Sei sulla pagina 1di 14

ICE CHILLER

Thermal Storage Units


Refrigeration
Refrigeration

Product Detail
Why Ice Storage? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .J2
Construction Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .J5
Selection Flexibility . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .J6
Unit Selection-Ammonia . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .J7
Engineering Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .J9
Engineering Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .J13
J12
J1

ICE CHILLER Thermal Storage Units


Low Temperature Chilled Water for: Lower First Cost, Reduced Energy, and Space Savings

ICE CHILLER Thermal Storage Units

Why Ice Storage?

Stored cooling, because of its lower first cost and


operating cost, is now widely recognized as an excellent
answer to the increasing cost of operating todays cooling
systems. Generating and storing cooling capacity at a
constant rate during off-peak hours results in smaller
cooling equipment being used, reducing maximum
system peak electrical demand and taking advantage of
lower, off-peak energy costs.

Ice storage, in particular, has emerged as the most


practical method of storing cooling capacity. The high
latent heat of fusion of ice permits large capacity storage
in a relatively small space, and the low melting
temperature of ice provides the cooling system with a
constant source of low temperature chilled water.
Ice storage is a proven technology that has been used for
decades in churches, dairies, breweries and theaters due
to the advantages of lower first cost, reduced energy cost
and minimum space requirements. Today with these
advantages, ice storage provides lower cost cooling on a
wider variety of process/batch cooling systems, industrial
refrigeration and comfort cooling applications.

Lower First Cost

Cooling systems using BAC ICE CHILLER Thermal


Storage Units can be installed for the same or lower first
cost than conventional instantaneous cooling systems.
This important breakthrough results from:
Smaller Refrigeration System

When designed to operate on a 24-hour basis, or when


the time available for building ice is significantly greater
than the duration of the load, a smaller refrigeration
system is required compared to a chiller sized for an
instantaneous peak load.
Smaller Electrical Equipment and Wiring

Electrical equipment and wiring costs are also lower since


the smaller mechanical equipment can reduce connected
horsepower by over 50%.

For most system requirements, these significant savings


will exceed any cost premium associated with the ice
storage equipment.

J2

Baltimore Aircoil Company

Reduced Energy Cost

With less connected horsepower, ice storage can lower


electrical demand charges by over 50%. In addition, total
annual kilowatt-hours used can be less than with a
conventional instantaneous cooling system. As an
increasing number of electric utility companies impose
rate schedules with higher peak demand charges and/or
time-of-use rates, ice storage can provide even greater
future savings in operating costs.

Space Savings

Ice has proven to be the most space efficient thermal


storage system. Since ice storage systems utilize the
latent heat of fusion, they require approximately onefourth the volume of an equivalent capacity chilled water
storage system.

Industrial Cooling

For industrial applications, stored cooling using ICE


CHILLER Thermal Storage Units provides many
opportunities for savings: smaller compressors and
likewise smaller system components and electrical
equipment; shifting or leveling of energy usage peaks;
and efficient use of equipment. Also, since ice storage
systems are sized to operate primarily at full capacity,
compressor wear from capacity adjustment is minimized,
providing maintenance savings over the life of the
compressor. Stored cooling from ICE CHILLER Thermal
Storage Units supplies consistently low temperature
water, making them appropriate for daily and/or infrequent
cooling loads in many industrial processes such as:

Bakeries
Dairies
Breweries, Wineries, Distilleries
Chemical/Plastics Manufacturers
Laboratories
Food Product Cooling
Bottling Process
Vegetable/Fruit Cooling

Suitable For: Industrial Refrigeration Process Cooling Batch Cooling


Principle of Operation

When no cooling load exists, the refrigeration system


operates to build ice on the outside surface of the coil.
This refrigeration effect is provided by feeding refrigerant
directly into the coil. To increase the heat transfer during
the ice build cycle the water is agitated by air bubbles
from a low pressure distribution system beneath the coil.
When the ice has reached design thickness, BACs
exclusive ICE-LOGIC Ice Thickness Controller sends a
signal to turn off the refrigeration system.

For a closed chilled water loop, see Figure 2. With this


system, warm return water from the load is pumped
through a heat exchanger and cooled by the ice water
circuit from the ICE CHILLER Thermal Storage Unit.

Refrigeration

The basic ice storage system includes an ICE CHILLER


Thermal Storage Unit, a refrigeration system, and ice
water pump as shown below in Figure 1.

When chilled water is required for cooling, the ice water


pump is started, and the meltout cycle begins. Warm
water returning from the load circulates through the ICE
CHILLER Thermal Storage Unit and is cooled by direct
contact with the melting ice. During this cycle, the tank
water is agitated to provide more uniform ice melting and
a constant supply water temperature of 34 to 36F .

