floor
Rate of RCC(1X0.75X0.063)
Add 10% extra on labour charges
Lift charges beyond initial lift of 3.0M
Cost of centering

/0.15

/0.15

92.4
4553.35
4553.35
637.47
5190.82

5191.00
1680.00
0.00

491.56
1680.00
168.33

6871.00
1030.65

2171.56
325.73

491.56
6.04
4.10
0.00
501.70
491.56
0.00
491.56

491.56
0.00
491.56

491.56
6.04
4.10
0.00
501.70

674

BLD-CSTN

Index-code

S No Description

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

22

Supply and placing of the Design Mix Concrete corresponding to IS 456 using WEIGH
BATCHER / MIXER with 20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and excluding Seigniorage charges,
including sales & other taxes on all materials including all operational, incidental and labour
charges such as weigh batching, machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)with
minimum cement content as per IS code from standard suppliers approved by the department
including pumping, centering, shuttering, laying concrete, vibrating, curing etc. complete but
excluding cost of steel and its fabrication charges for finished item of work.

FOUNDATIONS, PLINTH, PEDESTALS (Below


Plinth)
ANY GRADE OF MIX
Cement
20mm HBG graded metal
Sand
1st Class Mason
2nd Class Mason
Mazdoor (Both Men & Women)
Muncipal allowance at 20%
Weigh Batcher Hire charges (Machine mixing)
charges(Hire& Crew)
20% MA on Crew
40mm needle vibratar petrol (Hire& Crew)
20% MA on Crew
Water (including for curing)
BASIC COST per 1 cum
Grand Total

DESIGN MIX CONCRETE (WEIGH BATCH at SITE)

BLD-CSTN-2-14

Basic cost of concrete


Centring charges incl MA
Add 13.615% over head charges

COLUMNS, LINTELS, WATER TANKS, RCC


WALLS IN BUILDINGS
ANY GRADE OF MIX
cement
20mm HBG graded metal
Sand
1st Class Mason
2nd Class Mason
Mazdoor (Both Men & Women)
Add 20% for MC on Labour charges
Weigh Batcher Hire charges (Machine mixing)
charges
MA on Crew charges
Needle Vibrator
MA on Crew charges
Water (including for curing)
BASIC COST per 1 cum

Columns
RCC Concrete
Cost of Centring Charges incld MA on labour
Material Lift charges

Excluding Cement cost

MT

0.35
0.80
0.40
0.133
0.267
4.600
0.000
1.333

4848.76
1687.27
134.23
415.00
370.00
310.00
1579.99
548.30

1697.07
1349.82
53.69
55.20
98.79
1426.00
0.00
730.88

1.33
h
1.33
kl

0.000
1.330
0.000
1.200

318.20
175.10
146.90
77.00

0.00
232.88
0.00
92.40
5736.73
5736.73

Footing

Plingth Beam

Pedastal

5736.73
750.00
6486.73
0.00
6486.73
6487.00

5736.726
2476.000

5736.73
1068.00

8212.73
0.00
8212.73

6804.73
0.00
6804.73

8213.000

6805.00

Mt

0.350
0.80
0.40
0.167
0.167
5.600
0.00
1.333
1.333
1.333
1.333
1.200

4848.76
1687.27
134.23
415.00
370.00
310.00
1867.10
548.30
318.20
175.10
146.90
77.00

cum
cum
day
day
day

cum
cum
day
day
day
H
H
h
H
kl

GL-FL
Cum
6024.36
1567.00
7591.36

FL-SL

Cum
6024.36
1701.00
186.71
7912.07

2nd F-TF

Cum
6024.36
1835.00
373.42
8232.78

1697.07
1349.82
53.69
69.31
61.79
1736.00
0.00
730.88
0.00
233.41
0.00
92.40
6024.36
6024.36

3rd F-FthF

Cum
6024.36
1968.00
560.13
8552.49

1697.07
1349.82
53.69
69.31
61.79
1736.00
730.88
0.00
233.41
0.00
92.40
6024.36

4th F

Cum
6024.36
2102
746.84
8873.20

675

BLD-CSTN

Index-code

S No Description
1

Over head charges 13.615%


Grand Total

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

0.00
7591.36
Say 7591.00
per Cum

Walls of thick 100mm


100.00
RCC Concrete
Cost of Centring Charges
Material Lift charges

GL-FL
sqm
602.44
156.70

0.00
7912.07
7912.00
per Cum
FL-SL

602.44
156.70

0.00
8232.78
8233.00
per Cum
2nd F-TF

602.44
156.70

0.00
8552.49
8552.00
per Cum

0.00
8873.20
8873.00
per Cum

3rd F-FthF

602.44
156.70

4th F

602.44
156.70

Over head charges 14%


Grand Total
Say
Lintel

GL-FL
Cum
6024.36
1713.00

RCC Concrete
Cost of Centring Charges
Material Lift charges
Over head charges 13.615%
Grand Total

7737.36
0.00
7737.36
Say 7737.00
per Cum

RCC SLABS, BEAMS


ANY GRADE OF MIX
Cement
20mm HBG graded metal
Sand
1st Class Mason
2nd Class Mason
Mazdoor (Both Men & Women)
Add 20% for MC on Labour charges
Weigh Batcher Hire charges (Machine mixing)
charges
Add 20% for MC on crew Labour charges
Needle Vibrator
MA on Crew charges
Water (including for curing)
BASIC COST per 1 cum

RCC Concrete
Cost of Centring Charges
Material Lift charges
Over head charges 13.615%
Grand Total

BEAMS
RCC Concrete
Cost of Centring Charges
Material Lift charges
Over head charges 13.615%
Grand Total

6024.36
1808.00
186.71
8019.07

0.00
8019.07
8019.00
per Cum

0.00
8241.78
8242.00
per Cum

0.00
8518.49
8518.00
per Cum

0.35
0.80
0.40
0.067
0.133
3.077
0.00
0.308
0.308
0.308
0.308
1.200

4848.76
1687.27
134.23
415.00
370.00
310.00
1030.89
548.30
318.20
165.70
136.60
77.00

0.0375
FL-SL

4443.77
2nd F-TF

h
h
h
H
kl

344.24
0.00
344.24
Say 344.00
per1Rmt
GL-FL
Cum
4443.77
2464.00
6907.77
0.00
6907.77
Say 6908.00

3rd F-FthF

Cum
6024.36
1934.00
560.13
8518.49

MT

GL-FL
RM
166.64
177.60

2nd F-TF

Cum
6024.36
1844.00
373.42
8241.78

cum
cum
day
day
day

Rate per RMt

Sun Shades

FL-SL

Cum

RM
166.64

177.60

RM
166.64

177.60

1697.07
1349.82
53.69
27.81
49.21
953.87
0.00
168.88
0.00
51.04
0.00
92.40
4443.77
4443.77
166.64
3rd F-FthF

RM
166.64

177.60

4th F

Cum
6024.36
2024
746.84
8795.20

0.00
8795.20
8795.00
per Cum

1697.07
1349.82
53.69
27.81
49.21
953.87
168.88
0.00
51.04
0.00
92.40
4443.77

4th F

RM
166.64

177.60

6.44
350.68

6.44
350.68

6.44
350.68

6.44
350.68

0.00
350.68
351.00
per1Rmt

0.00
350.68
351.00
per1Rmt

0.00
350.68
351.00
per1Rmt

0.00
350.68
351.00
per1Rmt

FL-SL

Cum
4443.77
2576.00
103.09
7122.86

0.00
7122.86
7123.00

2nd F-TF

Cum
4443.77
2688.00
103.09
7234.86

0.00
7234.86
7235.00

3rd F-FthF

Cum
4443.77
2801.00
103.09
7347.86

0.00
7347.86
7348.00

4th F

Cum
4443.77
2913
103.09
7459.86

0.00
7459.86
7460.00

676

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

per1Cum

Slab up to 100mm

GL-FL
Sqm
444.38
279.00

RCC Concrete
Cost of Centring Charges
Material Lift charges
Over head charges 13.615%
Grand Total

444.38
292.00
2.01
738.39

0.00
738.39
738.00
per1Sqm

GL-FL
Sqm
666.57
287.00

RCC Concrete
Cost of Centring Charges
Material Lift charges

FL-SL

Sqm
666.57
300.00
0.00
966.57

953.57
129.83
1083.39
Say 1083.00
per1Sqm

Slab 200mm

131.60
1098.16
1098.00
per1Sqm

GL-FL
Sqm
1547.47
0.00

RCC Concrete
Cost of Centring Charges
Material Lift charges
Over head charges 14%
Grand Total

FL-SL

Sqm

723.38
0.00
723.38
Say 723.00
per1Sqm

Slab 150mm thickness

Over head charges 13.615%


Grand Total

per1Cum

FL-SL

Sqm

1547.47
0.00
1547.47
Say 1547.00
per1Sqm

per1Cum

2nd F-TF

Sqm
444.38
304.00
2.01
750.39

0.00
750.39
750.00
per1Sqm
2nd F-TF

Sqm
666.57
313.00
0.00
979.57

133.37
1112.93
1113.00
per1Sqm

2nd F-TF

Sqm

per1Cum

3rd F-FthF

Sqm
444.38
317.00
2.01
763.39

0.00
763.39
763.00
per1Sqm
3rd F-FthF

Sqm
666.57
326.00
0.00
992.57

135.14
1127.70
1128.00
per1Sqm

3rd F-FthF

Sqm

per1Cum

4th F

Sqm
444.38
330
2.01
776.39

0.00
776.39
776.00
per1Sqm
4th F

Sqm
666.57
339
0.00
1005.57

136.91
1142.47
1142.00
per1Sqm

4th F

Sqm

1547.47
0.00
3.02
1550.49

1547.47
0.00
3.02
1550.49

1547.47
0.00
3.02
1550.49

1547.47
0
3.02
1550.49

0.00
1550.49
1550.00
per1Sqm

0.00
1550.49
1550.00
per1Sqm

0.00
1550.49
1550.00
per1Sqm

0.00
1550.49
1550.00
per1Sqm

Note : Quantity of cement proposed for various design mixes is for


estimating purpose only. Actual quantity of cement will be as per
approved mix design. Similarly quantity for coarse and fine
aggregates is for estimating purpose and the exact quantity shall be
as per the mix design. Nominal mix of grades M20 is to be used with
adequate supervision and quality control requirements.
For Design mix concrete, allow Cement as follows
(for estimate purpose only) :

Grade

Kgs

M 20

350

M 25
M 30
M 35
M 40

380
400
420
430

677

BLD-CSTN

Index-code

S No Description
1

23

Supply and placing of the Ready Mix (RMC)


Standard Design Mix Concrete grade as per IS
4926-2003 with minimum cement content as
per IS code 456-2000 using 20 mm graded
metal, from standard suppliers approved by
the department including pumping, laying
concrete, vibrating, curing etc. complete but
excluding cots of steel and its fabrication
charges, centering, shuttering for finished
item of work.

BLD-CSTN-2-15

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Excluding Cement any Grade.

FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)

Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded

cum

0.80

1687.27

1349.81807

cum

0.40

134.23

53.69009374

cum

0.80

cum

0.40

Fine aggregate (Sand)


Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour

kl

1.20

77.00

92.4

hour

0.222

703.70

156.2214

Transit mixer 4cum capacity for lead upto 1km

hour

0.222

Concrete Pump
C. LABOUR:
Mason 1st class

day

0.222

day

0.056

415.00

Mason 2nd class


Mazdoor (unskilled)
Grand Total
Note : Wherever concrete is carried out using
batching plant, transit mixer, concrete pump, then
Admixtures @ 0.4% of weight of cement may be
added for achieving desired slump of concrete. If
concentrated Admixture is proposed, only 0.04%
of weight of Cement shall be used.

day

0.056

370.00

20.72

day

0.917

310.00

284.27

cum

0.80

1687.27

cum

0.40

134.23

cum

0.80

cum

0.40

0
0
0

0
23.24

COLUMNS, LINTELS, WATER TANKS, RCC WALLS


IN BUILDINGS

Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour

kl

1.20

hour

0.444

Transit mixer 4cum capacity for lead upto 1km

hour

0.444

Concrete Pump
C. LABOUR:
Mason 1st class

day

0.444

day

0.111

415.00

Mason 2 class
Mazdoor (unskilled)
Grand Total
RCC SLABS, BEAMS
Unit : 1cum

day

0.222

370.00

day

1.556

310.00

cum

0.80

cum

0.40

nd

A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)

77.00

678

BLD-CSTN

Index-code

S No Description
1

Seigniorage charges for C.A


Seigniorage charges for F.A
Water (including for curing)

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.80

cum

0.40

kl

1.20

679

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

hour

0.133

Transit mixer 4cum capacity for lead upto 1km


Concrete Pump
C. LABOUR:
Mason 1st class

hour
day

0.133
0.133

day

0.033

415.00

Mason 2nd class


Mazdoor (unskilled)
Grand Total

day

0.067

370.00

day

0.433

310.00

5191.00

5190.82

S No Description
1

B. MACHINERY
Batching plant at 20 cum per hour

For Design mix concrete, allow Cement as follows


(for estimate purpose only) :

Grade

Kgs

M 20
M 25
M 30
M 35
M 40

350

SLAB UP TO 150MM THICK 1st floor


Rate of RCC(1X0.75X0.063)
Cost of centering
0.00
Rate per 1 Cum
Rate per 1 Sqm
SLAB UP TO 150MM THICK 2ND floor
Rate of RCC(1X0.75X0.063)
Add 10% extra on labour charges
Lift charges beyond initial lift of 3.0M
Cost of centering
434.40

380
400
420
430

/0.15

0.00

0.00

5191.00

5190.82

778.65

778.62

5191.00
85.20
4.10
/0.15

0.00
5280.30

ROOF LEVEL BEAMS 1st floor


Rate of RCC(1X0.75X0.063)
Cost of centering

5191.00

ROOF LEVEL BEAMS 2ND floor


Rate of RCC(1X0.75X0.063)
Add 10% extra on labour charges
Lift charges beyond initial lift of 3.0M
Cost of centering

5190.82

0.00

0.00

5191.00

5190.82

5191.00
85.20
4.10
3866.73
9147.03

Note: LIFT CHARGES - for all RCC Items


1. For Lift Charges of Labour, increase @ 10% on labour charges for each upper floor on
Ground Floor Rate
2. For Lift Charges of Materials only, for lifting Concrete above 6.1 M (2nd floor onwards)
Winch/ Lift hire charges may be allowed at following rates:

Description of Structure

Basic Rate for 2nd Floor


(6.1 M)

for each additional


floor (3.05 M) over and
above 2nd floor (6.1 M)

Nil

Nil

a. FOUNDATIONS, PLINTH, PEDESTALS (Below


Plinth)
b. COLUMNS, LINTELS, WATER TANKS, RCC
WALLS

1.333

Hrs

10%

c. RCC SLABS, BEAMS

0.267

Hrs

10%

680

BLD-CSTN

Index-code

BLD-CSTN-2-16

S No Description
1

24

Damp proof course 40mm thick with cement


concrete (1:2:4 Nominal mix), using 12mm hard
broken stone aggregate including cost of all
materials, seigniorage charges, excluding
conveyance charges of materials, including the
cost of machinery, labour charges, mixing, placing
in position, leveling, vibrating, curing etc. complete
for finished item of work. (Using concrete mixer)

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kgs
cum

320.00
0.90

4848.76
1419.27

1551.60
1277.35

cum
cum

0.45
0.90

134.23

60.40

cum
L.S.

0.45

hour

1.00

338.90

338.90

day

0.1

415.00

41.50

day

1.98

310.00

613.80

Unit = 25 sqm
A. MATERIALS:
Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate

Seigniorage charges of sand


Form work
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
D. Grand Total for 25 sqm
Rate per Sqm = D/25

3883.55
155.34

681

BLD-CSTN

Index-code

S No Description
1

25

Damp proof course 50mm thick with 1:2:4 cement


concrete Nominal mix, using 12mm hard broken
stone aggregate including cost of all materials,
seigniorage
charges,
excluding
conveyance
charges of materials including the cost of
machinery, labour charges, mixing, placing in
position, leveling, vibrating, curing etc. complete for
finished item of work. (Using concrete mixer)

BLD-CSTN-2-17

Unit = 20 sqm
A. MATERIALS:
Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate

BLD-CSTN-2-18

Seigniorage charges of sand


Form work
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
D. Grand Total for 20 sqm
Rate per Sqm = D/20
26 Supplying, fitting and placing HYSD bar
11.7 reinforcement in foundation complete as per
drawings and technical specifications for
Bars below 36 mm dia including over laps and
wastage, where they are not welded
1000 Unit = MT
&
(a) Material
1200

HYSD bars including 5 per cent for overlaps and


wastage
Binding wire
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Blacksmith / Bar bender
Mazdoor (Unskilled)
BASIC COST per 1 cum
Add 20% for MC on Labour charges
Grand Total

Basic Rate
Add Lift charges
Add 20% MA on lift charges
Over head charges 13.615%
Grand Total

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kgs

320.00

4848.76

1551.60

cum
cum
cum

0.90
0.45
0.90

1419.27
134.23

1277.35
60.40

cum
L.S.

0.45

hour

1.00

338.90

338.90

day
day

0.1
1.98

415.00
310.00

41.50
613.80
3883.55
194.18

1.05

34058.35

35761.27

35761.27

kg

6.00

70.00

420.00

420.00

day
day

10.00

415.00

4150.00

4150.00

10.00

310.00

3100.00

3100.00

43431.27

43431.27

0.00

7250.00

0.00
43431.27

43431.27

GF(F1)

FF(F2)

SF(F3)

3rdF(F4)

4thF(F5)

43431.27

43431.27

43431.27

43431.27

43431.27

0.00

725.00

1450.00

2175.00

2900.00

0.00

0.00

0.00

0.00

0.00

43431.27

44156.27

44881.27

45606.27

46331.27

0.00
0.00
43431.27
44156.27
Say 43431.00
44156.00
per1MT
per1MT
Supplying, fitting and placing HYSD bar
reinforcement
in
foundation
complete
including wastage, as per drawings and
technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars 36
mm dia and above, where welding required to
be done compulsorily.

0.00
0.00
0.00
44881.27 45606.27 46331.27
44881.00 45606.00 46331.00
per1MT
per1MT
per1MT

682

BLD-CSTN

Index-code

S No Description
1

1000 Unit = t
&
(a) Material
1200

HYSD bars including 2.5 per cent for wastage


Welding Electrodes @ 5 per joint (14 joints / ton)

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

1.025

34058.35

34909.81

each

70.000

9.00

630.00

Welding Charges (Hire charges of Welding


Machine)

Hr

10.00

58.00

580.00

Binding wire

kg

6.00

70.00

420.00

683

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day

2.50

415.00

1037.50

day

2.00

415.00

830.00

day

6.40

310.00

1984.00

(b) Labour for cutting, bending, shifting to


site, tying and placing in position
Welder
Blacksmith
Mazdoor (Unskilled)
BASIC COST per 1 cum
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

40391.31
962.88
41354.19
5789.59
47144.00

27 Supplying,
fitting and placingTMT bar
11.8 reinforcement in foundation complete as per

drawings and technical specifications for


Bars below 36 mm dia including over laps and
wastage, where they are not welded.

BLD-CSTN-2-19

1000 Unit = t
&
(a) Material
1200

TMT bars including 5 per cent for overlaps and


wastage

1.05

34058.35

35761.27

Binding wire
(b) Labour for cutting, bending, shifting to
site, tying and placing in position

kg

6.00

70.00

420.00

Blacksmith / Bar bender


Mazdoor (Unskilled)
BASIC COST per 1 cum
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

day
day

2.00

415.00

830.00

6.40

310.00

1984.00
38995.27
703.50
39698.77
5557.83
45257.00

Supplying, fitting and placingTMT bar


reinforcement
in
foundation
complete
including wastage, as per drawings and
technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars 36
mm dia and above, where welding required to
be done compulsorily.
Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding
Machine)

BLD-CSTN-2-20

1.025

each

70.000

Hr

10.00

Binding wire
(b) Labour for cutting, bending, shifting to
site, tying and placing in position

kg

6.00

Welder
Blacksmith
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
Rate per t = a+b+c+d
28 Supplying, fitting and placing MS bar
11.9 reinforcement in foundation complete as per
drawings and technical specifications for
Bars below 36 mm dia including over laps and
wastage, where they are not welded

day

2.50

day

2.00

day

6.40

1000 Unit = t
&
1200

684

BLD-CSTN

Index-code

S No Description

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

1000
1 2
&
(a) Material
1200

1.05

40058.35

42061.27

kg

6.00

70.00

420.00

day
day

10.00

415.00

4150.00

10.00

310.00

3100.00

0.00

7250.00

0.00

MS bars including 5 per cent for overlaps and


wastage
Binding wire
(b) Labour for cutting, bending, shifting to site,
tying and placing in position

Blacksmith / Bar bender


Mazdoor (Unskilled)
BASIC COST per 1 cum
Add 25% for MC on Labour charges

685

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Grand Total

BLD-CSTN-3
BLD-CSTN-3-1

Amount
without M.A

49731.27

Basic Rate
Add Lift charges
Add 25% MA on lift charges
Over head charges 14%
Grand Total

Amount
Rs.with
MA

GF(F1)

FF(F2)

SF(F3)

3rdF(F4)

4thF(F5)

49731.27

49731.27

49731.27

49731.27

49731.27

0.00

725.00

1450.00

2175.00

2900.00

0.00

0.00

0.00

0.00

0.00

49731.27

50456.27

51181.27

51906.27

52631.27

6962.38
7063.88
56693.65
57520.15
Say 56694.00
57520.00
per1MT
per1MT

7165.38
7266.88
7368.38
58346.65 59173.15 59999.65
58347.00 59173.00 60000.00
per1MT
per1MT
per1MT

BRICK WORK, HONEY - COMBWORK


29

Brick Masonry in CM (1:3) with Bricks with


traditional size 23 x 11 x 7 cms 2nd class

Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class

Mason 2 class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
nd

kg

96.00

4848.76

465.48

Nos
cum

512.00
0.20

5447.83
134.23

2789.29
26.85

cum

0.20

day

0.24

415.00

99.60

day

0.56

370.00

207.20

day

1.89

310.00

585.90

Toward water 1% charges


Grand Total
Add 14% over head charges
Add scaffolding charges for 1st floor
Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Add Lift charges for 2nd floor
Add scaffolding charges for 2nd floor
Rate for 2nd floor

0.01

77.60

4174.31

per sqm

0.00
4174.31
41.74
4216.06
590.25
4806.00
17.85
4824.00

0.00
0.00
0.00

4806.00
4.10
24.21
4834.00

105.28

per sqm

kg

48.00

4848.76

232.74

Note : For Bricks 2.4 % wastage taken.


ii

Brick Masonry in CM (1:4) with Bricks


traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2 class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
nd

Nos

512.00

5447.83

2789.29

cum

0.20

134.23

26.85

cum

0.20

day

0.24

415.00

99.60

day

0.56

370.00

207.20

day

1.89

310.00

585.90
0.00

Grand Total
Towards water charges

232.74

3941.57
0.01

3941.57

3941.57

39.42

Grand Total

3980.99

3941.57

Add 14% over head charges

557.34

551.82

686

BLD-CSTN

Index-code

S No Description
1

Add scaffolding charges for 1st floor

Unit

Quantity

Rate Rs.

41.28

per sqm

0.23

7
4493.39

183.47

183.47

4721.00

RATE FOR 2ND FLOOR


Rate /cum

4538.00

Add scaffolding charges for 2nd floor

Amount
without M.A

4538.00

Rate for 1st floor

Add Lift charges for 2nd floor

4.10
105.28

per sqm

24.21

Rate for 2nd floor

iii

Amount
Rs.with
MA

4566.00

Brick Masonry in CM (1:5) with Bricks


traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class

kg

57.60

4848.76

279.29

Nos
cum

512.00
0.20

5447.83
134.23

2789.29
26.85

cum

0.20

day

0.24

415.00

99.60

Mason 2 class
Mazdoor (unskilled)
Add 25% for MC on Labour charges

day

0.56

370.00

207.20

day

1.89

310.00

585.90

Towards water charges


Grand Total
Add 14% over head charges

0.01

3988.12

Add scaffolding charges for 1st floor


Rate for 1st floor

41.28

per sqm

nd

RATE FOR 2ND FLOOR


Rate /cum
Add Lift charges for 2nd floor
Add scaffolding charges for 2nd floor
Rate for 2nd floor

105.28

per sqm

0.00
3988.12
39.88
4028.00
563.92
4592.00
9.49
4601.00

4592.00
4.10
24.21
4620.00

687

BLD-CSTN

Index-code

S No Description
1

iv

Brick Masonry in CM (1:6) with 2nd class


Bricks traditional size 23 x 11 x 7 cms
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg

48.00

4848.76

232.74

Nos
cum

512.00
0.20

5447.83
134.23

2789.29
26.85

cum

0.20

day

0.24

415.00

99.60

Mason 2nd class


Mazdoor (unskilled)
Add 25% for MC on Labour charges

day

0.56

370.00

207.20

day

1.89

310.00

585.90

Towards water charges


Grand Total
Add 14% over head charges

0.01

3941.57

Add scaffolding charges for 1st floor


Rate for 1st floor

41.28

per sqm

RATE FOR 2ND FLOOR


Rate /cum
Add Lift charges for 2nd floor
Add scaffolding charges for 2nd floor
Rate for 2nd floor

Unit

105.28

0.00
3941.57
39.42
3980.99
557.34
4538.00
9.49
4547.00

4538.00
4.10
24.21
4566.00

per sqm

Brick Masonry in CM (1:8) with Bricks


traditional size 23 x 11 x 7 cms 2nd Class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2 class
Mazdoor (unskilled)
Add 20% for MC on Labour charges
nd

kg

36.00

4848.76

174.56

174.555402

Nos

512.00

5447.83

2789.29

2789.29

cum

0.20

134.23

26.85

26.85

cum

0.20

day

0.24

415.00

99.60

99.60

day

0.56

370.00

207.20

207.20

day

1.89

310.00

585.90

585.90

0.00

892.70

0.00
3883.39

Towards water charges


Grand Total
Rate for Cum

4.44 Sqm/Cum

0.01

38.83
3922.22

0.00

3922.22

0.00

GF(F1)

FF(F2)

SF(F3)

3rdF(F4)

4thF(F5)

3922.22

3922.22

3922.22

3922.22

3922.22

318.61

433.83

549.09

664.31

779.53

0.00

89.27

178.54

267.81

357.08

0.00

0.00

0.00

0.00

0.00

4240.84

4445.32

4649.86

4854.35

5058.83

0.00
4240.84
Say 4241.00
per1Cum

0.00
4445.32
4445.00
per1Cum

0.00
4649.86
4650.00
per1Cum

Basic Rate
Add scaffolding charges for 1st floor incld MA
on labour
Add Lift charges
Add 20% MA on lift charges
Over head charges 13.615%
Grand Total

3883.39

0.00
0.00
4854.35
5058.83
4854.00
5059.00
per1Cum per1Cum

688

BLD-CSTN

Index-code

S No Description
1

Brick Masonry in CM (1:3) with


Bricks
traditional size 23 x 11 x 7 cms 1st Class
Unit = 1cum
A. MATERIALS:
Cement
Bricks1st Class traditional size 23 x 11 x 7 cms

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg

96.00

4848.76

465.48

465.481072

Nos

512.00

5447.83

2789.29

2789.29

Fine aggregate (Sand)


Seigniorage charges for F.A
B. LABOUR:
Mason 1st class

cum

0.20

134.23

26.85

26.85

cum

0.20

day

0.24

415.00

99.60

99.60

Mason 2 class
Mazdoor (unskilled)
Add 25% for MC on Labour charges

day

0.56

370.00

207.20

207.20

day

1.89

310.00

585.90

585.90

Towards water charges


Grand Total
Add 14% over head charges

0.01

nd

0.00
4174.31

Add scaffolding charges for 1st floor


Rate for 1st floor

#REF!

RATE FOR 2ND FLOOR


Rate /cum
Add Lift charges for 2nd floor
Add scaffolding charges for 2nd floor
Rate for 2nd floor

4174.31

41.74

per sqm

4216.06

0.00

590.25

0.00

4806.00

0.00

#REF!

#REF!

#REF!

#REF!

4806.00

0.00

4.10
#REF!

per sqm

#REF!
#REF!

