Sei sulla pagina 1di 33

1

2
3
4
5
6
7
8
9
10
11
12

DENNIS J. HERRERA, State Bar #139669


City Attorney
ANDREA RUIZ-ESQUIDE, State Bar #233731
VICTORIA WONG, State Bar #214289
Deputy City Attorneys
City Hall, Room 234
1 Dr. Carlton B. Goodlett Place
San Francisco, California 94102-4682
Telephone:
(415) 554-4700
Facsimile:
(415) 554-4757
E-Mail:
andrea.ruiz-esquide@sfgov.org
Attorneys for Respondents
CITY AND COUNTY OF SAN FRANCISCO, ET AL.
DANIEL FRATTIN, State Bar #248373
REUBEN, JUNIUS & ROSE, LLP
One Bush Street, Suite 600
San Francisco, CA 94104
Telephone: (415) 567-9000
Facsimile: (415) 399-9480
E-Mail: dfrattin@reubenlaw.com
Attorneys for Real Parties in Interest
JEREMY RICKS, TRACY KIRKHAM, and JOE COOPER

13
14

SUPERIOR COURT OF THE STATE OF CALIFORNIA

15

COUNTY OF SAN FRANCISCO

16

UNLIMITED JURISDICTION

17
18
19
20
21
22
23
24

PROTECT TELEGRAPH HILL, an


unincorporated association;
Petitioner,
vs.
CITY AND COUNTY OF SAN
FRANCISCO; BOARD OF SUPERVISORS
OF THE CITY AND COUNTY OF SAN
FRANCISCO, and Does 1 to 5;
Respondents.

Case No. CPF 14-514060


CORRECTED JOINT BRIEF OF CITY AND
COUNTY OF SAN FRANCISCO AND REAL
PARTIES IN INTEREST IN OPPOSITION TO
PETITION FOR WRIT OF MANDAMUS1
Hearing Date:
Hearing Judge:
Time:
Place:

November 19, 2015


Hon. Teri L. Jackson
1:30 pm
Dept. 503

Date Action Filed:

December 26, 2014

JEREMY RICKS, TRACY KIRKHAM, and


JOE COOPER, and Does 6 to 10;

25
Real Parties in Interest.
26
27
28

The only correction contained in this brief is to the title of the brief on the caption page.

Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

TABLE OF CONTENTS

1
2
3

TABLE OF AUTHORITIES ......................................................................................................... iii


INTRODUCTION ...........................................................................................................................1

STATEMENT OF FACTS ..............................................................................................................1

I.

THE PROPERTY ....................................................................................................1

II.

THE PROJECT ........................................................................................................2

III.

CATEGORICAL EXEMPTION .............................................................................3

IV.

THE PLANNING COMMISSIONS CONDITIONAL USE


AUTHORIZATION. ................................................................................................4

V.

BOARD APPROVAL OF ADMINISTRATIVE CEQA AND CU APPEALS ......5

8
9
10
11

STANDARD OF REVIEW .............................................................................................................6


ARGUMENT ...................................................................................................................................8
I.

THE PROJECT HAS NO SIGNIFICANT ENVIRONMENTAL IMPACTS. .......8

12
13

1.

Construction of the Project Will Not Cause Significant Impacts. ...8

2.

The Project Will Not Significantly Impact Public Views from the
Coit Tower or Pioneer Park. ..........................................................10

3.

No Significant Geotechnical Impacts Exist. ..................................12

4.

The Driveway Placement Is Not a Significant Environmental


Impact. ...........................................................................................13

14
15
16
17

II.

NO UNUSUAL CIRCUMSTANCES DEFEAT THE EXEMPTION. .................14

18

1.

The Project is Not Located at a Sensitive Intersection. .................14

2.

The Project Is Consistent With City Policies Regarding Public


Views. ............................................................................................15

3.

The Project Sites Topography is Not Unusual. ............................16

4.

Petitioner Has Not Demonstrated that the Project Will Have


Environmental Impacts. .................................................................16

19
20
21
22
23
24
25
26
27
28

III.

THE CITY IMPOSED NO MITIGATION MEASURES. ....................................17


A.

Because The Project Does Not Have a Significant Environmental


Impact, the Conditions Imposed Do Not Constitute Mitigation Measures.17

B.

The Boards Conditions Merely Ensure Compliance with State and


Local Law, Not Mitigation Measures. .......................................................18
1.

The Construction Conditions Are Merely Generally Applicable


Regulations. ...................................................................................18

2.

The Proposed Mirror and Signage at the Project Are Not


Mitigation.......................................................................................20
i

Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

1
2
C.

3.

The City Did Not Improperly Defer Geotechnical Mitigation of


the Project. .....................................................................................20

4.

Petitioners Cited Authorities Are Irrelevant. ................................21

The Boards Affirmance of the Categorical Exemption Did Not Depend


on Mitigation Measures. ............................................................................22

IV.

THE CITY CONSIDERED THE ENTIRE PROJECT. ........................................23

V.

THE CONDITIONAL USE PERMIT WAS PROPERLY ISSUED. ....................24

CONCLUSION ..............................................................................................................................25

7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
ii
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

TABLE OF AUTHORITIES

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17

State Cases
Assn for Protection of Environmental Values in Ukiah v. City Of Ukiah
2 Cal.App.4th 720 ......................................................................................................................18
Azusa Land Reclamation Company v. Main San Gabriel Basin Watermaster
(1997) 52 Cal.App.4th 1165 .......................................................................................................23
Berkeley Hillside Preservation v. City of Berkeley
(2015) 60 Cal.4th 1086 ...................................................................................................... passim
Citizens for Responsible Equitable Envir. Dev. v. City of San Diego
(2011) 196 Cal.App.4th 515 ..................................................................................................6, 13
City of Pasadena v. State of California
(1993) 14 Cal.App.4th 810 ........................................................................................................23
Hines v. Cal. Coastal Com.
(2010) 186 Cal.App.4th 830 ...............................................................................................7, 9, 13
Laurel Heights Improvement Assn v. Regents of Univ. of Cal.
47 Cal. 3d 376 ..............................................................................................................................7
Lotus v. Department of Transportation
(2014) 223 Cal.App.4th 645 ......................................................................................................21
Perley v. Board of Supervisors of Calaveras County
(1982) 137 Cal.App.3d 424 .......................................................................................................12
Robinson v. City and County of San Francisco
(2012) 208 Cal.App.4th 950 ........................................................................................................6

18
19
20
21
22
23
24
25
26
27
28

Salmon Protection & Watershed Network v. County of Marin


(2004) 125 Cal.App.4th 1098 ..............................................................................................17, 21
San Francisco Beautiful v. City and County of San Francisco
(1st Dist. 2014) 226 Cal.App.4th 1023 ..................................................................7, 9, 10, 17, 22
San Lorenzo Valley Community Advocates for Responsible Education v. San Lorenzo Valley Unified
School District
(2006) 139 Cal.App.4th 1356 ......................................................................................................8
Topanga Assn for a Scenic Community v. County of Los Angeles
(1974) 11 Cal. 3d 506 ................................................................................................................25
Tracy First v. City of Tracy
(2009) 177 Cal.App.4th 912 ............................................................................................1, 18, 20
Vineyard Area Citizens for Responsible Growth, Inc. v. City of Rancho Cordova
(2007) 40 Cal.4th 412 ..................................................................................................................6
iii
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

State Statutes & Codes


California Building Code Section 3306 .....................................................................................9, 19

Public Resources Code Section 21099(d)(1) .................................................................................10

3
4

San Francisco Statutes, Codes & Ordinances


Administrative Code Section 31.08(a) ...........................................................................................24

Building Code Section 106A.3.2.6 ................................................................................................10

Building Code Section 106A.3.2.6.3 .............................................................................................10

Building Code Section 106A.4.1.4 ..........................................................................................12, 13

Building Code Section 3306.7 .......................................................................................................19

Planning Code Section 101.1 .............................................................................................10, 15, 25

10

Planning Code Section 303 ............................................................................................................25

11
12
13

Transportation Code Section 107...................................................................................................19


Transportation Code Section 501.....................................................................................................9
Transportation Code Section 501(d)(2) ...........................................................................................9

14
Police Code Sections 2907-2909 .....................................................................................................9
15
16

Regulations
CEQA Guidelines Section 15124 ..................................................................................................23

17

CEQA Guidelines Section 15300.2(a) ...........................................................................................21

18

CEQA Guidelines Section 15301(d) ................................................................................................3

19
20

CEQA Guidelines Section 15303(b) ................................................................................................4


CEQA Guidelines Section 21168.5 .................................................................................................6

21
22
23
24
25
26
27
28
iv
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

INTRODUCTION

Petitioner, a group of neighbors who live nearby the site of a proposed small, 4 unit residential

2
3

project on Telegraph Hill (the Project), fails to demonstrate that the City improperly issued a

categorical exemption for the Project. The record contains substantial evidence that no unusual

circumstances defeat the categorical exemption. In the urban context of San Francisco, neither the fact

that a high number of pedestrians visit nearby Coit Tower and Pioneer Park, nor the sites topography

are unusual. And as the record amply demonstrates, the Project will not affect public views from that

park.
Furthermore, the record shows that the Project will have no environmental impacts, and that

9
10

therefore, no mitigation measures are appropriate or needed. To the contrary, the conditions the City

11

imposed are merely requirements that the Project comply with generally applicable regulations and

12

implement good-neighbor practices to address less-than-significant effects.


