Sei sulla pagina 1di 176

City ofCarmel-by-the-Sea

PUBLIC WORKS DEPARTMENT


POST OFFICE BOX CC
CARMEL-BY-THE-SEA, CA 93921
(831) 620-2070 OFFICE

29 October 2015

SENT VIA E-MAIL AND U.S. MAIL

State of California
Department of Industrial Relations
Division of Occupational Safety and Health
Fremont District Offices
Attention: Noemi Herrera
39141 Civic Center Drive, Suite 310
Fremont, CA 94538
DIRDOSHFREMONT@DIR.ca.gov

SUBJECT:

COMPLAINT NO. 1025533, RELATED TO CITY OF CARMEL'S PUBLIC


WORKS/ POLICE FACILITY (CONSTRUCTED IN 1966)

Dear Ms. Herrera:


The City of Carmel-by-the-Sea is in receipt of your letter dated October 13, 2015, which is
attached for reference, and I have been directed to compile the City's response.
A. Responses to Item No. 1 as listed in your letter:

1. 'When it rains the roofs of the Police Station and Public Works Department leak'.
a. True. This is the current situation. However, we have addressed and repaired
several of the leaks over the last year, and are in the process of repairing
what we anticipate are the last two leak sources . These final leak repairs
should be complete by December 30, 2015, if not earlier.
2. "Also, the basement of the Communications Department floods":
a. Note: "Communications Department" is not a department, but is a specific
area within the Police Station.
b. The statement that this area "floods" is inaccurate and an exaggeration of the
situation. During a rain event on December 19, 2014, water entered into the
Police Station: into a corridor adjacent to the communications room, and
roughly 5 feet through the doorway leading into the communications room.
We would describe the amount of water as relatively minor. It did not "flood"
to the point of resulting in a non-habitable space. Staff immediately mitigated
this leak and took clean-up actions as follows:
i. Staff installed sand bags which significantly slowed the source of the
leak.
ii. Staff vacuumed and mopped up the water in the corridor (with the
flooring material being vinyl tile); staff also vacuumed and dried out the
carpet in the Communications Room with fans.

Page 1 of 4

iii. Within a few days following this event, staff and a contractor
performed an exploratory investigation to locate the source of this
leak. The cause was pinpointed to a damaged, built-up asphalt
membrane within an outdoor landscape planter that abuts the Police
Department Head Quarters building. This source of the leak was
further temporarily mitigated by installing a rain tarp over the planter.
Refer to Exhibit "A", Items 1, 2, and 3; and Exhibit "B".
3. "Buckets are used to collect the water":
a. True (historically for some leaks I locations, but not all leaks were mitigated
with buckets).
b. Work performed as listed in Exhibit "A" has permanently fixed all but two
leaks; which are the planter as shown in Exhibit "B" and a planter located
above the Public Works portion of the facility, as shown in Exhibit "C". The
rain tarp has mitigated the leak into the Police Station. A bucket is still used
to mitigate the effects of the one remaining leak into Public Works Building.
The source of this leak is from the planter as shown in Exhibit "C", presumed
to be due to tree root damage to the planter membrane.
4. "This condition has existed for 5 years and has not been corrected":
a. Statement is partly true. The leaks coming from the two planters still exist.
However, as noted above in Response No. 1, these leaks are currently being
addressed. Moreover, over the course of the last year, all other leaks have
been repaired as indicated in Exhibit "A".
b. A summary of the work conducted to date towards addressing leaks is as
follows:
i. October 2014: Executed consultant agreement for "Part 1) Roofing &
Waterproofing Inspection Analysis & Evaluation; and Part 2) an
Asbestos, Lead Paint, and Mold Sampling & Report". Exhibit "D".
ii. December 2014: "Part 1) Roofing & Waterproofing Inspection
Analysis & Evaluation". Exhibit "E".
iii. December 2014: "Part 2) an Asbestos, Lead Paint, and Mold
Sampling & Report". Exhibit "F".
iv. December 19, 2014: Rain event where water entered into the Police
Station, immediately followed by work as described in Exhibit "A".
v. April 2015: Executed consultant agreement for bid specifications for
the "Planter Waterproofing Project at the Public Works & PDHQ
Building" project. Exhibit "G".
vi. June 2015: Publicly advertised for bids for the "Planter Waterproofing
Project at the Public Works & PDHQ Building" project. Exhibit "H".
vii. August 4, 2015: Council rejected bids for the "Planter Waterproofing
Project at the Public Works & PDHQ Building" project due to being
significantly higher than the City Engineer's estimate. Exhibit "1". Staff
commenced value-engineering the project in order to reduce the
project cost.
viii. The following is the Value-Engineered scope of work to resolve the
leaks at the two planters, for which work started approximately one
month ago, with an anticipated completion of November or December
2015, after which we anticipate that the roof will then be watertight with
all leak sources repaired:
1. Staff relocation of the City's nursery out of the eastern planter.
Work completed.

Page 2 of 4

2. Installation of temporary ventilation air intake ducting away


from work area to avoid smells and dust from entering the
Police Station. Work completed. Exhibit "J".
3. Removal of all vegetation and organic material within the
planters. Removal of drip irrigation. Work completed.
Contractor's invoice pending.
4. Removal and abandonment of the low voltage landscape
lighting. Work in progress.
5. Re-grading of planter subgrade soil for future relocated planter
drains. Work to follow Item 4 above.
6. Raising of the planter drains approximately 18 inches to
become surface drains. Work to follow Item 5 above.
7. Pouring of a concrete cap over top of the planters. Sloping of
concrete to surface drains. Work to follow Item 6 above.
8. Installation of two scuppers per each planter. Work to follow
Item 7 above.
9. Application of elastomeric coating on top of concrete cap.
Work to follow Item 8 above.
5. "As a result, there may be mold growth ... ": True.
a. Response: The City obtained a mold inspection, included in Exhibit "D". The
wood concrete formwork, left over from the original construction, located
within a crawl space under the planters, as noted on page 7 of Exhibit "D",
has been removed as part of the work listed in Exhibit "A". Upon completion
of the Value Engineered scope of work, as listed elsewhere, the City will
mitigate I remove all mold.
6. " ... and there may have been areas where mold on surfaces was painted over". Staff
has no knowledge of this occurring.
Please also note that it is our understanding that the person(s) who filed the complaint with
your office met with City officials prior to filing the complaint as well as shortly after filing the
complaint. At both of these meetings, City staff informed them of the progress accomplished
to date in addressing these leaks, and that the Valued Engineered scope of work was
underway, and our schedule to completing those repairs within the next few months. We do
also acknowledge that more specifics were provided at the latter of these meetings.
B. Responses to Item No.2 as listed in your letter:
1. Not currently true; circuit breakers and outlet plugs have been relocated and
protected from water leaks.
a. Until these actions were taken in approximately 2012, during rains, water
would to run down the wall that contained an electrical panel with circuit
breakers, outlet plugs, etc. The 2012 mitigation work for this potential hazard
involved relocation of the panels away from the walls using "uni-strut" I
"spacers" so that water ran behind the electrical in lieu of into the electrical.
Exhibit "K".
b. In addition, as a result of the work as noted in Exhibit "A", water no longer
runs down this wall.
We want to assure OSHA that the City of Carmel-by-the-Sea takes worker safety very
seriously, and have made substantial progress on the items noted in the subject complaint.

Page 3 of 4

We have also brought on several new staff members to assist with the Department's
workload and responsibilities, including a new Public Works Director, a new Project
Manager, and a new Public Works Superintendent.
We would be happy to further discuss the issues noted in the complaint and the City's past
and present actions to address these issues. If you would like to further discuss, please
contact me at (831) 620-2078. Thank you very much.
Sincerely,

~~~u7
Project Manager

Attachments: OSHA letter dated October 15, 2015


Exhibits "A" through "K"
cc:

Doug Schmitz, City Administrator


Rob Mullane, AICP, Public Works Director
Mike Calhoun, Public Services Director

Page 4 of 4

EDMUND G. BROWN JR., Governor

STATE OF CALIFORNIA

DEPARTMENT OF INDUSTRIAl RElATIONS

Division of Occupational Safety and Health


Fremont District Office
39141 Civic Center Drive, Suite 310
Fremont, CA 94538
Tel. # (510) 794-2521 Fax# (510) 794-3889

October 13, 2015


Attn: Doug Schmitz, City Administrator
City of Carmel-by-the Sea
P.O . Box CC
Carmel-By- The- Sea, CA 93921

City of Carmel-by-the-Sea

OCT 19 2015
Received

Dear Employer:
The Division of Occupational Safety and Health has received a complaint (Complaint No. 1025533) alleging the
following condition(s) at your workplace at 2nd location: Torres & 4th, Carmel By The Sea, which may be a
violation of the Safety Orders found in Title 8 of theCa lifornia Code of Regulations:
Code Section(s) and Alleged Condition(s):
1.

When it rains the roofs of the Police Station and Public Works Department leak. Also, the basement ofthe
Communications Department floods. Buckets are used to collect the water. This condition has existed for
5 years and has not been corrected. As a result, there may be mold growth and there may be areas where
mold on surfaces was painted over. See T8CCR Section 3362

2.

Electrical hazards. Electrical equipment such as circuit breakers and outlet plugs are not protected from
water leaks. The location is at the exit from the Police Station into the Public Works garage. When it rains,
water runs down the wall where the electrical equipment is located. See TBCCR Section 2510.5

To review Title 8, California Code of Regulations, go to www.dir.ca.gov, click on "Title 8 Regulations" then click on
"Cai/OSHA" and enter the code section number mentioned above.
Or you can go directly to
www.dir.ca.gov/samples/search/query.htm.
The Division has not determined whether the hazard(s), as alleged, exist(s) at your workplace and, at this time, the
Division does not Intend to conduct an inspection of your workplace.
However, you are required to investigate the alleged condition(s) and notify this office in writing no later than
fourteen (14) calendar days after receipt of this letter whether the alleged condition(s) exist and, if so, specify
the corrective action(s) you have taken and the estimated date when the corrections will be completed. Please
mail your response to Noemi Herrera, Safety Engineer, or e-mail at DIRDOSHFREMONT@DIR.ca.gov
Please include any written documentation, e.g., equipment purchase orders or contracts for corrective work,
and PHOTOGRAPHS, if appropriate, in your response. If you do not respond in a timely and satisfactory
manner, an unannounced inspection of your workplace will be scheduled, which may result in citation(s) and
monetary penalties. Also, every tenth satisfactory letter response from employers is subject to verification by
an inspection.
You are required to post a copy of this letter in a prominent location in their workplace where it is readily
accessible for employee review for at least three (3) working days or until the hazard is corrected, whichever is
longer.

This letter is not a citation or a notification of a proposed penalty. Citations and penalties can only be issued
after an inspection of your workplace. If the Division does not receive a satisfactory response from you within
fourteen {14) calendar days after receipt of this letter, an on-site inspection will be conducted as appropriate.
If the identity of the complainant is known to the Division, a copy of this letter will be sent to the complainant.
Also, the complainant will be notified that California law protects any person who makes a complaint about
workplace safety or health hazards from being treated differently, discharged or discriminated against in any
manner by their employer. If a complainant believes they have been discriminated against, it is their right to
file a complaint with the Division of labor Standards Enforcement within six {6) months of the discriminatory
action.
If you have any questions concerning this matter, please contact me at the address in the letterhead.
Your interest in the safety and health of your employees is appreciated.

s~~~~;f
Noemi Herrera
Safety Engineer
/ep
reference: Complaint No. 1025533- ltr D

PUBLIC WORKS DEPARTMENT

Exhibit A
Scope of Work for Roof Leak Repairs at the Public Works I Police Headquarters Facility:

1. Excavate within the landscape planter exposing the waterproof membrane for
inspection to determine its condition and develop a repair plan.
2. Extend the temporary rain tarp over the entire landscape planter.
3. Caulking of joints in the crawl space under the landscape planter abutting the Police
building.
4. Re-caulking of joints located outside the police building front door, the exterior landing
and steps. Caulking of joints in the crawl space under the landscape planter.
5. Water test deck drain piping system & associated repairs
6. Water test deck drain housings & associated repairs
7. Removal of decomposing wood form work within crawl space (potential source of mold,
and potential health hazard)
8. New water-tight crawl space hatch cover
9. Systematic and repetitive water testing deck areas to troubleshoot leaks
10. Removal of an old retro-fitted exhaust fan and ducting (found to be a major source of
leaks). Cover duct work opening top-side with plate aluminum, and caulk sealing.
Cover opening bottom-side with sheet metal "leader-head" with drain pipe tie-in to the
existing building plumbing.
11. Re-caulking of entire perimeter of parapet wall-to-deck intersecting joint.
12. Re-caulking of joints located outside the police building front door, the exterior landing
and steps.
This work fixed a significant number leaks (all but two) entering into the public works and
police department buildings.
Invoices from contractors for the above mentioned work for amounts of $21 ,855.82, $3,296.21,
$2,422.00 are attached.

Page 1 of 4

CUSTOMER#: CARM

TOMBLESONINCORPORATED

INVOICE#: 1

PO BOX 1388
SALINAS, CA 93902

INVOICE DATE: 01/28/15

(831) 422-9696 Fax (831) 422..0566

DUE DATE: 02/27/15

JOB: 15-712

BILL TO:

CAMEL-BY-THE-SEA- POLICE DEPT

DOCUMENT

DATE

( CODE

CARMEL POLICE DEPARTMENT

DESCRIPTION

AMOUNT

LABOR:

ROUGH CARPENTRY
CONSTRUCTION LABOR

01/28115

LABOR TOTAL:

17.640.00
17.640.00

MATERIAL:

CONSTRUCTION MATERIAL

01/28115

PREVIOUSLY BILLED:

MATERIAL TOTAL:

1.365.06
1.365.06

TOTAL COSTS:
15,0 % PROFIT:

19.005.06
2.850.76

INVOICE TOTAL:

21.855 .82

Thank you for your business!

c:J /L

----rb

p~

~d7~
&2---c?-.-l:;-

r?12-?J~./

* 7o 1e1I

!Exhibit A, page 2 of 4

TOMBLESON INCORPORATED

CUSTOMER#: CARM
INVOICE#: 2

PO BOX 1388

INVOICE DATE: 02/03/15

SALINAS, CA 93902
(831) 422-9696 Fax {831) 422-0566

BILL TO:
CAMEL-BY-THE-SEA- POLICE DEPT

( CODE

DOCUMENT

DATE

DUE DATE: 03/05/15

JOB: 15-712
CARMEL POLICE DEPARTMENT

DESCRIPTION

AMOUNT

LABOR:

ROUGH CARPENTRY
02/03/15

CONSTRUCTION LABOR
LABOR TOTAL:

MATERIAL:
02/03/15

CONSTRUCTION MATERIAL
MATERIAL TOTAL:

1. 376. DO
1. 376 . 00
1.314.58
1.314.58

-----

TOTAL COSTS:
15.0 % PROFIT:

2. 690.58

INVOICE TOTAL:

3, 094.17

403 . 59

Thank you for your business!

!Exhibit A, Page 3 of 4

Legacy Roofing & Waterproofing, Inc.

Invoice

1698 Rogers Avenue #10


San Jose, CA 95112

Bill To

Date

Invoice#

2/16/2015

8001283-WO

Job Location
CARMEL-BY-THE SEA
POBOXCC
CARMEL-BY-THE SEA, CA 93921

Description

POLICE/PUBLIC WORK BUILDING


CARMEL, CA

Terms

Project

Due on receipt

8001283

Qly

PO#

Rate

FURNISHED LABOR & MATERIAL TO PERFORM THE


FOLLOWING WORK

Amount
2,422.00

2,422.00

WORK PERFORMED: 12/18114


REPAIRED LEAKS PER ANDY.

Thanks for your business.


To Pay By Phone ca11408-467-0150

Total
Payments/Credits
Balance Due

Phone#

Fax#

408-467-0150

408-467-0151

$2,422.00

$0.00
$2,422.00

www.legacyrooting.nct

!Exhibit A, Page 4 of 4

ource of leak into Police Station was through this


uecause the planter membrane was damage by tree roots.

andscape Planter at Police HQ


date 10-26-15)

EXHIBIT "D"

Professional Services Agreement

@t:/'

THIS CONTRACT is executed this


day of
/
2014, by and between the
CITY OF CARMEL-BY-THE-SEA, hereinafter referred to as "CITY", and Skyline Engineering, Inc.
hereinafter called "CONSULTANT'.
IT IS HEREBY MUTUALLY AGREED AS FOLLOWS:
1.
Scope. CONSULTANT hereby agrees to provide to CITY, as the scope of services
under this Contract the services set forth in the attached proposal for Part 1) Roofing &
Waterproofing Inspection Analysis & Evaluation; and Part 2) an Asbestos, Lead Paint, and Mold
Sampling & Report, and incorporated herein by this reference:
2.
Timely Work. CONSULTANT shall perform all duties incidental or necessary in a
within 60 calendar days of the City's issuance of the Notice to Proceed; and shall be performed
diligently, competently and in accordance with professional standards of performance. Failure to so
perform is hereby deemed a material breach of this Contract, and CITY may terminate this
Contract with no further liability hereunder. CITY may agree in writing with CONSULTANT to an
extension of time. It is expressly agreed and understood that CONSULTANT shall not be held
responsible for delays occasioned by factors beyond their control, nor by factors that could not
reasonably have been foreseen at the time of execution of this CONTRACT.
3.
Term . The work under this Contract shall commence upon the issuance of the
Notice to Proceed, and shall terminate 180 days thereafter.
4.
Compensation . CITY shall pay CONSULTANT on a lump sum basis in the amount
of $4,700.00 for Part 1 and $6,700.00 for Part 2, for a total of $11,400.00 for services described in
the attached proposals. In addition the Contract will incorporate a contingency in the amount of
$3,000.00 to be used only upon approval by the Director of the City's Department of Public
Services. The grand total amount shall not exceed $14,400.00 unless additional services are
agreed upon in advance by the CITY per Section 5 of this Contract.
Compensation under this Contract shall become due and payable thirty (30) days
after CITY'S approval of CONSULTANTS submission of monthly written invoices. Written
invoices shall clearly itemize each charge. The payment of any compensation to CONSULTANT
hereunder shall be contingent upon performance of the terms and conditions of this Contract to the
satisfaction of the City Administrator.
If the City Administrator determines that the work set forth in the written invoice has not
been performed in accordance with the terms of this Contract CITY shall not be responsible for
payment until such time as the work has been satisfactorily performed .
5.
Additional Services. In the event that CITY should request additional services not
covered by the terms of this Contract, said services will be provided by CONSULTANT and paid for by
CITY only after a fee for said services has been agreed upon between CONSULTANT and City
Administrator and the City Administrator provides written authorization for the additional work.
6.
Meet and Confer. CONSULTANT agrees to meet and confer with CITY or its agents or
employees with regard to services as set forth herein as may be required by City Administrator to
insure timely and adequate performance of this Contract.
1

7.
Indemnification. CONSULTANT hereby agrees to the following indemnification clause:
To the fullest extent permitted by law (including, without limitation, California Civil Code Sections 2782
and 2782.6), CONSULTANT shall defend (with legal counsel reasonably acceptable to the CITY),
indemnify and hold harmless CITY and its officers, designated agents, departments, officials,
representatives and employees (collectively "lndemnitees") from and against claims, loss, cost,
damage, injury expense and liability (including incidental and consequential damages, court costs,
reasonable attorneys' fees, litigation expenses and fees of expert consultants or expert witnesses
incurred in connection therewith and costs of investigation) to the extent they arise out of, pertain to,
or relate to, the negligence, recklessness, or willful misconduct of CONSULTANT, any
SUB-CONSULTANT, anyone directly or indirectly employed by them , or anyone that they control
(collectively "Liabilities"). Such obligations to defend, hold harmless and indemnify any Indemnitee
shall not apply to the extent that such Liabilities are caused in part by the negligence, or willful
misconduct of such Indemnitee.
Notwithstanding the provisions of the above paragraph, CONSULTANT agrees to
indemnify and hold harmless CITY from and against any and all claims, demands, defense costs,
liability, expense, or damages arising out of or in connection with damage to or loss of any property
belonging to CONSULTANT or CONSULTANT'S employees, contractors, representatives, patrons,
guests or invitees.
CONSULTANT further agrees to indemnify CITY for damage to or loss of CITY OF
CARMEL-BY-THE-SEA property to the proportionate extent they arise out of CONSULTANT'S
negligent performance of the work associated with this Contract or to the proportionate extent they
arise out of any negligent act or omission of CONSULTANT or any of CONSULTANT'S employees,
agents, contractors, representatives, patrons, guests or invitees; excepting such damage or loss
arising out of the negligence of CITY.
8.
Insurance. CONSULTANT shall submit and maintain in full force all insurance as
described herein. Without altering or limiting CONSULTANT'S duty to indemnify, CONSULTANT
shall maintain in effect throughout the term of this Contract a policy or policies of insurance with the
following minimum limits of liability:
Commercial general liability insurance including but not limited to premises, personal
injuries, bodily injuries, products, and completed operations, with a combined single limit of not Jess
than $1 ,000,000 per occurrence and $2,000,000 in the aggregate.
Professional Liability Insurance. CONSULTANT shall maintain in effect throughout the
term of this Contract professional liability insurance with limits of not less than $1,000,000 per claim
and $2,000,000 in the aggregate. CONSULTANT will either maintain or cause to be maintained
professional liability coverage in full force or obtain extended reporting (tail) coverage (with the same
liability limits) for at least three (3) years following CITY'S acceptance of work.
Commercial automobile liability insurance covering all automobiles, including owned,
leased, non-owned, and hired automobiles, used in providing services under this Contract, with a
combined single limit of not less than $1,000,000 per occurrence.
If CONSULTANT employs others in the
Workers' Compensation Insurance.
performance of this Contract, CONSULTANT shall maintain workers' compensation insurance in
accordance with California Labor Code section 3700 and with a minimum of $100,000 per occurrence
for employer's liability.

-2-

Other Insurance Requirements


A.
All insurance required under this Contract must be written by an insurance
company either:
1)
admitted to do business in California with a current A.M. Best rating of
no less than A: VI; or
2)
A:VII

an insurance company with a current A.M. Best rating of no less than

Exception may be made for the State Compensation Insurance Fund when not
specifically rated.
B.

Each insurance policy required by this Contract shall be endorsed to state that
CITY shall be given notice in writing at least thirty (30) days in advance of any
cancellation thereof, except CITY shall be given TEN (1 0) days notice for
nonpayment of the premium.

C.

The general liability and auto policies shall:


1)
Provide an endorsement naming CITY, its officers, officials, and
employees as additional insureds under an ISO CG 20 10 07 04 or ISO 20 37
07 04 or their equivalent.
2)
Provide that such insurance is primary and non-contributing insurance
to any insurance or self-insurance maintained by CITY.
3)
Contain a "Separation of Insureds" provision substantially equivalent to
that used in the ISO form CG 00 01 10 01 or their equivalent.
4)
Provide for a waiver of any subrogation rights against CITY via an ISO
CG 24 01 10 93 or its equivalent.

D.

Prior to the start of work under this Contract CONSULTANT shall file certificates
of insurance and endorsements evidencing the coverage required by this
Contract with the City Administrator. CONSULTANT shall file a new or
amended certificate of insurance promptly after any change is made in any
insurance policy which would alter the information on the certificate then on file.

E.

Neither the insurance requirements hereunder, nor acceptance or approval of


CONSULTANT'S insurance, nor whether any claims are covered under any
insurance, shall in any way modify or change CONSULTANT'S obligations
under the indemnification clause in this Contract, which shall continue in full
force and effect. Notwithstanding the insurance requirements contained herein,
CONSULTANT is financially liable for its indemnity obligations under this
Contract.

F.

Any deductibles or self-insured retentions must be declared to and approved by


CITY. At the option of CITY either: the insured shall reduce or eliminate such
deductibles or self-insured retentions as respects CITY, its officers, officials,
employees and volunteers; or CONSULTANT shall provide a financial
guarantee satisfactory to CITY guaranteeing payment of losses and related
investigations, claim administration, and defense expenses.

-3-

9.
Ownership of Work. Upon completion of any work under this Contract, ownership and
title to all materials and deliverables produced as part of this Contract will automatically be vested in
CITY and no further contract will be necessary to transfer ownership to CITY.
10.
Licensing . CONSULTANT represents that it is properly licensed to perform the work
specified under this Contract, including but not limited to, possession of a current city business
license.
11.
Termination . This Contract may be terminated by either party upon thirty (30) calendar
days written notice to the other party. In the event of such termination, CITY shall pay CONSULTANT
for all services performed to the satisfaction of CITY to the date of receipt of notice of termination. An
itemized statement of the work performed to the date of termination shall be submitted to CITY. In
ascertaining the services actually rendered hereunder up to the date of termination of this Contract
consideration shall be given to both completed work and work in process of completion , and to
complete and incomplete drawings and other documents whether delivered to CITY or in the
possession of the CONSULTANT.
12.
Agency. In performing the services specified under this Contract CONSULTANT is
hereby deemed to be an independent CONSULTANT and not an agent or employee of CITY.
13.
Authority of the City Administrator. CONSULTANT shall perform all necessary
services provided under this Contract and outlined in the proposal and shall do, perform , and carry out
said work in a satisfactory and proper manner as determined by and to the satisfaction of the City
Administrator. The City Administrator reserves the right to make changes, additions or deletions, to
the scope of work as deemed necessary or advisable to implement and carry out the purposes of this
Contract. The City Administrator is authorized to execute change orders.
14.
Responsibility of Consultant. By executing this CONSULTANT represents and states to
CITY that he/she possesses, or will arrange to secure from others, all necessary professional capabilities,
experience, resources and facilities necessary to provide to CITY the services contemplated under this
Contract. CONSULTANT further warrants that he/she will follow the current generally accepted practices
of the profession to make findings, render opinions, prepare factual presentations, and provide
professional advice and recommendations regarding the project for which services are rendered under
this Contract.
15.
Materials and Equipment. CONSULTANT shall furnish at his/her own expense all materials
and equipment necessary to carry out the terms of this Contract.
16.
Digital Files. CONSULTANT shall furnish copies of all materials and deliverables on
compact disks (for example, final report) in digital format. Files shall be compatible with the current
versions used by PC computers.
17. Audit Authority. CONSULTANT shall keep full and detailed accounts and exercise such
controls as may be necessary for proper financial management under this Contract; the accounting and
control systems shall be satisfactory to CITY. CITY and CITY'S auditor shall be afforded access to
CONSULTANT'S records, books , correspondence and other data relating to this Contract.
CONSULTANT shall preserve these records, books , correspondence and other data relating to this
Contract for a period of four (4) years after final payment, or for such longer period as may be required by
law. In addition, CONSULTANT agrees to make said records, books correspondence and other data
relating to this Contract available to CITY at CITY'S principle place of business upon seventy-two (72)

-4-

hours advance written notice. The City Administrator, or his or her designee, shall at all times have the
right to inspect the work, services, or materials. CONSULTANT shall furnish all reasonable aid and
assistance required by CITY for the proper examination of the work or services and all parts thereof. Such
inspection shall not relieve CONSULTANT form any obligation to perform said work or services strictly in
accordance with the specifications or any modifications thereof and in compliance with the law.
18.
Notices. All notices herein provided to be given, or which may be given by either party to
the other, shall be considered fully received when made in writing and deposited in the United States mail,
certified and postage prepaid, and addressed to the respective parties as follows :
CITY:

City of Carmel-by-the-Sea
Public Services Department
P.O. BoxCC
Carmel-by-the-Sea
California 93921

CONSULTANT:

Skyline Engineering, Inc.


Attention: Bryan Schalesky, P.E.
8100 Wild Horse Road
Salinas California, 93907

19.
Entire Contract. This Contract constitutes the entire contract between the parties hereto
and supersedes any and all prior contracts, whether oral or written, relating to the subject matter thereof.
Any modification of this Contract will be effective only if it is in writing signed by both parties hereto.
20.
Validity. If any provision in this Contract is held by a court of competent jurisdiction to be
invalid, void or unenforceable, the remaining provisions will continue in full force without being impaired or
invalidated in any way.
21.
Assignment of Interest. The duties under this Contract shall not be assignable, delegable,
or transferable without the prior written consent of CITY. Any such purported assignment, delegation, or
transfer shall constitute a material breach of this Contract upon which CITY may terminate this Contract
and be entitled to damages.
22.
Conflict of Interest. CONSULTANT shall at all time avoid conflicts of interest, or the
appearance of conflicts of interest, in the performance of this Contract. CONSULTANT shall file
statements of financial interest on forms provided by CITY to the extent and at the times required by
CITY'S Conflict of Interest Code and applicable law.
During the term of this Contract CONSULTANT shall not directly or indirectly, either as a
partner, employer, employee, consultant, principal, agent or in any individual or representative capacity,
engage or participate in any business or voluntary activity on behalf of any other party on any property
located within the City of Carmel-by-the-Sea without notification to City Administrator.
23.
Non-discrimination/Affirmative Action. CONSULTANT will not discriminate against any
employee or applicant for employment because of race, creed, color, sex, age, national origin, marital
status, physical or other motor handicap, unless based upon bonafide occupational disqualification.
CONSULTANT will take affirmative action to ensure that applicants are employed and that
employees are treated during employment without regard to their race, creed, color, sex, age, national
origin, marital status, physical or other motor handicap.

- 5-

24.

Counterparts. This Contract may be executed in multiple originals, each of which is deemed
to be an original, and may be signed in counterparts.

25.

Laws. CONSULTANT agrees that in the performance of this Contract it will reasonably
comply with all applicable state, federal and local laws and regulations. This Contract shall
be governed by and construed in accordance with the laws of the State of California and the
City of Carmel-by-the-Sea.

26.

Attorneys Fees and Court Venue . Should either party to this Contract bring legal action
against the other, (formal judicial proceeding, mediation or arbitration), the case shall be
handled in Monterey County, California, and the party prevailing in such action shall be
entitled to a reasonable attorney's fee which shall be fixed by the judge, mediator or arbitrator
hearing the case and such fee shall be included in the judgment, together with all costs .

27 .

Severability. If any term of this Contract is held invalid by a court of competent jurisdiction the
remainder of this Contract shall remain in effect.

IN WITNESS WHEREOF, this Contract is entered into by the parties hereto in Carmel,
California, on the day and year first above written.

CITY OF CARMEL-BY-THE-SEA

CONSULTANT

By:

By: ~~

Bryan Schalesky, P.E.


Skyline Engineering, Inc.

City Administrator

By: _____________________

-6-

f'1 Ofl Wild

liur~

Salina~
[

'

~~

t f

e Roarl
CA 33907

..

fl:~ 6s:~.6"c~5

B31 .6G3 .61f!7

August 5, 2014
Andy Vanderford
City of Carmel by the Sea
PO BoxCC
Carmel by the Sea CA 93921

jPARl 1 OF TWO PARTS]

The following is a proposal for phase 1 (inspection/analysis) roofing/waterproofing


consulting services for the Public Works complex including all city-owned roofs/decks
outlined in red in this photo.

Email: bryan@skylineengineering.com- www.skylineengineering.com

Skyline Engineering

Page 2

The survey will include the following:


1.

Visual inspection of roofing/decking systems. We will include an analysis of the planters


but we do not intend to excavate the dirt.

2.

Interview owner personnel to obtain history of roof (age, leaks, etc.)

3. Review of existing drawings to confirm construction.


4.

5.

Written report in PDF. Report shall include the following:


a.

CAD drawing of the site showing roof/deck areas.

b.

Description of roof/deck construction for each area.

c.

Description of roof/deck condition for each area.

d.

Recommendations for repair or replacement for each area.

e.

Budgets for recommended work.

f.

Digital photographs of defects .

Meeting with City to discuss report and recommendations.

We can perform the above inspection. provide the report, and attend one meeting for a fee
of $4,700.
The police headquarters building and all associated police adjacent buildings are not included in
this proposal. The proposal does not include structural engineering. If structural engineering
inspection is needed, please contact me. This proposal shall be valid for a period of 30 days.
Thank you for allowing me an opportunity to work with you. Please contact me if you have any
questions.

Sincerely,

~~

Bryan Schalesky, P.E.


Skyline Engineering

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: skylinelnc@ix.netcom.com - www.skylineengineering.com

- - ' - - - - - - ~RI ~ G

NGIN
1

~ ,. ;.

... .

.. .

: .. ..

( .

' :j .

,,

8100 Wild Horse Road


Salinas CA 93907
F' 831 .663.6188
F 831.663.6187

August 12, 2014


Andy Vanderford
City of Carmel by the Sea
PO Box CC
Carmel by the Sea CA 93921
The following is a proposal for haz mat testing of the Police HQ & PW/PS Admin
complex including all city-owned roofs/decks shown in this photo. This includes testing
for asbestos, lead and mold.

Email: bryan@skylineengineering .com - www.skylineengineering.com

Skyline Engineering

Page 2

The hazardous materials testing will include testing for lead, asbestos, and mold at all
areas associated with the building envelope including the following:
1.
2.
3.
4.
5.

Built up roof membrane, flashings, and repairs.


Wood shake mansard and underlayment.
Interstitial space under patio decking over parking area.
Sealants located at patio decking over parking area.
Paints and coatings at or near all roof and patio deck areas that may be affected
by repairs or replacement.
6. Note: This does not include testing of any membrane or material buried within or
under the patio slabs. However, if we see any opening or opportunity to retrieve
these, we will do so. We are assuming for the sake of this proposal that these
materials are not accessible unless concrete is removed.

The report shall include the following:


1. Drawing with locations of tests keyed to result page.
2. Photos of each test area.
We can perfonn the above inspection and provide the report for a fee of $6,700.

This proposal shall be valid for a period of 30 days. If you have any questions or
concerns, don't hesitate to call.
Sincerely,

~~

Bryan Schalesky, P.E.


Skyline Engineering

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email : skylineinc@lx.netcom.com - www.skylineenglneering.com

CERTIFICATE OF INSURANCE
SUCH INSURANCE AS RESPECTS THE INTEREST OF THE CERTIFICATE HOLDER NAMED BELOW WILL NOT BE
CANCELED OR OTHERWISE TERMINATED WITHOUT GIVING 10 DAYS PRIOR WRITTEN NOTICE TO THE
CERTIFICATE HOLDER, BUT IN NO EVENT SHALL THIS CERTIFICATE BE VALID MORE THAN 30 DAYS FROM
THE DATE WRITTEN. THIS CERTIFICATE OF INSURANCE DOES NOT CHANGE THE COVERAGE PROVIDED BY
ANY POLICY DESCRIBED BELOW.
This certifies that:

[g) STATE FARM MUTUAL AUTOMOBILE INSURANCE COMPANY of Bloomington, Illinois

STATE FARM
STATE FARM
STATE FARM
has coverage in force for the following

0
0

NAMED INSURED:

FIRE AND CASUALTY COMPANY of Bloomington, Illinois


COUNTY MUTUAL INSURANCE COMPANY OF TEXAS of Dallas, Texas , or
INDEMNITY COMPANY of Bloomington, Illinois
Named Insured as shown below:

SCHALESf:Y , BRY;,N

& ~~AR!..O

8100 WILD HORSE RD, SALINAS, CA

93~n7-922 .'l

ADDRESS OF NAMED INSURED:


POLICY NUMBER
EFFECTIVE DATE
OF POLICY
DESCRIPTION OF
VEHICLE (Including VIN)

151 7159-D03-05G
4/3/14-04/03/15
06 TOY l'.VALON
i4TBK36BG6U164421

LIABILITY COVERAGE

[g) YES

LIMITS OF LIABILITY
a. Bodily Injury
Each Person

1,000,0()0

ONO

DYES

ONO

DYES

ONO

DYES

ONO

ONO
Deductible

DYES

0NO
Deductible

DYES

DNO
Deductible

DYES

DNO
Deductible

$ 250

ONO
Deductible

DNO
Deductible

DNO
Deductible

DNO
Deductible

DYES

~NO

DYES

DNO

DYES

DNO

DYES

DNO

DYES

~NO

DYES

DNO

DYES

ONO

DYES

ONO

DYES

~NO

DYES

ONO

DYES

DNO

DYES

DNO

Each Accident
b. Property Damage
Each Accident
c. Bodily Injury &
Property Damage
Single Limit
Each Accident
PHYSICAL DAMAGE
COVERAGES
a. Comprehensive

1,000,000
~YES

$ 100
~YES

b. Collision
EMPLOYERS NON-OWNED
CAR LIABILITY COVERAGE
HIRED CAR LIABILITY
COVERAGE
FLEET - COVERAGE FOR
ALL OWNED AND LICENSED
MOTOR VEHICLES

DYES

l,GENT

Signature of Authorized Representative


Name and Address of Certificate Holder
Add') Insured:
City of Carrrel by the Sea
PO B::JY. CC
Ca:nrel by the Sea CA 93921

DYES

DYES

05/2833

Title
Agent's Code Number
Name and Address of Aqent
STl'.TE F.I\RH
AGE~:T, KEN FELS, Agent
Auto-Life-Health-Home and Business
16360 Monterey St. Ste 270
Morgan Hill, Ca 95037
(408)779-4186 Fax (408)778-5757

INTERNAL STATE FARM USE ONLY : 181 Request permanent Certificate of Insurance for liability coverage.

03/13/2012
Date

122449.2 Rev 06-10-2004

l8l Request Certificate Haidet to be added as an Additional Insured.

~ 6028BU ADDITIONAL INSURED


~ (Prior Notice of Termination)

This endorsement is 11 par1 of rhe policy. Exce,pr for the changes this endorsement makes, all other
provisions of the policy remain the Slime and apply to this endorsement.
A per.~on or organization shown on the Declarations Page as an Additional lnst1red is provided
Liability Coverage, but only to the extent that person or ot-glmizotion qualifies as an insmed fiS
defined in Liabi Iii)' Coverag~.
2. An Additional Insured has the same right of recovery under Liability Coverage as if they had
not been shown on the Declarations P11ge liS m1 Additional Insured.
3. J f Liability Coverage is changed or terminated as to the interest' of the Additional Insured, unless another number of days notice is shown on \'he Decim-ations Page, we will provide the Additional Insured:
n. J 0 dflyS notice of such change or termination if the policy is nonrenewed or the cance llation is for nonpayment of premium; and
b. 20 days notice of Sllch change or termination if the cancellation is for any reason ocher than
nonpayment of premium.

1.

I
II
I

Ii

I
)

Pagel of I
Automobile )n$UJ'ancc Company, 20 II

0, C(lpyright, Stale Fnnn Mutu11i

6028BU

ACORD

CERTIFICATE OF LIABILITY INSURANCE

DATE (MMIDDIYYYY)

9/9/2014

THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to
the terms and conditions of the policy, certain policies may require an endorsement A statement on this certificate does not confer rights to the
certificate holder in lieu of such endorsement(s).
PRODUCER

~~r:CT

Pinnacle Risk Solutions

::tJg.NJ'o. Erll:

82

t,~~ss

Old Bloomfield Ave

I iffc. Nol:

(973)284-0100

(913)294-1.655

INSURER(S) AFFORDING COVERAGE

07058

NJ

Pine Brook

INSURER A :Ha.ll

INSURED

INSURER B:
Inc

Skyline Engineering,

8100

NAIC.

& Company.

INSURERC:

Wild Horse Road

INSURER D:
INSURER E:

93907

CA

Salinas

INSURER F:

CERTIFICATE NUMBERl4-l5 GL

COVERAGES

REVISION NUMBER

llOS IS TO CERTIFY THAT lliE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. NOTIIIIITHSTANDING ANY REQUIREMENT, TERM OR COND!TlON OF ANY CONTRACT OR OTHER DOCUMENT WTH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL lliE TERMS,
EXCLUSIONS AND CON01110NS OF SUCH POLICIES. LIMITS SHOIM-l MAY HAVE BEEN REDUCED BY PAID CLAIMS.
PO~ICY EFF
,,~~~
TYPE OF INSURANCE
LIMITS
1~1:
POUCY NUMBER
lwvn
M
GENERAL ~IABI~ITY
2,000,000
EACH OCCURRENC
s
1
300,000
$
~~~~J 'te~~~~~ncel
er~ERCIAL GENERAL LIABILITY
~/11/2014 9/11/2015 MED EXP (Any one parson)
6B0-9637H280-TIL-13
5,000
$
CLAIMS.MADE
OCCUR
A