Note : 1. When Mortar mix is changed as CM 1:4, 1:5, 1:6


and 1:8, proportionate quantity of cement has to be
substituted. No change in other data.
2. When First class Modular Bricks are used provide 570 nos
bricks of size 19 x 9 x 9 cms.
b

Brick Masonry in CM (1:6) with Fly ash Bricks


of size 290 x 225 x 140 mms
Unit = 1cum
A. MATERIALS:
Cement

kg

24.00

4848.76

116.37

116.370268

Bricks1st Class traditional size 29 x 22.5 x14 cms

Nos

110.00

24.00

2640.00

2.64

Fine aggregate (Sand)

cum

0.10

134.23

13.42

13.42

Seigniorage charges for F.A

cum

0.10

Mason 1st class

day

0.24

415.00

99.60

99.60

nd

Mason 2 class

day

0.56

370.00

207.20

207.20

Mazdoor (unskilled)

day

1.89

310.00

585.90

585.90

0.00

892.70

0.00

B. LABOUR:

Grand Total

1025.13

Add 25% for MC on Labour charges


total

3662.49

Add 1% for water

0.01

3662.49

Grand Total

36.62
3699.12

Add 14% over head charges

1025.13

0.00

143.52

3699.00

1169.00

Masonry work for Foundation, Basement,


Rate

1Cum

1.00

3699.00

3699.00

689

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Add 14% over head charges

Amount
Rs.with
MA

Amount
without M.A

0.00

Rate per 1 Cum

3699.00

For Super Structure

FF

SF

TF

4th F

rate

3699.00

3699.00

3699.00

3699.00

Add Access Scoffolding incld MA

246.85

336.12

425.42

514.69

0.00

89.27

178.54

267.81

Add Lift charges


Add 25% MA on lift charges

5th F

357.08

0.00

0.00

0.00

0.00

0.00

3945.85

4124.39

4302.96

4481.50

357.08

Over head charges 14%

0.00

0.00

0.00

0.00

0.00

Grand Total for 10 Sqm

3945.85

4124.39

4302.96

4481.50

357.08

per1Cum

per1Cum

per1Cum

per1Cum

per1Cum

690

BLD-CSTN

Index-code

BLD-CSTN-3-2

S No Description
1

30

Brick Masonry in CM (1:3) with Modular Bricks


19 x 9 x 9 cms 2nd class

Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2 class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
total
Add 1% for water
Grand Total
Add 14% over head charges
nd

Add scaffolding charges for 1st floor


Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Add Lift charges for 2nd floor
Add scaffolding charges for 2nd floor
Rate for 2nd floor
ii

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg

100.60

4848.76

487.79

Nos
cum

520.00
0.21

6447.83
134.23

3352.87
28.19

cum

0.21

day

0.24

415.00

99.60

day

0.56

370.00

207.20

day

1.89

310.00

585.90
0.00
4761.54

0.01

#REF!

#REF!

4761.54

per sqm

47.62
4809.16
673.28
5482.00
#REF!
#REF!

5482.00
4.10
#REF!
#REF!

per sqm

Brick Masonry in CM (1:4) with Modular Bricks


19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2 class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
total
Add 1% for water
Grand Total
Add 14% over head charges
nd

Add scaffolding charges for 1st floor


Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Add Lift charges for 2nd floor
Add scaffolding charges for 2nd floor
Rate for 2nd floor
iii

kg

75.60

4848.76

366.57

Nos
cum

520.00
0.21

6447.83
134.23

3352.87
28.19

cum

0.21

day

0.24

415.00

99.60

day

0.56

370.00

207.20

day

1.89

310.00

585.90

0.01

#REF!

0.00

per sqm

#REF!

per sqm

kg

60.48

0.00
4640.32
0.00
4640.32
649.65
5290.00
#REF!
#REF!

5290.00
4.10
#REF!
#REF!

Brick Masonry in CM (1:5) with Modular Bricks


19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement

4848.76

293.25

691

BLD-CSTN

Index-code

S No Description
1

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

Bricks modular size 19 x 9 x 9 cms 2nd class


Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class

Nos
cum

520.00
0.21

6447.83
134.23

3352.87
28.19

cum

0.21

day

0.24

415.00

99.60

Mason 2nd class


Mazdoor (unskilled)
Add 25% for MC on Labour charges
total
Add 1% for water
Grand Total
Add 14% over head charges
Grand Total
Add scaffolding charges for 1st floor
Rate for 1st floor

day

0.56

370.00

207.20

day

1.89

310.00

585.90

RATE FOR 2ND FLOOR


Rate /cum
Add Lift charges for 2nd floor
Add scaffolding charges for 2nd floor
Rate for 2nd floor
iv

Unit

0.00
0.01

#REF!

4567.01

4567.01
45.67
4612.68
645.78
5258.00
#REF!
#REF!

per sqm

5258.00
4.10
#REF!
#REF!

#REF!

per sqm

kg

50.40

4848.76

244.38

Nos
cum

520.00
0.21

6447.83
134.23

3352.87
28.19

cum

0.21

day

0.24

415.00

99.60

day

0.56

370.00

207.20

day

1.89

310.00

585.90

Brick Masonry in CM (1:6) with Modular Bricks


19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2 class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
nd

0.00
4518.14

Add 1% for water


Grand Total
Add 14% over head charges

0.01

4518.14

45.18
4563.32
638.86
5202.00

Add scaffolding charges for 1st floor


Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Add Lift charges for 2nd floor
Add scaffolding charges for 2nd floor
Rate for 2nd floor
iv

#REF!

per sqm

#REF!
#REF!

5202.00
4.10
#REF!

per sqm

#REF!
#REF!

Brick Masonry in CM (1:8) with Modular Bricks


19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class

Fine aggregate (Sand)


Seigniorage charges for F.A
B. LABOUR:

kg

37.80

4848.76

183.28

Nos
cum

520.00
0.21

6447.83
134.23

3352.87
28.19

cum

0.21

692

BLD-CSTN

Index-code

S No Description
1

Unit

Amount
Rs.with
MA

Amount
without M.A
7

Mason 1 class

0.24

415.00

99.60

Mason 2nd class


Mazdoor (unskilled)
Add 25% for MC on Labour charges
total
Add 1% for water
Grand Total
Add 14% over head charges

day

0.56

370.00

207.20

day

1.89

310.00

585.90

0.01

Add scaffolding charges for 1st floor


Rate for 1st floor

#REF!

RATE FOR 2ND FLOOR


Rate /cum
Add Lift charges for 2nd floor
Add scaffolding charges for 2nd floor
Rate for 2nd floor

BLD-CSTN-3-3

Rate Rs.

day

st

31

Quantity

4457.04

per sqm

0.00
4457.04
44.57
4501.61
630.23
5132.00
#REF!
#REF!

5132.00
4.10
#REF!
#REF!

#REF!

per sqm

nos

565.000

5447.83

3078.02

11.5 cm wide Brick masonry for superstructure on ground floor in cm (1:3) using
second class traditional size bricks excluding
seigniorage charges, including cost of all
materials, labour and all operations for
constructing half brick masonry, mixing
cement mortar, curing etc., complete for
finished item of work, but excluding
conveyance charges of materials.
unit:10sqm
A. MATERIALS:
Country bricks, second class traditional size
23x11x7cm
Cement
Sand
Seigniorage charges for sand
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Add water charges 1%

kg.

106.000

4848.76

513.97

cum

0.220

134.23

29.53

cum

0.220

day

0.600

415.00

249.00

day

0.600

370.00

222.00

day

2.750

310.00

852.50

1.00%

Add 20% for MC on Labour charges


total

49.45
1323.50

0.00
4994.47

RBM 115mm thick with Fly Ash Blocks

GF(F1)

FF(F2)

SF(F3)

3rdF(F4)

4thF(F5)

Basic Rate

4994.47

4994.47

4994.47

4994.47

4994.47

Add scaffolding charges for 1st floor incld MA


on
Addlabour
Lift charges

318.61

433.83

549.09

664.31

779.53

0.00

132.35

264.70

397.05

529.40

0.00

0.00

0.00

0.00

0.00

5313.09

5560.65

5808.27

6055.83

6303.40

723.38
6036.46

757.08
6317.74

790.80
6599.06

824.50
6880.34

858.21
7161.61

Say

6036.00

6318.00

6599.00

6880.00

7162.00

Rate per 1 Sqm

604.00

632.00

660.00

688.00

716.00

per1Sqm

per1Sqm

per1Sqm

per1Sqm

per1Sqm

Add 20% MA on lift charges


Over head charges 13.615%
Grand Total for 10 Sqm

693

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

II Class Bricks

cum

221.000

14448.71

3193.16

3193.16

C.M.(1:6)

cum

0.200

1366.64

273.33

273.33

Mason 1st class

day

0.600

415.00

249.00

249.00

Mason 2 class
Mazdoor (unskilled)

day

0.600

370.00

222.00

222.00

day

2.750

310.00

852.50

852.50

Water charges 1%

0.010

4789.99

47.90

Add 20% for MC on Labour charges

0.00

1323.50

0.00

Add 1% Towards water

0.01

4837.89

S No Description
1

32

Reinforced Brick Masonary walls of 11.5cm in


CM(1:6) using FlyAsh bricks having a crushing
strength of not less than 35.00kg/cm2 and using
two mild steel bars of 6m dia in every third layer of
brick masory, with free joints of the main block
work including cost and seignorage charges and
conveyance of all materials and water from
approved sources to work site and all operational,
incidental, labour charges such as scaffolding
mixing mortor constructing masonary lift charges,
curing etc. complete but excluding the cost of steel
and its fabrication charges for finished item of work
as per SS 509

BLD-CSTN-3-4

Ground Floor :
A. MATERIALS:

B. LABOUR:
nd

4837.89

Grand Total
RBM 115mm thick with Fly Ash Blocks
Basic Rate
Add scaffolding charges for 1st floor incld MA
on
Addlabour
Lift charges
Add 25% MA on lift charges

33

BLD-CSTN-3-5

48.38
4886.27

0.00

GF(F1)

FF(F2)

SF(F3)

3rdF(F4)

4thF(F5)

4886.27

4886.27

4886.27

4886.27

4886.27

318.61

433.83

549.09

664.31

779.53

0.00

132.35

264.70

397.05

529.40

0.00

0.00

0.00

0.00

0.00

5204.89

5452.45

5700.07

5947.63

6195.20

Over head charges 14%

728.68

763.34

798.01

832.67

867.33

Grand Total for 10 Sqm

5933.57

6215.80

6498.08

6780.30

7062.53

Say

5934.00

6216.00

6498.00

6780.00

7063.00

Rate per 1 Sqm

593.00
per1Sqm

622.00
per1Sqm

650.00
per1Sqm

678.00
per1Sqm

706.00
per1Sqm

Exposed brick masonry for super structure on


ground floor in cm (1:6) using wire cut bricks
or
moulded
bricks
including
making
horizontal and vertical grooves 10mm Wide
12mm deep, cost of all materials, seigniorage
charges, labour and all operations, mixing
cement mortar, curing etc., complete for
finished item of work, but excluding
conveyance charges of materials
unit:1cum
A. MATERIALS:
Wire cut bricks or moulded bricks size 19x9x9cm

nos

520.000

6447.83

3352.87

Cement

kg.

48.00

4848.76

232.74

694

BLD-CSTN

Index-code

S No Description
1

Sand
Seigniorage charges for sand
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Add water charges 1%

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

cum

0.20

134.23

26.85

999.00

0.20

day

0.57

415.00

236.55

day

0.57

370.00

210.90

day

2.54

310.00

787.40

1.00%

1234.85

12.35

Add 25% for MC on Labour charges


total

0.00
4859.65

Add 1% Towards water

0.01

4859.65

48.60

Grand Total

4908.25

Add 14% over head charges

687.16
5595.00

Note : Compressive strength of individual Brick


shall not be less than 70 kg / cm2
34

BLD-CSTN-3-6

Brickwork in arches in cement mortar 1:4


complete including centering and shuttering
excluding pointing and plastering as per
drawing and technical specifications Clauses
606 and 1205.1 MORD
Unit = cum
a) Material
Brick 1st class
Cement mortar (1:4)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Add 25% for MC on Labour charges
total
Add 1% Towards water

Nos.

525.00

6447.83

3385.11

cum

0.24

1948.49

467.64

day

1.88

310.00

582.80

day

2.00

415.00

0.01

5265.55

830.00
0.00
5265.55
52.66
5318.20
744.55
6063.00
5792.10

Add 14% over head charges


c) Add for centering and shuttering @ 110% of
(a+b)

5265.55

Grand Total

28501.60

Add 25% for MC on Labour charges


Grand Total

28501.60

0.00

Add 14% over head charges

3990.22
32492.00

Note : 1 ) In case cement mortar 1:3 is used, proportionate rate is to be adopted.


2) Quantity of bricks for arches will be about 10 per cent more than that for ordinary brickwork .
3) In case special arch bricks are used, the quantity of bricks per cum shall be taken as 580 Nos.
4) Rates for spandrel walls shall be taken same as for brickwork in substructure.
5) Rate for spandrel filling will depend on the filling material adopted
6) Compressive strength of individual Brick shall not be less than 70 kg / cm2
35

BLD-CSTN-3-7

Honey Comb work with Bricks of traditional


Size and Plastered One Coat 10 mm. thick
Cement Mortar 1:5 including White Washing 2
Coats
Unit = cum
a) Material

695

BLD-CSTN

Index-code

S No Description
1

36

BLD-CSTN-3-8

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

Brick 2nd class 23 x 11 x 7

Nos.

750.00

5447.83

4085.87

Cement mortar (1:5)

cum

0.67

1599.38

1071.58

day
day
day
LS

6.60
2.41
6.21
LS

310.00
415.00
370.00

2046.00
1000.15
2297.70

Brick 2nd class 19 x 9 x 9

Nos.

790.00

6447.83

Cement mortar (1:5)

cum

0.67

1599.38

Mazdoor (Unskilled)

day

6.60

310.00

Mason (1st Class)

day

2.41

415.00

Mason (2nd Class)

day

6.21

370.00

White Washing 2 Coats

LS

LS

b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total
Honey Comb work with Bricks of Modular Size
and Plastered One Coat 10 mm. thick Cement
Mortar 1:5 including White Washing 2 Coats
Unit = cum
a) Material

b) Labour

696

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Grand Total

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

9142.21

STONE MASONRY, DAMP PROOF COURSE,


DRY STONE PACKING, QUARRY RUBBISH &
GRAVEL BACKING

BLD-CSTN-4
BLD-CSTN-4-1

37

Cut Stone Masonry in CM 1:2


Unit = 1cum
A. MATERIALS:
Cement
Cut Stone Roughly dressed to shape at quarry

kg

115.20

4848.76

558.58

cum

0.89

574.27

511.10

Bond Stones

cum

0.16

574.27

91.88

Fine aggregate (Sand)


Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2nd class

cum

0.16

134.23

21.48

cum

0.16

day

1.05

415.00

435.75

day

2.45

370.00

906.50

Man mazdoor
Woman mazdoor
Add 25% for MC on Labour charges

day

3.50

310.00

1085.00

day

2.80

310.00

868.00
0.00
4478.29

Add 1% Towards water


Grand Total
Add 14% over head charges

0.01

4478.29

44.78
4523.07
633.23
5156.00

Note : When Mortar mix is changed as CM 1:3, 1:4, 1:5, 1:6


and 1:8, proportionate quantity of cement has to be
substituted. No change in other data.
38

BLD-CSTN-4-2

CRS Masonry in CM (1:2) 1st Sort

Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 20% for MC on Labour charges
total
Add 1% Towards water
Grand Total
Add 14% over head charges

ii

CRS Masonry in CM (1:3) 1st Sort


Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 25% for MC on Labour charges

kg

201.60

4848.76

977.51

cum

0.94

654.27

615.02

7Nos.

0.16

1122.63

179.62

cum

0.28

134.23

37.58

cum
cum

0.28
1.10

day
day

2.50
2.32

415.00
310.00

1037.50
719.20

0.01

3566.43

0.00
3566.43
35.66
3602.09
504.29
4106.00

kg

134.40

4848.76

651.67

cum

0.94

654.27

615.02

7Nos.

0.16

1122.63

179.62

cum

0.28

134.23

37.58

cum
cum

0.28
1.10

day
day

2.50
2.32

415.00
310.00

1037.50
719.20
0.00
3240.59

697

BLD-CSTN

Index-code

S No Description
1

Unit
3

Add 1% Towards water


Grand Total
Add 14% over head charges
iii

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

0.01

3240.59

32.41
3273.00
458.22
3731.00

CRS Masonry in CM (1:4) 1st Sort


Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
total
Add 1% Towards water
Grand Total
Add 14% over head charges

kg

100.80

4848.76

488.76

cum

0.94

654.27

615.02

7Nos.
cum

0.16
0.28

1122.63
134.23

179.62
37.58

cum
cum

0.28
1.10

day
day

2.50
2.32

415.00
310.00

1037.50
719.20

3077.68

0.00
3077.68
30.78

0.01

3108.45
435.18
3544.00

698

BLD-CSTN

Index-code

S No Description
1

iv

CRS Masonry in CM (1:6) 1st Sort


Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 20% for MC on Labour charges
total
Add 1% Towards water
Grand Total
Add 13.615% over head charges

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg

67.20

4848.76

325.84

cum

0.94

654.27

615.02

7Nos.
cum

0.16
0.28

1122.63
134.23

179.62
37.58

cum
cum

0.28
1.10

day
day

2.50
2.32

415.00
310.00

1037.50
719.20
0.00
2914.76

0.01

2914.76

29.15
2943.90
400.81
3345.00

39

BLD-CSTN-4-3

CRS Masonry in CM (1:6) 2nd Sort

Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 20% for MC on Labour charges
total
Add 1% Towards water
Grand Total
Add 13.615% over head charges

kg

76.80

4848.76

372.38

372.38

cum

0.94

840.79

790.34

790.34

cum

0.16

1182.73

189.24

189.24

cum

0.32

134.23

42.95

42.95

cum

0.32

cum

1.10

day

1.50

415.00

622.50

622.50

day

2.32

310.00

719.20

719.20

0.00
2736.62
0.01

2736.62

2736.62

27.37

27.37

2763.98

2763.98

376.32

376.32

3140.00

3140.30

Note : When Mortar mix is changed proportionate quantity of


cement has to be substituted. No change in other data.
40

BLD-CSTN-4-4

Coursed rubble stone masonry arch (Ist sort)


in cement mortar (1:4) complete including
centering etc. complete as per drawing and
technical specifications Clauses 706 and
1205.1
Unit = cum
A. Material
Stone for CR masonry 1st sort
Through and bond stone (7 Nos 0.24x0.24x0.39 =
0.16 cum)
Cement mortar (Rate as in item 11.5 II)
B. Labour
Mason (1st Class)
Mazdoor (Unskilled)
C. Add for centering and shuttering @ 100 %
of (a+b)
Grand Total
Add 25% for MC on Labour charges
Grand Total

cum

0.94

654.27

615.02

Nos.

0.16

1182.73

189.24

cum

0.30

1948.49

584.55

day

3.00

415.00

1245.00

day

2.43

310.00

753.30
2802.55
6189.65
0.00
6189.65

699

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Add 14% over head charges

Amount
Rs.with
MA

Amount
without M.A

866.55
7056.00

Note : 1) In case cement mortar 1:3 is used,


proportionate rate is to be adopted.
2) The addition for centering and sluttering at (c) above is for arch
above 6 m span. For lesser span length the addition shall be 80 per
cent for span above 4 m length and 50 per cent for spans less than 4
m.
41

BLD-CSTN-4-5

Ashlar Arch Work in Cement Mortar (1:4)

Unit = 1cum
A. MATERIALS:
Cement

kg

57.60

4848.76

279.29

cum

0.89

654.27

582.30

Bond Stones of Cutstone quality


Fine aggregate (Sand)

cum

0.16
0.16

654.27
134.23

104.68
21.48

Seigniorage charges for F.A

cum

0.16

Cut Stone Roughly dressed to shape at quarry

700

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Mason 1st class

day

5.05

415.00

2095.75

Mason 2nd class

day

2.45

370.00

906.50

Mazdoor (unskilled)

day

6.30

310.00

1953.00

Centering Charges
Grand Total
Rubble Arch Work in Cement Mortar (1:4)

LS

kg
cum

100.80
1.15

4848.76
574.27

488.76
660.41

cum
cum

0.28
0.28

134.23

37.58

day

0.90

415.00

373.50

day
day

2.10
2.43

370.00
310.00

777.00
753.30

S No Description
1

B. LABOUR:

42

BLD-CSTN-4-6

Unit = 1cum
A. MATERIALS:
Cement
Seleted Stone of sizes as per specification
(including Bond Stones)
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Centering Charges
43

BLD-CSTN-4-7
I

LS

Grand Total
Providing & Laying
reinforced cement
concrete arch complete including centering
and shuttering excluding reinforcement as per
drawings
and
technical
specifications
Clauses 800, 900 and 1205.1
Unit = cum
RCC grade M20 nominal mix
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
b) Labour
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.3/0.20 cum capacity

3090.55

0.40

4848.76

cum

0.45

134.23

1939.50
60.40

cum

0.54

1687.27

911.13

cum

0.36

1257.27

452.62

day

0.20

415.00

83.00

day

2.15

310.00

666.50

hour

0.40

222.80

89.12

d) Add for cost of centering and shuttering @ 50 per


cent of (a+b) per sqm of surface of arch soffit

II

Grand Total
RCC Grade M 25 (Design mix)
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
b) Labour
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.3/0.20 cum capacity

4202.27

0.38

4848.76

cum

0.45

134.23

1842.53
60.40

cum

0.54

1687.27

911.13

cum

0.36

1257.27

452.62

day

0.20

415.00

83.00

day

2.15

310.00

666.50

hour

0.40

222.80

89.12

d) Add for cost of centering and shuttering @ 50 per


cent of (a+b) per sqm of surface of arch soffit

Grand Total

4105.30

701

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Note : The additional cost of centering and shuttering @ 50 per cent


of cost of material and labour shall hold good for arch spans of 6 m
and above. For lesser length of spans, the corresponding additional
cost can be taken as 40 per cent for spans above 4 m length and 30
per cent for spans less than 4 m.

702

BLD-CSTN

Index-code

S No Description
1

44

RR Masonry in CM (1:6)
Unit = 1cum
A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
total
Add 1% Towards water
Grand Total
Add 14% over head charges

BLD-CSTN-4-8

45

BLD-CSTN-4-9

46

BLD-CSTN-4-10

47

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg

79.20

4848.76

384.0

cum

0.44

654.27

287.88

cum

0.50

602.27

301.14

cum
cum

0.16
0.33

1122.63
134.23

179.62
44.29

cum
cum

0.33
1.10

day

1.20

415.00

498.00

day

2.00

310.00

620.00

RR Masonry in CM (1:8)
Unit = 1cum
A. MATERIALS:
kg
Cement
cum
CR Stone
cum
Rough Stone
cum
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
cum
Fine aggregate (Sand)
cum
Seigniorage charges for F.A
cum
Seigniorage charges for Stone
B. LABOUR:
day
Mason 1st class
day
Mazdoor (unskilled)
Add 25% for MC on Labour charges
total
Add 1% Towards water
Grand Total
Add 14% over head charges
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted. No change in other data
Dry Stone Masonry for Retaining Walls
Unit = 1cum
A. MATERIALS:
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mason 2 class
Mazdoor (unskilled)
Grand Total
Dry Stone Masonry for Well steining
Unit = 1cum
A. MATERIALS:
Rough Stone
Bond Stones
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
nd

BLD-CSTN-4-11

Unit

0.00
2314.95
23.15
2338.10
327.33
2665.00

0.01

2314.95

59.40

4848.76

288.0

0.00

654.27

0.00

1.10

602.27

662.50

0.00
0.33

1122.63
134.23

0.00
44.29

1.20

415.00

498.00

2.00

310.00

620.00

0.33
1.10

0.01

2112.81

cum
cum

1.04
0.16

602.27
1122.63

cum

1.20

day

0.33

415.00

day

0.77

370.00

day

1.10

0.00
2112.81
21.13
2133.94
298.75
2433.00

310.00
2819.90

cum
cum

1.04
0.16

cum

1.20

day

0.45

602.27
1122.63

415.00

703

BLD-CSTN

Index-code

S No Description
1

Mason 2 class
Mazdoor (unskilled)
Grand Total
nd

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day

1.05

370.00

day

1.10

310.00
2819.90

704

BLD-CSTN

Index-code

S No Description
1

48

Damp Proof, Course Damp Proof (or anti


Proof) Course with Cuddapah / Shabad slabs
50 mm. thick in CM (1:3)
(Unit - 10 sqm)

BLD-CSTN-4-12

A. MATERIALS:
Cuddapah / Shabad slabs 50 mm. thick
Cement Mortar 1:3
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Grand Total

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

sqm

10.50

86.00

cum

0.15

2530.34

day

0.90

415.00

day

2.10

370.00

day

2.00

310.00
3711.34

POINTING
BLD-CSTN-5

49

BLD-CSTN-5-1

Flush Pointing with CM (1:3) to Brick / CRS


Masonry
Unit = 10 sqm
A. MATERIALS:
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 2nd class

50

BLD-CSTN-5-2

Mazdoor (unskilled)
Add 20% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 13.615% over head charges
Rate for 10 Sqm
Rate for 1 Sqm
Flush Pointing with CM (1:3) to RR Masonry

14.40

4848.76

69.82

cum

0.03

134.23

4.03

cum

0.03

day

0.50

370.00

185.00

day

0.74

310.00

229.40

1.00%

488.25

0.00
488.25
4.88
493.13
67.14
560.00
56.00

Unit = 10 sqm
A. MATERIALS:
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 2nd class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
total
Add 1% Towards water
Grand Total
Add 14% over head charges
51

BLD-CSTN-5-3

kg

kg

14.40

4848.76

69.82

cum

0.03

134.23

4.03

cum

0.03

day

0.50

370.00

185.00

day

0.74

310.00

229.40

1.00%

488.25

0.00
488.25
4.88
493.13
69.04
562.00

Raised Pointing with CM (1:3) to RR Masonry


Unit = 10 sqm
A. MATERIALS:
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 2nd class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
total
Add 1% Towards water
Grand Total

kg

28.80

4848.76

139.64

cum

0.06

134.23

8.05

cum

0.06

day

0.50

370.00

185.00

day

0.74

310.00

229.40

1.00%

562.10

0.00
562.10
5.62
567.72

705

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Add 14% over head charges


Rate per 10 sqm
52

BLD-CSTN-5-4

Amount
Rs.with
MA

Amount
without M.A

79.48
647.00

Raised and cut pointing on coursed or Ashlar stone


masonry or concrete block walling in white cement
mortar 1 : 3 (1 white cement : 3 marble dust).

Details of cost for 10 sq.m


Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Add for contractor's profit and overheads @ 10%

cum

0.038

1948.49

74.04

day

1.460

370.00

540.20

day

2.260
1240.800

310.00

700.60
12.41

Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Rate per 10 sqm
Note : When Mortar mix is changed as CM 1:4 proportionate
quantity of cement has to be substituted. No change in other
data.

1327.25
0.00
1327.25
185.82
1513.00

706

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.15

2530.34

379.55

cum

0.15

day

0.60

415.00

249.00

day

0.96

310.00

297.60

PLASTERING
BLD-CSTN-6
BLD-CSTN-6-1

53

Plastering with CM (1:3), 12 mm thick


Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 14% over head charges
Add scaffolding charges for 1st floor
Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor
Rate for 2nd floor

54

BLD-CSTN-6-2

Plastering with CM (1:4), 12 mm thick


Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 14% over head charges

1.00%

#REF!

per sqm

0.15
#REF!

4.10
per sqm

cum

0.15

cum

0.15

day
day

926.15

0.00
926.15
9.26
935.41
130.96
1066.00
#REF!
#REF!

1066.00
0.62
#REF!
#REF!