This Court should reject Petitioners Petition for a Writ of Mandamus.

13

STATEMENT OF FACTS

14
15
16
17
18
19
20
21
22
23
24
25
26
27
28

I.

THE PROPERTY
Real Parties in Interest, Jeremy Ricks, Tracy Kirkham and Joe Cooper (Real Parties or

Project Sponsor) propose to construct a small residential infill development and rehabilitate an
existing uninhabitable cottage on a largely vacant lot at 115 Telegraph Hill Boulevard (the
Property). (AR: 316, 264.4-264.15.)
The Property is a 7,517 square foot lot, located on the south side of Telegraph Hill Boulevard,
between Montgomery and Kearny Streets, and near to the top of Telegraph Hill and Coit Tower. (AR:
266.) It is located in an RH-3 Zoning District. (AR: 314, 319.) The site slopes downhill significantly
from east to west. (AR: 315.) It is bordered to the north by Filbert Street, which consists of a set of
concrete public stairs with no vehicle throughway, used by pedestrians to access the nearby Pioneer
Park and Coit Tower (the Filbert Steps). (AR: 266, 314-315.)
The surrounding neighborhood is developed with residential buildings, including many large
homes. (AR: 384.) Immediately east of the Property is a three-story-over-garage, 6,100 sf. residential
building containing three dwelling units at 109-111 Telegraph Hill Boulevard. (AR: 315). To the west
1
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

is a two-story, 1,250 square foot building with two units at 381-383 Filbert Street, followed by a three-

story-over-garage single family home at 391 Filbert Street. (AR: 315). Both of these buildings are

also adjacent to the Filbert Steps. (AR: 261.3261.5, 315). South of the Project site are additional

two- and three-story-over-garage residential buildings. (AR: 315.)


The Property was once comprised of three separate lots containing five buildings, but except

5
6

for the cottage, it has been vacant since 1997. (AR: 226, 1174-1184). As photos of the site show,

today the site is marked by overgrown vegetation and enclosed by a chain link fence. (AR: 264.12,

261.4, 315, 413.)

II.

10

THE PROJECT
On August 12, 2013, representatives of Real Party Jeremy Ricks filed an Environmental

11

Evaluation application with the San Francisco Planning Department (Department) in connection

12

with the Project. (AR: 265.) The Project calls for the construction of a new three-unit, 15,554 square

13

foot residential building containing a shared below-grade garage with three off-street parking spaces.

14

(AR: 381.) In addition, the Project would include renovation of the existing uninhabitable cottage at

15

the rear of the lot, resulting in a total of four dwelling units. (AR: 381, 264.1-264.15.)

16

The new structure is designed to appear as three single-family homes, each less than 40 feet

17

tall, which will step down the hill relative to its naturally sloping topography. (AR: 381, 261.20-

18

261.22.) The Projects highest point would sit 462 below and to the west of the public viewing area

19

in Pioneer Park. (AR: 401, 433.) The Projects height would decrease along the hill. The height of the

20

eastern-most unit will be approximately 2 3 shorter than the adjacent building; the middle building

21

segment would be shorter than the eastern-most unit; and the building segment to the west would be

22

shorter than the middle unit. (AR: 386.) Each of the three new units would occupy only 2310 of

23

frontage, consistent with the width of building facades found throughout the neighborhood, and would

24

feature a modern design with a scale and massing compatible with other homes in the immediate area.

25

(AR: 384, 264.1-264.15, 261.20-261.22.)

26

To provide view corridors from the Filbert Street Steps and Telegraph Hill Boulevard, a

27

minimum of three feet of clear space will be provided between each of the new units, and the faade of

28

the western-most unit has been set back five feet from the west property line, to allow for a large view
2
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

corridor between the Property and 381 Filbert Street. (AR: 263, 264.14.) Real Parties have committed

to working in good faith with the San Francisco Department of Public Works to develop a stewardship

and maintenance agreement for the landscaped area to the north of the Filbert Steps, adjacent to the

Property. (AR: 384.) The Projects below-grade garage will be accessed by a single curb cut along

Telegraph Hill Boulevard. (AR: 384.) These features are shown below (AR: 429):

6
7
8
9
10
11
12
13
14
In connection with the Project, Real Parties developed a construction plan proposing several

15
16

standard measures regarding construction activities. (AR: 321.) These measures included (i) providing

17

a well-lit and ventilated pedestrian path or tunnel to maintain public access along the Filbert Steps

18

during construction; (ii) permanently staging a flag person at the intersection of the Filbert Steps and

19

Telegraph Hill Boulevard throughout construction; (iii) staging concrete trucks off-site at the

20

intersection of Filbert and Kearny Streets, rather than on Telegraph Hill Boulevard, to avoid temporary

21

lane closures; (iv) requiring dump trucks and delivery vehicles to use an on-site staging area to turn

22

around, avoiding access to the Coit Tower lot; and (v) limiting deliveries to morning hours; (AR: 321,

23

410, 2081-2082.) Several of these measures were noted on the Project plans. (AR: 410.)

24

III.

25

CATEGORICAL EXEMPTION
On May 9, 2014, following a thorough evaluation of the Project description and related

26

materials, the Department determined that the Project is categorically exempt from California

27

Environmental Quality Act (CEQA) review under Class 1: Existing Facilities, for renovation of the

28

existing cottage (14 C.C.R. 1500 et seq. [CEQA Guidelines], Section 15301(d)), and Class 3: New
3
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

Construction and Conversion of Small Structures, which allows exemption for projects constructing up

to six new units (CEQA Guidelines Section 15303(b)) (Cat Ex). The Cat Ex was amended and re-

issued twice, to reflect minor changes in the Project description; the final Cat Ex was issued on

September 3, 2014. (AR: 316.) The determination that the Project was exempt remained the same. (Id;

also AR: 70-76.)


The Projects Certificate of Determination of Exemption from Environmental Review stated

6
7

that the Project would not cause a significant adverse impact upon any historic resource as defined by

CEQA. (AR: 70-74, 286-287, 319, 1069-1070.) The Certificate also stated that the Project would

have no significant geotechnical impacts. (AR: 72-73.) Specifically, it discussed site conditions and

10

topography, noting that the Department had reviewed a geotechnical report prepared for the Project

11

that included information gathered from a site visit and four soil borings.
The Cat Ex also noted that the proposed Projects construction activities would be coordinated

12
13

with the San Francisco Department of Public Works, SFMTA, and the Transportation Advisory Staff

14

Committee to ensure that construction activities are conducted in a manner that maintains circulation

15

on public rights-of-way, to the maximum extent feasible, resulting in no environmental impacts.

16

(AR: 73.) In addition, the Cat Ex concluded that any temporary, short-term, delay to vehicular or

17

pedestrian travel would not be a significant impact. (Id.)

18

IV.

19

THE PLANNING COMMISSIONS CONDITIONAL USE AUTHORIZATION.


On July 17, 2014, the Planning Commission held a public hearing to consider the Projects

20

Conditional Use (CU) application. Telegraph Hill Dwellers (THD) expressed concerns regarding

21

the Projects scale, massing, and design, as well as alleged environmental impacts to public views,

22

shadow, pedestrian safety, and geological conditions. They requested that the Commission require

23

additional environmental review. (AR: 783-922.)

24

Following a detailed discussion, the Commission continued the matter until September 11,

25

2014, to allow time for the Real Parties to incorporate suggested design revisions. Real Parties then

26

revised the Project to: (i) reduce the width of the building sections to create 3 clear spacing between

27

each unit and an 8 3 view corridor; (ii) add additional setbacks, windows and decking to provide

28
4
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

articulation and detail; (iii) reduce the overall height and area of each unit; and (iv) shift the garage

curb-cut east by 16 to further minimize any potential for pedestrian or vehicle conflict. (AR: 263.)

