Sei sulla pagina 1di 43

SAVAN DKLS WATER SUPPLY CO.

LTD

2013

SECTION A: GENERAL
1.0
2.0

SCOPE OF WORKS
PROGRAMME AND PROGRESS OF WORKS

A.1
A.1

3.0

CONSTRUCTION SITE

A.1

4.0

PREPARATION OF THE WORK AREA

A.2

4.1

Detection of Existing Utilities and Services

A.2

4.2

Isolating of Valve

A.2

4.3

Trench Excavation / Cutting of Metalled Premix Road

A.3

4.4

Dewatering of Trench

A.3

5.0

REINSTATEMENT WORK

A.4

5.1

Normal Earth Shoulder

A.4

5.2

Shoulder with hard standing / tiles

A.4

5.3

Metalled Premix Road

A.5

6.0

SETTING OUT AND RE-SURVEY

A.6

7.0

PROVISION OF SURVEY INSTRUMENTS AND CHAINMEN

A.6

8.0

ORDERING MATERIALS

A.7

9.0

MATERIALS AND WORKMANSHIP

A.7

10.0

SUPPLY OF MATERIALS BY SAVAN DKLS

A.8

11.0

REQUIREMENTS OF OTHER CONTRACTOR

A.8

12.0

PUBLIC UTILITIES AND OTHER SERVICE

A.9

13.0

PUBLIC AND PRIVATE ROAD

A.10

14.0

WORK THROUGH PRIVATE LAND

A.11

15.0

CONTRACTORS FACILITIES

A.11

16.0

SAFETY AND SECURITY MEASURES

A.11

17.0

DAMAGES TO EXISTING WORK

A.12

18.0

PROTECTION OF WORKS

A.12

19.0

SITE DRAINAGE

A.12

20.0

PIPE DUMPS

A.13

21.0

FIRST AID BOX

A.13

22.0

CONTRACTORS PLANTS

A.13

23.0

CLEARING UP AND REINSTATEMENT ON COMPLETION

A.14

24.0

S.O.S APPROVAL

A.14

25.0

DAYWORK

A.14

26.0

COVERING UP OF WORK

A.15

27.0

A.15

29.0

SIGNBOARDS
CLAUSES RELATING TO WORK OR MATERIALS NOT REQUIRED IN THE
WORKS
EMPLOYEES SOCIAL SECURITY ACT

30.0

DELAYS AND STOPPAGES

A.16

31.0
32.0

WARRANTY
STATUTORY HOLIDAYS

A.16
A.17

28.0

A.16
A.16

SAVAN DKLS WATER SUPPLY CO. LTD

33.0
34.0
35.0
36.0

CONTRACT DOCUMENTS
EXPLANATION OF THE DOCUMENTS
CONTRACTOR'S AGENT
PROJECT DIARY

2013

A.17
A.18
A.18
A.19

37.0 CO-ORDINATION MEETINGS AND PROGRESS REPORTS


38.0 TRANSPORT
39.0 ASSISTANCE TO SUPERINTENDING OFFICER'S REPRESENTATIVE

A.19
A.20
A.20

40.0
41.0
42.0
43.0

A.21
A.21
A.21
A.21

SUPERINTENDING OFFICER'S APPROVAL


TEMPORARY ACCESS ROAD
WORK OUTSIDE NORMAL HOURS
FORMS FOR MONTHLY STATEMENTS

44.0 TEMPORARY CONNECTIONS DURING CONTRACT PERIOD


45.0 OBVIOUS WORK
46.0 STATUTORY REGULATIONS AND APPROVAL

A.22
A.22
A.23

47.0
48.0
49.0
50.0

A.23
A.24
A.24
A.24

NOISE
DELAYED TAKING OVER
FIRE
SUPERVISION

51.0 PIPE BALANCE AND EXCESS MATERIALS


52.0 RIGHT TO OPERATE UNSATISFACTORY EQUIPMENT

A.24
A.25

53.0 SUPPLY OF CLEAR WATER FOR TESTING AND COMMISSIONING


54.0 TRAINING OF OPERATORS
55.0
LABELS

A.25
A.25
A.25

56.0 APPLICATIONS FOR PAYMENT


57.0 REQUIREMENT OF CONSTRUCTION INDUSTRY DEVELOPMENT BOARD

A.26
A.27

58.0 ENVIRONMENTAL POLICY


58.1
General Policy

A.27
A.27

58.2

Compliance with Environmental Legislation

A.27

58.3

Environmental Co-ordination

A.28

58.4
58.5

Environmental Audit
Environmental Training

A.28
A.28

58.6

Close-Out

A.29

59.0 SURVEY WORK


59.1
Scope of Services

A.29
A.30

59.2 Accuracy of Survey

A.31

59.3

A.32

Survey Plan and Scales

60.0 AS-BUILT DRAWINGS


61.0 MANUFACTURERS WORKS INSPECTION AND TESTING

A.32
A.33

SAVAN DKLS WATER SUPPLY CO. LTD

2013

SECTION B: EXCAVATION
1.0

GENERAL

B.1

2.0

SITE CLEARING

B.1

3.0

EXCAVATION GENERALLY

B.1

4.0

EXCAVATION FOR PIPE TRENCHES

B.2

5.0

ROCK EXCAVATION

B.3

6.0

USE OF EXPLOSIVES

B.4

7.0

WEATHERED ROCK EXCAVATION

B.4

8.0

UNAUTHORIZED EXCESSIVE EXCAVATION

B.4

9.0

ADDITIONAL EXCAVATION ORDERED BY THE S.O.

B.5

10.0

TIMBER LEFT IN EXCAVATION

B.5

11.0

EXCAVATION IN ROADS

B.5

12.0

CROSSING WATER-COURSES ETC.

B.6

13.0

INSPECTION

B.6

14.0

BACKFILLING OF EXCAVATIONS OTHER THAN PIPE TRENCHES

B.6

15.0

BACKFILLING OF PIPE TRENCHES

B.6

16.0

APPROVED FILL MATERIAL

B.7

17.0

ROAD REINSTATEMENT

B.7

18.0

REMOVAL OF SURPLUS

B.8

19.0

EMBANKMENTS

B.8

20.0

SOILING AND TURFING

B.9

21.0

LEVELS TO BE RECORDED

B.9

22.0

CARE OF EXISTING SERVICES

B.9

23.0

HEDGES, FENCES AND WALLS

B.10

24.0

MACKINTOSH PROBES

B.11

25.0

UTILITY SURVEYING AND MAPPING

B.11

26.0

MEASUREMENT OF GENERAL EXCAVATION

B.11

27.0

MEASUREMENT OF TRENCH EXCAVATION

B.12

28.0

MEASUREMENT OF FILLING

B.14

29.0

PAYMENT FOR TRENCH EXCAVATION AND RESTORATION

B.14

30.0

MEASUREMENT OF TOP SOILING AND TURFING

B.15

31.0

PAYMENT FOR TURFING

B.15

32.0

PAYMENT OF FEES TO AUTHORITIES

B.15

SAVAN DKLS WATER SUPPLY CO. LTD

2013

A- GENERAL
1.0

SCOPE OF WORKS
The Works covered in this Contract comprise the provision by the
Contractor at his own risk and cost which comprise all materials,
scaffoldings, tools, plants, labour, transports, water, power, profi t and
attendance, overhead and everything else necessary for the construction
and completion of the Works to the entire approval of the Superintending
Officer hereinafter referred to as the S.O.
The Conditions of Contract for the Works , shall be read in conjunction
with this Specifi cation. If the Tenderer considers that any of the clauses
in the Conditions of Contract involves additional expenses not covered
elsewhere, the Tenderer shall allow for monetary value for such clauses in
his Tender, otherwise, it will be deemed to have been included.

2.0

PROGRAMME AND PROGRESS OF WORKS


Within 30 days after the acceptance of tender, the Contractor shall submit
to the S.O. for his approval three (3) copies of a detailed programme in
Microsoft Project format showing the time order, procedure and method
in which the Contractor propose to carry out the Works, and shall
whenever required by the S.O. or his representative, furnish for his
information particulars in writing of the Contractors arrangement for carrying
out such work and other construction plants and temporary works if any,
which the Contractor intends to supply, use or construct as the case may
be. The submission to and approval by the S.O. or his representative of
such programme or the furnishing of such particulars shall not relieve the
Contractor of any of his duties or responsibilities under this Contract.

If at any time it should appear to the S.O. that the actual progress of the
Works does not conform to the approved programme referred to herein,
the Contractor shall produce, at the request of the S.O. a revised
programme showing the modifications to the previously approved
programme necessary to ensure the completion of the whole Works within
the time set for completion.

3.0

CONSTRUCTION SITE
The location of the Site is shown on the Drawings. The Contractor shall be
deemed to have inspected the Site before tendering and to take into
account all the conditions there, such as means of access, facilities for
transport, storage and movement of plants and materials, and any other
contingencies liable to affect his tender price, as no claim for extra payment
in this connection will be entertained.
The Contractor shall be liable for and shall indemnify SAVAN DKLS against
any damage, expense, liability, loss, claim or proceedings whatsoever
whether arising at common l aw or by statute in respe ct of personnel
i nj ury to or de ath of any person whomsoever or to any property arising
out of or in the course of or by reason of the visit to the Site.

SAVAN DKLS WATER SUPPLY CO. LTD

4.0

PREPARATION OF THE WORK AREA

4.1

Detection of Existing Utilities and Services

2013

The Contractor shall investigate, and have full knowledge of the position of
existing utilities and underground services such as drains, pipes, electric
cables, culverts, etc. He shall take all necessary precaution as part of his
work. He shall undertake the following:-

4.2

i.

Detailed utility detection using radio and or ultrasonic machine. The


drawings must be submitted to the S.O in 2 set in A1 size, coloured to
differentiate the type of services. The type of utility, size and depth shall
be clearly indicated.

ii.

Where necessary, trial pits and exploration trenches to ascertain the


exact portions of these services shall be excavated, well ahead of
pipe repair / maintenance excavation, in places where they are known
or thought to be and elsewhere and these shall be backfilled with
approved materials.

iii.

All damages to the existing services shall be made good to the


satisfaction of SAVAN-DKLS and the relevant authorities.