1948.49

292.27

0.60

415.00

249.00

0.96

310.00

297.60
0.00
838.87

1.00%

838.87

8.39
847.26
118.62
966.00

Add scaffolding charges for 1st floor


Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor
Rate for 2nd floor
55

BLD-CSTN-6-3

Plastering with CM (1:5), 12 mm thick


Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 14% over head charges

7.69

per sqm

7.69
974.00

966.00
0.15

4.10

0.62

10.53

per sqm

10.53
977.00

cum

0.150

cum

0.150

1599.38

239.91

day

0.60

415.00

249.00

day

0.96

310.00

297.60
0.00
786.51

1.00%

786.51

7.87
794.37
111.21

707

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

906.00

Add scaffolding charges for 1st floor


Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor
Rate for 2nd floor
56

BLD-CSTN-6-4

Plastering with CM (1:6), 12 mm thick


Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:6)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 14% over head charges
Add scaffolding charges for 1st floor
Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor
Rate for 2nd floor

57

BLD-CSTN-6-5

Plastering with CM (1:5), 12 mm thick


Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 14% over head charges

7.69

per sqm

0.15
10.53

4.10
per sqm

cum

0.15

cum

0.15

day
day

7.69
1819.00

794.37
0.62
10.53
806.00

1366.64

205.00

0.60

415.00

249.00

0.96

310.00

297.60

1.00%

7.69

per sqm

0.15
10.53

4.10
per sqm

cum

0.15

cum

0.15

day
day

1503.19

751.60
0.00
1503.19
15.03
1518.22
212.55
1731.00
7.69
1739.00

1731.00
0.62
10.53
1742.00

1599.38

239.91

0.60

415.00

249.00

0.96

310.00

297.60
0.00
786.51

1.00%

786.51

7.87
794.37
0.00
794.00
79.00

Add scaffolding charges for 1st floor


Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor

7.69

per sqm

7.69
87.00

794.00
0.15

4.10

0.62

10.53

per sqm

10.53

708

BLD-CSTN

Index-code

S No Description
1

Rate for 2nd floor

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

805.00

709

BLD-CSTN

Index-code

S No Description
1

58

Plastering with CM (1:4), 15 mm thick

BLD-CSTN-6-6

Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
Mason 2nd class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 14% over head charges
Add scaffolding charges for 1st floor
Rate for 1st floor

59

BLD-CSTN-6-7

RATE FOR 2ND FLOOR


Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor
Rate for 2nd floor
Plastering with CM (1:4), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
Mason 2nd class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 14% over head charges

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.19

1948.49

370.21

cum

0.19

day

0.60

370.00

222.00

day

0.96

310.00

297.60

1.00%

7.69

per sqm

0.19
10.53

4.10
per sqm

cum

0.210

cum

0.21

day
day

889.81

0.00
889.81
8.90
898.71
125.82
1025.00
7.69
1033.00

1025.00
0.78
10.53
1036.00

1948.49

409.18

0.94

370.00

347.80

1.60

310.00

496.00
0.00
1252.98

1.00%

1252.98

12.53
1265.51
0.00
1266.00

Add scaffolding charges for 1st floor


Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor
Rate for 2nd floor
60

BLD-CSTN-6-8

Plastering with CM (1:3), 20 mm thick


Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3)
Seigniorage charges for F.A
B. LABOUR:
Mason 2nd class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 14% over head charges

7.69

per sqm

10.00

76.88
1343.00

1266.00
0.21

4.10

0.86

10.53

per sqm

10.53
1277.00

cum

0.210

cum

0.21

2530.34

531.37

day
day

0.94

370.00

347.80

1.60

310.00

496.00

1375.17

0.00
1375.17
13.75
1388.92
194.45

1.00%

710

BLD-CSTN

Index-code

S No Description
1

Add scaffolding charges for 1st floor


Rate for 1st floor

Unit

Quantity

Rate Rs.

7.69

BLD-CSTN-6-9

per sqm

1583.00
0.86
10.53
1594.00

4.10
per sqm

kg

43.00

4848.76

208.50

208.50

cum

0.18

134.23

24.16

24.16

kg

14.50

4848.76

70.31

70.31

cum

0.04

134.23

5.37

5.37

cum

0.22

day

0.63

415.00

261.45

261.45

1.47

370.00

543.90

543.90

3.90

310.00

1209.00

1209.00

day
Mason 2nd class
day
Mazdoor (unskilled)
Add 20% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted

20mm plastering
Basic Rate
Add scaffolding charges for 1st floor
Add Lift charges
Over head charges 13.615%
Grand Total
Rate for 10 Sqm

BLD-CSTN-6-10

6
1583.00
7.69

Plastering with CM 2 coats, 20 mm thick, base


coat in CM (1:6), 16mm thick and top coat in
CM (1:4), 4mm thick with Dubara sponze
finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:4), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class

62

Amount
without M.A

1591.00

RATE FOR 2ND FLOOR


Rate /cum
0.21
Lift charges for sand
10.53
Add scaffolding charges for 2nd floor
Rate for 2nd floor
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted
61

Amount
Rs.with
MA

1.00%

2014.35

0.00

2322.68

2322.68
23.23
2345.91

0.00

GF

FF

SF

3rdF

4thF

2345.91

2345.91

2345.91

2345.91

2345.91

71.70

71.70

97.70

123.60

149.6

0.00

201.44

201.44

201.44

201.44

2417.61

2619.05

2645.05

2670.95

2696.95

2417.61
2418.00
242.00
per1Sqm

2619.05
2619.00
262.00
per1Sqm

2645.05
2645.00
265.00
per1Sqm

2670.95
2671.00
267.00
per1Sqm

2696.95
2697.00
270.00
per1Sqm

Plastering with CM 2 coats, 12 mm thick, base


coat in CM (1:5), 8mm thick and top coat in
CM (1:3), 4mm thick with sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:3), 4 mm thick
Cement
Fine aggregate (Sand)

kg

31.70

4848.76

153.71

153.705729

cum

0.11

134.23

14.76

14.76

kg

19.20

4848.76

93.10

93.10

cum

0.04

134.23

5.37

5.37

711

BLD-CSTN

Index-code

S No Description
1

Unit

Amount
Rs.with
MA

Amount
without M.A

261.45

261.45

Seigniorage charges for F.A


B. LABOUR:
Mason 1st class

0.15

day

0.63

415.00

Mason 2 class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 14% over head charges

day

1.47

370.00

543.90

543.90

day

3.90

310.00

1209.00

1209.00

2014.35
1.00%

12mm plastering
Basic Rate
Add scaffolding charges for 1st floor
Add Lift charges

#REF!

per sqm

2281.29

10.00

22.81
2304.10

0.00

322.57

0.00

2627.00

0.00

#REF!

#REF!

#REF!

#REF!
#REF!

2627.00
0.15

4.10

0.62

#REF!

per sqm

#REF!
#REF!

GF

FF

SF

3rdF

4thF

2304.10

2304.10

2304.10

2304.10

2304.10

71.70

97.70

123.60

149.6

201.44

201.44

201.44

201.44

2304.10

Over head charges 14%


Grand Total

0.00
2281.29

Add scaffolding charges for 1st floor


Rate for 1st floor
Rate per 1 Sqm
RATE FOR 2ND FLOOR
Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor
Rate for 2nd floor

322.57
2626.67
Say 2627.00
per10Sqm

BLD-CSTN-6-10

Rate Rs.

cum

nd

62

Quantity

2577.23

2603.23

2629.13

2655.13

360.81
2938.05
2938.00

364.45
2967.69
2968.00

368.08
2997.21
2997.00

371.72
3026.85
3027.00

per10Sqm

per10Sqm

per10Sqm

per10Sqm

Plastering with CM 2 coats, 12 mm thick, base


coat in CM (1:6), 8mm thick and top coat in
CM (1:4), 4mm thick with sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 8 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:4), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Add 20% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
12mm plastering
Basic Rate
Add scaffolding charges for 1st floor
Add Lift charges

kg

26.50

4848.76

128.49

128.4921709

cum

0.11

134.23

14.76

14.76

kg

14.50

4848.76

70.31

70.31

cum

0.04

134.23

5.37

5.37

cum

0.15

day

0.63

415.00

261.45

261.45

day

1.47

370.00

543.90

543.90

day

3.90

310.00

1209.00

1209.00

0.00

2014.35

0.00
2233.28

1.00%

2233.28

22.33
2255.62

0.00

GF

FF

SF

3rdF

4thF

2255.62

2255.62

2255.62

2255.62

2255.62

71.70

71.70

97.70

123.60

149.6

0.00

201.44

201.44

201.44

201.44

2327.32

2528.75

2554.75

2580.65

2606.65

712

BLD-CSTN

Index-code

S No Description
1

Over head charges 13.615%


Grand Total

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

316.86
2644.18
Say 2644.00

344.29
2873.04
2873.00

347.83
2902.58
2903.00

351.36
2932.01
2932.00

354.90
2961.55
2962.00

per10Sqm

per10Sqm

per10Sqm

per10Sqm

per10Sqm

264.00

287.00

290.00

293.00

per 1Sqm

per 1Sqm

per 1Sqm
62

BLD-CSTN-6-10

296.00
per 1Sqm

Plastering with CM 2 coats, 12 mm thick, base


coat in CM (1:6), 8mm thick and top coat in
CM (1:4), 4mm thick with sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 8 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:4), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2 class
Mazdoor (unskilled)
Add 20% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
nd

kg

26.50

364.45

9.66

9.657996603

cum

0.11

2967.69

326.45

326.45

kg

14.50

364.45

5.28

5.28

cum

0.04

0.00

0.00

0.00

cum

0.15

day

0.63

0.00

0.00

0.00

day

1.47

310.00

455.70

455.70

day

3.90

4848.76

18910.17

18910.17

cum

19365.87

#VALUE!

1.00%

#VALUE!

#VALUE!
0.00

GF

FF

SF

3rdF

4thF

#VALUE!

#VALUE!

#VALUE!

#VALUE!

#VALUE!

0.00

0.00

0.00

0.00

0.00

1936.59

1936.59

1936.59

1936.59

#VALUE!

Over head charges 13.615%


Grand Total

#VALUE!
#VALUE!

12mm plastering
Basic Rate
Add scaffolding charges for 1st floor
Add Lift charges

#VALUE!

#VALUE!

#VALUE!
#VALUE!
Say #VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

per10Sqm

per10Sqm

per10Sqm

per10Sqm

per10Sqm

#VALUE!
per 1Sqm
b

per 1Sqm

#VALUE!

#VALUE!

#VALUE!

#VALUE!

per 1Sqm

per 1Sqm

per 1Sqm

#VALUE!

#VALUE!
per 1Sqm

Plastering with CM 2 coats, 12 mm thick, base


coat in CM (1:4), 8mm thick and top coat in
CM (1:2), 4mm thick with sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:4), 8 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:2), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Add 25% for MC on Labour charges

kg

39.62

4848.76

192.11

cum

0.11

134.23

14.76

kg

28.82

4848.76

139.74

cum

0.04

134.23

5.37

cum

0.15

day

0.63

415.00

261.45

day

1.47

370.00

543.90

day

3.90

310.00

1209.00

0.00

0.00

713

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Total
Add 1% Towards water
Grand Total
Add 14% over head charges

Amount
Rs.with
MA

Amount
without M.A

2366.33
1.00%

2366.33

23.66
2390.00
334.60
2725.00

Add scaffolding charges for 1st floor


Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor
Rate for 2nd floor

#REF!

per sqm

#REF!
#REF!

2725.00
0.15

4.10

0.62

#REF!

per sqm

#REF!
#REF!

Note : When Mortar mix is changed proportionate quantity of


cement has to be substituted
c

Plastering with CM 2 coats, 12 mm thick, base


coat in CM (1:5), 8mm thick and top coat in
CM (1:3), 4mm thick with sponze finishing.for
ceiling plastering.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:3), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 13.615% over head charges

kg

31.70

4848.76

153.71

cum

0.11

134.23

14.76

kg

19.20

4848.76

93.10

cum

0.04

134.23

5.37

cum

0.15

day

0.63

415.00

261.45

day

1.47

370.00

543.90

day

3.90

310.00

1209.00

0.00

0.00
2281.29

1.00%

2281.29

22.81
2304.10
322.57
2627.00

Add scaffolding charges for 1st floor


Rate for 1st floor
RATE FOR 2ND FLOOR
Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor
Rate for 2nd floor

9.28

per sqm

10.00

128.99
2755.99

2627.00
0.15

4.10

0.62

21.57

per sqm

21.57
2649.00

Plastering with CM 2 coats, 12 mm thick, base


coat in CM (1:5), 8mm thick and top coat in
CM (1:3), 4mm thick with sponze finishing.for
ceiling plastering.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement

kg

31.70

4848.76

153.71

714

BLD-CSTN

Index-code

S No Description
1

Unit

Fine aggregate (Sand)


Top Coat in CM(1:3), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Add 20% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
Add 13.615% over head charges

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

cum

0.11

134.23

14.76

kg

19.20

4848.76

93.10

cum

0.04

134.23

5.37

cum

0.15

day

0.63

415.00

261.45

day

1.47

370.00

543.90

day

3.90

310.00

1209.00
503.59
2784.87

1.00%

2784.87

27.85
2812.72
393.78
3207.00

Add scaffolding charges for 1st floor


Rate for 1st floor

4.59

10.00

63.80
3270.80

RATE FOR 2ND FLOOR


Rate /cum
Lift charges for sand
Add scaffolding charges for 2nd floor
Rate for 2nd floor
e

per sqm

3207.00
0.15

4.10

0.00

per sqm

0.62
0.00
3208.00

Ornamental Plastering with CM 2 coats, 12


mm thick, base coat in CM (1:5), 8mm thick
and top coat in CM (1:3), 4mm thick with
sponze finishing.for ceiling plastering.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:3), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Add 20% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
12mm plastering (Ornamental)
Basic Rate
Add scaffolding charges for 1st floor
Add Lift charges

kg

31.70

4848.76

153.71

cum

0.11

134.23

14.76

kg

19.20

4848.76

93.10

cum

0.04

134.23

5.37

cum

0.15

day

0.63

415.00

261.45

day

1.47

370.00

543.90

day

3.90

310.00

1209.00

0.00
1.00%

2281.29

22.81
2304.10

GF

FF

2304.10

2304.10

149.20

200.10

0.00
2453.30
Say 2453.00
per10Sqm

245.00
per1Sqm

SF

3rdF

4thF

0.00
2504.20
2504.00

2304.10
251.00
0.00
2555.10
0.00
2555.10
2555.00

2304.10
301.90
0.00
2606.00
0.00
2606.00
2606.00

0.00
2656.90
2657.00

per10Sqm

per10Sqm

per10Sqm

per10Sqm

0.00
2453.30

Over head charges 13.615%


Grand Total

0.00
2281.29

2504.20

250.00
per1Sqm

256.00
per1Sqm

261.00
per1Sqm

2304.10
352.8
0.00
2656.90

266.00
per1Sqm

715

BLD-CSTN

Index-code

S No Description
1

Ornamental Plastering 12 mm thick, single


coat in CM (1:5), with sponze finishing.for
ceiling plastering.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement
Fine aggregate (Sand)
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Add 25% for MC on Labour charges
Total
Add 1% Towards water
Grand Total
12mm plastering (Ornamental)
Basic Rate
Add scaffolding charges for 1st floor
Add Lift charges

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg

43.20

4848.76

209.47

cum

0.15

134.23

20.13

day

0.60

415.00

249.00

day

0.96

310.00

297.60

546.60
1.00%
GF

FF

783.96

783.96

149.20

200.10

0.00
933.16
Say 933.00

93.00
per1Sqm

BLD-CSTN-6-11

7.76

SF

3rdF

4thF

0.00
1038.72
1039.00

783.96
251.00
109.32
1144.28
0.00
1144.28
1144.00

783.96
301.90
163.98
1249.84
0.00
1249.84
1250.00

0.00
1355.40
1355.00

per10Sqm

per10Sqm

per10Sqm

per10Sqm

114.00

125.00

54.66

per10Sqm

63

776.20

783.96

933.16

Over head charges 13.615%


Grand Total

0.00
776.20

1038.72

104.00
per1Sqm

per1Sqm

per1Sqm

13.30

12.00

159.60

cum

0.25

2468.34

617.09

kg

50.00

4848.76

242.44

sqm

21.80

272.50

5940.50

day

8.00

415.00

3320.00

day

1.00

370.00

370.00

day

10.00

310.00

3100.00

222.80

445.60

783.96
352.8
218.64
1355.40

136.00
per1Sqm

RCM FACIA WORKS


RCM facia 5cm thick in CM (1:3) for drop walls, fins with
rabbit wire mesh & nominal reinforcement as directed by
Engineer-in-charge with dubara sponge finishing,
including cost & conveyance of all materials to site,
seigniorage charges, sales & other taxes on all materials,
operational & incidental, cost and conveyance of cement,
wire mesh, water to work site, centering, scaffolding and
form work, lift charges etc., complete for finished items of
work but excluding cost of steel & its fabrication charges,
for finished item of work. (APSS No.403 & 903)

Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop)
Cement Mortar 1:3 for 25 mm thick
Dry Cement for making Lumps
12 mm Plastering 2 coats in 1:4 & 1:2 cm both
sides
Excluding HYSD Steel/ Mild steel & Binding wire
B) LABOUR CHARGES
1st Class Mason
Miller Operator
Mazdoor (unskilled)
c) Machinery
Machine Mixing Mortar with Miller - Hire charges
BASIC COST per 10 sqm

sqm

32.00
Hrs

2.00

14195.22

716

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Add 25% for MC on Labour charges


Grand Total
Add 14% over head charges

Amount
Rs.with
MA

Amount
without M.A

0.00
14195.22
1987.33
16183.00

64

BLD-CSTN-6-12

20 mm thick rough cast exterior cement plaster on


walls upto height of 10 metres above ground level
consisting of 10 mm thick backing coat of 1 : 3
cement mortar (1 cement : 3 sand) and 10 mm thick
finishing coat of 1 : 3 cement mortar (1 cement : 3
coarse aggregate of size 6 mm to 10 mm) including
arrises, chamfers and/or rounded angles not
exceeding 80 mm in girth.

Details of cost for 10 sq.m


Materials :Cement mortar 1:3 (1 cement: 3 sand)
Cement mortar 1:3(1 cement: 3 coarse aggregate
of size 6 mm to 10 mm)
Cement

cum

0.110

2530.34

kg

52.800

4848.76

Coarse aggregate of size 6 mm -10 mm

cum

0.110

1157.27

Mazdoo (unskilled) for mixing mortar with coarse


aggreagate 6 - 10 mm

day

0.020

310.00

day
day

1.710
3.270

370.00
310.00

day
day

0.250
0.250
680.000

370.00
310.00
6.80
10213.18
0.00
10213.18
1429.84
11643.00

Labour for backing coat and finishing coat


-Plaster work :
Mason, llnd class
Mazdoo (unskilled)
Extra labour for scooping :
Mason, llnd class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 10 sq.m.
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

Cost per sq.m

1021.32

717

BLD-CSTN

Index-code

BLD-CSTN-6-13

S No Description
1

65

Rough cast exterior cement plaster on walls upto


a height of 10 metres above ground level with a
mixture of sand and gravel or crushed stone
graded from 6 mm to 10 mm nominal size dashed
over and including fresh plaster in two coats,
backing coat 10 mm cement plaster 1 : 3 (1
cemen" : 3 sand) and finishing coat 10 mm
cement plaster with cement mortar 1:3 (1 cement:
3 sand) mixed with 10% finely grounded hydrated
lime by volume of cement including arrises,
chamfers and/or rounded angles not exceeding
80 mm in girth.

(a) Natural cement finish using ordinary


cement.
Details of cost for 10 sq.m.
Materials :
Cement mortar 1:3 (1 cement: 3 sand)
Sand and gravel or crushed stone graded from 6
mm to 10 mm nominal size
Coarse aggregate of size 6 mm -10 mm
Carriage
Grounded hydrated lime
Carriage
Labour for backing coat and finishing coat
-Plaster work :
Mason, llnd class
Mazdoo (unskilled)
Add labour for dashing crushed stone
Mason 1st class
Mazdoo (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
(b) Dark coloured finish using
cement and pigment

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.224

cum

0.100

kg

9.280

day
day

1.710
3.270

day
day

0.500
1.000

kg

6.000

kg

6.000

ordinary

Details of cost for 10 sq.m.


Same rate as per (a) above item ()
Add cost of colour
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
(c) Light coloured finish using white cement
and pigment
Details of cost for 10 sq.m.
Same rate as per (a) above item ()
Add cost of light colour
Add for water charges on cost of colour @ 1 %
Add for contractor's profit and overheads on cost
of colour and water charges
Cost for 10 sq.m.
Cost per sq.m

718

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Details of cost for 10 sq.m


Materials :
Cement mortar 1:3
Grounded hydrated lime
Pebbles or crushed stone graded from 6 mm to
12 mm nominal size

cum
kg

0.224
9.280

Crushed stone / Pebble of size 6 mm -12 mm

cum

0.100

day
day

1.710
3.270

day
day

0.500
0.610

cum

0.023

day
day

0.300
0.350

cum

0.023

day
day

0.300
0.350

cum

0.023

day
day

0.380
0.430

S No Description
1

66

Pebble dash exterior plaster on walls upto a height of


10 metres above ground level with a mixture of washed
pebble or crushed stone graded from 6 mm to 12 mm
nominal size dashed over and including fresh cement
plaster in two coats, backing coat 10 mm cement
plaster 1 : 3 (1 cement : 3 sand) and finishing coat 10
mm cement plaster 1 : 3 (1 cement : 3 sand) mixed with
10% finely grounded hydrated lime by volume of
cement including arrises, chamfers and/or rounded
angles not exceeding 80 mm in girth

BLD-CSTN-6-14

Labour for backing coat and finishing coat :Mason llnd class
Mazdoor (unskilled)
Labour for pebble dashing
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Plain Cement Mortar Bands :
67

BLD-CSTN-6-15

20 mm thick plain cement mortar bands in


cement mortar 1 : 4 (1cement : 4 sand) upto 300
mm in width
(a) Flush Band :Details of cost for 10 metres long and 10 cm wide
band
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
b) Sunk band :Details of cost for 10 metres long and 10 cm wide
band
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
C) Raised Band :Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long

719

BLD-CSTN

Index-code

BLD-CSTN-6-16

S No Description
1

68

20 mm thick plain cement mortar bands in


cement mortar 1:4(1 cement: 4 sand) above 300
mm in width

(A)

Flush Band :Details of cost for 10 sq.m


Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m

(B)

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.224

day
day

2.200
2.700

cum

0.224

day
day

2.500
3.000

cum

0.224

day
day

3.000
3.500

cum

0.023

day
day

0.870
0.920

Sunk band :Details of cost for 10 sq.m

Materials :Cement mortar 1 :4


Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
(C) Raised band
Details of cost for 10 sq.m
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Moulded Cement Mortar Bands 15 mm
69

15 mm thick moulded cement mortar band in


cement mortar 1 : 4 (1cement: 4 sand)
Details of cost for 10 metres long and 10 cm wide
band

BLD-CSTN-6-17

Materials :Cement mortar 1 :4


Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
70

BLD-CSTN-6-18

Masonry work in CM (1:8) prop with Flyash


Cement solid blocks of size 290 x 225 x 140
mm for manufacturing of flyash solid blocks
using flyash of 80 kgs, cement of 15 kgs.
Gypsum of 5 kgs. and stone dust including
cost and conveyance of all materials, labour
charges, seiniorage charges, scaffolding and
curing etc., cpomplete with a compresive
streangth not lessthan 50 kg/sqm for walls for
Superstructure Walls.
Ground Floor
Unit = 1 cum

720

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

A. MATERIALS:
No of blocks required for one cum of Masonry
Cost of Cement Mortar (1:6)

day

110.000

0.00

cum

0.100

0.00

day
day

0.420
0.920

415.00
370.00

174.30
340.40

day
day

0.700
2.100
0.00%

310.00

217.00

557.40

1.00%

871.05

139.35
871.05
8.71
879.76

sqm

10.5

1691.32

17758.90

kg.
kg.
cum

21.6
9.6
0.12

1075.71

23235.41

2530.34

24291.28

134.23

16.11

cum
cum

0.02
0.14

134.23

2.68

B. LABOUR
Mason 1st class
Mason 2nd class
Man Mazdoor
Woman Mazdoor
Add 25% for MC on Labour charges
Flooring with Rough Kadapa/Shahabad ...
Total
mm thick stones, set over base coat of
Add 1% Towards water
cement mortar (1 : 8) 12 mm thick over
Grand Total

BLD-CSTN-7
BLD-CSTN-9-2

CC bed already laid or RCC roof slab,


FLOORING
including pointing with cement mortar
100
1:3 duly filling joints nearly, including
cost of all materials
like
flooring stone,
Unit = 10
sqm
cement, sand, and water etc., complete,
A. MATERIALS:
including seigniorage
charges, labour
Rough Cuddapah/Shabad stones (40 mm
charges for dressing of flooring stones
thick)
(0.457
x 0.457 m) for base
Cement
for
CMfor
(1:8)
proportion
etc.,
complete
finished
item of work, .
Cement for CMcoat
1:3 proportion for
pointing
Sand for CM (1:8) proportion
Sand for CM (1:3) proportion
Seigniorage charges of sand

0.00

B. LABOUR:
Mason 1st class

day

0.96

415.00

Mason 2nd class


Mazdoor (unskilled)

day
day

2.24
3.3

370.00

828.80

310.00

1023.00

0.00
398.40

67554.58

Add water charges 1%

675.55

Grand Total

68230.13

Add 14% over head charges

9552.22
77782.35
say

71

BLD-CSTN-7-1

77783.00

/10Sqm

Flooring with 16 to 18mm thick polished


shabad stones set over base coat of CM (1:8)
over already laid CC bed / RCC Roof Slab,
including neat cement slurry of honey like
consistency spread @ 3.3 kgs per sqm. &
Jointed with neat cement to full depth
including cost of all materials like cement,
sand, and water and flooring stones etc.,
complete, including seigniorage charges,
labour charges for dressing of flooring stones
etc., complete for finished item of work, but
excluding the cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:

Polished Shabad Stone (White) (0.457 x 0.457m)


SSR item No. (25)

sqm

11.00

1691.32

1860.46

Cement for CM (1:8) proportion for base coat

kg.

21.60

4848.76

104.73

Cement for slurry


Cement for jointing
Sand for CM (1:8) proportion
Seigniorage charges of sand
B. LABOUR:

kg.

33.00

4848.76

160.01

kg.

20.00

4848.76

96.98

cum

0.12

134.23

16.11

cum

0.12

721

BLD-CSTN

Index-code

S No Description
1

BLD-CSTN-7-2

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

Mason 1 class

day

3.10

415.00

1286.50

Mason 2nd class


Mazdoor (unskilled)
Add water charges 1%

day

1.10

370.00

407.00

day

0.86

310.00

266.60

st

72

Unit

1960.10

Grand Total
Add 20% for MC on Labour charges
Grand Total
Add 13.615% over head charges
Rate for 10 Sqm
Rate for 1Sqm
Flooring
with
40
mm
thick
Rough
Cuddapah/Shabad stones, set over base coat
of cement mortar (1 : 8) 12 mm thick over CC
bed already laid or RCC roof slab, including
pointing with cement mortar 1:3 duly filling
joints nearly, including cost of all materials
like flooring stone, cement, sand, and water
etc., complete, including seigniorage charges,
labour charges for dressing of flooring
stones etc., complete for finished item of
work, but excluding the cost of conveyance of
all materials.
Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm thick)
(0.457 x 0.457 m)

0.00

0.00
4217.98
574.28
4792.00
479.00

sqm

10.50

Cement for CM (1:8) proportion for base coat

kg.

21.60

Cement for CM 1:3 proportion for pointing


Sand for CM (1:8) proportion
Sand for CM (1:3) proportion
Seigniorage charges of sand
B. LABOUR:
Mason 1st class

kg.

9.60

cum

0.12

cum

0.02

cum

0.14

day

0.960

day

2.240

day

3.30

Mason 2nd class


Mazdoor (unskilled)
Add water charges 1%
Grand Total

19.60
4217.98

722

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

sqm

10.10

638.00

6443.80

kg.

48.00

4848.76

232.74

kg.

33.00

4848.76

160.01

kg.
cum

5.00
0.20

134.23

26.85

cum

0.20

day

1.00

day

2.10

415.00

day

3.00

370.00

day

5.00

310.00

sqm

10.05

229.00

2301.45

Cement for CM (1:6) proportion for base coat

kg.

28.80

4848.76

139.64

Cement for slurry


Cement for jointing & pointing
Pigment
Sand for CM (1:6) proportion
Seigniorage charges of sand
B. MACHINERY
Nill
C. LABOUR
Mason 2nd class
Man mazdoor
Mazdoor (unskiled)

kg.

33.00

4848.76

160.01

kg.