The Planning Commission approved the revised Project by a vote of five-to-two on September

11, 2014. (AR: 1125.20.) In connection with the CU, the Commission imposed several conditions of

approval. (AR: 404-409.) These included, among other standard measures, requiring (i) the general

contractor to ensure that construction workers park legally and not in the Coit Tower lot; (ii) the

project sponsor and construction contractor(s) to coordinate with the Traffic Engineering and Transit

Divisions of the San Francisco Municipal Transportation Agency (SFMTA), the Police Department,

the Fire Department, the Planning Department, and other construction contractor(s) for any concurrent

10

nearby projects to manage traffic congestion and pedestrian circulation; (iii) that there be no queuing

11

of construction trucks along Telegraph Hill Boulevard, and that all trucks waiting to unload material

12

shall be staged at a location offsite; (iv) that the project sponsor shall post signs or other devices to

13

alert pedestrians to vehicles exiting the garage; and (v) that the Project Sponsor install parabolic

14

mirrors to enhance the view of drivers exiting the garage. (AR: 404-409.)

15

V.

16

BOARD APPROVAL OF ADMINISTRATIVE CEQA AND CU APPEALS


Petitioner filed appeals of both the Projects CU authorization and Cat Ex determination to the

17

San Francisco Board of Supervisors on October 11 and October 14, 2014, respectively. (AR: 1543-

18

1569, 1561-1648). The Board of Supervisors heard the appeals jointly at a noticed public hearing on

19

November 4, 2014. (AR: 1015-1019.) Petitioner alleged that the Projects Cat Ex was improperly

20

issued because the Project would result in potentially significant impacts due to unusual

21

circumstances. (AR: 1026-1034, 1543-1560.) Petitioner claimed a number of environmental impacts

22

regarding construction practices, vehicle and pedestrian safety, historic resources, and slope stability,

23

but failed to provide any evidence supporting those claims. (AR: 1026-1034, 1543-1560.) Through

24

both written submittals and testimony at the hearing, Department staff responded to each of

25

Petitioners claims. (AR: 311-317, 754-782.) The Board of Supervisors then affirmed the Projects

26

Categorical Exemption determination by a vote of seven-to-three, with Supervisor Campos excused.

27

(AR: 47-50.)

28
5
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

After affirming the Cat Ex, the Board voted to amend the CU Authorization by modifying and

expanding upon conditions of approval that had been included in the Planning Commissions motion,

reflecting construction staging procedures that addressed the interest ofall the parties and

representatives of the nearby Garfield Elementary School. (AR: 1115-1124.) These conditions

included project sponsor obligations to (i) provide a well-lit, naturally ventilated pedestrian tunnel

throughout Project construction along the Filbert Street stair frontage; (ii) provide a flag person at the

top of the Filbert Stairs at all times during construction to monitor and direct construction and

pedestrian activities; (iii) provide that trucks waiting to unload materials will use an off-site staging

location and limit the hours of delivery; (iv) provide detailed construction plans to various City

10

departments; and (v) consult with Garfield Elementary regarding construction plans. (AR: 57-60.)
STANDARD OF REVIEW

11
12

A governmental agency's determination that [a particular] project [is] exempt from

13

compliance with CEQA requirements ... is subject to judicial review under the abuse of discretion

14

standard in section 21168.5 of the California Environmental Quality Act (CEQA) (Robinson v. City

15

and County of San Francisco (2012) 208 Cal.App.4th 950, 955 [internal quotation marks and citation

16

omitted] (Robinson).) Such an abuse is established if the agency has not proceeded in a manner

17

required by law or if the determination or decision is not supported by substantial evidence.

18

(Vineyard Area Citizens for Responsible Growth, Inc. v. City of Rancho Cordova (2007) 40 Cal.4th

19

412, 426-27 (citations and internal quotations omitted).)

20

Substantial evidence means enough relevant information and reasonable inferences from this

21

information that a fair argument can be made to support a conclusion, even though other conclusions

22

might be reached. (Citizens for Responsible Equitable Envir. Dev. v. City of San Diego (2011) 196

23

Cal.App.4th 515, 522.) Thus, the Court must uphold the Citys determination that the Project qualifies

24

for a categorical exemption as long as substantial evidence supports that determination, even if some

25

evidence exists to support a different conclusion. Substantial evidence includes fact, a reasonable

26

assumption predicated upon fact, or expert opinion supported by fact. Substantial evidence is not

27

argument, speculation, unsubstantiated opinion or narrative, [or] evidence that is clearly inaccurate or

28
6
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

erroneous. (Hines v. Cal. Coastal Com. (2010) 186 Cal.App.4th 830, 856-57 [citations and internal

quotation omitted].)

Once an agency determines that a project falls within a categorical exemption, the burden then

shifts to the challenging party to produce evidence showing that one of the exceptions applies to take

the project out of the exempt category. (San Francisco Beautiful v. City and County of San

Francisco (1st Dist. 2014) 226 Cal.App.4th 1012, 1013.)

Earlier this year the California Supreme Court clarified the standard of review that applies to a

claim that unusual circumstances precludes the use of a categorical exemption under CEQA

Guidelines Section 15300.2. (Berkeley Hillside Preservation v. City of Berkeley (Berkeley Hillside),

10

(2015) 60 Cal.4th 1086, 1092). The Court established a two-step inquiry. First, a court determines

11

whether substantial evidence supports the agencys determination that there are no unusual

12

circumstances. This is essentially [a] factual inquiry Accordingly, the agency serves as the

13

finder of fact and a reviewing court should apply the traditional substantial evidence standard. (Id. at

14

p. 1114 [internal citations omitted].) This means all inferences and disputes in the record are resolved

15

in favor of the agency, and the court must uphold the agencys determination if there is any

16

substantial evidence, contradicted or uncontradicted, to support it. (Id.; Laurel Heights Improvement

17

Assn v. Regents of Univ. of Cal., (1988) 47 Cal.3d 376, 393 [holding that the courts task is not to

18

weigh conflicting evidence and determine who has the better argument or whether an opposite

19

conclusion would have been equally or more reasonable].).

20

Only if the court finds that substantial evidence does not support the agencys determination of

21

no unusual circumstances does the court make a second inquiry. In that case, the court must then

22

review the agencys determination that there is no reasonable possibility of a significant effect on the

23

environment due to the unusual circumstance. For this second prong, the court applies the fair

24

argument standard. (Berkeley Hillside, supra, 60 Cal.4th at p. 1115.) Under the fair argument

25

standard, the agencys determination that the exemption applies must be upheld unless petitioners can

26

show a fair argument that the proposed activity may have a significant environmental impact. (Id.)

27
28

[T]o establish the unusual circumstances exception, it is not enough for a challenger merely to
provide substantial evidence that the project may have a significant effect on the environment. (Id. at
7
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

p. 1105.) Rather, the challenger has the burden to establish unusual circumstances by showing that

the project has some feature that distinguishes it from others in the exempt class, such as its size or

location, or with evidence that the project will have a significant environmental effect. (Id.) In

other words, the challenger must demonstrate not just that the project could have a significant

environmental effect, but that the project differs from the general circumstances of the projects

covered by a particular categorical exemption, and that those circumstances create an environmental

risk that does not exist for the general class of exempt projects. (San Lorenzo Valley Community

Advocates for Responsible Education v. San Lorenzo Valley Unified School District (2006) 139

Cal.App.4th 1356, 1394.) If there is nothing unusual about the circumstances of a project, and it

10

presents the same general risk of environmental impacts as the class of projects that the Natural

11

Resources Agency has already determined will not have a significant impact, then the exception will

12

not apply.

13

The Citys determination easily survives review under those standards.

14

ARGUMENT
THE PROJECT HAS NO SIGNIFICANT ENVIRONMENTAL IMPACTS.

15
16
17
18
19
20
21
22
23
24
25
26
27
28

I.

As Petitioner concedes, the Project falls within the Class 1 and Class 3 categorical exemptions
set forth by the CEQA Guidelines. (Pet.s Br. at 9-10.) In fact, this Project is a textbook example of
the type of small, urban infill project those exemptions were meant to apply to. Petitioner fails to
demonstrate that the Cat Ex nevertheless was improper. As the Departments thorough analysis and
other substantial evidence in the record shows, the Project has no significant environmental impacts,
even absent the conditions imposed by the Planning Commission and Board of Supervisors.
1.

Construction of the Project Will Not Cause Significant Impacts.

As the Department determined, construction activities associated with the Project would not
have any significant environmental impact, at either the Project site or at Garfield Elementary School.
First, the removal of dirt and debris and other hauling to and from the Project site would not
constitute a significant environmental impact. Petitioner misunderstands the weight limits for trucks,
leading to a gross overestimate of the number of truck trips required for construction work. (AR: 1880
[alleging the Project would require 10,000 truck trips].) In fact, San Francisco Transportation Code
8
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

Section 501 exempts construction trucks from the weight limit otherwise applicable on Telegraph Hill

Boulevard. (S.F. Transp. Code 501(d)(2).) The Project Sponsors representative testified before the

Board of Supervisors that, given this exemption, the number of truck trips required for both debris

hauling and other construction work would be about 8 percent of what the THD alleged before the

Board of Appeals. (See AR: 321, 1090.) Petitioner does not challenge that testimony. Moreover,

Petitioner provides no evidence that the truck trips will cause a significant impact.

