Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abhishek
A
Project Report
On
MUMBAI METRO ONE PVT. LTD.
Submitted in partial fulfillment
Of the requirement for the award of the degree of
Bachelor of Technology
In
Civil Engineering
By
Abhishek Jain
10ce000708
Submitted to
2|Page
CERTIFICATE
This is to certify that the Internship project entitled Mumbai Metro being
submitted by Abhishek Jain, in fulfillment of the requirement for the award of
degree of Bachelor Of Technology in Discipline of engineering, has been
carried out under my supervision And guidance. The matter embodied in this
thesis has not been submitted, in part or in Full, to any other university or
institute for the award of any degree, diploma or Certificate.
3|Page
ACKNOWLEDGEMENT
4|Page
CONTENTS
A GLANCE OF MUMBAI METRO ONE ......................................................................................... 6
1.
5|Page
Figure 1.1
6|Page
7|Page
4) Receiving Station:
Receives the 33KV of power supplied from the grid for running of metro.
8|Page
5) Auxiliary substation 2:
At this station 33 KV is lowered to 22KV
6) Auxiliary Substation 3:
At this station 33KV is lowered to 11KV
7) Administration Building:
This building has 2 basements for placing machinery, a ground floor, 3
podiums for car parking, and 4 floors of office space for administration purpose.
10) Store:
Houses the mechanical spare parts for stock.
9|Page
10 | P a g e
Another vehicle known as CMRV is also stationed which has all the spare
parts and repairing functionalities for small repairs on the tracks for the rolling
stock and its related items
11 | P a g e
2.2
Package
Awarded to
Trackwork
Indra
E&M
ABB
Escalators
Schindler
Lifts
OTIS
12 | P a g e
3. ROOF WATERPROOFING
3.1 INTRODUCTION
Waterproofing is a treatment of a surface or structure to prevent the passage of
water under hydrostatic pressure. Waterproofing barrier system may be placed
on the positive or negative side. Water may be forced through building
members by hydrostatic pressure, water vapour gradient, capillary action, winddriven rain, or any combination of these. This movement is aggravated by
porous concrete, cracks or structural defects, or joints that are improperly
designed or installed. Leakage of water into structure may cause structural
damage, and invariably cause damage to the contents of the structure.
New roofs RB or RCC slabs must be constructed specified by the designer.
Roof waterproofing is a widely misunderstood subject. Often inadequate
attention given during the construction of RB or RCC roof slab, wrong products
used for waterproofing and generally insufficient treatment given, lead to
leakage. Movement because of structural deflection, settlement, etc. and steep
temperature variation being exposed, cause development of cracks in the roof
slab and water start leaking from these cracks.
While constructing RCC roof slab, it should be borne in mind that the practice of
using concrete which is not watertight and placing too much reliance on the
waterproofing measures is not desirable. Concrete should be made watertight
in itself and the waterproofing method should be looked upon as additional
safety devices.
The grade of roof slab concrete shall be strictly as specified by the designer.
The concrete materials should be properly proportioned, maintaining the
specified maximum water, cement ratio, minimum cement content and required
workability. The concrete should be admixed with a Superplasticiser.
13 | P a g e
Figure 3.1
14 | P a g e
Figure 3.2
Figure 3.3
15 | P a g e
e. Difficult to insulate - Block has a very low "R" value and generally, walls
must be insulated by adding width to them - decreasing available floor
square footage.
Figure 4.1
16 | P a g e
5.1 INTRODUCTION
Cement concrete paving blocks are precast solid products made out of cement
concrete. The product is made in various sizes and shapes viz. rectangular,
square and round blocks of different dimensions with designs for interlocking of
adjacent tiles blocks. The raw materials required for manufacture of the product
are Portland cement and aggregates which are available locally in every part of
the country.
Interlocking Concrete Block Pavement (ICBP)
has been extensively used in a number of countries for quite some time as a
specialized problem-solving technique for providing pavement in areas where
conventional types of construction are less durable due to many operational
and environmental constraints. ICBP technology has been introduced in India in
construction, a decade ago, for specific requirement viz. footpaths, parking
areas etc. but now being adopted extensively in different uses where the
conventional construction of pavement using hot bituminous mix or cement
concrete technology is not feasible or desirable.
17 | P a g e
5.2 APPLICATION
3. Medium
Traffic: Boulevard,
City
Streets,
Small
Market
Roads,
18 | P a g e
a) Proportioning
b) Mixing
c) Compacting
d) Curing
e) Drying
A concrete mix of 1:2:4 (cement: sand: stone chips) by volume may be used for
cement
concrete mix should not be richer than 1:6 by volume of cement to combined
aggregates before mixing. Fineness modules of combined aggregates should
be in the range of 3.6 to 4.0. All the raw materials are placed in a concrete
mixer and the mixer is rotated for 15 minutes. The prepared mix is discharged
from the mixer and consumed in the next 30 minutes.
Vibrating table may be used for compacting the concrete mix in the moulds of
desired sizes and shapes. After compacting the blocks are remolded and kept
for 24 hours in a shelter away from direct sun and winds. The blocks thus
hardened are cured with water to permit complete
19 | P a g e
5.4 ADVANTAGES
ICBP tolerates higher deflections without structural failure and will not be
affected by thermal expansion or contraction.
ICBP does not require curing, and so can be opened for traffic
immediately after construction.
Maintenance of ICBP is easy and simple and it is not affected by fuel and
oil spillage.
Low maintenance cost and a high salvage value ensures low life cycle
cost.