BLOWER

Figure 1

Figure 2

...because temperature matters

J3

Energy Efficient Design

ICE CHILLER Thermal Storage Units

The ICE CHILLER Thermal Storage Unit coils are


designed for efficient energy use in building ice and
constant leaving water temperatures during the meltout
cycle.

J4

Compared to traditional ice builders used in the past for


industrial refrigeration, the ICE CHILLER Thermal
Storage Unit design with its smaller diameter coil circuits
and thinner ice (Figure 3) results in more evaporator
surface per ton-hour of latent storage. Ice builds to a thin
2.0 inches, which results in more than a 16% gain in
refrigeration system efficiency by permitting compressor
operation at higher suction pressures.
OTHERS

BAC

1.66" O.D. COIL

1.05" O.D. COIL


2.0"

2.5"

COIL SURFACE: 3.0 FT2/TON-HOUR


ICE SURFACE: 14.5 FT2/TON-HOUR

Figure 3

2.8 FT2/TON-HOUR
11.1 FT2/TON-HOUR

The BAC ICE CHILLER Thermal Storage Unit is


specifically designed to provide consistent 34- 36F
supply water temperatures throughout the melt cycle. Two
keys to maintaining this consistently low temperature are
an extensive ice surface area and direct contact of the
water to be cooled with the ice. As shown in Figure 3, the
unique BAC coil design provides over 30% more ice
surface than traditional designs. This provides a greater
surface area for the warm return water to come into direct
contact, making consistent cold temperatures available
throughout the entire melt cycle.

The ICE CHILLER Thermal Storage Unit is designed for


efficient operation with either of two liquid refrigerant feed
systems: gravity flooded with surge drum or pumped
recirculation. With either arrangement, liquid refrigerant is
supplied to the coils at a rate several times greater than
that required to satisfy the load. This excess flow rate
thoroughly wets the entire internal surface of the coil,
assuring high heat transfer coefficients throughout to
efficiently utilize the entire coil surface for ice building.

Baltimore Aircoil Company

ICE-LOGIC ICE Thickness Controller

All BAC ICE CHILLER Thermal Storage Units are


furnished with the exclusive ICE-LOGIC ICE Thickness
Controller. This state-of-the-art controller was designed
by BAC to provide maximum operating efficiency by
enabling the operator to limit the ice build to only the
amount needed for the next cooling cycle.

The ICE-LOGIC Controller operates by sensing the


difference in the electrical resistance between water and
ice. When the desired amount of ice is built, the change in
resistance opens a control relay which typically
deactivates the refrigeration system. A series of probes
are employed, accurately positioned to detect ice
thickness corresponding to 20, 40, 60, 80 and 100
percent of design ice storage. The amount of ice required
for the next cooling cycle can be conveniently set on the
face of the control box. In addition, the ICE-LOGIC
Controller contains the necessary logic to prevent
unwanted compressor cycling after the desired ice build is
complete. The controller requires approximately 20
percent of the ice to be melted before the control relay is
activated. Lights on the face of the control panel indicate
the current status of the relay.

By building only the amount of ice needed, the operating


time for the refrigeration system and the kilowatt-hours of
energy used are kept at the lowest possible levels for
maximum system efficiency.

ICE-LOGIC Ice Thickness Controller

Construction Details

Centrifugal regenerative blower


for field mounting to supply low
pressure air for agitation of the
water. Blower is furnished with an
inline air filter, check valve and
rain shield for field installation.

Sectional insulated tank covers


are provided with a thermosetting
hybrid polymer. Covers are
interlocking and rain shedding.

6 COIL

The coil is constructed of multiple


prime surface serpentine steel
circuits and tested at 375 psig air
pressure under water. It is encased
in a steel frame, and the entire
assembly is hot-dip galvanized after
fabrication. For ammonia systems,
purge connections are provided on
each coil for oil maintenance.

5
4

6
2

EXTERIOR PANELS

Exterior panels sealed at all seams


provide a complete vapor barrier
and protect the insulation. They are
furnished with a thermosetting
hybrid polymer

2 INSULATION

7 ICE-LOGIC ICE
THICKNESS
CONTROLLER

An electronic, multi-point
adjustable ice thickness
control is mounted on the unit.
A control relay is provided for
deactivating the refrigeration
system when a full build of ice
is reached.

Refrigeration

4 AIR BLOWER

5 COVERS

8 AIR DISTRIBUTOR

Expanded polystyrene insulation is


provided between the tank and the
exterior panels. The insulation is
three inches thick (R-13) on the
tank sides and ends, two inches
thick (R-8) on the bottom and one
inch thick inside the covers.