'"""

r-r-r--

r--

'--

GEN'L AGGRn LIMIT A o PER.


j~
LOC

Xl POLICY

'--

UMBREL~

EXCESS

SCHEDULED
AUTOS
NON-OWNED
r-- AUTOS

2,000,000
4,000,000
4,000,000

BOOILY INJURY (Per accident) S

r--

LIAB

PRODUCTS- COM PlOP AGC:

BODILY INJURY (Per person)

......-

~lAB

r--

ANYAlJTO
ALL OWNED
AliT
OS
r-HIRED AUTOS

I ~~~~~fiSINGLE LIMIT

AUTOMOBI~ ~IABI~ITY

r--

PERSONAL .& AOV INJURY


GENERAL AGGREGATE

_fp~~;c%~J!AMAG~o

HOCCUR
C~IMS.MADE

j RETENTION S
DEO j
WORKERS COMPENSATION
AND EMP~OYERS' UABIUTY
YIN
ANY PROPRIETORIPARTNERIEJ(ECUTIVE
NIA
OFFICER/MEMBER EXCLUDED?
(Mandatory In NH)

EACH OCCURRENCE

AGGREGATE

s
s

JT~~T~J#;;J

JOJ:

E.L. EACH ACCIDENT

11 ves, Oescrlbe unc;ter

DESCRIPTION OF OPERATIONS bebv.

E.L DISEASE - EA EMPLO)'_Ef

E L CISEASE POLICY LIMIT

DESCRIPTION OF OPERATIONS I ~OCATIONS I VEH/C~ES (Attach ACORD 101, .Addlllonal Romarks Schedule, If more space lo required)
The City of Carmel by the Sea, its officers, officials and employees shall be named as additional insured
as per writen contract.
Waiver of SUbrogation applies as per written contract.

CANCELLATION

CERTIFICATE HOLDER

City of Ca.r.mel by the Sea


PO Box
93921
Carmel by the Sea, CA

cc

30 days written notice of cancellation applies.

SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE


THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS.
AUTHORIZED REPRESENTATIVE

M Caradimitropoulo/JP

ACORD 25(2010/05)
INS025 (201005).01

_c.

<;;;

--=:::-

@ 1988-2010 ACORD CORPORATION. All rights reserved.


The ACORD name and logo are registered marks of ACORD

COMMERCIAL GENERAL LIABILITY

Policy Number: 680-9637M280-TIL-13

THIS ENDORSEMENT CHANGES T'HE POUCY. PLEASE READ IT CAREFULLY.

BLANKET ADDITIONAL INSURED


(ARCHITECTS, ENGINEERS AND SURVEYORS)
This endorsement modifies insurance provided under the follOWing:

COMMERCIAL GENERAL LIABILITY COVERAGE PART


A

The following is added !o WHO IS AN INSURED


(Section H):

INSURANCE (Se<:tlon Ill) for this COverage


Part.

Any pe~n or organization that you agree In a


contract or agreement requiring insurance" to indude as an additional insured on this Coverage
Part, but only with respect to liability for "bodily Injury", 'property damage" or "personal injury
caused. in whole or in part, by your ac:ts or omissions or the acts or omissions of those ading on
your behalf:

B. The falowlng is added to Paragraph a. of 4.

In the perfonnance of your ongoing opera-

tions;
b. In connection with premises owned by or
rented to you; or
c. In connection with your woi'X" and Included
Within the 'product$-completed operatiOns
hazard".

Such person or organization does not Qualify as


an addlUonal insured for "bodHy injury", "property
damage or "personal injury' for which

that per-

son or organization has assumed llablity In a contract or agreement.


The insurance pro>Aded to such additional insured
is Hmited as follows:

d. This insurance does not apPly on any basis to

agreement requiring insurance that the insurance


provided lo an additional insured under this Coverage Part must apply on a primary baSis, or a
primary and non-contrllutory basis. this insurance
is primary to other insurance that is available to
such additiOnal insured which covers such aDditional insured as a named insured. and we Will not
share with the other insurance, provided that:
(1) The "bod"y injury" or ~property damage for
which oeverage is sought occurs; and

(2) The "personal injury" for which coverage is


sought arises out or an offense commiUed;
after you have entered into that -contract or
agreement requiring insurance. But this il'lsurance still is excess a-.er valid and CXIIIeclible other
insurance, whether primary, ~. contingent or
on any other basiS, that Is available to the Insured
when the insured is an additional insured under
any other insurance.

any person or organization for which cover-

C. The folloWing is added to Paragraph 8. Tre11sfar

Of Right Of RKovery Agatnst others To Us


in COMMERCIAL GENERAl UABIUTY CON
DITIONS (Section IV):

This inStJrance does not apply to the render-

ing of or failure to render any "professional


services".

f,

However, if you specifically agree in a contract or

age as an addiUonal insured spedflcally Is


added by another endorsement to this Coverage Part.
e.

other Insurance In COMMERCIAL GENERAL

LIABIUT't' CONDITIONS (Section IV):

The limits or insurance afforded to the additional insured shall be the limits which you
agreed in that "conttact or agreement requiring insurance to provide for that additional
insured, or !he limits shown in the Dedarations for this Coverage Part, whichever are
!ess. This endorsement does not increase the
limits of insurance stated in the UMITS OF

CG 03 8109 07

!';

We waive any rights of recovery we may have


against any person or organization because of
payments we make for bodily IJiury', "property
damage or personal Injury" arising out of your
work" performed by you. or on your behalf, under
a "contract or agreement requitlf'IQ Insurance With
that person or organilation. We waive these
right~ only where you have agreed to do so as
part of the "contract or agreement requiring insurance with sucn person or organization entered
inlo by you before, and in effect when, the 'bodily

2007 The Tr.;velers Companies. lrre.

Includes :11e Cllpyrighled llta!Pnal of Insurance Services O!'fice, Inc.. with 1IS p&<miSSIOtl

Page 1 of2

,.

CCMM~RCIAL GEt..:I::F-iJ\1.

LIABILITr

ifl!ury" cr Pft)perty damage OCOJI'$, or the personal injury' offensE. is cornmtltod.


0. The loAowing dP.ftniliOI1 i~ added

ot r~ge Part, P!VIIldea that tho "bodily il\iurl' tid


"t:ruporty damA{re.. c-::ctJrs, and lho 'pct$0:1al i<~
JUIJ'" is Cllused t:y on offense CO!l'lrnilled:
a. After you have entered Int.., !hat C{Jntrac! or
&gruement;

to OEFJNrTIONS

(Sec:tlon V):
'Contme; or agreement requir1ng insuranc~
means lhat part or any contract or "9ro&ment un-der whid1 you are required to lni..iude ll ):>(mlOn or
argan!zalton as an aedlt.onol lnl'>\.ln:"d O'l this Cnv-

::;.:.::.:::Jt
:t\e .!:lt~::..

f;n.~

b. WhilE! thai part of th~ C'.onlrilct or agreement r..


in ~tract; and

c.

P,rJoro the end Crr the polict pt.riorl

CG 03 61 09 07

~f~t )p,!.!t~, irlo)mp~"lct,,ltr.

u ..J.:Y"~ d.1 rn.111 r,~l o' If'' ..tntr.r.''

St'.J"~"r.,.t

.- 0/ft::e, 1-r. , w~ as

pffr.n.::-~ ;.:,,,

TRAVELERS]

One Tower Square, Hartford, Connecticut 06183


RENEWAL CERTIFICATE
POLICY NO.: 680-9637M280-TIL-13
ISSUE DATE: 07-16-13

COMMON POLICY DECLARATIONS

OFFICE PAC

BUSINESS: ENGINEERS
INSURING COMPANY:
TRAVELERS PROPERTY CASUALTY COMPANY OF AMERICA
1.

NAMED INSURED AND MAILING ADDRESS:


SKYLINE ENGINEERING, INC

8100 WILD HORSE ROAD


SALINAS

2. POLICY PERIOD: From


3.

LOCATIONS:
PREM.
BLDG.

NO.
01

NO.
01

CA 93907
09-11-13 to 09-11-14

OCCUPANCY

12:01 AM. Standard Time at your mailing address.

ADDRESS (same as Mailing Address


unless specified otherwise)

8100 WILD HORSE ROAD

ENGINEERS

SALINAS

4.

CA

93907

COVERAGE PARTS AND SUPPLEMENTS FORMING PART OF THIS POLICY AND INSURING
COMPANIES:
COVERAGE PARTS AND SUPPLEMENTS
Businessowners Coverage Part

INSURING COMPANY

TIL

s.

The COMPLETE POLICY consists of this declarations and all other declarations, and the forms and endorsements for which symbol numbers are attached on a separate listing.

6.

SUPPLEMENTAL POLICIES: Each of the following is a separate policy containing its complete provisions.
POLICY

POLICY NUMBER

INSURING COMPANY

DIRECT BILL

7.

PREMIUM SUMMARY:
Provisional Premium
Due at Inception
Due at Each
NAME AND ADDRESS OF AGENT OR BROKER

HALL\MICHAEL J\& COMPANY


19660 lOTH AVE NE
POULSBO

COUNTERSIGNED BY:

CFC98
Authorized Representative
W:r.

Q~i7n

r'\1\.TI.

POLICYHOLDER COPY

NG

. . . =.--:..

STA"T:t=

.:
"'

P.O. BOX 8192, PLEASANTON. CA 94588

CV M~t;J'ol.=, ?r-."r.t<l~
I N ":j lJ ;: ~ 'N ..
G

.F .U
NO""'~

ISSUE DATE :

CERTIFICATE OF WORKERS' COMPENSATION INSURANCE


GROUP:
1595532-2014
POLICY NUMBER:
CERTIFICATE ID:
139
CERTIFICATE EXPIRES: 09-01-2015
09-01-2014/09-01-2015

09-09-2014

CITY OF CARMEL BY THE SEA


PO BOX CC
CARMEL BY THE SEA CA 93921-1757

NG

This is to certify that we have issued a valid Workers' Compensation insurance policy in a form approved by the
California Insurance Commissioner to the employer named below for the policy period indicated.
This policy is not subject to cancellation by the Fund except upon 30 days advance written notice to the employer.
We will also give you 30 days advance notice should this policy be cancelled prior to its normal expiration.
This certificate of insurance is not an insurance policy and does not amend, extend or alter the coverage afforded
by the policy listed herein. Notwil hstanding any requirement, term or condition of any contract or other document
with respect to which this certificate of insurance may be issued or to which it may pertain, the insurance
afforded by the policy described herein is subject to all the terms, exclusions, and conditions, of such policy.

~tl./

!L_ .J/~~

Authorized Representative

President and CEO

EMPLOYER'S LIABILITY LIMIT INCLUDING DEFENSE COSTS:

PER OCCURRENCE.

$1,000,000

ENDORSEMENT

#1600-

BRYAN SCHALESKY PRES,TRES,SEC- EXCLUDED.

ENDORSEMENT

#1800 -

JUSTIN SCHALESKY VP - EXCLUDED.

ENDORSEMENT #2065 ENTITLED CERTIFICATE HOLDERS' NOTICE EFFECTIVE


ATTACHED TO AND FORMS A PART OF THIS POLICY.

09-01-2004

IS

EMPLOYER

SKYLINE ENGINEERING, INC


8100 WILD HORSE RD
SALINAS CA 93907

NG

[P13.NG]
(REV. 7-2014}

PRINTED

09-09-2014

o;

;..
5~Yl1Nt

uoa

t8J.
(

' ,.r

IWl~; f'Lf:ll~ E NOTIFY !'TI.T F.t.RJ! .&1 Tlit


.Of\DRlS~ llf.TEO Al 'THf "IClF" .
C.(l'!'~f.P
OF 111~ F"AGf: RlUAI=:!)fNG / ,flY Cli'-llC' E. (Jf.
ADORFSS II~Funii.OllON.

fNGIUEfFlHr

~JIJ
S'LlNA~ LA

hnr.sl rr,
95~b7

un

9~lj

' !.DDil ,ONAl INSURED'S NOliCE Of" COVERAGE


Slot .. Fom M&~tud AulonJobll~ lnsurrnce
tlAf."f 0 IIISIJR0:
,_ ~/>~a :; .. y, ;>< :r..: i ~l'l ~ L'
F~ ~~. , .. J CJ H::P.r,r ;,~:
< .. :'.'~. r,. ~o:;<>' !<''-'

f\:Jd:;V t.f5,J!.GE!' :

C:t-mp;lny
POLICY NO:
YR:V.AKtlMODf!. :

\tN.;CAIIPE.R:

! 1 ,, r., o~: .J~


rr.t:r '01,; ;.-. t ;;.
'1 1H;.Jr. s;.n~ !!v...~~

AQlNTNAMl:
AGENTPHOHf:

(4UBF'> 'olP.<

I:.NOOR&EMENT NO;

~ENF"-!.~
~02111.\U

CD\'EflA(.,f:;
; ''.!

. : .

'
,,,

'

\ _..
~ I

POLW' ;.!'fH "VE


APR u:. 2 . 1~ U,., ll,. 1LF.~fr..;J, TLO

i1Ht p<:;~, at_,_,, abov a-4"'11'1>0"' FOIcy11~1715~ 0~1<


. ,. r o!.:y ~~,c;.~.~tr" It ~Lt) ;~CJL C::- L)t plL.",...ctn~, lh t.dd1ls~n' int"rM'I 1r.lforetllll ltl Of'' ~,oCl o.: to In' r r;t!.r.1 o the ,,,laa,,o ..
.....!"' .. .l.'':O r...t. r"1' ,.. uolt""J prr.\'t """ ~~tiP IOdC:M1Qf'Je.1 tntuAKS Yt.h t"e -g ""'; 2{; 06l.) . noi!.;- t# h.t J'O' c.; 11 ,._1,'11J"Dtt.l Unb ll'Ch n.:.J'll
; ~:._~ co.K'I ' t 1p lro .. !"I Ci t ,.,..w.:oj t,,,.. u,!. r..0!4~'1 renfiw.lll pre,...L!mt tl~1r l"H: JUl:'! 'Tr ~ lldcL":tu\al t'1t..J :; M"'~ r.)tt) ~ '!" ,.. . ~_.,,n 10 dra~& o1
J... :~~ -.,, ,,,. e :~. '!'.t e e~:"'~:-s, . p coro-.nt:; I~ tr~~.:tte~h.n fa h.u 1r. uc. u ....."'' ,.,~r'! 1':;111 '!'\ ':) ~~~ r....... .c..::

::

ACORD

CERTIFICATE OF LIABILITY INSURANCE

DATE (MMIDDIYYYY)

1/10/2014

THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER .
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to
the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the
certificate holder in lieu of such endorsement(s) .

~~1~cT Judith Robinsky

PRODUCER
Pinnacle Risk

82

I rffc. Nol: (973) 284-1655

~~~&fl (973)284-0100

Solutions

~;.,~~

Old Bloomfield Ave

.....
INSURER(S) AfJ'ORDIHG COVERAGE

NJ

Pine Brook

07058

INSURED

INSURER B :
Inc

Skyline Engineering,

8100

NAICII

INSURER A :L l oyds

INSURER C :

Wild Horse Road

INSURER D :
INSURER E :

93907

CA

Salinas

INSURER F:

CERTIFICATE NUMBERl4-15 E

COVERAGES

& 0

REVISION NUMBER

THIS IS TO CERTlFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. N01WITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO VIHICH THIS
CERTlFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.

[1~-f:

TYPE OF INSURANCE

ION.<A

lwvn

POLICY NUMBER

ic:'r.Jo~~~ II~OLICY EXP

GENERAL LIABILITY

r-f--

PMERCIAL GENERAL LIABILITY


CLAIM5-t.IADE

r--

OCCUR

GEN'L AGGRnE LIMIT APn PER

~~&

POliCY
AUTOMOBILE LIABILITY

r-r-'r-

ANY AUTO
ALL OWNED
AUTOS
HIREOAUTOS

MED EXP (Any one person)

PERSONAL & ADV INJURY

GENERAL AGGREGATE

PRODUCTS- COM PlOP AGG

I (Eo occldont~ 1 N<>Lt LIMI


BODILY INJURY (Per person)

UMBRELLA LIAB
EXCESS LIAB

SCHEDULED
AUTOS
NON-OWNED
AUTOS

$
$

BOOILY INJURY (rer acx:ident) f

tP~~~;c~~tPAMAGE

HOCCUR
CLAIM5-M.ODE

I I

EACH OCCURRENCE

AGGREGATE

$
$

IT~~TfJIs I

jOJ:

E.L. EACH ACCIDENT

E.L DISEASE- PO'-lCY LIMIT

& Omissions

E.L DISEASE- EA EMPlOYEE $

~~~tt'tirb~ ~?~ERATIOI<S belo .