5.5 LIMITATIONS
High quality and gradation of coarse bedding sand and joint filling
material are essential for good performance.
20 | P a g e
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
Cleaning of surface
x.
Filling any remaining empty portions in the block layer especially near
edge restraint blocks with in situ concrete.
Figure 5.1
21 | P a g e
Figure 5.2
Figure5.3
6. BALLAST TRACK
6.1 INTRODUCTION
Considering extended experience and capital investment constraints, it is
proposed to adopt ballasted track for running freight trains with axle loads of
32.5 tones and passenger trains at a speed of 250 280 kmph. A typical
railway track consists of superstructure (rails, fastenings and sleepers) and substructure (ballast, sub-ballast and formation including sub-grade). The function
of the ballast is to transfer the load from the super structure to the sub grade.
Performance of the track system depends on the effectiveness of the ballast in
providing drainage, stability, flexibility, uniform support to the super structure
and distribution of the track loading to the sub grade and facilitating
maintenance.
Increase in axle loads, traffic
density and speed increase the rate of settlement of the track. And to keep this
within permissible limits, stresses in sub grade should be reduced suitably to
ensure stability of track parameters. There are two modes to achieve this- either
by strengthening the track superstructure or by strengthening the track sub
structure. Studies worldwide have shown that strengthening of track super
structure does not help much in reducing sub grade stresses and, therefore, its
rate of settlement. Numerical analysis using finite element modeling carried in
RDSO, Lucknow in collaboration with IIT/Kanpur have shown that sub grade
stresses reduce marginally ( 4 to 6%) with the increase in rail section or sleeper
density. But the stresses reduce drastically with the depth of construction, i.e.
total depth of ballast and sub-ballast.
22 | P a g e
The ballast should be clean and graded crushed stone aggregate with
hard, dense, angular particle structure providing sharp corners and
cubical fragments with a minimum of flat and elongated pieces. These
qualities will provide for proper drainage of the ballast section.
The ballast must have high wear and abrasive qualities to withstand the
impact of traffic loads without excessive degradation. Excessive abrasion
loss of an aggregate will result in reduction of particle size, fouling of the
ballast section, reduction of drainage and loss of supporting strength of
the ballast section.
The ballast particles should have high internal shearing strength to have
high stability.
23 | P a g e
Figure 6.1
Figure 6.3
24 | P a g e
Figure 6. 2
Figure 6. 4
7. PILE
7.1 INTRODUCTION
cast in situ.
The pile may be placed separately or they may be placed in a form of cluster
throughout the length of the structure.
The load of the structure is transmitted by the piles to the hard stratum below
or it resist by the friction developed on the side of pile.
In this project all piles are cast in situ and load transmitted by the piles to the
rock strata is considered for design.
Anchor piles are used in construction of water treatment plant.
Shore piles are used in construction of water tank and waste water treatment
plant.
25 | P a g e
1. Survey
Survey points were first marked at points where boring has to be carried out.
Two reference points was also marked which are at right angles with respect
to the point of boring to serve as reference during the boring operation.
2. Boring
Boring was carried out by rotator driller and by conventional tripod method
where working space was limited. All bores are circular in shape.
A MSS liner was used up to a depth of 6.5m to avoid collapsing of surrounding
soil.
Three types of augers were used namely depending on the requirement of
Soil Auger
Rock Auger
Cleaning bucket
After socketing has been done into the rock material attachment bucket was
lowered inside the bore to clean up the bottom of the bore.
Quality of Strata is checked by soil auger by applying 10 bar pressure for 10
minutes, if the penetration is less than 300 mm then it signifies rock material is
encountered, if not soil is still present
26 | P a g e
4. Sounding
Sounding is performed to check the depth of bore achieved at regular stages
5. Concreting
Concreting in the pile shall be produced as per the approved design mix at the
centralized plant at the casting yard and transported by the transit mixture to the
pouring location.
Termite method for concreting was implemented for the piles.
The Diameter of Termite used is 250 mm & 200 mm.
Before pouring concrete slump shall be checked at pouring location.
Concreting is done in a single go and for every type of pile; the start of
concreting is not performed until and unless the required amount of concrete for
pile is at the site.
Concreting was performed in less than 6 hours of the construction of the bore.
27 | P a g e
It is made sure that the pipe used for draining the concrete into the bore is
kept at least 150 to 300 mm far from the base of the bore.
It is also made sure that it is always submerged at least 1 to 2 m inside the
concrete.
For 0.5 m diameter pile concrete required for 1 m increase in height is
0.193and that for 1.0 m pile is 0.783.
Concrete should be continuously in one pouring.
28 | P a g e
8. EXPANSION JOINT
are
commonly
found
between
sections
of buildings, bridges, sidewalks, railway tracks, piping systems, ships, and other
structures.
Bridge expansion joints are designed to allow for continuous traffic
between
structures
accommodating
movement,
shrinkage,
temperature
Figure 8.1
29 | P a g e
9. CONCLUSION
This intern gave me a whole new side of civil engineering construction in the
real scenario. The training under Mumbai metro one project has given me first
hand exposure to the practical aspects of engineer, the challenges faced, the
way they tackle the problem right from conception stage, design, planning
leading to its execution and of course, the importance of an engineer in this
world.
A very friendly environment is prevalent in Mumbai Metro One. It was a place
where i had chance to mingle among engineers from different Companies
though working on a single platform and learn about each of their views.
On the whole, my training in Mumbai metro one was an enjoyable and
enlightening experience.
30 | P a g e