SEWP ZG622
Course Title
Type of Exam
Closed Book
Weightage
30 %
Duration
90 minutes
Date of Exam
No. of Pages : 2
No. of Questions : 9
Session : FN
Note:
1. Please read and follow all the instructions given on the cover page of the answer script.
2. Start each answer from a fresh page. All parts of a question should be answered consecutively.
3. Please answer the questions in the order in which they appear in the question paper.
Questions 1 to 5 each carry 1 mark and negative marking (-1) for each incorrect answer (1x5 =5)
1. Parkinsons Law states that Work expands to fill the time available. Which of the following
statement(s) does this law try to explain:
a) If you allot more time than is required for the job the extra time really does not appear to be extra
but gets consumed in the same work.
b) More work gets done if there is more time.
c) When you have more time the boss gives you more work to utilise your time better.
d) If you have more time you become inefficient and waste your time on the work.
2. Define payback period in financial terms.
3. Pick the odd one out and justify your answer
a. Quality b. Design c. Configuration d. Communication
e. Metrics
4. If uncertainty and complexity in a software project are low, then we can use:
a) Agile methodology
b) Prototyping Model
c) Waterfall Model
d) Incremental Model
Justify your answer.
5. When is the risk and uncertainty in a project's life cycle at the highest? Justify your answer.
A. start
B. design
C. closing
D. implementation
Questions 6 carry 10 marks; Questions 7 to 9 each carry 5 marks
1X10 + 3X5 = 25
6. Describe the Project in which you are currently member or team leader or manager (or whatever role
you play) by identifying the Project Goals, Development Model, Business Model and sample Metrics
used for tracking project progress. Draw the Project organization chart. Describe the functions of each
role in realizing the project goals.
Marks [10M: 3 + 3 +
4]
7. For the following table work out the Net Profit, Payback period, ROI and compare them from each
of the perspectives and rank the projects:
5 Marks
Period
Project1
Project2
Project3
Project4
Year0
50,000
1,00,000
75,000
1,00,000
Year1
5,000
10,000
20,000
20,000
Year2
20,000
50,000
20,000
20,000
Year3
30,000
20,000
40,000
20,000
Year4
5,000
20,000
10,000
50,000
8. For a moderately complex system with a count of 3 as the external input, external output and inquiries
and a count of 4 for internal logical files and external logical files, calculate the FP using Function point
analysis method of Albretch. Assume the complexity multiplier 4, 5, 4, 10, 7 for the EI, EO,IQ, ILF and
ELF respectively. The value adjustment count factor is 46. With a productivity of 12 FPs per month what
is the effort required for the project?. If the project is of 3 months duration, what is the team size required
for the project?
5 Marks
9.
What is the difference between direct and indirect measures in software engineering process?
5 Marks