Errors

:;~~~l~E~~.7r~encel

LOC

RETENTION$
OED
WORKERS COMPENSATION
AND EMPLOYERS' LIABILITY
YiN
A~ PROPRIETORJPARTNERJEXECUTIVE
N/A
OFFICER/MEMBER EXCLUDED?
(Mandatory In NH)

LIMITS
EACH OCCURRENCE

~1087.264 . 14

/8/.2014.

/8/2015

$1,000,000
$2,000,000

Umn or Llabtttr Per Claim


Lim~

ol Llabilil)' Aggeregate

DESCRIPTION OF OPERATIONS I LOCATIONS I VEHICLES (Attach ACORD 101, Addnlonal Remarks Schedule, If mo,.. spate Is requlrtd)

CANCELLATION

CERTIFICATE HOLDER

***

Evidence Of

Insurance

SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE


THE EXPIRATION DATE THEREOF, NOTlCE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS .

'***

AUTHORIZED REPRESENTATIVE

~ Caradimitropoulo/SR

ACORD 25 (2010/05)
INS025 (201005)0 1

The ACORD name

and logo

c:

--=::::-

1988-2010 ACORD CORPORATION. All rights reserved.


are registered marks of ACORD

CITY OF CARMEL-BY-THE-SEA
Administration Department
"IN and ABOUT" Business License Application

Phone: 831-620-2000
Fax: 831-620-2004

Post Office Box CC


Carmel, CA 93921
Business Name: Skyline Engineering, Inc.
Name of Principal(s)/Owner(s): Bryan, Justin and Nathan Schalesky
Ownership Type : 0 Sole

X Corporation

Partnership

Limited Liability Corporation

Required: FederaiiD#: 77-0528032 or Social Security#: _ _ _ _ _ _ _ __


Mailing Address: 8100 Wild Horse Road
Zip: 93907
City: Salinas
State: CA
Telephone: (Business) 831-663-6188 (Home)
(Fax) 831-663-1185
(Cell) 831-235-5797 (E-Mail) bryan@skylineengineering.com
For Contractors Only: State of California License#: _ _ _ _ _ _ _ _ Type: _ _ _ __
Proposed Use/Business Activities: Include a detailed description of the specific products or services
you intend to offer: Engineering consulting services for roofing and waterproofing