Isolation of Valves
Before any excavation, SAVAN-DKLS representative and the Contractor shall
jointly locate all valves & pipelines in the area.
1. Ascertain the type, size and estimated length of pipe that may be
affected due to the excavation and repair works. The information will
enable the maintenance team to mobilize the appropriate tools, spare
parts, etc. The information will be important in estimating the volume of
water loss due to pipe bursts or pipe leaks .
2. Sketch the location plan and the distribution network layout in a Record
Form for updating and record purposes.
3. SAVAN-DKLS representative shall identify all isolating and scour valves
affected by the pipe to be repaired as well as valves located in the
vicinity. It is important to ensure that water scouring will not result in
flooding of the area, in particular the area for excavation.
Prior to excavation, shut the isolating valves as identified. As a direct
effect, the pipeline pressure will drop and hence, water will stop. When
this has been confirmed, the scour valves may be opened to discharge
the remaining water from the main prior to excavation work.
4. However, if water pressure neither drops nor leakage subsides after
closing of the identifi ed valve, then SAVAN-DKLS representative and
his team may need to locate any possible unknown inter-connections.

SAVAN DKLS WATER SUPPLY CO. LTD

2013

5. When the inter-connections have been identifi ed, the isolating valve
shall be shut to facilitate repair work. Update the sketch of the pipe layout
in the attached Record Form. The sketch shall then be submitted to SAVANDKLS representative upon completion.

4.3

Trench Excavation / Cutting of Premix Road


The trench shall be excavated by such method as allowed by SAVANDKLS for proper maintenance and repair work.
1.

Trench excavation shall be carried out by such methods and to such


lines, dimensions and depths to allow for the proper construction of the
works.

2.

As a general guide, the approximate width of trench excavation is as per

Table1. Table1: Width of trench and road cutting based on pipe


diameter
Pipe OD with sheathing
(D) mm

< 500 mm
> 500 mm but < 750mm
> 750mm

4.4

Clear width of trench


excavation

Clear width of
premix road cut

D + 450 mm
D + 600 mm
D + 900 mm

D + 1050 mm
D + 1200 mm
D + 1500 mm

3.

Under no circumstances shall the Contractor be allowed to place


excavated materials by the road-side. Excavated materials shall be
carted away to a waiting lorry and transported to dump site to be
determined by the Contractor.

4.

In cases where the trench depth exceeds 1.5 m, sheet pile wall or
strutting of trenchs wall shall be provided to prevent any untoward
incident such as cave in from happening.

Dewatering of Trench
The Contractor shall note that certain parts of the pipeline may be laid in
ground with high water table, especially in areas adjacent to the streams, river
crossings and ponds.
1.

The Contractor shall allow cost for dewatering and keeping all the
excavations and trenches dry for the pipeline repair work to be carried in a
safe manner during the execution of the work.

2.

Dewatering shall be carried out using dewatering pump with long


hose. The dewatering pump shall have the capacity to drain a trench ( 1
m x 1 m x 1.5m ) within 5 minutes ( 70 igpm ).

SAVAN DKLS WATER SUPPLY CO. LTD

5.0

2013

REINSTATEMENT WORK.
Rei nstate me nt work for the foll owi ng types of road shoulder are
described accordingly.
1.
2.
3.

5.1

Normal earth shoulder


1.
2.
3.
4.
5.
6.

5.2

Normal earth shoulder.


Shoulder with hardstanding / tiles.
Premix road.

Excess water shall be pumped out from the trench using suitable sized
pump before any maintenance and repair work is carried out.
Under no circumstances shall soft and unsuitable materials be used as
backfill materials.
Approved backfill shall be compacted in 150 mm layers. The plate type
compactor shall be used.
After backfilling has reached approximately 100mm below the existing
ground surface, the existing top soil is shall reinstated.
The finished ground level shall be slightly higher than the original ground
level.
All surplus materials shall be removed from the site.

Shoulder with hard standing / tiles


1.
2.
3.

4.
5.

6.
7.
8.

The affected hard standing / tiles shall be cut using road cutter.
Excess water shall be pumped out from the trench using suitable sized
pump before any maintenance and repair work is carried out.
The trench will then be backfi lled with approved sand, suffi ciently
watered down and compacted in layers of 150 mm thick. Plate type
compactor shall be used.
The backfi lling of compacted sand shall be carried out to a level
suitable to receive crusher run.
300 mm thick crusher run shall be laid on top of the compacted
sand. Compaction of crusher run shall be carried out using Plate type
compactor.
Any over-break of concrete hard standing and tiles is to be cut square.
Concrete screed shall then be laid on top of the compacted crusher
run and level adjusted to suit the existing ground level.
All surface finishes shall be reinstated to their original conditions.

SAVAN DKLS WATER SUPPLY CO. LTD

5. 3

2013

Premix road

1. The affected premix road shall be cut using road cutter.


2. Excess water shall be pumped out from the trench using suitable size
pump before any maintenance and repair work is carried out.
3. After the pipe has been repaired, the trench shall then be backfilled
with sand, suffi ciently watered down and compacted in 150 mm layers.
Sand shall be laid in 150 mm layers on both sides of the pipe simultaneously
and thoroughly compacted around the pipe alternately on either side of the
pipe until it reached the base course of formation level. Compaction shall be
carried out using Plate Compactor.
4. Crusher-run is to be laid in layers of 150 mm thick. Compactions of
crusher run shall be carried out using a Plate Compactor. The crusher run
shall be reinstated to the original thickness of the road, but subject to a
minimum thickness of 300 mm.
5. Additional make-up crusher run shall then be added to the excavated
area and compacted accordingly.
6. After the whole surface of the crusher run has been compacted, the
surface shall be brushed to remove loose stones and debris.
7. A layer of bituminous tack coat shall be applied at a rate of not less
than 270 ml/m2, paying particular attention to all square cut edge and
all around manhole to be installed where applicable.
8. The premix shall be reinstated to its original thickness ranging from 60 mm
to 100 mm thick ACWC 20 depending on the Class of the road.
9. All compaction of premix shall be carried out using a Plate Compactor.
10. Make-up premix shall be added 3 days after the completion of the
work to reinstate settlement.

6.0

SETTING OUT AND RE-SURVEY


The Contractor shall be responsible for the true and proper setting out of
the Works and for the correctness of the positions, levels, dimensions and
alignment of all parts of the Works.
B e f o re t h e c o m m e n c e m e n t o f t h e Wo r k s , t h e C o n t r a c t o r s h a l l
u n d e r t a ke topographical survey of the area and forward this information
to S.O, in order for S.O. to establish the lines and level of the Works. The
Contractor shall verify the dimensions and levels shown in the Drawings
and shall notify the S.O. of any discrepancy, which may affect the
dimensions or levels of any part of the Works.

After clearing and grubbing, and before any excavation of any part of the
Site is carried out or the Works thereon begun, the Contractor shall take
and record level of any such parts, in the manner specified or as agreed
with the S.O. shall form the basis of measurement and payment. The
Contractor shall carry out to the S.Os instructions all extra surveys
required to resolve any doubts, which may arise as to the correctness of
any survey or record and the S.Os decisions shall be fi nal regarding
what shall be recorded as the correct dimensions and levels.

SAVAN DKLS WATER SUPPLY CO. LTD

2013

The levels and dimensions, which have been agreed by the S.O, shall form
the basis of measurement for the appropriate Works.

7.0

PROVISION OF SURVEY TEAM AND CHAINMEN


The Contractor shall provide and maintain for the sole use of the S.O., a
survey team complete with instruments and chainmen. All instruments
and equipment shall be in good operational condition, duly calibrated.
Thus, may call upon their services any time, to provide surveys of any site
and the surveyor shall prepare the drawings in the specified format.
Additional instruments to be provided and kept available by the
contractor are as follows:

Aluminium leveling staff 5 metres long in 1 sections with attached


bubble, 1 no.

Flexible steel tape 4 metres long on plastic case, graduated in


metres and millimeters - 1 no.

Linen tape 30 metres long in leather graduated in metres and


millimeters 1 no.

The Contractor shall provide as many full time or part-time chainmen as


may be required by the S.O.

8.0

ORDERING MATERIALS
The Contractor shall be responsible for placing his orders for all
materials and articles required to be supplied by him/Savan-DKLS
(Employer Supplied Materials) at the earliest possible date for the
completion of this Contract.
Before placing any order for materials or articles to be incorporated in the
Works, the Contractor shall submit to the S.O. for his approval, a complete
description of such items and the names of the suppliers from whom he
propose to obtain them. Where so directed, the Contractor shall submit
samples and test certifi cates for approval. The Contractor shall not place
any order without the approval of the S.O. which may be withheld until
samples have been submitted and satisfactorily tested.
The source of supply shall be approved by the S.O.
Additional testing of materials and complete pipes, fi ttings and specials
may be carried out at any time by the S.O. Any of the materials, pipes,
fittings and special not complying with this Specification shall be rejected by
the S.O.
Unless specifically provided for in the Specification or the Bill of Quantities,
the cost of any testing including the supply of materials, pipes and fittings
carried out on

SAVAN DKLS WATER SUPPLY CO. LTD

2013

SAVAN DKLS STANDARD SPECIFICATION FOR PIPE LAYING WOKS


First Edition : June 2013

samples submitted by the Contactor shall be borne by SAVAN-DKLS. If the


tests show that the materials, pipes and fittings are not in accordance with
the requirements of this Specification, the said batch of material will be
rejected. The contractor shall remove all the rejected materials out of the
site immediately. For further quality control, the S.O may require testing of
other materials, whether installed or not. The cost of testing shall be boned
by the contractor. If results show similar trend, then the material must not
be further used. The contractor must demonstrate how rectification
measure can be implemented on all installed items.

9.0

MATERIALS AND WORKMANSHIP


All materials and articles to be incorporated in the Works shall be new and
of the kind and quality described in the Contract and shall be at least
equal to the approved samples.
In all cases where materials and articles are specifi ed to comply with
Malaysian Standards or British Standards or equivalent, the Contractor
shall, if required, obtain from the manufacturers and supply the S.O. the
appropriate certificate of compliance with the Standard.
If no Standard is indicated, the relevant Malaysian Standard, British
Standard or other Standard shall apply in the order of priority as listed.

10.0

SUPPLY OF MATERIALS BY SAVAN-DKLS


If the Contractor fails for any reason to supply any materials, which the
Contractor has contracted to supply or if he fails to supply any such
materials in sufficient time to enable the Contract to be completed by the
agreed Date for Completion, then in either event SAVAN-DKLS may supply any
portion, or all of such materials.
If the Contractor fails for any reason to supply any materials, the cost in
respect thereof to be borne by the Contractor shall be either the current
market rate or the actual cost to SAVAN-DKLS and any other charges,
whichever is the greater.
The cost to be borne by the Contractor as detailed above shall be
deducted from monies due or to become due to the Contractor under this
Contract. No claim for lost of profit under the Conditions of this Contract
shall be deemed to have arisen. No action taken by the S.O. under this
clause shall, in any way, affect or modify the right of SAVAN-DKLS to claim
for damages in the event of the Contractors failure to complete the Works
by the agreed Date of Completion.

