COMPANY:

Agip Kazakhstan North Caspian Operating COMPANY

DOCUMENT NUMBER:

PROJECT:

KE01-00-000-KD-E-SF-0020-000

Kashagan Development Experimental Program


ASSET:

Kashagan
SUB PROJECT:

JOB NO:

GENERAL

180375

DOCUMENT TITLE:

HOLDS

SHEET NR.

1 OF 33

NO

CONTRACTORS NUMBER:

PROJECT SPECIFICATION FOR


ELECTRICAL INSTALLATION AND TESTING

ABSTRACT

This document specifies the minimum


requirements and working practices to be
adopted during the installation of electrical
equipment,
materials
and
systems
associated with the onshore and offshore
facilities.

D02
D01
F01
P01
P00

REV.

Re issued for Detail Design


Issued for Detailed Design
Approved for FEED
Issued for Company Review
Issued for internal review

REASON FOR ISSUE

SK
TW
AG
BM
SD

PREPD BY

GCC
RF
TW / MK
SD
BM

CHKD BY

DRW
RF
BM
BM
BM

DS
JT
MP
MP
MP

Lead
Eng

Eng
Mgr

RE
GN
GN/DW

11/02/2008
25/08/04
01/07/03
09/04/03
11/02/03

Company

APPRVD BY

DATE

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

REVISION DESCRIPTION SHEET


Rev.

Para.

Revision Description

P00

Issued for Internal Review

P01

Issued for Client Review

F01

AGIP comments incorporated.


Sections and paragraphs re-numbered in line with project guidelines for specifications
3.1.3
6.4

D01

Corrections to Russian Standards numbers and titles.


Cable separation/segregation details and trench depths added.
Issued for Detailed Design. Project number revised

D01

3.1.3

PUE referenced as applicable to onshore only.

D01

3.1.3

VSN 59-88 reference deleted.

D01

3.1.3

SN 174-75 reference deleted.

D01

3.1.3

RDS RK 4.04-191-02 reference deleted.

D01

3.1.3

SNiP 3.05.06-85 reference deleted.

D01

3.1.3

18220f 07.12.2000g reference deleted.

D01

3.1.3

GOST 28668.1-91 reference deleted.

D01

3.1.3

GOST 22789-94 reference deleted.

D01

3.2

D01

5.5.1

Generation system - added reference to onshore and offshore facilities. Added reference to
neutral earthing via earthing transformer.
Offshore Complex D essential generation revised to emergency generation.
Offshore motors above 2000kW service voltage revised to 6kV or 10kV via unit transformer from
the 35kV system.
400V motors clarified for Building Services and special cases.
Added Trace Heating Supplies.
Pipeline communication DC supply earth polarity changed from negative to positive.

D01

5.5.2

Power supply arrangements reference revised to include offshore.

D01

6.2.1

Hold removed cables / hot surfaces clearance detailed.

D01

6.3.10.1

Requirements for the delivery of various battery types and their state of charge, etc. given in
greater detail.

D01

6.4.2.1

Hold removed cables separation distance added.

D01

6.4.3.16

LV / HV cables separation details added. Revised to refer to Approved contract drawings.

D01

6.4.3.18
6.4.3.20
6.4.4.11

Revised to refer to Approved contract drawings.

D01

6.4.4.5

Trench depth for cables rated less than 35kV rvised from 900mm to 1000mm..

D01

6.6.2.2

Added minimum earth conductor cross section. Added reference to non acceptability of multiple
connections on any earth connection point.

D02

5.5.1

Changes made in Cell of Motors up to 350kW inclusive & Process Heaters above
250kW

D02

5.5.2

Changes in the Document Numbers and Names

D02

6.4.3.5

Addition of L.V Multicore Specification

D02

6.4.3.16

Addition of Notes

ORDER OF PRECEDENCE: Wording altered.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 2 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

D02

6.4.3.23

Hold
No.

Para.

Addition of Company Approval


Description of Hold

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 3 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

CONTENTS

1.
1.1
1.2
1.3

INTRODUCTION
PURPOSE AND SCOPE
DEFINITIONS
UNITS OF MEASUREMENT

2.
2.1
2.2

SCOPE
SUPPLIERS SCOPE OF SUPPLY
EXCLUSIONS TO THE SCOPE OF SUPPLY

3.
3.1
3.2
3.3

CODES, STANDARDS, REGULATIONS AND REFERENCES


CODES, STANDARDS, REGULATIONS AND REFERENCES
ORDER OF PRECEDENCE
DEVIATIONS AND EXCLUSIONS

4.
4.1
4.2
4.3

HEALTH, SAFETY AND ENVIRONMENTAL REQUIREMENTS


ENVIRONMENTAL CONDITIONS
AREA CLASSIFICATION
HEALTH, SAFETY AND ENVIRONMENTAL REGULATIONS

5.0
5.1
5.2
5.3
5.4
5.5
5.6

GENERAL DESIGN REQUIREMENTS


INSTALLATION AND OPERATING REQUIREMENTS
DESIGN LIFE
NOISE LIMITS
VIBRATION LIMITS
UTILITIES
PROVEN EQUIPMENT AND MATERIAL CRITERIA

6.0
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11

EQUIPMENT INSTALLATION REQUIREMENTS


CONTRACTOR RESPONSIBILITIES
EQUIPMENT INSTALLATION
MAJOR ELECTRICAL EQUIPMENT - GENERAL
CABLE INSTALLATIONS
CABLE GLANDS AND TERMINATIONS
EARTHING AND LIGHTNING PROTECTION
LIGHTING AND SMALL POWER INSTALLATIONS
ELECTRIC SURFACE HEATING
CATHODIC PROTECTION
PAINTING AND COATING
EQUIPMENT PLATES, NAMEPLATES, RATING PLATES AND LABELS

7.0
7.1
7.2
7.3
7.4
7.5
7.6

INSPECTION TESTING, PRE-COMMISSIONING AND COMMISSIONING


GENERAL
INSULATION TESTING
CONDUCTIVITY AND EARTH RESISTANCE TESTING
EQUIPMENT WIRING AND TERMINAL CHECKS
FUNCTIONAL TESTS
PRE-COMMISSIONING

8.0

PRESERVATION, HANDLING, STORAGE & SHIPPING

9.0

WEIGHT

10.0

MAINTENANCE REQUIREMENTS

11.0

SPARE PARTS & SPECIAL TOOLS

12.0

DOCUMENTATION

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 4 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

1.0

INTRODUCTION

1.1

PURPOSE AND SCOPE

1.1.1

This specification defines in general terms, the minimum standard of workmanship and installation practice that
is acceptable to the COMPANY during the installation of electrical equipment, materials and systems
associated with the onshore and offshore production facilities of the Kashagan Field Development, to be
operated by Agip Kazakhstan North Caspian Operating COMPANY (Agip KCO).

1.1.2

This specification defines the responsibility of an Electrical Installation Contractor and also identifies typical
tests that are to be carried out on electrical equipment to confirm installation quality and equipment integrity
prior to energisation and commissioning activities taking place.

1.1.3

The Contractor shall furnish the complete electrical installation, as defined in the contract and in the design,
installation and detail drawings, the Vendor Installation Operation and Maintenance [IOM] manuals and the
contract documentation. The Contractor shall also record and submit complete and accurate sets of as-built
installation drawings.

1.1.4

The Contractor shall have sole responsibility for all aspects of the works, inclusive of all services subcontracted or purchased from other parties. Nothing in this specification shall be construed to relieve the
Contractor of his contractual obligations. Any deviation from this specification requires the written approval of
Agip KCO.

1.1.5

The specification shall be read in conjunction with the particular conditions of contract issued for this project.

1.1.6

Distribution, Intended Use and Regulatory Considerations

1.1.6.1 Unless otherwise authorised by Agip KCO the distribution of this document is confined to the nominated
Contractors.
1.1.6.2 If Kazakh national and/or local regulations exist in which some of the requirements may be more stringent than
in the applicable Requisition, the Contractor (or his sub-contracted Kazakh Design Institute) shall determine by
careful scrutiny which of the requirements are the more stringent and which combination of requirements will be
acceptable as regards safety, environmental, economic and legal aspects. In all cases the Contractor shall
inform the COMPANY of any deviation from the requirements of the Contract, which is considered to be
necessary in order to comply with Kazakh national and/or local regulations. The COMPANY may then
negotiate with the Authorities concerned with the object of obtaining agreement to follow the requirements of
the Contract as closely as possible.
1.2

DEFINITIONS

1.2.1

The COMPANY is the party that initiates the project and ultimately pays for its design and construction. The
COMPANY will generally specify the technical requirements. The COMPANY may also include an agent or
consultant authorised to act for, and on behalf of, the COMPANY.

1.2.2

The CONTRACTOR is the party that carries out all or part of the design, engineering, procurement,
construction, commissioning or management of a project, or operation or maintenance of a facility. The
COMPANY may undertake all or part of the duties of the Contractor.

1.2.3

The SUPPLIER (MANUFACTURER / VENDOR) is the party that supplies or manufactures equipment and services
to perform the duties specified by the COMPANY or Contractor.

1.2.4

The word shall indicates a mandatory requirement.

1.2.5

The word should indicates a recommendation.

1.3

UNITS OF MEASUREMENT
In general, the International System (SI) units shall be used. However exceptions will include units as
indicated in the COMPANYs data sheets and specifications within the Requisition.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 5 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

2.0

SCOPE

2.1

SUPPLIERS SCOPE OF SUPPLY

2.1.1

This specification defines the general requirements for the installation of electrical equipment and materials
used in typical systems associated with the following aspects of electrical work for the Kashagan Field
Development Project, located in Kazakhstan.

2.1.2

Power and control: Including generators, transformers, distribution switchboards, motors, motor
control centres, cables, busbar trunking, heating equipment, rectifiers, batteries, converters.

Lighting and low voltage installations (e.g. socket outlets)

Supplies to instrumentation

Earthing and Supplementary Bonding

Testing and energising

The COMPANY will be responsible for the selection and supply of free issue electrical equipment as
specified in the Contract documents.

2.1.2.1 The Contractor shall be responsible for the supply of all other installation equipment, materials and
consumables that are not included in the scope of free issue items.
2.1.2.2 The quantities shown on any Electrical Material Take Off included in the Contract documents, are estimates
compiled to assist the Contractor. These quantities shall not to be construed as a final list of equipment and
material requirements.
2.1.2.3 The Contractor shall review and confirm material quantities based on his Approved for Construction (AFC)
drawings so as to ensure satisfactory completion of the works in accordance with the scheduled programme
and shall immediately advise the COMPANY representative of any shortfalls in the quantities of free issue
equipment or materials to be supplied via the COMPANY. The COMPANY representative will then advise the
CONTRACTOR to purchase the additional requirements.
2.1.3

All work shall be executed strictly in accordance with this specification and the project specifications referenced
herein.

2.1.4

The Contractor shall be responsible for the installation of all free issue equipment and bulk materials supplied
by the COMPANY.

2.1.5

The Contractor shall supply any other installation equipment and materials necessary to complete the electrical
installation including, but not limited to, the following:

all necessary temporary construction power supplies.

all necessary electrical testing equipment.

all necessary leveling and fixing equipment including shims, holding down bolts and suchlike.

all necessary drum jacks, cradles and transporters, cable rollers and pulling gear.

all necessary hand tools and portable electric tools with associated transformers.

all cable trench backfill material, protection tiles and route markers.

all miscellaneous installation and fixing materials, and consumables, including support steelwork for
small power equipment, cable tray and suchlike.

any scaffolding, platforms, ladders, hoists, lifting or jacking devices, block and tackle or any
equipment necessary to undertake the safe execution of the works.

other

2.1.6

Any equipment supplied by the Contractor shall be designed, manufactured and tested in accordance with local
statutory requirements and the latest editions of the relevant Codes and Standards.

2.1.7

The Electrical Installation Contractor shall thoroughly inspect all items of electrical equipment for damage prior
to locating the equipment and proceeding with the installation. If any damage is evident or suspected, it shall
be reported to the COMPANY representative who will determine the remedial action to be taken and advise the
Contractor accordingly.

2.1.8

The Contractor will be responsible for generating all documentation required by the project to satisfy full
compliance with installation completion, pre-commissioning and commissioning of all electrical equipment
within this project.
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 6 of 33

Agip KCO
KDPC
2.1.9

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

All test equipment shall be supplied complete with valid calibration certificates, which shall be approved by a
local Approval Authority, prior to being used during installation and testing procedures.