6.00

4848.76

29.09

cum

0.12

134.23

16.11

cum

0.12

day

0.960

415.00

398.40

day

2.240

370.00

828.80

day

3.30

310.00

1023.00

S No Description
1

73

Flooring with polished marble slab 20 mm


thick set over base coat of cement mortar
(1:6) 20 mm thick (joints of stone must be
flushed) over CC bed already laid or RCC roof
slab, including near cement slurry of honey
like consistency spread @ 3.30 kgs per sqm.
Jointed with neat cement to full depth mixed
with pigment of matching shade, including
cost of all materials like flooring slab, cement,
sand, and water etc., complete, including
seigniorage charges, labour charges for
dressing, rubbing and polishing of flooring
stones etc., complete for finished item of
work, but excluding the cost of conveyance of
all materials.

BLD-CSTN-7-3

Unit = 10 sqm
A. MATERIALS:
Marble slab of size 0.305 M x 0.305 M
Cement for CM (1:6) proportion for base coat
Cement for slurry for bedding
White Cement for pointing
Sand for CM (1:6)
Seigniorage charges of sand
B. Machinery
Machine for rubbing of floor
C. LABOUR:
Mason 1st class
Mason 2 class
Mazdoor (unskilled)
nd

Add water charges 1%


Grand Total
74

BLD-CSTN-7-4

Flooring with chequrred terrazzo tiles of 22 mm


thick (medium shade) set over base coat of cement
mortar (1:6) 12 mm thick over CC bed already laid or
RCC roof slab, including near cement slurry of
honey like consistency spread @ 3.3.kgs per sqm &
jointed with neat cement to full depth mixed with
pigment of matching shade including cost of all
materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, complete
for finished item of work, but excluding the cost of
conveyance of all materials.

Unit = 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles of 22 mm thick
(medium shade) SSR 89

kg.

723

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Add water charges 1%


Grand Total

4896.50

Add 25% for MC on Labour charges


Grand Total
Add 14% over head charges

75

BLD-CSTN-7-5

Cement for CM (1:8) for base coat


Cement for slurry
Cement for Pointing with CM (1:3)
Sand for CM (1:8)
Sand for pointing
Seigniorage charges of sand
B. LABOUR
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Add MC on Labour charges
Grand Total
Add 13.615% over head charges
Rate per 10Sqm
Rate per 1Sqm

BLD-CSTN-7-6

0.00
4896.50
685.51
5582.00

Flooring with vitrified tiles of 1st quality, set


over base coat of cement mortar (1:8), 12 mm
thick over CC bed already laid or RCC roof
slab, including neat cement slurry of honey
like consistency spread @ 3.3.kgs per sqm &
jointed neatly with white cement paste to full
depth mixed with pigment of matching shade,
including cost of all materials like cement,
sand water and tiles etc., complete, excluding
seigniorage charges, etc., complete for
finished item of work, but excluding the cost
of conveyance of all materials.

Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size 600 x600 mm
(TBSC-C.II-02)

76

0.00

sqm

10.10

635.00

6413.50

kg.

21.60

4848.76

104.73

kg.

33.00

4848.76

160.01

kg.

6.000

4848.76

29.09

cum

0.12

134.23

16.11

cum

0.020

134.23

2.68

cum

0.140

day

0.96

415.00

398.40

day

2.24

370.00

828.80

day

3.30

310.00

1023.00

1.00%
0.00

2250.20

8976.33
0.00
8976.33
1222.13
10198.00
1020.00

Flooring with ceramic tiles of size 300 x 300


mm and thickness between 7-8 mm 1st quality
set over base coat of cement mortar (1:8), 12
mm thick over CC bed already laid or RCC
roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with white cement paste
to full depth mixed with pigment of matching
shade, including cost of all materials like
cement, sand water and tiles etc., complete,
excluding seigniorage charges, etc., complete
for finished item of work, but excluding the
cost of conveyance of all materials.

Unit = 10 sqm
A. MATERIALS:

724

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

Ceramic tiles SSR TBSC-C.I-01

sqm

10.10

450.00

4545.00

Cement for CM (1:8) for base coat


Cement for slurry
White cement SSR 353
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR
Mason 1st class

kg.

21.60

4848.76

104.73

kg.

33.00

4848.76

160.01

kg.

2.00

29.00

58.00

cum

0.12

134.23

16.11

cum

0.12

day

0.96

415.00

398.40

day

2.24

370.00

828.80

3.30

310.00

1023.00

1.00%

7134.05

Mason 2 class
Mazdoor (unskiled)
Add water charges 1%
nd

day

Grand Total
Add 25% for MC on Labour charges
Grand Total
Rate per 10Sqm
Rate per 1Sqm

12mm plastering (Ornamental)


Basic Rate
Add scaffolding charges for 1st floor
Add Lift charges

GF
721.00

721.00

Over head charges 13.615%


Grand Total

0.00
721.00
Say 721.00
per1Sqm

0.00

2250.20

FF
721.00
0.00
225.02
946.02

SF
721.00
0.00

450.04
1171.04

71.34
7205.39
0.00
7205.39
7205.00
721.00

3rdF
721.00
0.00

675.06
1396.06

4thF
721.00
0
900.08
1621.08

0.00
946.02
946.00

0.00
1171.04
1171.00

0.00
1396.06
1396.00

0.00
1621.08
1621.00

per1Sqm

per1Sqm

per1Sqm

per1Sqm

725

BLD-CSTN

Index-code

S No Description
1

77

Flooring with high polished granite 16 to 18


mm mm thick slabs other than black set over
base coat of cement mortar (1:8), 20 mm thick
over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm &
jointed neatly with white cement paste mixed
with pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tilesetc., complete, including
seigniorage charges, labour charges for
dressing of tilesetc., complete for finished
item of work, but excluding the cost of
conveyance of all materials

BLD-CSTN-7-7

Unit = 10 sqm
A. MATERIALS:
High polished granite 16 to 18 mm thick slab
other than black SSR no 29
Cement for CM (1:8) for base coat
Cement for slurry
White cement for jointing & pointing
Cement for jointing
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR
Mason 1st class

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

sqm

10.10

2300.00

23230.00

kg.

36.00

4848.76

174.56

kg.

33.00

4848.76

160.01

kg.

6.00

29.00

174.00

cum

0.20

134.23

26.85

cum

0.20

day

3.00

415.00

1245.00

day

1.00

370.00

370.00

day

8.00

310.00

2480.00

kg.

Mason 2 class
Mazdoor (unskiled)
Add water charges 1%
nd

1.00%

Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

78

BLD-CSTN-7-8

27860.41
0.00
27860.41
3900.46
31761.00

0.00

Flooring with marble tiles polished 8 mm thick set


over base coat of cement mortar (1:8), 12 mm thick
over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed
neatly with white cement paste mixed with pigment
of matching shade to full depth, including cost of all
materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc.,
complete for finished item of work, but excluding
the cost of conveyance of all materials

Unit = 10 sqm
A. MATERIALS:
Marble tiles polished 8 mm thick SSR 35
Cement for CM (1:8) for base coat
Cement for slurry
White cement for jointing & pointing
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR (including for polishing
rubbing)

sqm

10.10

371.00

3747.10

kg.

36.00

4848.76

174.56

kg.

33.00

4848.76

160.01

kg.

5.00

29.00

145.00

cum

0.20

134.23

26.85

cum

0.20

Mason 1st class

day

4.00

415.00

1660.00

Mazdoor (unskiled)

day

8.00

310.00

2480.00

&

726

BLD-CSTN

Index-code

S No Description
1

Add water charges 1%

Unit
3

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

1.00%

Grand Total
Add 25% for MC on Labour charges

8393.51
0.00

0.00

Grand Total

8393.51

Add 14% over head charges

1175.09
9569.00

727

BLD-CSTN

Index-code

S No Description
1

79

Flooring with granite stone tiles 8 mm thick


(mirror polished of all shades) set over base
coat of cement mortar (1:6), 12 mm thick over
CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm &
jointed neatly with white cement paste mixed
with pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for
finished item of work, but excluding the cost
of conveyance of all materials.

BLD-CSTN-7-9

Unit = 10 sqm
A. MATERIALS:
Granite stone tiles 8 mm thick (mirror polished of
all shades) SSR 36
Cement for CM (1:6) for base coat
Sand for CM (1:6)
Seigniorage charges of sand
B. LABOUR
Mason 1st class
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

80

BLD-CSTN-7-10

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

sqm

10.10

780.00

7878.00

kg.

48.00

4848.76

232.74

cum

0.20

134.23

26.85

cum

0.20

day

4.00

415.00

1660.00

day

8.00

310.00

2480.00

1.00%
0.00

21846.59
0.00
21846.59
3058.52
24905.00

Flooring with decorated white back ground


glazed tiles, set over base coat of cement
mortar (1:6), 12 mm thick over CC bed already
laid or RCC roof slab, including neat cement
slurry of honey like consistency spread @
3.3.kgs per sqm & jointed neatly with white
cement paste mixed with pigment of matching
shade to full depth, including cost of all
materials like cement, sand water and tiles
etc., complete, including seigniorage charges,
etc., complete for finished item of work, but
excluding the cost of conveyance of all
materials

Unit = 10 sqm
A. MATERIALS:
Decorated white back ground glazed tiles

Cement for CM (1:6) for base coat


Cement for slurry
White cement for jointing & pointing
Sand for CM (1:6)
Seigniorage charges of sand
B. LABOUR
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%

sqm
kg.

10.10
28.80

kg.

33.00

kg.

6.00

cum

0.12

cum

0.12

day

0.96

day

2.24

day

3.30
1.00%

Grand Total

728

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

1000 Nos

0.255

kg.

21.600

kg.

6.000

10sqm

1.000

Deduct CM (1:3)

cum

0.040

Sand for CM (1:8)


Seigniorage charges of sand
B. LABOUR
Mason 1st class

cum

0.120

cum

0.120

day

0.960

Mason 2 class
Mazdoor (unskiled)
Add water charges 1%

day

2.240

S No Description
1

81

Flooring with pressed clay flooring tiles, set


over base coat of cement mortar (1:8) 12 mm
thick over CC bed already laid or RCC roof
slab, including neat cement slurry of honey
like consistency spread @ 3.3.kgs per sqm &
jointed neatly with cement mixed with
pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for
finished item of work, but excluding the cost
of conveyance of all materials

BLD-CSTN-7-11

Unit = 10 sqm
A. MATERIALS:
20 X 20 cm pressed clay flooring tiles
Cement for CM (1:8) for base coat
Cement for jointing & pointing
Pointing with CM (1:3)

nd

82

BLD-CSTN-7-12

day

4.30
1.00%

Grand Total
Flooring with Plain Cement tiles, set over
base coat of cement mortar (1:8) 12 mm thick
over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm &
jointed neatly with cement paste mixed with
pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for
finished item of work, but excluding the cost
of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Plain cement Tiles 20 x 20 cms

1000 Nos

0.255

kg.

21.600

kg.

6.000

10sqm

1.000

cum

0.040

Sand for CM (1:8)


Seigniorage charges of sand
B. LABOUR
Mason 1st class

cum

0.120

cum

0.120

day

0.960

Mason 2 class
Mazdoor (unskiled)
Add water charges 1%

day

2.240

Cement for CM (1:8) for base coat


Cement for jointing & pointing
Pointing with CM (1:3)
Deduct CM (1:3)

nd

day

3.30
1.00%

Grand Total

729

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.17

1244.61

211.58

Note : When Mortar mix is changed proportionate quantity of


cement has to be substituted for all above Flooring Items. The
same data holds good for stones with all colours. Adopt same
data for polished Kadapa Stones and Bethamcherla stones.
83

BLD-CSTN-7-13

Gronolithie Concrete Flooring 20 mm thick


with (1:1:2), using 6mm to 12 mm size hard
granite machine crushed metal laid over CC
bed already laid or RCC roof slab, in alternate
panels of size not exceeding 1.50 m x 1.50 m
and finishing the top surface to required
smoothness and slopes and thread lining
including cost of all materials like cement,
metal, sand and water etc., complete,
including seigniorage charges, etc., complete
for finished item of work, but excluding the
cost of conveyance of all materials

Unit = 10 sqm
A. MATERIALS:
6mm to 12 mm H.G. Metal (Machine crushed)
Cement
Sand
Seigniorage charges of sand
B. LABOUR
Mason 1st class
Mason 2 class
Mazdoor (unskiled)
Add water charges 1%
nd

kg

120.00

4848.76

581.85

cum

0.085

134.23

11.41

cum

0.085

day

1.25

415.00

518.75

day

0.06

370.00

22.20

day

3.00

310.00

930.00

1.00%

2275.79

Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

84

BLD-CSTN-7-14

BLD-CSTN-7-15

Flooring with 100mm thick Cement Concrete 1:6:10,


using 40mm metal, 100mm thick and 20 mm
Cement Concrete surface (Ellis Pattern, 1st Sort)

Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete mixer

85

0.00

22.76
2298.55
0.00
2298.55
0.00
2299.00
230.00

cum

1.000

Stone Chippings 3.34 mm - 10 mm


Cement
B. LABOUR
Mason 1st class

cum

0.250

kg

120.000

day

0.150

Mason 2nd class


Mazdoor (unskiled)
Add water charges 1%

day

0.350

day

5.40
1.00%

Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered over
with 12 mm thick in CM(1:3)
Unit = 10 sqm

730

BLD-CSTN

Index-code

S No Description
1

A. MATERIALS:
Cement Concrete 1:6:10 using concrete mixer

86

BLD-CSTN-7-16

Plastering with CM (1:3), 12 mm thick


Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered over
with 12 mm thick in CM(1:3) using Red oxid,
with polished surface
Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete mixer
Plastering with CM (1:3), 12 mm thick
Red oxid

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

1.00

10 sqm

1.00

cum

1.00

10 sqm

1.00

kg

10.00

731

BLD-CSTN

Index-code

S No Description
1

87

BLD-CSTN-7-17

B. LABOUR
Masons for polishing
Grand Total
6 mm thick terrazzo flooring in situ with white,
black, chocolate, gray, yellow or green
superior marble chips, over 20 mm thick base
coat of CM (1:3) laid over CC bed already laid
or RCC roof slab, including cost of all
materials like cement marble powder, marble
chips, sand & water etc., complete including
polishing to get high smooth finishing,
seigniorage charges, etc., complete for
finished item of work, but excluding the cost
of conveyance of all materials

Unit = 10 sqm
A. MATERIALS:
Marble Powder
Marble Chips
Cement for top layer
Cement for base coat in CM (1:3)
Sand for base coat
Seigniorage charges of sand
B. MACHINERY
Polishing Charges
C. LABOUR
Mason 1st class

88

BLD-CSTN-7-18

Mason 2nd class


Mazdoor (unskiled)
Grand Total
Providing skirting to internal walls to 15 cm
height/risers of steps with ceramic tiles 7.30
mm thick length equal to flooring stones, set
over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and
jointed with white cement paste mixed with
pigment of matching shade to full depth,
including cost of all materials like tiles,
cement, sand and water etc., complete
including seigniorage charges, etc., complete
for finished item of work, but excluding the
cost of conveyance of all materials

Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
Mason 1st class
Mazdoor (unskiled)
Add 20% for MC on Labour charges
Grand Total
Add 13.615% over head charges

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Nos

1.10

kg

17.000

cum

0.060

kg.

50.000

kg.

96.000

cum

0.200

cum

0.200

sqm

10.000

day

0.960

day

2.240

day

3.30

sqm

10.00

372.00

3720.00

3720

cum

0.12

2530.34

303.64

303.64

kgs

57.60

4848.76

279.29

279.2886432

kgs

33.00

4848.76

160.01

160.0091185

25.00

150.00

150

kgs

6.00

cum

0.12

day

0.77

415.00

319.55

319.55

day

0.80

310.00

248.00

248

0.00

0.00
5180.49

5180.488784

705.32

705.32

732

BLD-CSTN

Index-code

S No Description
1

Rate per 10 Sqm


Rate per 1 Sqm

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

5886.00

5886.00

589.00

589.00

733

BLD-CSTN

Index-code

S No Description
1

89

Providing skirting to internal walls to 15 cm


height/risers
of
steps
with
marble
slab..mm thickness, length equal to
flooring stones, set over base coat of CM (1:3)
12 mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
marble slab, cement, sand and water etc.,
complete including seigniorage charges, etc.,
complete for finished item of work, but
excluding the cost of conveyance of all
materials

BLD-CSTN-7-19

Unit = 10 sqm
A. MATERIALS:
Marble slabmm thickness
Sand for base coat
Cement for base coat
Cement for slurry
White cement for jointing & pointing
Flate nosing charges
Machine cutting charges
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Man mazdoor (Beldar)
Man mazdoor (Beldar) for polishing & rubbing
Woman mazdoor
Grand Total
90

BLD-CSTN-7-20

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

sqm

10.10

cum

0.12

kg

57.60

kg

33.00

kg

5.00

RM

66.67

RM

67.67

cum

0.12

day

2.10

day

4.90

day

4.00

day

4.00

sqm

10.10

635.00

6413.50

cum
kgs
kgs
kgs
cum

0.12
34.56
33.00
2.00
0.12

134.23
4848.76
4848.76
29.00

16.11
167.57
160.01
58.00

day
day
day

0.96
2.24
3.30
1.00%

415.00
370.00
310.00

398.40
828.80
1023.00

Providing skirting to internal walls to 15 cm


height/risers of steps with vitrified tiles length
equal to flooring stones, set over base coat of
CM (1:5) 12 mm thick with cement slurry of
honey like consistency spread at the rate of
3.30 kgs per sqm and jointed with white
cement paste mixed with pigment of matching
shade to full depth, including cost of all
materials like tiles, cement, sand and water
etc., complete excluding seigniorage charges,
etc., complete for finished item of work, but
excluding the cost of conveyance of all
materials

Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size 600 x600 mm
(TBSC-C.II-02)
Sand for cm 1:5 base coat
Cement for cm 1:5 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mason 2nd class
Mazdoor (unskilled)
Add water charges 1%

734

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Grand Total

Amount
without M.A

9065.39

Add MC on Labour charges

91

Amount
Rs.with
MA

0.00

0.00

Grand Total

9065.39

Add 13.615% over head charges

1234.25

Rate for 10 Sqm

10300.00

Rate for 1Sqm

1030.00

Providing skirting to internal walls to 15 cm


height/risers of steps with 8 mm thick mirror
polished granite tiles length equal to flooring
stones, set over base coat of CM (1:3) 12 mm
thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like tiles,
cement, sand and water etc., complete
including seigniorage charges, etc., complete
for finished item of work, but excluding the

cost of conveyance of all materials

BLD-CSTN-7-21

Unit = 10 sqm
A. MATERIALS:
8 mm thick mirror polished granite tiles
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mazdoor (unskiled)
Mason 2nd class
Add water charges 1%
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

sqm

10.10

780.00

7878.00

cum
kgs
kgs
kgs
cum

0.12
57.60
33.00
5.00
0.12

134.23
4848.76
4848.76
29.00

16.11
279.29
160.01
145.00

day

2.10

415.00

871.50

day

0.80
4.90
1.00%

370.00
310.00

296.00
1519.00
11164.90

0.00

0.00
11164.90
1563.09
12728.00

92

Providing skirting to internal walls to 15 cm


height/risers of steps with 25 mm thick
polished Cuddapah stone length equal to
flooring stones, set over base coat of CM (1:3)
12 mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
Cuddapah stone, cement, sand and water etc.,
complete including seigniorage charges, etc.,
complete for finished item of work, but

excluding the cost of conveyance of all


materials

BLD-CSTN-7-22

Unit = 10 sqm
A. MATERIALS:

735

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

25 mm thick polished Cuddapah stone

sqm

10.10

1291.00

1303.91

Sand for cm 1:3 base coat


Cement for cm 1:3 base coat
Cement for slurry
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%

cum
kgs

0.12
57.60

134.23
4848.76

16.11
279.29

kgs
cum

33.00
0.12

4848.76

160.01

day

0.96

415.00

398.40

day
day

2.24
3.10
1.00%

370.00
310.00

828.80
961.00

Grand Total

3947.51

Add 25% for MC on Labour charges

0.00

0.00

Grand Total

3947.51

Add 14% over head charges

552.65
4500.00

93

Providing skirting to internal walls to 15 cm


height/risers of steps with 25 mm thick
polished Shahabad stone length equal to
flooring stones, set over base coat of CM (1:3)
12 mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
Shahabad stone, cement, sand and water etc.,
complete including seigniorage charges, etc.,
complete for finished item of work, but

excluding the cost of conveyance of all


materials

BLD-CSTN-7-23

Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Shahabad stone (White)
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total

sqm
cum
kgs
kgs
cum

10.10
0.12
57.60
33.00
0.12

day

0.96
2.24
3.10
1.00%

day

Note : When Mortar mix is changed proportionate quantity of


cement has to be substituted for all Skirting Items.

94 Providing dadooing to walls with glazed plain coloured wall tiles 1st
quality of size with borders as approved by Engineer-in-Charge set over base
coat of CM(1:5) 12 mm thick using screened sand with cement slurry of honey
like consistency spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full depth, including
cost of all materials like tiles, cement, sand and water etc., complete excluding
seigniorage charges etc., and overheads & contractors profit complete for
finished item of work.
(BLD-CSTN-9-18)
Unit = 10 sqm
736

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

A.MATERIALS :
Cost of glazed coloured tiles
Sand for CM(1:5) base coat
Cement for CM(1:5) base coat
Cement for slurry
White cement for jointing & pointing
B.LABOUR
Mason 1st class
Mazdoor(unskilled)
Add water charges 1%
Add 20% MA

sqm
cum
Kgs
Kgs
Kgs

10.50
0.12
34.56
33.00
6.00

Nos.
Nos.

0.77
0.80
0.01
0.00

Rate for 10 sqm


Rate for other Floors
Rate as worked out above
Lift charges ( Page 131 of Std. Data )
Add 20% MA
Over head charges & Contractor profit
13.615%
Seigniorage charges
Fine aggregate
Rate per 10 Sqm
Rate per 1 Sqm
Say
94

BLD-CSTN-7-24

413.00 4336.50
16.11
134.23
167.57
4848.76
160.01
4848.76
174.00
29.00
415.00
310.00
567.55
573.23

319.55
248.00
5.68
0.00
5427.41

FF
5427.41
0.00
0.00
5427.41
738.94

SF
5427.41
57.32
0.00
5484.74
746.75

TF
4F
5427.41 5427.41
114.65
171.97
0.00
0.00
5542.06 5599.38
754.55
762.36

0.00
6166.36
616.64
617

0.00
6231.48
623.15
623

0.00
0.00
6296.61 6361.74
629.66
636.17
630
636

Teak Wood Flooring 40mm. Thick Tongued


and Grooved Planks, including cost of all
materials, labour etc., complete
Unit = 10 sqm
A. MATERIALS:
cum
Teak Wood Planks 40mm thick
100 Nos
75 mm Long Screws
B. LABOUR
day
Carpenters 1st Class
day
Carpenters 2nd Class
day
Man mazdoor
Note : Deduct 4.3 Nos Carpenters if plank rate is for tongued
and grooved ready planned.

0.44
3.00
1.95
4.55
5.40

Grand Total

737

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

1.53

day

1.10

day

0.50

kgs

103.09

60.00

6185.37

G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884


BMT-W.62
G.I bolts & nuts 20 x 6

nos

47.91

5.00

239.57

G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos =


810 nos. with washers or srews, if wooden
battens used. BMT-W.64
Limpet washers (for scam & J bolts)
884 +
810 = 1694 BMT-w.66

nos

43.90

10.00

439.02

nos

91.82

0.50

45.91

Bitumen washers BMT-w.67


Zinc cromate yellow paint
Ready mixed paint
B. LABOUR
For roofing
Carpenter II class
Man mazdoor (beldar)
For premier painting one coat
Painter
Mazdoor (coolie)
For two coats of painting to over laps
Painter
Mazdor (coolie)

nos

91.82

0.30

27.54

litre

0.14

0.00

litre

0.20

0.00

Sundries including 50 x 6 mm iron wind ties white lead


etc.

LS

0.00

Add for Standard specification 1mm. Thick ridging and


1.25 mm thick sheet vallyes when such are required for
a particular work. Average allowance for 10 sqm
roofing.

LS

0.00

S No Description
1

95

Flooring with Gravel 150 mm thick including


cost of all materials, labour, watering etc.,
complete

BLD-CSTN-7-25

Unit = 10 sqm
A. MATERIALS:
Gravel (including 2% wastage)
B. LABOUR
Man mazdoor
Woman mazdoor
Grand Total

ROOFING & CEILING


96

BLD-CSTN-8

BLD-CSTN-8-1

Roofing with corrugated G.I sheets 0.80mm


thick fixed with G.I J bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (up to a
pitch of 600) and seigniorage charges, etc.,
complete, excluding the cost of purlins,
rafters, trusses & cost of conveyance of all
materials
Unit = 184.518 sqm
A. MATERIALS:
G.I corrugated 0.80 mm thick sheets BMT-E.20

Add 25% MA on Muncipal allowance

Grand Total

nos

0.00

0.00
0.00
day

0.84

370.00

310.84

day

0.91

310.00

282.28

day

0.06

0.00

day

0.06

0.00

day

0.14

0.00

day

0.14

0.00

0.00

0.00

0.00

593.12

0.00
7530.53

Rate per 10 sqm = Grand Total/10

738

BLD-CSTN

Index-code

S No Description
1

97

Roofing with corrugated G.I sheets 1.00mm


thick fixed with G.I J bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (upto a
pitch of 600) and seigniorage charges,
turnover tax etc., complete, excluding the cost
of purlins, rafters, trusses & cost of
conveyance of all materials

BLD-CSTN-8-2

Unit = 184.518 sqm


A. MATERIALS:
G.I corrugated 1.00 mm thick sheets
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884

BLD-CSTN-8-3

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kgs

126.07

nos

47.91

G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos =


810 nos.

nos

43.90

Limpet washers (for scam & J bolts)


810 = 1694

nos

91.82

nos

91.82

litre

0.14

litre

0.20

day

0.84

day

0.91

day

0.06

day

0.06

day

0.14

day

0.14

884 +

Bitumen washers
Zinc cromate yellow paint
Ready mixed paint
B. LABOUR
For roofing
Carpenter II class
Man mazdoor (beldar)
For premier painting one coat
Painter
Mazdoor (coolie)
For two coats of painting to over laps
Painter
Mazdor (coolie)
Grand Total
98

Unit

Rate per 10 sqm = Grand Total/10


Roofing with corrugated G.I sheets 1.25mm
thick fixed with G.I J bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (upto a
pitch of 600) and seigniorage charges, turnover tax
etc., complete, excluding the cost of purlins, rafters,
trusses & cost of conveyance of all materials
Unit = 184.518 sqm
A. MATERIALS:
G.I corrugated 1.25 mm thick sheets
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884

kgs

154.80

nos

47.91

G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos =


810 nos.

nos

43.90

Limpet washers (for scam & J bolts)


810 = 1694

nos

91.82

nos

91.82

litre

0.14

litre

0.20

day

0.84

day

0.91

Bitumen washers
Zinc cromate yellow paint
Ready mixed paint
B. LABOUR
For roofing
Carpenter II class
Man mazdoor (beldar)

884 +

739

BLD-CSTN

Index-code

S No Description
1

For premier painting one coat


Painter
Mazdoor (coolie)

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day

0.06

day

0.06

740

BLD-CSTN

Index-code

BLD-CSTN-8-4

S No Description
1

99

For two coats of painting to over laps


Painter
Mazdor (coolie)
Grand Total
Rate per 10 sqm = Grand Total/10
Roofing with 6 mm thick corrugated asbestos
cement sheets, fixing with G.I J bolts & nuts
8 mm dia G.I plain washers complete
including seigniorage charges etc., complete
for finished item of work, but excluding the
cost of purlins, rafters, trusses & cost of
conveyance of all materials upto 600 pitch.
Unit = 216.14 sqm
A. MATERIALS:
6 mm thick corrugated AC sheets
8 mm dia G.I J bolts & nuts
G.I washers
Bitumen washers
B. LABOUR
Carpenter II class
Man mazdoor
Sundries including 50 x 6 mm iron wind ties white
lead etc.
Add for Standard specification 1mm. Thick ridging
and 1.25 mm thick sheet vallyes when such are
required for a particular work. Average allowance
for 10 sqm roofing.