FEES: ADMINISTRATION $51.65 ADA STATE TAX $1.00 .................. TOTAL FEE $52.65
I, THE UNDERSIGNED, UNDER PENALTY OF PERJURY, STATE THAT I AM THE APPLICANT FOR THIS
BUSINESS LICENSE. THAT THE INFORMATION FURNISHED BY ME ON THIS APPLICATION IS TRUE
AND CORRECT. I UNDERSTAND THAT THE ADMINISTRATIVE FEE IS NON-REFUNDABLE AND THAT I
AM RESPONSIBLE TO PAY ANY BUSINESS LICENSE TAXES ON ALL REVENUES COLLECTED WITHIN
THE CITY LIMITS . I WILL ALSO NOTIFY THE CITY OF ANY CHANGES IN OWNERSHIP OR ADDRESS.

~~~

9-9-14
Date

Signature of Applicant
[ " - - - - - ------------------------ FOR--OFFICE US-E

ONLY-------------------------------------~

I
i

Ii Date Received:

Receipt #

i Business License#:

ID#

By

-----------

Issue date_ _ _ _ _ _ _ __

I
!

! Renewal Date:

SIC:

CLASS _Mailed

PLEASE COMPLETE OTHER SIDE

by_____

PROOF OF EMPLOYERS' WORKERS' COMPENSATION INSURANCE

State law requires that every employer who applies for a business license shall provide valid Workers'
Compensation Insurance or proof of compliance with the State Labor Code. Accordingly, please
respond to one of the following questions:

I have and will provide a Certificate of Self-Insurance issued by the State Director of Industrial
Relations.

I have and will provide a Certificate of Workers' Compensation Insurance.

I certify that, in the performance of work for which this license is issued, I shall not employ any
person in any manner that is or will become subject to the Workers' Compensation laws of the
State of California.

Bryan Schalesky
Printed Name

~~

Signature of Applicant

President
Title (Owner/Manager/Partner, etc.)

9-9-14
Date

Andrew Vanderford
From:

Bryan Schalesky [Bryan@skylineengineering.com]


Thursday, September 18, 2014 8:29AM
Andrew Vanderford
Re : Business License
IN & ABOUT LICENSE APPLICATION FORM.pdf

Sent:
To:
Subject:
Attachments:

Attached is the application . I sent in the check along with this on the 9th . They should have gotten the check by
the11th .
Bryan Schalesky, PE
President
Skyline Engineering, Inc.
831.663.6188 office
831.235.5797 mobile

(
\
I

\'

'

r. . .
'

From: Andy Vanderford <AVanderford@ci.carmel.ca.us>


Date: Thursday, September 18, 2014 at 8:14AM
To: Bryan Schalesky <bryan@skylineengineering.com>
Subject: RE: Business License
E-mail me the application you sent in . I'll use that for the agreement.

From: Bryan Schalesky [mailto:Brvan@skvlineenqineering.com]


Sent: Wednesday, September 17, 2014 6:58 PM
To: Andrew Vanderford
Subject: Re: Business License
I mailed that in with check. They should have it.
Bryan Schalesky, PE
Skyline Engineering, Inc.
831-663-6188

From: Andy Vanderford <AVanderford@ci.carmel.ca.us>


Date: Tuesday, September 16, 2014 at 5:49 PM
To: Bryan Schalesky <bryan@skylineengineering.com>
Subject: Business License
Alii need is the business license and were done.

a~~- 1/cv;1-d~oui
Andy Vanderford
Project Manager

8100 Wild Horse Road


Salinas CA 93907

ENGINEER
r . - ;:.r',,

~-!

"':

.,..:

i ,;

NG

f,. :-.~ i ',.!;,r-:

jExhibit "E"

p 831.663.6188
F 831.663.6187

December 3, 2014
ROOF ANALYSIS
City of Carmel by the Sea

Administration Buildings
Junipero Street in Carmel

Email: bryan@skylineengineering.com- www.skylineengineering.com

Skyline Engineering

PURPOSE OF THE ROOF SURVEY AND REPORT

Information in this report is based upon the visual inspection as performed by


Bryan Schalesky, PE on October 30, 2014. Bryan was accompanied by Cleve
and Andy during part of the inspection. Previously we toured the facility looking at
various areas of leakage.
The purpose of this report is to document the source of existing leaks over patio
areas. We will also analyze the condition of the built up roofing systems.
Finally, we will make recommendations for various options for the patio decks
and roofs. We will outline comparative budgets for each option.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

POLICE STATION

PLANTER
PLANTER

PATIO OVER GARAGE

HI RANGER
COVER
0::

w
z

1-

5
a.
z

~
~

FLAGPOLE

en
w
u:::
u_
L)

PLANTER

PATIO OVER GARAGE

LOADER
SHELTER

PAINT RpOM
& STORJ GE

IP~NTEj

CITY CARMELADMIN BUILDING

NOT DRAWN TO SCALE

DRAWN BY: B. SCHALESKY

SKYLINE ENGINEERING, INC


81 00 Wild Horse Road
Salinas CA 93907

Skyline Engineering

PATIO DECK AND PLANTER CONSTRUCTION AND CONDITION

Patio decks are poured concrete slabs varying in thickness as depicted in this
drawing from the 1960's. There is a structural slab underneath. A "membrane" is
installed between the slabs.

The underlying membrane is not visible. We did not take destructive tests to view
it. However, this is extremely typical construction AND condition for a deck this
old. The membrane is most assuredly failing.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

PLANTER CONSTRUCTION AND CONDITION


Similarly, planters are lined with "membrane." These membranes are likely also
failing. If the planters were to be irrigated or become saturated from rain, leaks
would occur here as well.
1.> :.. . , 'r.e.t""':"e. =' r.r
$if.t::. ;~1-r.i~L.t l'<l

tz
._..,..

T~~'f

1-'t.~~~..... "'" ' .


!

l .

'

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

The area around the flag pole used to be a pool. Now it is filled with bark. It also
has a waterproofing "membrane."
I

1:.

'if;,

.,_,

. ~
..

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - t-ax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

STEPS

Steps are located throughout the patio decks. This drawing shows likely
construction under steps. Notice the horizontal concrete area that has
waterproofing membrane.

'

i
i,

\Fil-L-

____ l;z.ur.~PU"-L.i

--......,

IMP~E~J.Tfi.D

f!P.>E.~ fi!>O,I>.jLO

-..,.:..'f''Ot.:lflP,ATION WAf&~PJLOOf-fl'l&.

./

-~.:;..WAl-t....

- F.l }J; 651-Ar::>E.. of- (5-I..Ac-t!- T

?1 ,A.f~

AT

R;:. t)tL DIIJ G

WALL-

iC(~1~6
-;rT+---;-

'i

L - . L ...

(}I~

~-----......_-+-/I =~t~

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

8100 Wild Horse Road


Salinas CA 93907
p 831.663.6188

NGINffRING

F 831.663.6187

December 2, 2014

PHOTO ANALYSIS
City of Carmel by the Sea
Administration Building Patio Decks
Junipero Street in Carmel

Email: bryan@skylineengineering.com- www.skylineengineering.com

Skyline Engineering

The area around the flag pole used to be a pool. Now covered with bark.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: t131i663-6187
Email: bryan@skylineengineering.com - www.skylineengineering .com

Skyline Engineering

Stairwell areas. Note sealant at perimeter failed.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Sealant throughout the perimeter of the patio decks were a previous attempt to
stop leakage. This may have slowed leakage, but would not eliminate it.

Bad benches should be removed permanently or replaced.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Perimeter walls are constructed of framing and exterior plaster system. here the
coating is sagging indicating water entry behind the wall.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Base of the wall chipped away revealing the lath.

Wall cracking. Perimeter walls will need to be repaired and coated as part of any
system that is installed on these decks. These walls are an integral part of the
waterproofing for this building.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - ax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Interior drain. All interior joints and cracks were previously repaired as an attempt
to stop or slow leakage.

Cellular equipment "hut." As part of any major repair on these patio decks, this
structure will have to be removed and replaced.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Exhaust fan. Not sure if this is operational. If not, it should be removed.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

The following are photos of leaks under the patio decks.


This is a very serious leak that is actually located under the large planter in front
of the Police Admin building. It is likely that the water is entering at the patio deck
and traveling in the interstitial space to this wall. It is less likely (but certainly
possible) that the actual planter is leaking.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Leaking is so severe that structures have been built to divert water away from
interior spaces.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering .com - www.skylineengineering.com

Skyline Engineering

Water entering the system will find cold joints, cracks and openings in the
concrete to actually enter the interior space. This makes it nearly impossible to
track leaks because they travel.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering .com

Skyline Engineering

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email : bryan@skylineengineering.com - www.skylineengineering.com

,
K
N G

'

8100 Wild Horse Road


Salinas CA 93907
p 831.663.6188
F 831 .663.61 87

NffRING

December 2, 2014
PHOTO ANALYSIS
City of Carmel by the Sea

Administration Building Planters


Junipero Street in Carmel

Email: bryan@skylineengineering.com- www.skylineengineering.com

Skyline Engineering

This is the planter located adjacent to the Police Admin Building. Planters do
have living plants or trees present.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering .com - www.skylineengineering.com

Skyline Engineering

This is the southernmost planter. The bench surrounding this planter is in poor
condition and should be replaced or eliminated.

This planter is located between the patio decks and the Hi Ranger cover roof.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

fNG
'. ~ -

8100 Wild Horse Road


Salinas CA 93907

p 831.663.6188
F 831.663.6187

NEfRING
::

. 'f

..

I ....

December 3, 2014
PATIO DECK & PLANTER
RECOMMENDATIONS AND BUDGETS
City of Carmel by the Sea

Administration Buildings
Junipero Street in Carmel

Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

SQUARE FOOTAGES

Dual slab patio decks: 9,200


Stairs: 600
Planters: 2,300 (footprint - not including sides) This does not include the
large planter area just southwest of the Police Station.
Perimeter walls: approx. 3,000
RECOMMENDATIONS AND BUDGETS FOR PERIMETER WALLS

Repair exterior plaster. Fabricate and install sheet metal coping cap. Install
elastomeric coating over wall. Estimated budget $30,000.
RECOMMENDATIONS AND BUDGETS FOR PLANTERS

Option #1: Remove vegetation and cover planters with framing, plywood, and
roof covering. Estimated cost $50,000.
Option #2: Excavate planters. Install waterproofing membrane to line
planters. Replace soil and vegetation. Estimated cost $150,000.

This is a photo of a planter that was excavated (PG&E 111 Almaden in San
Jose). PVC membrane lines the planter creating a waterproof barrier.

1-l
I

-.
8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

This is a photo of the completed planter.

RECOMMENDATIONS AND BUDGETS FOR PATIO DECKS

Option #1: Remove topping slab. Install new thermoplastic membrane over
lower structural slab (slope to drain). Install new pavered system set on stands.
There are numerous manufactures and dozens of configurations for these types
of plaza decks. Below are some links to those we have specified in the past.
Approximate budget estimate for this option is $500,000.

20 or 30 year manufacturer warranties are available for the underlying membrane


system. Because the system is sheltered from UV radiation, its life expectancy
should exceed 30 years. Pavers do not have a life expectancy.
http://www. tiletechpavers.com
http://westile.com
http://usa.sarnafil.sika.com/en/solutions products/1 0/1 Osa01 /choosing-aroofing-system/lightguard-roof. html
http://www.carlislesyntec.com/view.aspx?page=view&mode=post&contentiD=

49
http://www. hanoverpavers. com/roof. asp

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Some images of roof paver systems courtesy Hanover.

---

--'~~-------- ...,.

-L..:-.

- -- -- - .... - -- -- - - --

8100 Wild Horse Road, ::ialinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering .com - www.skylineengineering .com

Skyline Engineering

Option #2: Retrofit % " plywood over existing deck. Install PVC membrane
specially designed for pedestrian traffic. Stairs will need to be specially sealed
and coated in order to integrate into the system. Approximate budget for this
option $200,000.
20 year manufacturer warranties are available for these systems. The system life
expectancy is 25- 30 years.
The following are links to PVC pedestrian traffic membrane systems.
http://ibroof.com/sites/default/files/IB%2060%20Mii%20DeckShield%20SinglePiy%20TDS%20201 11222.pdf
http://www.mulehide.com/home/modular-systems-dectec-walkable-membranepvc
http://www.duradek.com
Photo courtesy of Duradek.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-618!:! - Fax : 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering .com

Skyline Engineering

Photos from our project at SF Unified School District.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Option #3: Prep the existing deck. Seal all joints. Install liquid applied urethane
deck coating system. Approximate budget $150,000.

Ten year manufacturer warranties are available for these systems. The estimated
life expectancy is 15 to 20 years before re-coating becomes necessary.
Note: This option would need to be approved by the manufacturer providing the
system. Prior to final approval of this option we would need to invite two or three
manufacturer reps to the site in order to confirm and verify that their systems
could be properly installed and warranted.
Photos of UCSC Kerr Hall deck coating project from 2013. Sika deck coating
system.

I ~

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email : bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

~-- - .

....___

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

-..._I

8100 Wild Horse Road

fNGINffR

Salinas CA 93907
p 831 .663.6188
F 831.663.6187

NG

December 2, 2014
MEMBRANE ROOFING ANALYSIS
City of Carmel by the Sea
Administration Building Built-up Roofs
Junipero Street in Carmel
SUMMARY OF CONSTRUCTION- CONDITION- RECOMMENDATIONS- BUDGETS
Loader Shelter
Roof system: mineral surfaced built up roof over a wood deck
456 sf
Age: approx. 15 years
Drainage: gutter
Condition: Fair to poor
Recommendation: Replacement in 2016 (Thermoplastic membrane roofing)
Estimated replacement cost: $15,000
Hi Ranger Shelter
Roof system: mineral surfaced built up roof over a wood deck
1,088 sf
Age: approx. 15 years
Drainage: gutter
Condition: Fair to poor
Recommendation: Replacement in 2016 (Thermoplastic membrane roofing)
Estimated replacement cost: $30,000
Paint Room & Storage
Roof system: composition shingle roofing over a wood deck
544 sf
Age: approx. 15 years
Drainage: gutters
Condition: good
Recommendation: None
Offices & Admin
Roof system: gravel surfaced built up roofing over wood deck
856 sf
Age: 25 years
Drainage: scuppers
Condition: Fair to poor
Recommendation : Replacement 2016 (Thermoplastic membrane roofing)
Estimated replacement cost: $30,000

Email: bryan@skylineengineering.com- www.skylineengineering.com

Skyline Engineering

The loader shelter roof is a mineral surfaced built up roof over a wood deck. It is possible
that this awning was constructed about the same time as the Hi Ranger Closure at or
old .
around 2000 . This roof would then be about 15

Vegetation should not be allowed to cover the roof. This will damage the roof in the long
term.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Gutters for both roofs sit close to each other. Roof on right is the Paint Room & Storage.
lacement.
Both utters are in fair condition and would not require
P""""'

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering
Comp shingle roof is in good condition. These roofs have a much longer life expectancy
than fla! built up roofs.

Gravel surfaced BUR over the Offices win . Mineral surfaced

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
-~~------------------------------~----~------~--------------==~~
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email : bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering
Drainage scupper. Previous repairs indicate a history of leaks. Note the needles blocking
drain
on both inside and outside of the scupper.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Questionable flashing. This looks like Grace membrane. This is the incorrect material for
this

Admin roof.

8100 Wild Horse Road , Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

........

----

_..,
_,.,.,.,.
_..,

~/

,..........

.-"

--- ~ /~

/.

....,;

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Gutter drainage.

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

!EXHIBIT "F"

N G

N G

fNGINFERING SERVICES FOR lHf BUilDING fNVHOPf


Asbestos, Lead, and Mold Exterior Building Envelope Survey
Report

CITY OF CARMEL BY THE SEA


POLICE HEADQUARTERS AND PW/PS ADMIN COMPLEX

December 16, 2014

Prepared for:
Andy Vanderford
City of Carmel by the Sea
PO Box CC
Carmel by the Sea, CA 93921

Prepared by:
Nathan Schalesky
Skyline Engineering Inc.
81 00 Wild Horse Road
Salinas, CA 93907
(831) 663-6188
nate@skylineengineering.com

Skyline Engineering Inc., 2014

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 2

Table of Contents

Introduction .................................................................................... 3
Methodology ...................................................................................3
Site Details .....................................................................................4
Findings .........................................................................................4-7
Conclusions ....................................................................................8
Recommendations ........................................................................... 8
Limitations ......................................................................................8-9

Appendix A: Asbestos and Lead Sample Location Drawings


Appendix B: Asbestos and Lead Chain of Custody Forms and Laboratory
Reports
Appendix C: Asbestos and Lead License and Certification
Appendix D: Mold Survey Section

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 3

Introduction

Skyline Engineering Inc. was retained by the City of Carmel by the Sea to
conduct an asbestos, lead, and mold survey at the Police Headquarters and PW/
PS Administration building located at the corner of Junipero St. and 4th Avenue.
The asbestos and lead portion of the survey was limited to the materials on the
various roof levels and patio levels (the patio levels will be referred to below as
roof levels) found at the facility- please refer to the site map found in Appendix A
to locate the areas sampled. The mold portion of the survey was limited to the
interstitial space below the patio deck levels and above the garage area below.
This did not include the inside of the building. Please refer to Appendix D to
locate the mold sample locations and mold survey findings and conclusions.
This section only refers to the asbestos and lead portion of the survey.
Methodology

The performing of an asbestos survey prior to commencement of any demolition


and renovation is regulated by the local air quality district. In the Carmel by the
Sea area, an asbestos survey is required regardless of the building's
construction date. This asbestos survey was performed in accordance with the
Monterey Bay Unified APCD regulations.
In addition, OSHA regulates work practices and worker protection when
employees have a potential to be exposed to asbestos occupationally. The
asbestos survey was overseen by a Certified California Asbestos Consultant.
The lead survey was performed for workers protection purposes and was not
intended as a US Department of Housing and Urban Development (HUD) LeadBased Paint Inspection.
The lead survey was overseen by a California
Department of Public Health (CDPH) Certified Lead Inspector.
Bulk samples collected in this survey were submitted to Forensic Analytical
Laboratories Inc. and were analyzed using Polarized Light Microscopy (asbestos
samples) in accordance with EPA Method 600/R-93-116, and Atomic Absorption
Spectrometry (lead samples) using EPA Method 7420.

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 4

Forensic Analytical Laboratories, Inc. is accredited by the CDPH and the National
Institute of Science and Technology's (NIST) National Voluntary Laboratory
Accreditation program (NVLAP).
Forensic Analytical Laboratories, Inc.
participates in the National Institute for Occupational safety and health (NIOSH)
Proficiency analytical Testing Program, and has substantial experience in the
analysis of asbestos and lead.

Site Details

The asbestos and lead portion of the survey included the materials on the
various roof levels found at the facility to be inspected at the Police HQ & PW/PS
Admin Complex in Carmel by the Sea. The sampled roof levels may be found on
a site map included in this report for reference - Appendix A. The existing roof
levels - associated with the Police Headquarters building - are a BUR (built up
roof) with gravel system. The deck is plywood. This building also has a wood
shake mansard surrounding the main levels flat BUR area. The various patio
levels below are concrete panels with two large planters filled with dirt and
foliage. Three small levels of the patio area are BUR's with gravel. One small
area is asphalt shingles. And the two remaining roof levels are BUR with cap
sheet systems. The purpose of this portion of the survey was to find all asbestos
and/or lead containing building materials on these designated roof and levels.
The survey was limited to the roofing materials.

Findings

Asbestos
Samples were taken from the roofing materials of the Police HQ & PW/PS
Administration Complex. Suspect asbestos materials observed in the roofing
systems included the roofing felts, mastic repairs, coatings, and sealants. If
multiple layers of suspected material were present, the sample was taken all the
way down to the substrate.

On all of the designated roof levels, only three samples from the front Police
Headquarters building (referred to as the Large BUR) came back positive for
asbestos.

A summary of the samples that were taken are listed below:


Skyline Engineering - Engineering Services for the Building Envelope
www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Building Sample
Number

ACM
Location

ACM Materiai

Page 5

Color

Result

NESHAP
Category

----- ---- -

current II
ACM I
Condition!

Black

None
Detect

Felts and
Mastic

Black

None
Detect

Small
BUR Pen

Repair Mastic

Black

None
Detect

A4

Small
BUR2
Field

Felts and
Mastic

Black

None
Detect

CCPD

A5

Small
BUR2
Base Flas

Felts and
Mastic

Black

None
Detect

CCPD

A6

Small
BUR2
Scupper

Repair Mastic

Grey

None
Detect

CCPD

A7

Small
BUR3
Field

Felts and
Mastic

Black

None
Detect

CCPD

A8

Small
BUR3
Cap Undr

Felt

Black

None
Detect

CCPD

A9

Patio Con
Panel
Seam

Sealant

Light
Grey

None
Detect

CCPD

A10

Patio Con
Panel
Seam

Sealant

Light
Grey

None
Detect

CCPD

A11

Patio
Parapet
Wall

Coating

Cream

None
Detect

CCPD

A12

Patio
Parapet
Wall

Coating

Cream

None
Detect

CCPD

A13

Small
BUR4
Field

Felts and
Mastic

Black

None
Detect

CCPD

A14

Small
Shingle
Roof

Composition
Shingle

Black

None
Detect

CCPD

A1

Small
BUR Field

Felts and
Mastic

CCPD

A2

Small
BUR Base
Flash

CCPD

A3

CCPD

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering .com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Building

Sample
Number

ACM
location

ACM Material

Page 6

Color

Result

NESHAP
Category

Current
ACM:
Conditt

on

CCPD

A15

Small
BUR5
Field

Felts and
Mastic

Black

None
Detect

----

CCPD

A16

Small
BUR5
Base Flas

Felts and
Mastic

Grey

None
Detect

CCPD

A17

Small
BUR5
Pen

Repair Mastic

Grey/
Black

None
Detect

CCPD

A18

Large
BURAC
Seam

Mastic

Grey

None
Detect

CCPD

A19

Large
BUR Field

Felts and
Mastic

Black

None
Detect

CCPD

A20

Large
BUR Base
Flash Cap

Felts and
Mastic

Grey

None
Detect

CCPD

A21

Large
BUR BF
Seam

Repair Mastic

Grey

10%

Category II

Fair

CCPD

A22

Large
BUR Pen

Mastic

Black

10%

Category II

Fair

CCPD

A23

Large
BUR Field

Felts and
Mastic

Black

None
Detect

CCPD

A24

Large
Bldg Eye
BUR Field

Felts and
Mastic

Black

None
Detect

CCPD

A25

Large
Bldg Eye
BUR Pen

Repair Mastic

Black

10%

Category II

Fair

----

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 7

Lead

Samples were taken from the roofing materials of the Police HQ & PW/PS
Administration Complex. Suspect lead materials observed in the roofing systems
included coatings on the patio parapet walls and sitting benches, and coatings on
the HVAC equipment and parapet cap of the large BUR roof level.

On the designated roofs, Lead containing materials (LCM) was found to be


present in four out of five of the samples taken.

A summary of the samples that were taken are listed below:

Building

Sample
Number

LCM
location

Substrate

CCPD

PB1

BURS
Flashing

Metal

CCPD

PB2

Patio
Parapet
Wall

CCPD

PB3

CCPD
CCPD

Color

Resutts
wt%

LCM
Condition

Yellow

.01S

Intact

Stucco

Cream

None
Detect

Patio Bench

Wood

Brown

.028

Intact

PB4

Large BUR
HVAC Duct

Metal

Tan

.072

Intact

PBS

Large BUR
Edge Cap
Flash

Metal

Tan

.034

Intact

**LCM - Lead containing material - material or surface coatings containing


detectable levels of lead as regulated under the Cai/OSHA Lead in Construction
Standard, 8 CCR 1532.1.

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering .com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 8

Conclusions

Skyline Engineering performed an asbestos and


PW/PS Admin Complex in Carmel by the Sea.
materials on various roof levels of the complex.
were found to be present in the samples taken.
identified to be present in the samples taken.

lead survey at the Police HQ &


The survey was limited to the
Asbestos containing materials
Lead containing materials were

Recommendations

Skyline Engineering conducted limited bulk sampling of various roofing materials


suspected to be Asbestos Containing Material. If additional materials are to be
disturbed or if suspect asbestos containing materials that were not tested will be
disturbed, the Contractor will need to treat those materials as asbestos
containing unless testing proves otherwise.
Skyline Engineering recommends that an appropriately qualified contractor
complete the handling or the removal of ACM and LCM. Any work disturbing
lead containing material should comply with the Cai/OSHA 8CCR 1532.1 Lead in
Construction Standard. Any work disturbing asbestos containing material should
comply with the Cai/OSHA 8CCR 1529.

Limitations

This investigation is limited to the conditions and practices observed and


information made available to Skyline Engineering Inc.
The methods,
conclusions, and recommendations provided are based on Skyline's judgment,
experience and the standard of practice for professional service. They are
subject to the limitations and variability inherent in the methodology employed.
As with all environmental investigations, this investigation is limited to the defined
scope and does not purport to set forth all hazards, nor indicate that other
hazards do not exist.

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 9

Thank you for the opportunity to work with you. Please do not hesitate to give us
a call with any questions or concerns.

Sincerely,
Skyline Engineering Inc.

Nathan Schalesky

Paulo Parra

Director of Environmental Services

CAC, CDPH 1/A

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

Appendix A

Sample Location Drawings

SURVEY FLOOR PLAN FORM


Project

City of Carmel CCPD ACM LCM Survey

Building

Police HQ & PW/PS Admin Complex

Inspectors

Nathan Schalesky and Gene Spector

Date of Survey

10.30.14

SKYliNE
ENGINEERING
EriGINEERIIIG SERVICES FOR THE BLIILDir;G E~VE~OPE

Appendix B

Chain of Custody Forms


And
laboratory Reports

Analysis Request Form (COd

Forensic Analytical Laboratories, Inc.


PO/Job#: CCPD

dient Name & Address:

Skyline Engineering

Date:

Tum Around Time: Same Day I 1Day I 2Day I .may I 4Day I

#Cl3550

0 PCM: 0 NIOSH 7400A

!ll Pl.M: ill Standatd I a


Contact:
Phone;

E-mall:
Site:

0
0
0
0

Nathan Schalesky

fax:

831-521-0076

10.30.14

I 0 NIOSH 74008

I 0 CARE 435

TEM Air; 0 AHERA / D Yarnarel I 0 NIO:SH 7402


TEM Bulk: 0 Quantitalive I 0 QL1i!litative I 0 Olal1ield
-n/1.1 W~r: 0 Potable I 0 Non-Potable I 0 Weight%
TEM Miaovac: 0 Qu~tll+/l I 0 057S5WareJ) I 0 DS7S~s.1)
D PLM Opaques&lot
D Sptdal Projed

Pan!de Jdentlfication (TEM LAB)


D Metals Anal)'Sis: Method:

City of Carmel Police Department

0 Rolomete<

Point Count 400 1000

0 IAQ Particle Identification CPLM lAB)

nate@skylineengineering.com

5~

Matrix:

Site location:

Analytes:

Comments:

Report Vla;
OFax

CAC onsite Gene Spector

FOR AJR SAMPlES ONLY

Date/

Sample 10

Sample Location I Description

Time

Type
A

CCPD-Al

SMALL B'DR Fil!IJ>

CCPD-A2

SHALL BUR BASE !"LASH BLACX

AVK-

Total

lPM

Time

c
A
SMAI..L BUR PEliETl\ATIOll MAS'l'rC BLJ(

CCPD-A4

SMALL B'DR 2 FIELD

c
A

CCPD-AS

SMALL 'BUli. 2 BABE FLASH BLX

SMALL BUR 2 GREY SCUPPER MASTIC

SMALL BUll 3 FIELD

CCPD-A6

CCPD-A7

S!IAl.L BUR 3 CAP UJil)ElllJI.Y BLr;

CCPD-A8

c
PATIO SEAM SAI.Aitt L'r GJIEY

CCPD-A9

c
PATIO SEAM SEALANT LIGHT GREY

CCPD-AlO

Nathan Schalesky
o Fed ~~UPS

Shipped Via:

Time
OrVOff

OVetbal
Sample
Area/
Air
Volume

c
A

CCPD-A3

Sampled By:

R E..t-.tail

Dare:
D

US Mail

o Courier

c
Time;

10.30.14
D Drop Off

Other.

Relinquished

By-~
~..L-L

R.ell nquished By:

Relinquished By;

Date/Time;

10.30.1

Date/Time:

Date/Time:

Reai~By;

Rl!cei ved By;

Date/Time:

Dau-/Time:

:00 pm

"

Recei~~v
Da.te/l}r(je:- 31-1

4 PO 1 : 3 7

Condition Acceptable?

Yes

RCVD

oNcM~

Condition At;ceptable?

o Yes

ONo

Condition Ac~table! 0 Yes

ONe

San Fr.ancisca Office: ;rrn Oepac R.aad. Suite 409, Ha)'Wanl, California 94545-2761/ l'tl: (51 0)887-8828 (800)627.3274/ Fax: (51 0)887-4218
Los Angeles Offi C@: 2959 Padfi c Commuce Drive, Rancho Dominguez, California 90221 I Ph: (31 0)763-1374 (888)813-9417 I Fax: (31 0)763-4450
las Vegas Office: 6765 5. Eastern Avenue, Suite 3, lAs Vegas, Nevada 89119/ Ph: (702)784-0040 I fax: 1702)784-0030

Forensic Analytical Laboratories, Inc.

Analysis Request Form (COC)


PO/}ob#; CCPD

dlent Name & Address:

Skyline Engineering
#Cl3550

Tum Around lime: Same Day I 1Da)' I 2Day I 3Day I 4Day I SDif
Cl PCM! t:l

~IOSH

7-400A I 0 NIOSH 74001l

PlM: 1!. Standard /


Contaa:
Phone:

E-mail:
Site:

D Rotameter

t:l Poir'll Count 400 1 000 / 0 CARB 435

D TEM Air. t:l AHERA I 0 Yamare2 I 0 NIOSH 7<402


t:J TEM Bulk: 0 QuanliiMlve I 0 Qualit&tive / t:J Olatfield
t:l TEM Water: 0 Potable I a Non-Pot!.ble I 0 Weight%
t:l TEM Mlcrovac: 0 Qual(+/.) I 0 D57S5(str/areal I a DS756(str/m;us)

Nathan Schalesky
831-521-0076

1 0 . 3 0 . 14

Date:

Fax:

nate@skylineengineering.com

t:J IAQ Particle lderditic.ation (PlM lAB)

t:J Pl.A-1 Opaques/Soot

D Particle ldentifiation (TEM L.All)

t:l Special Pro)ea

Cl Metals Analysis: Method:

City of Carmel Police Department

Matrlx:

Site Location:

Comments:

Anal}1es!

ReportVta:
t:IFax

CAC onsite Gene Spector

FOR AIRSMtPlES ONLY

Date/

Sample ID

Sample Location I Description

Time

T}-pe
A

CCPD-All

SMALL SHINGLE ROOF SHINGLE

c
A

SMALL Btll\ 5 PIEIJ)

c
l'LAS~G

GRtt

CCPD-A17

SMALL "BUR 5 PEllE MASTl:C GRY/BLIC

CCPD-AlB

LARGE BUR BVAC SEAM MASTIC GREY

c
A

c
A

c
A

LARGE BUR FIELD

CCPD-A19

c
LARGE BUR BASE FLASH CAPSHEET

CCPD-A20

c
Date:

Nathan Schalesky

Shipped Via: Cl Fed Ex~2-n.! UPS

o.n"""'"""'~.A'

Condit

CCPD-A16

0.14 3: 00 pm

1 0- 3 1 - 1 4 P0 1 : 3 7 RC 1

Oaie/.~D{l

SMALL BUR S BASE

Received By:

Air

Volume

6liALL BUR 4 Fl:ELD

CCPD-A15

Total

Time

c
A

CCPD-A14

00!12/lime:

Avg.
LPM

Sample
Area/

PARAPET COATING CJUtAJol

CCPD-A13

11me

OrVOff

o Verbal

PARAPET COATDTG CIIZM!

CCPD-Al2

Sampled By:

ME-Mall

r:fYes

~
t:JNo

Cl

us Mail

Cl Courier

10.30.14

Time:

0 Drop Off

0 Other:

Relinquished By;

Relinquished By:

Da~/Time:

Date/Time:

~eceivedBy:

Recei...ed 8)-:

Date/Time:

Date/Time:

Condition Acceptable/ t:J Yes

t:INo

Condition Acceptable1 t:J Yes

t:JNc

San Fra

Los Angeles

Offi~: 3777 Depot Road, Suit 409, Hayward, California 94545-2761/ Ph: (51 0)887.alll8 (800)827-3274/ Fax; (Sl 0)887-4218
ce: 2959 Pacific Commerce Drive, Rancho Dominguez, Callfumia. 90221 I Ph: C310l76J-2374 4 (888}813-9417/ Fax: (31 0)763-4450
Las Vegas Office: 6765 S. Eastern Avenll@, Suite .3, Las Vegas, Nevada 89119 I Ph: 1702)784-0040 I Fax; 1702)784-0030

Analysis Request Form (COC)

Forensic Analytical Laboratories, Inc.


PO I .Job#: CCPD

dient Name & Address:

Skyline Engineering

Tum Around Time: Same Day

#C13550

0 PCM: 0 NJOSH 7400A


~PU.t: I:!ISt.aodard

Contact:
Phone:

I faJC

831-521-0076

E-mail:
Site:

0
0
0
0

Nathan Schalesky

I lDay I 2Day I 3Day I 4Da}' I

S~

ClR~

0 NIOSH 74008

I OPointCount400-1000 I OCARB435

TD\1 Air: D AHEM I 0 Yamate2 I 0 NIOSH 7402


TFJ,.I Bulk: 0 Quantitative I 0 Quali~ative I 0 Oialfield
TEM Water. 0 Potable / 0 Non-l'ot.abl~ I 0 Welght "
Th\1 Miaovac: 0 QuaU+/-1 I o DS7SS(str/area) I Ll DS7S6(stl)'rnass)

Cl IAQ P.amde !&!ntlticatlon I?L\.i lAB)


0 Particle Identification fiD.1lA8)

nate@skylineengineering.com

1 0 . 3 0 . 14

Dare:

0 PU.I Opaques/Soot

D Special ProJect

0 Metals: Analysls: Ml!thod:

City of Carmel Police Department

Matrlx:
Site Location:
Comments:

Analytes:

Report Via:
DFax

CAC onsite Gene Spector

Sample ID

~E-Mail

FOR AIR SAMPlES ONlY

Date/
Time

Sample Location I Description

Type
A

CCPD-A21

I.AAGl! BUR llF SEAM JlEPAlll HASTIC GRE

CCPD-A22

LARGE BUR PEllET MASTJ:C :8I..X

Time

Orv'Off

Avg.
LPM

Total
Time

o Verbal
Sample
Area/
Air

Volume

c
A

c
A

CCPD-A23

LARGE BUR FIELD