P:\zRAZMANN\SPEC\A-GENERAL 1. D O C

A.2

SAVAN DKLS WATER SUPPLY CO. LTD

11.0

2013

REQUIREMENTS OF OTHER CONTRACTOR


The Contractor shall afford every facility to other contractors on the Site and
to allow them to carry out their work unhindered. The Contractor shall
maintain constant and careful liaison with them to ensure the correlation of
the respective Programmes of Works and the accurate laying and building-in
of pipes, formation of ducts, and the likes as the Works proceed. The S.O.
will do everything possible to assist in the maintenance of this liaison and
co-operation and the Contractor shall be prepared to assist in the progress
of the Works by other contractors generally by carrying out construction
and laying operations in the order required.
The Contractor shall take all reasonable precautions to avoid any damage to
other contractors work and/or property. The Contractor shall be entirely
responsible for making good, at his own expense, any such damage
caused by, or due to, any action or lack of action on the part of the
Contractor.
No claims for extra shall be entertained for any additional work, which
arises through lack of co-operation between the Contractor and other
contractors.
All costs involved in complying with this Clause shall be deemed to
have been covered by the Contract Rates or Sum unless specifically
provided for in the Bill of Quantities.

12.0

EXISTING PUBLIC UTILITIES AND OTHER SERVICE


a. Information on existing utilities is given as a guide only, SAVAN-DKLS shall not be
held responsible for this information provided.
a. The Contractor shall be responsible for locating all services including
drains, pipes, cables and the like whether above or below ground level
and shall adopt such methods of working as will ensure that no damage
is caused to the services. The Contractor shall make good at his own
expense any damage whatsoever to existing services resulting from his
operation to the approval of and in accordance with the i n st ru ct i o ns o f
t he au th or i t y or ow ne r co nc e rne d an d s ha l l ke e p S AVA N - DK L S
indemnified at all times from all claims which may be bought against
SAVAN- DKLS for or on account of any damage to the said services.
The cost of deviating or realigning any of these services shall not be borne
by the Contractor but the Contractor shall provide and maintain at his own
expense any temporary works necessary to support or protect the
services aff ected by his excavation to the satisfaction of the authorities or
owners concerned.
The Contractor shall attend to the authorities or owners concerned and
afford them all facilities necessary to enable them to undertake any work
required to deviate those services or to prevent interruption of such
services during the progress of the Works.
All costs involved in complying with this Clause shall be deemed to

SAVAN DKLS WATER SUPPLY CO. LTD

2013

have been covered by the Contract Rates or Sum unless specifically


provided for in the Bill of Quantities.

SAVAN DKLS WATER SUPPLY CO. LTD

13.0

2013

PUBLIC AND PRIVATE ROAD


All operations necessary for the execution of the Works and for the
construction of any temporary Works shall, so far as compliance with the
Contract permits, be carried out so as not to interfere unnecessary or
improperly with the convenience or the access or use and occupation of public
or private roads and footpaths or to or of properties whether in the
possessions of the SAVAN-DKLS, the Government or of any other person
and the Contractor shall save harmless and indemnify SAVAN-DKLS and the
Government in respect of all claims, demands, proceedings, damages, costs,
charges and expenses whatsoever arising out of or in relation to any such
matters.
No private road or footpath shall be blocked or obstructed by the Contractor
without the prior consent of the owner/ occupier and the prior approval of the
S.O.
No public road shall be blocked or obstructed by the Contractor without
the prior consent of the authorities and the prior approval of the S.O.
The Contractor shall be responsible for providing, operating and
maintaining all traffic signs, traffic control signals, barriers and lightings as
detailed in the Drawings unless otherwise directed by the S.O. The signs,
barriers and lightings shall be repositioned or removed as required during
the progress of the Works.
If the Contractor fails to comply with the requirements of this Clause, the
S.O. may carry out such works as he deems necessary and to charge the
Contractor with the actual cost including any other charges. Such cost and
charges shall be deducted from any monies due or which may become
due to the Contractor under this Contract, and the Contract Sum shall be
adjusted accordingly. No action by the S.O. under this Clause shall relieve
the Contractor of his obligations or affect or modify the right of SAVAN-DKLS
under the Contract.

14.0

WORK THROUGH PRIVATE LAND


The Contractor shall be responsible for obtaining the consent of private
owner and occupier to the use of such land or private roads for temporary
access to the working space along the pipeline route or for other
temporary purpose. Before entering private land for the purpose of
commencing construction, the Contractor shall confirm in writing to the
S.O. that he has obtained such consent.

15.0

CONTRACTORS FACILITIES
The Contractor shall, at his own expense, provide and maintain in good
condition throughout the Contract Period such temporary buildings, tanks,
stores, temporary sanitary conveniences, access roads and other facilities as
may be necessary for the execution, completion and maintenance of the Works.
The location of all such

SAVAN DKLS WATER SUPPLY CO. LTD

2013

facilities shall be subjected to the approval of the S.O. All such facilities
shall comply with the requirements of the Local Authorities.

16.0

SAFETY AND SECURITY MEASURES


The Contractor shall take all necessary safety precautions on the Site
and shall conduct his operations on the Site and shall conduct his
operations in a manner so as to ensure the safety of the S.O. and his staff,
the Contractors employees and the public.
The Contractor shall, at his own expense, provide and maintain to the
approval of the S.O. all notices, warning signboards, fencing, watching and
lighting necessary to ensure the security of the Works and the safe
keeping of the materials and tools stored on the site.

17.0

DAMAGES TO EXISTING WORK


The Contractor shall be responsible for any damage to road verges, drains,
ditches, turfing areas, or other structures, which may result from the
construction work or the passing of his vehicle, plants or equipment of
whatever kind to or from the Site of the Works. The contractor shall
make good such damage at his own expense immediately after it occurs
to a standard acceptable to the S.O.
Any existing structures and obstructions, which are designed to be removed
shall be demolished, broken up, removed and disposed off as approved by the
S.O.

18.0

PROTECTION OF WORKS
From the commencement of the Works until the date stated in the
Certificate of Practical Completion for the whole of the Works, the
Contractor shall take full responsibility for the care thereof. In case of
damage, loss or injury to the Works, or any part thereof, from any cause
whatsoever, the Contractor shall, inform the S.O in writing. He shall make
proposals, submit method statement for the S.Os approval. After the S.O.
has consented to the work, the contractor shall at his own cost, repair and
make good the same so that at completion the permanent works shall be
in good order and condition in every respect as per requirements of the
Contract. The contractor is not allowed to undertake any repair work until he has
received specific instruction from the S.O. The S.O. shall also not delay his
approval unless he has specific reasons or comments on the proposed
rectification measures.

19.0

SITE DRAINAGE
The Contractor shall make proper provision for the drainage of water from the
Site of the works including rainfall run-off from surrounding areas, which
drain onto the Site.

SAVAN DKLS WATER SUPPLY CO. LTD

2013

The Contractor shall at no extra cost to SAVAN-DKLS provide, form, fix,


maintain and work as and where directed by the S.O. such pumps, chutes,
walls, drains, bunds silt traps and other temporary works necessary for the
proper drainage of the Site so that no fl ooding, silting or other damages or
disturbances is caused in the areas surrounding the Works or to the Works
for the duration of the Contract.

20.0

PIPE DUMPS
The Contractor shall be solely responsible to find a suitable pipe storage
yards and stores to store the pipes, valves and fittings supplied by or to the
Contractor.
The Contractor shall allow in his Contract Rates for expenses incurred in
locating, hiring, preparation and reinstatement to original condition of such
storage yards and stores.
The Contractor shall be responsible for obtaining the consent of the owner,
tenants or occupier of lands to the use of such land for storing of the
pipes, valves and specials. The Contractor shall pay all cost, expenses, rental,
compensation or other disbursement, which may be incurred by him in
negotiations with the owner, tenant or occupier and during the subsequent
use by him of such land for these purposes. No reimbursement will be
made to the Contractor in this respect. The full cost thereof shall be
deemed to be included in the Contract Rates.

21.0

FIRST AID BOX


The Contractor shall be required to provide a complete approved first aid
box and shall keep it in a metal box in his Site Offi ce. The first aid box
shall be in the charge of either the Contractors Site Representative or
some other responsible person who will be on the Site during all working
hours to ensure that the fi rst aid box is available without delay at all
times when work is in progress. The person in charge of the first aid box
shall be trained in simple first aid duties.

22.0

CONTRACTORS PLANTS
All mechanical plants used by the Contractor in the execution of the Works
shall be of such type, size and method of the working as the S.O. shall approve.
The S.O. shall not unreasonably withhold approval for the use of any plant
but if, in the S.Os opinion, circumstances arises which made it desirable
that the use of any plant should be suspended either temporarily or
permanently, the Contractor shall change the method of performing the
work affected at the Contractors own cost and the Contractor shall have no
cause for claim if any order issued by the S.O. result in any plant having to
stand idle for a period of any duration whatsoever or having to be removed
from the Site.

23.0

CLEARING UP AND REINSTATEMENT ON COMPLETION


On completion of the Works, the Contractor shall dismantle and remove
from the Site, all his plant, equipment, temporary buildings and

SAVAN DKLS WATER SUPPLY CO. LTD

2013

unused materials. The Contractor shall fill in and make good all holes and
temporary excavations, dig up

SAVAN DKLS WATER SUPPLY CO. LTD

2013

and remove all temporary roads if directed, clean out all gutters, clear
away all rubbish, and leave the whole of the Site of the Works in a clear
and tidy condition acceptable to the S.O.
The Contractor shall clean and wash all windows, paintwork, walls and
floors, and shall leave permanent buildings, tanks and other structures
in a clean and tidy condition ready for use by SAVAN-DKLS.

24.0

S.O.S APPROVAL
Any S.Os approval given to any portion or stage of the Works shall not absolve
the Contractor from his liability to make good any defects which may be
discovered or occur subsequently during the Defects Liability Period of the
Contract.