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day

0.14

day

0.14

T /sqm

0.15

nos

22.03

nos

22.03

nos

22.03

day

0.43

day

0.54

LS
LS

Grand Total
Rate per 10 sqm = Grand Total/10
100 Best Tiled Roofing with Pan tiles over Flat
196 Tiles and Lime mortar Borders including Teak

Reapers.

BLD-CSTN-8-5

Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick

1000 No

1560

Flat Tiles 150 x 150 x 15 mm

1000 No

470

10RM
kgs
cum
cum

75.000
0.500
0.008
0.300

day
day
day
day
LS

0.800
2.200
1.100
5.400
LS

cum
cum
cum

0.500
1.000
1.000

Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime
Lime Mortar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Sundries including tarring reepers, extra labour /
for pointing the underside of flat tiles and white
washing the same.
Grand Total
Sub Analysis :
Lime Moratar 1:2
lime
Sand
Grinding Lime Mortar
Total

741

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

1000 No

1560

10RM
kgs

107.000
0.700

cum

0.120

day
day

1.100
1.400

day
day

1.100
3.200

1000 No

1560

101 Best Tiled Roofing with Pan tiles and Lime


197 mortar Borders including Teak Reapers at 100

mm. centres

BLD-CSTN-8-6

Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime Moratar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Grand Total
102 Best Tiled Roofing with Pan tiles laid on
198 Bamboo Rafters, Bamboo Reepers and

Bamboo Mats, including Lime mortar Borders

BLD-CSTN-8-7

Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Bamboo rafters (450 mm apart) 75 to 100 mm dia

RM

25

Bamboo reepers, Split 25 mm dia

100 No

150

Bamboo mats

10 sqm

10.500

cum

0.120

day
day
day
day

1.100
1.400
1.100
3.200

Mangalore tiles (vide Stadard Specification)

1000 No

160

Flat Tiles 150 x 150 x 15 mm

1000 No

470

10RM
kgs
cum
cum

75.000
0.500
0.008
0.380

day
day
day
day
LS

0.800
1.600
1.100
4.300
LS

Lime Moratar for Borders


B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Sundries including nails
Grand Total
103 Best Tiled Roofing with Mangalore tiles set in
199 Lime mortar over Flat Tiles and including Teak

Reepers

BLD-CSTN-8-8

Unit = 10 sqm
A. MATERIALS:

Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime
Lime Moratar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Sundries including tarring reepers iron wind ties
30 x 3 mm, G.I. Screw, washers etc., and extra
labour for pointing the underside of flat tiles and
white washing the same.
Grand Total

742

BLD-CSTN

Index-code

S No Description
1

104 Best Tiled Roofing with


200 including Teak Reepers

BLD-CSTN-8-9

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

1000 No

160

10RM
kgs

36.000
0.500

cum

0.090

day

0.500

day
day
day

0.500
1.100
2.200

10 sqm

10.000

100 No

156

day
day

0.500
1.100

cum
cum
cum
LS

0.670
1.000
1.000

cum
cum
cum

0.180
0.080
0.023

day
day
LS

3.200
6.500
LS

Mangalore tiles

Unit = 10 sqm
A. MATERIALS:
Mangalore tiles (vide Stadard Specification)
Teak Reepers 50 x 12 mm
Wire Nails 50 mm long
Lime Moratar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Grand Total
105 Best Tiled Roofing with Mangalore tiles over
201 Ceiling Tiles with Air Spaces and including
Teak Reepers

BLD-CSTN-8-10

Unit

Unit = 10 sqm
A. MATERIALS:
Rate for "Best Mangalore tiled roofing with
Mangalore tiles including teak reeper".
Add
Terracing tiles
B. LABOUR
Bricklayers
Woman mazdoor
Grand Total

Common note Applicabable for Items 196


to 201 :1. The quantity proposed for Pan Tiles / Mangalore
Tiles includes allowance for cost of special tiles for
ridges and hips.
2. Reepers size is for rafter spacing 600 mm. including
allowance for eves and valleys.
3. Labour including fixing galvanized iron sheeting-cost
of sheeting to be paid separately.

Sub Analysis :
Lime Mortar (1: 1.5) :

Unit = 1 cum
Lime
Fine Sand
Grinding Mortar (Spl Grinding)
Sundries
Total
106 Plastering with Lime Mortar 3 Coats, 25 mm
thick (Sebara Rendering)

BLD-CSTN-8-11

Unit = 10 sqm
Lime Mortar (1:2)
Lime Mortar (1:1.5)
Lime
LABOUR
Bricklayers
Mazdoor (unskilled)
Sundries
Total

743

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Unit = 10 sqm
A. MATERIALS:
Terracing Bricks 150 x 75 x 25mm

1000 No

2000

Flat Tiles 150 x 150 x 15 mm

100 No

900

cum
cum

0.980
0.380

cum
10 sqm

0.210
1.000

Cement Mortar 1:3

cum

0.240

B. LABOUR
Bricklayers
Mazdoor (unskilled)
Grand Total

day
day

4.300
6.500

S No Description
1

107 Terrace Roofing with Brick on edge 75 mm.


204 Concrete 2 Courses of Flat Tiles at Top and

pointing Flat Tiles in Cement Mortar (1:3) and


one coat of Cement Plaster (1:3)

BLD-CSTN-8-12

Broken brick 20 mm cube


Lime
Lime Moratar
Pointing with cement mortar 1:3 (for rate - vide
relevant schedule item)

Note : The quantity proposed for broken brick allows for the
brick powder formed, replacing sand for concrete layers.
108 Reinforced cement Concrete Roofing 125 mm
205 thick with CC (M 20) using 20 mm graded

metal and 2 courses of Flat Tiles at Top


including pointing with Cement Mortar (1:3)

BLD-CSTN-8-13

Unit = 10 sqm
A. MATERIALS:
Reinforced Concrete Roofing slab 125 mm thick (for
rate - vide relevant schedule item)

10 sqm

10.000

Flat Tiles 150 x 150 x 20 mm

100 No

900

Cement Mortar 1:3


Pointing with cement mortar 1:3 (for rate - vide
relevant schedule item)
B. LABOUR
Bricklayers
Woman mazdoor
Sundries including crude oil
Grand Total
Sub Analysis :
RCC (M 20) using 20 mm HG graded metal
using Concrete mixturefor Roofing 125 mm
thick

cum
10 sqm

0.260
1.000

day
day
LS

2.200
2.200

cum

1.250

10 sqm

1.000

10 sqm

1.000

CC (M 20) (Item No.


Centering Charges
Form Work
Total
109 Reinforced cement Concrete Roofing 140 mm
206 thick with CC (M 20) using 20 mm graded

metal and 2 courses of Flat Tiles at Top


including Pointing with Cement Mortar (1:3)

BLD-CSTN-8-14

Unit = 10 sqm
A. MATERIALS:
Rate of "Reinforced cement Concrete Roofing 125 mm
thick and 2 courses of Flat Tiles at Top including
pointing with Cement Mortar (1:3)"

744

BLD-CSTN

Index-code

S No Description
1

Add :
For extra thickness of roofing slab
Grand Total

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.150

745

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

10 sqm

1.000

cum

0.250

10 sqm

1.000

cum

0.250

Unit = 10 sqm
Reinforced Concrete Roofing slab 100 mm thick
(for rate - vide relevant schedule item)

10 sqm

1.000

Centering Charges

10 sqm

1.000

Plastering with CM (1:3), 12 mm thick

10 sqm

1.000

kgs

1.500

S No Description
1

110 Reinforced cement Concrete Roofing 150 mm


207 thick with CC (M 20) using 20 mm graded

metal and 2 courses of Flat Tiles at Top


including Pointing with Cement Mortar (1:3)

BLD-CSTN-8-15

Rate of "Reinforced cement Concrete Roofing 125 mm


thick and 2 courses of Flat Tiles at Top including
pointing with Cement Mortar (1:3)"

Add :
For extra thickness of roofing slab
Grand Total
111 Reinforced cement Concrete Roofing 100 mm
207 thick with CC (M 20) using 20 mm graded

metal and 2 courses of Flat Tiles at Top


including Pointing with Cement Mortar (1:3)

BLD-CSTN-8-16

Rate of "Reinforced cement Concrete Roofing


125 mm thick and 2 courses of Flat Tiles at Top
including pointing with Cement Mortar (1:3)"
Deduct :
For Less thickness of roofing slab
Grand Total
112 Reinforced cement Concrete Roofing 100 mm
207 thick with CC (M 20) using 20 mm graded
metal with Imprevious Coat with 12 mm thick
Plastering in CM (1:3) with 1 kg. of Impermo
Compound or ACCO Proof per Bag of Cement
and laid when slab is Green.

BLD-CSTN-8-17

Impermo Compound
Grand Total
Note for Items 204 - 207 :
1. No extra rate will be paid for finishing the
bottom surface of the roofing slab as described in
SS No.
"For estimating purpose the extra allowance
for camber concrete, when such is required
may be given under sundries."

746

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

1000 No

450

113 Complete Surface Repairs to Leaky Terrace


208 Roofs with Flat Tiles

BLD-CSTN-8-18

Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm
Cement Mortar 1:3
Pointing with cement mortar 1:3 (for rate - vide
relevant schedule item)
B. LABOUR
Bricklayers
Man Mazdoor
Clean removal of lime plaster from terraced roofs
and raking out joints 12 mm deep (for rate - vide
relevant schedule item)
Sub Analysis :
Mazdoor (unskilled)
Mate
Sundries including crude oil
Grand Total
114 Best Sloping Bengal Terrace with 3 courses of
209 Flat Tiles at Top including Teak Wood Reepers

BLD-CSTN-8-19

cum

0.110

10 sqm

1.000

day
day

1.100
1.100

10 sqm

1.000

Day
Day
LS

Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm

1000 No

1350

Lime
Lime Moratar (1:1.5)
Teak Reepers 52 x 12 mm

cum
cum
10 RM

0.008
0.150
75.000

Wire Nails 40 mm long


Plastering with lime mortar 3 coats (for rate - vide
relevant schedule item)

kgs
10 sqm

0.500
1.000

day
day
day
LS

0.800
2.200
2.200

B. LABOUR
Carpenter
Bricklayers
Woman mazdoor
Sundries including tarring reepers
Grand Total
Note : 1. Reepers size is for rafter spacing 600
mm. including allowance for eves and valleys.
2. No extra rate will bepaid for finishing the
bottom surface of the roofing slab as described in
SS No.

747

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

1000 No

1560

cum

0.120

day

1.400

day
day
LS

1.100
4.300

day
day

1.100
0.800

10 sqm

1.000

115 Removing Old Tiles and Retiling with New Pan


212 Tiles over Old Teak Reepers including New

White Washed Lime Mortar Borders 230 x 50


mm. at 2 Metres Intervals

BLD-CSTN-8-20

BLD-CSTN-8-21

Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick

116
213

117
214

BLD-CSTN-8-22

Lime Moratar
B. LABOUR
Bricklayers
Man Mazdoor
Woman mazdoor
Sundries
Grand Total
Shifting Pan Tiles (Labour Only)
Unit = 10 sqm
Bricklayers
Man Mazdoor
Grand Total
Shifting Pan Tilesand forming new White
Washed Lime Mortar Boarders, 230 x 50 mm
at 2 Metres Intervals
Unit = 10 sqm
Rate of "Shifting Pan Tiles"

Add : Lime Mortar Borders and White Washing


Grand Total
118 12 mm. Teak Wood Plank Ceiling Tongued and
222 Grooved Planking

BLD-CSTN-8-23

Unit = 10 sqm
A. MATERIALS:
Teak Wood Planks 150 x 12 mm

LS

cum

0.132

100 No

300

day
day
LS

6.500
5.400

Unit = 10 sqm
Rate for "12 mm. Teak Wood Plank Ceiling
Tongued and Grooved Planking"

10 sqm

10.000

Teak Wood Battens 40 x 12 mm

10 RM

66.000

Brass screws 25 mm long

100 No

240

day
LS

1.100

Screws 40mm long


B. LABOUR
Carpenter
Man Mazdoor
Sundries
Grand Total
Note : Deduct 4.3 Nos Carpenters if plank rate is
for tongued and grooved ready planned.
119 12 mm. Teak Wood Plank Ceiling with 40 x 12
223 mm Teak Wood Battens

BLD-CSTN-8-24

Deduct :
Carpenter
Sundries
Grand Total

748

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.210

2530.34

531.37

kg

2.000

24.00

48.00

day

0.660

415.00

273.90

day

1.540

370.00

569.80

day

3.70

310.00

1147.00

1990.70

0.00

120 Providing impervious coat to exposed RCC

roof slab surface with CM(1:3), 20mm thick


with 1kg of water proof compound per bag of
cement
laid over roof when it is green
including cost of all materials, excluding
seigniorage charges, including conveyance
charges of materials and including all
operational, incidental and labour charges for
mixing mortar, laying, rendering smooth and
thread lining, curing, rounding off junctions of
wall and slab etc,, complete for finished item
of work

BLD-CSTN-8-25

Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3
Water proof compound
B. LABOUR
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Add muncipal at 20% on L.C
Grand Total
Add 13.615% over head charges
Rate for 10 Sqm
Rate for 1 Sqm
121 Providing & fixing insulating board ceiling of
approved quality with nails etc., complete,
excluding the cost of frame work for base and
cost of conveyance of all materials

BLD-CSTN-8-26

BLD-CSTN-8-27

Unit = 10 sqm
A. MATERIALS:
12 mm thick insulating board
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
122 Providing & fixing hard board sheet ceiling of
approved quality with nails etc., complete,
excluding the cost of frame work for base and
cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
3 mm thick standard quality of hard board
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
123 Providing & fixing flat pressed 3 layer medium
density particle board sheet with necessary
nails etc., complete, excluding the cost of
frame work for base and cost of conveyance
of all materials

BLD-CSTN-8-28

0.00
2570.07
349.92
2919.99
292.00

sqm

11.00

day

2.50

day

2.00

sqm

11.00

day

2.50

day

2.00

sqm

11.00

day

2.50

day

2.00

Unit = 10 sqm
A. MATERIALS:
Standard quality of flat pressed 3 layer medium density
board sheet 4.50 mm thick

B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total

749

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

sqm

11.00

day

2.50

day

2.00

cum

0.05

48543.00

2305.79

kg

0.75

57.00

42.75

sqm

10.20

16.00

163.20

kg

219.76

1.50

329.64

day

2.60

415.00

1079.00

day

1.60

310.00

496.00

day

2.62

415.00

1085.23

day

1.62

370.00

597.55

day

0.38

310.00

124 Providing & fixing plain AC sheet ceiling of

BLD-CSTN-8-29

approved quality with necessary nails etc.,


complete, excluding the cost of frame work
for base and cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
Plain AC sheet for ceiling
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
125 Providing

10 mm thick plaster of paris


(Gypsum anhydrous) ceiling upto a height of 5
m above floor level over first class BT wood
strips 25 x 6 mm with 10 mm gap in between
and reinforced with rabbit wire mesh fixed to
wooden frame excluding cost of wooden
frame for base & cost of conveyance of all
materials.

BLD-CSTN-8-30

Unit = 10 sqm
A. MATERIALS:
Wooden strips 1st class BT wood 25 x 6 mm size
Nails BMT-F.02
Rabbit wire mesh BMT-F.28
Plaster of paris
B. LABOUR
for Jointing the wooden strips including fixing
the rabbit mesh
Carpenter Ist class
Man mazdoor (beldar)
For doing plaster of paris over wooden strips
Mason Ist class
Mason IInd class
Mazdoor (unskilled)
BASIC COST per 1 sqm
Add 25% Muncipal allowance

116.87
6216.03

0.00

3374.65

0.00
6216.03

Add 14% towards contractor profit


Rate per 10 Sqm
or Say

870.24
7086.27
7086.00

Gypboard Suspended false ceiling


126 Supplying and fixing Gyp Board Suspended regular single layer false ceiling (GS-MFSC-4.1 as
per India Gypsum) using 12.5 mm thick Gyp Board conforming to IS 2095 - 1982 fixing to Gyp
steel GI perimeter channels of size 20 mm x 27 mm x 30 mm(web) of 0.55 mm thick along the
perimeter of ceiling screw fixed to brick work/ partition at 610 mm c/c and suspending the frame
work using Intermediate channels (45 mm x 15mm x 15mm x 0.9 mm) from soffit at 1220 mm c/c
with ceiling angle (25 mm x 10 mm x 0.55 mm) fixed with GI Cleat and steel expansion fasteners
& connecting clip to the ceiling channels (with knurled web of 51.5 mm x 26 mm x 10.5 mm x 0.55
mm) fixed in direction perpendicular to the intermediate channel at 457 mm c/c and fixing the
12.5 mm tapered edge Gypboard with 25 mm drywall screws at 230 mm c/c & jointing and
finishing using joint compound and paper tape to have a flush look including filling the tapered &
square edges with jointing compound, two coats of drywall topcoat complete for finished item of
work as per Idia Gypsum Ltd specification.

BLD-CSTN-8-31

UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm Gypboard
1219 mm x 1829 mm size Boards

sqm

1.03

750

BLD-CSTN

Index-code

S No Description
1

Ceiling Angle
25 mm x 10 mm x 0.55 mm
Connecting Clips
Ceiling Section
51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick
Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm
Perimeter Channel
20 mm x 27 mm x 30 mm(web) of 0.55 mm thick
Rawl Plug
Soffit Cleats
Drywall Screws - 25 mm
Jointing Compound
Jointing Paper Tape
Drywall Top Coat
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
Gyp Board Fine Line Grid false ceiling

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

RM

0.64

Nos

1.84

RM

2.30

RM

0.84

RM
Nos
Nos
Nos
Kgs
RM

0.40
0.64
0.64
18.00
0.55
1.46

Lits

0.15

day

0.40

day
day
day

0.40
0.08
0.08

day
day
day

0.04
0.08
0.24

Hrs
Hrs

0.32
0.64
1%

127 Supplying and fixing Gyp Board Fine Line Grid false ceiling (GS-FLC-4.6 as per India Gypsum) in
size 600 mm x 600 mm using 12.5 mm thick/ 9.5 mm thick Gyp Board sheet tiles of size 595 mm
x 595 mm or 595 mm x 1195 mm conforming to IS 2095 - 1982 fixing to Gyp steel precoated GI
wall angle of size 25 mm x 25 mm x of 0.70 mm thick along the perimeter of ceiling screw fixed to
brick work/ partition at 610 mm c/c and suspending the frame work using precoated GI Tee
section (24 mm x 38 mm x 0.7 mm) from soffit at 1220 mm c/c fixed with GI Soffit Cleat, rawl
plugs and steel expansion fasteners & connecting clip to the GI T section with 4 mm dia GI Rod
with galvanised spring steel level clip of PVC unversal holding clips system at 1200 mm c/c and
fixing the 12.5 mm / 9.5 mm Gypboard Sheet tiles of size 595 mm x 595 mm or 595 mm x 1195
mm and finishing two coats of drywall topcoat complete for finished item of work as per Idia
Gypsum Ltd specification.

BLD-CSTN-8-32

UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm / 9.5 mm - Gypboard Tiles
Either - 595 mm x 595 mm Or - 595 mm x 1195 mm GI Angle - Precoated
25 mm x 25 mm x 0.7 mm
GI - Precoated - T Section - 3600 mm long
24 mm x 38 mm x 0.7 mm thick
GI - Precoated - T Section - 600 mm long
24 mm x 38 mm x 0.7 mm thick
GI Rod - 4 mm Dia
Connecting Rod
Rawl Plug
Soffit Cleats
Unversal Holding Clips

sqm

1.00

220.00

220.42

RM

0.40

36.00

14.40

RM

1.60

47.00

75.20

RM

1.60

47.00

75.20

RM
Nos
Nos
Nos

1.28
1.28
1.28
5.36

10.00
1.50
1.50
2.50

12.80
1.92
1.92
13.40

751

BLD-CSTN

Index-code

S No Description
1

Drywall Top Coat


B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

Lits

0.15

125.00

18.75

day
day
day
day
day
day
day

0.40
0.40
0.08
0.08
0.04
0.04
0.24

350.00
320.00
350.00
320.00

140.00
128.00
28.00
25.60
0.00
0.00
0.00

Hrs
Hrs

0.32
0.32
1%

0.00
0.00

Gypboard Suspended false ceiling

Modified

BLD-CSTN-8-31

126 Supplying and fixing Gyp Board Suspended regular single layer false ceiling (GS-MFSC-4.1 as
per India Gypsum) using 12.5 mm thick Gyp Board conforming to IS 2095 - 1982 fixing to Gyp
steel GI perimeter channels of size 20 mm x 27 mm x 30 mm(web) of 0.55 mm thick along the
perimeter of ceiling screw fixed to brick work/ partition at 610 mm c/c and suspending the frame
work using Intermediate channels (45 mm x 15mm x 15mm x 0.9 mm) from soffit at 1220 mm c/c
with ceiling angle (25 mm x 10 mm x 0.55 mm) fixed with GI Cleat and steel expansion fasteners
& connecting clip to the ceiling channels (with knurled web of 51.5 mm x 26 mm x 10.5 mm x 0.55
mm) fixed in direction perpendicular to the intermediate channel at 457 mm c/c and fixing the
12.5 mm tapered edge Gypboard with 25 mm drywall screws at 230 mm c/c & jointing and
finishing using joint compound and paper tape to have a flush look including filling the tapered &
square edges with jointing compound, two coats of drywall topcoat complete for finished item of
work as per Idia Gypsum Ltd specification.

UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm Gypboard
1219 mm x 1829 mm size Boards
Ceiling Angle
25 mm x 10 mm x 0.55 mm
GI ceiling section 51.5x26x10.5x0.55mm
Intermediate channel 45x15x15x0.9mm
Perimeter chaneel 20x27x30mmx0.55mm
Connecting Clips
Rawl Plug
Soffit Cleats
Drywall Screws - 25 mm
Jointing Compound
Jointing Paper Tape
Drywall Top Coat
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm

sqm

1.03

RM
RM
RM
RM

0.64
0.84
0.84
0.40

Nos
Nos
Nos
Nos
Kgs
RM
Lits

1.84
0.64
0.64
18.00
0.55
1.46
0.15

day
day
day
day
day
day
day

0.40
0.40
0.08
0.08
0.04
0.08
0.24

Hrs
Hrs

0.32
0.64
1%

752

BLD-CSTN

Index-code

S No Description
1

Gyp Board Fine Line Grid false ceiling


(Modifide)

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

(Modifide)

Supplying and fixing Gyp Board Fine Line Grid false ceiling (GS-FLC-4.6 as per India Gypsum) in size 600 mm
x 600 mm using 12.5 mm thick/ 9.5 mm thick Gyp Board sheet tiles of size 595 mm x 595 mm or 595 mm x
1195 mm conforming to IS 2095 - 1982 fixing to Gyp steel precoated GI wall angle of size 25 mm x 25 mm x of
0.70 mm thick along the perimeter of ceiling screw fixed to brick work/ partition at 610 mm c/c and suspending
the frame work using precoated GI Tee section (24 mm x 38 mm x 0.7 mm) from soffit at 1220 mm c/c fixed
with GI Soffit Cleat, rawl plugs and steel expansion fasteners & connecting clip to the GI T section with 4 mm
dia GI Rod with galvanised spring steel level clip of PVC unversal holding clips system at 1200 mm c/c and
fixing the 12.5 mm / 9.5 mm Gypboard Sheet tiles of size 595 mm x 595 mm or 595 mm x 1195 mm and
finishing two coats of drywall topcoat complete for finished item of work as per Idia Gypsum Ltd specification.

UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm / 9.5 mm - Gypboard Tiles
Either - 595 mm x 595 mm Or - 595 mm x 1195 mm GI Angle - Precoated
25 mm x 25 mm x 0.7 mm
GI - Precoated - T Section - 3600 mm long
24 mm x 38 mm x 0.7 mm thick
GI - Precoated - T Section - 600 mm long
24 mm x 38 mm x 0.7 mm thick
GI Rod - 4 mm Dia
Connecting Rod
Rawl Plug
Soffit Cleats
Unversal Holding Clips
Drywall Top Coat
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
Add 25% Muncipal allowance
Add 14% towards contractor profit
or Say

sqm

1.00

220.00

220.42

RM

0.40

36.00

14.40

RM

1.60

47.00

75.20

RM

1.60

47.00

75.20

RM
Nos
Nos
Nos
Lits

1.28
1.28
1.28
5.36
0.15

10.00
1.50
1.50
2.50
125.00

12.80
1.92
1.92
13.40
18.75

day
day
day
day
day
day
day

0.12
0.12
0.024
0.024
0.012
0.012
0.07

415.00
370.00
480.00
370.00
320.00
320.00
310.00

49.80
44.40
11.52
8.88
3.84
3.84
22.32

Hrs
Hrs

0.32
0.32
1%

105.00
97.00

0.00

144.60

33.60
31.04
6.43
649.68
0.00
649.68
90.96
740.64
741.00

Armstrong False ceiling

753

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

sqm

1.00

RM

0.40

RM

1.60

RM

1.60

RM
Nos

1.28
1.28

day
day
day
day
day
day
day

0.40
0.40
0.08
0.08
0.04
0.04
0.24

Hrs
Hrs

0.32
0.32
1%

128 Providing and fixing in true horizontal level 600 mm x


600 mm 15 mm thick Arm strong false ceiling system
manufactured by M/s Arm strong world Industries using
hot dipped Galvanised Steel section exposed surface
with pre-coated capping, main Tee of size 24 x 32 mm
at every 1200 mm c/c maximum and rotary stiched
cross tee of size 24 x 27 mm at evry 600 mm c/c and
sub-cross tee of size 24 mm x 25 mm at 1200 mm c/c
and wall angle of size 19 x 19 mm fixed to periphery of
the wall and the above grid is suspended at every 1200
mm c/c in both directions using 2.0 mm thick prestraightened GI Wire laying fine fissured butt edge
ceiling tiles of 15 mm thick mineral fiber Board
manufactured by M/s Arm Strong World Industries Ltd.,
having RH 99% and for finished of size 600 x 600 mm
including Cost &conveyance of all materials and labour
charges such as cutting , fixing of standing of frame
work exposing roof making complete for finished item of
work

BLD-CSTN-8-33

UNIT 1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x 600
Hotdipped GI Angle - Precoated - Grid
19 mm x 19 mm
Polyster painted GI - T Section - 1200 mm
(1) 24 x 32 mm and (2) 24 x 25 mm (sub-cross
Tee)
Polyster painted GI - T Section - 300 mm
24 mm x 27 mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
6 mm Nylon Rawl Plug
B) LABOUR CHARGES
PER UNIT 1 sqm
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm

754

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

sqm

1.00

RM

0.40

RM

3.20

Nos
Nos

1.28
1.28

day
day

0.36
0.36

day
day
day
day
day

480.00
0.00
0.02
0.04
0.20

Hrs
Hrs

0.16
0.32
1%

Kgs

23.00

13.00

299.00

299.00

day
day
day

0.27
0.64
0.91
0.00

480.00
370.00
310.00

131.04
235.69
282.10
0.00

131.04
235.69
282.10

947.83
132.70

947.83
132.70

Thermocole False ceiling


129 Providing and fixing Thermocole False ceiling in true
horizontal level 600 mm x 600 mm using 15 mm/ 19
mm thick Thermocole sheet anodised Aluminium Tee
sections of size 24.50 mm x 24.0 mm x 2.4 mm in grid
with cross tee of size 24 x 24.5 mm at every 600 mm
c/c and anodised aluminium wall angle of size 24 x 24
mm fixed to periphery of the wall and the above grid is
suspended at every 1200 mm c/c in both directions
using 2.0 mm thick GI Wire for finished of size 600 x
600 mm including Cost &conveyance of all materials
and labour charges such as cutting , fixing of standing
of frame work exposing roof making complete for
finished item of work

BLD-CSTN-8-34

UNIT 1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600
Alumninium Angle
24 mm x 24 mm
Anodised Aluminium T Section
(1) 24 x 24.5 x 2.4 mm mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
Rawl Plugs
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
1

Providing Putty to Internal walls


Providing and applying synthetic plaster of paris putty
or lime punning of average 1 to 2 mm thicknes over
plastered surface to prepare the surface even and
smooth after thoroughly brusing the surfaceto remove
all dirt and remains of loose powered materials,
applying emery paper, sand the surface, clean & wipe
off loose dust, applying knifing paste filler by putty
knife/susllin pad, air dry for 2-3 hrs, sand with 180 and
320 No., emery paper for the surface preparation
including cost and conveyance of all marerials to work
site and all oprational, incidental, labour charges etc.
complete for finished item of work for internal walls

Total cost for 10 sqm


A) MATERIALS:
Synthetic/Plaster of Paris Putty
B) LABOUR:
Painter - 1st class
Painter - 2nd class
Mazdor
c) Labour allowance on B)
Sundries for Emery papers, fillers,knife etc.
D) Overheads and Contractor's Profit

LS
0.14

755

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Rate for 10 Sqm


Rate for 1Sqm
2

Amount
Rs.with
MA

Amount
without M.A

2028.36
202.84

2028.36
202.84

Providing Putty to External walls


Providing and applying synthetic plaster of paris putty
or equivalent putty such as birla wall care putty to
textaure paint or equivalent such as NCL/Saicoat
texture paint of average 2 to 3 mm thicknes over
plastered surface to prepare the surface even and
smooth after thoroughly brusing the surface to remove
all dirt and remains of loose powered materials,
applying emery paper, sand the surface, clean & wipe
off loose dust, applying putty/texture paint filler by putty
knife/muslin pad, air dry for 2-3 hrs, for the surface
preparation including cost and conveyance of all
marerials to work site and all oprational, incidental,
labour charges etc. complete for finished item of work
for External walls.