Second, there is no significant hazard to pedestrians due to construction traffic. As a general

matter, all construction, including for this Project, must comply with all state and local code

requirements for pedestrian safety, including California Building Code Section 3306 (which sets forth

10

requirements for walkways, barriers, and railings), and the San Francisco Municipal Transit

11

Authoritys Regulations for Working in San Francisco Streets (commonly known as the SFMTA

12

Blue Book) (8th ed., Jan. 2012). These regulations require contractors to provide adequate paths of

13

travel along sidewalks, based on the volume of foot traffic; flag control of traffic to ensure safety

14

while construction vehicles are entering and exiting a work site; and coordination between different

15

contractors to ensure smooth traffic flow. (Blue Book at pp. 11-13.) Petitioner offers no evidence

16

that, despite Projects required compliance with all of these standard safety measures, pedestrians will

17

be unable to safely cross the street or the Project sites driveway during construction. (See San

18

Francisco Beautiful, supra, 226 Cal.App.4th at p. 150 [agency may rely on generally applicable

19

regulations to conclude a project has no significant environmental impact].) Substantial evidence

20

exists to support the Citys determination of no significant effect, and Petitioner offers no evidence to

21

the contrary. (See Hines, supra, 186 Cal.App.4th at pp. 856-57 [substantial evidence is not argument,

22

speculation, unsubstantiated opinion or narrative].)

23

Third, construction noise impacts would not constitute significant impacts because the Project

24

must comply with San Franciscos Police Code, which limits those impacts to less than significant

25

levels. For example, San Franciscos Police Code sections 2907-2909 set decibel limits for daytime

26

construction equipment noise, as well as a strict nighttime noise limit of 5 decibels of ambient noise,

27

the same limit that applies to other nighttime noise at residential properties. (See San Francisco

28

Beautiful, supra, 226 Cal.App.4th at p. 150.)


9
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

Fourth, San Francisco Building Code 106A.3.2.6, the Citys Dust Control Ordinance,

imposes extensive construction dust control requirements for this Project. As for all projects with the

potential to create dust, the Project Sponsor must water all active construction areas sufficiently to

prevent dust from becoming airborne; wet sweep or vacuum the streets, sidewalks, paths, and

intersections during excavation and dirt-moving activities; cover and brace large stockpiles of

materials; and use dust enclosures, curtains, and dust collectors in the excavation area. (S.F. Building

Code 106A.3.2.6.3) These extensive requirements ensure that dust will not create a significant

environmental impact. (See San Francisco Beautiful, supra, 226 Cal.App.4th at p. 150.)

2.

The Project Will Not Significantly Impact Public Views from the Coit
Tower or Pioneer Park.

10
The Project will not result in any impacts to views, for several reasons. First, under a recently
11
adopted amendment to CEQA, aesthetic and parking considerations of residential infill projects within
12
transit priority areas, such as the Project, are no longer considered impacts under the statute. (See
13
Public Resources Code Section 21099(d)(1) [aesthetics and parking impacts of a residential, mixed14
use residential, or employment center project on an infill site within a transit priority area shall not be
15
considered significant impacts on the environment]; see also AR: 320.)
16
In addition, even if Section 21099 did not apply, there is no significant impact on public views
17
because, as the Planning Commission found, the Project does not obstruct public views. It is
18
consistent with Planning Code Section 101.1, which mandates that the Citys parks and open space
19
and their access to sunlight and vistas be protected from development:
20

23

The project includes the infill development of three new dwelling units on a
largely vacant lot in a residential neighborhood. The project will not adversely
affect any public parks or open spaces. It is located below Coit Tower and
Pioneer Park on Telegraph Hill, and will incorporate green rooftops to ensure
that the Project blends with the hillside when viewed from above. It will not
adversely affect Coit Towers access to sunlight or public vistas.

24

(AR 14). Petitioner includes a diagram in its brief that purports to show that the Project would

25

obstruct protected public views. (Compare Pet.s Br. at p. 22 with figure from AR: 1931.) Ironically,

26

the diagram proves just the opposite the Project does not obstruct public views from Coit Tower or

27

Pioneer Park. It may partially block some views from the Filbert Steps, in the area immediately

28

adjacent to the Project, but those views are not protected under the General Plan. (AR: 1078 [the

21
22

10
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

General Plan and the Residential Design Guidelines do not protect private views. They also do not

protect views from the sidewalk through private property]; see also General Plan, Urban Design

Element, Policy 1.1; Policy 2.7; Residential Design Guidelines, p. 18 [explaining that views from

public areas, such as parks, are protected].)

The Planning Commission also found that the Project is consistent with the General Plan

Urban Design Element, and, more specifically, its policies regarding Telegraph Hill - including

provision of views of downtown. The Commission found that

8
9
10

The Project is compatible with Telegraph Hills special characteristics, in that


the buildings are designed to be consistent with the scale and massing of
surrounding properties [They] have been designed with a pedestrian scale and
texture, incorporating both landscaping and side setbacks along the west side of
each of the three new units, which provide for views of downtown.

11

(AR: 12 [emphasis added]; see also AR: 1074-75.) When asked at the Board of Supervisors hearing

12

if the Project violated General Plan policies intended to protect views, Department staff explained that

13

the General Plan and the Residential Design Guidelines do not protect private views, nor views from

14

the sidewalk through private property.

15
16
17

The General Plan does, however, protect the views from public vistas... It is our
opinion that both Pioneer Park and Coit Towers views of downtown are not
being obstructed by this Project. Since this Project is consistent with the height
of the adjacent neighbor, its actually shorter than the existing building to the
east, and it progresses down the hill as the General Plan instructs.

18

(AR: 1079 [emphasis added].). Further, Department staff explained that the Project was consistent

19

with the Urban Design Elements characterization of Telegraph Hill as an area with intimate

20

pedestrian scale and texture of streets and housing, with sudden and dramatic views of the Bay and

21

downtown through narrow openings. (AR: 1079, citing General Plan, Urban Design Element, [Policy

22

2.7].) This Project as designed, by providing the three foot setbacks between buildings and a five

23

foot side setback on the west side does just that, as directed by the General Plan. (AR 1079; 419.)

24

Petitioners make much of the fact that an individual Planning Commissioner expressed her

25

opinion that the Project may affect views. (Pet.s Op. Br. at 21.) But the opinion of an individual

26

commissioner is not determinative of the existence of potential impacts. To the contrary, courts have

27

upheld decisions that a project will have no significant environmental impacts despite dissenting

28

opinions by City officials, and even in the face of contrary findings and decision by a full planning
11
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

commission. (See, e.g., Bowman v. City of Berkeley (2004) 122 Cal.App.4th 572, 579 [affirming

adoption of mitigated negative declaration despite two dissenting votes by city council members];

Perley v. Board of Supervisors of Calaveras County (1982) 137 Cal.App.3d 424, 435-36 [approving

boards rejection of planning commissions determination that an EIR was required].)

In fact, as voluminous public testimony demonstrates, the Project will improve views from the

Filbert Steps, which currently look onto an abandoned, trash-strewn lot. (See, e.g., AR: 147 [referring

to site as an eye-sore], 150 [explaining that dumping, graffiti and loitering now occur on the vacant

lot], 152-53 [describing lot as a refuse collection point, empty and unattractive, and a fire

hazard]; AR: 122, 124, 135 [offering similar testimony].)2

10
11

In sum, substantial evidence supports the Departments determination that the Project will not
obstruct public views from Coit Tower or Pioneer Park.
3.

12

No Significant Geotechnical Impacts Exist.

13

Substantial evidence also supports the Departments conclusion that the Project would not have

14

significant geotechnical impacts. The first geotechnical report prepared for the Project found that risks

15

from liquefaction, surface rupture from earthquake faults, lateral spreading, densification and

16

landslides would be low, and contained specific recommendations to be considered during the DBI

17

permit review process. (AR: 1212-1221.) This report was prepared by a registered geotechnical

18

engineer at Earth Mechanics Consulting Engineers.