25.0

DAYWORK
The S.O. may order in writing that any additional or substituted work be
executed on a day-work basis. The Contractor shall then be paid for such
work under the conditions set out in the Day-work Schedule included in
this Contract and at the rates and prices agreed to by both parties.
The Contractor shall furnish to the S.O. such receipts or other vouchers as
may be necessary to prove the amounts paid and before ordering
materials shall submit to the S.O. quotations for the same for the S.O.s
approval.
In respect of all work executed on a day-work basis, the Contractor shall during
the continuance of such work deliver each day to the S.O. an exact list in
duplicate of the names, occupation and time of all workmen employed
on such work and a statement also in duplicate showing the description
and quantities of all materials and plants used thereon or therefore. Upon
agreement by the S.O., one copy of each list and statement shall be signed
by the S.O. and returned to the Contractor. At the end of each week the
Contractor shall deliver to the S.O. a priced statement of the labour,
materials and plant used. All price statements, which have been agreed to
between the Contractor and the S.O. shall be incorporated in the
subsequent certificate or payment.
The rates shown shall include all allowances for administration and
profi t, all t r a v e l i n g a n d a c c o m m o d a t i o n ex p e n s e , s t a t u t o r y
o v e rh e a d s s u c h a s E P F Contributions, SOCSO, holiday pay, annual and
sick leave as appropriate where these apply. Rates shown for Plant shall
be the complete compensation required by the Contractor for the operation
of this Plant, including the cost of the operator, fuel and transportation and
maintenance.
In the case of materials used in labour work, the Contractor shall be
paid the complete on site cost of any materials used, plus an agreed
percentage to cover purchase of material and organization by the
Contractor etc including profits.
Payments for day labour work will only be certified for the actual hours
worked. No payment will be made for standby time caused by inclement
weather.

SAVAN DKLS WATER SUPPLY CO. LTD

26.0

2013

COVERING UP OF WORK
Before any part of the Works be permanently covered up, the Contractor
shall give due notice to the S.O. of his intention. The S.O. shall, without
unreasonable delay, examine and measure if necessary, the said part of
the Works unless the S.O. considers it unnecessary and advises the
Contractor accordingly.

27.0

SIGNBOARDS
Where specified in the Bill of Quantities, the Contractor shall provide,
erect, paint and maintain signboards as shown on the relevant drawing or
as directed by the S.O. The signboard shall be erected at a prominent
position at the site as approved by the S.O. and the Contractor shall pay
all charges in connection with this, including obtaining permission, licences
and fees etc.
On completion of the project, the Contractor shall dismantle and clear
away the signboard as directed by the S.O.

28.0

CLAUSES RELATING TO WORK OR MATERIALS NOT REQUIRED IN THE


WORKS
Any clauses in this Specification, which relate to work or materials not
required in the Works shall be deemed to be for general information only.

29.0

EMPLOYEES SOCIAL SECURITY ACT


Not used.

30.0

DELAYS AND STOPPAGES


Not used.

31.0

WARRANTY

Not used.

SAVAN DKLS WATER SUPPLY CO. LTD

32.0

2013

STATUTORY HOLIDAYS
Extension of time will not be allowed for statutory

holidays.

33.0

CONTRACT DOCUMENTS
The Contractor shall be deemed to have fully examined the Contract
Documents, have read each and every Clause and all details therein
and have had full opportunity to consider the same and make necessary
investigations in relation t h e re t o. H e s h a l l n o t m a ke a n y cl a i m s o r
a n y o t h e r o c c a s i o n b e c a u s e o f misunderstanding of the Contract
Document or because of lack of information.
If the Contractor considers that any of the conditions and/or instruction
in the Contract Document involves additional cost, he shall allow for
the same in the Tendered Price as no claim extra in this connection will be
entertained.
All parts and sections of the Specifi cation shall be read in conjunction
with one another and unless particularly specified otherwise, the provisions and
requirements of any Clauses under any one section apply to the Works under
the Contract where Work is of as similar nature.
Drawings are included in the Contract Document. Further drawings may
be issued to the Contractor as work progresses.

34.0

EXPLANATION OF THE DOCUMENTS


In the event that additional information is required, the Contractor shall
make a written request for the details required by him. A period of two (2)
weeks shall be allowed by the Contractor for the details to be prepared and
delivered to him.
No claims for costs arising from delays to the job will be entertained
where in the opinion of the S.O. a delay has occurred through the
Contractors failure to comply with the requirements of this clause.

35.0

CONTRACTOR'S AGENT
A competent, duly authorised, and responsible site agent or
representative of the Contractor shall be appointed. The agent's name,
qualification and experience shall be submitted to and approved, in writing,
by the S.O. prior to appointment and who shall have full authority to act for
and bind the Contractor. The agent shall reside on the Site and shall have an
office thereon. This agent shall attend to the S.O.s office at all reasonable
times when required to do so. He shall be fl uent in English and all
correspondence will be conducted in English.
The agent shall be stationed on the site for the duration of the Contract. If
Contractor desires to replace his agent, the name of the proposed new agent
shall be submitted to the S.O. for approval prior to replacement.
In the event of the agent being absent from the works for any period exceeding

SAVAN DKLS WATER SUPPLY CO. LTD

2013

3 consecutive days, he shall notify the S.O. in writing of the name of his
responsible and fully authorized deputy. In any case, the agent shall
always inform the S.O. in advance, should he intend to be absent from the
Works.

36.0

PROJECT DIARY
The Contractor shall keep a daily project diary, which shall record the major
events of each day. The format shall be approved by the S.O.s
Representative and as a minimum, it shall include:Weather record for the day
Number of operatives (identified by their trade or skill) present on site
Number of items of major plant; make, model and physical location on
site

The locations and description of major activities on site


At the end of each week the Contractor shall give a copy of that weeks
diary to the S.O. duly signed and dated.

37.0

CO-ORDINATION MEETINGS AND PROGRESS REPORTS


Meeting shall be convened by the S.O. from time to time to facilitate coordination of various works necessary for completion of this Contract.
The Contractor shall attend the meetings when so directed in writing by the
S.O.
Any person attending the meeting on behalf of the Contractor shall be
deemed to act on the Contractors behalf, and any agreements made
shall be binding on the Contractor.
The Contract Sum shall include allowance for attendance at monthly
meetings or any other meetings called during the cause of this Contract.
At monthly intervals, the Contractor shall submit to the S.O. four (4)
copies of the written detailed progress report in the form of up-dated
progress chart in Microsoft Project and supported by other bar charts
indicating the stages of work in all main operation as aspects, design,
ordering of materials, manufacture, inspection and delivery. These
reports shall be accompanied by such additional information in
approved standard form, as may be required by the S.O. The report shall
reach the S.O. before the seventh of each new month. The reports
shall be forwarded promptly so that on receipt by the S.O., the
information contained therein is not more than 7 days out of date.

38.0

TRANSPORT
Not used.

39.0

ASSISTANCE TO SUPERINTENDING OFFICER'S REPRESENTATIVE


The Contractor shall render all necessary assistance to the S.O.'s
Representative and shall provide and maintain a sufficient supply of pegs,
poles, sight rails, paint, lines, spirit levels, stores, and tool sets required for
checking the setting out of the Works, as well as suitable protective
clothing, rubber boots and the like. The Contractor shall provide as many

SAVAN DKLS WATER SUPPLY CO. LTD

2013

full time or part time chainmen as may be required.


The cost of the labour, plant and materials required by the S.O.'s
Representative's staff for checking the setting out of the Works, inspection
and supervision of the Works, and for the sampling and testing of materials
for which no separate item is provided in the Bills of Quantities, shall be
deemed included in the rates.

40.0

SUPERINTENDING OFFICER'S APPROVAL


Wherever the S.O.'s approval is given to any portion or stage of the Works
before the succeeding portion or stage of the Works is allowed to be
carried out, such approval shall not absolve the Contractor from his
liability to make good any defects, which may be discovered or occur
subsequently during the Defects Liability Period of the Contract.

41.0

TEMPORARY ACCESS ROAD


The Contractor shall at his own expense and risk provide, operate and
maintain to the satisfaction of the S.O. all temporary roads used by him
and his vehicles for access to the site. These access roads shall be
maintained such that access to the site is possible at all times for the S.O. by
means of light vehicles.
The Contractor shall also be entirely responsible for any damage caused by
his staff to any other roads used for access to the site and obtaining any
approval from the authorities in connection with the use of the road.

42.0

WORK OUTSIDE NORMAL HOURS


No work shall proceed outside normal working hours without the prior
approval of the S.O. and such other Statutory Authorities as may be
required. This applies to work before 7.00am on any day or later than
5.30pm on any day, and on Sundays, and Public Holidays.
It is anticipated that works may have to be carried out during the night
and the Contractor shall allow all necessary cost in executing work at night.

43.0

MONTHLY STATEMENTS
Format for monthly statements may be proposed and prepared by the
Contractor or adopted from any format approved by the S.O. Such forms shall
be provided by the Contractor and shall be printed to the

SAVAN DKLS WATER SUPPLY CO. LTD

2013

approval of the S.O. as soon as practicable after the receipt of the S.O.'s
Order to commence the works. Each statement shall be fully detailed and
two (2) copies shall be submitted to the S.O. through his Representative.

44.0

TEMPORARY CONNECTIONS DURING CONTRACT PERIOD


The Contractor shall make his own arrangements for supply of water and
power required for the Works. All costs associated with the supply of
water and power supply shall be paid by the Contractor and shall be priced
accordingly.
Should the Contractor wish to connect to any water mains where such
mains exist, the Contractor shall obtain the express approval of the S.O.
in each and every instance. The repair of damage occasioned by the
Contractor to any water supply fixture of fitting shall be charged to the
Contractor.
The Contractor shall arrange for and pay all costs connected with the installation
of temporary power supplies for use during the Contract Period. The cost of
all power used shall be borne by the Contractor.
Contractor shall be responsible to ensure water and power supply are
made available all the times including during testing and commissioning.
All cost incurred to be borne by the Contractor.

45.0

OBVIOUS WORK
The intent of this Contract includes the survey, preparation of detailed
drawings or shop drawings, manufacture, test, supply, erection and
commissioning of all pipes and fittings for the proper completion and
operation of the Works. Notwithstanding that these documents have been
drawn up with all possible care, if any details of the Works have not been
included within this Specification or detailed on the Drawings but the
necessity of which might reasonably be implied from the above stated intent,
and, such details are usual or essential to the completion of the Works,
the same details shall be deemed to be included within this Contract
whether so particularly itemized or specified or detailed or not, at NO
additional cost to the Contract.
The word `approved'
equipment or material,
the S.O., shall select or
Contractor shall provide

46.0

or `to be approved' used in conjunction with


the make of which is not defined, shall mean that
reject a type from samples or drawings, which the
and that the S.O. decision shall be final.