c
A

CCPD-A24

LARGE BLDG EYEBRO'If BUR FIELD

c
A

CCPD-A25

LARGE BLDG En:Dll.OW .Btllt REPAIR Gl i.E~

c
A
p

c
A

c
A

c
A

c
A
p

c
Sampled By:

Nathan

Shipped VIa: D Fed Ex~~UPS


Relinquished By~~~
Date/Time:

.30 . . 14 3:00 pm

Received By:

Dat.e I nme:

10 - 3 1- 1 4 p 0 1 : 3 7 RcI

~oo~~ thes

b).cisco Ollie~:

Date:

S~alesky

CJ

No~
~oad,

CJ

US Mail

r:J Courier

Time:

10.30.14

o Drop Off

Other:

Relir>quished By:

Relinquished By:

Dale/Time:

Date/Time:

Received By:

Received By:

[!Date/Time:

Date/Time:

Condition Acreptablel 0 Yes

CJ No

Condition i\cceptable? 0 Yes

ONo

S<Jn
37n Depot
Suite 409, Hayward, Califomia 94545-2761 {Ph: (51 0)887-&828 (800)827-3274 /FillC (51 0)887-4218
Los Angeles Office: 2959 Pacific Commerce Drive, Rancho Dominguez, CaUfornia 90221 I Ph: 01 0)7&3-2374 {8&81813-~17 I fax: (31 0)763-4450
l.ts V~!ga! Office: 6765 S. Eastem Avenue, Suite 3, La$ Vegas, NevadA 8911 9/ Ph: (702}784.004{) I Fax: (702)7114-0030

Final Report

Forensic Analytical Laboratories

Bulk Asbestos Analysis


(EPA Method 600/R-93-116, Visual Area Estimation)
Skyline Engineering, Inc.
Nathan Schalesky
8100 Wild Horse Rd.

Client ID:
Report Number:
Date Received:
Date Analyzed:
Date Printed:
First Reported:

Salinas, CA 93907
Job ID/Site:

CCPD - City of Carmel Police Department

FALl Job ID:


Ll355
Total Samples Submitted: 25
Total Samples Analyzed: 25

Date(s) Collected: 10/30/2014


Sample ID

Lab Number

CCPD-Al
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt

11577391

Asbestos
Type

Percent in
Layer

Asbestos
Type

Percent in
Layer

Asbestos (ND)

ND
ND
ND
ND
ND
ND
ND
Asbestos (ND)

11577393
ND

Total Composite Values ofFibrous Components:


Cellulose (Trace)
CCPD-A4
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt

Percent in
Layer

11577392

Total Composite Values of Fibrous Components:


Fibrous Glass (45 %)
Cellulose (2 %)
Comment: Bulk complex sample.
CCPD-A3
Layer: Black Mastic

Asbestos
Type

ND
ND
ND
ND
ND
ND

Total Composite Values of Fibrous Components:


Cellulose (2 %)
Fibrous Glass (45 %)
Comment: Bulk complex sample.
CCPD-A2
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Brown Fibrous Material

L1355
B197778
10/31114
11107/14
11/07114
11107/14

Asbestos (ND)

11577394

Total Composite Values of Fibrous Components:


Cellulose (2 %)
Fibrous Glass (45 %)
Comment: Bulk complex sample.

ND
ND
ND
ND
ND
ND
Asbestos (ND)

I of 5
3777 Depot Road, Suite 409, Hayward, CA 94545

I Telephone: (51 0) 887-8828 (800) 827-FASI I Fax: (51 0) 887-4218

Report Number:
Date Printed:

Client Name: Skyline Engineering, Inc.


Sample ID

Lab Number

CCPD-AS
Layer: Stones
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt

11577395

Percent in
Layer

Asbestos (ND)

Asbestos (ND)

ND
ND
ND
ND
ND
ND
Asbestos (ND)

11577398
ND
ND
Asbestos (ND)

11577399
ND

Total Composite Values of Fibrous Components:


Cellulose (Trace)
CCPD-AIO
Layer: Grey Non-Fibrous Material

Asbestos
Type

11577397

Total Composite Values ofFibrous Components:


Cellulose (10 %)
CCPD-A9
Layer: Grey Non-Fibrous Material

Percent in
Layer

ND

Total Composite Values of Fibrous Components:


Cellulose (2 %)
Fibrous Glass (45 %)
Comment: Bulk complex sample.
CCPD-A8
Layer: Black Mastic
Layer: Black Non-Fibrous Material

Asbestos
Type

11577396

Total Composite Values of Fibrous Components:


Cellulose (1 0 %)
CCPD-A 7
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt

Percent in
Layer
ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
ND

Total Composite Values ofFibrous Components:


Cellulose (2 %)
Fibrous Glass (45 %)
Comment: Bulk complex sample.
CCPD-A6
Layer: Black Mastic

Asbestos
Type

Bl97778
11/07114

Asbestos (ND)

11577400

Total Composite Values ofFibrous Components:

ND
Asbestos (ND)

Cellulose (Trace)

2 of 5
3777 Depol Road, Suite 409, Hayward, CA 94545

I Telephone : (51 0) 887-8828 (800) 827-FASI I Fax : (51 0) 887-4218

Report Number:
Date Printed:

Client Name: Skyline Engineering, Inc.


Sample ID

Lab Number

CCPD-All
Layer: Off-White Coating

11577401

Asbestos
Type

Percent in
Layer

Asbestos (ND)

Asbestos (ND)

11577403
ND
ND
ND
ND
ND
ND
Asbestos (ND)

11577404
ND
ND
ND

Total Composite Values of Fibrous Components:


Cellulose (15 %)
Fibrous Glass (35 %)
Comment: Bulk complex sample.
CCPD-AlS
Layer: Stones
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt

Percent in
Layer

ND

Total Composite Values of Fibrous Components:


Fibrous Glass (45 %)
Cellulose (2 %)
Comment: Bulk complex sample.
CCPD-A14
Layer: Brown Roof Shingle
Layer: Brown Roof Shingle
Layer: Black Felt

Asbestos
Type

11577402

Total Composite Values of Fibrous Components:


Cellulose (Trace)
CCPD-Al3
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt

Percent in
Layer
ND

Total Composite Values of Fibrous Components:


Cellulose (Trace)
CCPD-A12
Layer: Off-White Coating

Asbestos
Type

B197778
11/07114

Asbestos (ND)

11577405

Total Composite Values of Fibrous Components:


Cellulose (2 %)
Fibrous Glass (45 %)
Comment: Bulk complex sample.

ND
ND
ND
ND
ND
ND
ND
Asbestos (ND)

3 of 5
3777 Depot Road, Suite 409, Hayward, CA 94545

I Telephone: (51 0) 887-8828 (800) 827-FASI I Fax: (51 0) 887-4218

Report Number:
Date Printed:

Client Name: Skyline Engineering, Inc.


Sample ID

Lab Number

CCPD-A16
Layer: Stones
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt

11577406

Percent in
Layer

Asbestos (ND)

Asbestos (ND)

11577408
ND
Asbestos (ND)

11577409
ND
ND
ND
ND
ND
ND
ND

Total Composite Values of Fibrous Components:


Fibrous Glass (45 %)
Cellulose (2 %)
Comment: Bulk complex sample.
CCPD-A20
Layer: Stones
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Brown Fibrous Material

Asbestos
Type

ND

Total Composite Values ofFibrous Components:


Cellulose (Trace)
CCPD-A19
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Brown Fibrous Material

Percent in
Layer

Asbestos
Type

11577407

Total Composite Values of Fibrous Components:


Cellulose (Trace)
CCPD-A18
Layer: Grey Mastic

Percent in
Layer
ND
ND
ND
ND
ND
ND
ND

Total Composite Values ofFibrous Components:


Cellulose (2 %)
Fibrous Glass (45 %)
Comment: Bulk complex sample.
CCPD-A17
Layer: Grey Mastic

Asbestos
Type

Bl97778
11/07/14

Asbestos (ND)

I 1577410

Total Composite Values of Fibrous Components:


Cellulose (2 %)
Fibrous Glass (45 %)
Comment: Bulk complex sample.

ND
ND
ND
ND
ND
ND
ND
ND
Asbestos (ND)

4 of 5
3777 Depot Road, Suite 409, Hayward, CA 94545

Telephone: (510) 887-8828 (800) 827-FASI

Fax: (510) 887-4218

Report Number:
Date Printed:

Client Name: Skyline Engineering, Inc.


SampleiD

Lab Number

CCPD-A21
Layer: Grey Mastic

11577411

Total Composite Values of Fibrous Components:


Cellulose (Trace)
CCPD-A22
Layer: Grey Mastic

10%

Asbestos
Type

Percent in
Layer

Asbestos
Type

Percent in
Layer

Asbestos (10%)

10%

Asbestos (10%)

11577413
ND
ND
ND
ND
ND
ND
ND
Asbestos (ND)

11577414
ND
ND
ND
ND
ND
ND
ND

Total Composite Values of Fibrous Components:


Fibrous Glass (45 %)
Cellulose (2 %)
Comment: Bulk complex sample.
CCPD-A25
Layer: Grey Mastic

Chrysotile

Chrysotile

Total Composite Values of Fibrous Components:


Fibrous Glass (45 %)
Cellulose (2 %)
Comment: Bulk complex sample.
CCPD-A24
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Brown Fibrous Material

Percent in
Layer

11577412

Total Composite Values of Fibrous Components:


Cellulose (Trace)
CCPD-A23
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Black Tar
Layer: Black Felt
Layer: Brown Fibrous Material

Asbestos
Type

B197778
11/07/14

Asbestos (ND)

11577415

Total Composite Values ofFibrous Components:


Cellulose (Trace)

Chrysotile

10%

Asbestos (10%)

Tad Thrower, Laboratory Supervisor, Hayward Laboratory


Note: Limit of Quantification ('LOQ') = I%. 'Trace' denotes the presence of asbestos below the LOQ. 'ND'

= 'None Detected'.

Analytical results and reports are generated by Forensic Analytical Laboratories Inc. (fALl) at the request of and for the exclusive use of the person or entity (client) named on such
report. Results, reports or copies of same will not be released by FALl to any third party without prior written request from client. This report applies only to the sample(s) tested.
Supporting laboratory documentation is available upon request. This report must not be reproduced except in full, unless approved by FALL The client is solely responsible for the
use and interpretation of test results and reports requested from FALL Forensic Analytical Laboratories Inc. is not able to assess the degree of hazard resulting from materials
analyzed. FALl reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified. All samples were
received in acceptable condition unless otherwise noted.

3777 Depot Road, Suite 409, Hayward, CA 94545

Telephone: (51 0) 887-8828 (800) 827-FASI

5 of 5
Fax: (51 0) 887-4218

Analysis Request Form (CQC)

Forensic Analytical Laborcitories, Inc.


PO/~

Oient Name & Adt.lr~:

LJat~: 10. 30. 14

CCPD

- - - - - - - - - - - - . . . . ..----:--t
'lum/\roundlime: Same Day /ID<Jy /20ay I 3Day I 40ory IS~

Skyline Engineering
#Cl3550

1:1 l"t.M: C NIOSH 7400A I 0 NIOSH 7401.16

Rotameter

1------- --- -------......-----0 P\.M: 0 Standard I 0 Polnl Couna.WO- 1000 I n CARll 435

N th

C.ont.ld:

S h l

a an C a es Y
1-,..._:--_n-f!----------r::
IF,-~~-.--------~
rnu .: 831-521-0076
.. ~.
E-mail:
Site:

nate@ s kylineengineer ing . com


City of

- - - - - - - - - - -- ...
Carmel Police DepartJnent

0 lt.M Air: C 1\HERA I C Yam.ale2 I n NIOSH 7402


0 TtM Bulk: 0 QuartiL~ve I 0 Qu~lila!ive I 0 <hatfield
Cl TI'M W;ftt!r: :J Poblble I !J Non-Potable I r.1 Wtit~hl 'Yo
0 TEM MicrOYac: 0 Qual(+/-) I 0 OS755~r/arel} I 0 D57SC.(Jtr/m.a~~

1:1 tAQ P;wtide kJI!nlilicalion tf'LM l.4Jll


o PIM Op.1quL'!/Sool.
0 1-'anide ldentlflc:ation ffiM LAA)
1:1 Special Projea
:I ~Is 1\nalysb: Method; FI.oM! ..AA., ( Pb)

_______

Malri~~:

Site l...or.<~linn:

Ana lyles:
~port

CLI onsite Gene Spector

0 fax

~le L.or..arion I Description

Time

Type
A

CCPO-PBl
f--- .. ...

COA:rDIG

--------+-----+---

CCPD-PB2

Ill E-Mail

rOR AIR SAMPI fS ONlY

Date/

Samplt~IO

Via:

------------------------

PATIO PAlW'El' tiALL COATnM CREAN

Time
O.YOff

1\VJ(.
LPM

Sample

Ama/

Total

Air

Tl~

Volume

.;. .....:~------+----+---- .. ---~


A
p

c
A

CCPD-PB3

c
A

CCPD-PB4

c
A

CCPD-PB5

~---

c
A

c
A

"c

,.,
c

---~

c
Sampled By:

~~UPS
/.;r-__,"""
r-..

Shipped Via: 0 ff!!d Elc

__)

Relinqulshl!d82Yoy
:
~.JfR'/

! .... _

D.!t<!ilime:
ltt!~ived

D.lte:

Nathan Schalesky

0.30.14 3:00 pm

By:

01/SMail

1:1 Coorier

Off

OthH:
Rf.llrw)ui..hed By:

I.J<Ite/Time:

D~eiTime;

Rraived By:

By;

D01~ /lime:

c~.d'ves

Cnndition Anwt.able/ 0 Yes

LA.fS

0 Drop

Time:

Retinqulshe.i Fly:

10-31-14P12=48 RCV
l').f<! Timt':
1:1 No

10. 30. 14

lJate I Time:

0 No

Cordi~on Mx:IUltable1 0 Yes

0 No

SanUisco Offia!: .1 777 Oepot Muad, Suite 409, HIIY"o'llrd, (alilomia 94545-2761 I Ph: <510)667-88211 (R00)827-ll74/ fax: 1510)687-4216
Office: 2959 Pacific COI'I'ImP.fTE' Driw. Kardlo DomlnJ!lJeZ, Callfnrni.a '10221 i t'h: (310)763-2374 (OOO)l)D-9417 I Fax: (J 10)7>3--1-450
Las Vega~ Of(i(e; 6765 S. Easllern J\ven~~e, Suit!! l, l. VegdS. NIMida 891191 PI\; 1702)704-0040 I Fall : (702)7640030

to~ A"'!de~

--------------

Final Report
Forensic Analytical Laboratories

Metals Analysis of Paints


Skyline Engineering, Inc.
Nathan Schalesky
8100 Wild Horse Rd.

Client JD:
Report Number:
Date Received:
Date Analyzed:
Date Printed:
First Reported:

Salinas, CA 93907
Job JD I Site: CCPD, City of Carmel Police Department
Date(s) Collected:

Ll355
M155501
10/31/14
11107/14
11107/14
11/07114

FALl Job JD:


Ll355
Total Samples Submitted: 5
Total Samples Analyzed: 5

Lab Number

Analyte

Result

Result
Units

Reporting
Limit*

Method
Reference

CCPD-PBI

30699189

Pb

0.015

wt%

0.006

EPA 3050B/7420

CCPD-PB2

30699190

Pb

< 0.006

wt%

0.006

EPA 3050B/7420

CCPD-PB3

30699191

Pb

0.028

wt%

0.007

EPA 3050B/7420

CCPD-PB4

30699192

Pb

0.072

wt%

0.006

EPA 3050B/7420

CCPD-PB5

30699193

Pb

0.034

wt%

0.006

EPA 3050B/7420

Sample Number

* The Reporting Limit represents the lowest amount of analyte that the laboratory can confidently detect in the sample, and is not a
regulatory level. The Units for the Reporting Limit are the same as the Units for the Final Results.

Daniele Siu, Laboratory Supervisor, Hayward Laboratory


Analytical results and reports are generated by Forensic Analytical at the request of and for the exclusive use of the person or entity (client) named on such report. Results,
reports or copies of same will not be released by Forensic Analytical to any third party without prior written request from client. This report applies only to the sample(s)
tested. Supporting laboratory documentation is available upon request. This report must not be reproduced except in full, unless approved by Forensic Analytical. The client
is solely responsible for the use and interpretation of test results and reports requested from Forensic Analytical. Forensic Analytical is not able to assess the degree of hazard
resulting from materials analyzed. Forensic Analytical reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal
guidelines, unless otherwise specified. Any modifications that have been made to referenced test methods are documented in Forensic Analytical's Standard Operating
Procedures Manual. Sample results have not been blank corrected. Quality control and sample receipt condition were acceptable unless otherwise noted.
I of I

3777 Depot Road, Suite 409, Hayward, CA 94545 I Telephone: (510) 887-8828 (800) 827-FASI I Fax: (510) 887-4218

Appendix C

License and Certification

State of California
Division of Occupational Safety and Health
Certified Asbestos Consultant
Paulo C Parra
Name

Certification No. 11=4806


Expires on

1 0/19/15

This CI8I1IIDIIion was lllsued bV fie Oivisloo It


CJca4Bional Safety n! Hssth as 8l.CIIorizad bV

Sdlns 7180 et aeq. It fie l!uilnlm llld


~Code.

State of California Department of Public Heatth


L

ei'>d "latet

f'ql'

OI~Struclor

'I

C crt1hcat-

Inspector/Assessor

....

111081201!

Appendix D

Mold Survey Section

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 1

Introduction

This section contains the findings and recommendations from our limited mold
investigation. The purpose of the investigation was to attempt to identify areas of
mold growth in the lower level parking garage - the area directly related to the
possible re-roofing of the above court yard, make recommendations regarding
corrective actions, and provide information for consideration in assessing risk to
occupants.
The data collected in the course of the investigation is presented in this report as
follows:
Table 1 -visual observations, moisture readings, photo & sample references.
Floor Plan- showing the locations of key observations and samples taken.
Photographs - depicts inspection observations.

Methodology

Moisture Meter Readings - the moisture content of various building substrates


was evaluated using a direct reading instrument. We routinely use a Delmhorst
BD 2100 moisture meter. The BD 2100 is capable of measuring the moisture
content of wood, concrete/plaster and wallboard using preset factory scales.
Tape Lift Surface Sampling - transparent adhesive tape is pressed onto a surface
with suspected fungal growth or contamination. The tape is gently lifted off of the
surface and affixed to a clean microscope slide. The surface samples are labeled
with unique sample numbers and information recorded on field chain of custody
forms. The samples are promptly delivered to the laboratory for analysis.

Site Details

The lower level parking garage is located directly below an open court yard which
may be re-roofed, and is constructed primarily of unfinished concrete floors and
painted concrete walls and ceiling. There are four large planters above the
garage - in the courtyard. These planters seem to be the source of some

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 2

leakage seen on the ceiling. There is also damage under the main entrance
stairwell from a previous leak.

Findings and Conclusions


Limited areas of mold growth were discovered under the main entrance concrete
stairwell and the parking garage ceiling which require corrective actions. No other
mold growth was observed in the lower level garage area. A more complete
discussion of findings, conclusions and recommendations is provided below.

Based on this investigation, the following conclusions are reached:


1. Mold Growth & Remediation (General). Mold (a.k.a., "fungal") growth can
occur when organic building materials or accumulated organic debris is
impacted by moisture. This may occur within 24-48 hours from the time such
materials become wet, hence it is critical that materials are substantially dried
within this time frame in order to minimize the potential for mold growth to
develop. Mold growth has the potential to elicit negative health effects in
sensitive persons. This most frequently manifests as allergic respiratory
symptoms which may range from mild to severe depending on individual
sensitivities. Irritant and infectious effects are possible. It is generally
accepted that mold growth in buildings should be removed following
appropriate precautions to protect workers involved in the clean-up and the
surrounding environment. Greater precautions are taken for greater amounts
of mold growth. In addition, the underlying cause of mold and moisture
intrusion should be identified and corrected in order to minimize the potential
for recurrent mold growth. Additional information can be found at the U.S.
Environmental Protection Agency website (http://www.epa.gov/mold/).
2. Locations of Mold Growth. Mold growth was observed in two (2) localized
areas. The first location where mold growth was observed was at the plywood
boards and wood framing, in the confined space under the stairwell and in the
ceiling of the parking garage. Elevated moisture was indicated on the ceiling
of the parking garage and there was also delaminating paint throughout the
parking garage due to elevated moisture. Specific locations, descriptions,
conclusions and supporting reasoning are provided in Table 2.
3. Occupant Exposure.
a. Air samples were not collected during this inspection.
Skyline Engineering - Engineering Services for the Building Envelope
www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 3

b. No accepted quantitative standards currently exist by which to assess the


health risks related to fungal exposure. Since fungus and airborne fungal
spores are common in the natural environment, most guidelines focus on
the amount and location of visible fungal growth present and comparison
of indoor and outdoor spore levels.
c. Airborne fungal spore levels can vary greatly over time due to changes in
environmental conditions and activity patterns. In addition, commonly
employed air sampling methods exhibit variability from sample to sample
and can mask differences in fungal species between indoor and outdoor
environments. More definitive data can be developed by more extensive
and repeated sampling over time.
d. Based on these limitations, and on the potential presence of other adverse
biological agents that may develop on moisture impacted materials, mold
growth and dampness in buildings should be controlled and impacted
areas should be appropriately addressed in order to promote a healthful
indoor environment.
4. Causal Conditions. Conditions resulting in moisture impact upon organic
building materials should be determined and corrected in order to prevent the
development of additional mold growth. Preliminary FAGS findings related to
potential causes of moisture intrusion are provided in Table 2. These findings
should be reviewed and verified by an appropriately qualified construction
professional in order to ensure accurate identification and correction of the
causes of moisture intrusion issues.

Recommendations

Based on this limited investigation, the following recommendations are made:


1. All mold cleaning, removal and drying activities should be conducted in
accordance with commonly accepted guidelines for mold remediation and
water damage restoration as summarized in the General Mold Remediation
Guidelines provided at the end of this report.
2. Prior to and during the removal of building materials, consider the potential for
disturbance of materials containing asbestos, lead or other hazardous
substances and take appropriate measures in accordance with applicable
federal, state and local regulations.

Skyline Engineering- Engineering Services for the Building Envelope


www.skylineengineering .com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 4

3. Inspect for hidden mold growth using appropriate precautions as called for in
Table 2 and the General Mold Remediation Guidelines referenced therein.
4. Remove identified areas of mold growth following appropriate guidelines to
protect workers and control contamination as called for in Table 2 and the
General Mold Remediation Guidelines referenced therein.
5. Dry out any discovered wet organic building materials following appropriate
guidelines as identified in the General Mold Remediation Guidelines
referenced therein.
6. Following completion of mold remediation activities, conduct a postremediation assessment to confirm that the recommended mold cleaning and
removal activities have been completed appropriately. Specific postremediation assessment recommendations are provided in Table 2 and the
General Mold Remediation Guidelines referenced therein.
7. Concurrent with mold remediation efforts, determine and address the causes
of moisture intrusion in consultation with an appropriately qualified
construction professional in order to prevent additional mold growth from
occurring.

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 5

Table 1: Observations
Ref

Functional
Area or
Location

Stairwell

Parking
Garage

Area
of
Mold

Observations and History

Visible lumber mold and


deterioration of wood on OSB
board and wood framing .
No elevated moisture observed
. on wood framing.
: Wood framing seems to be a
fake wall.
: No other notable observations .

i -6 SF

Visible mold observed on ceiling


of garage .
Visible water staining observed
throughout.
Delaminating paint observed on
ceiling of garage.
Efflorescence salts were
observed on concrete walls .

Area of
Moisture

Moisture
Readings<

'jd

Sample 'jd

1127,
1128,
1130

'

99.9
-2 SF

Photo

-2 SF

(Concrete
Scale)

1133,
1136,
1137,
1139

Notes:
Estimated total surface area of mold growth actually observed and mold growth intensity (light, moderate or heavy).
b Estimated total cross-sectional area of moisture impact actually observed (i.e., staining/damage, elevated moisture
meter readings, visible moisture).
c Moisture meter readings and substrate.
d Refer to photo and laboratory report appendices.

Table 2: Mold Growth Conclusions and Repair Recommendations


#

Mold Growth Location,


Description and Reasoning
Stairwell
Visible mold was observed on
the OSB board and wood
framing on stairwell. This
conclusion is supported by the
assumed history of moisture
intrusion and visible mold
growth.

Parking Garage Ceiling


Visible mold was observed on
the ceiling . Water staining,
efflorescence and
delaminating paint was
observed throughout. This
conclusion is supported by the
assumed history of moisture
intrusion and visible mold
growth, and efflorescence.

Mold
Growth

6 SF
Moderate

2 SF
Moderate

Repair Levelb

Repair Detail

Preliminary
Cause

M2
MT

Clean wood framing.


Remove and replace
damaged framing if
possible.

Possible Leak

M2
MT

Clean ceiling and


efflorescence.

Leak

Notes:
Conclusion regarding presence of mold growth/contamination
, Potential, ~ l$
), total surface
area of mold growth anticipated (visible and hidden) and anticipated mold growth intensity (light, moderate, heavy).
b Refer to appendix containing General Mold Remediation Guidelines for description of work practices and guidance
documents.
c Preliminary cause of moisture intrusion and mold growth based upon general observations. Construction related
causal factors should be confirmed by an appropriately qualified building professional.

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

..

~- 0
~ ::l

1l

,...
....
,.

. .,

. ... . ...

.....

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

.. -.- ... f

FLOOR PLAN

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 6

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 7

PHOTOGRAPHS

1127- Visible mold and water staining on OSB


and wood framing.

1128- Moisture reading and wood damage.

1130- Visible mold on wood framing.

1133 - Water staining and paint delaminating


on concrete ceiling.

Skyline Engineering- Engineering Services for the Building Envelope


www.skylineengineering .com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

1136 - Visible mold and water staining on


concrete ceiling.

Page 8

1137 - Elevated moisture on concrete ceiling.

1138 - Efflorescence on concrete walls.

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 9

SAMPLING RESULTS SUMMARY

Surface Tape Lift Samples (Lab Report #F1 05362)


Sample
Number

Location

Substrate

Summary Finding

Wood

Minor - Ascospores, Basidiospores


Trace- Hyphae, Rusts/Smuts/
Myxomycetes

TL-1

Crawlspace under main stairs

TL-2

Garage deck

Concrete

TL-3

Garage office exterior wall

Concrete

Note: Findings in bold considered elevated.

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 10

GENERAL MOLD REMEDIATION GUIDLINES

CONTENTS

Global Mold Remediation Guidelines


General Procedures for:
MO
M1
M2
M3

De Minimus Mold Remediation


Small Scale Mold Remediation
Medium Scale Mold Remediation
Large Scale Mold Remediation

MC Removal of Mold Spore Contamination


ME Exterior Mold Remediation
MT Invasive Inspection for Mold

GLOBAL MOLD REMEDIATION GUIDELINES

1. General Practices. All work, which may result in the disturbance of mold
growth or contamination, should be performed using work practices that
minimize the disturbance of affected materials and dispersion of mold spores.
Measures should also be taken to protect the health and safety of individuals
performing remediation activities. At a minimum, work should be performed in
accordance with the following guidelines addressing mold/water intrusion
remediation:
Environmental Protection Agency. (September 2008). Mold Remediation in
Schools and Commercial Buildings. EPA 402-K-01-001. Appendix B. Retrieved
6/5/12: http://www.epa.gov/mold/mold_remediation.html
New York City Department of Health. (November 2008). Guidelines on Assessment
and Remediation of Fungi in Indoor Environments. Appendix A. Retrieved 6/5/12:
http://www.nyc.gov/html/doh/html/epi/moldrpt1 .shtml
U.S. Department of Labor Occupational Safety and Health Administration (March
2010). Safety and Health Information Bulletin: A Brief Guide to Mold in the
Workplace. SHIB 03-10-10. Retrieved 6/5/12: http://www.osha .gov/dts/shib/
shib 101003.html
American Industrial Hygiene Association . (2008). Recognition, Evaluation and
Control of Indoor Mold. IMOM08-679.
Institute of Inspection, Cleaning and Restoration Contractors. (2006). IICRC 500
Standard and Reference Guide for Professional Water Damage Restoration. Third
edition .
Institute of Inspection, Cleaning and Restoration Contractors. (2008). IICRC S520
Standard and Reference Guide for Professional Mold Remediation . Second
edition.

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering.com

Asbestos, Lead , and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 11

2. Material Removal. In the course of removing building materials, bulk


quantities of visible mold growth shall be removed from all wood structural
members or other materials. Materials should be cleaned or removed 18
inches past visible mold growth unless otherwise specified.
3. Regulated Materials. Prior to commencing remediation activities, building
materials that may be disturbed should be assessed for asbestos and leadbased paint hazards per applicable regulations.
4. Sources of Moisture. Mold growth is most frequently caused by a failure to
adequately control moisture. Thus, whenever mold remediation is performed,
measures should be taken to correct the conditions resulting in excess
moisture and mold growth.
GENERAL PROCEDURES
MO: General Procedures for De Minimus Mold Remediation

------------------

The following procedures are provided for general guidance and may be modified as
appropriate to address specific conditions on a case-by-case basis. All work should be
performed in accordance the aforementioned guideline publications.
Example Applications
Surface cleaning and non-aggressive removal of S1 ft. 2 of mold growth.
Surface cleaning of areas with light or minimal mold spore deposition/
contamination.
Typical housekeeping activities.
Personal Protective Equipment
May include the use of an N-95 disposable respirator, gloves and eye protection.
Containment Provisions
None required.
Work Practices
Mist surface and wet-wipe in a manner that minimizes disturbance of growth.
Post-Remediation Assessment
Visual confirmation of removal of growth.
M1: General Procedures for Small Scale Mold Remediation __________________

The following procedures are provided for general guidance and may be modified as
appropriate to address specific conditions on a case-by-case basis. All work should be
performed in accordance the aforementioned guideline publications.
Skyline Engineering- Engineering Services for the Building Envelope
www.skylineengineering .com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 12

Example Applications
Surface cleaning and non-aggressive removal of >1 to <1 0 ft.2 of mold growth.
Aggressive removal of materials with :51 ft. 2of dense mold growth, or <1 0 ft.2 of
sparse mold growth.
General construction dust control for removal of building materials.
Personal Protective Equipment
N-95 disposable respirator, gloves and eye protection.
Containment Provisions
Cover the immediate work area with plastic sheeting.
A floor to ceiling plastic barrier should be erected to further isolate the work area
if greater than approximately 5 ft. of material is being aggressively removed (e.g.,
removal of drywall).
Ensure ventilation provisions in the area are turned off.
Work Practices
Remediation performed by maintenance/construction personnel with awareness
training regarding proper clean up methods, personal protection, and potential
health hazards associated with mold.
Clean surfaces using a HEPA vacuum or dust suppression methods (e.g.,
misting).
Remove materials using methods to minimize the disturbance of growth and for
general dust suppression (e.g., HEPA vacuum positioned at the point of
operation/removal and misting).
If removal cannot be accomplished without significant disturbance of mold growth
or more extensive mold growth is encountered, then work should stop and
medium or large scale remediation procedures should be implemented.
All contaminated materials should be removed from the work area in a sealed
plastic bag.
Following removal of mold growth, clean the work area and immediately adjacent
surfaces using a HEPA vacuum or wet-wiping.
Post-Remediation Assessment
Assessment by a designated individual familiar with these procedures and with
mold awareness training.
Visual confirmation of removal of growth and absence of contamination and
debris prior to removal of containment provisions.
Materials should be dried and causes of moisture impact controlled to prevent
future growth.

M2: General Procedures for Medium Scale Mold Remediation_ _ _ _ _ _ __

The following procedures are provided for general guidance and may be modified as
appropriate to address specific conditions on a case-by-case basis. All work should be
performed in accordance the aforementioned guideline publications.
Example Applications
Surface cleaning and non-aggressive removal of 10 to <1 00 ft. 2 of mold growth.
Aggressive removal of materials with >1 to <10 ft. 2 of dense mold growth, or 10 to
<100 ft. 2of sparse mold growth.
Skyline Engineering - Engineering Services for the Building Envelope
www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 13

Personal Protective Equipment


1/2 face respirator with HEPA filters, gloves, disposable coveralls and goggles.
Consider the use of HEPNorganic vapor combination cartridges if strong musty
odors are present.
Containment Provisions
Isolate the work area from the surrounding environment using 1 layer of plastic
sheeting configured with a slit entry and covering flap .
Seal all penetrations to surrounding areas using plastic and tape (e.g., outlets,
light switches, ventilation grills).
Negatively pressurize the work area and exhaust out of the work area with
HEPA filtration.
Work Practices
Remediation performed by professional mold remediation contractors with
appropriate training and experience in mold remediation practices.
Clean surfaces using a HEPA vacuum or dust suppression methods (e .g.,
misting).
Remove materials using methods to minimize the disturbance of growth to the
extent feasible.
All contaminated materials should be removed from the work area in a sealed
plastic bag .
Following removal of mold growth, clean the work area, immediately
surrounding area, and worker egress pathways using a HEPA vacuum or wetwiping.
Post-Remediation Assessment
Assessment performed by a professional mold consultant with appropriate
training and experience.
Visual confirmation of removal of growth and absence of contamination and
debris.
Collection and evaluation of air and surface samples as appropriate to support
visual inspection.
Materials should be dried and causes of moisture impact controlled to prevent
future growth .
Containment provisions remain in place until the work areas has passed the
assessment criteria.
M3: General Procedures for Large Scale Mold Remediation _ _ _ _ _ _ _ __