19

Furthermore, after a CU approval authorizes the overall approach and design a project, the

20

Department of Building Inspection will review building permit applications and may require

21

additional reports, surveys, and site monitoring to ensure slope stability. (AR: 758, 1069.) And as the

22

Department noted, the Property is subject to the Slope Protection Act of 2008, S.F. Building Code

23

Section 106A.4.1.4. This law requires the Project Sponsor to obtain approval of geological and

24

geotechnical reports regarding potential instability and to undergo design review for geological and

25

geotechnical issues. In addition, the DBI Director may require that DBIs Structural Advisory

26
27
28

Petitioner cites to the fact that the designer of Coit Tower in the 1930s may have expected a
southern view corridor. (Pet.s Br. at p. 21.) This is not determinative, nor does it mean that the
project significantly impacts views.
12
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

Committee review the Project. If the Committee determines that there is a reasonable likelihood that

the proposed design and construction would result in unavoidable unsafe conditions, DBI must deny

the building permit. (See S.F. Building Code 106A.4.1.4; AR: 1069.)

The two letters by Lawrence Karp, which THD submitted in their appeal of the Cat Ex, do not

invalidate the Citys determination of no significant geotechnical effects. The fact that one expert

reached a different conclusion than the City does not invalidate the Citys determination. (See

Citizens for Responsible Equitable Envir. Dev., supra, 196 Cal.App.4th 515 at p. 522.) Moreover, the

supplemental Project geotechnical report prepared by Cotton, Shires and Associates (CSA)

underscores the fact that substantial evidence exists to support the Citys categorical exemption. (See

10

Hines, supra, 186 Cal.App.4th at pp. 856-57 [substantial evidence includes expert opinion supported

11

by fact]; AR: 2208-2218.)

12

First, the CSA report noted that the alleged removal of lateral and subjacent support for

13

adjacent structures was not a legitimate concern. CSA explained that this typical concern is

14

addressed later in the development process by the Citys Building Code, pursuant to which City

15

engineers will review proposed engineering plans to ensure adequate shoring and stabilization work.

16

(AR: 2212-2213, citing S.F. Building Code 106A.6 and 106A.4.1.4.4.) Second, CSA explained

17

that the alleged need for dewatering, which Dr. Karp opined could lead to destabilization, was

18

unfounded. Based on its investigation of twelve other sites at this elevation on Telegraph Hill, CSA

19

concluded there should be no groundwater table at this elevation. (AR: 2214-2215.) Thus, the Karp

20

letters do not defeat the categorical exemption. (Berkeley Hillside, supra, 60 Cal. 4th at p. 1105.)

21
22

4.

The Driveway Placement Is Not a Significant Environmental Impact.

Substantial evidence also supports the Planning Departments determination that the Projects

23

driveway is safe for pedestrians. For example, only three cars would use the garage (see AR: 788);

24

both a stop sign and a crosswalk are located at the driveway, requiring drivers to turn into the

25

driveway at low speed (AR: 1068); and drivers will both enter and exit the driveway facing forwards,

26

increasing visibility (AR: 796). Petitioner offers no evidence to the contrary.

27
28
13
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

1
2
3
4
5
6
7
8
9
10
11
12
13

II.

NO UNUSUAL CIRCUMSTANCES DEFEAT THE EXEMPTION.


When issuing the Cat Ex, the City found that there was nothing unusual about the Project.

(AR: 330 [stating that there are no unusual circumstances surrounding the current proposal that
would suggest a reasonable possibility of a significant effect].) Later, Department staff rejected each
of Petitioners claims regarding the alleged unusual circumstances during the administrative appeals.
(AR: 314-338.)
Yet Petitioner continues to argue that the unusual circumstances precludes the Cat Ex
because the Projects location and site are unique. It posits: is there any other Telegraph Hill,
Pioneer Park, Coit Tower and Filbert Steps? (Pet.s Br. at p. 19.) This argument is a red herring, as
the same could be said of practically any site no two locations are exactly alike, and many are near
notable scenic or historic sites. The question, rather, is whether substantial evidence supports the
agencys determination that there are no unusual circumstances.
1.

The Project is Not Located at a Sensitive Intersection.

14

Petitioner claims the Project site is unusual because it is adjacent to a sensitive intersection

15

on a curvy road, near a transit stop, a pedestrian crosswalk, and a stop sign, in an area frequented by

16

visitors and tourists. (Pet.s Br. at p. 19.) But in San Francisco, these features are common. As

17

Department staff explained in their response to the Cat Ex appeal,

18
19
20
21
22
23
24
25
26

[I]n a city where tourism is one of three major industries (together with financial
services and technology), many roadways and sidewalks are heavily travelled,
whether by commuters or tourists. Thus, the intersection adjacent to the project
site is not unusual, but rather commonplace, given the context of San Francisco.
(AR: 318.) Staff added that the roadways and sidewalks that provide access to Coit Tower have been
designed to provide safe transportation to this tourist destination, like other roads that lead to other
heavily visited destinations in the City. (Id.) In addition, staff explained that locating a driveway near
that intersection was not unusual, because all sidewalks in San Francisco are in fact pedestrian
facilities; therefore, all driveways in the City cross the pedestrian right of way. (Id.; see also AR:
1067-68 [Department staff explaining that it is common for roadways and sidewalks in San Francisco
to be heavily travelled, and that the site was not unusual or dangerous].)

27
28
14
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

Thus, the Citys determination that conditions in the intersection immediately adjacent to the

Project were not unusual, but rather commonplace, especially in the urban context of San Francisco, is

supported by substantial evidence. (See Berkeley Hillside, supra, 60 Cal.4th at pp. 11181119

[agencies have discretion to consider conditions in vicinity of proposed project in determining whether

unusual circumstances exist].)


2.

6
7

The Project Is Consistent With City Policies Regarding Public Views.

Petitioner next claims that the Projects impacts on public views create unusual

inconsistencies with mandates in the Citys adopted land use plans, specifically, the Planning Codes

Priority Policies and the Residential Design Guidelines. (Pet.s Br. at pp. 20-21.) Petitioner appears to

10

be particularly concerned that the Project will block views of downtown from the stairway and

11

landings in Pioneer Park. (Pet.s Br. at p. 20.) Their arguments fail, for several reasons.

12

First, alleged inconsistencies with the General Plan or other City policies do not constitute

13

unusual circumstances. (Berkeley Hillside, supra, 60 Cal.4th at p. 1105 [holding that a challenger

14

has the burden to establish unusual circumstances by showing that the project has some feature that

15

distinguishes it from others in the exempt class, such as its size or location, or with evidence that the

16

project will have a significant environmental effect]; see also AR: 1071 [Department staff explains

17

that inconsistencies with plans and policies are not in and of themselves an impact under CEQA.

18

Rather, we look at inconsistencies to determine whether there would be any physical environmental

19

effects].)

20

Second, the Planning Commission, which reviews a projects consistency with City policies

21

(see San Francisco Charter, Section 4.105; Planning Code Section 101.1) determined that the Project

22

was consistent with the General Plan, the Residential Design Guidelines, and the Planning Code. (AR:

23

4-46 [Planning Commission Resolution Approving the CU authorization].) The Commission found

24

that the project will not adversely affect any public parks or open spaces. It is located below Coit

25

Tower and Pioneer Park on Telegraph Hill, and will incorporate green rooftops to ensure that the

26

Project blends with the hillside when viewed from above. It will not adversely affect Coit Towers

27

access to sunlight or public vistas. (AR: 14 [reviewing the Projects compliance with Planning Code

28

Section 101.1]; see also AR: 12 [reviewing compliance with the Urban Design Element and stating
15
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

that the Project was designed with a pedestrian scale and texture, incorporating both landscaping and

side setbacks along the west side of each of the three new units, which provide for views of

downtown]; AR 1079 [reviewing compliance with the Residential Design Guidelines and stating that

both Pioneer Park and Coit Towers views of downtown are not being obstructed by this Project.

Since this Project is consistent with the height of the adjacent neighbor, its actually shorter than the

existing building to the east, and it progresses down the hill as the General Plan instructs].)

7
8
9

The City's finding that there are no unusual circumstances regarding obstruction of public
views is supported by substantial evidence, and must not be disturbed.
3.

The Project Sites Topography is Not Unusual.

10

Lastly, Petitioner fails to demonstrate that the Projects topography is unusual, and that

11

therefore it would need a big excavation that would require dewatering, impair lateral and subjacent

12

support, and affect neighboring properties. (Pet.s Br. at 23.) As explained by the Planning

13

Department, the sites topography is not unusual in San Francisco. Slopes greater than 20% are not

14

unusual in San Francisco, a City with up to 48 recognized hills. Development on such lots is

15

routinely reviewed and construction undertaken in accordance with applicable City regulations

16

(and) the Department of Building Inspection (DBIs) permit review process. (AR: 318; see also AR:

17

757 [neither Appellant nor Mr. Karp have demonstrated that this depth [of excavation] is so unusual

18

that safety requirements could not be adequately addressed through DBIs permit review process];

19

see Berkeley Hillside, supra, 60 Cal.4th at pp. 1118-19 [agencies may consider conditions in a

20

projects vicinity to determine whether unusual circumstances exist].) As explained above, those

21

regulations ensure that construction of the Project will not have any environmental impacts.