STATUTORY REGULATIONS AND APPROVAL


The Works and all plant, equipment and materials forming part of this
Contract shall comply in all respects with the relevant Malaysian Statutory
Regulations, Bye-Laws and Orders currently in force; and the Contractor's
attention is drawn particularly to the Re gul ati ons of the Machi ne ry
De partme nt, C hi e f El e ctri cal I nspe ctors Department, Tenaga Nasional
Berhad, Suruhanjaya Tenaga, local authorities, JKR, OR local Lao authorities
equivalents.

SAVAN DKLS WATER SUPPLY CO. LTD

2013

The Contractor shall be responsible for obtaining the necessary approvals


from the relevant Departments and Authorities for all items of Works under
this Contract. It shall also be deemed that the Contract Price includes
the attendance to local authorities, Chief Electrical Inspector, Fire Officer,
the Machinery Inspector, etc. and all costs to ensure conformity with
current regulations of the above-named Departments. The approval of
equipment and materials by the relevant authority shall not prejudice the
right of the S.O. to reject such equipment or materials which may not comply
with the Specification.
The supply of all danger notices, warning notices, etc. to the requirements
of the Chief Electrical Inspector and other relevant departments or
authorities shall be included in the Contract.
The Contractor shall allow for and obtain all necessary permits and
licenses, etc. required from the relevant authorities in connection with
the carrying out of the works and pay all deposits, fees, royalties in
connection therewith. The Contractor shall also allow for the costs of
arranging for inspection by offi cials of local authorities from time to time
during the Contract period and defects liability period.

47.0

NOISE
Not used.

48.0

DELAYED TAKING OVER


Not used.

49.0

FIRE
All rubbish, packing, discarded or surplus materials shall be removed from
the site periodically and shall not be burned on site.

50.0

SUPERVISION
The Contractor or his authorised representative shall be fully responsible to
ensure all the Works included in the Contract are faithfully executed and
commissioned in accordance with the provisions of the Contract Documents.
The Clerk of Works, Inspector or Resident Engineer (R.E) appointed for the
purpose of supervising work under this Contract will be responsible for:(i)

Keeping records of the progress of the work as required by the S.O.

(ii)

Inspecting the works in progress from time to time to ensure


compliance with the Specifications.

iii)

Verifying and recording the quantity of any works carried out daily
for the purpose of monthly payment.

SAVAN DKLS WATER SUPPLY CO. LTD

51.0

2013

INVENTORY CONTROL OF EMPLOYER SUPPLIED MATERIALS


The Contractor shall be responsible for inventory control of all materials
supplied by the Employer.
The Contractor is required to submit in a format to be agreed with the
S.O.s Representative details of materials supplied, laid and excess materials,
all of which are to be incorporated in an overall Materials Balance list.
The said list shall be endorsed by the Contractor and the S.O.s
Representative and attached to the Final Certificate for submission to the
S.O.
All excess materials are to be returned to the Employer.

52.0

RIGHT TO OPERATE UNSATISFACTORY EQUIPMENT


The Contractor shall be responsible for ensuring that the equipment
supplied and installed by him performs as guaranteed and specified.
Equipment that fails to meet these requirements shall be made good at no
cost to the S.O. Equipment that continues to fail to meet the required
performance as specified shall be replaced by the Contractor at no cost to
the S.O. The S.O. reserves the right to continue using the rejected equipment
until the replacement is available at no additional cost to the Contract.

53.0

SUPPLY OF CLEAR WATER FOR TESTING AND COMMISSIONING


Upon completion of installation, the Contractor shall supply clear water at
his own cost for testing and commissioning of the Works.

54.0

TRAINING OF OPERATORS
Following the complete acceptance testing of all the equipment installed
under the Contract, and satisfactory commissioning of the Plant, the
Contractor shall give full training to the plant operators in the proper
procedures for operation and maintenance of all items of equipment provided
under the Contract. The Contractor shall allow in his Tender Price for such
training to be carried out.

55.0

IDENTIFICATION LABELS
W h e n i n s t r u c t e d b y t h e S . O. , m e c h a n i c a l i t e m s s h a l l h a v e a n
identification label/plate securely fixed to the body. The identification
labels shall be of approved non-corrodible metal and the data shall be
engraved or stamped. Data required for mechanical equipment shall include
the manufacturer, the date of manufacture, the country of manufacture,
the operating conditions and supply conditions that might be applicable.
The direction of opening of valves shall be permanently indicated by
arrows on hand-wheels or operating levers. All valves shall be clearly
labelled with the appropriate function and identification.

SAVAN DKLS WATER SUPPLY CO. LTD

56.0

2013

APPLICATIONS FOR PAYMENT


Unless instructed otherwise by the S.O., each of the Contractor's
applications for payment shall be numbered consecutively and shall be
submitted in two (2) identical copies to the S.O.
Claims shall be accompanied by Bill of Quantities giving the following
detailed particulars: (a)

Every item for which payment (in whole or in part) is being claimed up
to the date of the application, listed in the manner and in the order
of the Bill of Quantities.

(a)

The amount of payment being claimed in respect of each item (quantities


or
percentage
of
Works
completed
to
be
stated
where
appropriate),justification of proof of completed works or stages of
completion, sketches, drawings, etc.

(a)

Details of Variation Orders, if any, approved by the S.O., with the


amounts to be added or deducted in respect of each,

(b)

A summary of Dayworks, if any, ordered by the S.O.,

(c)

A summary, grouped in the same manner as in the Schedule of Prices,


showing the total gross value of work done to the date of the
application,

(b)

The deduction in respect of retention money, details being given


where necessary,

(d)

The resulting net total amount claimed,

(e)

The deduction in respect of amount previously certified for payment,

(c)

The resulting amount claimed as payment due on the application.

(d)

The provision of Material Inventory properly endorsed by all parties.

A fixed date for measurements shall be agreed upon with the S.O. on a
monthly basis for which measurements for Works completed are
conducted. This fixed date shall not vary from month to month without the
prior and written consent of the S.O.
The application for payment shall be duly certified by the S.O.'s
Representative and the Contractor's Site Agent.

57.0

Not Used.

SAVAN DKLS WATER SUPPLY CO. LTD

58.0

Not Used.

59.0

SURVEY WORK

2013

The Contractor shall engage an experienced surveyor to carry out ground


survey of the work.
Complete topographical survey of the site shall be completed within 30
days after the acceptance of the tender. This information shall be forwarded to
S.O. for design updating.
Survey works shall include:
Planimetric control

Height control

Benchmarks & TBM


Strip survey corridor of minimum 20m
Longitudinal profiling

Presentation of survey data shall be according to standard pipeline survey


format (plan and longitudinal section) including overall plan approved by the
S.O. Three (3) sets of the drawings shall be issued in hard copy format (A1
size), two (2) sets of the drawings in A3 size and soft copy format (ACAD
drawings in drawing format).
The Contractors surveyor shall update the survey data during the
construction for preparation of as-built drawings, which shall include:-

59.1

Recording of actual work done.

Cost for this survey works shall include provision of drawings and CDs.

Scope of Services
The scope of service to be provided by the Surveyor shall include:(a)

Obtaining all necessary topographical maps, certified plans, revenue


sheets

(a)

Discussions with the relevant authorities before commencing the Works


(b) Study all relevant information and maps provided/available
and obtain additional data if necessary for the proper execution of the
Works
(c) Set out a control traverse connecting the above to the nearest
State Grid net and provide height control from existing bench marks (BM)

(b)

Set out a control traverse for the proposal pipeline route carry out a
strip survey at 1 m contours and setting out of routes

SAVAN DKLS WATER SUPPLY CO. LTD


(c)

2013

Establishment of Special Types of Reference Marks


(d) Performance of all fi elds survey works necessary to locate
accurately the location and dimensions of the following features

59.2

i.

Locations and description of all topographic features such as


roads, tracks, mines and a description of surface features

ii.

Location and extent of all existing grave sites, burial plots


and holy ground, if these are evident on the ground

i.

Location and extent of all existing and proposed structures


which will influence the design of the scheme to the extent that
such information is available, at the time of survey, from the Local
Offices of the Authorities concerned.

ii.

Location and depth, within the specified survey of all existing


service conduits both overhead and exposed such as water
mains, electrical
cables, drainage pipes or channels
(indicating discharge direction), Telecom cables; including location
of all associated chambers, valves, valve boxes, pits, inspection
chambers and other similar appurtenances.

iii.

Location and extent of swampy and waterlogged areas as


can be determined at the time of survey

iv.

Bridges and culverts

Survey Plan and Scales


The Surveyor shall prepare the following survey plans based on the
data and information of the field surveys:(a)

Computer drawn plans, in State Grid Net where possible to a scale of


1: 1000 or other suitable scale to fit A1 size for the incorporating all
features detected.

(b)

Computer drawn location plan

60.0 AS-BUILT DRAWINGS


As built drawings shall be produced by the Contractor on a continuous basis
and as soon as possible after the construction of the various system, or
within one month after completion of the Works. For this purpose, an item has
been allowed in the Bill of Quantities. The standard and details to which
such as-built plans shall be drawn up as directed by the S.O.
The Contract Price shall be deemed to include the cost of preparation,
supply and delivery of all original drawings and information duly certified by
the Contractor and his surveyor as follows: a)
a)

2 full sets of drawings in paper (A1 size)


2 full sets of drawings in paper (A3 size)
b) 1 full set of drawings in digitized format.

All drawings submitted to the S.O. shall be in accordance with the

SAVAN DKLS WATER SUPPLY CO. LTD

2013

following guidelines:(a)

Each Drawing shall have a Title Block indicating the Title of the Job,
Title of the Drawing, Scale, Date, Contractor's Name and Address,
Revision Index and Drawing No.

(b)

On each Drawing, details such as pipe invert level, size, valves,


bends, etc shall be indicated as clearly as possible to include all the
works to be carried out on si te. Such detai ls shal l be presente d
in both pl an and longitudinal section.

(c)

Plan and longitudinal section of pipe profile drawings showing invert


level of pipe, alignment of pipe, details of pipe particulars.

(d)

Details drawing showing air valves, washout, valves chamber,


crossing pipe bedding method, jointing etc.

Failure to observe any of the above shall delay the approval of the
shop drawings and the Contractor shall be held entirely responsible for
such delay and no extension of time shall be allowed.
Standard symbols and legends for SAVAN-DKLS requirements as per
Standard Drawings.