The following procedures are provided for general guidance and may be modified as
appropriate to address specific conditions on a case-by-case basis. All work should be
performed in accordance the aforementioned guideline publications.
Example Applications
Surface cleaning and non-aggressive removal of ~1 00 ft .> of mold growth.
Aggressive removal of materials with ~100ft.> of dense or sparse mold growth.
Personal Protective Equipment

Skyline Engineering - Engineering Services for the Building Envelope


www.skylineengineering .com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 14

Full-face respirator with HEPA filters, gloves, disposable coveralls with head
and foot coverings and goggles. Consider the use of HEPA/organic vapor
combination cartridges if strong musty odors are present.
Containment Provisions
Isolate the work area from the surrounding environment using 2 layers of
plastic sheeting configured with a decontamination area between two slit
entries with covering flaps.
Seal all penetrations to surrounding areas using plastic and tape (e.g., outlets,
light switches, ventilation grills).
Negatively pressurize the work area and exhaust to the outdoor environment
with HEPA filtration.
Work Practices
Remediation performed by professional mold remediation contractors with
appropriate training and experience in mold remediation practices.
Clean surfaces using a HEPA vacuum or dust suppression methods (e.g.,
misting).
Remove materials using methods to minimize the disturbance of growth to the
extent feasible.
All contaminated materials should be removed from the work area in a sealed
plastic bag.
Following removal of mold growth, clean the work area, immediately
surrounding area, and worker egress pathways using a HEPA vacuum or wetwiping .
Mist surface and wet-wipe in a manner that minimizes disturbance of growth.
Post-Remediation Assessment
Assessment performed by a professional mold consultant with appropriate
training and experience.
Visual confirmation of removal of growth and absence of contamination and
debris .
Collection and evaluation of air and surface samples as appropriate to support
visual inspection .
Materials should be dried and causes of moisture impact controlled to prevent
future growth.
Containment provisions remain in place until the work areas has passed the
assessment criteria.

MC: General Procedures for Removal of Mold Spore Contamination/Deposition_


The following procedures are provided for general guidance and may be modified as
appropriate to address specific conditions on a case-by-case basis. All work should be
performed in accordance the aforementioned guideline publications.

Example Applications
Removal of secondary mold spore deposition from surfaces and contents
resulting from the presence of mold growth reservoirs in the shared
environment.
Skyline Engineering - Engineering Services for the Building Envelope
www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 15

Note: Areas of light or minimal contamination may be cleaned in accordance


with procedure MO.
o Note: Cleaning of HVAC systems should be conducted in accordance with
procedure MV.
Personal Protective Equipment
o Minimum of N-95 disposable respirator, gloves and eye protection. More
extensive protective equipment may be appropriate depending on the severity
of contamination.
Containment Provisions
o Not generally required, however conditions of severe contamination may
necessitate containment provisions depending on conditions in surrounding
environments.
Work Practices
o Remediation performed by professional mold remediation contractors with
appropriate training and experience in mold remediation practices.
o Clean horizontal and vertical surfaces in place.
o Wet-wipe hard, non-porous surfaces.
o HEPA vacuum soft, porous surfaces. Disposal of porous materials exhibiting
growth may be necessary.
o Launder or dry-clean textiles.
o Consider use of HEPA filtered negative air machines to purge or scrub the air in
the area.
Post-Remediation Assessment
o Assessment performed by a professional mold consultant with appropriate
training and experience.
o Visual confirmation of removal of growth and absence of contamination and
debris.
o Collection and evaluation of air and surface samples as appropriate to support
visual inspection.
o

ME: General Procedures for Exterior Mold Remediation _ _ _ _ _ _ _ _ __

The following procedures are provided for general guidance and may be modified as
appropriate to address specific conditions on a case-by-case basis. All work should be
performed in accordance the aforementioned guideline publications.
Example Applications
o Cleaning of ~1 0 ft.2 of mold growth from exterior surfaces.
o General construction dust control for the exterior removal of building materials.
o Note: Cleaning of <1 0 ft.2 of exterior mold growth may be conducted in
accordance with procedure MO.
Personal Protective Equipment
o Minimum of N-95 disposable respirator, gloves and eye protection . More
extensive protective equipment may be appropriate depending on the severity
of growth or intensity of removal activities .
Containment Provisions
Skyline Engineering- Engineering Services for the Building Envelope
www.skylineengineering.com

Asbestos, Lead, and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 16

Prior to commencing work, close all windows and doors in or adjacent to the
work area and seal interior window and door penetrations with tape (easy
release or painters tape).
If removal of exterior building materials is to occur, seal all wall penetrations
(i.e., electrical outlets and light switches) and base of wall on the associated
interior wall being repaired with tape (easy release or painters tape).
Work Practices
Remediation performed by maintenance/construction personnel with
awareness training regarding proper clean up methods, personal protection,
and potential health hazards associated with mold. The use of a professional
mold remediation contractor may be appropriate depending on the severity of
mold growth.
Proceed with exterior cleaning or building material removal using dust control
methods (e.g., misting).
Inspect the back of exposed interior wall systems for evidence of mold growth.
If mold growth is observed, proceed with cleaning or removal in accordance
with procedures MO-M3 as appropriate.
Use a HEPA vacuum to remove excess debris from the wall cavity prior to
reconstruction.
Post-Remediation Assessment
Assessment by a designated individual familiar with these procedures and with
mold awareness training.
Visual confirmation of removal of growth and absence of contamination and
debris prior to removal of containment provisions.
Materials should be dried and causes of moisture impact controlled to prevent
future growth.
MT: General Procedures for Invasive Inspection for Mold,_ _ _ _ _ _ _ _ __

The following procedures are provided for general guidance and may be modified as
appropriate to address specific conditions on a case-by-case basis. All work should be
performed in accordance the aforementioned guideline publications.
Example Applications
Removal of building materials in areas where there is the potential for mold
growth (i.e., the presence of mold growth has not been confirmed).
Personal Protective Equipment
May include the use of an N-95 disposable respirator, gloves and eye
protection as appropriate for general construction activities.
Containment Provisions
Follow practices for general construction dust control (see M1 above). No
special provisions for controlling mold growth are required.
Work Practices
Remove a small area of building material from the area in question to facilitate
visual inspection (e.g., <1ft. 2 ).
In the course of removal, proceed in a manner that minimizes disturbance of
potential concealed mold growth reservoirs. For example, cut around and
Skyline Engineering - Engineering Services for the Building Envelope
www.skylineengineering.com

Asbestos, Lead , and Mold Survey Report


Police HQ & PW/PS Admin Complex
Carmel by the Sea
Exterior Building Envelope HAZMAT Survey

Page 17

gently remove a section of drywall as a single piece rather than demolishing


the area with a hammer. A HEPA vacuum nozzle placed at the point of removal
may further control potential releases.
Continue removal of materials in a stepwise fashion in order to perform desired
construction repairs or to determine if any hidden mold growth exists.
If mold growth is encountered in the course of removal, immediately stop and
proceed in accordance with mold remediation procedures as appropriate (see
MO-M3 above).
Post-Remediation Assessment
No assessment is necessary if no mold growth is encountered. If mold growth
is encountered, follow the appropriate post-remediation assessment guidelines
as discussed in MO-M3 above.

Skyline Engineering- Engineering Services for the Building Envelope


www.skylineengineering .com

: SURVEY FLOOR PLAN FORM


Project

City of Carmel CCPW ACM Survey

Building

Public Works Patio Roof

Inspectors

Nathan Schalesky

Date of Survey

5.15.15

SKYLINE
ENGINEERING
ENGINEERING SERVICES FOR THE BUilDING f~'VELOPE

,,

...

_. . . ... .,. .;.

w: - ------5 -.;

.... -- .

------ ------ ,..,

--r--
.. s

Forensic Analytical Laboratories, lnc.

Analysis Request Fonn (COC)

PO/Job#;

Client Name & Address:

Skyline Engineering

Date;

CCPW

Tum Around Time: Same Day /lOa)'

#Cl3550

0 PCM: 0 N!OSH 7400A

5.15.15

I 2Day I 3Day I

I 0 NJOSH 74008

4Day

I SDlW

0 Rotameter

!2PLM: !I Standard I 0 Point Counl400 . 1000 I 0 CARB 435


Contact;
Phone:

Fax:

831.-521-0076

E-mail:
Site;

OTE.\tAir: aAHERAI OYa~ I ON!OSH7402


0 TE.\~ Bulk: D Quantitative I D Qua?itative I a Chatfield
0 reM Water. 0 Pocable I 0 Non-Potable I o Weight%
D TM Microvac 0 Qual(+/) I 0 DS75Slstr/areal I D D57S~tfll'la5S)

Nathan Schalesky

0 IAQ Panlde ldentlflcation [PLM LABJ


0 Partide identlficatlon ITEM LAB)
0 Meials Analysis: Method:

nate@skylineengineering.com
City of Carmel Publfc Works

Comments:

Anal )'US:

ReportVia:
DFax

CAC Oversight Paulo Parra


Sample Location I Descrlptlon

Time

Type
LUG! PIJIN'1'ER EXTERIOR nLL XEIIBlWIIE
BELOW GRADE BLACK

CCPW-Al

LARGE PLAmEB. DB l.TRl\GE PIPE BELOW

CCPW-A2

ME-Mall

fOR AIR SAMPLES ONLY

Date/

Sample ID

a Special Project

MattiiC
Site Location: Patio Roof

0 PLM Op1quef/Soot

D Vefbal

. Sample

Area/

Time

Avg.

Total

Air

OrlOff

LPM

Time

Volume

G.IIAOll BIJ>.CJi:

'

c
A

c
A

A
A

c
c

c
Sampled By: Nathan

Schalesky

~Hl
/
../")
Relinquished By: -:::;t:.~~

Shipped ViiiC 0 Fed Ex

t1 UPS

,~-~

Dare/Tim

Reuived&J:/

1_5 ~~\am

RECEIVEU

'\;"\

"''TI6 MA'I 2 0 20\5 ;:1/t{),l;


~le~ ot:Jo-:1
0

Date:

o US Mail

5.15.15

0 Courier

D Drop Off

Time:

0 Other.

Relinquished By:

Relinquished By:

Date/Time:

Oate/Time;

'
Received By:

Received B)':

Date/Time:

Date /1ii'M!

ConditionAcceptable1

[J

Yes

ONo

Condition Acceptable? 0 Yes

.
0 No

.,\!,~.{~, S.l:o409, Ho>"''~ C.llfumO 94'045-2761/ PI< 010)087-8828 ~DOl827-J27/ F= 010)887-<218

Los Angeles

'""" fii'e
merc.e Drive, Rancho Dominguez. Cailfumla 90221/ Ph: (31 0)7632374 {888)813-9417 I fax: (3 10)763-4450
~
; 6765 S. Eutem Avenue, Suite 3, Las Vegas, Nevada 89119/ Ph: (702)784-0040 I Fax: (702)784-0030

Amended Report

Forensic Analytical Laboratories

Bulk Asbestos Analysis


(EPA Method 600/R-93-116, Visual Area Estimation)
Skyline Engineering, Inc.
Nathan Schalesky
8100 Wild Horse Rd.

Client ID:
Report Number:
Date Received:
Date Analyzed:
Date Printed:
First Reported:

Salinas, CA 93907

FALl Job ID:


Ll355
Total Samples Submitted: 2
Total Samples Analyzed: 2

Job ID/Site: CCBACH, Patio Roof


Date(s) Collected:
Sample ID

Lab Number

CCPW-Al
Layer: Black Semi-Fibrous Tar

11645494

Asbestos
Type

Percent in
Layer

Asbestos
Type

Percent in
Layer

Asbestos
Type

Percent in
Layer

ND

Total Composite Values ofFibrous Components:


Fibrous Glass (15 %)

CCPW-A2
Layer: Black Pipe

Ll355
B205910
05/20/15
06/08/15
06/08/15
05/28/15

Asbestos (ND)

11645495

Total Composite Values ofFibrous Components:


Cellulose (25 %)

ND
Asbestos (ND)

Tad Thrower, Laboratory Supervisor, Hayward Laboratory


Note: Limit of Quantification ('LOQ') = I%. 'Trace' denotes the presence of asbestos below the LOQ . 'ND' ='None Detected'.
Analytical results and reports are generated by Forensic Analytical Laboratories Inc. (FALl) at the request of and for the exclusive use of the person or entity (client) named on such
report. Results, reports or copies of same will not be released by FALl to any third party without prior written request from client. This report applies only to the sample(s) tested.
Supporting laboratory documentation is available upon request. This report must not be reproduced except in full, unless approved by FALl. The client is solely responsible for the
use and interpretation of test results and reports requested from FALl. Forensic Analytical Laboratories Inc. is not able to assess the degree of hazard resulting from materials
analyzed. FALl reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified. All samples were
received in acceptable condition unless otherwise noted.

1 of 1
3777 Depot Road, Suite 409, Hayward, CA 94545 I Telephone: (510) 887-8828 (800) 827-FASI I Fax: (510) 887-4218

jExhbit "G"
CONTRACT FOR PROFESSIONAL CONSULTING SERVICES
THIS CONTRACT is executed this .2()~ day of.Afl?-\ \ , 2015, by and between
the CITY OF CARMEL-BY-THE-SEA, a municipal corporation (hereinafter "CITY"), and Skyline
Engineering, Inc., (hereinafter "CONSULTANT").
IT IS HEREBY MUTUALLY AGREED AS FOLLOWS:
1.
Scope. CONSULTANT hereby agrees to provide to CITY, as the scope of
services under this Contract the services set forth in the proposal for services dated March 25,
2015 (Exhibit "A), for Planter Waterproofing Project at the Public Works & PDHQ Building,
attached hereto and incorporated herein by this reference.
CONSULTANT is bound by the contents of CITY'S Request for Proposal,
attached as Exhibit "B" and incorporated herein by this reference, and the contents of the
proposal submitted by CONSULTANT (Exhibit "A"). In the event of conflict the requirements of
CITY'S Request for Proposal and this Agreement shall take precedence over those contained in
CONSULTANTS proposal.
2.
Timely Work. CONSULTANT shall perform all duties incidental or necessary in
a timely fashion; and shall be performed diligently, competently, and in accordance with
professional standards of performance. Failure to so perform is hereby deemed a material
breach of this Contract, and CITY may terminate this Contract with no further liability hereunder.
City may agree in writing with CONSULTANT to an extension of time. It is expressly agreed and
understood that CONSULTANT shall not be held responsible for delays occasioned by factors
beyond their control, nor by factors that could not reasonably have been foreseen at the time of
execution of this CONTRACT.
3.
Term. The work under this Contract shall commence upon the issuance of the
Notice to Proceed, and shall terminate 365 days thereafter. The parties may agree to extend or
amend this Contract prior to its expiration.
4.
Compensation. CITY shall pay CONSULTANT in an amount not to exceed
$6,350.00 which said sum shall include all costs, as presented in the proposal dated March 25,
2015 (Exhibit "A"), and in accordance with this Contract.
Compensation under this Contract shall become due and payable thirty (30) days
after CITY's approval of CONSULTANT'S submission of monthly written invoices. Written
invoices shall clear1y itemize each charge. The payment of any compensation to CONSULTANT
hereunder shall be contingent upon performance of the terms and conditions of this Contract to
the reasonable satisfaction of the City Administrator.
If the City Administrator determines that the work set forth in the written invoice
has not been performed in accordance with the terms of this Contract, CITY shall not be
responsible for payment until such time as the work has been performed to the reasonable
satisfaction of the City Administrator.
5.
Additional Services. In the event that CITY should request additional services
not covered by the terms of this Contract, said additional services and compensation shall be
agreed upon in advance and in writing by CONSULTANT and the City Administrator.
CONSULTANT shall not be compensated for any additional services unless such additional
services and compensation are approved by the City Council inasmuch as all contracts
exceeding $24,999.00 require City Council approval to be valid .

6.
Meet and Confer. CONSULTANT agrees to meet and confer with CITY or its
agents or employees with regard to services as set forth herein as may be required by City
Administrator to insure timely and adequate performance of this Contract.
7.
Suspension or Termination of Contract Without Cause. CITY may at any
time , for any reason , with or without cause, suspend or terminate this Contract, or any portion
hereof, by serving upon the CONSULTANT at least ten (10) business days prior written notice.
Upon receipt of said notice CONSULTANT shall immediately cease all work under this Contract
unless the notice provides otherwise. If CITY suspends or terminates a portion of this Contract
such suspension or termination shall not make void or invalidate the remainder of this Contract.
In the event this Contract is terminated pursuant to this section CITY shall pay
CONSULTANT the actual value of the work performed up to the time of termination provided
that the work performed is of value and approved by CITY. Upon termination of this Contract
pursuant to this section CONSULTANT will submit an invoice to CITY pursuant to section 4 of
this Contract.
8.
Default of CONSULTANT.
CONSULTANTS failure to comply with the
provisions of this Contract shall constitute a default. In the event that CONSULTANT is in
default for cause under the terms of this Contract, CITY shall have no obligation or duty to
continue compensating CONSULTANT for any work performed after the date of default and can
terminate this Contract immediately by written notice to CONSULTANT. If such failure by
CONSULTANT to make progress in the performance of work hereunder arises out of causes
beyond CONSULTANT'S control, and without fault or negligence of CONSULTANT, it shall not
be considered a default.
9.

Indemnification. CONSULTANT hereby agrees to the following indemnification

clause:
To the fullest extent permitted by law (including, without limitation, California Civil
Code Sections 2782 and 2782.6, if applicable), CONSULTANT shall defend (with legal counsel
reasonably acceptable to designated agents, departments, officials, representatives, and
employees, collectively "lndemnitees") from and against claims, loss, cost, damage, injury
expense and liability (including incidental and consequential damages, court costs, reasonable
attorneys' fees, litigation expenses and fees of expert consultants or expert witnesses incurred in
connection therewith and costs of investigation) to the extent they arise out of, pertain to, or
relate to, the negligence, recklessness, or willful misconduct of CONSULTANT, any subconsultant, anyone directly or indirectly employed by them, or anyone that they control
(collectively "Liabilities"). Such obligations to defend, hold harmless and Indemnify any
Indemnitee shall not apply to the extent that such Liabilities are caused in part by the negligence,
or willful misconduct of such Indemnitee.
Notwithstanding the provisions of the above paragraph, CONSULTANT agrees to
indemnify and hold harmless CITY from and against any and all claims, demands, defense costs ,
liability, expense, or damages arising out of or in connection with damage to or loss of any
property belonging to CONSULTANT or CONSULTANT'S employees, contractors,
representatives, patrons, guests or invitees.
CONSULTANT further agrees to indemnify CITY for damage to or loss of CITY
OF CARMEL-BY-THE-SEA property to the proportionate extent they arise out of
CONSULTANT'S negligent performance of the work associated with this Contract or to the

-2-

proportionate extent they arise out of any negligent act or omission of CONSULTANT or any of
CONSULTANT'S employees, agents, contractors, representatives, patrons, guests or invitees;
excepting such damage or loss arising out of the negligence of CITY.
10.
Insurance. CONSULTANT shall submit and maintain in full force insurance as
described herein. Without altering or limiting CONSULTANT'S duty to indemnify,
CONSULTANT shall maintain in effect throughout the term of this Contract, a policy or policies
of insurance with the following minimum limits of liability:
Commercial general liability insurance including but not limited to premises,
personal injuries, bodily injuries, products, and completed operations, with a combined single
limit of not less than $1,000,000 per occurrence and $2,000,000 in the aggregate.
Workers' Compensation Insurance If CONSULTANT employs others in the
performance of this Contract, CONSULTANT shall maintain workers' compensation insurance in
accordance with California Labor Code section 3700 and with a minimum of $100,000 per
occurrence for employers' liability.
Professional Liability Insurance. CONSULTANT shall maintain in effect
throughout the term of this Contract professional liability insurance with limits of not less than
$1,000,000 per claim and $2,000,000 in the aggregate. CONSULTANT will either maintain or
cause to be maintained professional liability coverage in full force or obtain extended reporting
(tail) coverage (with the same liability limits) for at least three (3) years following CITY'S
acceptance of work.
Commercial automobile liability insurance covering all automobiles, including
owned, leased, non-owned, and hired automobiles, used in providing services under this
Contract, with a combined single limit of not less than $1,000,000 per occurrence.
Other Insurance Requirements

A.

All insurance required under this Contract must be written by an


insurance company either:
1)
Admitted to do business in California with a current A.M. Best
rating of no less that A:VI;

Or
2)
An insurance company with a current AM. Best rating of no less
that A: VII
Exception may be made for the State Compensation Insurance Fund
when not specifically rated.
B.

Each insurance policy required by this Contract shall be endorsed to state


that CITY shall be given notice in writing at least thirty (30) days in
advance of any cancellation thereof, except CITY shall be given TEN (10)
days' notice for nonpayment of the premium.

C.

The general liability and auto policies shall:

- 3-

1)
Provide an endorsement naming CITY, its officers, officials, and
employees as additional insureds under an ISO CG 20 10 07 04 and ISO
20 37 07 04 or their equivalent.

2)
Provide that such insurance is primary and non-contributing
insurance to any insurance or self-insurance maintained by CITY.
3)
Contain a "Separation of Insureds" provision substantially
equivalent to that used in the ISO form CG 00 01 10 01 or their
equivalent.

4)

Provide for a waiver of any subrogation rights against CITY via an


ISO CG 24 01 10 93 or its equivalent.

D.

Prior to the start of work under this Contract CONSULTANT shall file
certificates of insurance and endorsements evidencing the coverage
required by this Contract with the City Administrator. CONSULTANT shall
file a new or amended certificate of insurance promptly after any change
is made in any insurance policy which would alter the information on the
certificate then on file.

E.

Neither the insurance requirements hereunder, nor acceptance or


approval of CONSULTANT'S insurance, nor whether any claims are
covered under any insurance, shall in any way modify or change
CONSULTANT'S obligations under the indemnification clause in this
Contract, which shall continue in full force and effect. Notwithstanding the
insurance requirements contained herein, CONSULTANT is financially
liable for its indemnity obligations under this Contract.

F.

Any deductible or self-insured retentions must be declared to and


approved by CITY. At the option of CITY either: the insured shall reduce
or eliminate such deductibles or self-insured retentions as respects CITY,
its officers, officials, employees, and volunteers; or CONSULTANT shall
provide a financial guarantee satisfactory to CITY guaranteeing payment
of losses and related investigations, claim administration, and defense
expenses.

11 .
Ownership of Work. Upon completion of the work under this Contract,
ownership and title to all materials and deliverables produced as part of this Contract will
automatically be vested in CITY and no further contract will be necessary to transfer ownership
to CITY. CONSULTANT shall not be held liable for any modification or re-use of CITY-owned
materials and deliverables for purposes outside their original intent.
12.
Licensing. CONSULTANT represents that it is properly licensed to perform the
work specified under this Contract, including but not limited to, possession of a current city
business license.
13.
Termination. This Contract may be terminated by either party upon thirty (30)
calendar day's written notice to the other party. In the event of such termination, CITY shall pay
CONSULTANT for all services performed in accordance with this Contract to the date of receipt
of notice of termination . An itemized statement of the work performed to the date of termination
shall be submitted to CITY. In ascertaining the services actually rendered hereunder up to the
-4-

date of termination of this Contract, consideration shall be given to both completed work and
work in process of completion, and to complete and incomplete drawings and other documents
whether delivered to CITY or in the possession of the CONSULTANT.
14.
Agency. In performing the services specified under this Contract, CONSULTANT
is hereby deemed to be an independent CONSULTANT and not an agent or employee of CITY.
15.
Authority of the City Administrator.
CONSULTANT shall perform all
necessary services provided under this Contract and outlined in the proposal and shall do,
perform, and carry out said work in accordance with this Contract as determined by and to the
reasonable satisfaction of the City Administrator. The City Administrator reserves the right to
make changes, additions or deletions, to the scope of work as deemed necessary or advisable to
implement and carry out the purposes of this Contract. The City Administrator is authorized to
execute change orders.
16.
Responsibility of Consultant.
By executing this CONSULTANT represents
and state to CITY that he/she possesses, or will arrange to secure from others, all necessary
professional capabilities, experience, resources and facilities necessary to provide to city the
services contemplated under this Contract. CONSULTANT further represents that he/she will
follow the current generally accepted practices of the profession to make findings, render
opinions, prepare factual presentations, and provide professional advice and recommendations
regarding the project for which services are rendered under this Contract.
17.
Materials and Equipment. CONSULTANT shall furnish at his/her own expense,
all materials and equipment necessary to carry out the terms of this Contract.
18.
Digital Files. CONSULTANT shall furnish copies of all deliverables on compact
disks (for example, final report) in digital format. Files shall be compatible with the current
versions used by PC computers.
Audit AuthoritY. CONSULTANT shall keep full and detailed accounts and
19.
exercise such controls as may be necessary for proper financial management under this
Contract; the accounting and control systems shall be satisfactory to CITY. CITY and CITY's
auditor shall be afforded access to CONSULTANT's records, books, correspondence and other
data relating to this Contract. CONSULTANT shall preserve these records, books,
correspondence and other data relating to this Contract for a period of four (4) years after final
payment or for such longer period as may be required by law. In addition, CONSULTANT agrees
to make said records, books, correspondence and other data relating to this Contract available to
CITY at CITY's principle place of business upon seventy-two (72) hours advance written notice.
The City Administrator, or his or her designee, shall at all times have the right to inspect the
work, services, or materials. CONSULTANT shall furnish all reasonable aid and assistance
required by CITY for the proper examination of the work or services and all parts thereof. Such
inspection shall not relieve CONSULTANT form any obligation to perform said work or services
strictly in accordance with the specifications of any modifications thereof and in compliance with
the taw.
20.
Notices. All notices herein provided to be given, or which may be given by either
party to the other, shall be considered fully received when made in writing and deposited in the
United States mail, certified and postage prepaid, and addressed to the respective parties as
follows:
CITY:

City of Carmel-by-the-Sea
- 5-

Public Works Department


Attention: Andy Vanderford
P.O. Box CC
Carmel-by-the-Sea California, 93921
CONSULTANT:

Skyline Engineering, Inc.


Attention: Bryan Schalesky, P.E.
8100 Wild Horse Road
Salinas California, 93907

21.
Entire Contract. This Contract constitutes the entire contract between the
parties hereto and supersedes any and all prior contracts, whether oral or written, relating to the
subject matter thereof. Any modification of this Contract will be effective only if it is in writing
signed by both parties hereto.
22.
Validity. If any provision in this Contract is held by a court of competent
jurisdiction to be invalid, void or unenforceable, the remaining provisions will continue in full
force without being impaired or invalidated in any way.
23.
Assignment of Interest. The duties under this Contract shall not be assignable,
delegable, or transferable without the prior written consent of CITY. Any such purported
assignment, delegation, or transfer shall constitute a material breach of this Contract upon
which CITY may terminate this Contract and be entitled to damages.
Conflict of Interest/Political Reform Act. CONSULTANT shall at all times
24.
avoid conflicts of interest, or the appearance of conflicts of interest, in the performance of this
Contract.
During the term of this Contract CONSULTANT shall not directly or indirectly,
either as a partner, employer, employee, consultant, principal, and agent or in any individual or
representative capacity, engage or participate in any business or voluntary activity on behalf of
any other party on any property located within the City of Carmel-by-the-Sea without notification
to City Administrator.
If CITY determines CONSULTANT comes within the definition of CONSULTANT
under the Political Reform Act (Government Code Sections 87100 et seq.) CONSULTANT shall
complete and file, and shall require any other person doing work under this Contract, to
complete and file a "Statement of Economic Interest" with CITY disclosing CONSULTANT'S
and/or such other person's financial interests.
25.
Non-discrimination/Affirmative Action. CONSULTANT will not discriminate
against any employee or applicant for employment because of race, creed, color, sex, age,
national origin, marital status, physical or other motor handicap, unless based upon bonafide
occupational disqualification.
CONSULTANT will take affirmative action to ensure that applicants are employed
and that employees are treated during employment without regard to their race, creed, color,
sex, age, national origin, marital status, physical or other motor handicap.
Counterparts. This Contract may be executed in multiple originals, each of
26.
which is deemed to be an original , and may be signed in counterparts.
-6-

27.
Laws. CONSULTANT agrees that in the performance of this Contract it will
reasonably comply with all applicable state, federal and local laws and regulations. This
Contract shall be governed by and construed in accordance with the laws of the State of
California and the City of Carmel-By-The-Sea.

28.
Attorneys Fees and Court Venue. Should either party to this Contract bring
legal action against the other, (formal judicial proceeding, mediation or arbitration), the case
shall be handled in Monterey County, California, and the party prevailing in such action shall be
entitled to a reasonable attorney's fee which shall be fixed by the judge, mediator or arbitrator
hearing the case and such fee shall be included in the judgment, together with all costs.
29.
Severabllltv. If any term of this Contract is held invalid by a court of competent
jurisdiction, the remainder of this Contract shall remain in effect.
IN WITNESS WHEREOF, this Contract is entered into by the parties hereto in Carmel,
California, on the day and year first written above.

By:
Its:

CONSULTANT
By:
Its:

By:
Its:

City Cieri<

-7-

CITY OF CARlvtEL ..BY..THB-SEA


UCE~SE

ORIG.

'J]{A~S.

REF.

TA..X REGISTRATION CERTIFICATE


CODE REF.

CL-\SS

_x OF BUSINESS: ____ --- 5.04..140 ----G---n1'E

DATE ISSCED

09110/14

:------~

ENGINEERING

LOCATION:

.
[ No.

-~--

--

l
24430
-

E"Xpircs:

SKY0003

8711
O\VNER1

B./JJN. SCHALESKV
DBA:
MAILING

ADDRE;:;;~:

I::~C.\XCE

SKYLINE ENGINEERING INC


8100 \VILD HORSE RD
SALINAS, CA 93907

!
I

09/09/15 -<---__]

SIC~

ID::

VAUDATED:

?)x'tW-a0
Cit\' Clerk

OF TIHS UCE::--:SE DOES ~OT GR.r\~1 COMJ'IJA:-.:CE \\'ITH fu~Y OTHER STATE LA\V OR Cln ORDtN1\l"C

THE ~H)N'ICIPAL CODE REQUIRES CONSPICIOUS DISPlAY OF TIHS LICE~SE

ACORD

CERTIFICATE OF LIABILITY INSURANCE

DATE (r.uNDDIVYYY)
9/9/2014

THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFARMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to
the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certiricate does not confer rights to the
certificate holder in lieu of such endorsement(s) .
PRODUCER