2.1.10 Unless otherwise authorised by COMPANY, the distribution of this document is confined to the nominated subcontractor(s).
2.2

EXCLUSIONS TO THE SCOPE OF SUPPLY

2.2.1

Unless deviations or exclusions are specifically identified by the Contractor in the bid proposal and agreed by
the COMPANY, the Contractor shall be deemed to have confirmed full compliance with the scope of supply
defined in the Contract.

2.2.2

If, after commencement of the works, the Contractor wishes to propose a deviation from the agreed scope of
supply, such deviation shall only be permitted after obtaining the written approval of the COMPANY.

3.0

CODES, STANDARDS, REGULATIONS AND REFERENCES

3.1

CODES, STANDARDS, REGULATIONS AND REFERENCES

3.1.1

The Regulations, Codes and Standards listed in the following sections shall be applicable and used in
conjunction with this Specification. Equivalent alternatives may be offered, however these shall be identified
and based on mutual agreement.

3.1.2

Equipment and materials must be approved for use by the recognised national certifying authorities of the
country of origin and by the Kazakhstan authorities.

3.1.3

Kazakh Regulations, Codes and Standards


The following regulations, Codes and Standards shall be applied:
PUE
RD 34.21.122-87

3.1.4

Rules for Electrical Installation. (Applicable to onshore only)


Design of Lightning Protection for Buildings & Structures.

Industry Codes and Standards


The equipment and installations shall comply with the latest editions of the referenced Codes or Standards,
including addenda, supplements or revisions thereto, unless specified otherwise.
International Electrotechnical Commission (IEC)
IEC-60050

International electrotechnical vocabulary.

IEC-60079

Electrical apparatus for explosive gas atmospheres

IEC-60287

Calculation of the continuous current rating of cables (100% load factor)

IEC-60364

Electrical installations of buildings

IEC-60445

Identification of equipment terminals and of terminations of certain designated conductors


including general rules for alphanumerical systems

IEC-60446

Identification of conductors by colours or numerals.

IEC-60529
IEC 60840

Degrees of protection provided by enclosures


Tests for power cable with extruded insulation for rated voltages above 30kV

IEC 60885

Electrical test methods for electrical cables

IEC 61035

Specification for conduit fittings for electrical installations

IEC 61084

Cable trunking and ducting systems for electrical installations.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 7 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

3.2

ORDER OF PRECEDENCE

3.2.1

It is project policy to adopt, where possible, International and de facto International standards for all high
integrity offshore and onshore process facilities. For infrastructure, such as roads, rail, utilities, etc. the
project policy is largely to use local Kazakhstan standards such as GOSTs and SNiPs.
Should there be any conflict between this document, the requisition, data sheets, drawings, specifications,
codes & standards or lack of clear definition as to the applicability of any specification or standard, this will
be identified by CONTRACTOR in writing to the COMPANY immediately or within 30 days for
resolution/clarification before proceeding.
In general, the order of precedence for all design work shall be:y

Contract

Datasheets & Drawings

Project Specification

International/National Standards

Referenced Industry Codes & Standards e.g. IEC or other National Standards

In the event of any conflict arising between the referenced standards the more stringent shall be applied. It
shall be the CONTRACTORs responsibility to satisfy all technical & certification requirements for and on
behalf of the COMPANY and the local Kazakhstan authorities.
Except for Republic of Kazakhstan Regulations, GOSTs and SNiPs where the original language version takes
precedence, the English version shall take precedence should there be any conflict between English &
Russian versions of the applicable documents.
3.3

DEVIATIONS AND EXCLUSIONS

3.3.1

The Contractor shall identify and list all deviations and exclusions to the documents and associated
requirements listed in 3.1.

3.3.2

Unless deviations / exclusions are specifically identified by the Contractor in the bid proposal and agreed by the
COMPANY, the Contractor shall be deemed to have confirmed full compliance with all the documents listed.

4.0

HEALTH, SAFETY AND ENVIRONMENTAL REQUIREMENTS

4.1

ENVIRONMENTAL CONDITIONS
Refer to Project documentation listed in the Contract documentation.

4.2

AREA CLASSIFICATION

4.2.1

All equipment intended for installation within hazardous areas shall be certified, as specified in the
Specifications, Data Sheets and shall be suitable for use in areas as classified and defined in the project
Hazardous Area Classification Drawings.

4.2.2

The Contractor shall ensure that all equipment installed within hazardous areas is suitably certified for
installation within such areas.

4.2.3

Certificates, licences and related drawings for any item or component of certified, EEx protected, equipment
supplied by the Contractor shall be submitted to the Site Representative for acceptance. Where certificates are
in a language other than English, a certified translation shall be supplied.

4.2.4

The Contractor shall create and maintain a Hazardous Area Equipment Certification Schedule for all items or
components within his scope of supply.

4.2.5

The installation site location is not in a region subject to the requirements of the European Union ATEX
Directive. However, when equipment, which is certified for installation and use in accordance with the ATEX
Directive is installed on the installation site, it shall be installed fully in accordance with the manufacturers
recommendation and the conditions attached to the respective certification in order that such certification is
valid.
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 8 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

4.3

HEALTH, SAFETY AND ENVIRONMENTAL REGULATIONS

4.3.1

The Contractor shall be responsible for ensuring that the electrical installation meets all applicable regulations
related to health, safety and environmental issues and that any materials, goods or services within his scope of
supply also satisfy the regulations.

4.3.2

The Contractor shall notify the COMPANY representative of any intention to bring to site any equipment likely
to cause a hazard, e.g. space heating or welding apparatus and/or any container holding liquid or gaseous fuel,
explosives, cartridges and tools or any other harmful substances. The storage of petroleum spirit shall comply
with the local Petroleum Regulations and any Local Regulatory Authority requirements and all rules and orders
applying to the site.

4.3.3

Contractor shall not bring or cause to be brought any radioactive substances or any apparatus using such
substances or any X-ray or similar apparatus, until written permission and direction regarding the use and
storage of such equipment has been given by the COMPANY representative.

4.3.4

Naked lights, cutting torches, welding equipment etc., shall not be used in areas designated hazardous without
written consent of COMPANY representative. All no smoking notices shall be strictly observed. COMPANY
representative shall have the right to prohibit the use of all equipment or substances or to prescribe the
conditions under which such equipment or substances may be used or stored. Such equipment or substances
shall not be brought on to the site without the prior written consent of COMPANY representative.

4.3.5

Where a source of electricity at 110 Volts with centre point earthed, is available on the site, Contractor may
connect suitable equipment (i.e. small tools, hand lamps etc.). In cases where the available supply is above
110 Volts, Contractor shall provide suitable low voltage centre point earthed transformers to serve all such
portable tools.

4.3.6

Contractor shall not, at any time, derive power from power points fitted to control panels, or that have been
fitted into the plant control system and form a functional part of the plant.

4.3.7

All temporary distribution, cables and equipment for construction purposes shall conform to the applicable
regulations. All electrical cables and equipment in use by the Contractor shall be regularly inspected, at agreed
intervals, and maintained in a safe condition and safely dismantled and removed upon completion of the work
for which it was erected. Records of tests and inspection shall be kept on site and made available upon
request.

4.3.8

The Contractor, without prior permission of the COMPANY representative, shall not intentionally disturb
electrical cables or electrical equipment in use on the site. No mechanical loads or attachments may be
imposed on any cables. In all cases where the Contractor wishes to connect electrical equipment to existing
facilities the Contractor shall: 1) Ensure that the appliance is in a safe condition and suitable for use on the voltage available
2) Obtain permission from the COMPANY representative and provide details of where any appliance is
required to be connected.
3) Inform COMPANY representative of the maximum current consumption and duration of anticipated use.

4.3.9

All construction equipment used by the Contractor on the site shall be in good safe working order, and comply
with all current construction regulations in force and be operated by competent persons.

4.3.10 COMPANY representative shall have the right to inspect all construction equipment and forbid its use if, in his
opinion, it is unsuitable or unsafe for the purpose it is to be, or is being used.

5.0

GENERAL DESIGN REQUIREMENTS

5.1

INSTALLATION AND OPERATING REQUIREMENTS


The Contractor shall be responsible for ensuring that all items of electrical equipment, materials, ancillary
components, and all monitoring and control systems, cabling and wiring interconnections are suitably
installed for the specified operating conditions indicated in the contract documentation.

5.2

DESIGN LIFE
The design life of equipment and materials supplied by the Contractor shall be 40 years under the specified
operating conditions.
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 9 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

5.3

NOISE LIMITS

5.3.1

The Contractor shall include noise level testing within the scope of pre-commissioning activities.

5.3.2

Equipment noise limits shall comply with requirements detailed in requisition or associated data sheets.

5.4

VIBRATION LIMITS

5.4.1

The Contractor shall not include vibration level testing within the scope of pre-commissioning activities.

5.5.2

Equipment Suppliers will be responsible for ensuring that their equipment operates within the vibration
tolerance limits specified.

5.5

UTILITIES

5.5.1

The electrical network supply voltages and frequency shall be:


Onshore transmission:

110kV, 3ph, 3 wire, system neutral


solidly earthed

Onshore and offshore generation system (excluding


generation for pipeline facilities):

10kV, 3ph, 3 wire, system neutral


resistance earthed via earthing
transformer and resistor.

Pipeline facilities distribution:

400V, 3ph+N, 4 wire + PE (TN-S


system), system neutral solidly earthed

HV distribution system: (onshore)

35kV and 10kV, 3ph, 3 wire, system


neutral resistance earthed

HV distribution system: (offshore)

35kV and 6kV, 3ph, 3 wire, system


neutral resistance earthed

Essential generation system (onshore main plant):

10kV, 3ph, 3 wire, system neutral


resistance earthed

Emergency generation system (offshore Complex D):

6kV, 3ph, 3 wire, system neutral


resistance earthed

Essential generation system (offshore Complex A):

400V, 3ph, 4 wire, system neutral


solidly earthed

Motors 5000 kW and above:

10kV, 3ph, 3 wire + PE, system neutral


resistance earthed (motors are
supplied from 35kV system using unit
transformers with Dyn11 vector group)

Motors 351kW to 4999kW (onshore):

10kV, 3ph, 3 wire + PE, system neutral


resistance earthed

Motors 200kW to 2000kW (offshore):

6kV, 3ph, 3 wire + PE, system neutral


resistance earthed

Motors above 2000kW (offshore):

6kV or 10kV, 3ph, 3 wire + PE, system


neutral resistance earthed.
motors are supplied from 35kV system
using unit transformers with Dyn11
vector group.

Motors up to 350kW inclusive (onshore):


Motors above 200kW up to 350kW inclusive (offshore
Special Cases) by agreement with COMPANY only:

690V, 3ph, 3 wire + PE, system neutral


resistance earthed

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 10 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

Motors up to 200kW inclusive (onshore Building


Services and Special Cases) by agreement with
COMPANY only:

400V, 3ph, 3 wire + PE, system neutral


solidly earthed

Motors up to 150kW inclusive (offshore):

400V, 3ph, 3 wire + PE, system neutral


solidly earthed

Motors above 150kW up to 200kW inclusive (offshore


Building Services and Special Cases) by agreement with
COMPANY only:
Fractional horsepower (not process motors):

230V, 1ph, 2 wire + PE, system neutral


solidly earthed

Motor operated valves:

400V, 3ph, 3 wire + PE, system neutral


solidly earthed

Non-motor loads such as lighting, convenience socket


outlets, electrical trace heating, etc.

400V, 3ph, 4 wire + PE / 230V, 1ph 2


wire + PE (TN-S system), system
neutral solidly earthed

Welding socket outlets:

400V, 3ph, 4 wire + PE (TN-S system),


system neutral solidly earthed

Escape lighting:

230V, 1ph, 2 wire + PE, (vital supply


from UPS), system neutral solidly
earthed

Safety lights (portable lighting):

230V, 1 ph, 2 wire + PE (TN-S


system), system neutral solidly earthed
or 100V, dc, 2 wire, unearthed (vital
supply from UPS)

Power tools:

230V, 1ph, 2 wire + PE (TN-S system),


system neutral solidly earthed

Anti-condensation heaters:

230V, 1ph, 2 wire + PE (TN-S system),


system neutral solidly earthed

Process and tank heaters up to 3kW inclusive:

230V, 1ph, 2 wire + PE (TN-S system),


neutral solidly earthed

Process and tank heaters above 3kW up to 250kW


inclusive:

400V, 3ph, 3 or 4 wire + PE (TN-S


system), system neutral solidly earthed

Process heaters above 250kW:

690V, 3ph, 3 wires + PE system


neutral resistance earthed. To be
verified case by case during detailed
design phase by agreement with
company only.

Electric Surface Heating - General Frost Protection and


Process Temperature Maintenance :

230V, 1ph, 2 wire + PE (TN-S system),


system neutral solidly earthed.