61.0

MANUFACTURERS WORKS INSPECTION AND TESTING

All items of equipment and materials: pipe, specials and valves shall be
subjected to inspection and testing before despatch unless officially waived
in writing by the S.O. All inspection, examination and testing at the
manufacturers works shall be carried out strictly in accordance with the
appropriate Malaysian Standard, British Standard, International Standard or
such other equivalent standard as may be approved by the S.O. unless
otherwise specifi ed to ensure that the equipment and materials being
supplied meets the requirements of the Specification.

SAVAN DKLS WATER SUPPLY CO. LTD

2013

B EXCAVATION
1.0

GENERAL
Excavation work shall include site clearing, the removal, hauling, proper
utilization or disposal of all excavated materials and the construction,
shaping and finishing of all excavations and embankments over the entire
extent of the Works in conformity with the Drawings and this Specification.

2.0

SITE CLEARING
The Contractor shall remove and dispose all trees and bushes within the
site of the Works as and wherever directed by the S.O. Site clearing shall
include clearing, grubbing, demolishing, breaking up and removing all
trees, shrubs, vegetation, stumps, structures such as walls, fences and
other obstruction within the Site except those which have been
designated to be retained.

3.0

EXCAVATION GENERALLY
The Contractor shall carry out all excavations in such manner and order as
approved by the S.O. and in whatever material as may be found. All
excavated materials shall be deposited so that it will cause as little damage
and inconveniences as possible.
All excavations shall be carried out to the required lengths, breadths,
depths, inclinations or curvatures as may be necessary for the proper
construction of the Works or as shown on the Drawings. All excavations
shall be suffi cient to provide for the necessary working space, shuttering
and any other temporary structures required during construction. Where so
directed by the S.O. the turf and top sub-soil shall be reserved and stacked
separately until required for re-use in reinstatement.
Top soil shall mean the top layer of soil which can support vegetation.
Unless otherwise stated, the excavation, whether in open cut or in trench,
shall be proceed in such portions at a time as the S.O. may approved and shall
not in the first instance be carried down to a depth nearer than 150mm
above formation level. The last 150mm of depth to formation level shall
be carried out by manual labour immediately in advance of placing
concrete screed, concrete or pipe laying.

The bottom of all excavations shall be carefully trimmed and leveled, well
rammed and consolidated to ensure good solid foundations.
The contractor shall be responsible for keeping dry all excavations, whether
in open cut or in trench, so as not to interfere with the work in progress.
He shall without extra cost to SAVAN-DKLS provide, form, fix, maintain and
work as and where directed by the S.O. such pumps, wells, drains,
bunds, and other thing necessary to effectively deal with all water which
may collect or find its way into the excavations from any cause whatsoever.
Nevertheless, all methods employed for dealing with the water shall be to the
approval of the S.O. Such approval shall not relieve the Contractor from
his liability for any damages to the Works or adjoining land and property
or water courses due to his operations.

SAVAN DKLS WATER SUPPLY CO. LTD

2013

The Contractor shall be responsible for the stability of the excavations at


all times. He shall, without extra cost to SAVAN-DKLS and to the approval
of the S.O. slope the sides of the excavations and or provide and fix
strong and suffi cient timbering to support the sides and or bottom of the
excavations to prevent against collapse, and shall maintain the same until,
in the opinion of the S.O., the construction work is suffi ciently advanced
to permit the timbering to be withdrawn. Timbering shall be removed only
under the personal supervision of the competent foreman.
The Contractor shall be responsible for any injury to the Works or
consequential damages caused by or arising out of the removal of
timbering and any advice, permission or approval given by the S.O.
relating to the removal of the timbering shall not relieve the Contractor from
his responsibility under the Contract.
The Contractor shall carry out any diversion and subsequent restoration
of such existing river, water-courses, land springs, ditches etc. wherever
encountered during the execution of the Works, whether shown on the
Drawings or not.
4. 0

EXCAVATION FOR PIPE TRENCHES

Before commencing the excavation of pipe trenches, the routes of the


pipelines shall be pegged out accurately. Strong sight rails shall be fixed
and maintained at each change of gradient, and at as many intermediate
points as may be necessary but not exceeding 100 metres apart. On these
rails shall be marked the centre line and level to which the pipes are to be
laid, and such rails shall be maintained in position and at the correct level
from the time the excavation commences until backfi lling is completed.
The run of pipe trenches opened up ahead of pipe-laying operations at any
one time shall not be more than:

100 metres if the pipe-laying operations are in an urban area,

300 metres if the pipe-laying operations are in the side-tables of a


trunk road, or

600 metres if the pipe-laying operations are in unoccupied land


schemes or housing estates under development or are in the sidetables of minor rural roads.

The S.O. may, at his absolute discretion, vary the distances stated
above if he considers that traffi c, road or weather conditions or road
side-table limitations warrant the variation.
Unless the S.O. permits otherwise, the trenches shall be excavated to the
widths given in Table B1 below.

SAVAN DKLS WATER SUPPLY CO. LTD

2013

TABLE B1 Widths of Pipe Trenches.


External Pipe Diameter, D
(mm)
Not exceeding 460
Exceeding 460

Width of Trench
(mm)
D + 450
D + 600* or 900*

*600 for pipe 500mm 750mm


*900 for pipe > 750mmm
Where pipes are to be laid on a concrete bed, the width of the excavation
at the bottom of the trench shall be the width of the underside of the
concrete bed. At all joints the trench shall be so excavated as to give a
working space of not less than 300mm all round the joint. Where bends are
made by deflecting pipes at joints the trench shall be widen to permit this
operation. The sides of the trench shall be cut vertical, and where
necessary, shall be protected against caving in by timbering to the
approval of the S.O.
The trench shall be excavated to the depths intended or shown in the
Drawings and shall be finished and trimmed accurately to level and grade.
Where no invert levels are shown or indicated the bottom of the trench
shall be graded so that the pipe invert slopes evenly between the adjacent
invert levels.
Should the ground be so wet or soft that, in the opinion of the S.O. it does
not from a firm base for the pipe, or should rock be encountered at the
bottom of the trench, the trench shall be excavated 250mm below the
level intended or shown in the Drawings and then brought back to the
correct level with sand well rammed into place. Such deepening of pipe
trench and filling back shall be treated as a variation under the terms of
the Contract. Should the bottom of the trench be inadvertently excavated
below the specified level, it shall be bought back, at the Contractors
expense, to the correct level with sand carefully rammed into place.

5.0

ROCK EXCAVATION
Rock shall mean those geological strata of hard material which necessitate the
use of blasting or approved pneumatic tools for their removal. Solid
boulders found in trench excavation and foundation pits shall be
considered as rock if such boulder is of size each exceeding 0.08 cubic
metre or each exceeding 0.17 cubic metre if occurring in general
excavations.
Shale and clay boulders shall not be classified as rock. The S.O.s
decision as to whether or not the material of the excavation is to be classified
as rock shall be final.
Notwithstanding the above, rock shall not include materials which in the
judgment of the S.O. can be loosened with a tractor mounted and
drawn ripper of the following description:

SAVAN DKLS WATER SUPPLY CO. LTD

2013

The Contractor shall be entitled to extra payment for rock excavation


only if reasonable notice is given to the S.O. to examine and measure such
material prior to breaking up. The volume of rock excavated shall be
taken as its volume in-situ before it is broken up.

6.0

Not Used.

7.0

Not Used.

8.0

UNAUTHORIZED EXCESSIVE EXCAVATION


Unless otherwise directed or approved by the S.O., if any excavation including
rock excavation is carried beyond the limits on or against which permanent
work is to be supported in accordance with the Drawings, the Contractor
shall at his own expense be required to fi ll the excess excavation with
Grade 20 mix concrete or other suitable materials acceptable to the S.O.

9.0

ADDITIONAL EXCAVATION ORDERED BY THE S.O.


If after excavating the sites on which the various parts of the Works are
to be constructed, it is found that any part of the formation is unsuitable
to provide a satisfactory foundation, such portion shall be further excavated
to such depths as the S.O. may direct and refilled to the correct formation
level with Grade 20 concrete or other selected materials acceptable to the
S.O. Such extra excavation and refilling shall be treated as a variation under
the terms of the Contract.

10.0

TIMBER LEFT IN EXCAVATION


If, in the opinion of the S.O., it is necessary to leave in position any timbering,
the Contractor shall be paid at the rate stated in the Bill of Quantities
provided that, in the opinion of the S.O., the necessity of leaving the
timbering has not arisen from carelessness or negligence on the part of the
Contractor.

11.0

EXCAVATION IN ROADS
No trench is to be excavated in the carriageway unless specific approval
has been given by the local authority. The whole operation of excavation and
reinstatement of the trench shall be completed as quickly as possible.
The Contractor shall ensure that minimum interference to traffic flow is
maintained at all times.
A joint site inspection shall be arranged by the Contractor before
commencement of work if so requested by the local authority. After pegging
out, the Contractor shall inform the local authority and the police of the
actual date of commencement at least one week in advance of and on the
day of commencement.
All materials from the excavation, if accepted for backfilling shall be neatly
stacked outside the carriageway. Where there is no place to stack the
excavated materials outside the carriageway, all excavated materials shall be
removed from the work site immediately after excavation.

SAVAN DKLS WATER SUPPLY CO. LTD

2013

Where specifi c approval has been given by for half width construction,
the traffic lines may be reduced to not less than 4.0 metres wide and where
necessary, the shoulder should be strengthened by the Contractor to
accommodate traffic load to the satisfaction of the S.O. and at the Contractors
cost.
Trenches shall be provided with adequate shuttering, walling and struts to
prevent the adjoining road pavement from cracking and subsiding.
If a road diversion is required, the Contractor shall build it to the
specifications of the appropriate local authority. It shall be maintained to
allow for smooth traffi c flow until the reinstatement is completed.
Carriageway excavation across important and busy road and junctions
shall be carried out during off-peak hours e.g. Saturday afternoons,
Sundays or at night. The S.O. will specify the appropriate times based on
the merits of each case and such conditions shall be strictly adhered to by
the Contractor.

12.0

CROSSING WATER-COURSES ETC.


Where the pipeline crosses underneath streams, culverts and other watercourses, the Contractor shall be deemed to have allowed for all
additional measures necessary for the proper construction of the pipeline
especially maintaining the flow of water.

13.0

INSPECTION
Until the S.O. has inspected and approved the excavation, no concrete
shall be placed and no pipes shall be laid upon the surface prepared by
excavation. Any work built on foundations which have not been approved
by the S.O., shall on the order of the S.O., be uncovered or removed by the
Contractor and the foundations reinstated all at the Contractors own
expense.