~~~CT

Pinnacle Risk Solutions

fl~NJ~

I r~. Nol: (973) 284-1655

"vn (973)284-0100

11=~~.

82 Old Bloomfield Ave

INSURERISl AFFORDING COVERAGE

NJ

Pine Brook

07058

NAIC#

INSURER A :Hall & Company .

INSURED

INSURER B :
Inc

skyline Engineering,

INSURER C:

8100 Wild Horse Road

INSURERO :
INSURER E:
CA

Salinas

9390'7

INSURER F :

CERTIFICATE NUMBER14-15 GL
REVISION NUMBER
COVERAGES
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR lHE POLICY PERIOD
INDICATED. N01WITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCWENT WTH RESPECT TO w-IICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, TliE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOW~! MAY HAVE BEEN REDUCED BY PAID CLAIMS.
POLICY EFF
POLICY E.XP
LIMITS
TYPE OF INSURANCE
POUCY NUMBER
r.i.l.:.> lwvr.
[l~~:

--

GENERAL LIABLITY

COMMERCIAL GENERAL LIABILITY

1-f---

CLAIIoiS.MADE

~/11/2014

~B0-9637M280-TIL-13

OCCUR

~/ll/2015

1--

GEN'L AGGREGATE LIMIT APnS PER

rxl' POLICYO~&
-

HIRED A\JTOS

300,000

MED E.XP (Any one person)


PERSONAl

2,000,000

&

ADV INJURY

r - SCHEDULED
AUTOS
f--- NON-OWNED
AliTOS

GENERAL AGGREGATE

4,000,000

4,000,000

's

BOOILY INJURY (Per accident) S


"!!Df'ER'f'i']:5AM~

EACH OCCURRENCE

Per acadenl

1--

EJ(CESS UAB

5,000

PRODUCTS- COMP/OP AGG

BOOILY INJURY (Per pe,on)

UMBRELLA LIAB

1--

2,000,000

s
s

~~~~nSING(E lllillT

'---

~~~~~i?e~=~encel

LOC

AUTOMOBILE LIABIUTY
ANY AUTO
All 0'1\'NED
AUTOS

EACH OCCURRENCE

HOCCUR
CLAIMS.MAOE

AGGREGATE

I I

RETENTIONS
OED
lo\IORI<ERS COMPENSATION
ANO EMPLOYRS' UABIUTY
V/N
ANY PROPRIETOR/PARTNER/EXECUTIVE
N/A
OFFICER/MEMBER EXCLUDED?
(Mandalol)l In NH)

E L. DISEASE EA EMPLOYEE $

g~~~~~i~ ~'gPERATIONS t>elow

EL

~T~!f~g;.]

jOJt

E.L. EACH ACCIDEilT


DISEASE - POLICY LIMIT

DESCRIPTION OF OPERATIONS/ LOCATIONS /VEHICLES (AnacM ACORD 101 , AddiUonal Remarks Schedule , If more space Ia required)
The City of Carmel by the Sea, its officers, officials and employees shall be named as additional insured
as per writen contract.
waiver of Subrogation applies as per written contract.

CANCELLATION

CERTIFICATE HOLDER

City of Carmel by the Sea


PO Box
93921
Cannel by the Sea, CA

cc

SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE


THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIV~ED IN
ACCORDANCE WITH THE POLICY PROVISIONS.
AUTHORIZED REPRESENTATIVE

M
ACORD

25 (2010/05)

INS025 !201005) 01

30 days written notice of cancellation applies.

Caradimitropoulo/JP

<

.:;;;;;:::

1988-2010 ACORD CORPORATION. All nghts reserved.


The ACORD name and logo are registered marks of ACORD

POLICYHOLDER COPY

NG

STATE: ,!
~ OM .... ':':V~ATil,l\=

P.O. BOX 8192, PLEASANTON, CA 94588

.F.ugNo
t
-- -

CERTIFICATE OF WORKERS' COMPENSATION INSURANCE

ISSUE DATE:

GROUP:
1595532-2014
POLICY NUMBER:
CERTIFICATE ID:
139
CERTIFICATE EXPIRES: 09-01-2015
09-01-2014/09-01-2015

09-09-2014

CITY OF CARMEL BY THE SEA


PO BOX CC
CARMEL BY THE SEA CA 93921-1757

NG

This is to certify that we have issued a valid Workers' Compensatton insurance policy in a form approved by the
California Insurance Commissioner to the employer named below for the policy period indicated.
This policy ts not subject to cancellation by the Fund except upon 30 days advance written notice to the employer.
We will also give you 30 days advance notice should this policy be cancelled prior to its normal expiration.
This certificate of insurance is not an insurance policy and does not amend, extend or alter the coverage afforded
by the policy listed herein. Notwithstanding any requirement, term or condition or any contract or other document
with respect to which this certificate of insurance may be issued or to which it may pertain, the insurance
afforded by the policy described herein is subject to all the terms, exclusions. and conditions, of such policy.

~tl-6?1'

!L~ xll~~

Authorized Representative

President and CEO

EMPLOYER'S LIABILITY LIMIT INCLUDING DEFENSE COSTS:

PER OCCURRENCE.

$1,000,000

ENDORSEMENT

#1600-

BRYAN SCHALESKY PRES,TRES,SEC- EXCLUDED.

ENDORSEMENT

#1600 -

JUSTIN SCHALESKY VP - EXCLUDED .

ENDORSEMENT #2065 ENTITLED CERTIFICATE HOLDERS' NOTICE EFFECTIVE


ATTACHED TO AND FORMS A PART OF THIS POLICY.

09-01-2004

IS

EMPLOYER

SKYLINE ENGINEERING, INC


8100 WILD HORSE RD
SALINAS CA 93907

NG

[P13,NG]
(REV.7 - 20141

PRINTED

09-09-2014

t~...)

DATE OF NOTICE

000 Old Ri>'tll Rosd


CA !133115501

APR 08 2013

CODE

E~A-.rr;~I(J

17BA

All

02

A
llf<?l.t

).~;J

NOTE: PLEASE NOTIFY STATE FARt.~ AT THE


ADDRESS LISTED AT THE TOP, LEFT CORNER
OF THIS PAGE REGARDING ANV CHANGE OF
ADDRESS INFORMATION.

SKYLINE lHGINEERING
8100 WILD HORSE RD
~:~

SALINAS CA

939079223

j"ADOJTIONAL INSURED'S NOTICE OF COVERAGE


2833-FBFF'-J

Stale Farm Mutul Automobile Insurance Compnny


NAMED INSURED:
:

SCHALEBKY, BRYANJ & MARLO M

~ 81DO WILD HORSE RO

SAUNAS CA 93907922~

Jij

POLICY NO;
YRIMAKEIMOOEL:
VINICAMPER:
AGENT NAME:
AGENTPHONE:
ENDORSEMENT NO:

151 715!i-00305L
2006 TOYOTA 401'1
4T1BJ<J6856U164427
KEN FELS
(408)7794186
6028BU

COVERAGE:

e ,.. rm'"')L".Pll.l;,

i'l'l,
~

wo or~

f ;'5:J 1>!::;)

C~'-'~

('!.}l..(

POLICY EFFECTIVE
APR 03 2013 UNTIL TERMINATED

POLJC Y t.U.SSAGES: 'Thll poiiO'J anown Abo.., auperndee pollc)'f 151 715~05K
i h~ pc;hcy Include ~ loar poy&ble duuoe proll>cUne lho oddibonal ineur&darnterul rn lhe aeconbed Q;lr to lht ulenl

of'""

rnoumnoe
" proJKII!d ~nd aubjt>CIIo &li policy piDYIIIOna Tho odaobon~lonaunod will be giVIIn 20 ~~ no~ce If tno policy II terminated . UnUituoh not~e
.,; "proVIded, ott hall b pr~1urnod lho11he '"""'~ ren-~t pren'llun no"" beon paid Tlw addolionol inaultld mull notry ua wll!\in 10 ""Y" "'
~ nny change- of 1ntereet or own~I'Jhlp com~ng to thetr llUanlon FIIJ.Iure to dO ao ..n r.ncr tt\11 pohcy null and votd

ACORD@,

DATE(MMIDOIYYYY)

CERTIFICATE OF LIABILITY INSURANCE

3/3/2015

THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to
the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the
certificate holder in lieu of such endorsement(s).

~~~lc Dana Dasaro

PRODUCER

82

I Ftfc. No: (973) 2Bt-1655

r~N:ft ~~ (973)284-o1oo

Pinnacle Risk Solutions

l~o~ss:

Old Bloomfield Ave

INSURER($) AfFORDING COVERAGE

NJ

Pine Brook

07058

NAICII

INSURER A :Ll oyds

INSURED

INSURER B:

Skyline Engineering, Inc


9100 Wil.d Horse Road

INSURERC:
INSURERD:
INSURER E:

93907

CA

Salinas

INSURER F:
CERTIFICATE NUMBER15-16 E&O
REVISION NUMBER
COVERAGES
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. N01WITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WiiCH THIS
CERTlFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.

~~::

TYPE OF INSURMICE
GENERAL LIABILITY

IJNSR IWVD

POUCV

HUMBER

c,:OMM~~ 'c,:O"-K?r EXJ>

I-COMMERCIAL GENERAL LIABIUTY


I-CLAIM5-MAOE
OCCUR
I--

--

~~~~~~?E:~~nce

MEO EXP (Any one person)


PERSONAL & AOV INJURY

GEN'L AGGREGATE LIMIT APnS PER


~-POliCY n~&
Lot
AUTOMOBILE LIABLrrY
1-ANY AUTO
I-- ALL OWNED
;-- SCHEDULED
AUTOS
AUTOS
1-NON-OWN EO
HIRED AUTOS
AUTOS

EXCESS

UAB

GENERAL AGGREGATE

s
1S

BOOIL Y INJURY (Per person)

BOOIL Y INJURY (Per accident)

r~~~J.:;~MAGE
1

EACH OCCURRENCE

HOCCUR
CLAIMS-MADE

AGGREGATE

OED I I RETENTION s
WORKERS COMPENSATION
AHD EMPLOYERS' UABJLITY
YIN
A~ PROPRIETOR/PARTNER/EXECUTIVE
H/A
OFFICER/MEMBER EXCLUDED?
(Mandatory In NH)