22

4.

Petitioner Has Not Demonstrated that the Project Will Have


Environmental Impacts.

23
As discussed above, Petitioner has failed to establish that unusual circumstances exist due to
24
the Projects characteristics, such as size or location. Under Berkeley Hillside, a petitioner may also
25
demonstrate that unusual circumstances exist by showing that the project will have a significant
26
effect on the environment. (Berkeley Hillside, supra, 60 Cal.4th at p. 1105.) Petitioner here makes
27
only a half-hearted attempt to make this argument. (Op. Br. at 19.) But Petitioners arguments fail,
28
16
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

because substantial evidence supports the Planning Departments thorough analysis and conclusion

that the Project would not have any significant impacts. (See Section I, above.)3

III.

THE CITY IMPOSED NO MITIGATION MEASURES.

Petitioner also conflates the concepts of mitigation and run-of-the-mill conditions on a project

approval that have nothing to do with CEQA compliance. Because substantial evidence supports the

Citys finding that this Project has no significant environmental impacts, no mitigation was required.

Moreover, the alleged mitigations are for the most part merely requirements that the Project Sponsor

comply with applicable laws and regulations. And the Board of Supervisors requirement of a mirror

and signs at the Project driveway are simply good-neighbor provisions that address less-than-

10
11

significant impacts, and therefore do not defeat the categorical exemption.4


A.

Because The Project Does Not Have a Significant Environmental Impact, the
Conditions Imposed Do Not Constitute Mitigation Measures.

12
Projects with no significant effect on the environment are categorically exempt from CEQA
13
review. (See San Francisco Beautiful, supra, 226 Cal.App.4th at p. 1032 [quoting Salmon Protection
14
& Watershed Network v. County of Marin (2004) 125 Cal.App.4th 1098, 1102].) If a project may
15
have a significant effect on the environment, CEQA review must occur and only then are mitigation
16
measures relevant. (Id.) Thus, if no significant environmental impact otherwise exists, any
17
conditions placed on the project do not constitute mitigation.
18
Petitioner concedes that the Project falls within the Class 1 and Class 3 categorical exemptions
19
under the CEQA Guidelines, as the City determined. (Pet.s Br. at p. 9-10.) Yet Petitioner argues
20
21
22
23
24
25
26
27

Petitioner appears to obfuscate the Berkeley Hillside test at p. 25 of its brief, stating that
CEQAs unique fair argument standard applies to the question of whether a project proposed for a
categorical exemption meets the unusual circumstances exception vis a vis environmental impacts.
This is precisely the position the Supreme Court rejected. (See Berkeley Hillside, supra, 60 Cal.4th at
p. 1105 [to establish the unusual circumstances exception, it is not enough for a challenger merely to
provide substantial evidence that the project may have a significant effect on the environment.
Rather, the challenger has the burden to establish unusual circumstances by showing that the project
has some feature that distinguishes it from others in the exempt class, such as its size or location, or
with evidence that the project will have a significant environmental effect].)
4
In fact, Petitioners claims are ironic, given that Telegraph Hill Dwellers, which appears to be
the main member of Protect Telegraph Hill, actively negotiated with Real Party in Interest for
conditions such as these during the administrative appeals at the Board of Supervisors. (AR: 1116.)

28
17
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

without support that the conditions imposed by the Planning Commission and Board of Supervisors

were CEQA mitigation measures that were improperly incorporated into the project as part of the

categorical exemption. This argument ignores the fact that because the Project as originally proposed

had no significant impacts, no CEQA mitigation occurred. Substantial evidence, including the

Projects required compliance with state and local laws that address Petitioners concerns, supports the

conclusion that the Project as originally proposed would have no significant environmental effects.

Therefore, this Court should uphold the Citys determination.

B.

The Boards Conditions Merely Ensure Compliance with State and Local Law,
Not Mitigation Measures.

9
Furthermore, most of the conditions that Petitioner label as improper mitigation are really
10
nothing more than requirements that the Project Sponsor comply with generally applicable laws and
11
regulations and take other steps to address less-than-significant impacts. Compliance with City Codes
12
is not mitigation because, CEQA aside, the Project could not be approved absent compliance. (See
13
Assn for Protection of Environmental Values in Ukiah v. City Of Ukiah, (1991) 2 Cal.App.4th 720,
14
734-36 [EIR not required to address concerns about proper foundation construction and drainage,
15
because those concerns were already addressed by building code requirements]; Tracy First v. City of
16
Tracy (2009) 177 Cal.App.4th 912, 933 [city could rely on projects compliance with building code
17
standards for conclusion that it would not have a significant impact; hence no mitigation was
18
required].)
19
20
21

1.

The Construction Conditions Are Merely Generally Applicable


Regulations.

Petitioner mischaracterizes the construction-related conditions as unstudied construction

22

mitigation measures. But these conditions are not novel propositions that need to be studied. Instead,

23

they are typical construction management measures that, as Petitioner concedes, were part of

24

theproject plans. (Pet.s Br. at 12, AR 389.) Moreover, most of the construction-related conditions are

25

merely restatements of existing regulations that every project like this one would have to comply with.

26

First, the Boards requirement of a pedestrian tunnel along the Filbert Steps does not constitute

27

an impermissible mitigation. San Franciscos Building Code, which incorporates the California

28

Building Code, expressly requires a pedestrian walkway in front of this Project site. (S.F. Building
18
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

Code 3306.2; AR: 1082.) In addition, the Building Code requires covered walkways under

circumstances like this one, where the distance from the construction to the lot line is less than five

feet and the construction will be over six feet high. (S.F. Building Code 3306.7 & Table 3306.1.)

The condition therefore merely reiterates that the Project Sponsor must comply with these provisions

of the Building Code.

Second, Petitioner inaccurately claims the requirement for a flag person at Filbert Street and

Telegraph Hill Boulevard during construction is a mitigation measure. (AR 390). In fact, SFMTA

regulations always require flag-persons where workers or equipment temporarily block a traffic lane

for access into and out of a construction area. (SFMTA Blue Book at 115; S.F. Transportation Code

10
11

107.) Thus, this condition simply reflects a generally applicable regulatory requirement.
Third, the Boards requirement that the Project Sponsor must work with various permitting

12

agencies to develop a construction management approach cannot be considered mitigation under any

13

reasonable reading of CEQA. As a matter of law, the Citys various departments review every project

14

that requires their approval. It is typical for these departments to coordinate in order to ensure that the

15

departments decisions are consistent. That coordination often occurs, as it would here, through the

16

Transportation Advisory Staff Committee, a multi-agency body that includes the Municipal Transit

17

Authority, the Police Department, the Fire Department, the Department of Public Works, and the

18

Planning Department. (AR: 61.2.) If inter-departmental coordination were a mitigation measure, no

19

project in the City requiring multiple approvals could obtain a categorical exemption.

20

Fourth, the requirement that Petitioner consult with Garfield Elementary and the San Francisco

21

Unified School District before finalizing its construction staging, traffic and truck route plans is

22

merely a more specific articulation of a generally applicable requirement for all projects near schools.

23

The SFMTA Blue Book requires that a contractor shall give advance notice of construction activities

24

to the school principal and administration at any adjacent school. The Contractor is responsible for

25

making arrangements with the school officials to maintain all school bus loading zones and passenger

26

loading zones. (SFMTA Blue Book at p. 18.) And as discussed above in Part I, the Project is subject

27
28

available at https://www.sfmta.com/sites/default/files/pdfs/BlueBook8thEd_Accessible.pdf.
19

Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

to strict noise, dust and safety regulations. Thus, the condition of approval merely reiterates these

requirements.
2.

3
4

The Proposed Mirror and Signage at the Project Are Not Mitigation.

Petitioner offers no support for its contention that the requirement of a mirror to aid drivers

exiting the Projects driveway and signs warning pedestrians of the driveway crossing are improper

mitigation measures. As discussed above, the driveway does not create a significant environmental

impact. Thus the Project Sponsors agreement to nonetheless install additional features to enhance

pedestrian safety does not constitute mitigation. (See Wollmer v. City of Berkeley (1st Dist. 2011) 193

Cal.App.4th 1329, 1353 [rejecting the proposition that a positive effort between developers and a

10

municipality to improve the project for the benefit of the communitysomehow becomes an evasion

11

of CEQA].)

12
13

3.

The City Did Not Improperly Defer Geotechnical Mitigation of the Project.

Petitioner improperly claims that, by relying on future permit review to ensure compliance

14

with the Citys Codes, the City improperly deferred geotechnical analysis of the Project. As explained

15

above, the Project must comply with the Municipal Codes, which are generally applicable standards,

16

not mitigation specific to this project. (See Pet.s Br. at p. 24 fn 2.) The City did not unlawfully defer

17

mitigation of geotechnical impacts.