14.0

BACKFILLING OF EXCAVATIONS OTHER THAN PIPE TRENCHES


Backfilling of all excavations shall not be carried out until the works
therein have been inspected and approved by the S.O. In backfilling
excavations other than pipe trench excavations, approved portions of the
excavated materials shall be employed. Where required, approved materials
shall be brought to site for backfilling works. The materials shall be
deposited and spread in layers of not more than 300 mm deep, and each
layer shall be thoroughly rammed by a mechanical vibrating tamper or
smooth wheel roller and watered if required.
If so directed by the S.O., the backfilling shall be finished off slightly proud
of the surrounding ground to allow for settlement, but the contractor shall
make good any settlement, which may occur during the construction of the
works and during the Defects Liability Period of the Contract at his own
expense.

15.0

BACKFILLING OF PIPE TRENCHES


After the pipe laying has been approved by the S.O. and before the
pipelines are tested, only suffi cient backfi lling of the trenches to

SAVAN DKLS WATER SUPPLY CO. LTD

2013

prevent snaking and to maintain the pipes in position will be


permitted, but all joints shall be left exposed. However, i n the case of uPVC
pipes , complete backfilling is required before testing. In low lying ground or
any other locality where the trench may be filled with water and cause
floatation of the pipes, or elsewhere as my be decided by the S.O., the
backfilling shall follow the pipe laying as closely as possible.

SAVAN DKLS WATER SUPPLY CO. LTD

2013

In backfilling pipe trenches, only approved sand free from stones or rocks
shall be carefully spread along the trench bottom between the pipes and the
trench walls to a depth of about 150 mm and shall be hand rammed.
Further layers each of about 150 mm thick of the same material shall
then be spread and rammed in the same manner up to the top of the pipe.
I t s h a l l b e p l a c e d i n l a ye r s e a c h o f 1 5 0 m m t h i c k n e s s a n d h a n d o r
mechanically rammed until the backfill is 500mm above the top of the
pipes. The rest of the trench backfill shall be in layers each of 300mm
thickness and compacted by a mechanical vibrating tamper to fi nish off
slightly proud of the surrounding ground. The degree of compaction of
each layer shall not be less than 95 percent of the dry density obtainable
using the BS Standard Compaction Test. The Contractor shall have to
make good any settlement to avoid formation of drains at gulleys within
the refilled trenches.

16.0

APPROVED FILL MATERIAL


Approved fill material to be used as backfill to the top of the pipes shall be
uniform low plasticity granular material. The material shall be free from all
organic or other materials subject to decay. Highly plastic or expansive
soils or clay shall not be used. The filling material shall be readily
compactable to its maximum density and must not form mud, or otherwise
breakdown when wet.
Should the material being placed as fill or backfill while acceptable at the
time of section, become unacceptable to the S.O. or his representatives
due to exposure to weather conditions or due to flooding or have become
puddled, soft or segregated during the process of the works, the Contractor
shall, at his own expense, removed such damaged, softened or segregated
material and replaced it with fresh approved material.
Where the pipeline crosses a road, approved sand shall be used as fill
material up to the road formation level.

17.0

ROAD REINSTATEMENT
Road reinstatement works shall be carried out by the Contractor to a
standard equivalent or superior to the road condition existing prior to
excavation and to the approval of the S.O.
All backfilling shall be done by the Contractor with approved sand. No
organic soil, broken pre-mix or stones are to be used. The sand shall be
compacted 150mm layers. The degree of compaction of each layer below
the pavement course shall not be le ss than 95 pe rce nt of the dry
de nsi ty obtai nabl e usi ng the BS He avy Compaction Test. The
Contractor shall bear the cost of such tests and shall make good any works
which are found to be unsatisfactory.
Sand material shall be deposited in layers on both sides of the pipe
simultaneously and thoroughly compacted and around the pipe working
alternately on either side of the pipe until the trench have been fi lled up
to 150m above the top of the pipe except for pipes laid in roads where the
sand backfill shall be brought up to the base

SAVAN DKLS WATER SUPPLY CO. LTD

2013

course formation level. The sand vibrator and/or by an approved system


of water jet. The topping of the refilling for trench excavation as described
above the backfill with excavated material.
Where necessary the Contractor shall adjust the moisture content of
the refi ll material either by drying out or by adding water to assist the
compaction of the material.
The road surface shall be reinstated with new materials of the type
existing on site. Edges of the reinstated road pavement shall be
straight and neatly finished to match the existing road to the satisfaction
of the S.O.
Final road surfaces over pipe trenches shall be reinstated within the
following periods or as per local authorities approval:

Along major roads Immediately after backfilling,

Along minor roads within 3 days after backfilling,

Pilot pits immediately after backfilling.

If the Contractor fails to carry out the reinstatement to the satisfaction of the
S.O. or any further reinstatement that may be necessary of any trenches
across roads and footpaths, the S.O. or the local authority may proceed with
such repairs and the cost of such reinstatement shall be deducted by the S.O.
from any payments due or to become due to the Contractor.
18 . 0

REMOVAL OF SURPLUS

The contractor shall dispose off all surplus excavated materials, earth,
rubbish and waste matters to an approved tip to be provided by him unless
otherwise directed by the S.O. If surplus spoil is tipped into or fill materials
obtained from private property, the operations shall be executed with the
approval of the owner and occupier of the same. The Contractor shall have
no right of ownership to the surplus materials excavated.
19 . 0

EMBANKMENTS

Embankments and filled areas shall be made by depositing approved soil in


regular layers not more than 300 mm in loose thickness. Each layer shall be
well compacted with approved mechanical rammers or rollers before the
next layer is placed. Compaction shall continue until the soil is at a
density not less than that of any adjacent cuttings in the in situ state. All
practical steps shall be taken to avoid the inclusion of excess water in the
fill and the finished surface of each layer shall be sufficiently even to
prevent the ponding of rain water in ruts and hollows. The S.O. may direct
the fi lling to stop in inclement weather. In dry weather eff ective
consolidation shall be assisted by watering. If the soil of the fill or the
previous layer of compacted soil is too moist for further effective
compaction, compaction shall be deferred until in the opinion of the S.O., it has
dried sufficiently. The Contractor

SAVAN DKLS WATER SUPPLY CO. LTD

2013

shall disk harrow the soil to aid the drying if so directed by the S.O.
The fi ll materials shall be obtained from the surplus excavated materials
at the site of the works or from approved borrow pits.

20.0

SOILING AND TURFING


The exposed surfaces of all embankments and cuttings as well as flat
areas where directed by the S.O. shall be properly graded and covered
with top soil at least 80 mm in depth before turfing. The surface shall be
loosen by raking before placing of top soil. Turf shall be freshly cut,
approved runner grass. For spot turfing, the slabs of grass shall not be
smaller than 200 mm square and shall be set at 300 mm centres. Turf shall
be firmly bedded or pegged into the earth surface to ensure satisfactory
rooting.
The Contractor shall water and maintain the turf in good condition until all
areas to be grassed are substantially covered with healthy, well
established, firmly rooted grass and planted areas shall be free from
erosion channels. All bare areas shall be made good at the Contractors own
expense.

21.0

LEVELS TO BE RECORDED
Before the surface of any part of the site is disturbed or the commencement
of each stage of filling the Contractor shall take and record levels of any
such part, in the manner specified or as agreed with the S.O. in his
presence and such levels when agreed with him shall form the basis for
measurement.
The Contractor shall obtain the S.O.'s prior approval to the proposed
methods of obtaining and recording this information and shall aff ord the
S.O. all facilities to attend and check each survey and recording. The
Contractor shall give to the S.O. notice of his intention to carry out such
survey work at least 24 hours in advance of the commencement of the
survey. The Contractor shall carry out to the S.O.'s instructions, all
extra surveys required to resolve any doubts which may arise as to the
correctness of any survey or record and the S.O.'s decision shall be
fi nal regarding what shall be recorded as the correct survey.
A similar procedure shall be adopted to record any rock surface limits
and levels before they are blasted or excavated.
Each survey drawing with agreed data shall be referred to as a "Record
Survey" which shall be signed by the Contractor and the S.O. and shall
form the basis of measurement of the appropriate work. The Contractor
shall supply two copies of each Record Survey to the S.O.

22.0

CARE OF EXISTING SERVICES


Information relating to the positions of all existing mains, cables,
culverts, pipes, d r a i n s o r s e r v i c e s o f a n y k i n d s h a l l b e a s c e r t a i n e d
b y t h e C o n t r a c t o r. Notwithstanding any information which may be
furnished by the authorities or the S.O., the Contractor shall be responsible
to ascertain the correctness of this information provided.

SAVAN DKLS WATER SUPPLY CO. LTD

2013

Where services are shown on the drawings or where there is evidence of


services in the ground, the Contractor shall also determine their exact
positions. In addition the Contractor shall watch for and determine the
position of any services which may not have been marked.
Where Trench Excavation is carried out close to or across the line of sewers,
pipes, cables and other services the Contractor shall provide temporary
adequate supports to secure the services and where such sewer, pipe,
cable or other service is temporarily displaced or disturbed it shall be
restored to its original state. If restoration or any service to its original state
cannot be achieved then it shall be replaced and made good. The cost of
excavating around any service which crosses the trench and of temporally
supporting it while pipelaying is undertaken, shall be deemed to be included
in the rates for excavation.
All damages to services shall be made good to the satisfaction of the S.O.
and the authorities concerned. The cost of making good any damage shall
be deemed to be included in the rates for excavation. In the event that any
damaged services shall only be repaired by the authority concerned, all
costs whatsoever relating to the repairing of the damaged service
undertaken by the authority shall be at the Contractors expense.
Where damage to a service had already existed prior to excavation or
other work, repair of the damaged service shall be undertaken by the
Contractor, if so ordered by the S.O. the Contractor shall be paid for
repairing such service.
Where in the opinion of the S.O., construction of the pipeline cannot
reasonably be carried out unless the sewer, pipe, cable or other service is
permanently severed or permanently diverted or permanently supported the
Contractor shall undertake such work is so ordered by the S.O. Any such
work if carried out shall be to the satisfaction of the S.O. and of the
authority concerned and shall be paid where necessary and at the
appropriate Contract Rates.
Where pipes are laid under culverts they shall, subject to other provisions
in the Contract and to the S.O.s instructions, be given a concrete surround
extending for 600mm clear on each side of the culvert, and a concrete half
haunch to the culvert shall be provided over the width of the trench cast
directly on top of the concrete surround. The cost of all work in removing
any piles and concrete bend under culverts and of temporarily
supporting the culvert during pipelaying shall be deemed to be covered
by the rates for the items in the Bills of Quantities for pipe crossing under
culverts.