Electric Surface Heating Long Line Frost Protection and


Process Temperature Maintenance :

400V, 3ph, 4 wire + PE (TN-S system),


system neutral solidly earthed.

Electric Surface Heating Skin Effect (SECT) Pipeline


Heating Systems :

Power supply according to system


requirements, subject to review and
approval by COMPANY.

Non vital instruments:

230V, 1ph, 2 wire + PE (TN-S system),


system neutral solidly earthed

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 11 of 33

Agip KCO
KDPC

5.5.2

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

DCS, ESD.F&G and other vital instruments:

230V, 1ph, 2 wire + PE, (vital supply


from UPS), system neutral solidly
earthed

Solenoid valves:

24V dc, 2 wire, unearthed

Alarms:

24V dc, 2 wire, unearthed

Communication system for main plant (onshore/offshore):

230V, 1ph, 2 wire + PE, (vital supply


from UPS), system neutral solidly
earthed

Communication system for pipelines:

48V dc, 2 wire + PE, positive earthed

SCADA for pipelines:

24V dc, 2 wire, unearthed

ESD/F&G systems for pipelines:

24V dc, 2 wire, unearthed

Control/protection of HV and LV switchboards (circuit


breakers):

110V dc, 2 wire, unearthed (from UPS)

Circuit breaker spring winding motors:

110V dc, 2 wire, unearthed (from UPS)

Electrical control of HV motor starters:

110V dc, 2 wire, unearthed (from UPS)

Electrical control of 690V and 400V motor starters:

230V, 1 ph, 2 wire + PE, solidly


earthed

Frequency (ac mains supplies) and variation (steady


state):

50Hz + 5%

Frequency (ac UPS supplies) and variation (steady state):

50Hz + 1 Hz

Voltage variation, ac mains supplies (steady state):

+5/-5%

Voltage variation, ac UPS supplies (steady state):

+5/-5%

Voltage variation, dc UPS supplies (steady state):

+ 5 / - 5 % of float voltage.

For descriptions of the power supply arrangements of the Onshore, Offshore, Pipeline and Early Works
facilities refer to the following documents:
KE01-B4-000-KD-E-YP-4001-000

Electrical Generation and Distribution Overview

KE01-00-000-KD-E-YP-0001-000

Electrical Design Criteria

KE01-C0-000-KD-E-YP-0003-000

Pipelines Power System Philosophy

KE01-00-000-KD-E-YP-0004-000

Electrical Control Philosophy.

5.6

PROVEN EQUIPMENT AND MATERIAL CRITERIA

5.6.1

Only equipment and material of proven reliability in similar service conditions shall be included in the
Contractors bid proposal (prototypes shall not be proposed). The Contractor shall provide the related
necessary evidence (reference lists with installation dates and run hours accumulated by date, etc.). The units
shall have equivalent design features to the units proposed.

5.6.2

Where the requirements above prevent the application of the latest technology, the Contractor may submit a
second alternative proposal incorporating the latest technology features for evaluation by the COMPANY. This
alternative proposal shall specifically identify the un-proven features and state their advantages.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 12 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.0

EQUIPMENT INSTALLATION REQUIREMENTS

6.1

CONTRACTOR RESPONSIBILITIES

6.1.1

Installation Design

6.1.1.1 Where specified in the Contract, the basic design of, and the calculations for, the electrical installation shall be
the responsibility of the Contractor. The Contractor shall liaise with the COMPANY to clarify any queries
relating to design intent and to resolve any unforeseen queries that affect the design of the installation.
6.1.1.2 The installation shall be complete in all respects and based on the specific requirements stated in the electrical
design documents, specifications, installation detail drawings and any equipment Suppliers Installation,
Operation & Maintenance (IOM) data. The installation Contractor is considered to be aware of all electrical
data that may be essential for the correct installation of the electrical equipment and materials.
6.1.2

Installation Drawings

6.1.2.1 All installation work shall be carried out in accordance with the Approved for Construction (AFC) drawings,
requisitions, bills of materials, specified standards, this specification and documents referred to in the Contract.
It is the responsibility of the Contractor to ensure that he is working to the latest revision of all documents
approved by the COMPANY and that the installation fully complies with them.
6.1.2.2 The Contractors site personnel shall not undertake any work against drawings that are not Approved for
Construction.
6.1.2.3 The Contractor shall keep comprehensive up-to-date records of progress on the whole of the electrical works
and shall provide the COMPANY with the required copies of As-Built drawings and documents as per the
requirements of the Contract.
6.1.3

Contractors Personnel

6.1.3.1 The installation Contractor shall be responsible for the provision of all qualified personnel, tools, services and
test equipment necessary for the proper and successful completion of all electrical work shown within the
Contract documentation.
6.1.3.2 The Contractor shall ensure that the correct tools are used for each task undertaken during the installation of
electrical equipment and material.
6.1.3.3 The Contractor shall ensure that the installation workforce is qualified, skilled and experienced to work on all
tasks allocated to them, especially those activities involving high voltage electrical equipment and cabling /
termination.
6.1.3.4 Senior personnel employed by the Contractor in the installation of electrical equipment within areas designated
as hazardous shall be fully conversant with all applicable regulations and standards relating to the installation of
such equipment and shall be suitably qualified, skilled and experienced, competent personnel.
6.1.3.5 At least one Senior Person thoroughly familiar with the class and character of work to be executed shall be
present at the work site during all working hours.
6.2

EQUIPMENT INSTALLATION

6.2.1

General
In carrying out the installation, the Contractor shall pay particular attention to:

Quality of work.

Accessibility for maintenance.

Protection of equipment and accessories against general construction site hazards and adverse
weather conditions.

Installation materials are not damaged due to being handled or worked on in the extreme cold.

Protection and preservation of equipment during storage utilising integral anti-condensation heaters
where available.

Protection of fire-proofing.
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 13 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

Protection of insulation on pipelines, vessels and towers.

The use of modern construction tools noting that cartridge or shot firing tools may only be used with
the written approval of the COMPANY.

Ensuring work with temperature sensitive materials is carried out within the conditions specified by
that material Supplier/Manufacturers recommendations.

Ensuring work in Hazardous Areas shall be carried out strictly in accordance with the Regulations.

Ensuring no acid resistant tiled surface shall be cut into for any fixing by the Contractor.

Ensuring no fixing shall be made to a pipeline or vessel without the written permission of the
COMPANY.

Ensuring an adequate space is allowed between any hot surface and cable or conduit. All hot
surfaces adjacent to cables shall be insulated.

Ensuring any unused entries on equipment shall be sealed with screwed stopper plugs suitable for
the ambient temperatures. In Hazardous Areas, the plugs shall be suitably certified for this
requirement and the Contractor shall ensure that at least five full threads are engaged such that
certification requirements are met and Ingress Protection ratings are maintained.

Ensuring power distribution systems installed for the express purpose of providing temporary power
for construction works shall be subject to the same standards of workmanship as the permanent
installation, except where otherwise allowed by the COMPANY.

Ensuring there shall be no overhead power supply or distribution systems utilising bare conductors,
whether of a temporary or permanent nature, in any work area. Overhead systems utilising insulated
conductors shall only be permitted when unavoidable and then only with the written authorisation of
the COMPANY.

6.3

MAJOR ELECTRICAL EQUIPMENT GENERAL

6.3.1

The Contractor shall acquaint himself with the equipment Suppliers erection and installation instructions prior
to removing equipment from the store.

6.3.2

Due care shall be taken in transporting equipment from the store to its place of installation.

6.3.3

During all stages of installation the Contractor shall co-ordinate with the civil Contractor where applicable, to
determine installation schedule and the accurate location, alignment and level tolerances of equipment
foundations and/or channels, to confirm all are in accordance with the Equipment Suppliers procedures and/or
the Contract drawings.

6.3.4

During the construction period, the Contractor shall be wholly responsible for the protection of the equipment,
from construction site hazards and prevailing weather conditions, and shall be responsible for the security of
the equipment from loss due to any cause.

6.3.5

Whilst equipment Suppliers may have supervision personnel on site it shall remain the responsibility of the
Contractor to complete the installation of all shipped sections of the equipment. This shall include, but is not
limited to the following:

Bolting packages and equipment sections together.

Completing any floor or wall fixings including alignment and shimming to level.

Bolting bus-bar sections to manufacturers torque settings.

Looping switchboard bus-wiring from section to section and completing connections.

Installing all loose ancillary equipment to main equipment.

Removing any internal or external packing.

Removing any shipping clamps on anti-vibration devices.

Installing outer covers, doors or panelling.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 14 of 33

Agip KCO
KDPC
6.3.6

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

110kV Switchyard
The installation of the 110kV switchyard as defined in the Contract shall be carried out by the Contractor
under the supervision of the switchgear Supplier.

6.3.7

Transformers

6.3.7.1 The Contractor shall be responsible for the final assembly of any transformer that is delivered to site not
completely assembled. The work shall be completed in accordance with the transformer Suppliers instructions,
under the Suppliers supervision, and shall include the fitting of any loose items of ancillary equipment such as
gauges, switches and marshalling boxes.
6.3.7.2 Where transformer oil is supplied to the Contractor in drums, the Contractor shall ensure that the drums are
stored in clean and dry conditions. Drum seals shall only be broken immediately prior to the oil being tested
and used to fill the transformer. Contractor shall take all steps necessary to prevent contamination of the oil by
moisture or dirt particles. In the event that the oil, which is free issued to the Contractor, fails the initial dielectric
test, the Contractor shall immediately communicate the problem to the COMPANY representative who will take
responsibility for resolving the matter.
6.3.7.3 The Contractor shall ensure that the concrete base within the transformer bay, and cable or bus-duct entry
positions, are all in a suitable state of completion before starting the installation. The transformers shall be
placed on flat, level, bases in the positions shown on the layout drawings and shall be positioned using the
wheels and lifting points provided, all as required by the Supplier IOM instructions and contract design
drawings.
6.3.7.4 After positioning, and where applicable, the Contractor shall ensure correct alignment with bus-duct.
Transformers shall be fastened directly to their bases strictly in accordance with the instructions on the
Suppliers installation drawings. This may be a Supplier supervised activity.
6.3.7.5 The Contractor shall provide any lifting equipment needed to off-load and manoeuvre the transformers to their
final locations.
6.3.8

Bus-duct Systems

6.3.8.1 When specified, bus-duct shall be utilised for the low voltage connections between transformers and the
incoming terminals of associated LV switchboard circuit breakers.
6.3.8.2 All supports, couplings, horizontal and vertical elbows, flexible terminal elements, sealed fire-rated wall
bushings, transformer and switchboard flanges shall be supplied with the bus-duct for complete installation by
the Contractor, all as required by the Supplier IOM instructions and contract design drawings.
6.3.8.3 Where bus-duct junctions require on-site over-casting of epoxy-resin insulation material, the
temperature/humidity conditions and methodology must comply strictly with the Supplier installation
instructions. Care must also be taken to store these epoxy-resin materials strictly within the guidelines specified
by the bus-duct Supplier. All connection torque settings, phase rotation and insulation resistance must be
checked prior to over-casting the connections. This may be a Supplier supervised activity.
6.3.9