1 TANK

The tank is constructed of heavy


gauge, hot-dip galvanized steel
reinforced with full-length structural
steel angles beneath and on all four
sides. All seams are welded to
ensure watertight construction. A
zinc rich coating is applied to all
exposed edges and welds.

Low pressure air from the air


blower is distributed below the
coils through multiple perforated
Schedule 40 PVC pipes.

...because temperature matters

J5

ICE CHILLER Thermal Storage Units

Selection Flexibility
Full Storage

System Design Flexibility

TSU Selection

Full Storage

2. Determine the build time, which is the number of hours


with no load that is available for ice building. If less than
ten (10) hours, consult your BAC Representative.

The system design involving an ICE CHILLER Thermal Storage


Unit can range from full storage to partial storage of the cooling load
requirements.
With full storage, the ICE CHILLER Thermal Storage Unit
generates and stores ice to handle the entire cooling load. The
refrigeration system operates to build the ice only during no-load
periods when utility rates are usually lowest. This design offers the
maximum energy cost savings, but requires the largest ice storage
capacity and refrigeration system.

Partial Storage

A partial storage system builds ice during no-load periods as with the
full storage system. However, the refrigeration system continues to
operate during the cooling load period. The compressor operation
supplements the stored cooling capacity of the ICE CHILLER
Thermal Storage Unit to satisfy the cooling requirements. Since a
portion of the cooling requirement is supplied by the refrigeration
system, a partial storage system will require less storage capacity.

Parallel Chilled Water Evaporator

The most common type of partial ice storage is the parallel


evaporator system. During the melt cycle, cooling is provided by the
refrigeration system to a separate evaporator for direct water chilling.
By using a separate evaporator, the refrigeration system gains
system efficiency from operation at higher suction pressures.
The refrigeration system will operate continuously during full design
load. At less than full load the compressor operates only as needed
to supplement the ICE CHILLER Thermal Storage Unit. When the
load is less than 50% of design, this system can operate in the full
storage mode. Systems which often operate at part load can
benefit most from a partial system with equipment sizes typically over
50% smaller than required for full storage.
For additional information on ICE CHILLER Thermal Storage Units
and their system design options consult your BAC Representative.

System Load

1. From the system load profile (figure 4) establish the required


system cooling capacity in ton-hours. This is the ton-hours
of storage required.

3. For a gravity flooded ammonia feed system, continue


the selection with the gravity flooded procedure on
page J7. For a pump recirculated ammonia feed
system, continue the selection with the pump
recirculated procedure on page J8.

Parallel Chilled Water Evaporator Partial Storage

1. From the system load profile (figure 4), establish the required
system cooling capacity in ton-hours and the number of hours
this cooling is needed.
2. Determine the cooling capacity in tons of the compressor
operating with the parallel evaporator (figure 5) during the
cooling load hours established in Step 1.

3. Multiply the cooling capacity of the compressor operating with


parallel evaporator found in Step 2 times the number of
cooling load hours found in Step 1. This gives the capacity in
ton-hours that will be handled by direct refrigeration during the
cooling period.
4. Subtract the direct cooling ton-hours found in Step 3 from the
total system cooling capacity found in Step 1. This is the
storage capacity in ton-hours that are required in ice storage.
5. Determine the build time, which is the number of hours with
the compressor dedicated to ice building. If less than (10) ten
hours, consult BAC Representative.

6. For gravity flooded ammonia feed system, continue the


selection with the gravity procedure on page J7. For a pump
recirculated ammonia feed system, continue the selection with
the pump recirculated procedure on page J8.

The system load is the amount of cooling capacity that must be


generated and stored, expressed in ton-hours or Btu. (1 ton-hour =
12,000 Btu = 83.3 pounds of ice). This load is equal to the area under
the typical system load profile curve (figure 4) shown below.

Load handled
by Stored Ice

Load handled
by Parallel
Evaporator

Figure 4

J6

Baltimore Aircoil Company

Figure 5

Unit Selection Ammonia


Application Notes

2. The evaporator temperatures for each build time are


average values. During the build cycle, the temperature will
initially be about 8F above the average and gradually drop
through the cycle to about 4F below the average when full ice
is reached. Throughout the cycle the refrigeration system
should be allowed to run fully loaded. Reciprocating and rotary
screw compressors are suitable for this duty. If in doubt
about the use of a particular compressor, review the application
with the compressor manufacturer.