23. 0

HEDGES, FENCES AND WALLS

Where the Trench Excavation passes under barrier such as hedges, fences
and walls the Contractor shall, as a temporary measure during construction
of the pipeline, provide temporary fencing for any parts of such barriers as
have had to be removed.
After trenches have been refilled and surfaces reinstated, the Contractor
shall carry out work as the S.O. may order for permanent restoration of
such barriers. In the case of a hedge the section removed shall be
replaced by new plants of the appropriate variety and where ordered by
the S.O. the plants shall be protected from livestock on both sides by an
adequate post and barbed wire fenced. During the Defects Liability Period all

SAVAN DKLS WATER SUPPLY CO. LTD

2013

hedges replanted in the above manner shall be inspected and any dead
plant replaced by the Contractor.

24.0

MACKINTOSH PROBES
The apparatus used shall be the standard JKR probes or the normal
Mackintosh probes.
Probing shall stop when the resistance has reached 400 blows/0.30 m.
penetrations or the depth has reached 15 metres, whichever is reached
earlier, unless directed otherwise by the S.O.s representative.
Mackintosh probes shall be measured by the penetration depth into the

ground.

25.0

Not Used.

26.0

MEASUREMENT OF GENERAL EXCAVATION


Items in the Bill of Quantities for General Excavation except where
expressly indicated otherwise, shall apply to excavation whether Bulk or
Incidental Excavation i n any mate ri al and shal l i ncl ude not onl y for al l
w ork i n conne cti on w i th excavation but also for disposing of the
excavated material on the Site as backfill or to permanent spoil tips or to
embankments or backfilling as specified or off the Site to the Contractor's
disposal tips and any necessary double handling. No separate payment
shall be made in respect of forming spoil tips as indicated in the Drawings or
at designated areas as directed by the S.O. on site.

Items for "Excavation in Rock" measured extra over General Excavation


Items, shall include for any allowance the Contractor considers necessary
to cover overbreak and the making good thereof.
All work in connection with excavation and subsequent disposal of
excavated material as specified shall be valued by measurement of such
items as are set forth in the Bills of Quantities for "excavation" and,
where appropriate, of the further extra over items for Rock. All such
measurements unless otherwise specified shall be excavated to the
specified levels and limits described herein or shown on the Drawings,
no allowance being made for bulking. No separate measurement shall be
made in respect of Excess Excavation or the backfilling thereof.
Incidental Excavation for removal of unsuitable material shall (unless it is
held to be Excess Excavation) be measured as the volume ordered by the S.O.
to be excavated beyond the nominal dimensions of general excavation
and shall include for the disposal of the excavated material off the Site
and for refilling the excavation with approved material emanating from
excavation elsewhere.
Quantities against items in the Bill of Quantities are based on ground
levels obtained from survey data. Existing ground levels shall be
determined from joint s u r v e y s c a rr i e d o u t b y t h e C o n t r a c t o r a t t h e

SAVAN DKLS WATER SUPPLY CO. LTD

2013

p re s e n t o f t h e S . O. a t t h e commencement of construction.
Excess Excavation and the backfilling shall not be measured for payment.
27.0

MEASUREMENT OF TRENCH EXCAVATION

Items for Trench Excavation shall apply to excavation in any material


and shall include not only for all work in connection with excavation but
also for refilling of trenches spreading and compacting excavated
material over pipeline reserve as directed and for disposal of surplus
material, for temporary fencing and, in fields, for the stripping and
subsequent reinstatement of the top surface all as specified.
Trench Excavation shall be measured by length along the centre line of the
pipeline at the various depths stated in the Bill of Quantities and the
Contractor shall be deemed to have made his own assessment (subject to
any specific requirements of the Contractor) of the widths of Trench
Excavations necessary for the proper construction of the works
including all allowances to provide support for the excavations, to
accommodate joints and bends in the pipeline and to provide working
space. The length of Trench Excavation shall be measured through and
including any space occupied by manholes, chambers, thrust blocks and
the like. No extra payment shall be made for trenches which are curved in plan
or elevation.
The depth of Trench Excavation for pipes shall be measured normal to the
profile of the ground along the centre line of the trench from the original
ground level of where appropriate from the ground level remaining after
the completion of any general excavation down to the specified invert
level of the pipe plus the thickness of the pipe barrel and plus, where
appropriate, the specified thickness of bedding for the pipe.
The sides of Trench Excavation shall be deemed to be vertical in all
materials and the nominal widths defi ned in Clause 4 shall apply to any
depth of trench and whether or not bedding or surround to the pipe is
specified.
Trench Excavation and all work in connection therewith as specified shall be
valued by the measurement only of such items as are set forth in the Bill of
Quantities, except where expressly provided for otherwise by the
inclusion in the Bill of Quantities of any of the following further items :Incidental Excavation for Structures situated in the pipeline shall be measured
only to the extent that the net excavation required to accommodate the
structures falls outside the nominal dimensions of the Trench Excavation.
Incidental Excavation for removal of unsuitable material shall (unless it is held
to be excess Excavation) be measured as the volume ordered by the
S.O. to be excavated beyond the nominal dimensions of Trench
Excavation and shall include for the disposal of the excavated material
off the site and for backfi lling the excavation with approved material
emanating from Trench Excavation elsewhere or for backfilling the excavation
with the grades of concrete ordered by the S.O.
Rock, measured E.O. Trench Excavation items, shall be measured as the
volume of Rock within the nominal limits of Trench Excavation in Rock.
When measured E.O. Incidental Excavation items it shall be measured as for

SAVAN DKLS WATER SUPPLY CO. LTD

2013

those items.
Excess Excavation and the backfilling thereof shall not be measured for
payment. Trench Excavations in roads and in footpaths as specified shall
be measured (E.O. Trench Excavation) as the area calculated by
multiplying the length of trench so excavated by its nominal width. The
stripping of the top surface and the surface reinstatement of Trench
Excavation in road verges, fields, etc. shall be included in Trench Excavation
and shall not be separately measured.
28. 0

MEASUREMENT OF FILLING

Items in the Bill of Quantities for filling shall include not only work in
connection with working and supplying of fill materials, within or outside
the site transporting, placing, spreading, watering, drying, compacting and
grading approved fill materials but also field tests, supervision, disposing of
reject material and condemned material at spoil tips on or off the site and
construction and maintenance of necessary access roads, bridges and
drainages.
Fill material shall be measured as the volume placed after filling has
completed. Joint measurement of fill levels shall be taken once the required
level has reached. No allowance shall be made in the measurement for
filling for settlement during construction.
The Contractor shall be deemed to have made due allowance for any
delays to filling occasioned by sampling and testing materials from fill
and borrow areas as specified by the installation and testing of measuring
instruments for fill.
The earthworks and all work in connection therewith as specified shall be
valued by the measurement of only such items as are set forth in the Bill
of Quantities. No separate measurement for payment shall be made in
respect of any part of this work unless separate items are expressly provided
for in the Bill of Quantities.
Excavation of reject material in borrow areas shall be measured as the volume
lying between the surface recorded after stripping topsoil but before
excavation of unsuitable material starts, and the surface recorded before
excavation of suitable material starts.
If the Contractor excavates unsuitable material from the ground surface
with the intention of later using the underlaying material as a borrow area,
and then does not work the area as a borrow area to the extent required
by the S.O., then such excavation of unsuitable materials shall not be
measured for payment.

29.0

PAYMENT FOR TRENCH EXCAVATION AND RESTORATION


Payment for trench excavation shall be made in two stages, as
follows :(a)

75% of the total amount due will be paid on completion of pipe-laying.

(b)

The remaining 25% for any length, will be due on completion of


restoration of the final surface, including reinstatement of all surface

SAVAN DKLS WATER SUPPLY CO. LTD

2013

damage, completion of chambers, thrust blocks, etc.


Payment for the second stage shall be due only after restoration of any
length has been inspected and approved by the S.O. and by any relevant
authority. Payment for the separate items in roads, footpaths, etc. will be
made at the same time as the second stage payment for excavation.

30.0

MEASUREMENT OF TOP SOILING AND TURFING


Items where included in the Bill of Quantities for spreading topsoil shall
include for obtaining topsoil from spoil tips on the site, hauling and spreading
all as specified.
The rate shall include spreading a layer of fertilizer with N : P : K of 10 :15
:10% prior to turfing.
Items where included for turfing shall include for all work in connection with
turfing as specified, and for cutting and trimming and weeding at least
once a month until the end of the Defects Liability Defects.
Topsoil shall be measured as the areas so treated, and except where
expressly indicated otherwise items shall apply to sloping as well as to
horizontal surfaces.
Topsoil and turfi ng of re-fi lled trenches shall be included in items for
Trench Excavation and shall not be separately measured for payment.

31.0

PAYMENT FOR TURFING


Payment for continuous turfing shall be the area covered by the turves
provided. Where spot turfing is required the distance between the centre
lines of divots in the form of a triangular pattern shall not exceed 500 mm and
the percentage of the area covered shall be agreed and payment made on
the total area spot turfed multiplied by the percentage.
Turfing will be paid for in two parts :(a)

at fifty percent of the Contract Rate when the turfing has been carried out;

(b)

at fi fty percent of the Contract Rate at the issuance of the


Certifi cate of Practical Completion when the S.O. is satisfied that the
grass has established itself.

Where grass fails to establish itself, the Contractor shall turf the relevant
area again at no extra cost to the S.O.

32.0

PAYMENT OF FEES TO AUTHORITIES


The Contractor shall pay to all Authorities or developers all deposits,
fees and charges required to be paid in relation to the execution of the
works or to any temporary works.
If after due notice to the Contractor calling his attention to the necessity
for the payment of fees and/or charges to the Authorities the Contractor has
failed to make payment, the S.O shall be entitled to pay such fees and/or
charges direct to the Authorities concerned out of any moneys at any time

SAVAN DKLS WATER SUPPLY CO. LTD

2013

due to the Contractor under the contract and such payment shall be
deemed to be payment made to the Contractor under and by virtue of the
Contract.

The cost of all fees and charges payable by the Contractor shall be
deemed to be included in the Contract Rates unless otherwise expressly
provided for in the Bill of Quantities

Potrebbero piacerti anche