Metalclad Switchgear and Large Control Panels

6.3.9.1 HV and LV switchboards, large heater control panels, generator control panels and similar control panels will
be delivered in sections for assembly and connection on site.
6.3.9.2 Prior to installation, the Contractor shall ensure that all floors are level within tolerances required for the
equipment and fixing arrangements and cable entries are all in a suitable state of completion, as required by
the Supplier IOM instructions and contract design drawings.
6.3.9.3 Each switchboard, or panel, shall be assembled and mounted in the correct sequence and switchboard
sections shall be tightly and rigidly bolted together. All bus-bars and bus-ducts shall be correctly aligned with
fish plates and splice plates, and termination elements bolted to correct torque settings, all in accordance with
Supplier instructions. Withdrawable units/ chassis shall be checked for mechanical alignment, ease of
insertion/ withdrawal and, where applicable, mechanical interchange ability.
6.3.9.4 Circuit designation labels shall be checked for correct identification, all inter-cubicle wiring and bus wiring
connections completed, cover plates and removable panels secured. This may be a Supplier supervised
activity.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 15 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.3.9.5 The Contractor shall, where applicable, use only the special tools and equipment supplied by the Supplier and
shall ensure that such tools are available and in good condition for later use by the COMPANY. When the
installation is complete, the Contractor shall return any special tools and equipment to the COMPANYs
representative.
6.3.9.6 During storage and subject to confirmation by COMPANY and/or Supplier, space heaters of switchgear
cubicles, motor control centres and other large control panels may require to be temporarily energised via a
reliable source of construction power.
6.3.10 UPS Systems
6.3.10.1 The panels of UPS systems will be delivered in sections for assembly and connection on site. Lead Acid
batteries (where specified) shall be delivered (separate to the UPS equipment), filled, fully charged and ready
for installation (onto purpose built racks). Nickel Cadmium batteries (where specified) shall also be delivered
separately and ready for installation but empty and discharged, wherever practicable.
6.3.10.2 Battery cell interconnection links, cable connections to UPS units and all terminal connection shrouds will be
included with the batteries. Battery racks will be supplied dismantled with loose assembly fittings, nuts and bolts
ready for erection on site.
6.3.10.3 Prior to installation, the Contractor shall ensure that all floors are level within tolerances required for the
equipment, and fixing arrangements and cable entries are all in a suitable state of completion, as required by
the Supplier IOM instructions and contract design drawings. This may be a Supplier supervised activity.
6.3.10.4 The Contractor shall ensure that his installation schedule takes account of battery shelf life and that the
batteries are suitably charged prior to the expiry date. The storage and charging instructions supplied with the
batteries shall be rigorously followed.
6.3.10.5 The Contractor shall ensure that a free flow of ventilation air is possible around batteries and UPS system
panels, and that ventilation inlets and extracts are clear of obstructions.
6.3.10.6 The Contractor shall install links between battery cells only when directed by the COMPANY during precommissioning activities. All such links and all cable connections shall be made secure and checked for
tightness. Terminals and connections shall be liberally greased with petroleum jelly, or other Supplier
recommended lubricant, with shrouds placed in position. Only Supplier supplied cables or links shall be used
for inter-cell connections.
6.4

CABLE INSTALLATIONS

6.4.1

General

6.4.1.1 Cables shall be run overhead on tray or rack as the preferred method of cable installation. Alternatively, where
defined in the Contract drawings or by agreement with the COMPANY, cables may be directly buried in the
ground.
6.4.1.2 During the construction period, the Contractor shall be responsible for protecting cables against construction
site hazards, prevailing weather conditions, and damage or loss due to any cause.
6.4.1.3 Cables shall be pulled from cable drums and laid directly onto tray or rack, or into trenches. Cables shall not be
left laying on platforms or on the ground. The only exception to this requirement is where a loop has to be
created, generally at a change in cable route direction. In such cases, the Contractor shall ensure that after the
cables are removed from their drums, and prior to being pulled into position, they are protected against damage
from vehicular traffic or any other possible cause.
6.4.1.4 Cables have been specified for installation in temperatures down to -150C. Where cables are to be installed in
air temperatures below -150C, precautions shall be taken to avoid mechanical damage to insulation or sheath.
Any cables to be installed under such conditions shall be stored in a heated environment at a minimum
temperature of 200C for a period of at least 24 hours before installation.
6.4.1.5 Once cables have been removed from the heated area, installation shall be completed as quickly as possible,
taking into account the manufacturers recommendations on time limits for handling of heated cables in low
temperatures.
6.4.1.6 Heated tents or warehouses shall be utilised to provide shelter. In locations where large areas of tray/rack or
trenches have to be exposed for cable pulling in sub-zero temperatures, consideration shall be given to the
erection of a tent over the installation area and the installation of forced air heaters to provide a suitable
environment for cable storage and pulling.
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 16 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.4.1.7 Armoured cables shall be installed with the aid of specially constructed rollers. All un-armoured cables and
armoured cables up to 38mm overall diameter shall be installed by hand, but larger cables may, with the
COMPANYs approval, be installed with the assistance of a suitable winch, having an adjustable tensioning
device and indicator, and operated by a trained and competent operator.
6.4.1.8 Under no circumstances shall the maximum permitted tension for the type and size of cable be exceeded.
Drum jacks, cable rollers and other equipment shall be of the correct type and size for each drum and each
cable laid. This equipment shall be kept in a sound condition and be used in the approved manner.
6.4.1.9 Cable pulling stockings shall be sized to the cable and fitted in a correct manner. Where recommended by the
manufacturer pulling eyes will be fitted to the cable at the time of manufacture. Under no circumstances shall
metal levers or tools be used in direct contact with cables during installation unless of a proprietary type
specifically designed for the purpose.
6.4.1.10 Cables shall be laid in flat parallel formations, in accordance with the construction drawings and standard
installation details. Twisting, crossing or inter-twining of cables is not acceptable and the utmost care shall be
exercised at all times to avoid excessive bending or twisting of a cable which may result in damage to core
insulation, core screens, armour or sheath. At no time, during or after installation, shall the bending radius of
any cable be less than the minimum value recommended by the manufacturer.
6.4.1.11 The cut ends of any installed un-terminated cables, or of cable left on a drum, shall be sealed with proprietary
heat shrink end caps designed for the purpose.
6.4.1.12 Once installed, cables shall be temporarily marked for identification purposes, pending termination and the
fitting of permanent identification markers, which shall be attached to the cables at intervals of 30 m, at
changes of direction and on both sides of every cable transit.
6.4.1.13 Cables shall be installed as continuous unbroken lengths. Jointing or splicing will not be permitted unless
specifically identified in the Drawings. If, for any reason, cable jointing is deemed necessary this shall only be
with the express prior agreement of the COMPANY. In such circumstances, only COMPANY approved
proprietary joint kits may be employed and cable joints shall be made in accordance with the joint
manufacturers instructions. All cables that are jointed during installation are to be included in a schedule and
are to be highlighted on the associated cable routing drawings.
6.4.1.14 Due regard shall be given to the specified ambient conditions. Jointing shall not take place when moisture
ingress could result. Consideration shall be given to the erection of a heated tent or enclosure over the joint
location. The Contractor shall liase with the COMPANY before any tent or enclosure is erected. Cable
terminations at outdoor locations, or within HV equipment, shall also be made under the same protective
conditions.
6.4.1.15 The Contractor shall measure the route length of each run of cable prior to cutting. Cables shall be cut from the
designated drum in accordance with the drumming and pulling schedules; any shortfalls shall be brought to the
notice of the COMPANY.
6.4.2

Cable Separation

6.4.2.1 Wherever possible, cables shall be installed in accessible groups. The minimum separation distance between
electrical power cables and instrument or telecommunications cables shall, where practicable, comply with the
following:
Power Wiring Capacity
Max. Voltage
less than:
125V
250V
690V
5kV
10kV
35kV

Max. Current
less than
10 A
50 A
200 A
800 A
1000 A
2000A

Minimum Separation Between


Power Cables and Signal Cables
Instrument
Instrument
Instrument
Category 1
Category 2
Category 3
12 (300mm) 12 (300mm) 12 (300mm)
12 (300mm) 12 (300mm) 18 (450mm)
12 (300mm) 12 (300mm) 24 (600mm)
12 (300mm) 24 (600mm) 48 (1200mm)
12 (300mm) 24 (600mm) 60 (1500mm)
12 (300mm) 24 (600mm)
72 (1800mm)

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

System 2

System 1

Sheet 17 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

Where cables are classified by System Type:


System 1

High voltage systems (above 1000V).


Low voltage power supply and control cables for electrical
systems (1000V and below).
Instrumentation and Telecommunication systems.

System 2
System 3

and System 3, Instrument cables, are further Categorised:


Category 1

System 2

System 3

Instrument power and control wiring (above 50V);


includes a.c. and d.c. power supplies and control signals
(including emergency shutdown circuits).
High level signal wiring (5V to 50V d.c.);
includes digital signals, alarm signals, shutdown signals and high
level (e.g. 4-20mA) analogue signals.
Low level signal wiring (below 5V d.c.);
includes temperature signals and low level analogue signals, e.g.
analyser measuring circuits.

6.4.2.2 The above separation distances may be relaxed to 300mm minimum at the entries to equipment, or where
parallel runs are less than 20m long.
6.4.2.3 All inter-sections that bring power and signal cables into close proximity shall be made at right angles, the
cables shall not touch.
6.4.3

Cable Installations Above Ground

6.4.3.1 The Contractor shall adhere strictly to the cable routes and cable groups as detailed on the construction
drawings. Failure to meet this requirement will result in the Contractor having to correct the installations at his
own expense and without detriment to any target completion date.
6.4.3.2 The Contractor will be given access to review the 3D PDS plant design model to aid in site routing and clashchecking of installations.
6.4.3.3 The Contractor shall carry out a clash check of above ground cable routes to ensure that an unobstructed run
can be accomplished without clashing with any other equipment or steelwork, piping or ductwork. Personnel
and equipment access ways, including maintenance or withdrawal areas, shall remain unobstructed. Any such
clashes, if identified, shall be resolved with the COMPANY before cable installation commences.
6.4.3.4 Where specific routes are not defined, as in the case of final lighting and small power circuits, the Contractor
shall detail routes for approval by the COMPANY representative, prior to installation. Such minor cable routes
shall be established by the Contractor in co-ordination with other trades and shall use the shortest length of
cable possible. Where practicable, common cable routes shall be adopted to avoid duplication of installation
work.
6.4.3.5 Normally, cables shall be installed throughout their length on heavy duty cable ladder rack or cable tray.
Onshore cable rack and tray systems shall be heavy duty, hot dipped, deep galvanised, silicon enriched steel.
Offshore cable rack and tray systems shall be heavy duty stainless steel. All cables shall be securely fixed by
cleats, ties or straps at regular intervals in accordance with design documentation. The LV multicore cables
may be secured using EVA coated stainless steel subject to COMPANY approval as per item 6.4.3.32.
On vertical runs cables will be secured on every rung of the cable ladders.
6.4.3.6 Single cables, routed by the Contractor, may be individually attached to structures with approved cable cleats,
but shall not be supported or attached to personnel ladders. Cables shall not be installed on the exterior wall
faces of buildings without the specific approval of the COMPANY.
6.4.3.7 Cables that leave main ladder rack routes for connection to motors, push button stations or other items of
electrical equipment shall be installed on intermediate lengths of tray, channel or angle iron supports, fitted
between the main cable rack and the equipment.
6.4.3.8 Where a cable joint, specifically authorised by the COMPANY, is installed above ground it may be
independently supported or located on cable ladder rack, or tray, which must have adequate strength to
support the joint without deflection.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 18 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.4.3.9 Where cables pass vertically through floors, platforms or walkways, substantial permanent metal kick-plates up
to a height of 150mm above the floor level shall be provided as protection against mechanical damage. Such
protective metal work shall include reasonable space for the installation of additional cables and shall be so
positioned as not to constitute a trip hazard. The Contractor shall consult the COMPANY as to the precise form
of steelwork required. Where cables pass through solid floors, access holes, transits or cable sleeves shall be
sealed to inhibit the spread of fire.
6.4.3.10 The entry of overhead cables into buildings shall be inclined at an angle of 10 below the horizontal away from
the entry, to prevent the ingress of rainwater. Following final installation of all cables, the entry penetrations
shall be sealed. The method of sealing penetrations shall be in accordance with the construction drawings or
as otherwise agreed with the COMPANY
6.4.3.11 Cable ladder rack and tray systems shall be designed and installed to maintain electrical continuity throughout
the route. Consecutive lengths of rack and tray shall be bonded together and to earth, at the intervals specified
in the contract drawings, to ensure a low resistance earth fault path. Earth bonding cables shall be installed
across expansion joints and splice plates where the mechanical connection does not provide an adequate
bonding connection.
6.4.3.12 Rack and tray systems shall be designed to ensure that water cannot collect or remain in any part of the
installation.
6.4.3.13 In general, only proprietary fittings, bends, elbows and tees, shall be employed in the construction of ladder
rack and tray systems. In exceptional circumstances, subject to the approval of the COMPANY representative,
site welded bends may be employed provided their quality shall be not less than that of a standard
manufactured item and that the bending radius of any installed cable is not reduced below the manufacturers
recommended minimum value. Site welded sections shall be fully corrosion protected after fabrication using
proprietary coating material approved by the COMPANY.
6.4.3.14 Cable rack and tray systems shall have a minimum of 25% spare capacity, and access for future installation of
cables shall be maintained.
6.4.3.15 Cable rack and tray systems shall be designed such that separation and segregation is maintained between
power, control and instrumentation cables as specified in the project specifications and detailed on the
construction drawings.
6.4.3.16 Unless otherwise stated on the approved contract drawings, cables installed above ground shall maintain the
following minimum clearances:

HV multicore cables up to 35kV

1 cable diameter

HV Single core cables in trefoil between trefoil groups

250mm Note 1

LV Single core cables in trefoil between trefoil groups

100mm Note 1 - 2

LV power cable to any other LV power or control cable

100mm Note 1- 2

LV power cable to any HV power cable

Separate cable rack or tray

LV motor cables

Single layer on tray touching


Note 2

Lighting, small power cables, control cables, etc

Bunched with maximum


100mm bunch diameter
Note 2

Electrical power and control to Instruments

Refer to section 6.4.2

Note 1:
For offshore facilities, the minimum clearances given above may be reduced up to 0mm (touching),
if required due to space limitations, subject to COMPANY approval. The cable shall be sized
accordingly.
Note 2:
For onshore facilities LV multicore cables installed on above ground cable ladder/trays, suitable
derated cables shall be installed as follow subject to COMPANY approval:
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 19 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

Power cables (distribution feeders and motor feeders) will be grouped (touching) in a single
layer not exceeding nine cables. Between each group a 100 mm space will be left clear.
Lightly loaded cables (e.g. MOVs, welding, lighting and other intermittent loaded cables
etc.) will be run in multilayer bunches not exceeding the equivalent of 100mm diameter.
Between each bunch a 50mm space will be left clear. In the event that such a bunch is adjacent to a
Power cable group a 100mm space will be provided.