18

Instead, the Planning Commission and Board of Supervisors simply recognized that DBIs

19

review of the Project for Building Code compliance, which necessarily would not occur until after the

20

CU authorization, will ensure that slope stability requirements are met. (See, e.g., AR: 50-51 [Cmsr.

21

Antonini stating that concerns about shoring and slides are the province of DBI. [I]ts part of the

22

process of building something that that has to be done. So anything thats built there has to follow that

23

order of business to be able to be safe.]; AR: 56 [Cmsr. Johnson stating that DPW and DBI, not the

24

Planning Commission, are responsible for making sure that its going to workphysically and sort of

25

technically]; AR: 1113 [Sup. Chiu stating that the Slope Protection Act sufficiently ensures that

26

slope issues are addressed safely and appropriately].) It is appropriate for an agency to rely on a

27

projects compliance with building codes and standards to conclude there will be no impacts; this does

28

not constitute mitigation. (Tracy First, supra, 177 Cal.App.4th at p. 933.)


20
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27

4.

Petitioners Cited Authorities Are Irrelevant.

Lotus v. Department of Transportation (2014) 223 Cal.App.4th 645 does not compel a
conclusion that the City improperly imposed mitigation measures. In that case, the Court of Appeal
held that, where an EIR had been prepared, the agency failed to first determine whether the project
(the improvement of a highway through an old growth redwood forest) created a significant
environmental impact on old growth trees. Instead, the agency simply required avoidance and
mitigation measures to address possible impacts. The court held that this approach sidestepped
CEQAs requirements that if a significant effect exists, the EIR must evaluate a range of possible
mitigation measures, including potentially feasible alternatives to the project, and that the agency must
adopt an enforceable monitoring program. (Id. at 656.)
Likewise, Salmon Protection and Watershed Network v. County of Marin (2004) 125
Cal.App.4th 1098 (SPAWN) does not apply to this case. In that case, the court held that Marin
County improperly relied upon mitigation measures in granting a categorical exemption for the
proposed construction of a home next to a creek in a designated stream conservation area. While the
construction of a single family home ordinarily is categorically exempt, the Guidelines contain an
exception for projects that may impact an environmental resource of critical concern. (CEQA
Guidelines 15300.2(a).) The County conceded that the project was in a designated area of
environmental critical concern, and its findings demonstrated that development on the site could
have adverse impacts on the habitat of threatened or endangered species. (SPAWN, supra, 125
Cal.App.4th at p. 1106.) Despite these findings, the County granted a categorical exemption that was
expressly founded on dozens of conditions that have been applied to enhance mitigations and reduce
to a minimum the possibility of any adverse environmental impacts. (Id. at p. 1107.) The Court
found that the County improperly relied upon mitigation measures. (Id.)
Unlike in Lotus and SPAWN, here the City made a determination that under CEQA, no
significant impacts would occur, separate from and prior to its consideration of conditions to address
concerns that do not trigger further CEQA review. Substantial evidence supports the Citys
determination that the Project is categorically exempt, and Petitioner cites no evidence to the contrary.

28
21
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

The Project Sponsors agreement to take additional steps beyond what CEQA requires does not

constitute unlawful mitigation. (See Wollmer, 193 Cal.App.4th at p. 1353.)

C.

The Boards Affirmance of the Categorical Exemption Did Not Depend on


Mitigation Measures.

4
Conditions on a project endorsed by a governmental agency do not constitute mitigation, where
5
the record shows that those conditions were not the basis for the agencys conclusion that the project
6
qualified for a categorical exemption. (San Francisco Beautiful, supra, 226 Cal.App.4th at p. 1033.)
7
Here, as Petitioner concedes, the Project falls within the Class 1 and 3 categorical exemptions set forth
8
in the CEQA Guidelines. (Pet.s Br. At 9-10.) There is no merit to Petitioners contention that
9
mitigation measures were incorporated into the Project description in order to allow the Project to
10
qualify for a categorical exemption. In fact, the record demonstrates the opposite.
11
On November 18, 2014, the Board of Supervisors considered two issues with respect to the
12
Project: first, whether the Project was entitled to a categorical exemption, and second, whether to
13
approve a CU authorization for the Project. (AR: 1026 [President of the Board explaining that the
14
Board would first vote on whether to affirm the certification of the categorical exemption, and in the
15
event that the [categorical exemption] is affirmed, well then consider whether to affirm or overturn
16
the conditional use authorization].) The Board then passed Motion No. M14-189, affirming the
17
categorical exemption. (AR: 47-49.) Then, only after affirming the categorical exemption did the
18
Board consider imposing additional conditions on the Project, as part of the appeal of the CU
19
Authorization. During this second phase of the hearing, the City Attorneys Office publicly advised
20
the Board that any conditions of approval would be adopted through the Boards authority on appeal
21
of the conditional use authorization and are not to address significant impacts of the project under
22
CEQA. (AR: 1121.) In Motion No. M14-190, the Board then approved the CU with the conditions
23
now challenged by Petitioner.
24
The Boards conditions were not a basis for its affirmance of the Cat Ex. In San Francisco
25
Beautiful, supra, 226 Cal.App.4th at p. 1033, the Court of Appeal rejected an argument similar to
26
Petitioners. That case involved a project to install metal telecommunications cabinets in various
27
locations on sidewalks across the City. The project received a categorical exemption, which was
28
22
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

appealed to the Board of Supervisors. The petitioners in that case contended that the project sponsors

agreement at the Board of Supervisors hearing to take additional steps to benefit local residents

constituted improper mitigation. These additional steps included, among other things, expanded

public notice and a website, consideration of alternative locations and screening for some cabinets, and

payment for the cost of graffiti removal. (Id.) The Court of Appeal held that [a]lthough members of

the Board of Supervisors expressed approval of [the] agreement to increase public outreach, the record

does not show that the agreement was the basis for the Boards conclusion that the project qualified for

a categorical exemption or that it constituted a mitigation measure for a significant effect on the

environment. (Id.) Likewise, in this case the conditions imposed by the Board were not the basis

10

for the Boards conclusion that the project qualified for a categorical exemption or that [they]

11

constituted [ ] mitigation measure[s]. (Id.)


Azusa Land Reclamation Company v. Main San Gabriel Basin Watermaster (1997) 52

12
13

Cal.App.4th 1165 and City of Pasadena v. State of California (1993) 14 Cal.App.4th 810 are

14

irrelevant. In Azusa, the public agency concluded that the project likely would have a significant

15

environmental impact absent mitigation measures, and then issued a categorical exemption after taking

16

into account those mitigation measures. (52 Cal.App.4th at pp. 1199-1201.) And City of Pasadena

17

merely states the general rule that a categorical exemption determination is made before formal

18

environmental review. (14 Cal.App.4th at p. 820.)

19

Petitioners approach would transform all generally applicable regulations into project-specific

20

mitigation measures. Yet if generally applicable regulations amounted to mitigation measures, then all

21

zoning, building, and safety regulations would be mitigation measures and every building project in

22

the State would require an EIR. That clearly is not the law.

23

IV.

24

THE CITY CONSIDERED THE ENTIRE PROJECT.


Furthermore, the City properly considered the entire project in affirming the Cat Ex. Petitioner

25

makes only a weak argument to the contrary, merely listing several minor features related to the

26

project and at least one nonexistent one.

27

CEQA requires that a project description contain no more extensive detail beyond what is

28

necessary to understand its potential environmental impacts. (CEQA Guidelines Section 15124.)
23
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

Consistent with that mandate, Section 31.08(a) of the San Francisco Administrative Code requires a

project description with sufficient detail to convey the location, size, nature and other pertinent aspects

of the scope of the project as necessary to explain the applicability of a categorical exemption. The

project description in the Cat Ex satisfies his requirement.


The Project description states that the project would include replacement of a portion of the

5
6

concrete sidewalk, steps and retaining walls of Filbert Street. (AR: 71.) This refutes Petitioners claim

that the project description did not include improvements to the Filbert Steps to meet Department of

Public Works requirements and replacement and relocation of the steps. (Pet.s Br. at 16.) In

addition, contrary to Petitioners assertion, this work does not require a General Plan referral or major

10

encroachment permit. (See AR: 324.)


The Project description also states that the Project includes an approximately 160 square foot

11
12

(sf) demolition and exterior renovation of an existing 1000-square-foot cottage constructed in 1906

13

(AR: 70), despite Petitioners claim that the cottage renovation was not specified (Pet.s Br. at 16).