Selection Procedure Gravity Flooded

1. Enter Table 1 and read down the base ton-hours column to the
capacity which meets or exceeds the ton-hours of storage
required. Select either an E, F, or G series unit. (Units are
grouped by tank width in Table 1. Refer to pages J9 thru J12 for
unit dimensions.)
2. Read the selected unit from the model number column
on the left.
3. Calculate the Storage Factor for the selected unit.

Base Ton-Hours
=
Ton-Hours of Storage Required

Storage Factor

Ton-Hours of Storage Required =


Build Time (Hrs)

Compressor Tons

4. Using the Storage Factor from Step 3 and the available build
time, enter Table 2 to find the design evaporator temperature.
5. Determine the design compressor capacity in tons.

6. Using the design conditions from Steps 4 and 5, select a


compressor. (Note: The evaporator temperature must
be adjusted for the system suction line losses to arrive at the
compressor saturated suction temperature.)
7. Once the compressor has been selected, use the compressor
manufacturers heat rejection data to size a BAC Evaporative
Condenser or Cooling Tower.
EXAMPLE: Gravity Flooded Ammonia
Given:
16,700 lbs ice required storage capacity
14 hours available build time
To get Ton-Hours of storage required:

16,700 lbs ice required storage capacity


83.3 lbs ice per Ton-Hour

201 Ton-Hours

1. Enter the base ton-hours column of Table 1 and find 211 tonhours, which is the smallest value that meets or exceeds the
201 ton-hours of storage required.
2. Read to the left to find the selected model number, in this case
a TSU-230E.
3. Calculate the Storage Factor.

211 Base Ton-Hours


=
201 Ton-Hours of Storage Required

1.05

3. The capacities of all BAC ICE CHILLER Thermal Storage


Units are based on latent storage (ice) only. The temperature of
the water supplied from the storage tank for most system
designs will be 34 - 36F throughout the latent storage
discharge (melt) cycle. For specific system design
requirements, contact your BAC Representative.
4. For selections based on other refrigerants, contact your
BAC Representative.

5. These procedures assume that no system cooling load occurs


while ice is being formed. For ICE CHILLER Thermal Storage
Unit selections involving systems with continuous cooling loads
consult your BAC Representative.
4. Using the Storage Factor of 1.05 from Step 3 and the build time
of 14 hours, enter Table 2 to find the design evaporator
temperature of 19.9F.
5. Calculate the design compressor capacity.

201 Ton-Hours of Storage Required =


14 Hours Build Time

Refrigeration

1. To use the selection procedures outlined below, the ton-hours


of storage capacity required and the available build time must
first be known. For guidance on estimating these values refer to
the TSU selection on pages J6 or contact your local BAC
Representative.

14.4 Tons

6. Based on the design evaporator conditions of 14.4 tons at a


19.9F evaporator temperature (17.9F saturated suction
temperature, with 2.0F estimated suction line losses), select
an ammonia refrigerant compressor.
7. Select a BAC Evaporative Condenser or Cooling Tower to
match the compressor manufacturers heat rejection
requirements.

Table 1: Base Storage Capacity (ton-hours) For


Gravity Flooded Ammonia Feed
E-Series Units
Model
Number
TSU-125E

F-Series Units

F-Series Units
Model
Number

Base
TON-HRS

Base
TON-HRS

Model
Number

Base
TON-HRS

112

TSU-145F

128

TSU-840F

756
894

TSU-155E

137

TSU-175F

157

TSU-990F

TSU-180E

163

TSU-205F

186

TSU-1140F

1,031

TSU-210E

188

TSU-240F

215

TSU-1290F

1,169

TSU-235E

214

TSU-270F

244

TSU-1520F

1,375

TSU-190E

173

TSU-220F

197

TSU-230E

211

TSU-265F

243

TSU-280E

251

TSU-320F

288

TSU-320E

291

TSU-370F

332

TSU-940G

851

TSU-365E

331

TSU-420F

377

TSU-1110G

1,007

TSU-290E

261

TSU-330F

300

TSU-1280G

1,163

TSU-345E

310

TSU-395F

356

TSU-1450G

1,315

TSU-395E

359

TSU-455F

410

TSU-1710G

1,550

TSU-450E

408

TSU-515F

466

TSU-505E

456

TSU-580F

522

TSU-590E

536

TSU-675F

614

TSU-700E

631

TSU-800F

722

TSU-810E

729

TSU-920F

834

TSU-910E

827

TSU-1040F

947

TSU-1080E

968

TSU-1230F

1,110

G-Series Units
Model
Number

...because temperature matters

Base
TON-HRS

J7

Table 2:

Design Evaporator Temperature (F) for


Gravity Flooded Ammonia Feed

4. Using the Storage Factor of 1.10 from Step 3 and the build
time of 11 hours, enter Table 4 to find the design evaporator
temperature of 17.7 F.