6.4.3.17 Instrument signal and control cables shall be run on different racks from power cables. Separation distances
shall be in accordance with the requirements of specification number KE01-00-000-KD-I-ST-0021-000,
Instrument Installation.
6.4.3.18 Unless otherwise stated on the approved contract drawings, when multiple levels of ladder rack are to be
installed above one another, the minimum vertical spacing between rack surfaces shall be 600mm.
6.4.3.19 The height and location of cable routes crossing main access ways and roadways shall be as shown on the
construction drawings. Generally vertical clearances to the underside of cable racks or trays, or their associated
supports systems shall be not less than:
Maintenance roads, for crane access

5,500mm

Operating areas, for truck access

4,300mm

Operating areas, over walkways, minor access ways and stairwells

2,200mm

6.4.3.20 Unless otherwise stated on the approved contract drawings, vertical and horizontal clearances between cable
racks, or trays, and lagged process or service pipes shall be not less than:
Between cables and pipes

500mm

Between cables and oil/gas pipes

1,000mm

6.4.3.21 Cable installations above ground shall have ventilated covers fitted to all rack and tray up to a height of 2.5
metres above grade. Above 2.5 metres, ventilated covers shall be fitted only where cables require protection
from direct sunlight. Care shall be taken not to obstruct the free ventilation of cables.
6.4.3.22 Cables within non-elevated substation buildings or switchrooms shall be installed on cable ladder rack or tray
suspended from the underside of the roof, unless otherwise specified on the construction drawings.
6.4.3.23 Cables within elevated substation buildings or switchrooms shall be installed on cable ladder rack or tray or
fixed to dedicated profile subject to Company approval, suspended from the underside of the floor, or
buried in the ground below the substation floor, as specified on the construction drawings. The method of
installation will be defined during detailed design.
6.4.3.24 Cable entry penetrations shall be provided in the building floor or walls, as indicated on contract drawings or as
required. Penetrations shall be sealed after installation of the cables, to prevent ingress of dust, moisture or
fire. The method of sealing shall allow the installation of additional, future cables without the need to disturb
existing cables. All sealed penetrations shall maintain the building fire rating.
6.4.3.25 Cable rack and tray supports shall be spaced as shown on the construction drawings. If support brackets
cannot be installed at the specified spacing then, to avoid deformation, the rack or tray shall be framed with
angle iron of adequate section consistent with the total weight involved.
6.4.3.26 Cable rack and trays shall be bolted or clamped to support systems or steelwork, welding shall not be
permitted. Structure steelwork shall not be drilled for any reason.
6.4.3.27 Only approved proprietary accessories and clamps, utilising hot dipped galvanised steel brackets onshore or
stainless steel offshore, shall be employed in the construction of ladder rack or tray support systems. Suitable
methods shall be employed to prevent galvanic corrosion taking place between stainless steel and mild steel.
6.4.3.28 Cable ladder rack or tray shall not be drilled for fixing purposes. Drilling will only be permitted for joining site cut
lengths and for earthing purposes, or where detailed on the construction drawings.
6.4.3.29 Installation techniques for cable rack and tray shall comply with the standard details shown on the contract
drawings.
6.4.3.30 All sharp edges and burrs shall be removed from cable ladder rack and tray following cutting on site. Cable tray
shall only be cut along a line of un-perforated metal. Any damaged galvanised surfaces shall be made good
immediately with a proprietary cold galvanising paint. The paint type shall be subject to the approval of the
COMPANY representative.
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 20 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.4.3.31 Where cables are to be installed through, or across, the lipped edges of cable tray, or other metal work, the
edges of the lips shall be smoothed, painted and lined with protective sleeves to avoid damage to cables.
6.4.3.32 All HV and LV multi-core power cables run above ground and having an overall diameter in excess of 30mm
shall be fixed with proprietary non-corrodible cable cleats. All other cables shall be fixed with EVA coated
stainless steel cable straps. Cable cleats shall be two hole fixing, mechanically rated for the highest prospective
short circuit fault level.
The LV multicore cables installed above ground on pipe rack cable ladder/trays may be secured using
EVA coated stainless steeel all-round-band subject to Company approval.
The LV and HV single Core cables installed above ground may be secured using trefoil cable
clamps/cleats subject to Company approval.
6.4.3.33 Single core a.c power cables shall be installed on ladder rack in trefoil formation and secured along their
complete length by heavy duty non-corrodible trefoil cleats with intermediate straps fitted midway between the
cleats. Cleats and straps shall be Type-Tested and have a certified cable containment capability to a level in
excess of the prospective short circuit levels.
6.4.3.34 Maximum fixing intervals shall be in accordance with the following table:
Overall Diameter of Cable (mm)

Spacing of Single Cleats or Straps (mm)


Horizontal Run
Vertical Run
900
225
2,000
600

< 20
20
Voltage
HV, LV

Horizontal Run
900

Spacing of Trefoil Cleats (mm)


Flat Bend / Riser
300

Vertical Run
600

Where cable runs are inclined at up to 30O from horizontal, spacing shall be as for horizontal runs.
Where cable runs are inclined at more than 30O from horizontal, spacing shall be as for vertical runs.
Where horizontal runs are installed with rack or tray in the vertical plane, the spacing shall be as for
vertical runs.
Where closer spacings are required to comply with short circuit fault ratings of cleats, the manufacturers
recommended spacings shall be used.

6.4.3.35 Cable cleats shall be manufactured from non-corrodible material and shall have adequate mechanical strength
for their designed duty. Cable ties shall be heavy duty stainless steel type coated with UV resistant plastic and
of a make approved by the COMPANY.
6.4.3.36 Single core cables forming a d.c. circuit, or positive and negative battery connections, shall be run side by side
as far as possible for their full length and shall be cleated or tied in similar manner to low voltage multi-core
cables.
6.4.3.37 Cables leaving a rack or tray shall be supported to within 600mm of wall transits, penetrations or terminal
points.
6.4.4

Cables Installed Directly in the Ground

6.4.4.1 Cables must be laid without deviation from the routes specified in the contract drawings. If deviation is
necessary, for any reason, authority must be obtained and the new route given written approval by the
COMPANY. The Contractor shall, as installation progresses, maintain as built records of all cable routes which
shall be handed over to the COMPANY
6.4.4.2 The Contractor shall be responsible for liaising with the COMPANY, and with other trades, to confirm the
detailed location of cable trenches, their finished grade level along the proposed route and the correct depth of
excavation. Interference with other underground equipment and services shall be minimised.
6.4.4.3 The Contractor shall also confirm, with the COMPANY, if clearance or permit to work certificates are
necessary.
6.4.4.4 Cables shall be laid in trenches strictly in accordance with the construction drawings, paying particular attention
to the depth of lay and the designated spacing between cables and cable groups. Failure to meet this
requirement will result in the Contractor having to correct the installations at his own expense and without
detriment to any target completion date.
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 21 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.4.4.5 Direct buried cables shall have sand bedding and cover. Unless noted otherwise on the contract drawings,
trenches shall be at least 1000mm deep for cables rated less than 35kV, and at least 1200mm deep for 35kV
cables. Where cable routes intersect, there shall be a vertical separation of at least 500mm of backfill material
or sand between them. This separation may be reduced to 150mm provided the cables are separated along
the whole intersection, plus 1 metre either side, by pipes or plates of concrete or other materials of similar
strength. Concrete or earthenware tiles shall be laid above the cables in unpaved areas, however tiles may be
omitted where red coloured concrete paving is placed above cable trenches. Where cables leave the main
trenches they may be run for short lengths in PVC ducting. Cables shall be in concrete encased ducts at road
crossings. Cables installed underground in any areas that may be subject to hydrocarbon contamination shall
either be installed in concrete encased ducts through the area or be lead sheathed for the whole of the route.
However, routing of 35kV and 110kV cables underground through areas of potential hydrocarbon
contamination shall be avoided.
6.4.4.6 Cable trenches shall be a minimum of 500mm wide unless noted otherwise on the contract drawings.
6.4.4.7 All cables shall be subjected to a continuity test on the drum, prior to pulling and installation. Installation shall
not commence until the entire route has been excavated and the trench is prepared ready to receive the
cables.
6.4.4.8 Typical values of thermal conductivity for bedding, sand and back fill material will be established by a series of
site tests during the design phase and used as the basis for cable sizing, as developed in the Cable Sizing
Philosophy (Document No. KE01-00-000-KD-E-YP-0003-000). Thermal conductivity values must be checked
before installation of cables commences. If values are lower than those on which cable ratings and grouping
factors have been determined in the Cable Sizing Philosophy, the Contractor shall agree with the COMPANY
the corrective measures to be adopted.
6.4.4.9 Prior to laying cables the bottom of each trench shall be levelled, reasonably compacted and generously
spread with clean thermal conducting sand to a depth of 75mm. A visual inspection shall be made to ensure
the absence of debris and sharp objects.
6.4.4.10 Separation and segregation intervals between cables of different types, and between the layers of cables in a
given trench, shall be as defined in the construction cable route layouts, project specifications and/or the
standard details. Cables shall be laid with a slight snaking to avoid possible stress during ground settlement.
6.4.4.11 Unless stated otherwise on the approved contract drawings, cables installed direct buried underground shall
maintain the following minimum clearances:

Any cable to any foundation or other structure

600mm

Up to 35kV cable to gas pipelines

2000mm

Up to 35kV cable to pipelines (other than gas), water


ducts, sewerage pipes or drainage systems

1000mm

35kV cable to any other cable

250mm

10kV or 6kV cable to any other 10kV, 6kV, LV power or


any control cable

100mm

Single core cables in trefoil to any other cable

250mm

LV power cable to any other LV power or control cable

100mm

Lighting, small power cables, etc

Bunched

Electrical power and control to Instruments

Refer to section 6.4.2

6.4.4.12 After each layer of cables is in place, and before covering with sand, each cable shall be visually inspected and
subjected to a continuity and insulation test, all in the presence of the COMPANY (if requested). Any cable
proven defective, or even suspect, shall be replaced before installing the next layer of cables. Test
documentation shall be completed. All test data shall be recorded by the Contractor, as installation progresses,
and such test data shall be submitted to the COMPANY for acceptance prior to back-filling cable trench.
6.4.4.13 A final 75mm layer of sand shall be placed over the top layer of cables, followed by a row of correct width,
suitably marked cable tiles. The tiles shall cover the width of the cable run, with a minimum 50 mm overlap at
each side. Cable trenches will be subject to inspection by the COMPANY prior to final back fill.
6.4.4.14 A continuous line of proprietary plastic warning marker tape shall be installed along the line of the cable trench,
300mm below the surface, to give future excavators warning of buried cables.
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 22 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.4.4.15 The back fill material in cable trenches shall be well compacted and the ground re-instated to its finished grade
level. The back fill shall be free from large stones or other injurious objects to a level at least 150 mm above the
cable protection tiles.
6.4.4.16 If cables are left exposed above the ground they shall be coiled and suitably protected against damage, with
the cut ends protected against the ingress of moisture. Alternatively if any such cable is left on the drum then
the drum must be lowered from its jacks and firmly anchored. The immediate area around the drum shall be
fenced.
6.4.4.17 Installed cables shall be fitted with corrosion resistant identification tags at 30m intervals, at joints, at bends and
either side of wall penetrations. All tags shall be suitable for installation below ground.
6.4.4.18 The routes of buried cables shall be identified by red concrete cable markers set into the ground and projecting
approximately 600mm above grade. The markers shall be positioned at 50m intervals on straight runs and at
points where the cable route changes direction. The markers shall be placed directly above the underground
cable identification tags. Cable trenches shall be provided with single markers on the centreline of the run.
Similar markers suitably inscribed shall be used to indicate the position of any underground joints.
6.4.4.19 Where cables are to be installed in ducted road crossings, the precise location of each cable, as indicated on
the construction drawings, shall be strictly adhered to.
6.4.4.20 All such ducts shall be cleaned and inspected prior to installation, to ensure the absence of debris and sharp
objects, and temporarily sealed immediately after cable installation to prevent the entry of such debris, or water.
The ducts shall be permanently sealed as soon as all cables are installed with easily removable material.
6.4.4.21 French chalk shall be applied to the outer sheath of cables before installation to prevent abrasion between
cables and between cables and duct.
6.5