14

And the alleged reconfiguration of the sidewalk to relocate the stop sign and bus stop, which in fact

15

involves moving the stop sign one foot and leaving the bus stop in place, is not part of the Project

16

description but instead is governed by the Public Works Code. (AR: 321.)
Furthermore, descriptions of onsite and offsite staging areas are not required in the Project

17
18

description. As discussed above, the noise, safety, access and dust impacts of these staging areas are

19

governed by generally applicable state and local requirements. And Petitioners allegations that the

20

Project will remove part of a historic stone wall is simply inaccurate. (See AR: 28 [plans indicating

21

ROCK WALL TO REMAIN; AR: 319 [Planning Dept. determination that the wall will not be

22

removed and that no evidence exists that the wall is a historic resource].)

23

V.

THE CONDITIONAL USE PERMIT WAS PROPERLY ISSUED.

24

Lastly, Petitioner argues, almost in passing, that the Projects CU Authorization is

25

unsupported, because of the Projects alleged violations of General Plan and planning policies.

26

(Pet.s Br. at p. 25.)

27

As discussed above, both the Planning Commission and the Board of Supervisors granted the

28

Project a CU authorization, after finding that that it was compliant with all relevant General Plan and
24
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

Planning Code policies. (AR: 10-13 [finding the Project complies with the Housing, Transportation,

and Urban Design Elements of the General Plan]; 13-14 [finding the Project complies with the Priority

Policies of Section 101.1 of the Planning Code]; 60 [Board of Supervisors incorporates Planning

Commissions findings by reference].) The Commission also specifically found that the Project

satisfied all the conditions set forth in Planning Code Section 303, which provides criteria for the

Commission to consider when granting a CU authorization. (AR: 8-10.) The Commission found that

the Project was necessary and desirable because it would provide much needed family-sized housing

in a residential neighborhood, on a lot that had long been vacant and that was a detriment to the

neighborhood and create[d] a gap in the urban fabric. (AR: 8.) Further, the Commission found that

10

the Project was consistent with the neighborhood uses, and the proposed design was compatible with

11

the immediate vicinity. (AR: 9; see also 1073-74 [the Project will improve a dilapidated vacant lot

12

with a well-designed, high-quality residential development].)

13

In sum, there is ample evidence in the record to support the issuance of the CU authorization.

14

This Court should ignore Petitioners request to set aside the CU. (See, e.g., Topanga Assn for a

15

Scenic Community v. County of Los Angeles (1974) 11 Cal.3d 506, 514 [when reviewing an

16

adjudicatory decision such as the granting of a variance or the imposition of conditions on a project, a

17

reviewing court must resolve all reasonable doubts in favor of the local agencys findings and

18

decisions].)
CONCLUSION

19
20

For the reasons stated above, the City and Real Parties in Interest respectfully request that the

21

Court deny the Petition for Writ of Mandamus.

22

Dated: October 15, 2015

23
24
25
26
27

DENNIS J. HERRERA
City Attorney
ANDREA RUIZ-ESQUIDE
VICTORIA WONG
Deputy City Attorneys

DANIEL FRATTIN
REUBEN, JUNIUS & ROSE, LLP

By:___/s/ Andrea Ruiz-Esquide________


ANDREA RUIZ-ESQUIDE

By: ___/s/ Daniel Frattin_____________


DANIEL FRATTIN

28
25
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

PROOF OF SERVICE

1
2
3
4
5
6
7
8
9
10
11
12

I, LAUREN SKELLEN, declare as follows:


I am a citizen of the United States, over the age of eighteen years and not a party to the aboveentitled action. I am employed at the City Attorneys Office of San Francisco, City Hall, Room 234, 1
Dr. Carlton B. Goodlett Place, San Francisco, CA 94102.
On October 15, 2015, I served the following document(s):
CORRECTED JOINT BRIEF OF CITY AND COUNTY OF SAN FRANCISCO AND REAL
PARTIES IN INTEREST IN OPPOSITION TO PETITION FOR WRIT OF MANDAMUS
on the following persons at the locations specified:
Susan Brandt-Hawley
BRANDT-HAWLEY LAW GROUP
P.O. Box 1659
Glen Ellen, CA 95442
Telephone: (415) 938-3900
Facsimile: (415) 938-3200
susanbh@preservationlawyers.com

13

Attorneys for Petitioner


Protect Telegraph Hill

14

in the manner indicated below:

15
16
17
18
19
20
21
22
23
24

BY UNITED STATES MAIL: Following ordinary business practices, I sealed true and correct copies of
the above documents in addressed envelope(s) and placed them at my workplace for collection and mailing with
the United States Postal Service. I am readily familiar with the practices of the San Francisco City Attorney's
Office for collecting and processing mail. In the ordinary course of business, the sealed envelope(s) that I placed
for collection would be deposited, postage prepaid, with the United States Postal Service that same day.
BY PERSONAL SERVICE: I sealed true and correct copies of the above documents in addressed
envelope(s) and caused such envelope(s) to be delivered by hand at the above locations by a professional
is attached or
will be
messenger service. A declaration from the messenger who made the delivery
filed separately with the court.
BY ELECTRONIC MAIL: Based on a court order or an agreement of the parties to accept electronic
service, I caused the documents to be served electronically through File and ServeXpress e-service System in
portable document format ("PDF") Adobe Acrobat.

I declare under penalty of perjury pursuant to the laws of the State of California that the
foregoing is true and correct.
Executed October 15, 2015, at San Francisco, California.
/s/ Lauren Skellen
LAUREN SKELLEN

25
26
27
28

26
Opp. Brief; Case No. CPF 14-514060

n:\land\li2015\150674\01054352.doc

Page 1 of 2
Your transaction has been successfully submitted to File & ServeXpress. Your transaction information appears below. To print this
information for your records, click anywhere on the transaction information, then click the browser Print button.
For a formatted copy of this information, obtain a transaction report.
To perform another transaction, click Begin a New Transaction.
To exit Filing & Service, click Return to My File & ServeXpress.
TIP: Receive notifications of new Filing & Service activity that match your search criteria. Click on the Alerts tab.

File & ServeXpress Transaction Receipt


File & ServeXpress Transaction ID:
Submitted by:

58024827
Lauren Skellen, City Attorneys Office-San Francisco

Authorized by:

Victoria Wong, City Attorneys Office-San Francisco

Authorize and file on:

Oct 15 2015 3:04PM PDT

Time received by San Francisco County: Pending


Court:
Division/Courtroom:

CA Superior Court County of San Francisco-Civil


N/A

Case Class:
Case Type:
Case Number:

Civil-General Civil-Unlimited - $25,001+


Writs of Mandate/Proh/Certi/Admin Agen (Civil 2)
CPF-14-514060

Case Name:

Protect Telegraph Hill vs City & County Of San Francisco et al

Transaction Option:

File and Serve

Billing Reference:
Read Status for e-service:
Note to Clerk:

150674
Not Purchased
The only correction contained in this brief is to the title of the brief on the caption page. We
are exempt from filing fees.

Documents List
1 Document(s)
Attached Document, 31 Pages
Document Type:
Brief

Document ID: 75304567


Access:
Public

PDF Format | Original Format


Statutory Fee:
Linked:
$0.00

Document title:
CORRECTED JOINT BRIEF OF CITY AND COUNTY OF SAN FRANCISCO AND REAL PARTIES IN INTEREST IN OPPOSITION TO PETITION FOR
WRIT OF MANDAMUS
Expand All
Sending Parties (2)
Party
Party Type
Attorney
Firm
Attorney Type
City & County of San Francisco Respondent Wong, Victoria
City Attorneys Office-San Francisco Attorney in Charge
City & County of San Francisco Respondent Ruiz-Esquide, Andrea City Attorneys Office-San Francisco Attorney in Charge
Recipients (2)
Service List (2)
Delivery
Option

Party

Party Type

Attorney

Service

Cooper, Joe

Real Party in
Interest

Frattin, Daniel A

Service

Protect Telegraph
Hill

Petitioner

Brandt-Hawley,
Susan

Firm
Reuben Junius & Rose
LLP
Brandt-Hawley Law
Group

Attorney Type
Attorney in
Charge
Attorney in
Charge

Method
EService
EService

Additional Recipients (0)

Case Parties

Begin a New Transaction

Return to My File & ServeXpress

Print

Transaction Report

https://secure.fileandservexpress.com/WebServer/WebPages/FileAndServe/prcReviewSubmit.asp?doWh... 10/15/2015

Page 2 of 2

About File & ServeXpress


Resource Center

FAQs

Terms & Conditions

Client Support
1-888-529-7587

Privacy

2015 File &


ServeXpress, LLC. All rights

support@fileandservexpress.com
Chat Online

reserved.

https://secure.fileandservexpress.com/WebServer/WebPages/FileAndServe/prcReviewSubmit.asp?doWh... 10/15/2015

Potrebbero piacerti anche