IT~.nfli#s I
E.L EAOi ACCIDENT

Errors & omissions

IOJ~

E L DISEASE EA EMPlOYEE

~~~:ti~ ~~PERATIONS below


A

s
s

-----

UMBRELLA UAB

s
s

PRODUCTS COM PlOP AGG

I ~~~~n"'""'Lt LIM I

1--

LIMITS
EACH OCCURRENCE

s
$
$

E L DISEASE POLICY LIMIT s


!INE10B7264.14

/B/2015

/B/2016

Lim1l of LlablbJy Per Claim


Lim~

$1,000,000

ol Llatxllty A990f"'jate

$2,000,000

DESCRIPTION OF OPERATIONS I LOCATIONS I VEHICLES (Attach ACORD 101, Addhlonal Re"'arks Schedule, If "'on: space Is n:qulred)

CERTIFICATE HOLDER

Evidence of Insurance

CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS.
AUTNOR~DREPRESENTATNE

~ Caradimitropoulo/JG

ACORD 25 (201 0/05)


INS025 (201005) 01

:s:: c:

--=

1988-2010 ACORD CORPORATION. All rights reserved.


The ACORD name md logo are registered marks of ACORD

COMMERCIAL GENERAL LIABILITY

Policy Number: 680-9637M280-TIL-13

THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

BLANKET ADDITIONAL INSURED


(ARCHITECTS, ENGINEERS AND SURVEYORS)
This endorsement modilles insurance provided under the following:

COMMERCIAL GENERAL LIABILITY COVERAGE PART


A. The following is added lo WHO IS AN INSURED
(Section II):

INSURANCE (Section lll) for this Coverage


Part.

Any person or organization that you agree In a


contract Of agreement requiring insuranCe" to indude as an additional insured on this Coverage
P&rt, but only with respect to liability for "bodily injury", 'property damage or 'personal 1njury'
caused, in whole or in part, by your acts or omissions or the acts or omissions of !hose acting on
your behalf:

B. The fcllowing is added to Paragraph a. of 4.


other Insurance In COMMERCIAL GENERAL
LIABIUTY CONDJnONS (Section IV):

However, if you specifically agree in a 'contract or

b. In connection With premises owned by or


rented to you; or

agreement requiring insurance that the insuranci!


provided to 11n additional insured under this Coverage Part must apply on a primary basis, or a
primary and non-contributory basis. this insurance
is primary to other insurance that is available to
such additional insured which covers such additional insured as a named insured, and -we will not
share with the other insurance, provided that;

In connection wilh "your woric" and included


Within the 'products-completed operations

(1) The "bodily injury' or "property damage for


whch coverage is sought rx;curs; and

hazard".

(2) The personal injury ror which coverage is


sought arises out of an offense committed;

a.

In the perlormance of your ongoing opera-

tions;

c.

Such person or organization does not qualify as


an additional Insured for 'bodDy injury, "property
damage or "personal injury for which that person or organization has assumed liab~itY in a contract or agreement.

The insurance proVided to such additional insured


is limited as follows:
d. This 1nsurance does not apply on any basis to
any person or organization for which coverage as an additional insured specifically is
added by another erdorsemenl to this Coverage Part.

e.

This insurance does not apply to the rendering of or faaure to render any 'professional
services' .

f.

The limits of insurance afforded to the addJ!Jonal insured shall be the limits which you
agreed in that "contract or agreement reQuiring insurance to provide for that additional
insured. or the limits shown in the Dedarations for this Coverage Part, whichever are
!es.s. This endorsement does not increase the
limits of insurance stated in the UMITS OF

CG 03 81 09 07

after you have entered into that "contract or


agreement requiring insurance. But this insurance still is excess over valid and COllectible other
insurance, whether primary. excess, contingent or
on any other basis, tnat is available to the insured
when the insured is an additional iflSUI'ed under
any other insurance.

C. The following is added to Paragraph 8. Transfer


Of Rights Of RKOVety Against others To Us

m COMMERCIAL GENERAl UABIUTY CON


DITIONS (SecUon IV):
We waive any rights or recovery we may have
against any person or organization because of
payments we make for "bodily Injury, "property
damage" or "personal injury" arising out of your
wori\" performed by you, or on your behalf, under
a "contract or agreement requiring insurance With
that person or organization. We waive !hese
rights only where you have agreed to do so as
part of the contrae1 or agreement requinng insurance with such person or organization entered
into by you before, and in effect when, the "bodily

. ~ 2007 The Tr.;weleJS Compames. Inc


lnc::luaes the copynghled marenal of Insur-ance SeMces Ort.ce, Inc. Wllh ols P""'"uoon

Page I or 2

fif1

602BBU ADDITIONAL INSURED


(Prior Notice of Termination)

This endorsement is a par1 of the policy. Except for the changes this endorsement makes, all other
provisions of the policy remain the same and apply to this endorsement.

A person or organization shown on the Declar!!lions Page as an Additional Insured is provided


Liability Coverage, bur only to the extent that person or orgnnizotion qualifies as an insured as
defined in Liability Coverage.
2. An Additional Insured has the same right of recovery under Liability Coyeragc as if they had
not been shown on the Declarations Page RS nn Additional Insured.

3. If Linbility Coverage is changed or terminated AS to the interest of' the Additional Insured. unless another mlmbcr of days notice Js shown on the Decimations Page, wa will provide the Ad~
ditionallnsured:
a. I 0 days notice of such change or terminatior. if the policy is non renewed or the cancellation is for nonpnyment of premium: and
b. 20 days no rice of s\lch change or tenn ination if the cancellation is for any reason ocher than
nonpa)ment of premium.
1.

~.

Page I of I
C<pyright, Stale Fnnn MuiUill Au1omobile lm:umncc Company, 20 II

60288U

COMMERCIAL GENERAL LIABJUTY

injury" or "property damage ocetJrs, or the per


sonal injury" offense is committed.
D. The ronowing definition is added to DEFINITIONS
(Section V}:

emge Part, provided ll'lal !he 'bodily injury and


"property damage occur$, and tho 'personal injury" is e<~used by an offense commfUed:
a.

After you have entered Into lhat contract or


agreement;

b.

While thai part of the contract or agreement Is


in effect, and

c.

Before the end or the policy period.

'Contract or agreement requiring insurance


means that pa11 of any contract or .agreement under which you are required to lndude a per50n or
organization ~s an additional Insured on this Cov-

P~ge

2 of 2

tl2007 rhe Truvtl&r\ Con>pnles, Inc.


InCludes lhtl COPY"!JII~d rnolorial of tn~ul':lnCCI St>~lice& Office, Inc . wilh n~ p~mllsion

CG 03 81 09 07

lr&U ,._.

CERTIFICATE OF INSURANCE

SUCH INSURANCE AS RESPECTS THE INTEREST OF THE CERTIFICATE HOLDER NAMED BELOW WILL NOT BE
CANCELED OR OTHERWISE TERMINATED WITHOUT GIVING 10 DAYS PRIOR WRITIEN NOTICE TO THE
CERTIFICATE HOLDER, BUT IN NO EVENT SHALL THIS CERTIFICATE BE VALID MORE THAN 30 DAYS FROM
THE DATE WRITTEN. THIS CERTIFICATE OF INSURANCE DOES NOT CHANGE THE COVERAGE PROVIDED BY
ANY POLICY DESCRIBED BELOW.
This certifies that:

[8J

STATE FARM
STATE FARM
STATE FARM
STATE FARM
has coverage in force for lhe following
NAMED INSURED:

0
0
0

MUTUAL AUTOMOBILE INSURANCE COMPANY of Bloomington, Illinois


FIRE AND CASUALTY COMPANY of Bloomington, Illinois
COUNTY MUTUAL INSURANCE COMPANY OF TEXAS of Dallas, Texas , or
INDEMNITY COMPANY of Bloomington, Illinois
Named Insured as shown below:

SCHALES!<Y, BRYAN & MARLO


8100 WILD HORSE RD, SALINAS, CA 9390'1-9/.23

ADDRESS OF NAMED INSURED:


POLICY NUMBER
EFFECTIVE DATE
OF POLICY
DESCRIPTION OF
VEHICLE (Including VIN)

1~1

11~9-D03-05G

4/3/15-04/03/16
06 TOY AVALON

~~TBK36B66U164427

LIABILITY COVERAGE

~YES

LIMITS OF LIABILITY
a. Bodily Injury
Each Person

1,000,000

ONO

DYES

DNO

DYES

ONO

DYES

ONO

ONO
Deductible

DYES

ONO
Deduclible

DYES

DNO
Deductible

DYES

DNO
Deductible

Each Accident
b. Property Damage
Each Accident
c. Bodily Injury &
Property Damage
Single Limit
Each Accident
PHYSICAL DAMAGE
COVERAGES
a. Comprehensive

$ 100

b. Collision

$ 250

DNO
Deductible

DNO
Deductible

DNO
Deductible

DNO
Deductible

DYES

181 NO

DYES

DNO

DYES

DNO

DYES

DNO

DYES

~NO

DYES

DNO

DYES

DNO

DYES

DNO

DYES

181 NO

DYES

DNO

DYES

DNO

DYES

DNO

1,000,000
~YES
~YES

EMPLOYERS NON-OWNED
CAR LIABILITY COVERAGE
HIRED CAR LIABILITY
COVERAGE
FLEET- COVERAGE FOR
ALL 0\t\NED AND UCENSED
MOTOR VEHICLES

DYES

AGENT
Signature of Authorized Representative
Name and Address of Certificate Holder
Add'! Insured:

CiLy of Carmel by the Sea


PO Box CC
Carmel by the Sea CA 93921

DYES

DYES

05/2833

Title
Agent's Code Number
Name and Address of Agent
STATE FARM
AGENT , KEN FELS, Agent
Auto-Life-Health-Home and Business
16360 Monterey St. Ste 270
Morgan Hill, Ca 95037
(408)779-4186 Fax (408)778-5757

INTERNAL STATE FARM USE ONLY: 181 Request permanent Certificate of Insurance for liability coverage .

03/13/2012
Date

1224:?9.2 Rev. 06-10.2004

181 Request Certificate Holder lobe added as an Additional Insured.

TRAVELERSJ

One Tower Square, Hartford, Connecticut 061 83


RENEWAL CERTIFICATE
POLICY NO.: 680-963 7M280 -'I'CT-14
ISSUE DATE: 07-30-14

COMMON POLICY DECLARATIONS


OFFICE PAC

BUSINESS: ENGINEERS
INSURING COMPANY:

THE TRAVELERS INDEMNITY COMPANY OF CONNECTICUT


1. NAMED INSURED AND MAILING ADDRESS:
SKYLINE ENGINEERING, INC
8100 WILD HORSE ROAD
SALINAS

CA

2. POLICY PERIOD: From 09-11-14

93907

to 09-11-15

3. LOCATIONS:
BLDG.
OCCUPANCY
PREM .
NO.
NO.
01
01
ENGINEERS

12:01 A.M. Standard Time at your mailing address .

ADDRESS (same as Mailing Address


unless specified otherwise)
8100 WILD

HORSE ROAD

SALINAS

4.

CA

9390'1

COVERAGE PARTS AND SUPPLEMENTS FORMING PART OF THIS POLICY AND INSURING
COMPANIES:
COVERAGE PARTS AND SUPPLEMENTS
Businessowners Coverage Part

INSURING COMPANY

TCT

5.

The COMPLETE POLICY consists of this declarations and all other declarations. and the forms and endorsements for which symbol numbers are attached on a separate listmg.

G.

SUPPLEMENTAL POLICIES: Each of the following is a separate policy containing its complete provisions.
POLICY

POLICY NUMBER

INSURING COMPANY

DIRECT BILL
7.

PREMIUM SUMMARY:

$
$
$

Provisional Premium
Due at Inception
Due at Each

NAME AND ADDRESS OF AGENT OR BROKER

HALL\MICHAEL J\& COMPANY


AVE NE

COUNTERSIGNED BY

CPC98
Aulhonzed Representative

19660 lOTH
POULSBO

IL TO 25 08 01 (Page 1 of 01)
Office: SPECIALIST A&E

WA

DOWN

9 83 7 0

DATE:

TRAVELERSJ

One Tower Square, Hanford, Connecticut 06183

BUSINESSOWNERS COVERAGE PART DECLARATIONS


POLICY NO.: 6B0-9637M280-TCT-14
ISSUE DATE: 07-30-14

OFFICE PAC

INSURING COMPANY:
THE TRAVELERS INDEMNITY COMPANY OF CONNECTICUT
POLICY PERIOD:
From 09-11-14 to 09-11-15 12:01 A.M. Standard Time at your mailing address.
FORM OF BUSINESS:

CORPORATION

COVERAGES AND LIMITS OF INSURANCE: Insurance applies only to an item for which a
"limit" or the word "includeda is shown.
COMMERCIAL GENBRAL LIABILITY COVERAGE
LIMITS OF INSURANCE
OCCURRENCE FORM
4,000,000
General Aggregate (except Products-Completed Operations Limit)
$
4,000,000
Products-Completed Operations Aggregate Limit
$
2,000,000
Personal and Advertising Injury Limit
$
2,000,000
Each Occurrence Limit
$
300,000
Damage to Premises Rented to You
$
Medical Payments Limit (any one person)
5,000
$
BUSINESSOWNERS PROPERTY COVERAGE
DEDUCTIBLE AMOUNT:

Businessowners Property Coverage:


Building Glass:

$
$

1,000 per occurrence.


1,000 per occurrence.

BUSINESS INCOME/EXTRA EXPENSE LIMIT:

Actual loss for 12 consecutive months

Period of Restoration-Time Period:

Immediately

ADDITIONAL COVERAGE:
Fine Arts:

other additional coverages apply and may be changed by an endorsement.


read the policy.

SPECiAL PROVISIONS:

COMMERCIAL GENERAL LIABILITY COVERAGE


IS SUBJECT TO A GENERAL AGGREGATE LIMIT
MP TO 01 02 05

(Page 1 of 02)

Please

I.

[~

8100 Wild Horse Road


Salinas CA 93907
p 831.663.6188
F 831.663 .6187

March 25, 2015


Andy Vanderford
City of Cannel by the Sea
PO Box CC
Carmel by the Sea CA 93921
The following is a proposal for design and project inspections for the planter waterproofing project
at the Admin building. The project will involve the following :

1. Two planters shall be addressed.


2. Removal of existing fill and waterproofing membrane .
3. Clean and prep surface to receive new waterproofing system.
4. Restore any electrical to original.
5. Restore irrigation to original.
6. Our scope will not include any landscaping.
Engrneenng d es1gn & projec serv1ces
TASK
FEE
Haz mat sampling of existing planter membrane and drainage pipes .
$500
Provide written specifications for the following sections:
1. 002400 Procurement Scope of Work
$1,900
2. 024119.13 Selective Building Demolition
3. 071300 Sheet Waterproofing (planter waterproofing system)
Provide the following drawings on 8.5X11 :
1. Site plan drawing
2. Detail drawings of membrane
If lead and/or asbestos is present. Include sections 028200 Asbestos Remediation $1,500
and/or 028300 Lead Remediation. Haz mat testing for this facility is under a different
proposal.
Attend pre-bid meeting with contractors.
$350
Provide consulting services during pre-construction meeting.
$350
Provide quality assurance site visits during the project. Estimated 3 sile visit for this
project at $350 each.
$1,050
Provide final punch list.
$450
Time for any items not listed above. Billed at hourly rates not to exceed.
$250
TOTAL NOT TO EXCEED $6,350
.'
Services provided under th1s contract are limited to those spec1f1cally listed above. Structural and
electrical engineering is not part of this contract. Landscape engineering is not included.
This proposal shall be valid for a period of 30 days.
Sincerely,

-~i?Ef??-

Bryan Schalesky, P.E.


Skyline Engineering

Email: bryan@skylineengineering .com- www .skylineengineering.com

City ofCarmel-by-the-Sea
PUBLIC SERVICES DEPARTMENT
POST OFFICE BOX CC
CARMEL-BY-THE-SEA, CA 93921
(831) 620-2070 OFFICE
(831) 624-2132 FAX

October 9, 2014

SENT VIA E-MAIL

REQUEST FOR QUALIFICATIONS


THE CITY OF CARMEL-BY-THE-SEA IS INVITING CONSULTANTS TO SUBMIT
"STATEMENTS OF QUALIFICATIONS" (SOQs) FOR ROOFING I
WATERPROOFING CONSULTING
SERVICES FOR VARIOUS PROJECTS ON AN AS-NEEDED I ON-DEMAND BASIS

I. Introduction
The City of Carmel-by-the-Sea Public Services Department (City) is requesting SOQs
from qualified Roofing I Waterproofing consulting firms to provide consulting services for
various types of construction and maintenance projects on an as-needed I on-demand
basis.
11. Synopsis of Scope of Services
The City is seeking Roofing I Waterproofing consultants for various construction and
maintenance projects over the next two (2) years whom can provide comprehensive fullservice consulting services. Consultant services may include but are not limited to the
following:
1. Project design which may include; planning, estimating, and preparation of
phased designs (schematic, design development and construction documents).
Construction projects typically range in estimate from $1,000 to $250,000.
2. Processing construction documents through all applicable permitting agencies.
3. Participation during bidding, which may include; pre-bid meetings, bid questions,
addendums, evaluation of bids, etc.
4. Construction administration which may include; Requests for Information, project
meetings, inspections, punch lists, close-out reports, etc.
5. A wide range of projects for the repair or improvements to various city owned
facilities is anticipated, such as: Building remodels. Re-roofs or major
maintenance. New or modifying HVAC systems. Roof I Waterproofing
evaluations & remedies. Etc.
If your firm is interested then please submit two (2) copies of your SOQs by October 22,
2014 at 4:00PM, which includes the following information:
1. Overview of the consultant.
2. Summary of the consultant's project experience within the last five years within
the relevant discipline(s), including references.
3. Resumes for the Project Manager(s) and key staff relevant to project experience.
The SOQs shall not exceed 20 single sided pages.
Page 1 of 3

April 22, 2015

All firms or individuals interested in responding to this Request for Qualifications shall
do so by submitting two (2) copies of their SOQs by October 22, 2014 at 4:00PM to
the following location:
City of Carmel-by-the-Sea
Attention: Andy Vanderford
Public Services Department
Post Office Box CC
Carmel-by-the-Sea CA, 93921
Hand-in submittals may be delivered to Carmel-by-the-Sea City Hall.
Ill. Schedule to select consultants:
The tentative schedule for selecting consultants is as follows:
SOQs submitted to City by 4:00 PM on October 22, 2014.
Optional interviews of candidates by October 29, 2014.
Notify selected consultants by October 31, 2014.
IV. Consultants selection policy & process:
Consultant selection shall be in accordance with City's consultant selection
policy.
The City reserves the right to make the consultant selection based on any
factors, whether quantitatively and/or qualitatively identifiable or not.
The City reserves the right to choose the scope of services which may be
assigned to the consultant.
The City may select one or more consultants within each discipline in meeting
the interest of the City.
The City reserves the right to define and/or redefine the scope of services
through amendments to an Agreement.
The City reserves the right to select consultants and /or assemble selected
consultants into implementation teams as it sees fit.
This solicitation for SOQs does not commit the City to enter into a contract.
This solicitation for SOQs does not commit the City to pay any costs incurred by
a consultant in the preparation of their SOQs.
The City reserves the right to accept or reject any SOQs, or to cancel in part or in
its entirety this solicitation for SOQs.
The City reserves the right to re-advertise for consulting services at any time in
this process.
Consultants may propose on some or all of the areas of expertise within a
discipline.
The scope of services and fee will be negotiated for each individual project under
a base Agreement. The aggregate sum of fees for all projects performed under a
base Agreement shall not exceed $25,000.

Page 2 of 3

April 22, 2015

V. Award of an Agreement
A City of Carmel-by-the-Sea "Professional Services Agreement" will be
developed and administered for the base Agreement, and applicable portions of
the same may be used for each project that arises. Refer to attachment.
A base Agreement will typically be executed once negotiations have been
successful and a consultant is approved for award of the Agreement.

Sincerely,

~c~r 1/~k}o~rt
Andy Vanderford
Project Manager
City of Carmel-by-the-Sea
Public Services Department
Office: 831-620-2078
avanderford@ci. carmel. ca. us

C:

Sharon Friedrichsen, Director

Attachments:

Page 3 of 3

Professional Services Agreement

April 22, 2015

. i

8100 Wild Horse Road


Salinas CA 93907
p 831.663.6188

N G

I N G

F 831.663.6187

October 16, 2014


City of Carmel-by-the-Sea
Attention: Andy Vanderford
Public Services Department
Post Office Box CC
Carmel-by-the-Sea CA, 93921

Andy,
Thank you for giving us consideration for Roofing/Waterproofing Engineering
Services for your City. We ask that you keep this information close-held as
confidential proprietary information in compliance with the Public Records Act of
California especially reference lists with contact names and phone numbers.
Skyline Engineering, Inc. has been in business since 1998. Our firm specializes
in engineering and consulting services for the building envelope (roofing,
waterproofing, walls, below grade, etc.) as well as roof mounted mechanical
equipment. We also provide haz mat consulting, testing and engineering
services for the same building components as listed above. Below are some of
the services we provide:
1. Initial
evaluation
of building
envelope
components.
Provide
recommendations for repair or replacement including engineer's estimates
of recommended work.
2. Engineering design services: Planning, estimating, and preparation of bid
documents and CAD drawings. Consulting during any permitting process
necessary.
3. Construction management services including assembling bidders lists,
conducting pre-bid meetings, pre-construction meetings, quality control
inspections, and final inspection. Provide RFI responses during entire
process.
Skyline is independent of any and all material manufactures and contractors and
does not receive benefits from the use of any particular brand or contracting firm.
Skyline is certified by the DGS (Department of General Services) Small Business
and DVBE Services (registration #0018468).
We work primarily with public agencies such as school districts, colleges,
universities, and city/county governments.
--

-:~..~:

;:

-.-.:.:;;~-

H - - - - -
--.-. :_ ,.

-- - - - - - - - -

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

Skyline Engineering

Page 2

PROJECT EXPERIENCE
Please refer to attached reference list for specific projects. Projects are listed by
name along with responsibilities that were assumed by our firm .
I am confident that few local engineering firms have more experience working
with public agencies than Skyline Engineering. We are currently working with
four city governments and have worked with many others in the past. We work
with about ten public schools, three college districts, and two universities. County
of Monterey is our client as well.

PROJECT TEAM
1 shall be the principal in charge as well as project manager for all work
performed under this contract. Nathan will be heading up any haz mat testing
and removal design. Mike Perry, Director of Quality Control will manage site
inspections during ongoing projects. Any of us can be available to handle all
requests and tasks for the City. If structural engineering is needed, we will work
with one of several local registered engineers as a sub-constultant.

Special Note: Some firms will respond to this RFQ using resumes and
qualifications for their principals that are very impressive. However, you will likely
not work with the principal engineers. Rather, you will be working with newer less
experienced people in their organization who have no ownership or personal
liability. With Skyline Engineering you will be working directly with me. I am the
owner and principal registered engineer for our firm.

PROFESSIONAL QUALIFICATIONS AND EXPERIENCE


PLEASE REFER TO THE RESUMES & BIOGRAPHIES OF OUR PERSONNEL
IN ORDER TO FURTHER UNDERSTAND VARIOUS QUALIFICIATIONS.
Again, I would like to thank you for giving Skyline Engineering the opportunity to
work with the City. I look forward to speaking with you in person about any
questions or concerns you may have about our firm.
Sincerely,

~~

Bryan Schalesky, PE
President
Skyline Engineering, Inc.

l"'-

.,. ~-~-

1!3.ta .. ~'t.~,J.. -~.,__ ".;ll~~f".-"..0::.'"''~-4 .....:

8100 Wild Horse Road, Salinas CA 93907 - Phone: 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering .com - www.skylineengineering.com

..:::...::

-.o:.:-:r.

'--

'

(' fl
~) l

vI

fNG

INflR

.... --

------

l.

[.{ IL
N G

PARTIAL PROJECT REFERENCE LIST


Updated October 2014
Thank you for keeping this client list confidential.

CITY GOVERNMENT
CITY OF SANTA CLARA

Eight Buildings

CITY OF SAN LEANDRO

Five Buildings

CITY OF SOUTH SAN FRANSICO

Two Buildings

CITY OF WALNUT CREEK

Jim Parisentti

(408) 615-3061

Roof replacement design, project management


services, inspection services, and environmental
engineering services.
Glen Contreras at 510-577-6014
Roof replacement design, project management
services, and inspection services.
Robert Hahn

(650) 8293830

Roof replacement design, project management


services, and inspection services.
Carolyne Challice 925-451.()601
challice@walnut-creek.org

Larkey Park & Clarke Swim Centers Roof inspections and recommendations

Boundary Oak Golf Course clubhouse exterior building envelope restoration.


Evaluation, design specifications , project management services.

ADDITIONAL CITIES WORKED WITH IN THE PAST

City of San Jose: Skyline was the official roofing/waterproofing consultant between
2001 and 2006.

City of Sunnyvale

City of Mountainview

City of Fremont: City-wide roof management program in 2000. Roof replacement


design and project management services 2000 to 2009.

831-663-6188- bryan@skylineengineering.com- skylineengineering.com

Page2

Skyline Engineering

UNIVERSITIES
UC SANTA CRUZ

Henry Salameh
Damon Adlao
Josephine Ortega

831-459-2094
831-459-2338
831-459-2152

Dorm #6

Roof replacement design

McHenry Library

Waterproofing evaluation and design

Kerr Hall

Roof replacement design & project management.


Roof deck coating replacement design & project
management.

Oaks College

Wall & Roof replacement evaluation & specifications

Crown College Cafeteria

Roof replacement design & inspection services

Stevenson dorms

Roof replacement design & inspection services

Kresge College Admin

Building envelope analysis & renovation design &


inspection services

Kresge College Library

Roof replacement design & inspection services

Crown College Library

Building envelope analysis & renovation design &


inspection services

Music Hall

Waterproofing design & inspection services

Provost House

Roof replacement design & inspection services

Heat Plant

Roof replacement design & inspection services

MBEST

Metal roof analysis & repair design services

Barn G

Environmental Engineering testing & specifications


for removal of hazardous materials. Historical
Building roof replacement design & project
management

Old Theater

Environmental Engineering testing & specifications


for removal of hazardous materials. Historical
Building roof replacement design & project
management

Stores

Environmental Engineering testing & specifications


for removal of hazardous materials. Roof replacement
design & project management

Village Housing

Roof replacement design & project management

Crown College Housing

Environmental Engineering testing & specifications


for removal of hazardous materials. Roof replacement
design & project management

Hahn Art Center

Roof replacement design and project management.

(831) 663-6188- bryan@skylineengineering .com- skylineengineering.com

Skyline Engineering
-:~...::..;.:- ..~-:.~.;..-.

'"1:.!"":-- .;..

.... ~~.;.-_.-._.::-..............

.:--...:.- ....'!.":".=..:::.:.~..:.."::.

--

.-

Page3
-~:.~ ... -:

c .. ,:;.:.

PROJECTS THROUGH NOVA PARTNERS at UCSC. Nova is no longer at UCSC

Oaks College UCSC

Roof & wall covering design & inspection services

Stevenson College UCSC

Roof & wall coating design & inspection services

Porter College UCSC

Building Envelope analysis

College 8

Roof replacement design

Kresge College Housing

Exterior wall analysis

STANFORD UNIVERSITY

Kevin Hutcherson

650-723-6072

Cantor Art Museum

Exterior patio & wall sealant design & project


management

Gilbert Biology Building

Exterior window/wall sealant analysis


Window & wall sealant replacement design & project
management.

SAN JOSE STATE UNIVERSITY

John Skyberg john.skyberg@sjsu.edu


Mike Ham

mike.ham@sjsu.edu

Joyce Fan

joyce.fan@sjsu.edu

2014 campus-wide roof assessment

Duncan Hall Phase 1

Roof consulting services 2011

Old Engineering

Quality control inspection services 2003

SPX swimming pool

Deck & pool design & proj management 2003

Industrial Studies Building

Roof replacement design 1999 & 2003

Sweeney Hall

Roof, deck design & inspections 2002

Spartan Complex Gym

Roof, deck design & inspections 2003

Clark Library

Roof system design & quality inspections 2005

Student Union

Waterproofing design 2005

Hugh Gillis Hall

Roof replacement and wall coating design

Walquist Library

Deck coating, roof replacement design

Spartan Complex & Mens Gym

Tile & BUR roof replacement and wall coating

Old Engineering

Roof replacement design

Art Building

Roof replacement and wall coating design

Music Building

Roof replacement design

Central Classroom Building

Roof replacement design

Business Classroom Building

Roof replacement and wall coating design

~.:. ;:~.;:-:.:_.~~:::-:-:::; ____ ,...-:,. ...... --:::'- .. -:PQ!Il:.-~;~;c:~~~~~'1":'"1Y.teriC.%..~,--- . ..;-:.-.-.-

(831) 663-6188- bryan@skylineengineering .com- skylineengineering.com

Skyline Engineering
-

----------------
:.-.'n
----.-;-.-.:-.._;.:.. - ---:- --.: ..:~:r;:::r. ...

:::-::=-.-:-~-"":;"

-:.:~.

-~.;;;:.

Page4
--~-:~--:;_-...:...:..
-~

.-.~-

--

--- --

--:-.;:.;-~~

Cafeteria Building

Roof replacement and HVAC design

Duncan Hall Phase 1

Deck coating, roof replacement design

.;...:..1"'

Margaret Hom, Assoc Dir Facilities 408-795-5600

SJSU Housing Services

Moulder Hall

Roof replacement design & quality inspections

Markham Hall

Roof replacement design & quality inspections

Joe West Hall

Roof replacement design & quality inspections

Dining Commons

Roof replacement design & quality inspections

Campus Village

Consulting services during specification phase &


inspection services during construction phase 2004

Chuck Copus, AlA 510-885-4259

CSU East Bay

University Union Bldg

Quality control inspections.

Science Bldg

Quality control inspections.

Library Bldg

Quality control inspections.

UC BERKELEY

Past project managers worked with no longer at UCB:


Valerie Neumann & Mike Topperkoff

Law School

Roof replacement design & quality inspections

Press Building

Roof replacement design & quality inspections

SAN FRANCISCO STATE UNIVERSITY

Evan Christianson & Barry Jodathian

Consulting services for various facilities for HVAC installation on roofing systems

Business Building

Roof design & quality control inspections

(831) 663-6188- bryan@skylineengineering.com- skylineengineering.com

Skyline Engineering

----,----- ------ - - - -...- ..-..

Page 5

~:-: .-~.;

COLLEGES
CONTRA COSTA COMMUNTIY COLLEGE DISTRICT
Ray Pyle (no longer at CCCD)

Arts & Administration Building

2009 Roof design & quality control inspections

Auto Technology Building

2009 Roof design & quality control inspections

Brian Adair 510-466-7269


badair@peralta.edu

PERALTA COMMUNITY COLLEGE DISTRICT

FOOTHILUDEANZA COMMUNITY COLLEGE DISTRICT


Art Heinrich 650-949-6295
Ron Deller 650-949-7226 dellerron@fhda.edu
Michael Hua (408) 690-6735 MHua@GilbaneCo.com

Japanese Cultural Center

2009 Roof design & quality control inspections

Carriage House

2009 Roof design & quality control inspections

2012 New construction projects- Classroom & Lab Wings. Quality control
inspections

2013 New construction projects- 5100, 5600 & 5800 bldgs. Quality control
inspections

Faculty Office Building

Roof replacement specifications & quality control


inspections .

CABRILLO COLLEGE
Richard Kurk 831-477-3217

Watsonville Extension Building

2009 Exterior wall assessment. Stucco wall


repair & waterproofing design

Music & Theater Buildings

2010 Exterior wall assessment & repair


recommendations.

HARTNELL COLLEGE
Barbara Yesnosky (831) 755-6914
Damon Felice (831) 770-7044

King City Education Center

Roof replacement design & inspection services

CAB Building

Roof replacement design & inspection services

--::-..,..,.---- ---- . .
...
.. -.;::....--- . -- ..:. .... .. .. '
(831) 663-6188- bryan@skylineengineering.com- skylineengineering.com
;:.""-:~-

~ :;

~ --

,;

-- --

Page6

Skyline Engineering

PUBLIC SCHOOL DISTRICTS


SAN MATEO- FOSTER CITY SCHOOL DISTRICT

Alex Krista! 650-312-7880

In 2009 Skyline was successful in the RFQ process for this district. The primary directive was to provide
design and project management services for roof replacement projects under their Measure L bond program.
We also provide peer reviews for roofing projects provided by architects.
1. Borel Middle School 2010

Roof replacement design & quality inspections

2.

North Shoreview School2010

Roof replacement design & quality inspections

3.

San Mateo Park School2010

Roof replacement design & quality inspections

4.

Shoreline Elementary School2010

Roof replacement design & quality inspections

5.

Park Elementary School 201 0

Roof replacement design & quality inspections

6. Parkside Elementary School2010

Roof replacement design & quality inspections

7.

Meadow Heights Elementary School 2011

Roof replacement design & quality inspections

B.

Bowditch Middle School 2011

Roof replacement design & quality inspections

9.

Horrall Elementary School2012

Roof replacement design & quality inspections

10. Bayside Middle School2012

Roof replacement design & quality inspections

11 . Baywood Elementary School 2012

Architectural peer review

12. College Park School2012

Architectural peer review & quality inspections

13. Fiesta Gardens School 2012

Architectural peer review & quality inspections

14. Foster City Elementary School 2012

Architectural peer review

SAN FRANCISCO UNIFIED SCHOOL DISTRICT

Joel Cadiz 415-241-4312,


Simon Reyes 415-241-4311

In 2010 Skyline was successful in the RFQ process for this district. The primary directive was to provide
design and project management services for roof replacement projects. We also provide general consulting
services for roofing and waterproofing issues throughout the district.
1. McKinley Elementary
2.

Independence High School

Roof replacement design & quality inspections


Roof replacement design & quality inspections

3 . O'Connel High School

Waterproofing analysis. Waterproofing project


design & quality control inspections

4. June Jordan School

Environmental Engineering testing & specifications


for removal of hazardous materials. Roof
replacement design & quality inspections

5.

Environmental Engineering testing & specifications


for removal of hazardous materials. Roof
replacement design & quality inspections

Nutrition Center

6. Nourse Auditorium

Roof/deck replacement design & quality inspections

7.

Roosevelt Middle School

Roof inspection/analysis

8.

MLK Middle School

Leak investigation of new roofing system installed


under bond program .

9. Tenderloin School

Deck coating leak investigation

(831) 663-6188- bryan@skylineengineering.com- skylineengineering.com

Page 7

Skyline Engineering
=:.::::
--~
- =::-;;::
:r=--=

...-.. -.=-- =

=
. -::
.,._
=.,..,..
z=
.-"
~-

Cathy Braun (831) 427-4813


Ed Victorine (831) 212-6089

SANTA CRUZ CITY SCHOOLS

In 2008 Skyline was successful in the RFQ process for this district. The primary directive was to provide
design and project management services for roof replacement projects. We also provide general consulting
services for existing roofing systems that are under warranty.
Harbor High School

Roof replacement design & quality inspections. Roofing


system analysis & leak investigation.

Delaveaga Elementary School

Roof replacement design & quality inspections

Santa Cruz High School Science Bldg

Environmental Engineering testing & specifications for


removal of hazardous materials. Roof & Skylight
replacement design & quality inspections

Santa Cruz HS Adult Health Ed Bldg

Environmental Engineering testing & specifications for


removal of hazardous materials. Roof & Skylight
replacement design & quality inspections

EAST SIDE UNIFIED HIGH SCHOOL DISTRICT

Eric Chiu 405-347-5116 chiue@esuhsd.org

In 2014 Skyline was successful in the RFQ process for this district. The primary directive was to provide
design and project management services for roof replacement projects.
District-wide roof assessments and report for 19 high schools.

BELMONT REDWOOD SHORES SO

Mitch Rhodes 408-244-71 DO Mitch.Rhodes@Biach.com

In 2011 Skyline was successful in the RFQ process for this district. The primary purpose of the RFQ was to
provide inspections on existing roofing systems in order to determine recommendations for replacement
under their current bond. We also provide quality control inspections during roof replacement.
1.

Benjamin Fox Elementary School

Roof condition inspection & report.

2.

Central Elementary School

Roof condition inspection & report.

3.

Cipriani Elementary School

Roof condition inspection & report.

4.

Nesbit Elementary School

Roof condition inspection & report.

5.

Ralston Middle School

Roof condition inspection & report. Quality control


inspections during roof replacement.

, :.. - . ~- -.:-Q:f"~~~---.__.~~.ti:...,Q']F'!:;'.Iti,S- :.::::-#::.a~

~::..-r-:-.::.: . . !:::.t'.. .a-:-;.:-~:~-~ ..:'.- ' .::.:.... ..::-::--~~~;: -.- -: ... :"":''.~

....

(831) 663-6188- bryan@skylineengineering.com- skylineengineering.com

...

-.

- -- .

":~-

PageS

Skyline Engineering

OAKLAND UNIFIED SCHOOL DISTRICT

Mike Seuferrer (no longer with District)


TadashiNakadegawa
Tad ash i. Nakadegawa@ousd.k12.ca.us

1.

Cole School

Roof replacement design & quality control inspections

2.

Lowell School

Roof replacement design & quality control inspections

3. Ralph Bunche School

Roof replacement design & quality control inspections

4. Cox School

Roof replacement design & quality control inspections

5. Marshall School

Roof replacement design & quality control inspections

6.

Luther Burbank School

Roof replacement design & quality control inspections

7.

Calvin Simmons School

Roof replacement design & quality control inspections

8.

Roosevelt School

Roof replacement design & quality control inspections

9. Glenview School

Roof replacement design & quality control inspections

10. Westlake School

Roof replacement design & quality control inspections

11. Oakland High School

HVAC upgrade consulting. Roof replacement design &


quality control inspections

12. Brei Harte School

Roof replacement design & quality control inspections

2012 Roof inspections for Solar Initiative project for the following schools.
Victor Manansala (510) 535-7089
0
0
0
0
0
0
0
0
0
0
0

Roosevelt Middle School


Oakland High School
Brewer Middle School
Bret Harte Middle School
Havenscourt Middle School
Woodland ES
Elmhurst MS
Madison MS
Castlemont HS
King Estates MS
Skyline HS

CAMPBELL UNION SCHOOL DISTRICT

o
o

o
c

o
o
o
o

Montara MS
Carter MS
Oakland Tech HS
Claremont MS
Washington ES
Lowell MS
McCiymonds HS
Westlake MS
Cleveland School
Burbank School

Doug Williams 408-364-4200 ext. 7044

1.

Rolling Hills School

Roof replacement design & quality control inspections

2.

Blackford School

Roof replacement design & quality control inspections

3.

Lynhaven School

Roof replacement design & quality control inspections

4.

Campbell Middle School (cafeteria)

Roof replacement design & quality control inspections

5.

Castleman! School

Roof replacement design & quality control inspections

MILPITAS UNIFIED SCHOOL DISTRICT

John Cimino 408-945-5567

1.

Spangler School

Roof replacement design & quality control inspections

2.

District Office

Roof replacement design & quality control inspections

3.

Rose School

Roof replacement design & quality control inspections

(831) 663-6188- bryan@skylineengineering.com- skylineengineering .com

Skyline Engineering
-.;...;;:--.:;;-:-~

~.:--

..

__

.. -

...!..:.~.-

.... :.=:z..;..- -:;:-; ... ~

. -=-..

___

_____ Page 9
,..

,..

--=:~

-~-~.:..:~~---:;:

4.

Burnett School

Roof replacement design & quality control inspections

5.

Milpitas High School

Roof replacement design & quality control inspections

BERKELEY UNIFIED SCHOOL DISTRICT

Lew Jones 51 0-644-6060

1. Jefferson School

Roof replacement design & quality control inspections

2. Willard School

Roof replacement design & quality control inspections

Oxford School

Roof replacement design & quality control inspections

4. Hillside School

Roof replacement design & quality control inspections

3.

MLK School

Roof replacement design & quality control inspections

6. Emerson School

Roof replacement design & quality control inspections

5.

7.

Berkeley High School

MORGAN HILL UNIFIED SCHOOL DISTRICT

Roof replacement design & quality control inspections

Anessa Espinosa 408-201-6087

In 2012 we assisted the District by providing roof inspections and budget numbers in preparation for Measure
G which was successful last November.

1. Burnett Elementary School


2. El Toro School
3. Jackson School
4.

Los Paseos

5. Nordstrom
6. Paradise Valley
7.

San Martin/Gwinn

ATASCADERO UNIFIED SCHOOL DISTRICT

Atascadero High School Gym

SALINAS UNION HS DISTRICT

El Saulsal High School

B.

Walsh
Encinal Charter
Machado
Britton
Martin Murphy
Live Oak HS
14. Central Continuation

9.
10.
11.
12.
13.

Stu Stoddard (805) 462-4243


Roof analysis and
replacement design

recommendation

report.

Karen Luna & Liz Ortiz 831-796-7075

Roof replacement design & quality control inspection


services

(831) 663-6188- bryan@skylineengineering.com- skylineengineering.com

Roof

Skyline Engineering
~,.t.iz-:-

Page 10

----------- - - - - - - - - - - - -

---r ~....:.: ":-::- - - .... : ::---- --:-:


..~"..:- .. ;;. ... .::... .. _.: :; -l~:!~;t-""'..:;:.:;.-;:.'1:..:~.:. ::... m

:::--!.:-~-.-.-; ....... -

"'"::-:-- -.:..

. .... __ ,. __ , ---

The following are school districts that Skyline Engineering has provided services for
throughout the years. They are not currently references due to changes in personnel or
roofing/waterproofing needs have been completely met.
NORTH MONTEREY COUNTY USD
Prunedale Elementary

Roof Condition Survey/report of all buildings

Castroville Elementary

Roof Condition Survey/report of all buildings

North County High School

Roof Condition Survey/report. Roof replacement design &


quality control inspection services

MT. DIABLO UNIFIED SCHOOL DISTRICT

Delta View Elementary

Engineering study of store front systems

Strandwood Elementary

Engineering Study on skylight systems

Burlingame School District, Burlingame CA


Gilroy Unified School District, Gilroy CA
Bellermine College Preparatory, San Jose CA
Scotts Valley Unified School District

-------------------....
---~:.;;:.._;,_:,

-~~

~-7"

(831) 663-6188- bryan@skylineengineering.com- skylineengineering.com

Page 11

Skyline Engineering

-- - - - - - - - - - ..

-....

~ .

COUNTY GOVERNMENT
COUNTY OF MONTEREY

Dave Pratt
(831) 755-4982
prattdw@co.monterey .ca.us

Men's Jail

Foam roof restoration & rooftop pipe support design


and project management services

Women's Jail

Foam roof restoration & rooftop pipe support design


and project management services

Rehabilitation Center

Foam roof restoration & rooftop pipe support design


and project management services

Monterey Health Bldg

Roof replacement evaluation & specifications

Old Jail historical Bldg

Roof replacement design & inspection services

Agricultural Bldg

Metal roof coating design & project management

Courthouse

Exterior waterproofing design & inspections

Courthouse

Below grade waterproofing inspection & consulting

Juv Hall Gym

Roof replacement design & inspection services.


Environmental Engineering services

831-663-6188- bryan@skylineengineering.com- skylineengineering.com

Skyline Engineering

Page 12

UTILITIES
PACIFIC GAS & ELECTRIC

Ed Conner (925) 674-6436

Skyline Engineering provides a variety of consulting services for PG&E throughout Northern
California. We currently manage their roofing inventory and inspection program. This is a
comprehensive program of inspection, analysis, reporting, recommendations, and planning for
roof repair and replacement.
Skyline has provided roof surveys and roof replacement design and inspection services for
the following PG&E facilities:

Cinnebar Service Center in SJ


Fremont Service Center
Cupertino Service Center
Merced Service Center
Newark Substation
San Ramon Conference Center
Headquarters San Francisco
San Francisco Service Center
Davis Service Center
111 Almaden San Jose
Colma Service Center
Salinas Service Center
Sonora Service Center
Belmont Service Center
Coalinga Service Center
Colma Service Center
Eureka Service Center
Jackson Service Center
Santa Ynez Service Center
Richmond Service Center
Bakersfield Service Center
Oroville Service Center
Humbolt Sub-Station
Red Bluff Service Center

Merced Service Center


Fresno Materials Distribution
Center
San Luis Obispo Service Center
Ukiah Service Center
Hayward Service Center
San Ramon TES
Stockton CSO
Stockton Gas Plant
Stockton Service Center
Sacramento Call Center
Marysville Service Center
Tracey Service Center
Vacaville Service Center
Watsonville Service Center
Orland Service Center
Redding Service Center
Rio Vista Service Center
Woodland Service Center
Vallejo Service Center
Jackson Service Center
Victor Service Center

831-663-6188- bryan@skylineengineering.com- skylineengineering.com

Page 13

Skyline Engineering

PACIFIC GAS & ELECTRIC- GAS SYSTEMS

Dave Boitano 925-974-4215

System-wide roofing & waterproofing inspection & assessments

2008
Tracy Maintenance Station
Bethany Compressor Station
Delevan Compressor Station
Willows District Office
Gerber Compressor Station
Burney Compressor Station
Tionesta Compressor Station
2003
Milpitas Terminal
Los Medanos Compressor Station
Antioch Terminal
Hinkley Compressor Station
Topock Compressor Station
Kettleman Compressor Station
Hollister Station

831-663-6188- bryan@skylineengineering.com - skylineengineering.com

RESUME
Bryan Schalesky, P.E.
8100 Wild Horse Road
Salinas CA 93907

BIOGRAPHY
Bryan Schalesky is a registered Professional Engineer in lhe State of CA (License #M030834) and has been
president of Skyline Engineering since 1998. Bryan obtained a Bachelor of Science Degree in Mechanical
Engineering from Stanford University in 19BB.
Bryan has extensive experience providing specification documents for public agencies and districts. In 2010 Bryan
was invited to testify before the California State Assembly on behalf of the Assembly Committee on Accountability
and Administrative Review in support of Assembly Bill 635. This bill, which was eventually made into law and added
to the Public Contract Code Section 3400, helped better define the legalities associated with fair public bidding
practices in the roofing Industry.
Prior to founding Skyline in 1998, Bryan worked as Field Engineer for Tremco. As representative of this major roofing
and sealant manufacturer, Bryan learned the inner wort<ings of materials manufacturing and the manner in which
manufacturers develop new products and mart<el their systems. He became involved In litigation when roofing
systems did not meet building owner expectations. Bryan now uses this unique expertise and insight to provide his
current clients with consulting services when specifying and designing roofing and waterproofing projects.
While with Tremco, Bryan became knowledgeable and efficient in the discipline of water infiltration detection
technology including infra-red and capacitance scanning. Bryan's most notable accomplishment during the decade of
the 90s while with Tremco included the management of roof replacement at the campus of San Jose State University.
Most roofing systems on campus were replaced during this lime under Bryan's management and design services.
Today Bryan uses his Mechanical Engineering background and license to analyze and design building envelope
systems (roofing and waterproofing) as well as exterior mechanical systems that affect the building envelope.
Building envelope systems are mechanical systems experiencing stress, strain, heat transfer, and vapor flow. The
selection of new roofing and waterproofing systems requires knowledge of material science. Engineering of roofing
systems to withstand high winds requires knowledge of fastener technology and building dynamics. All of these
disciplines are integral to the field of Mechanical Engineering. As a licensed mechanical engineer Bryan also has the
ability to address rooftop mechanical equipment along with roofing projects. Design Integration of these two industries
can become seamless complimentary rather than at odds with one another.
Bryan's most notable clients include HCA (Healthcare Corporation of America) where he manages the roofing and
waterproofing program from the Mid-West to West Coast. HCA is the largest private health care system in the USA.
Bryan also manages the Pacific Gas and Electric roofing program in Northern California.
Universities and School Districts comprise over half of the wort< performed by Skyline Engineering. UC Santa Cruz
uses Bryan and Skyline Engineering for most of its roofing and waterproofing projects. The most notable school
districts include East Side USD in San Jose, Oakland USD, Berkeley USD, Milpitas USD, San Francisco USD, San
Mateo- Foster City School District, and Santa Cruz City Schools.
Bryan is the author of several articles on roofing technology and has investigated building envelope failures from the
Lorna Prietta Earthquake . Bryan has lectured to industry groups and building owners regarding building envelope
design and maintenance on numerous occasions throughout the years.
Bryan has been married to Mario for twenty five years and has five beautiful daughters ages 14, 11 , 9 (twins), and 3.
He has only one little boy age 5. When not wort<ing or chasing after the twins, Bryan spends time swimming and
playing stable boy while girls ride horses.

8100 Wild Horse Road, Salinas CA 93907- phone: 831/663/6188- fax: 831/663/6187
email : bryan@skylineengineering.com- website: skylineeningeering.com

Skyline Engineering

Page 2

------------------------------------- -..:.;.,- . - -- -;.:; ..


. . -.::r:. ... '"::;;_:.......--::::--4- - -

------~--- --~----~::::1.:::
-::~-~::..::;;&..-

...;;:_ -

--~-

..--:::..~.":!==~

';.."""";.;:_;;a,-

EXPERIENCE
Field Engineer
TREMCO, INC.

1986 -1998
CALIFORNIA (SANTA CLARA, SANTA CRUZ, MONTEREY COUNTIES)

Responsibilities include providing roof consulting services and asset management as follows:
-Roof inspections and assessments.
-Roof asset management services and leak management programs.
-Specification design for roof repair, replacement, and restoration
-Roof construction management
-conduct pre-bid job conferences
-conduct pre-construction conferences
-conduct field inspections and quality control
-conduct final inspections
-conduct follow up warranty inspections
President
SKYLINE ENGINEERING , INC .

1998 - PRESENT
CALIFORNIA, NEVADA, WASHINGTON, TEXAS, IDAHO, UTAH,
KANSAS, MISSOURI , MINNESOTA, OKLAHOMA, ALASKA,
COLORADO

Responsibilities include providing engineering consulting services as follows :


-Roofing, Waterproofing, Window, Wall & HVAC inspections and assessments.
-Roofing, Waterproofing, Window, Wall & HVAC asset management services.
-Specification design for system repair, replacement, and restoration
-Construction management
-conduct pre-bid job conferences
-conduct pre-construction conferences
-conduct field inspections and quality control
-conduct final inspections
-conduct follow up warranty inspections

EDUCATION
Bachelor of Science Mechanical Engineering 1988
Certifications:

Stanford University

Registered Professional Engineer, State of California


Independent Inspector, accredited by the SPRAY POLYURETHANE
DIVISION of the SOCIETY OF THE PLASTICS INDUSTRY

Affiliations:

Stanford Alumni Association


RCI, Roof Consultants Institute

8100 Wild Horse Road, Salinas CA 93907- phone: 831/663/6188- fax: 831/663/6187 email: bryan@skylineengineering.com- website: skylineeningeering.com

8100 Wild Horse Road


Salinas CA 93907
p 831.663.6188
F 831.663.6187

Michael Perry
BIOGRAPHY
Mike Perry is acting Director of Quality Control for Skyline Engineering. His primary
responsibilities include the following:
Roofing and waterproofing system inspection and analysis.
Quality control inspection services during construction.
Project management services including conducting pre-bid and preconstruction meetings.
Mike Perry came to California from his childhood home in Indiana in the early 1980s.
After working odd jobs for a while Mike began working for a roofing contractor
repairing leaking roofing systems. Here he gained valuable experience tracking and
solving difficult leaks.
Later Mike began working on roof replacement crews where he soon became foreman
and superintendent. Mike came to Skyline Engineering in 2002 to perform quality
assurance inspections. Mike's inside experience as a roofing foreman and
superintendent made him uniquely qualified to monitor the work performed during
construction .
Over the years with Skyline Engineering, Mike has become proficient at using
capacitance scanning to help detect moisture under roofs and behind walls. He has
taken on design responsibilities for new roofing systems and has developed skills as a
CAD technician. Mike also provides most of the field inspections required for roof
management programs. He is proficient at RoofPro roof management software.

i'

I,

f.,
I

I,

.'

.(
'

l , [

l
I,

'..
..

! '

8100 Wild Horse Road


Salinas CA 93907
p 831 .663.6188
F 831.663.6187

RESUME/810
NATHAN SCHALESKY

Nathan heads Skyline Engineering's Environmental Engineering Department.


Nathan has been in the roofing industry since 1986. With his degree in
Environmental Studies along with this roofing experience, Nathan becomes
one of the most highly qualified individuals when it comes to consulting on our
roofing projects.
Nathan also has experience in project management services. Nathan has
managed PG&Es roof inspection program throughout Northern California for
the past five years . Nathan also manages the roof inspection program for the
second largest school district in California. These two programs alone consist
of several hundred buildings.

EDUCATION
Bachelor of Science in Environmental Studies at the University of California
Santa Barbara

CERTIFICATIONS

Asbestos - Gal/OSHA Certificates - Building Inspector, Management Planner,


Abatement Contractor/Supervisor, Abatement Project Designer - from the
University of California Berkeley
Lead - Cai/OSHA Certificates - Inspection and Assessment, Abatement
Supervisor and Monitoring- from the University of California Berkeley

1(

-...-...-...

8100 Wild Horse Road, Salinas CA 93907 - Phone : 831/663-6188 - Fax: 831/663-6187
Email: bryan@skylineengineering.com - www.skylineengineering.com

This space is reserved for the County Clerk's Filing Stamp

Published by The Monterey Herald


P.O. Box 271 Monterey, California 93942
(831) 726.4382

CARMEL-BY-THE-SEA
AccountNo.2140473
PO DRAWERG
CARMEL BY THE SEA, CA 93921

Lega1No.0005509860
waterproofing raised planters
Total Cost: $1778.30
Ordered by: AVanderford@ci.marina.ca

PROOF OF
PUBLICATION
STATE OF CALIFORNIA
County of Monterey

I am a citizen of the United States and a resident of the County aforesaid .


I am over the age of eighteen years, and not a party to or interested in
the above-entitled marrer. I am the principal clerk of the printer of The
Monterey Herald, a newspaper of general circulation, printed and published daily and Sunday in the City of Monterey, County of Monterey,
and which newspaper has been adjudged a newspaper of general circulation by the Superior Court of the County of Monterey, State of California;
that the notice, of which the annexed is a printed copy (set in type not
smaller than 6 point), has been published in each regular and entire issue
of said newspaper and not in any supplement thereof on the following
dates, to wit:

06/25/15, 06/30/15

I certify (or declare) under penalty of perjury that the foregoing is true
and correct.

Executed on 06/30/2015 at Monterey, California.

Signature

!EXHIBIT "H"

!EXH IBIT "I"

CITY OF CARMEL-BY-THE-SEA
Council Report
August4,2015
To:

Honorable Mayor and Members of the City Council


Douglas J. Schmitz, City Administrator

From:

Andy Vanderford, Public Works Project Manager

Subject:

Consideration of a resolution rejecting bids for a Construction


Contract for the Waterproofing Raised Planters project

RECOMMENDATION: Approve a resolution rejecting bids for a construction contract for the
Waterproofing Raised Planters project.
EXECUTIVE SUMMARY: On July 10, 2015, two bids were submitted to the City for the
Waterproofing Raised Planters project (located at the Public Works I Police Headquarters
facility). The project primarily consists of excavating two existing raised planters, replacing the
waterproof membrane, and filling back-in the planters with top soil. Per Municipal Code
3 .12.420, public works contracts for more than $24,999 shall be let by formal written
contract, or if rejecting bids, approved by resolution of City Council. Therefore, this item is on
the agenda for Council to reject bids.
ANALYSIS/DISCUSSION:
The bids received included :
Contractor
Best Contractinq Services
Legacy Roofing

Bid
$91,250.00
$100,938.00

The engineer's estimate for the project is $55,000.00. The low bid is 66% above the
engineer's estimate. Staff recommends that the Council reject the bids and direct staff to
expeditiously pursue a different design approach with the anticipation for a much less
expensive solution to keep water from entering the facility. Staff estimates a re-design and
rebid effort will result in project a completion sometime this coming winter.

FISCAL IMPACT:

The PD/PW Roof/Patio Replacement project was funded as part of the Fiscal Year 2014-15
budget for a project cost of $75,000. During the course of the year, staff spent approximately
$46,000 on this project, including about $11,000 on engineering and design and $20,000 on
emergency repair work related to the December 2014 rain. Staff estimates a total project cost
of $42,1 00 by using a different design approach, which would be paid for primarily through the
remaining project fund balance. Any project shortfall would require either reallocating funds
from another capital project or using Measure D prior fund balance, both which require
Council approval. These options would be brought forward for consideration after redesigning and rebidding the project.
Budgeted (yes/no)

Funding Source

Partially

MeasureD

PREVIOUS COUNCIL ACTION/DECISION HISTORY:

Council approved the Fiscal Year 2014-15 budget on June 10, 2014, and approved the
carryover of FY 14-15 projects and their associated fund balances as part of the Fiscal Year
2015-16 budget on June 15, 2015.
ATTACHMENTS:

Attachment 1 - Resolution

APPROVED:

Date: _ _ _ _ _ _ __

Douglas J. Schmitz, City Administrator

Christopher Dinner Heating, Inc.


PO Box 2348
Monterey, CA 93942

Invoice
IEXHIIB!T "J" I

Date

Bill To

9!23/2015

Invoice#

6174

Terms

City of Carmel
Attn Andrew Vanderford

Project

P.O. No.

License #: 684975
Phone: (831) 393-9661
Fax no: (831) 394-2667
Email: offtcechrisdinnerheatinginc. net
Description

Rate

Qty

Manufacture and install plenum with two 20" round flexible outside air vents
10 - Labor hours
1/2 - Roll of duct tape
2- Boxes 20" flex
40# - 26 gauge galvanized

10
0.5
2
40

90.00
24.00
183.00
2.00

Amount
900.00
12.00

366.00
80.00

f--~-;r

~~/
13-7010/

J/l<kl~
t7\.) cf==\

le-

t ~~

<!M~.

t...carc:G

Total
Payments/Credits

Balance Due

$1,358.00
$0.00
$1,358.00

LAST ONE TO
LfAVfTHlS
BlJ!LDING

-rt'J1~~

~r.!-11~

.l
I

Potrebbero piacerti anche