CABLE GLANDS AND TERMINATIONS

6.5.1

Cable Glands and Entries

6.5.1.1 All cables shall be properly terminated using proprietary compression type cable glands of the correct size and
specification. All cable glands used in plant areas shall be dual certified EExd IIC / EExe. Industrial glands
shall be used indoor in non-hazardous area buildings. Conductors shall be terminated using approved pin
crimp ferrules or compression lugs. Cable gland shrouds are not required and shall not be used. It is not
envisaged that barrier type cable glands will be employed on the power cable terminations.
6.5.1.2 The type and size of gland shall be in strict accordance with the construction drawings, data sheets and
schedules. The Installation Contractor shall confirm that the purchased cable is dimensionally in accordance
with the applicable standards and be responsible for checking the correctness of cable gland fit to cable prior to
installation.
6.5.1.3 The Contractor shall ensure that all personnel involved with cable terminations are familiar with the various
types of glands to be used, their method of installation and the correct spanner size to be used. Failure to meet
this requirement will result in the Contractor having to rectify installations at his own expense, without detriment
to any target completion date. The Contractor shall be required to replace, at his expense, any badly installed,
severely marked or damaged glands or lock nuts, as directed by the COMPANY.
6.5.1.4 Glands for multicore power and control cables shall be manufactured from brass. Glands for single core
aluminium armoured power cables shall be manufactured from aluminium. All glands shall have an appropriate
IP rating and utilise fibre washers between the gland body and the gland plate to maintain the IP rating of the
enclosure.
6.5.1.5 During assembly, the threads of all cable glands shall be lubricated with approved, non toxic, safe handling
grease prior to installation into EExd threaded entries.
6.5.1.6 Cable entries of explosion proof equipment shall not be drilled out or altered in any way. Any surplus, unused,
threaded cable entries shall be sealed using an appropriate type of certified screwed plug that also maintains
the maximum and minimum Temperature Rating of the enclosure.
6.5.1.7 Where enclosures have clearance holes instead of threaded gland entries, cable glands shall be secured by
locknuts fitted with serrated star washers to ensure earth continuity.
6.5.1.8 Where the design of HV switchgear and control-gear necessitates the provision of an externally mounted core
balance current transformer for earth fault protection, the following requirements shall be implemented:
a)
b)

All conductors shall pass through the current transformer.


Insulated gland adaptors shall be fitted to the respective gland plates
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 23 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

c)
d)

Earth tags shall be fitted between gland bodies and the insulated adaptors
Earth tags at each termination shall be bonded together and earthed by an insulated earth cable
passing back through the core balance current transformer prior to terminating on the switchboard
earth bar.
e)
Each gland plate shall be bonded with a protective conductor to the respective earth bar or stud.
6.5.1.9 Generally, cable entries to equipment in external locations shall be located on the underside of equipment.
Where this is impracticable, side entry may be used provided the cables are installed with a downward slope.
All cables shall be supported to avoid strain on either the cable gland or the equipment and at least 100mm of
straight cable shall be left before a bend is formed.
6.5.2

HV and LV Cable Terminations

6.5.2.1 HV cable terminations above 6kV shall be of a stress relieving design. Power cable connections to Generators,
transformers and motors shall, generally, be effected via proprietary moulded, separable, elbow/bushing
connectors. Cable connections to HV switchgear and control-gear shall be carried out using stress-relieving
sleeves with trifurcating gloves, or heat shrink type terminations. The manufacturers instructions regarding
cable end preparation and termination shall be followed exactly, employing any recommended special tools. It
is particularly important that the Manufacturers recommendation for the length of individual core terminations is
followed. The Contractor shall immediately notify COMPANY representatives if this requirement is
compromised by space limitations within the equipment terminal box. COMPANY representatives will take
responsibility for defining the required solution.
6.5.2.2 The cores of power cables to be connected to motors, switchboards, process heaters and other power users,
shall be set to ensure strain free connections prior to fitting conductor termination lugs.
6.5.2.3 Only proprietary compression lugs shall be used for terminations, soldered lugs shall not be used.
6.5.2.4 LV cables with conductor cross-section up to and including 6mm2 shall be fitted with insulated pin crimp type
ferrules and terminated into SAK, or similar, type terminals, as supplied or approved by the COMPANY
representative.
6.5.2.5 Cables with conductor cross-section larger than 6mm2 shall be fitted with compression lugs to suit the
equipment terminals. The Contractor shall be responsible for confirming the type of terminations to be
employed and the utilisation of appropriate compression lugs.
6.5.2.6 It is of the utmost importance that the correct size of lug and that an appropriate ratchet or hydraulic crimping
tool are used for the size of cable being terminated. The Contractor shall ensure that all personnel are
conversant with the required termination techniques and fully aware of the standard of workmanship required.
6.5.2.7 The shanks of compression lugs used for the termination of cables in LV motor terminal boxes and other fieldmounted equipment shall be insulated with heat shrink sleeving to avoid the possibility of inadvertent contact
between adjacent uninsulated lugs. Care shall also be taken to ensure adequate clearance between lugs to
avoid abrasion fatigue and insulation breakdown of the sleeves.
6.5.2.8 Where practical, an adequate length of cable tail shall be left at all cable terminations to enable cores to be
connected to any terminal by the longest route. Cable tails shall be neatly looped or coiled and supported.
6.5.2.9 Spare cores shall be marked as spare and terminated in spare terminals, provided within the equipment, and
earthed. Where insufficient spare terminals are available, spare cores shall be connected directly to a
convenient earth point. Spare core length shall be maximised within the constraints imposed by the
equipment. Exceptions to this requirement, whereby only one conductor end is terminated due to potential
EMC constraints, will be defined in the construction drawings. Unless noted otherwise on construction
drawings, conductor earthing at one end only shall be at the field end.
6.5.2.10 For control cables, no more than two conductors shall be connected to any one terminal, one incoming and one
outgoing. Where multiple conductors are required to be terminated at the same point, then the required number
of terminals shall be interconnected by proprietary links. The link shall not occupy the same terminal as the
conductor.
6.5.2.11 The arrangement and connection of power cables within LV Distribution Boards shall provide sufficient room to
enable a clip-on ammeter to be used without stressing the cable.
6.5.3

Cable and Core Identification

6.5.3.1 Every cable shall have a unique identification number, as recorded in the construction drawings and cable
schedules.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 24 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.5.3.2 All cables shall be identified at their points of origin and destination and at both sides of any wall or floor
penetration. The DOT cable marking system shall be used. Identification labels shall consist of user printable
flame retardant heat shrink sleeves for cable cores and smaller diameter cables, and polyamide strips for larger
cables. Marker strips shall have slotted ends to permit fixing to the cable by means of nylon ties.
6.5.3.3 Each cable core shall be uniquely identified at both ends by a core number or by phase colour, as applicable,
and as shown on the construction drawings, schematic and connection diagrams. For power cables where the
core insulation colour matches the corresponding phase colour, no further marking is necessary. However,
where core insulation does not match the phase colour, appropriately coloured sleeves shall be fitted at the
termination point.
6.5.3.4 Core identification shall be by proprietary heat shrink ferrules suitable for thermal print inscription. Ferrules that
do not completely encircle the conductor, or paper or adhesive markers, are not permitted.
6.5.3.5 Cable core identification on horizontally terminated cores shall read from left to right, and on vertically
terminated cores shall read from bottom to top.
6.6

EARTHING AND LIGHTNING PROTECTION

6.6.1

Earthing System Installations

6.6.1.1 Earthing protection systems shall be installed in accordance with the construction drawings and standard
earthing installation details.
6.6.1.2 The Contractor shall ensure that all personnel carrying out earthing installation work are fully trained and
experienced, and that any manufacturers instructions are strictly observed.
6.6.1.3 The plant earth system for onshore plants shall take the form of a ring of insulated copper conductors laid
around the plant with sub-rings connected, as required, to the main ring and with branch interconnections to
equipment and structures. Exothermic fusion welded type joints shall be used for underground connections and
compression type crimps for above ground connections. All underground connections shall be insulated with
suitable insulation tape or heat shrink insulation. Stainless steel rod electrodes shall be installed at selected
points around the ring to form a multi-point earthing system. The rods shall be driven directly into the ground
without excavation or drilling. Locations and depths of electrodes are indicated on the construction drawings.
The maximum value of resistance of individual earthing electrodes to the general mass of earth shall not
exceed 1 ohm. Rod type earth electrodes shall be spaced at intervals required to comply with resistance values
stated on drawing number KE01-00-945-KD-E-YS-0001-001, Earthing Methods Diagram .
6.6.1.4 If earth loop impedance tests are unsatisfactory, the Contractor will be required to install additional lengths of
electrodes until the specified value of resistance is attained. If necessary, buried earth mats shall be formed
from stainless steel tapes. The electrodes shall be bonded by PVC insulated copper cables to the earth mats
and to the main earth bars located in Substations, within buildings and on external steel plant structures.
Disconnecting links shall be installed at earth bars to permit periodic maintenance testing. Electrodes shall be
connected by clamps.
6.6.1.5 Earth electrodes shall be installed via proprietary earth pits, as recorded on the construction drawings and
earthing layouts.
6.6.1.6 Underground earthing conductors routed independently from cable rack or plant structures, outside of a
dedicated cable trench, shall be installed at a minimum depth of 600mm below grade.
6.6.1.7 On offshore installations the welded structure of the installation shall be considered as earth.
6.6.1.8 Earthing system interconnections shall be by single core cables with stranded copper conductors and
green/yellow PVC insulation. The cross sectional areas of earth bars and earth conductors shall be equal to, or
greater than, the relevant dimensions specified in the construction drawings and project specifications.
6.6.1.9 Earthing systems within substations or electrical equipment rooms shall be installed in accordance with the
construction drawings. Where applicable, earth bus bars shall be installed 600mm above floor level and
adequately supported from the substation or electrical room walls in accordance with the Standard Earthing
Details. The Contractor shall ensure that there is ample access space around the earth bars for testing
purposes.
6.6.1.10 Joints and tees between sections of copper bar shall be tinned and bolted, each joint shall have a minimum of
two bolts, soldering is not permitted. Cable connections to earth bars shall be bolted via tinned lugs crimped to
earth cables, the earth bar shall be tinned at the point of connection.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 25 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.6.1.11 The armour of all cables shall be earthed via the cable glands and gland plates. Cable armour shall not be
used as the principal earth conductor. Where necessary, power system earth continuity shall be maintained
via a separate earth core, as indicated in Table 5.5.1.
6.6.1.12 The armour of all single and multicore cables shall be earthed at each end of the cable via compression glands.
Single core cables are specified with aluminium armour and shall be terminated via aluminium cable glands
fitted to non-ferrous gland plates. All gland plates shall be separately earthed and shall not rely on the gland
plate fixing bolts.
6.6.2