ICE CHILLER Thermal Storage Units

Build Time (HRS)


Storage
Factor

10

11

12

13

14

1.00

14.3

15.7

17.2

18.3

19.4

1.05

15.6

16.8

18.1

19.0

19.9

1.10

16.5

17.7

18.9

19.7

20.5

1.15

17.4

18.5

19.6

20.3

21.1

1.20

18.1

19.1

20.2

20.9

21.7

1.25

18.8

19.7

20.7

21.4

22.1

1.30

19.4

20.3

21.2

21.9

22.6

NOTE: Interpolation between values is permitted, but extrapolation of


values is not.

Selection Procedure
Pump Recirculated

2. Read the selected unit from the model number column


on the left.
3. Calculate the Storage Factor for the selected unit.

Base Ton-Hours
Ton-Hours of Storage Required

Storage Factor

4. Using the Storage Factor from Step 3 and the available build
time, enter Table 4 to find the design evaporator temperature.
5. Determine the design compressor capacity in tons.

Compressor Tons

6. Using the design conditions from Steps 4 and 5, select a


compressor. (Note: The evaporator temperature must be
adjusted for the system suction line losses to arrive at the
compressor saturated suction temperature.)

7. Once the compressor has been selected, use the compressor


manufacturers heat rejection data to size a BAC Evaporative
Condenser or Cooling Tower.
EXAMPLE: Pump Recirculated Ammonia
Given:
700 Ton-Hours Required Storage
11 Hours Available Build Time

1. Enter the base ton-hours column of Table 3 and find 771


ton-hours, which is the smallest value that meets or exceeds
the 700 ton-hours of storage required.

2. Read to the left to find the selected model number, in this case a
TSU-800F.
3. Calculate the Storage Factor.

771 Base Ton-Hour


=
700 Ton-Hours of Storage Required

J8

6. Based on the design evaporator conditions of 63.6 tons at a


17.7 F evaporator temperature (15.7 F saturated suction
temperature, with 2.0 F estimated suction line losses), select
an ammonia refrigerant compressor.
7. Select a BAC Evaporative Condenser or Cooling Tower to
match the compressor manufacturers heat rejection
requirements.

Table 3:

Base Storage Capacity (ton-hours) for


Pump Recirculated Ammonia Feed

E-Series Units

1. Enter Table 3 and read down the base ton-hours column to


the capacity which meets or exceeds the ton-hours of
storage required. Select either an E, F, or G Series unit. (Units
are grouped by tank width in Table 3. Refer to pages J9 thru J12
for unit dimensions.

Ton-Hours of Storage Required


Build Time (Hrs)

5. Calculate the design compressor capacity.


700 Ton-Hours of Storage Required = 63.6 Tons
11 Hours Build Time

1.10

Baltimore Aircoil Company

F-Series Units

F-Series Units

Model
Number

Base
TON-HRS

Model
Number

Base
TON-HRS

Model
Number

Base
TON-HRS

TSU-125E

121

TSU-145F

138

TSU-840F

TSU-155E

147

TSU-175F

169

TSU-990F

966

TSU-180E

175

TSU-205F

199

TSU-1140F

1,116

TSU-210E

201

TSU-240F

228

TSU-1290F

1,263

TSU-235E

227

TSU-270F

258

TSU-1520F

1,480

TSU-190E

187

TSU-220F

212

TSU-230E

227

TSU-265F

258

TSU-280E

270

TSU-320F

308

Model
Number

Base
TON-HRS

TSU-320E

311

TSU-370F

353

TSU-940G

912

TSU-365E

351

TSU-420F

399

TSU-1110G

1,076

TSU-290E

282

TSU-330F

322

TSU-1280G

1,229

TSU-345E

334

TSU-395F

381

TSU-1450G

1,378

TSU-395E

385

TSU-455F

435

TSU-1710G

1,593

TSU-450E

434

TSU-515F

492

TSU-505E

481

TSU-580F

547

TSU-590E

578

TSU-675F

660

TSU-700E

679

TSU-800F

771

TSU-810E

779

TSU-920F

886

TSU-910E

879

TSU-1040F

1,000

TSU-1080E

1,022

TSU-1230F

1,154

Table 4:

Storage
Factor
1.00
1.05
1.10
1.15
1.20
1.25
1.30

820

G-Series Units

Design Evaporator Temperature (F) for


Pump Recirculated Ammonia Feed
Build Time (HRS)
10
14.3
15.5
16.5
17.4
18.3
19.0
19.7

11
15.7
16.8
17.7
18.5
19.3
20.0
20.6

12
17.1
18.1
19.0
19.7
20.4
21.0
21.6

13
18.1
19.0
19.9
20.5
21.2
21.7
22.3

14
19.1
20.0
20.8
21.4
22.0
22.5
23.0

NOTE: Interpolation between values is permitted, but extrapolation of values


is not.