Total cost for 10 sqm


A) MATERIALS:
Synthetic/Plaster of Paris Putty
B) LABOUR:
Painter - 1st class
Painter - 2nd class
Mazdor
labour for access scaffold
c) Labour allowance on B)
Acess scaffold as per building SoR (Cumulative
raes for higher floors)

Kgs

34.500

13.00

448.50

448.50

day
day
day
Sqm

0.546
1.274
1.820
10.000
0.000
10.000

480.00
370.00
310.00
40.43

262.08
471.38
564.20
404.30
0.00
54.60

262.08
471.38
564.20
404.30

2205.06
308.71
2513.77
251.38

2205.06
308.71
2513.77
251.38

Sqm

D) Overheads and Contractor's Profit


Rate for 10 Sqm
Rate for 1Sqm

5.46

0.14

54.60

WHITE WASHING, COLOUR WASHING &


DISTEMPERING
130 White washing one coat with lime of approved

BLD-CSTN-9

BLD-CSTN-9-1

quality to give an even shade after thoroughly


brushing the surface to remove all dirt and
remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift
charges etc., complete for finished item of
work, but excluding conveyance charges of
materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
Brick Layers
Mazdoor (unskilled)
Sundries including brushes etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 13.615% over head charges

cum

0.005
L.S

29.00

139.20
10.00

day
day
LS

0.11
0.22

415.00
310.00

45.65
68.20
0.81
263.86

0.00

0.00
263.86
0.00
264.00
26.00

756

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.007
L.S

29.00

194.88
10.00

day
day
LS

0.160
0.32

415.00
310.00

66.40
99.20
0.81
371.29

131 White

washing two coats with lime of


approved quality to give an even shade after
thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift
charges etc., complete for finished item of
work, but excluding conveyance charges of
materials

BLD-CSTN-9-2

Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime (960 Kgs/cum)
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
Brick Layers
Mazdoor (unskilled)
Sundries including brushes etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total

0.00

0.00
371.29

Add 14% over head charges

51.98
423.00

132 White

washing three coats with lime of


approved quality to give an even shade after
thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift
charges etc., complete for finished item of
work, but excluding conveyance charges of
materials

BLD-CSTN-9-3

Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
White washer
Brick Layers
Man Mazdoor
Women mazdoor
Mazdoor (unskilled)
Sundries including brushes, ladders etc.,
Grand Total
Add 25% for MC on Labour charges

cum

0.009
L.S

day
day
day
day
day
LS

0.220
0.43

0.00

29.00

0.26
10.00

415.00

91.30

310.00

133.30
0.40
235.26
0.00

Grand Total

235.26

Add 14% over head charges

32.94
268.00

757

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

133 White washing one coat with whiting of

approved quality to give an even shade after


thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift
charges etc., complete for finished item of
work, but excluding conveyance charges of
materials

BLD-CSTN-9-4

Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement

with White Cement Grade II

cum / kg

1.20

29.00

34.80

day
day

0.11
0.22

415.00
310.00

45.65
68.20

0.50%

113.85

56.93
205.58

Gum, conjee water, or prickly pear juice including


necessary fire wood
B. LABOUR
Brick Layers / Painter
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 13.615 over head charges

0.00

0.00
205.58
0.00
206.00

758

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum / kg

2.00

29.00

58.00

134 White washing two coats to ceiling with

whiting of approved quality to give an even


shade after thoroughly brushing the surface
to remove all dirt and remains of loose
powdered materials including cost of all
materials, labour charges and incidental such
as scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials

BLD-CSTN-9-5

Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement (TBSC-R.I-01)

L.S

Gum, conjee water, or prickly pear juice including


necessary fire wood
B. LABOUR
Brick Layers / Painter
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,

10.00

day

0.210

415.00

87.15

day

0.320
1.00%

310.00
186.35

99.20
93.18

Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 13.615% over head charges
Rate for 10 Sqm
Rate for 1 Sqm

347.53
0.00

347.53

0.00
347.53

347.53

0.00

47.32

348.00

394.84

35.00

135 White washing three coats with whiting of

approved quality to give an even shade after


thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift
charges etc., complete for finished item of
work, but excluding conveyance charges of
materials

BLD-CSTN-9-6

Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement

kg

2.800

29.00

Gum, conjee water, or prickly pear juice including


necessary fire wood
B. LABOUR
Brick Layers / Painter
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 13.615 over head charges

Colour Washing, One Coat


Unit: 10 sqm
254
Rate for "White Washing" one coat

81.20
10.00

day
day

0.300
0.430

344.00
310.00

0.00

103.20
133.30
327.70

327.70

0.00
327.70

327.70

0.00

45.88

328.00

373.58

136

BLD-CSTN-9-7

BLD-CSTN-9-8

10 sqm

1.000

263.86

263.86

Add: For Colours, etc., (50 percent of above rate)

131.93

Total

396.00

137 Colour Washing, Two Coats


255 Unit: 10 sqm

Rate for "White Washing"single coats

10 sqm

2.000

205.58

411.15

759

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Unit: 10 sqm
A. MATERIALS :
Distemper
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

Amount
without M.A

205.58
617.00

Add: For Colours, etc., (50 percent of above rate)


Total
138 Distempering, 2 Coats with Water Bound
256 Distemper

BLD-CSTN-9-9

Amount
Rs.with
MA

kg

1.340

60.00

80.40

day
day

0.500
1.300
1.000%

272.00
310.00
539.00

136.00
403.00
5.39

0.00

624.79
0.00
624.79

624.79

87.47
712.00

87.47
712.26

624.79

760

BLD-CSTN

Index-code

S No Description
1

139 Distempering,
257 Distemper

BLD-CSTN-9-10

Coats

with

Oil

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg

1.700

70.00

119.00

day

1.200
1.000%

403.00
483.60

483.60
4.84

Bound

Unit: 10 sqm
A. MATERIALS :
Distemper
B. LABOUR
Painter
Sundries including brushes, ladders, etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

607.44
0.00
607.44

0.00

607.44
607.44

0.00

85.04

607.00

692.48

PAINTING & VARNISHING


140 Painting to new walls with 2 coats of ready mixed

BLD-CSTN-10

BLD-CSTN-10-1

oil bound wahsable distemper of approved brand


and shade over a base coat of appropriate primer
of approved brand, making 3 coats in all to give
an even shade after thourughly brushing the
surface to remove all dirt and remains of loose
powdered materials, including cost and
conveyance of all materials to work site and all
operational, incidental, labour charges etc.
complete for finished item of work as per SS 911
for internal walls

PRIMARY COAT:
Cost of Primer
Painter I st class
Pianter IInd class
Cost of washable Oil Bound Distemper
1st class painter
II class painter
Grand Total
Add 20% for MC on Labour charges
Grand Total
Add 13.615% over head charges
Rate for 10 Sqm
Rate for 1 Sqm
141 Painting, Priming Coat on New Plastered
270 Surface

BLD-CSTN-10-2

Unit: 10 sqm
A. MATERIALS :
Cement Primer
B. LABOUR
Painter
Sundries including brushes, soaps, putty etc.,
Total cost for 10 sqm
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

Lts
Nos
Nos
Kgs
Nos
Nos

0.50
0.08
0.19

165.00
480.00
370.00

82.50
38.40
70.30

1.70
0.36
0.84

90.00
480.00
370.00

153.00
172.80
310.80
827.80
0.00
827.80
112.70
941.00
94.00

0.00

kg

1.00

134.00

134.00

day

0.700
0.500%

344.00

240.80
1.20
376.00

0.00

827.80
827.80
112.70
940.50

376.00

0.00
376.00

376.00

52.64

52.64

429.00

428.64

761

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg

2.000

55.00

110.00

day
day

0.300
1.500
1.000%

403.00
310.00
585.90

120.90
465.00
5.86
701.76

701.76

0.00
701.76
98.25

701.76
98.25

800.00

800.01

142 Painting Walls with Snowcem or other equal


284 and approved Water Proof Cement Paint over

Priming Coat, One Coat (All Colours)

BLD-CSTN-10-3

Unit: 10 sqm
A. MATERIALS :
Cement Paint at 5 sqm., per kg
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

0.00

143 Painting Walls with Snowcem or other equal


285 and approved Water Proof Cement Paint over

Priming Coat, 2 Coats (All Colours)

BLD-CSTN-10-4

Unit: 10 sqm
A. MATERIALS :
Cement Paint at 3 sqm., per kg
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, etc.,
Muncipal allowance
Grand Total
Add 20% for MC on Labour charges
Grand Total
Add 13.615% over head charges
Rate for 10 Sqm
Rate for 1 Sqm

kg

3.500

55.00

192.50

day
day

0.500
1.500
1.000%

403.00
310.00
666.50

201.50
465.00
6.67

25.000%

0.00

0.00

865.67
0.00
865.67

865.67

117.86
984.00
98.00

121.19
986.86

865.67

144 Painting to new walls with 2 coats of water proof

cement paint of apporved brand and shade over


a base coat of approved cement primer grade I
making making 3 coats in all to give an even
shade after thourughly brushing the surface to
remove all dirt and remains of loose powdered
materials, including cost and conveyance of all
materials to work site and all operational,
incidental, labour charges etc. complete for
finished item of work as per SS 912 for external
walls

BLD-CSTN-10-5

Cost of Cement Primer


Ist class painter
2nd class painter
Add 20% for MC on Labour charges

kg
day
day

1.00
0.21
0.49

165.00
480.00
370.00
282.10

165.00
100.80
181.30
0.00

Cost of water proof cement Paint of approved


quality BMT-J.24

kg

3.50

55.00

192.50

1st class painter


2nd class painter
Mazdoor (unskilled)
Grand Total
Add 20% for MC on Labour charges
Grand Total

day
day
day

0.15
0.35
1.50

480.00
370.00
310.00

72.00
129.50
465.00
0.00

0.00

0.00
1306.10

0.00

762

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Add 13.615% over head charges


Rate for 10 Sqm
Rate for 1 Sqm

Amount
Rs.with
MA

Amount
without M.A

177.83
1484.00

0.00
0.00

148.00

145 Painting, Priming Coat on New Wood Work


268

BLD-CSTN-10-6

Unit: 10 sqm
A. MATERIALS :
Wood Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Grand Total

0.700

158.00

110.60

day

0.700
1.000%

403.00

282.10
2.82
395.52

Add 20% for MC on Labour charges

0.00

395.52

0.00

Grand Total

395.52

395.52

Add 13.615% over head charges

53.85

55.37

Rate for 10 Sqm

449.00

450.89

Rate for 1 Sqm

45.00

146 Painting, Priming Coat on New Iron Work


269

BLD-CSTN-10-7

Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Grand Total

0.70

90.00

63.00

day

0.70

403.00

282.10
0.40
345.50

Add 25% for MC on Labour charges

BLD-CSTN-10-8

0.00

345.50

0.00

Grand Total

345.50

Add 14% over head charges

48.37

48.37

394.00

393.87

345.50

147 Varnishing to Wood Work, One Coat


281 Unit: 10 sqm

A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Grand Total
Add 25% for MC on Labour charges

L
L

0.800
0.600

72.00
40.00

57.60
24.00

day
day

0.700
0.700

403.00
310.00

282.10
217.00
0.60
581.30

0.00

581.30

0.00

Grand Total

581.30

581.30

Add 14% over head charges

81.38

81.38

663.00

662.68

763

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

L
L

1.200
1.100

72.00
40.00

86.40
44.00

day
day

1.100
1.100

403.00
310.00

443.30
341.00
0.20
914.90
0.00

148 Varnishing to Wood Work, Two Coats


282

BLD-CSTN-10-9

BLD-CSTN-10-10

Unit: 10 sqm
A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

0.00

914.90

914.90

914.90

128.09

128.09

1043.00

1042.99

149 Painting with Ready mixed oil paint (all


256 colours)
to
265 i. One Coat - New Wood Work :

ii

iii

iv

Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
One Coat - Old Wood Work & New Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - Old Wood Work & New Iron
Work:
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Add 25% for MC on Labour charges
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Add 14% over head charges

One Coat - Old Iron Work :


Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter

kg

1.600

199.00

318.40

day
LS

0.700

403.00

282.10

kg

2.800

199.00

557.20

day
LS

1.200

403.00

483.60

kg

1.500

199.00

day
LS

0.700

403.00

kg

2.400

199.00

477.60

day

1.200

403.00

483.60
961.20
0.00

0.00
LS

0.20
961.40
134.60
1096.00

kg

1.200

170.00

204.00

day

0.700

403.00

282.10

961.20

961.20
134.57
1096.00

764

BLD-CSTN

Index-code

S No Description
1

Add 25% for MC on Labour charges


Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Add 14% over head charges

Unit

Quantity

Rate Rs.

0.00
LS

Amount
Rs.with
MA

Amount
without M.A

486.10
0.00

486.10

0.20
486.30
68.08
554.00

486.10
68.05
554.15

765

BLD-CSTN

Index-code

S No Description
1

vi

Two Coats - Old Iron Work :


Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Add 25% for MC on Labour charges
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Add 14% over head charges

Three Coats - Old Iron Work :


Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
viii Three Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg

2.100

170.00

357.00

day

1.100
0.00

403.00

443.30
0.00
0.20
800.50
112.07
913.00

LS

vii

BLD-CSTN-10-11

kg

3.400

day
LS

1.500

kg

3.900

day
LS

1.600

0.500

day

0.700

0.400

day

0.700

403.00

0.900

170.00

153.00

day

1.200

403.00

483.60

403.00

403.00

150 Painting with :


266 i. Plastic Emulsion paint Grade I - One Coat

for New Wood Work, Old Wood Work & New


Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter

ii

Sundries including brushes, soap, putty etc.,


Total cost for 10 sqm
Plastic Emulsion paints - One Coat for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter

iii

403.00

Sundries including brushes, soap, putty etc.,


Total cost for 10 sqm
Plastic Emulsion paints - Two Coats for New
Wood Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm

766

BLD-CSTN

Index-code

S No Description
1

iv

Plastic Emulsion paints - Two Coats for Old


Wood Work & New Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter

B. LABOUR
Painter

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

0.800

day

1.200

0.800

day

1.100

0.700

day

1.100

1.200

day

1.600

1.100

day

1.500

403.00

0.700

199.00

139.30

day

0.700

403.00

282.10
0.40
421.80
0.00
421.80
59.05
481.00

403.00

403.00

Sundries including brushes, soap, putty etc.,


Total cost for 10 sqm
Plastic Emulsion paints - Two Coats for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter

vii

Quantity

Sundries including brushes, soap, putty etc.,


Total cost for 10 sqm
Plastic Emulsion paints - Two Coats for New
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.

vi

Unit

403.00

Sundries including brushes, soap, putty etc.,


Total cost for 10 sqm
Plastic Emulsion paints - Three Coats for
New Wood Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter

403.00

Sundries including brushes, soap, putty etc.,


Total cost for 10 sqm
viii Plastic Emulsion paints - Three Coats for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter

151
i

BLD-CSTN-10-12

Sundries including brushes, soap, putty etc.,


Total cost for 10 sqm
Painting with Synthetic Enamel paints - One
Coat - for New Wood Work, Old Wood Work &
New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 10 sqm

0.00

767

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

768

BLD-CSTN

Index-code

S No Description
1

ii

Painting with Synthetic Enamel paints - One


Coat - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Muncipal allowance 25%

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

0.500

199.00

99.50

day

0.700

403.00

282.10
0.40
70.53
452.53

Add 14% over head charges


Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 10 sqm

iii

Painting with Synthetic Enamel paints - Two


Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd. BMT-J.30
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 10 sqm

63.35
968.40
0.00

0.00

968.40
135.58
1104.00

1.200

276.00

331.20

day

1.200

403.00

483.60
0.40
815.20
0.00
815.20
114.13
929.00

0.00

0.00
0.00
0.00

815.20
815.20
114.13
929.33

Painting with Synthetic Enamel paints - Two


Coats - for New Wood Work
145 Painting, Priming Coat on New Wood Work
268 Unit: 10 sqm

A. MATERIALS :
Wood Primer (TBSC-G.I-07)
B. LABOUR
Painter
Synthetic Enamel paint
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd. (TBSC-G.V-02)

iv

B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Grand Total
Add 20% for MC on Labour charges
Grand Total
Add 13.615% over head charges
Total cost for 10 sqm
Rate for 1 Sqm
Painting with Synthetic Enamel paints - Two
Coats - For Old Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.

0.700

158.00

110.60

day

0.700

403.00

282.10

1.200

210.00

252.00

day

1.200

403.00

0.00

765.70

483.60
0.40
1128.70
0.00
1128.70
0.00
1129.00
113.00

1.100

276.00

1128.70
1128.70
158.02
1286.72

303.60

B. LABOUR

769

BLD-CSTN

Index-code

S No Description
1

Painter
Sundries including brushes, soap, putty etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 10 sqm

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

day

1.200

403.00

483.60
0.10
787.30
0.00
787.30
110.22
898.00

0.00

787.30
787.30
110.22
897.52

Painting with Synthetic Enamel paints - Two


Coats including red oxide primer coat- For
New Iron Work
Painting, Priming Coat on New Iron Work
Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter

0.70

142.00

99.40

day

0.70

403.00

282.10
0.40

1.100

210.00

231.00

day

1.100

403.00

0.00

725.40

443.30
0.20
1056.40
0.00
1056.40
143.83
1200.00
120.00

Sundries including brushes, soap, putty etc.,

Grand Total
Add 20% for MC on Labour charges
Grand Total
Add 13.615% over head charges
Total cost for 10 sqm
Rate for 1 Sqm
Painting with Synthetic Enamel paints - Two
Coats - For New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter

1.100

276.00

303.60

day

1.100

403.00

443.30

Sundries including brushes, soap, putty etc.,

Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 10 sqm
vi

0.00

1056.40
147.90
1204.30

747.10
747.10
104.59
851.69

Painting with Synthetic Enamel paints - Two


Coats - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.

0.20
747.10
0.00
747.10
104.59
852.00

1056.40

B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Three
Coats - for New Wood Work

0.900

276.00

248.40

day

1.100

403.00

443.30
0.14
691.84
0.00
691.84
96.86
789.00

0.00

691.84
691.84
96.86
788.70

770

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.

1.700

276.00

469.20

day

1.600

403.00

644.80
0.20
1114.20
0.00

S No Description
1

B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 10 sqm

0.00

1114.20
155.99
1270.00

1114.20
1114.20
155.99
1270.19

771

BLD-CSTN

Index-code

S No Description
1
viii

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

1.600

276.00

441.60

day

1.500

403.00

604.50

Painting with Synthetic Enamel paints - Three


Coats - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 10 sqm

0.00

1046.10
0.00
1046.10

1046.10

146.45
1193.00

146.45
1192.55

1046.10

152 Polishing on wood work with readymade wax

polish of approved brand and manufacture

BLD-CSTN-10-13

New Work :
A. MATERIALS :
Readymade wax polish
B. LABOUR
Painter
Healper
Sundries including brushes, soap, cloth etc.,
Grand Total

kg

0.500

400.00

200.00

day
day
LS

0.800
0.800

403.00
310.00

322.40
248.00
4.00
774.40

Add 25% for MC on Labour charges

0.00

774.40

0.00

Grand Total

774.40

774.40

Add 14% over head charges

108.42

108.42

Total cost for 10 sqm

883.00

882.82

153 Melamine polishing on wood work (one or

more coat)

BLD-CSTN-10-14

BLD-CSTN-10-15

New Work :
A. MATERIALS :
Melamine polish
B. LABOUR
Painter
Healper
Sundries for Spraying Machine etc.,
Total cost for 10 sqm
154 French Spirit polishing Two or more coats on
new works including a coat of wood filler.
A. MATERIALS :
Shellac
Spirit
B. LABOUR
Painter
Sundries such as pigment, terpentaine, sand paper,
putty, wood filler, white woolen cloth, linseed oil, cotton
etc.,

0.650

day
day
LS

0.800
0.800

kg
L

0.228
1.630

day
LS

3.200

cum

1.000

403.00
310.00

403.00

Total cost for 10 sqm

WOOD WORK, ALUMINUM DOORS,


WINDOWS, VENTILATORS Etc.,
BLD-CSTN-11
BLD-CSTN-11-1

155 Best Teak Wood wrought and put up to 2

meters (Schedule Item No 286)


Unit = 1 cum
Materials :
Teak wood large scantlings upto 2 m
Labour :

772

BLD-CSTN

Index-code

S No Description
1

Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day
day

17.700
8.800

350.00
310.00

LS

773

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

1.000

day
day

17.700
8.800
LS

cum

1.000

day

17.700

350.00

day

8.800

310.00

156 Best Teak Wood wrought and put up over 2

metres and below 3


(Schedule Item No 287)

BLD-CSTN-11-2

metres

in

length

Unit = 1 cum
Materials :
Teak wood large scantlings over 2 m and below 3
m in length
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum

350.00
310.00

157 Best Teak Wood wrought and put up in large


scantling of over 3 metres in length (Schedule Item
No 288)

BLD-CSTN-11-3

Unit = 1 cum
Materials :
Teak wood large scantlings over 2 m and below 3
m in length
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
158 Best Teak Wood wrought and put up for
trusses including straps and all iron work
(Schedule Item No 289)

BLD-CSTN-11-4

BLD-CSTN-11-5

Unit = 1 cum
Materials :
Teak wood large scantlings
Iron Work (average)
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
159 Fully Panelled doors - External or Internal Moulded panels (Schedule Item No 290)
A
i

Single Shutter
800 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

LS

cum

1.000

kg

112.000

day

26.500

350.00

day

8.800

310.00

LS

cum

0.083

sqm

1.600

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard specification)

ii

Total for each door


900 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

LS

cum

0.088

sqm

1.800

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard specification)
Total for each door

774

BLD-CSTN

Index-code

S No Description
1

iii

1100 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.109

sqm

2.200

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard specification)

iv

Total for each door


1200 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

LS

cum

0.123

sqm

2.520

cum

0.094

sqm

1.890

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard specification)

Total for each door


900 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind appliances
(Vide relevant standard specification)

vi

Total for each door


1500 x 2400 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

LS

cum

0.159

sqm

3.600

Sundries inclusive of holdfasts and all wind appliances


(Vide relevant standard specification)
B
i

Total for each door


Double Shutter
900 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

LS

cum

0.096

sqm

1.800

cum

0.104

sqm

2.000

cum

0.134

sqm

2.860

Sundries inclusive of holdfasts and all wind appliances


(Vide relevant standard specification)
ii

Total for each door


1000 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

iii

Total for each door


1300 x 2200 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door

775

BLD-CSTN

Index-code

S No Description
1

iv

1400 x 2300 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.147

sqm

3.220

cum

0.068

sqm

0.720

sqm

1.600

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard specification)
Total for each door
* Note : Average rate for respective size
scantlings and rough plank
160 Fully Panelled doors - Internal Five Ply - Ply-

wood Panels (Schedule Item No 291)

BLD-CSTN-11-6

A
i

Single Shutter
800 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters

LS

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard specification)

ii

Total for each door


900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters

cum

0.071

sqm

0.870

sqm

1.800

cum

0.100

sqm

1.160

sqm

2.520

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard specification)

iii

Total for each door


1200 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

LS

Total for each door


iv

1300 x 2200 mm

*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

Total for each door


900 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

cum

0.106

sqm

1.390

sqm

2.860

cum

0.077

sqm

0.880

sqm

1.890
LS

Total for each door

776

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.091

sqm

0.880

sqm

2.100

cum

0.082

sqm

0.710

sqm

1.800

*Teak wood

cum

0.088

Five - Ply - Ply - Wood brich

sqm

0.820

Labour, wrought and putup in position frame &


shutters

sqm

2.000

*Teak wood

cum

0.090

Five - Ply - Ply - Wood brich


Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

sqm
sqm

0.940
2.200

*Teak wood

cum

0.123

Five - Ply - Ply - Wood brich


Labour, wrought and putup in position frame &
shutters

sqm
sqm

1.900
3.600

cum
sqm
sqm

0.130
1.280
3.600

S No Description
1

vi

1000 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

B
i

Total for each door


Double Shutter
900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind appliances
(Vide relevant standard specification)

Total for each door


ii

1000 x 2000 mm

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard specification)
Total for each door
iii

1100 x 2000 mm

Total for each door


iv

1400 x 2300 mm

Sundries inclusive of holdfasts and all wind


appliances (Vide relevant standard specification)
Total for each door
v

1500 x 2400 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind appliances
(Vide relevant standard specification)

Total for each door


* Note : Average rate for respective size
scantlings and rough plank

777

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Top Tower bolts (Ave : Size)

Nos

Bottom Tower bolts 150mm long

Nos

Parliament hings with screws

Nos

Oxidised aldrop with bolts

Nos

Wind cleats with hings

Nos

Top Tower bolts (Ave : Size)

Nos

Bottom Tower bolts 150mm long

Nos

Butt hings with screws

Nos

Wind cleats with hings

Nos

cum

0.072

sqm

0.470

sqm

1.600

S No Description
1

161 Furniture - Iron - for External doors (Schedule

Item 292)

BLD-CSTN-11-7

(Same for all doors)


162 Furniture - Iron - Internal doors (Schedule

Item 293)

BLD-CSTN-11-8

(Same for all doors)


163 Glazed and Panelled doors (Schedule Item No.

294)

BLD-CSTN-11-9

Single Shutter

800 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
all wind appliances (Vide relevant standard
specification)

ii

Total for each door


900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
all wind appliances (Vide relevant standard
specification)

LS

cum

0.076

sqm

0.560

sqm

1.800

LS

Total for each door


iii

1200 x 2100 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
all wind appliances (Vide relevant standard
specification)

iv

Total for each door


1300 x 2200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
all wind appliances (Vide relevant standard
specification)

cum

0.106

sqm

0.760

sqm

2.520

LS

cum

0.115

sqm

0.870

sqm

2.860

LS

Total for each door

778

BLD-CSTN

Index-code

S No Description
1

Double Shutter

900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
all wind appliances (Vide relevant standard
specification)

ii

Total for each door


1000 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
all wind appliances (Vide relevant standard
specification)

iii

Total for each door


1100 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
all wind appliances (Vide relevant standard
specification)

iv

Total for each door


1400 x 2300 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
all wind appliances (Vide relevant standard
specification)

Total for each door


1500 x 2400 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
all wind appliances (Vide relevant standard
specification)

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.087

sqm

0.420

sqm

1.800

LS

cum

0.092

sqm

0.510

sqm

2.000

LS

cum

0.096

sqm

0.600

sqm

2.200

LS

cum

0.123

sqm

1.060

sqm

3.220

LS

cum

0.130

sqm

1.280

sqm

3.600

LS

Total for each door


* Note : Average rate for respective size
scantlings and rough planks.