Bonding

6.6.2.1 Every structure and item of plant equipment, including prefabricated steel buildings and pipe-rack, shall be
substantially and effectively connected to earth in the manner specified in the construction drawings. Any
omission in this respect shall immediately be brought to the attention of the COMPANY.
6.6.2.2 Earthing and bonding connections, having a conductor cross section of at least 6mm2, shall be arranged such
that disconnection of an earth conductor from a piece of equipment does not break the continuity of the
earthing and bonding system. Two earth lugs on to a single point connection is not acceptable.
6.6.2.3 All non-current carrying metallic parts of electrical equipment shall be connected directly to the main earth
system. The scope shall include, but not be limited to, generator and motor frames, switchgear and MCC
enclosures, cable ladder rack and tray, cable armour and glands, conduit and trunking, minor electrical
equipment including distribution boards, luminaires, junction boxes, control stations and suchlike.
6.6.2.4 The armour of cables in feeder circuits at LV distribution boards shall be bonded together and directly
connected to earth.
6.6.2.5 The metallic enclosures of utilities plant within buildings, including boilers, ductwork, flues, pipework, vessels
and tanks shall be bonded to the building earth system. Hot and cold water pipework and HVAC ducting shall
be bonded together at strategic points, storage tanks shall be bonded over incoming and outgoing pipes.
6.6.2.6 Unless a conductive contact is established naturally (via bolts, welds, etc), all exposed metalwork of electrical
and non-electrical equipment shall be bonded to the structure to ensure that the entire installation is an
equipotential zone.
6.6.2.7 Rail tanker loading gantries shall have a connection to earth at each end of the gantry. The connections shall
be to the general earthing system of adjacent facilities. Product pipelines shall be bonded to the loading gantry
either by means of pipe clamps or pipe flange bolts and loading hoses shall be electrically continuous from the
product pipeline to the loading nozzle or flange. A bond shall be installed across each swivel joint in metallic
loading arms. All rails shall be bonded together and connected to the loading gantry or main earth grid.
6.6.2.8 To guard against stray currents from external sources, insulation shall be inserted in appropriate rails leading to
the loading gantry and any live contact rails or overhead conductors shall terminate outside the loading
compound.
6.6.2.9 For earthing helicopters during refuelling, a reel of flexible cable, minimum size 35mm2, with a clip for attaching
to the helicopter, shall be installed in a non-hazardous area adjacent to the helipad / helideck. The reel shall
incorporate a slip ring to pick up the connection to earth.
6.6.2.10 Pipes entering or leaving hazardous areas shall be bonded together and to a common local earth bar
connected to the main earth system. Pipe-work flanges and pipe to vessel, or equipment, connections, where
not electrically continuous, shall be provided with copper bonding straps unless cathodic protection is installed.
6.6.2.11 All earthing studs on equipment shall be cleaned prior to connection of earth conductors. The connection shall
be secured by locking nuts then coated with an approved anti-oxidant corrosion inhibitor.
6.6.2.12 Instrument and control panel steelwork in control rooms or in plant areas shall be bonded in accordance with
the construction drawings. Particular care shall be taken to ensure that instrument earth and power system
earth systems remain isolated up to the common point of connection.
6.6.3

Lightning Protection

6.6.3.1 Lightning protection systems shall be installed in accordance with the construction drawings and standard
earthing installation details.
6.6.3.2 The maximum value of earthing resistance for lightning protection systems to the general mass of earth shall
not exceed 10 ohms.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 26 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.6.3.3 Where practicable, lightning protective systems onshore shall utilise the same earth electrodes as used for
power system earthing installations but the interconnections from structures to earth electrodes shall be by
separate tapes or insulated cables. For offshore installations the platform steel structure shall be used as the
main earth for lightning protection.
6.7

LIGHTING AND SMALL POWER INSTALLATIONS

6.7.1

The lighting and small power layout construction drawings will indicate the approximate locations of luminaires,
switches and socket outlets and their methods of fixing. The Contractor shall determine the precise location of
each fixture on site and will be able to access the 3D PDS design model to assist this process. Luminaires shall
be located to facilitate re-lamping, avoid interference with piping, or other mechanical equipment, and to obtain
a uniform level of illumination.

6.7.2

Unless shown otherwise on the construction drawings the mounting height of luminaires and accessories shall
comply with the following, measured from the finished floor level, or working platform, to the centre of the item:
Switches for lights

1400mm

Socket outlets

500mm

Socket outlets above work tops.

1100mm

Bulkhead luminaires

2500mm

Emergency luminaires at exits

2000 - 2500mm

Distribution boards

1500mm

6.7.3

Luminaires shall be positioned so that areas or fixtures such as stairways, landings, and ladders are
adequately illuminated.

6.7.4

In order to facilitate re-lamping, light fittings over walkways and platforms shall be mounted not less than
2000mm and not more than 2200mm above the walkway, or platform, and shall be mounted not less than
1000mm inside the edge of any such platform or walkway. In the case of narrow platforms or walkways, less
than 2000mm wide, the luminaires shall be mounted on the centre line of the platform. The top handrails of
walkways, stairways and platforms shall not be obstructed by supports of stanchion type lighting fixtures.

6.7.5

Luminaires in plant areas shall, wherever possible, be spaced symmetrically. The sizes, types and colours of
lamps to be fitted will be shown on the construction drawings or schedules.

6.7.6

In pump compounds, and other areas at ground level, luminaires shall not be mounted more than 3250 mm
above the level of the floor, unless otherwise specified on the construction drawing.

6.7.7

In general, Goose Neck mountings shall not be used, except in isolated cases where no other method of
fixing is practicable. Generally, bulkhead fittings fixed between handrails, and recessed so as not to form an
obstruction, shall be used to illuminate platforms and the tops of tanks.

6.7.8

The number of junction boxes used on lighting circuits shall be kept to a minimum. When junction boxes are
used they shall be located in easily accessible positions, in-board of platform edges, and not more than
2200mm above the working floor level. All junction boxes shall be fitted with permanent labels denoting circuit
reference.

6.7.9

Luminaires and socket outlets shall be wired strictly in accordance with the circuits shown on the construction
drawings and Standard Detail drawings. Where two or more lighting cables are run together they shall be fixed
to cable tray, or run in trunking. Single cables may be fixed direct to steelwork.

6.7.10 All luminaires and items of small power equipment shall be bonded to earth in accordance with the Standard
Earthing Details.
6.7.11 Floodlights shall not be diverted from the aiming points indicated on the construction drawings. If, during
construction, the Contractor wishes to illuminate other working areas this will be subject to the approval of the
COMPANY. If re-alignment is approved the Contractor shall return the floodlights to their design aiming point
when requested or, in any event, before he leaves the site.
6.7.12 All lighting fittings shall be labelled with the fitting and circuit references shown on the construction drawings.
Labels shall be fixed near lighting fittings but not on them.
6.7.13 Certified lighting and small power equipment shall not be modified, altered or drilled in any way, neither shall
terminals be added or substituted in marshalling and junction boxes, unless allowed within the scope of
equipment certification. Should there be a need for modification the COMPANY shall be consulted.
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 27 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.7.14 The approximate locations of junction boxes and control stations will be shown on the construction drawings.
Precise locations shall be determined on site by the Contractor.
6.7.15 Junction boxes and control stations shall be securely fixed, they shall not be bracketed off pipes or pipe
flanges. Generally, motor control stations will be mounted on stands, supplied as indicated in the Standard
Installation Details, and located in positions so as not to interfere with maintenance access space required for
dismantling or removal of pumps, motors or pipe work at a future date.
6.7.16 Following installation and termination of incoming cables, all items of the equipment shall be thoroughly
checked for cleanliness and confirmed free from damage or rust. The Contractor shall clean dirty equipment
and will be required to replace damaged items.
6.8

ELECTRIC SURFACE HEATING

6.8.1

Electrical surface (trace) heating systems shall be installed strictly in accordance with the construction
drawings, Supplier IOM instructions and the directions of any relevant on-site Supplier representative and
where appropriate, in co-ordination with the insulation installer.

6.8.2

Trace heating tapes and jackets shall be stored in warm, dry, conditions to avoid moisture ingress. After
withdrawal of materials from the stores the Contractor shall ensure that the tapes continue to be stored in warm
dry conditions before installation.

6.8.3

The electrical insulation resistance and continuity of tapes and jackets shall be tested before and immediately
after installation, the results being recorded on formal project test sheets. A further test cycle shall be
performed after the application of pipe or jacket lagging to ensure that no damage has occurred to the heat
tracing equipment during installation and lagging.

6.8.4

Each trace heating tape shall be fitted with a tape seal kit as it passes through pipe or vessel cladding.

6.9

CATHODIC PROTECTION
Cathodic protection systems for submerged or buried structures, vessels, pipes and tank bases shall be
installed strictly in accordance with the construction drawings, the Supplier IOM instructions and the
instructions of any on-site Supplier representative, and in co-ordination with the tank and tank foundation
installers.

6.10

PAINTING AND COATING

6.10.1 Painting and coating of equipment shall comply with the Project Specification and data sheets listed in the
respective equipment requisition.
6.10.2 The Contractor shall make good any damage to painted or coated surfaces of equipment, or steelwork, as
necessary.
6.11

EQUIPMENT PLATES, NAMEPLATES, RATING PLATES AND LABELS

6.11.1 Manufacturers Equipment Plates, Nameplates and Rating Plates will be fitted to all equipment. Additional
Danger or Warning plates shall be fitted by the Contractor where necessary. All information shall be given in
dual language (Russian and English).
6.11.2 Warning notices, cable route markers, cable markers and wiring ferrules shall be installed by the Contractor in
accordance with the contract documentation.
6.11.3 All electrical minor equipment, bulk materials and components, as listed below, shall be clearly identified with
labels supplied and fitted by the Contractor. The wording and character size of all labels shall be in accordance
with the contract documentation, subject to approval by the COMPANY representative. Labels shall be
provided for, but not limited to, the following items:

Luminaires
Junction boxes/marshalling boxes
Control stations
Motors
Heaters
Isolating switches
Control switches
Cable ladder rack and tray
Cable Transit
SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 28 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

6.11.4 Labels shall be of the engraved laminated plastic type, or approved equal and shall be dual language,
Russian/English. Identification labels shall comprise black characters on a white background. Warning labels
shall comprise black characters on a yellow background, complying with the requirements of the relevant IEC
Standard, and shall be fitted directly to all items of electrical equipment.
6.11.5 Rotating machinery subject to automatic, remote, control shall be provided with a warning label reading:
DANGER THIS MACHINE LIABLE TO START AUTOMATICALLY
6.11.6 Warning of electrical hazard shall be provided on equipment and component cover plates and on any access
doors not provided with interlocked isolators. Warning labels shall be fitted with appropriate legends including:
WARNING SUPPLIES MUST BE ISOLATED BEFORE REMOVING COVER
WARNING HEATER ENERGISED WHEN MOTOR STOPPED
ISOLATE ELSEWHERE
6.11.7 Labels shall be fixed to equipment or supporting steelwork with stainless steel screws and shall not infringe
hazardous area Ex certification or IP rating of the respective enclosures. Self-tapping screws shall not be
employed.
7.0

INSPECTION, TESTING, PRE-COMMISSIONING AND COMMISSIONING

7.1

GENERAL

7.1.1

The Contractor shall undertake all inspection, testing, pre-commissioning, or mechanical completion activities
for the complete electrical installation, to verify compliance with the relevant specifications. Any additional tests
considered necessary by the COMPANY, or directed by the COMPANY representative, shall be included.

7.1.2

The Contractor shall provide all technical personnel, tools, certified/calibrated test instrumentation and test
power supplies, to carry out inspection, testing and pre-commissioning testing activities in accordance with this
specification and as per the COMPANYs procedures. In the specific case of a.c and d.c UPS systems the
Contractor shall provide a suitably rated load bank to facilitate battery discharge and re-charge tests.

7.1.3

The Contractor shall provide a complete set of As-Built documentation for the installations prior to any
commissioning activities being undertaken.

7.1.4

All inspection and test results shall be recorded on the appropriate Inspection and Test Record Sheets.
Inspection and test record sheets shall be prepared by the Contractor and approved by the COMPANY. The
Contractor shall be fully responsible for ensuring that Inspection and Test Record sheets satisfy the
requirements of the local ROK inspection authorities and that all documentation is properly certified and
stamped.

7.1.5

Unless otherwise agreed with the COMPANY, tests shall be carried out in the presence of and to the
satisfaction of COMPANYs Site Representative. All Test Record sheets shall be signed by an authorised
representative of the Contractor and by the COMPANYs site representative.

7.1.6

The Contractor shall transfer all original Inspection & Test Record sheets to the COMPANY in accordance with,
and as indicated in the COMPANYs procedures.

7.1.7

The Suppliers of major electrical equipment will provide, within their IOM manuals, details for installing, site
testing and commissioning equipment within their scope of supply and will provide representatives to assist
during installation, site testing, commissioning and initial energisation of the equipment. All items of electrical
equipment will have been fully tested at the respective Suppliers works and complete test records will be
supplied with the equipment.

7.1.8

The Contractor shall carry out standard tests of insulation, continuity, phase orientation and correct operation,
together with all other tests that may be deemed necessary to prove that the electrical installation is
satisfactory. Installations failing to pass such tests, to the satisfaction of the COMPANY, will be rejected and the
Contractor shall carry out all work necessary to bring the electrical installation to a satisfactory working
condition and repeat the tests to the satisfaction of the COMPANY.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 29 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

7.2

INSULATION TESTING

7.2.1

Insulation tests shall be carried out during construction and at the pre-commissioning stage, prior to the
energisation of equipment or cables. The following two methods shall be used:

Insulation resistance testing, applicable to all electrical equipment including, but not limited to,
generators, transformers, switchgear, motors, UPS systems, distribution boards, trace heating
installations, lighting and small power installations, field cables, earthing and bonding systems and
all other items of electrical equipment. Where equipment contains components, such as silicon
diodes or transistors, or wiring, that is susceptible to damage by over voltage, these items shall be
disconnected prior to commencing tests.