Engineering Data
Nominal 5 wide units:
Models TSU-125E to TSU-235E and TSU-145F to TSU-270F

REFRIG. CONN.

AIR INLET
SEE NOTE (4)

AIR OUTLET
+ OVERFLOW

4' 9"

7'7"

+ WATER OUT

DRAIN
+

+ WATER IN

6"
A
18"

Refrigeration

Do not use for construction. Refer to factory certified dimensions. This handbook includes data current at the time
of publication, which should be reconfirmed at the time of purchase.

W/2
W

LBS Of Ice2
Gravity
Flooded

Pump
Recirculated

Approx.
Shipping
Wgt (LBS)

Water
Volume
(GAL)

Pull Down
Volume
(GAL)

Coil
Volume
(FT3)

R-717
Charge
(LBS)5

Water
Conn
In/Out

TSU-125E

9,330

10,808

5,500

23,500

2,080

270

245

5 3-1/8 10 1 4.5

TSU-155E

11,410

12,250

6,230

TSU-180E

13,580

14,580

7,070

28,000

2,520

320

10

275

5 3-1/8 12 1 4.5

32,600

2,960

380

12

325

TSU-210E

15,660

16,740

5 3-1/8 14 1 4.5

8,090

37,400

3,400

440

13

355

5 3-1/8 16 0

TSU-235E

17,830

18,910

8,830

41,900

3,840

490

15

410

5 3-1/8 18 0

TSU-145F
TSU-175F

10,660

11,500

5,730

23,700

2,070

40

10

275

5 3-1/8 10 1 4.5

13,080

14,080

6,500

28,100

2,510

45

12

325

5 3-1/8 12 1 4.5

TSU-205F

15,490

16,580

7,370

32,800

2,950

55

13

355

5 3-1/8 14 1 4.5

TSU-240F

17,910

18,990

8,370

37,600

3,390

65

15

410

5 3-1/8 16 0

TSU-270F

20,330

21,490

9,140

42,100

3,820

70

17

460

5 3-1/8 18 0

Model
Number

Approx.
Air
Operating Wgt Pump
(LBS)
(HP)

E Series

F Series

Support

ICE CHILLER Thermal Storage Units should be continuously supported on a flat level surface.

Notes:

1. All dimensions are in feet and inches. Weights are in pounds.

2. Lbs. of Ice Capacity is based on R-717. For other refrigerants, consult your BAC Representative.

3. Dimensions showing location of connections are approximate and should not be used for prefabrication of connecting piping.

4. Dimension is installed height. Coils are capped for shipping and storage. Add 3 inches for shipping height.

5. Refrigerant charge listed is operating charge for gravity flooded system at 15F. For other feed systems, consult your BAC Representative.

...because temperature matters

J9

Engineering Data
Do not use for construction. Refer to factory certified dimensions. This handbook includes data current at the time
of publication, which should be reconfirmed at the time of purchase.
REFRIG. CONN.

SEE NOTE (4)

AIR INLET

+ OVERFLOW

AIR OUTLET

+ WATER OUT
4' 9"

7'7"

ICE CHILLER Thermal Storage Units

Nominal 8 and 10 wide units:


Models TSU-190E to TSU-505E and TSU-220F to TSU-580F

+ DRAIN
A

+ WATER IN

6"

W/2

*18" ON TSU-190E-365E; TSU-220F-420F


*16" ON TSU-290E-505E; TSU-330F-580F

LBS Of Ice2
Model
Number

Gravity
Flooded

Pump
Recirculated

Approx.
Shipping Wgt
(LBS)

Approx.
Operating
Wgt (LBS)

Air
Pump
(HP)

Water
Volume
(GAL)

Pull Down
Volume Coil Volume
(GAL)
(FT3)