779

BLD-CSTN

Index-code

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

*Teak wood
Labour, wrought and putup in position frame &
shutters

cum

0.107

sqm

2.000

Sundries inclusive of putty, brads, hold fasts and


wind appliances and screws for planks (Vide
standard specification)

LS

S No Description
1

164 Furniture - Same as for Fully Panelled Doors

External (Schedule Item No. 295)

BLD-CSTN-11-10

Total for each door


165 Framed and Planked Doors (Schedule Item

No. 296)

BLD-CSTN-11-11

ii

1000 x 2000 mm

Total for each door


1200 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)

cum

0.127

sqm

2.520

LS

Total for each door


* Note : Average rate for respective size
scantlings and rough planks.
166 Country wood Framed and Planked Doors

(Schedule Item No. 297)

BLD-CSTN-11-12

Single Shutter :
i

1000 x 2000 mm
Country wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)

ii

Total for each door


1200 x 2100 mm
Country wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)

cum
sqm

0.107
2.000

LS

cum

0.127

sqm

2.520

LS

Total for each door


167 Furniture - 6 Butt Hings - 1 Top and 2 Bottom

Tower Bolts and One Wrought steel safety


Hasp L.S. (Schedule Item No. 298)

BLD-CSTN-11-13

Each Door
168 Ledged Braced and Planked Doors (Schedule

Item No. 299)

BLD-CSTN-11-14
i

Single Shutter :
800 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)

cum

0.083

sqm

1.600

LS

780

BLD-CSTN

Index-code

S No Description
1

** Furniture - 3 Nos T - hinges - Vide SS for size 2 Nos Chain and slopes country make.

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

LS

Total for each door

781

BLD-CSTN

Index-code

S No Description
1

ii

1000 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.100

sqm

2.100

Sundries inclusive of hold fasts and wind


appliances and nails for planks (Vide standard
specification)

LS

** Furniture - 3 Nos T - hinges - Vide SS for size 2 Nos Chain and slopes country make.

LS

Total for each door


Note : * Average rate for respective size
scantlings and rough planks.
** Note that for this type of door the furniture will
be supplied and fixed by the contractor.
169 * Country wood Ledged Braced and Planked

Doors (Schedule Item No. 300)

BLD-CSTN-11-15

ii

800 x 2000 mm
Country wood
Labour, wrought and putup in position frame &
shutters

cum

0.083

sqm

1.600

Sundries inclusive of hold fasts and wind


appliances and nails for planks (Vide standard
specification)

LS

** Furniture - 3 Nos T - hinges - Vide SS for size 2 Nos Chain and slopes country make.

LS

Total for each door


1000 x 2100 mm
Country wood
Labour, wrought and putup in position frame &
shutters

cum

0.100

sqm

2.100

Sundries inclusive of hold fasts and wind


appliances and nails for planks (Vide standard
specification)

LS

** Furniture - 3 Nos T - hinges - Vide SS for size 2 Nos Chain and slopes country make.

LS

Total for each door


** Note that for this type of door the furniture will
be supplied and fixed by the contractor.
Note : * Class of Country wood to be defined in
relevent schedule item.
170 Flush type Doors with 35mm Thick Flush

Shutters with Bondwood solied Block Board


Type Faced on Both the sides with
Commercial Type Plywood (Schedule Item No.
301.)
Single Shutter :

BLD-CSTN-11-16
i

900 x 2000 mm
*Teak wood
Flush Shutter 35mm thick (Vide relevant standard
specification)
Labour, wrought and putup in position frame &
shutters

cum

0.035

sqm

1.530

sqm

1.800

Sundries inclusive of hold fasts and all wind appliances


(Vide standard specification)

Total for each door

782

BLD-CSTN

Index-code

S No Description
1

ii

1000 x 2100 mm
*Teak wood
Flush Shutter 35mm thick (Vide relevant standard
specification)
Labour, wrought and putup in position frame &
shutters

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.037

sqm

1.820

sqm

2.100

cum

0.028

sqm

0.390

sqm

0.720

cum

0.037

sqm

0.500

sqm

0.960

cum

0.041

sqm

0.700

sqm

1.200

cum

0.061

sqm

0.710

sqm

1.440

cum

0.072

sqm

0.920

sqm

1.800

cum

0.059

sqm

0.970

sqm

1.700

Sundries inclusive of hold fasts and all wind


appliances (Vide standard specification)
Total for each door
*Note : Average
scantlings.

BLD-CSTN-11-17

rate

for

respective

size

171 Windows Glazed (Schedule Item No. 302)


A Single Shutter :
i

600 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)

ii

Total for each window


800 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame & shutters

Sundries inclusive of putty, brads, hold fasts and


wind appliances (Vide standard specification)
B
i

Total for each window


Double Shutter :
1000 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances (Vide standard specification)

ii

Total for each window


1200 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame & shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)

iii

Total for each window


1500 x 1200 mm (3 Pannels)
*Teak wood
Glass
Labour, wrought and putup in position frame & shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)

iv

Total for each window


1000 x 1700 mm (2 Pannels)
*Teak wood
Glass
Labour, wrought and putup in position frame & shutters

783

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Sundries inclusive of putty, brads, hold fasts and


wind appliances (Vide standard specification)
Total for each window

784

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

*Note : Average rate for respective size scantlings.


172 Furniture for Double Leaf Windows Glazed

With Top Lights (Schedule Item No. 303)

BLD-CSTN-11-18

BLD-CSTN-11-19

BLD-CSTN-11-20

BLD-CSTN-11-21

Banel Bolts 100 mm long


Top tower bolts 150 mm long
Bottom bolts 150 mm long
Parliament hinges
173 Furniture for Double Leaf Windows Glazed
without Top Lights (Schedule Item No. 304)

each

each

each

each

Top tower bolts 150 mm long


Bottom bolts 150 mm long
Parliament hinges
Same for all such windows
174 Furniture for Single Leaf Windows Glazed
without Top Lights (Schedule Item No. 305)

each

each

each

Top tower bolts 150 mm long


Bottom tower bolts 150 mm long
Parliament hinges
Same for all such windows
175 Windows Panelled (Schedule Item No. 306)

each

each

each

cum

0.039

sqm

0.720

cum

0.043

sqm

0.840

cum

0.051

sqm

0.960

cum

0.059

sqm

1.200

cum

0.081

sqm

1.440

A
i

Single Shutter
600 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

LS

LS

Sundries inclusive of hold fasts and wind


appliances (Vide standard specification)
ii

Total for each window


700 x 1200 mm
**Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)

B
i

Total for each window


Double Shutter
800 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)

ii

Total for each window


1000 x 12000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind appliances
(Vide standard specification)

iii

Total for each window


1200 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind appliances
(Vide standard specification)

Total for each window


*Note : Average rate
scantlings.

for

respective

size

785

BLD-CSTN

Index-code

S No Description
1

iv

900 x 1200 mm
**Teak wood
Labour, wrought and putup in position frame &
shutters

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.056

sqm

1.080

cum

0.036

sqm

0.070

sqm

0.720

cum

0.052

sqm

0.100

sqm

1.080

cum

0.077

sqm

0.120

sqm

1.440

cum

0.094

sqm

0.150

sqm

1.800

each

each

each

each

each

Sundries inclusive of hold fasts and wind appliances


(Vide standard specification)

Total for each window


**Note : Average rate for
scantlings and rough planks.

respective

size

176 Windows Panelled & Glazed (Schedule Item

No. 307)

BLD-CSTN-11-22

Single Shutter
600 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances (Vide standard specification)

B
i

Total for each window


Double Shutter
900 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)

ii

Total for each window


1200 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)

Total for each window


1500 x 1200 mm (3 Pannels)
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances (Vide standard specification)
Total for each window

**Note : Average rate for respective size scantlings and


rough planks.
177 Furniture for Windows Panelled : Single Leaf with
half Shutters (Schedule Item No. 308)

Cabin hooks and eyes 200 mm long


Butt hinges 75 mm size
Top tower bolts 150 mm long
Bottom bolts 150 mm long
Same for all such windows
178 Furniture for Windows Panelled : Double Leaf
with half Shutters (Schedule Item No. 309)

BLD-CSTN-11-23

Cabin hooks and eyes 200 mm long

786

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

each

each

each

600 x 1200 mm (half Shutters)


*Teak wood

cum

0.034

Labour, wrought and putup in position frame & shutters

sqm

0.720

Sundries inclusive of all furniture and fitting in


accordance with relevant standard specification

LS

Butt hinges 75 mm size


Top tower bolts 150 mm long
Bottom bolts 150 mm long
Same for all such windows
179 Teak Wood Windows - Ledged Braced and

Planked (Schedule Item No. 310)

BLD-CSTN-11-24

ii

Total for each window


800 x 1200 mm (half Shutters)
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of all furniture and fitting in
accordance with relevant standard specification

iii

Total for each window


900 x 1200 mm (half Shutters)
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of all furniture and fitting in
accordance with relevant standard specification

iv

cum

0.048

sqm

0.960

LS

cum

0.052

sqm

1.080

LS

Total for each window


1000 x 1200 mm (half Shutters)
*Teak wood

cum

0.052

Labour, wrought and putup in position frame & shutters

sqm

1.200

Sundries inclusive of all furniture and fitting in


accordance with relevant standard specification

LS

Total for each window


*Note : Average rate for respective size scantlings
and rough planks.
180 Ventilators Glazed - Fixed Double Frame and

with Wire Netting (Schedule Item No. 312)

BLD-CSTN-11-25

800 x 500 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position
Sundries inclusive of putty brads and iron hold fasts
where such are necessary say in 30 cm wall.

ii

Total for each Ventilator


1000 x 500 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position
Sundries inclusive of putty brads and iron hold fasts
where such are necessary say in 30 cm wall.

iii

Total for each Ventilator


1200 x 600 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position

cum

0.012

sqm

0.240

sqm

0.190

sqm

0.400

LS

cum

0.014

sqm

0.310

sqm

0.240

sqm

0.500

LS

cum

0.018

sqm

0.480

sqm

0.290

sqm

0.720

787

BLD-CSTN

Index-code

S No Description
1

Sundries inclusive of putty brads and iron hold


fasts where such are necessary say in 30 cm
wall.

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

LS

Total for each Ventilator


*Note : Average rate for respective size scantlings

788

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

cum

0.021

sqm

0.190

sqm

0.400

181 Swing Ventilators - Glazed (Schedule Item No.

313)

BLD-CSTN-11-26

800 x 500 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres
brass ring iron cleats and window card - vide
relevant standard specifications.

ii

Total for each Ventilator


1000 x 500 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres
brass ring iron cleats and window card - vide
relevant standard specifications.

iii

Total for each Ventilator


1200 x 600 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres
brass ring iron cleats and window card - vide
relevant standard specifications.

LS

cum

0.025

sqm

0.024

sqm

0.500

LS

cum

0.030

sqm

0.390

sqm

0.720

LS

Total for each Ventilator


*Note : Average rate for respective size scantlings
and rough planks.
Aluminium Fixed Glazing
182 Supply and fixing of aluminimum fixed glazing as per
drawing using standard powder coated/ anodised
aluminimum section of 101.4 x 44.45 x 3.18 mm thick
fitted with 6.0mm thick / 4.0 mm thick plain glass
glazing fitted with suitable Aluminimum glazing clips
and aproved brand silicon sealant including cost and
conveyance of all materials labour charges for
manufacturing fixing in position using wooden blocks
and sheet metal screw etc. to complete for finished item
of work as approved by Engineer-in-charge

BLD-CSTN-11-27

Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING

B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator

day

0.947

day

1.158

day

0.105

Power Drill - Hand Operated - Operator


Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges

day

0.211

day

0.632

Hrs

0.842

Power Drill - Hand Operated - Hire Charges

Hrs

1.684

789

BLD-CSTN

Index-code

S No Description
1

Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Nos

0.211

Unit

1%

Aluminimum Partition partly glazed


183 Supply and fixing of aluminimum Partition partly

glazed as per drawing using standard powder


coated/ anodised aluminimum section of 101.4 x
44.45 x 3.18 mm thick fitted with 12.0mm thick
Particle Boards - prelaminated up to 2.1 M height
and balance height provided with 5.0 mm thick
plain glass glazing fitted with suitable
Aluminimum glazing clips and aproved brand
silicon sealant including cost and conveyance of
all materials labour charges for manufacturing
fixing in position using wooden blocks and sheet
metal screw etc. to complete for finished item of
work as approved by Engineer-in-charge

BLD-CSTN-11-28

Unit - 1 sqm
A) MATERIAL REQUIREMENT

ALUMINIUM SECTION
PARTICLE BOARD - Prelaminated
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING

as per design
as per design
as per design

B) LABOUR CHARGES

BLD-CSTN-11-29

1st Class Carpenter


2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator

day

1.042

day

1.042

day

0.104

Power Drill - Hand Operated - Operator


Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges

day

0.139

day

0.347

Hrs

0.833

Power Drill - Hand Operated - Hire Charges


Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
184 Aluminium Anodised Casement windows
Unit - 1 sqm

Hrs

1.111

Nos

0.174
1%

Supply and fixing Aluminium Anodised Casement


windows as per approved drawing with aluminium
anodised sections of Series C Jindal Hollow sections
and outer frame of 8804 of size 46 x 44 mm, Shutter
frame of 8802 of size 44 mm x 46 mm and Mullion
frame of 8803 of size 59 x 38 and glazing section of
4433 with plain clear float glass 6 mm thick fixed
including supply and fixing aluminium powder coated 1
No.of casement friction stay hinges for each shutter, 1
Nos. aluminium handles of 150 mm for each shutter
and all labour charges for fixing the fixtures with
required no.of screws, bolts and nuts and including
labour charges for fixing the frame in position, fixing
shutter to frame etc. completed for finished item of work

Unit - 1 sqm
A) MATERIAL REQUIREMENT

ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT

as per design
as per design
as per design

790

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

RUBBER BEADING

as per design

Alum.Anodised.PC Friction stay casement hinges

as per design

Alum.Anodised.PC Handles
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter

as per design
day

0.360

day

1.081

791

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Power Saw Cutter - Hand Operated - Operator

day

0.360

Power Drill - Hand Operated - Operator


Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges

day

0.360

day

1.081

Hrs

2.883

Hrs

2.883

Nos

0.360

Power Drill - Hand Operated - Hire Charges


Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminium Two/ Three Track Sliding Windows

1%

185 Supply and fixing Aluminium Anodised Two/ Three


Track Sliding Windows as per approved drawing with
aluminium anodised sections of Series C Jindal
sections and outer frame top horizontals & both
verticals of 8774 of size 62 x 29.5 mm and bottom
horizontal - two track frame of 8773 of size 62 x 29.5
mm, Shutter frame top, bottom and verticals of 8304 of
size 50 mm x 20 mm and Weather interlocking frame of
8306 of size 50 x 20 with plain clear float glass 5 mm
thick fixed including supply and fixing aluminium
handles of 100 mm for each shutter, nylon rollers
assembly and all labour charges for fixing the fixtures
with required no.of screws, bolts and nuts and including
labour charges for fixing the frame in position, fixing
shutter to frame etc. completed for finished item of work

BLD-CSTN-11-30

UNIT 1 sqm
A) MATERIAL REQUIREMENT

ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Handles

as per design
as per design
as per design
as per design
as per design

B) LABOUR CHARGES

1st Class Carpenter


2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator

day

0.347

day

1.042

day

0.347

Power Drill - Hand Operated - Operator


Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges

day

0.347

day

1.042

Hrs

2.778

Hrs

2.778

Nos

0.347

Power Drill - Hand Operated - Hire Charges


Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm

1%

792

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Aluminium Anodised Doors - Single Shutter


186 Supply and fixing Aluminium Anodised Doors - Single
Shutter as per approved drawing with aluminium
anodised sections of Jindal sections and outer frame
top horizontals & both verticals of 2408 of size 101.6 x
44.75 x 3.18 mm Shutter frame top, bottom and
verticals of 4504 of size 44.45 mm x 47.62 mm x 3.18
and Middle lock rail of 4621 of size 49.91 x 44.45 x 3
mm with plain clear float glass 5 mm thick fixed
including supply and fixing aluminium handles of 100
mm for each shutter, floor springs/ hydraulic door
closure assembly and all labour charges for fixing the
fixtures with required no.of screws, bolts and nuts and
including labour charges for fixing the frame in position,
fixing shutter to frame etc. completed for finished item
of work

BLD-CSTN-11-31

UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Handles
Hydraulic Floor Spring/ Door Closure
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
187 Removing white wash or colour wash by steel
wire brushing and/or scraping; sand papering and
preparing the wall surface smooth including
necessary repairs to scratches complete

BLD-CSTN-11-32

Details of cost for 10 sq.m


Labour :
White washer / Mason 2nd Class
Mazdoor (unskilled)
Sundries such as sand paper and scraper etc.
Scaffolding
Add for water charges @ 1 %
25% Muncipal Allowance on labour
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
188 Removing white wash or colour wash by steel
wire brushing and/or scraping; sand papering and
preparing the ceiling and/or sloping roofs surface
smooth including necessary repairs to scratches
complete

BLD-CSTN-11-33

as per design
as per design
as per design
as per design
as per design
as per design
day

0.417

day

0.833

day

0.417

day

0.417

day

1.250

Hrs

3.333

Hrs

3.333

Nos

0.417
1%

day
day

0.010
0.170

0.000
0.140

370.00
310.00

3.70
52.70

45.89

45.89
0.00
102.29
14.32
116.61
11.66

Deatailed cost for 10 sqm

793

BLD-CSTN

Index-code

S No Description
1

Rate as per above item

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

0.010
0.170

320.00
280.00

3.20
47.60

0.010

50.80

0.00

50.80

0.51
51.31
0.00
51.31
7.18
58.00
5.80

10 sqm

Add 10 % extra for ceiling / sloping roof


Cost per 10 sq.m
Cost per sq.m
189 Removing white wash or colour wash by steel
wire brushing and/or scraping; sand papering and
preparing the wall surface smooth including
necessary repairs to scratches complete for the
wall surface spoiled by smoke soot
10 sqm

BLD-CSTN-11-34
For washing the wall surface spoiled by smoke
soot with clear water before sand papering the
surface smooth and including necessary repairs
to the scratches complete
Details of cost for 10 sq.m
Labour :
Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Add for contractor's profit and overheads

day

0.080

Cost for 10 sq.m.


Cost per sq.m
190 Removing white wash or colour wash by steel

wire brushing and/or scraping; sand papering and


preparing the ceiling and/or sloping roofs surface
smooth including necessary repairs to scratches
complete for the ceiling surface spoiled by smoke
soot

BLD-CSTN-11-35

Rate as per Item No (205)

10 sqm

Extra 10% for washing the surface with clean


water on ceiling and/or sloping roofs
Cost per 10 sq.m
Cost per sq.m
191 Washing and cleaning of decorated wall surfaces

with soap, soda and water

BLD-CSTN-11-36

Details of cost for 10 sq.m


Labour :
White washer / Mason 2nd Class
Mazdoor (unskilled)
Sundries such as soap, soda, sand paper and
scaper etc
Add for water charges @ 1 %
Cost for 10 sq.m.
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 10 sqm
Cost per sq.m

day
day

0.00
0.00
0.00

192 Washing and cleaning of the old plastered ceiling

and/or sloping roofs with soap, soda and water

BLD-CSTN-11-37

Rate as per Item above


Extra 10% over
Cost per 10 sq.m
Cost per sq.m

794

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day

0.010

day

0.170

193 Washing and cleaning of oil and grease spots on

decorated wall surface by suitable chemical

BLD-CSTN-11-38

Details of cost for 10 sq.m


Labour :
White washer / Mason 2nd Class
Mazdoor (unskilled)
Sundries, such as chemical etc.
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m

795

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day

1.220

310.00

378.20

DISMANTLING & DEMOLITION


BLD-CSTN-12
BLD-CSTN-12-1

194 Demolishing

and disposal of unserviceable


materials within 100 metres lead

ii

iii

Lime concrete.
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 1cum

Unreinforced cement concrete upto 15 cm


thicknes
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 1cum

0.00

day

2.440

310.00

378.20
0.00
378.20
52.95

378.20

431.00

431.15

756.40

756.40
0.00

378.20
52.95

756.40

0.00
756.40

756.40

105.90

105.90

862.00

862.30

Unreinforced cement concrete more than 15


cm thickness
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 1cum

day

4.880

310.00

1512.80

1512.80
0.00
1512.80
211.79
1725.00

0.00

1512.80
1512.80
211.79
1724.59

195 Demolition

including stacking of serviceable


materials and disposal of unserviceable materials
within 100 metres lead

BLD-CSTN-12-2

ii

R.C.C. work
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 1cum

day

4.320

0.00

310.00

1339.20

1339.20
0.00
1339.20
187.49
1527.00

1339.20
1339.20
187.49
1526.69

Reinforced Brick work:


Details of cost for 1 cu.m.
Labour :-

796

BLD-CSTN

Index-code

S No Description
1

Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 1cum

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A
7

day

4.090

310.00

1267.90

1267.90
0.00
1267.90
177.51
1445.00

0.00

1267.90
1267.90
177.51
1445.41

196 Extra over item 20.3 for cutting steel bars in

R.C.C. of R.B. work (sectional area of R.C.C. or


R.B. Work to be measured) Details of cost for
one Sq.m. of sectional area

BLD-CSTN-12-3

Reinforced area considering 1% Labour for


cuttings 0.01 Sq.m. reinforcement
Blacksmith 2nd class
Mazdoor (Male)
Sundries
Add for water charges @ 1 %
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for 1Sqm

day
day

0.500
0.500

0.00

350.00
280.00

175.00
140.00

315.00

315.00

0.00
315.00
44.10
359.00

315.00
44.10
359.10

797

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day
day

0.100
0.200

320.00
310.00

32.00
62.00

day

0.050

415.00

20.75

197 Dismantling doors, windows and clear storey

windows, ventilators etc.; (wood or steel) shutters


including chowkhats, architraves, hold fasts and
other attachments etc., complete and stacking
them within 100 metre lead

BLD-CSTN-12-4

Not exceeding 3 sq.m. in area:


Details of cost per each
Labour :Mason, II class
Mazdoor (male)
Blacksmith II class
Sundries
Add for water charges @ 1 %
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for each

ii

0.00

114.75
0.00
114.75

114.75

16.07
131.00

16.07
130.82

114.75

Exceeding 3 sq.m. in area


Details of cost per each
Labour :Mason, II class
Mazdoor (male)
Blacksmith II class
Sundries
Add for water charges @ 1 %
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for each

day
day
day

0.130
0.270
0.070

320.00
310.00
415.00

41.60
83.70
29.05

154.35
0.00

154.35

0.00
154.35

154.35

21.61

21.61

176.00

175.96

198 Taking out doors, windows and clearestorey

window shutters (steel or wood)


stacking within 100 metres lead

BLD-CSTN-12-5

Not exceeding 3 sq.m. in area:


Details of cost per each
Labour :Carpenter II class
Mazdoor (male)
Sundries
Add for water charges @ 1 %
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Total cost for each

ii

including

day
day

0.060
0.120

415.00
310.00

24.90
37.20

62.10
0.00
62.10
8.69
71.00

0.00

62.10
62.10
8.69
70.79

Exceeding 3 sq.m. in area


Details of cost per each
Labour :Carpenter II class
Mazdoor (male)
Sundries
Add for water charges @ 1 %
Grand Total
Add 25% for MC on Labour charges
Grand Total

day
day

0.080
0.160

0.00

415.00
310.00

33.20
49.60

82.80
0.00
82.80

82.80
82.80

798

BLD-CSTN

Index-code

S No Description
1

BLC-CSTN 12-11

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

11.59
94.00

11.59
94.39

Plastic Emulsion paint-1 coat- Internal walls


Painting to new walls with 1 coat of plastic
emulsion paint of approved brand and shade after
thoroughtly brusing he surface to remove all dirt
and remains of loose powdered materials,
including cost and conveyance of all materials to
work site and all oprational, incicental, labour
charges etc. complete for finished item of work as
per SS 911 for internal walls.

lits

0.500

244.00

122.00

122.00

day
day
LS

0.210
0.490

400.00
320.00

84.00
156.80

84.00
156.80

0.00
362.80
50.79
413.59
41.36

362.80
50.79
413.59
41.36

195.20
0.00
144.00
268.80

195.2
0
144
268.8

0.00
608.00
85.12
693.12
69.31

608
85.12
693.12
69.31

0.000

D) Over head and contractor's profit on A+B+C


Rate per 10 Sqm
Rate per 1 Sqm
Plastic Emulsion paint-2 coats- Internal walls
Painting to new walls with 2 coats of plastic
emulsion paint of approved brand and shade after
thoroughtly brusing he surface to remove all dirt
and remains of loose powdered materials,
including cost and conveyance of all materials to
work site and all oprational, incicental, labour
charges etc. complete for finished item of work as
per SS 911 for internal walls.

Total cost for 10 Sqm


A) MATERIALS:
Plastic Emulsion paint ( 20 Sqm/ liters as per
British
paints(I) Ltd.
B) LABOUR
Painter - 1st Class
Painter - 2nd Class
Sudries for spraying Machine etc.,
C) Labour Allowance on B
D) Over head and contractor's profit on A+B+C
Rate per 10 Sqm
Rate per 1 Sqm
iii

Quantity

Add 14% over head charges


Total cost for each
Painting Items from Serial No: 185 to 192
item code BLD-CSTN-12-11 are deleted.

Total cost for 10 Sqm


A) MATERIALS:
Plastic Emulsion paint ( 20 Sqm/ liters as per
British paints(I) Ltd.
B) LABOUR
Painter - 1st Class
Painter - 2nd Class
Sudries for spraying Machine etc.,
C) Labour Allowance on B

II

Unit

lits

0.800

244.00

day
day
LS

0.360
0.840

400.00
320.00

0.000

Plastic Emulsion paint-1 coats- External walls


Painting to new walls with 1 coat of plastic
emulsion paint of approved brand and shade after
thoroughtly brusing he surface to remove all dirt
and remains of loose powdered materials,
including cost and conveyance of all materials to
work site and all oprational, incicental, labour
charges etc. complete for finished item of work as
per SS 911 for External walls.

Total cost for 10 Sqm

799

BLD-CSTN

Index-code

S No Description
1

A) MATERIALS:
Plastic Emulsion paint ( 20 Sqm/ liters as per
British
paints(I) Ltd.
B) LABOUR
Painter - 1st Class
Painter - 2nd Class
Mazdoor
Sudries for spraying Machine etc.,
C) Labour Allowance on B

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

lits

0.500

244.00

122.00

122

day
day
day
LS

0.150
0.350
1.500

400.00
320.00
310.00

60.00
112.00
465.00

60
112
465

0.00
637.00
89.18
726.18
72.62

637
89.18
726.18
72.62

0.000

D) Over head and contractor's profit on A+B+C


Rate per 10 Sqm
Rate per 1 Sqm

iv

Plastic Emulsion paint-2 coats- External walls


Painting to new walls with 12 coat of plastic
emulsion paint of approved brand and shade after
thoroughtly brusing he surface to remove all dirt
and remains of loose powdered materials,
including cost and conveyance of all materials to
work site and all oprational, incicental, labour
charges etc. complete for finished item of work as
per SS 911 for External walls.