High voltage testing, applicable to switchgear rated at 400V and above and HV cables.

7.2.2

Test voltages shall be in accordance with the relevant IEC Standard or manufactures recommendation and
shall be specified in the equipment commissioning procedure.

7.2.3

Insulation Resistance Tests

7.2.3.1 Insulation resistance tests shall be conducted prior to executing high voltage tests. Insulation resistance shall
be measured by applying a d.c test voltage from a Megger insulation meter or equal. For correct comparison
of test data, any subsequent insulation resistance tests should be carried out at the same voltage level as the
initial test.
7.2.3.2 The measured resistance value is also dependent on the temperature of the insulation and shall be corrected
as necessary. As a guide, the insulation resistance of windings reduces by approximately 50% for each 10C
rise in temperature.
7.2.4

High Voltage Withstand Tests

7.2.4.1 Prior to and on completion of conducting high voltage tests, insulation resistance tests shall have been carried
out.
7.2.4.2 High voltage testing may be carried out by applying either an a.c. power frequency voltage, a very low
frequency voltage (VLF) or a d.c. voltage, at a level above the operating voltage, in accordance with the
relevant International Standards.
7.2.4.3 Testing at power frequency is preferred and a.c test equipment must be capable of supplying the capacitive
current requirement of the item under test. As such test equipment is bulky, and normally impractical for field
use, d.c test equipment may be used for cables whereas a.c test equipment shall be used for switchgear.
Cable tests shall record values of leakage current versus time.
7.2.4.4 High voltage a.c testing of major electrical equipment will have been conducted at the Suppliers works to
values specified in the relevant International Standards. As repeated high voltage testing may stress winding
insulation such tests shall not be applied at site to generators, motors or transformers. If, however, for special
reasons (e.g. when equipment has been partially assembled at site) such tests are considered to be
necessary, they may be carried out after consultation and agreement with the COMPANY and the Suppliers
Site Representative but at a reduced voltage level corresponding to 70% of the factory test voltage.
7.2.5

Polarisation Index

7.2.5.1 Polarisation Index tests will be carried out on all HV motors. The test results will be compared with those
values obtained during the Factory Acceptance Tests.
7.2.5.2 The Polarisation Index is the ratio of the value of insulation resistance measured after one minute to that
measured after ten minutes, during continuous testing, at the appropriate voltage, ie: PI = R10 min/R1 min.
7.2.5.3 The Polarisation Index, being a ratio, is practically independent of winding temperature and test voltage. The
ten minute measurement allows the capacitive current, the leakage current over the surface of the insulation
and the dielectric absorption current to stabilise.
7.2.5.4 The Polarisation Index gives an indication of the condition of winding insulation, with regard to its dryness and
cleanliness. The value will be lower for dirty, wet or chemically contaminated windings.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 30 of 33

Agip KCO
KDPC
7.2.6

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

Interpretation of Results

7.2.6.1 Should values of insulation resistance or Polarisation Index fall below the minimum values specified, the
equipment should not be energized nor subjected to high voltage testing. The equipment and windings should
be heated and dried out prior to re-test.
7.2.6.2 Should a flash-over occur during high voltage testing then the test shall be deemed to have failed. Appropriate
remedial measures, such as cleaning, drying or, if necessary, repair should be adopted after which re-testing
shall take place.
7.2.7

Insulating Oil Tests

7.2.7.1 High voltage withstand tests shall be carried out using a standard Foster oil test set, or equal, with 25mm
diameter sphere head electrodes and a sphere gap of 2.5mm.
7.2.7.2 The minimum breakdown voltage shall be 30kV. The test sample shall be tested 6 times without breakdown
using the same cell filling.
7.2.8

Bearing Insulation Tests

7.2.8.1 Bearing Insulation tests shall be carried out on all HV motors.


7.2.8.2 The method of insulating bearings, as a means of controlling shaft current, depends upon the design and type
of construction and the methods employed to support the bearings.
7.2.8.3 In the case of pedestal bearings, or sleeve bearings, where housings are completely insulated from the body of
the machine, the insulation may be checked with the machine coupled and running at normal speed. This is to
establish that an oil film in the bearing will prevent electrical contact between shaft and bearing. An ohm-meter
applied across the insulation should indicate a resistance of >10k; values below this shall be investigated.
7.2.8.4 In the case of bearings having internally insulated shells or having insulated shafts, measurements shall be
carried out with the machine uncoupled and stationary. If, however, only one bearing is insulated verification is
limited to the inspection of the Suppliers QC documentation.
7.2.8.5 Where double insulation is applied to pedestal bearings, i.e. insulated around the bearing shell and at the
pedestal base, insulation resistance measurement at the mid section with respect to earth will indicate if either
insulation is bridged.
7.2.8.6 All tests shall be carried out in accordance with Suppliers instructions.
7.3

CONDUCTIVITY AND EARTH RESISTANCE TESTS

7.3.1

Conductivity Tests

7.3.1.1 Conductivity tests shall be carried out on switchgear bus-bar connections, and switchgear earth system joints,
in order to establish their tightness and condition. Conductivity testing shall be carried out with a Ducter (or
equal) low-resistance test set having a 20A, d.c, output.
7.3.1.2 Test results shall be recorded across all connections and for identical connections the measured values shall
not differ by more than 20% from each other.
7.3.2

Earth Resistance Tests

7.3.2.1 Earth resistance tests shall be conducted in accordance with the relevant International Standards.
7.3.2.2 All earth electrodes shall be tested by measurement of the resistance of the electrode against the mass of
earth, using a purpose made test set.
7.3.2.3 On offshore installations, random continuity checks using a Ducter or similar low resistance ohmmeter shall
be carried out to verify that equipment is effectively bonded to the structure.
7.4

EQUIPMENT WIRING AND TERMINAL CHECKS

7.4.1

Electrical wiring shall be checked against the Suppliers Schematic Diagrams and Diagrams of Connections, or
against the Contractors Interconnection Diagrams, as applicable.

7.4.2

The tightness of all terminals shall be verified.


SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 31 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

7.5

FUNCTIONAL TESTS

7.5.1

Functional mechanical & electrical tests shall be carried out to demonstrate the correct operation of all electrical
equipment and associated systems. This shall include primary and/or secondary current injection tests to check
the protection and metering circuits. Particular attention shall be paid to equipment interfaces, where there is a
greater likelihood of functional discrepancies.

7.5.2

Where complex control or interlock systems are used, the Contractor shall demonstrate compliance with the
design requirements using specific functional check-lists and system logic diagrams. Where such complex
systems require the input of the Suppliers site representative, for pre-commissioning activities, the Contractor
may be required to provide assistance.

7.6

PRE-COMMISSIONING

7.6.1

The Contractor shall provide means of access to enable a complete visual inspection of the installation and the
following visual checks shall be carried out in accordance with the COMPANYs approved Pre-Commissioning
Check Lists. All results shall be recorded.
a)

Removal and safe keeping of selected packing materials.

b)

Cleanliness of all equipment and components.

c)

Equipment identification plates, manufacturers nameplates and rating plate data comply with
the Drawings and the provision of cautionary or danger notices.

d)

Certified EEx (Ex) protection certification labels are correct and comply with the design
documentation and Hazardous Area Certification Schedule.

e)

Certified EEx (Ex) equipment enclosures and bulk materials comply with the manufacturers
specification, drawings and certification details.

f)

Configuration, alignment and tightness of fixing and holding down bolts. Integrity and
tightness of all electrical connections, terminations and cable glands.

g)

Operation of mechanical and key interlocks, safety shutters, access doors and locks. Provision
of padlocks and padlocking facilities.

h)

Correct degree of protection for equipment and materials. Provision, correct fitting and location
of gaskets and cable gland O ring seals.

i)

Application of approved corrosion resistant greases. Oil levels and grease packing of machine
bearings is satisfactory.

j)

Provision of earthing connections and effective earth bonding of equipment.

k)

Checking of fuse, MCCB and MCB ratings.

l)

Correct identification of equipment, cables and cable cores, cable ladder rack and cable tray.

m)

Correctness of circuit details with Schematic, Wiring and Interconnection Diagrams.

n)

Distribution board circuit schedules within the enclosures have been completed correctly.

7.6.2

On completion of all inspection, testing and pre-commissioning activities, the Contractor shall assist the
COMPANY in the commissioning of electrical installations as and when required. The Contractor shall not
energise any electrical equipment without prior approval of the COMPANYs Site Representative and, where
appropriate, the local RoK inspection authority.

7.6.3

Energisation of electrical equipment/systems will be done so under the strict control of the Permit to Work
system that will be in operation on the plant. The Contractor will be responsible for obtaining such Permit to
Work documents from the COMPANY representative or its appointed representative prior to any work being
carried out and such Permit to Work documents will be renewed on a daily basis.

8.0

PRESERVATION, HANDLING, STORAGE AND SHIPPING

8.1

Preservation, handling, storage, and shipping of Contractor equipment and materials shall comply with the
requirements detailed in the requisition and associated project specifications.

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING

Sheet 32 of 33

Agip KCO
KDPC

KE01-00-000-KD-E-SF-0020-000
Rev D02. 11 Feb 08

8.2

Panels or cabinets containing electronic components will be provided with silica gel bags and sealed with tape
or polyethylene sheeting. Panel fronts will be fitted with protective plywood sheets. Items with internal
preservation will be tagged and identified; the tagging will indicate the type of preservation used. Cable entries
shall remain plugged or capped throughout the period of storage and during installation.

8.3

Where it is necessary for the Contractor to lift any equipment, he shall be held responsible for the lift to be
carried out according to the Manufacturers instructions. Lifting tackle of adequate capacity and the correct
lifting points shall be used.

8.4

Internal anti-condensation heaters, when provided as permanent fittings within equipment, shall be energised
for the duration of the storage period.

8.5

Batteries shall be stored in a heated environment, charged up as necessary for preservation in accordance
with the manufacturers recommendations.

9.0

WEIGHT
The weights of all equipment, required for transport, lifting and installation activities, will be provided with
the Suppliers documentation.

10.0

MAINTENANCE REQUIREMENTS

10.1

During installation of electrical equipment due consideration shall be given to the ease of access for future
maintenance and operational requirements. Adequate access shall be provided for all equipment that shall be
installed such that all maintenance can be carried out with the minimum of special facilities or tools and with the
minimum use of ladders and scaffolding.

10.2

Major equipment items shall be supported on stainless steel shims at each mounting point to facilitate realignment at a later stage, tapered shims are not allowed. A sufficient quantity of pre-cut shims shall be
provided loose for site commissioning.

10.3

All components that require regular monitoring or maintenance shall be easily accessible by operations
personnel.

11.0

SPARE PARTS AND SPECIAL TOOLS

11.1

The Contractor shall take due notice where applicable of any special instructions detailed in the manufacturers
Manual for Erection and Testing.

11.2

All special tools supplied by equipment or material vendors for the installation, testing, commissioning and
maintenance of equipment, including any lifting equipment, shall be returned to the COMPANY after
commissioning.

11.3

Equipment Installation, Operation and Maintenance Manuals, which shall include a list of special tools, shall
also be returned to the COMPANY after commissioning.

12.0

DOCUMENTATION

12.1

The Contractor shall, as part of the scope of the electrical installation contract, supply complete sets of As-Built
drawings, and any other related design documentation as defined in the Contract documents.

12.2

As-Built drawings shall comprise the Contractors construction issue drawings, or Suppliers drawings, marked
up to accurately reflect all site implemented modifications or revisions to the design for the completed electrical
installation, as installed, connected, tested and commissioned.

12.3

The Contractor shall also supply As-Built drawings recording all work carried out under the Contract but not
covered in detail by the COMPANYs or Suppliers documentation. Typically this shall include cable routing
drawings above and below ground including any transits and rack numbers, supplementary lighting and small
power circuit diagrams and any additional support steel details.

12.4

All As-Built drawings and documentation shall be subject to the approval of the COMPANY representative.

12.5

One set of drawings shall be retained on site for an interim period whilst another set is used to revise the
Master Drawings.

12.6

The Contractor will be required to complete all Inspection and Test Record sheets as indicated in section 7.1

SPECIFICATION FOR ELECTRICAL INSTALLATION AND TESTING