14,410
17,580
20,910
24,240
27,570
21,740
25,820
29,900
33,990
37,980

15,580
18,910
22,490
25,910
29,240
23,490
27,820
32,070
36,150
40,070

7,670
8,740
9,700
11,120
12,100
9,950
11,200
12,900
14,050
14,700

36,200
43,200
50,200
57,700
64,500
53,400
62,000
71,300
80,000
88,600

3
3
3
3
3
3
3
3
3
3

3,300
4,000
4,700
5,400
6,100
5,040
5,920
6,800
7,080
8,550

420
510
600
700
800
640
760
860
980
1090

16,410
20,240
23,990
27,660
31,400
24,990
29,650
34,150
38,820
43,480

17,660
21,490
25,660
29,400
33,240
26,820
31,740
36,240
40,980
45,570

8,040
9,150
10,180
11,700
12,730
10,460
11,780
13,430
14,650
15,370

36,500
43,600
50,600
58,100
65,100
53,900
62,510
71,800
80,500
89,200

3
3
3
3
3
3
3
3
3
3

3,290
3,990
4,680
5,380
6,070
5,020
5,890
6,770
7,640
8,520

60
70
90
100
110
95
110
130
140
160

R-717
Charge
(LBS)5

Water
Conn
In/Out

15
17
19
22
24
21
23
26
29
32

410
465
515
600
650
570
625
705
790
870

4
4
4
4
6
6
6
6
6
6

7 10-1/2
7 10-1/2
7 10-1/2
7 10-1/2
7 10-1/2
9 9-3/8
9 9-3/8
9 9-3/8
9 9-3/8
9 9-3/8

10 1
12 1
14 1
16 0
18 0
12 1
14 1
16 0
18 0
20 0

5
5
5
5
6
6
6
6
6
6

16
19
21
24
26
23
26
29
32
35

435
515
570
650
705
625
705
790
870
950

4
4
4
4
6
6
6
6
6
6

7 10-1/2
7 10-1/2
7 10-1/2
7 10-1/2
7 10-1/2
9 9-3/8
9 9-3/8
9 9-3/8
9 9-3/8
9 9-3/8

10 1
12 1
14 1
16 0
18 0
12 1
14 1
16 0
18 0
20 0

5
5
5
5
6
6
6
6
6
6

E Series
TSU-190E
TSU-230E
TSU-280E
TSU-320E
TSU-365E
TSU-290E
TSU-345E
TSU-395E
TSU-450E
TSU-505E

F Series
TSU-220F
TSU-265F
TSU-320F
TSU-370F
TSU-420F
TSU-330F
TSU-395F
TSU-455F
TSU-515F
TSU-580F

Support

ICE CHILLER Thermal Storage Units should be continuously supported on a flat level surface.

Notes:
1.
2.
3.
4.
5.

J10

All dimensions are in feet and inches. Weights are in pounds.


Lbs. of Ice Capacity is based on R-717. For other refrigerants, consult your BAC Representative.
Dimensions showing location of connections are approximate and should not be used for prefabrication of connecting piping.
Dimension is installed height. Coils are capped for shipping and storage. Add 3 inches for shipping height.
Refrigerant charge listed is operating charge for gravity flooded system at 15F. For other feed systems,
consult your BAC Representative.

Baltimore Aircoil Company

Engineering Data
Nominal 10 wide units (cont.):
Models TSU-590E to TSU-1080E and TSU-675F to TSU-1230F

SEE NOTE (4)

REFRIG. CONN.
+ OVERFLOW

AIR INLET

AIR OUTLET

WATER OUT

4' 9"

7'7"

Refrigeration

Do not use for construction. Refer to factory certified dimensions. This handbook includes data current at the
time of publication, which should be reconfirmed at the time of purchase.

+ WATER IN

+ DRAIN
A

16"

6"

W/2

LBS Of Ice2
Model
Number

Gravity
Flooded

Pump
Recirculated

Approx.
Shipping Wgt
(LBS)

Approx.
Operating
Wgt (LBS)

Air
Pump
(HP)

Water
Volume
(GAL)

Pull Down
Volume
(GAL)

Coil
Volume
(FT3)

R-717
Charge
(LBS)5

Water
Conn
In/Out

44,650
52,560
60,730
68,890
80,630

48,150
56,560
64,890
73,220
85,130

18,200
20,820
24,300
26,600
30,060

106,900
124,500
144,400
160,200
186,200

3
3
5
5
5

10,240
12,030
13,790
15,540
18,180

1320
1540
1760
1990
2330

42
47
53
58
67

1140
1275
1440
1575
1820

6
6
8
8
8

9 9-3/8
9 9-3/8
9 9-3/8
9 9-3/8
9 9-3/8

23 11
27 11
31 10
35 10
41 9

6
6
7
7
7

51,150
60,140
69,470
78,891
92,460

54,980
64,220
73,800
83,300
96,130

19,240
21,960
25,380
27,820
31,460

107,900
125,600
143,700
161,300
187,500

3
3
5
5
5

10,200
11,980
13,700
15,480
18,100

190
230
260
290
340

46
52
59
65
74

1250
1410
1600
1765
2010

6
6
8
8
8

9 9-3/8
9 9-3/8
9 9-3/8
9 9-3/8
9 9-3/8

23 11
27 11
31 10
35 10
41 9

6
6
7
7
7

E Series
TSU-590E
TSU-700E
TSU-810E
TSU-910E
TSU-1080E

F Series
TSU-675F
TSU-800F
TSU-920F
TSU-1040F
TSU-1230F

Support

ICE CHILLER Thermal Storage Units should be continuously supported on a flat level surface.