Total cost for 10 Sqm


A) MATERIALS:
Plastic Emulsion paint ( 20 Sqm/ liters as per
British
paints(I) Ltd.
B) LABOUR
Painter - 1st Class
Painter - 2nd Class
Mazdoor
Sudries for spraying Machine etc.,
C) Labour Allowance on B

lits

0.800

244.00

195.20

195.2

day
day
day
LS

0.210
0.490
1.500

400.00
320.00
310.00

84.00
156.80
465.00

84
156.8
465

0.00
901.00
126.14
1027.14
102.71

705.8
98.81
804.61
80.46

0.000

D)14% Over head and contractor's profit on


A+B+C
Rate per 10 Sqm
Rate per 1 Sqm

MISCELLANEOUS BUILDING ITEMS


199 Providing and fixing aluminium step edging 'L'

BLD-CSTN-13
BLD-CSTN-13-1

shape of size 38 mm x 12 mm x 3 mm (thick) to


stairs

Details of cost for 3 metres length


Materials:
Aluminium step edging 'L' shape 38 x 12 x 3mm
(thick) = 3.00 metres with 5% wasage

3.150

day
day
day

0.090
0.250
0.250

Carriage of materials
Sundries (Wooden plugs, screws and painting
underneath of strips with bitumanistic paint, etc.,)
Labour :Carpenter II class
Mason I class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 3 m
Cost per m

800

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

3.150

day
day
day

0.090
0.250
0.250

day
day

1.000
0.100

1.310

day
day
day

0.100
0.400
0.400

1.310

200 Providing and fixing aluminium step edging 'L'

shape of size 57 mm x16 mm x 3 mm (thick) to


stairs

BLD-CSTN-13-2

Details of cost for 3 metres length


Materials:
Aluminium step edging 'L' shape 57 mm x16 mm
x 3 mm (thick) with 5% wasage
Carriage of materials
Sundries (Wooden plugs, screws and painting
underneath of strips with bitumanistic paint, etc.,)
Labour :Carpenter II class
Mason I class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 3 m
Cost per m
201 Cutting RCC steps for fixing of aluminium step

edging and make good to match the surroundings

BLD-CSTN-13-3

Details of cost for 3 metres


Cement Mortar
Labour :Mason, II Class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 3 m
Cost per m
202 Providing and fixing 25 mm bore galvanised M.S.
tube (light grade) outlet in cement mortar 1:3(1
cement: 3 fine sand) including cutting and making
good the wall

BLD-CSTN-13-4

Details of cost for 10 pipes 12.5 cm long day i.e.,


1.25 metres
Materials:
Galvanised mild steel tube (light grade) 25 mm
nominal bore 10 x 12.5 cm = 1.25 metre with
wastage of 5%
Labour :For cutting and fixing in position
Assistant fitter
Mason.
Mazdoor (male).
Sundries
Add for water charges @ 1 %
Cost for 1.25 m
Cost per m
203 Providing and fixing 1.80 metre long RCC fencing

posts with 6 mm bar nibs as per design in plate


No. 22/2/2. (earth work & concrete to be paid for
separately)

BLD-CSTN-13-5

Details of cost for 10 pipes 12.5 cm long day i.e.,


1.25 metres
Materials:
Galvanised mild steel tube (light grade) 40 mm
nominal bore 10 x 12.5 cm = 1.25 metre with
wastage of 5%
Labour :For cutting and fixing in position

801

BLD-CSTN

Index-code

S No Description
1

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

day
day

0.100
0.400

day

0.400

cum

0.336

kg

26.440

Centering and shuttering


(Details as per Annexure 'X')
(Rate as per item No.9.1.8. of Section 9 Form
work).

cum

0.336

10 mm cement plaster with cement mortar 1:2 (1


cement: 2 sand)

sqm

9.880

day
day
day

0.120
0.120
0.250

10 sqm

1.000

Assistant fitter
Mason.
Mazdoor (male).
Sundries
Add for water charges @ 1 %
Cost for 1.25 m
Cost per m
204 Providing and fixing 1.80 metre long RCC fencing
posts with 6 mm bar bibs as per design in plate
No. 22/2/2. (earth work & concrete to be paid for
separately)

BLD-CSTN-13-6

Unit

Details of cost for 10 posts, i.e., 0.336 Cu. m

(Details as per Annexure ' X ' at the end of this


item)
Materials:
Cement concrete 1:2:4 (1 cement : 2 coarse sand
:4 graded stone aggregate 12.5 mm nominal size)
(Rate as per item No.5.42.d Section Concrete
work)
M.S. reinforcement 6 mm dia bars
10 x 4 x
1.88 = 75.20 metres
10 x 9 x 0.50 =
45.00 metres./ l20.00 m 120.20 m @ 0.22
Kg/m=26.44 Kg
(Rate as per item No.5.51 Section Concrete work)

(Details as per Annexure 'X')


Carriage of R.C.C. posts
6 mm bar bibs
Sundries
Labour for fixing posts in line
Mason, 1st Class
Mason, 2nd Class
Mazdoor (Male)
Add Water charges on A @ 1%
Add Contractor's profit and overheads on 'A' + 'B'
+ 'C @ 10%
Cost for 10 posts
Cost per post
Sub Analysis :
Plastering with CM 1:3, 12 mm thick
Deduct - CM 1:3

cum

0.025

Add - Cement (720-480 x .125)

cum

30.000

Rate for 10 sqm


Rate per sqm
Annexure - 'X'
Details of quantities for RCC posts
Concrete quantity
Area of bottom A, =15+12.5/2 x 8.75+1/2 x 22/7
(6.25) = 120.31+61.38=181.69 Sq.m.

802

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Area of top A2= 10+7.5/1 x 6.25 + 1/2 x 22 x


(3.75)2/ 7= 54.69+22.10=76.79 Sq.Cm.
Av A2 = 118.12 Sq. Cm.
Volume = h/3(A, + A2 + VA,A2)
A2+A2+A, A2=0.V03766 Sq.m

803

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

kg

9.380

59.00

553.42

Volume = 1.05/3 * 0.03766 = 0.0131810 Cu.m.


=0.0132 Cu.m.
Volume
of
lower
square
=0.165x0.165x0.75 =0.0204 Cu.m

portion

Total volume = 0.0336 Cu. m


Quantity for 10 posts = 0.336 Cu.m
Quantity of centring & shuttering
1.05=0.2908 Sq.m.

0.2770*

3x0.165x0.75=0.3712
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.6992 Sq.m..
For ten posts=10 x 0.6992 = 6.992 Sq.m.
Quantity
of
surface
plaster
12.50+7.60+7.60=27.70 Cm.
xr=3.1416x5=15.71Cm./43.41Cm
1.05=0.4560 Sq.m.

area

0.434

4x0.165x0.75=0.4950
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.9882 Sq.m.
posts = 10 x 0.9882=9.88 Sq.m.

For 10

205 Supplying and fixing galvanised steel barbed wire

(IS : 278-1962 Type I) weighing 9.38 Kg per 100


metres (min.), Straining and fixing to any type of
standard, rails, straining bolts, including securing
with and provision of galvanised mild steel wire,
stapples or steel pins, etc., as directed (Posts and
struts of wood, concrete, steel, etc.) and straining
bolts shall be paid for separately).

BLD-CSTN-13-7

Details of Cost per 100 metres (day line of wire)


Materials:
Galvanised steel barbed wire IS type I weighing
9.38 Kg/100 metre
Carriage of barbed wire.
G.I. staples steel pins or binding wire
Labour :For fixing & stretching wire
Blacksmith, 1st Class
Blacksmith, 2nd Class
Mazdoor (male).
Sundries.
Add water charges @ 1 %
Cost for 100 metres day line of wire
Rate per m
Add 14% OH&CP

LS

day
day
day

25.00

0.150
0.150
0.300

285.00
260.00
215.00

42.75
39.00
64.50
7.25
731.92
7.32
1.02
8.34

or say

8.35

per

1RM

206 Broken glass coping as specified on top of walls

BLD-CSTN-13-8

In cement mortar 1:3 (1 cement: 3 sand)


Details of cost per one Sq.m.
Materials:
Broken glass.
Cement mortar 1:3(1 cement: 3 sand)
Labour :Mason (Skilled)
Mazdoor (Male)
Scaffolding etc
Add water charges @ 1 %

kg
cum

19.500
0.040

day
day

0.080
0.160

804

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Cost per Sq.metre

805

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Lit

4.100

Liters

0.41
4.51
1%

ANTE-TERMITE TREATMENT

BLD-CSTN-14

BLD-CSTN-14-1

207 Providing Antitermite treatment as per IS 6315 (Part - 2)


2001 (Pre-constructional chemical treatment measures)
along the internal & external vertical faces of the
columns, plinth beams, basement and top surface of
the basement filling below flooring bed as per the
specified procedure conforming to IS 6315 (Part-2)
2001 and other relevant approved specification duly
using Chlorpyriphos/ Lindane emulsifiable concentrate
20% with 1% concentration @ 7.5 Liters/ sqm of the
vertical surface & @ 5.0 Liters/ sqm of the horizontal
surface of the substructure to a depth of 500 mm
around columns & 300 mm deep around plinth beams,
basements & floor filling area including excavation
channel along the wall & rodding etc & cost &
conveyance of all materials to the site, cost of labour for
spraying, rodding etc complete for finished item of work
as per the approval of the Engineer-in-Charge

Unit = 10 sqm
A) Chlorpyriphos/ Lindane emulsifiable concentrate
of 20%

1 liter : 19 Parts water Therefore: 868.55 L /20


Add 12%wastage
Total Quantity
B) Add Water Charges @ 1%
C) Labour Charges

Man Mazdoor
Sprayer
D) Hire charges

day

3.0

day

0.22

Sprayer, drilling machine etc

10%

sundries & contingencies


Water charges & electricity

3%
1.50%

Add OH & CP
BASIC COST per 1 sqm
Note: CPWD - Rate Analysis per 9 Sqm

Vertical
Chloropyriphos
Earthwork excavation
Beldar
Horizontal
Chloropyriphos
Vertical
Beldar
Hire charges
Sprayer, drilling machine etc
sundries & contingencies
Water charges & electricity
Add OH & CP
ROOF SLAB
Rate of RCC
Cost of centering
ROOF BEAMS
Rate of RCC
Cost of centering

Lit
cum
Nos
Lit
Nos
Nos

5191.00
0.00
5191.00
5191.00
0.00
5191.00

HIRE CHARGES FOR CENTERING &SCAFFOLDING -UNSUPPORTED HEIGHT UPTO 3.66M CASUA
BALLIES,BAMBOOS,WOODEN REAPERS.RUNNERS,WOODEN POSTS, WALL PLATES

806

BLD-CSTN

Index-code

S No Description
1

Unit

Quantity

Rate Rs.

Amount
Rs.with
MA

Amount
without M.A

Material
hire
charges

Labour
charges

25% ML

14% over
head
charges

Total

208 Providing traditional centering, shuttering and

BLD-CSTN-15

BLD-CSTN-15-1

UNIT
PER 1 CUM
PER 1 CUM
PER 1 CUM
PER 1 CUM
PER 1 SQM
PER 1 CUM
PER 1 CUM
PER 1 SQM
PER 1 SQM

scaffolding using Cashewrina balli props and


bracings supporting wooden brackets, wooden
wall plates, wooden runners and steel plate form
work as per the approved plan and other
accessories as per the standard trade practice
including hire charges for ballies, runners,
wooden members and cost and conveyance of all
other consumable accessories, taxes etc
complete for finished item of work
UPTO 3.66 M HEIGHT

PER 1 SQM

FOOTINGS
PEDASTALS
PLINTH BEAMS
LINTELS
CHAJJAS - SUN SHADES
COLUMNS
BEAMS
SLABS - UPTO 150 MM THICK
SLABS - ABOVE 150 MM UPTO 300 MM THICK
SLABS - ABOVE 300 MM THICK
WAFLE - (GRID SLAB )( RIB BEAMS WITH
SLAB )

277.00
315.00
1335.00
760.00
150.00
229.00
1342.00
152.00
156.00
164.00
495.00

473.00
753.00
1141.00
953.00
146.00
1338.00
1122.00
127.00
131.00
137.00
404.00

94.60
150.60
228.20
190.60
29.20
267.60
224.40
25.40
26.20
27.40
101.00

844.60
1218.60
2704.20
1903.60
325.20
1834.60
2688.40
304.40
313.20
328.40
1000.00

PER 1 SQM
PER 1 SQM
PER 1 CUM
PER 1 CUM
PER 1 CUM

PARGOLA SLABS ( ONLY RIB BEAMS )


ARCH BEAMS UPTO 1.50 M SPAN
ARCH BEAMS ABOVE 1.50 M SPAN
DOME SLAB
HELICAL STAIRCASE

347.00
1366.00
1385.00
2209.00
168.00

284.00
1116.00
1132.00
1805.00
138.00

71.00
279.00
283.00
451.25
34.50

702.00
2761.00
2800.00
4465.25
340.50

807

B. (LEAD) CONVEYANCE CHARGES FOR MATERIALS BY HEAD LOAD FOR THE YEAR: 2012-13

Sl No.

1
2
3

Total Distance (Total lead includes initial


lead)

Total lead up to 50m (Covered by item


rate)
Total lead up to 100m
Total lead up to 150m

Earth / Sand
/Gravel
PCC
Murrum/
slab/Shahaba
lime/
Cement/Rein
d slab/CC
Surki/size
forement
block/BS
stone/cut
steel/ Rs /
slab/
stone/Rubbl
Tonne
Laterite/wood
e/Coarse
/ Rs/Cum
aggregate/
Rs / cum

intial lead
45.60
91.20

intial lead
26.60
53.20

intial lead
58.00
116.10

B. (LEAD) CONVEYANCE CHARGES FOR MACHINERY PER KILOMETER FOR TRANSPORTING MATERIALS BY
TIPPERS AND TRUCKS EXCLUDING LOADING, UNLOADING AND IDLE HIRE CHARGES OF MACHINERY FOR THE
YEAR: 2012-13
( No loading and unloading charges allowed for machinery loading and unloading )
90

Sl No.

Distance

Murrum/
Lime/
Surki/ per
cu.meter

1
1
2
3
4
5

2
Lead up to 1 km
Lead up to 2 km
Lead up to 3 km
Lead up to 4 km
Lead up to 5 km

for Every km beyond 5 km up to 30 km

(Lead)
(Lead)
charges for charges for
trucks and
trucks and
(Lead)
(Lead)
tippers for
tippers per charges for
charges
Cement/
cu.meter for trucks and for trucks
Steel/ RCC PCC slabs/ tippers per
and
poles/ AC & Shahabad cu.meter for tippers for
Stones/
Bricks /
GI sheets/ slabs/ CC & water/ 1000
Coarse
Laterite
litres
1000
nos
Packed
aggregate
blocks/
per cu.meter materials/ton
Wood/ cum
ne

(Lead)
(Lead)
charges for charges for
trucks and
trucks and
tippers for
tippers for
Earth / Sand Rubble/Size
/Gravel /
stones/ Cut

1
2
3
4
5

3
30.00
42.00
56.00
68.00
80.00

4
28.90
40.40
56.00
68.00
80.00

5
18.00
25.30
35.00
42.50
50.00

6
42.40
59.40
82.40
100.00
117.70

7
17.80
24.90
33.20
40.30
47.40

8
48.10
67.30
89.80
109.00
128.30

30

12.00

12.00

7.50

17.60

7.10

19.20

14.70

5.90

16.00

for Every km beyond 30 km


10000
10.00
10.00
6.30
Note: The lead and lift charges are inclusive of 14% Contractor Profit and Over head charges

C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS


( idle hire charges of trucks are not added )

Sl No.

Description of item

Earth / Sand
/Gravel
Murrum/ /
Surki/ Rs /
cum

Loading

15.20

Rubble/ size
stone/ cut
stone/
Coarse
aggregate,
Lime in
Rs/cum

cement in
Rs/tonne

steel in
Rs./tonne

brick work
Rs/1000

30.30

50.10

60.00

41.70

60.00

41.70

Unloading
7.60
15.15
50.10
Note: The lead and lift charges are inclusive of 14% Contractor Profit and Over head charges

D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS


( including hire charges of trucks )

Sl No.

Description of item

Earth / Sand
/Gravel
Murrum/ /
Surki/ Rs /
cum

Loading

102.60

Rubble/ size
stone/ cut
stone/
Coarse
aggregate,
Lime in
Rs/cum

cement in
Rs/tonne

steel in
Rs./tonne

brick work
Rs/1000

117.80

146.30

156.20

200.50

156.20

200.50

Unloading
36.60
58.90
146.30
Note: The lead and lift charges are inclusive of 14% Contractor Profit and Over head charges

E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS


( including hire charges of trucks )

Sl No.

Description of item

Earth / Sand
/Gravel
Murrum/ /
Surki/ Rs /
cum

Loading

50.50

Rubble/ size
stone/ cut
stone/
Coarse
aggregate,
Lime in
Rs/cum
101.10

Unloading
15.20
15.20
Note: The lead and lift charges are inclusive of 14% Contractor Profit and Over head charges

F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD

Sl No.

Total ligt (Total lift includes intial lift)

Total lift up to 3m (covered by Item rate)

Earth / Sand
/Gravel
PCC
Murrum/
slab/Shahaba
lime/
Cement/Rein
d slab/CC
Surki/size
forement
block/BS
stone/cut
steel/ Rs /
slab/
stone/Rubbl
Tonne
Laterite/wood
e/Coarse
/ Rs/Cum
aggregate/
Rs / cum

Initial lift

Initial lift

Initial lift

For every 1.00 lift beyond initial lift of 3


5.30
3.80
7.10
meters.
Note: The lead and lift charges are inclusive of 14% Contractor Profit and Over head charges

HIRE CHARGES FOR CENTERING &SCAFFOLDING -UNSUPPORTED HEIGHT UPTO 3.66M CASUARINA
BALLIES,BAMBOOS,WOODEN REAPERS.RUNNERS,WOODEN POSTS, WALL PLATES

BLD-CSTN-15
208

BLD-CSTN-15-1

Providing traditional centering, shuttering and


scaffolding using Cashewrina balli props and
bracings
supporting
wooden
brackets,
wooden wall plates, wooden runners and steel
plate form work as per the approved plan and
other accessories as per the standard trade
practice including hire charges for ballies,
runners, wooden members and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work
UPTO 3.66 M HEIGHT

UNIT

,Causorina
ballies,
rafters,Runners,
with
CENTERING PLATES ETC.,

GF
Material

wooden
hire
STEEL charges

Labour
charges

20% ML

Total

0.00

PER 1 CUM
PER 1 CUM
PER 1 CUM
PER 1 CUM
PER 1 SQM
PER 1 CUM
PER 1 CUM
PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 CUM
PER 1 CUM
PER 1 CUM
PER 1 SQM

277.00
FOOTINGS
61.00
BED BLOCKS, BANDS
315.00
PEDASTALS
1335.00
PLINTH BEAMS
LINTELS
760.00
CHAJJAS - SUN SHADES
150.00
COLUMNS
229.00
BEAMS
1342.00
SLABS - UPTO 150 MM THICK
152.00
SLABS - ABOVE 150 MM UPTO 300 MM
156.00
THICK
SLABS - ABOVE 300 MM THICK
164.00
WAFLE - (GRID SLAB )( RIB BEAMS WITH
553.00
SLAB
)
PARGOLA
SLABS ( ONLY RIB BEAMS )
387.00
ARCH BEAMS UPTO 1.50 M SPAN
1526.00
ARCH BEAMS ABOVE 1.50 M SPAN
1547.00
DOME SLAB
2467.00
HELICAL STAIRCASE
188.00

473.00
244.00
753.00
1141.00
953.00
146.00
1338.00
1122.00
127.00
131.00
137.00
462.00
324.00
1276.00
1294.00
2063.00
157.00

SHEAR WALLS,RCC WALLS,WATER TANK


WALLS

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

750.00
305.00
1068.00
2476.00
1713.00
296.00
1567.00
2464.00
279.00
287.00
301.00
1015.00
711.00
2802.00
2841.00
4530.00
345.00

HIRE CHARGES FOR CENTERING &SCAFFOLDING -UNSUPPORTED HEIGHT UPTO7.32M STEEL


SCAFFOLDING PIPES

, JACK PROPS,WALLERS,
PLATES,BRACKETS,STEEL
CENTERING PLATES ETC.,
PER 1 CUM
PER 1 SQM
PER 1 CUM
PER 1 CUM
PER 1 SQM

LINTELS
CHAJJAS - SUN SHADES
COLUMNS
BEAMS
SLABS - UPTO 150 MM THICK

0.00

FOOT

1519.00
300.00
229.00
2300.00
258.00

1064.00
163.00
1494.00
1253.00
141.00

0.00
0.00
0.00
0.00
0.00
0.00

2583.00
463.00
1723.00
3553.00
399.00

PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 CUM
PER 1 CUM
PER 1 CUM
PER 1 SQM

SLABS - ABOVE 150 MM UPTO 300 MM


268.00
THICK
SLABS - ABOVE 300 MM THICK
280.00
WAFLE - (GRID SLAB )( RIB BEAMS WITH
947.00
SLAB
)
PARGOLA
SLABS ( ONLY RIB BEAMS )
664.00
ARCH BEAMS UPTO 1.50 M SPAN
2615.00
ARCH BEAMS ABOVE 1.50 M SPAN
2651.00
DOME SLAB
4933.00
HELICAL STAIRCASE
376.00
SHEAR WALLS,RCC WALLS,WATER TANK
194.00
WALLS

146.00
153.00
516.00
362.00
1424.00
1445.00
2303.00
176.00
272.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

414.00
433.00
1463.00
1026.00
4039.00
4096.00
7236.00
552.00
466.00

HIRE CHARGES FOR SCAFFOLDING CHARGES FOR BRICK MASONRY/STONE MASONRY/WALL


PUTTY/TEXTURE PAINTS ETC., 1SQM
0

PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 SQM

1ST FLOOR
2ND FLOOR
3RD FLOOR
4TH FLOOR
5TH FLOOR

PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 SQM

1ST FLOOR
2ND FLOOR
3RD FLOOR
4TH FLOOR
5TH FLOOR

9.93
9.93
9.93
9.93
9.93

61.83
87.78
113.74
139.69
165.64

0.00
0.00
0.00
0.00
0.00

71.76
97.71
123.67
149.62
175.57

HIRE CHARGE SCAFFOLDING CHARGES FOR PLASTERING TO WALLS 1SQM

0.99
0.99
0.99
0.99
0.99

6.18
8.78
11.37
13.97
16.56

0.00
0.00
0.00
0.00
0.00

7.17
9.77
12.36
14.96
17.55

HIRE CHARGES SCAFFOLDING CHARGES FOR CEILING PLASTERING 1SQM

PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 SQM
PER 1 SQM

1ST FLOOR
2ND FLOOR
3RD FLOOR
4TH FLOOR
5TH FLOOR

2.37
2.37
2.37
2.37
2.37

12.55
17.64
22.73
27.82
32.91

0.00
0.00
0.00
0.00
0.00

14.92
20.01
25.10
30.19
35.28

GHT UPTO 3.66M CASUARINA


POSTS, WALL PLATES

FF
Labour
charges

20% ML

SF

Total

Labour
charges

508.00
356.00
1404.00
1423.00
2269.00
173.00

HEIGHT UPTO7.32M STEEL

Total

Labour
charges

1048.00
161.00
1472.00
1234.00
140.00
144.00
151.00

20% ML

TF

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

1808.00
311.00
1701.00
2576.00
292.00
300.00
315.00
1061.00
743.00
2930.00
2970.00
4736.00
361.00

1084.00
175.00
1606.00
1346.00
152.00
157.00
164.00
554.00
389.00
1531.00
1553.00
2476.00
188.00

20% ML

4th F

Total

Labour
charges

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

1844.00
325.00
1835.00
2688.00
304.00
313.00
328.00
1107.00
776.00
3057.00
3100.00
4943.00
376.00

1174.00
190.00
1739.00
1459.00
165.00
170.00
178.00
601.00
421.00
1659.00
1682.00
2682.00
204.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

1934.00
340.00
1968.00
2801.00
317.00
326.00
342.00
1154.00
808.00
3185.00
3229.00
5149.00
392.00

1264.00
204.00
1873.00
1571.00
178.00
183.00
192.00
647.00
454.00
1786.00
1812.00
2888.00
220.00

RY/STONE MASONRY/WALL

TO WALLS 1SQM

ASTERING 1SQM

4th F

20% ML

Total

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

2024.00
354.00
2102.00
2913.00
330.00
339.00
356.00
1200.00
841.00
3312.00
3359.00
5355.00
408.00

DATAS FOR LAYING OF PIPE LINES IN R&R COLONIES

S No

Description

Unit

Muncipal Allowance

20%

Quantity

Rate Rs.

Amount
Amount
Rs.with MA without M.A

EARTH WORK EXCAVATION


Earth work excavation and depositing on bank with initial
lead of 10m and initial lift of 2m in Loamy & Clayey Soils
like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20B) including shoring, strutting, sheeting, planking and
dewatering including cost of hire charges of T & P, labour
charges etc., complete for finished item of work for
Foundation of Building.(APSS No. 308)
Taking out put = 10 Cum
Light Mazdoor

Nos

3.64

Add 75% for excavation of foundation of building

cum

Add 25% Muncipal allowance

0.20

1879.15

295.00

1073.80

1073.80

805.350

805.35

805.35

1879.15

1879.15

375.83
2254.98

Add 14% over heads

cum

2254.98

0.14

315.70

Seigniorage charges

Cum

10.00

0.00

0.00

Rate per 10 cum


Rate per 1 cum

2570.68
257.00

2 Filling with useful available excavated earth (excluding


rock) in trenches, sides of foundations and basement with
initial lead in layers not exceeding 15cm thick,
consolidating each deposited layer by watering and
ramming including all operational, incidental, labour
charges, hire charges of T & P etc., complete for finished
item of work. (APSS NO. 309 & 310)
Unit =6Cum
Light Mazdoor
Add 25% Muncipal allowance

Nos
0.20

0.31
91.45

295.00

91.45
18.29
109.74

Add 14% over heads

109.74
Rate per 6cum

0.14
Total

Rate per 1Cum


3 Filling with Sand Cushion under footings with initial lead
in layers not exceeding 15cm thick, consolidating each
deposited layer by watering and ramming including all
operational & incidental charges, labour charges,
seignorage charges, hire charges of T & P etc., complete
for finished item of work. (APSS NO. 309 & 310)
unit =1Cum

15.36
125.10
20.85

Takeing out put = Cum


a) Labour
mate

day

Mazdoor (Un Skilled)

day

0.31

b) Material
Cost of Sand

cum

Water

KL

Muncipal Allowance

0.20

91.45

cum

251.67

Add 14% over heads


Rate per cum

1
0.1

295.00

91.45

134.23

134.23

77.00

7.70

0.14

233.38
18.29
251.67
35.23

Total

286.90

263.08
0.00
2142.23
214.00

S No
4

Description

Amount
Amount
Rs.with MA without M.A

Unit

Quantity

Rate Rs.

Kg

341.00

4848.76

1653.43

1653.43

cum

0.90

1687.27

1518.55

1518.55

cum

0.45

134.23

60.40

60.40

cum

0.90

cum

0.45

kl

1.20

77.00

92.40

92.40

hour

1.00

328.60

328.60

328.60

day

0.10

385.00

38.50

38.50

day

1.39

295.00

410.05

410.05

4101.92

4101.92

0.20

448.55

Plain Cement concrete (M 35) Nominal Mix using 20mm metal


using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges

89.71
4191.63

4101.92

586.83

574.27

4778.00

4676.19

Laying reinforced Cement Concrete NP2 Pipes on First class

5 bedding of granular bedding


100 mm dia
unit = metre
Taking in out put= RM

Cost of NP2 Pipe

lead = 30km
Lead charges for First 5 KM Distance
Lead charges for balance Distance

RM

Lowering the RCC plain ended carefully in to the trench

km
km
RM

1
25
4

Add 25% for MC on Labour charges

0.20

72.00

154.00

154.00

4
0.13

4.00
3.25
72

18

14.40

Rate per 1 metre


6

247.65

Plain Cement concrete (1:4:8) using 40 mm metal with hand


mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Add 25% for MC on Labour charges
Grand Total
Add 14% over head charges
Rate per Cum

kg

162.00

4848.76

785.50

785.50

cum

0.90

1167.27

1050.55

1050.55

cum

0.45

134.23

60.40

60.40

cum

0.90

cum

0.45

kl

1.20

77.00

92.40

92.40

day

0.10

385.00

38.50

38.50

day

2.36

295.00

0.20

734.70

696.20

696.20

2723.55

2723.55

146.94
2870.49

2723.55

401.87

381.30

3272.00

3104.84

S No

Description

Amount
Amount
Rs.with MA without M.A

Unit

Quantity

Rate Rs.

day
%

2.86
0.2

146.00
417.56
A=

417.56
83.51
83.51

hour

0.27

540.00

145.80

B=

145.80

Providing BT Patch work using 20 mm HBG metal with


required quantity of 10-12 mm size HBG Machine crushed
key chips and 80/100 grade Bitumen including removal
material in the pot holes trimming the edges to provide
vertical faces , cleaning applying tack coat , filling the pot
holes compacting with power Road Roller of 8 to 10
Tonnes finishing and blinding the surface using stone dust/
sand , including cot of all materials T&P , and labour
charges for all operations etc. at site of complete
Unit = cum
Taking output = 1 cum
(A) Labour
Mazdoor
Municipal Area Allowance
TOTAL
(B) Machinery
Finish rolling with 6-8 tonne
smooth wheeled tandem roller.
TOTAL
(C) Material
Bitumen
(ii) Aggregate
20 - 25 mm IRC HBG m/c chips
9.5 to 11.2 mm IRC HBG m/c chips
TOTAL
(A + B +C)
Rate per cum
Rate per cum

M.T

0.072

34058.35

2452.20

cum
cum

1.20
0.13

1635.27
1257.27
C=

1962.33
163.45
4577.97
4807.29
4807.29
4807.00

Rate per cum


Rate per cum

Potrebbero piacerti anche