Notes:
1.
2.
3.
4.
5.

All dimensions are in feet and inches. Weights are in pounds.


Lbs. of Ice Capacity is based on R-717. For other refrigerants, consult your BAC Representative.
Dimensions showing location of connections are approximate and should not be used for prefabrication of connecting piping.
Dimension is installed height. Coils are capped for shipping and storage. Add 3 inches for shipping height.
Refrigerant charge listed is operating charge for gravity flooded system at 15 F. For other feed systems,
consult your BAC Representative.

...because temperature matters

J11

Engineering Data
Do not use for construction. Refer to factory certified dimensions. This handbook includes data current at the time
of publication, which should be reconfirmed at the time of purchase.

SEE NOTE (4)

REFRIG. CONN.
+ OVERFLOW

AIR INLET
AIR OUTLET

+ WATER OUT
5' 2"

7'111/2"

ICE CHILLER Thermal Storage Units

Nominal 12 wide units:


Models TSU-840F to TSU-1520F and TSU-940G to TSU-1710G

+ WATER IN

+ DRAIN
A

22"

6"

W/2

LBS Of Ice2
Model
Number

Gravity
Flooded

Pump
Recirculated

Approx.
Shipping Wgt
(LBS)

Approx.
Operating
Wgt (LBS)

Air
Pump
(HP)

Water
Volume
(GAL)

Pull Down
Volume
(GAL)

Coil
Volume
(FT3)

R-717
Charge
(LBS)5

Water
Conn
In/Out

62,980
74,470
85,880
97,380
114,540

68,310
80,470
92,960
105,210
123,280

24,120
26,900
31,460
34,340
38,660

146,500
170,000
200,600
218,800
254,400

5
5
5
5
5

14,240
16,650
19,080
21,500
25,150

1,800
2,100
2,320
2,710
2,900

55
63
71
78
90

1,490
1,710
1,925
2,115
2,440

8
8
8
8
8

11 9
11 9
11 9
11 9
11 9

23 11
27 11
31 10
35 10
41 9

7
7
7
7
7

70,890
83,880
96,880
109,540
129,120

75,970
89,630
102,380
114,790
132,700

25,440
28,340
33,220
36,260
40,820

147,700
171,400
196,900
220,600
256,400

5
5
5
5
5

13,960
16,350
18,730
21,110
24,690

280
330
380
420
490

61
70
79
87
100

1,655
1,900
2,145
2,360
2,710

8
8
8
8
8

11 9
11 9
11 9
11 9
11 9

23 11
27 11
31 10
35 10
41 9

7
7
7
7
7

F Series
TSU-840F
TSU-990F
TSU-1140F
TSU-1290F
TSU-1520F

G Series
TSU-940G
TSU-1110G
TSU-1280G
TSU-1450G
TSU-1710G

Support

ICE CHILLER Thermal Storage Units should be continuously supported on a flat level surface.

Notes:
1.
2.
3.
4.
5.

J12

All dimensions are in feet and inches. Weights are in pounds.


Lbs. of Ice Capacity is based on R-717. For other refrigerants, consult your BAC Representative.
Dimensions showing location of connections are approximate and should not be used for prefabrication of connecting piping.
Dimension is installed height. Coils are capped for shipping and storage. Add 3 inches for shipping height.
Refrigerant charge listed is operating charge for gravity flooded system at 15F. For other feed systems,
consult your BAC Representative.

Baltimore Aircoil Company

Engineering Specifications
For ICE CHILLER Thermal Storage Units
Thermal Storage Unit - Furnish and install, as

Quality Assurance - The thermal storage unit

manufacturer shall have a Management System


certified by an accredited registrar as complying with the
requirements of ISO-9001:2000 to ensure consistent
services.

Capacity - The ICE CHILLER Unit(s) shall have a

thermal storage capacity


of ton-hours, operating with
refrigerant and a build time of
hours at a
F/(C) nominal evaporator temperature.

Tank - The tank shall be constructed of heavy gauge

hot-dip galvanized steel and reinforced with full-length


structural angles underneath and on all four sides. All
seams shall be welded to ensure watertight construction.
A zinc rich coating shall be applied to all exposed edges
and welds.

Coil - The coil shall be constructed of prime surface

serpentine steel circuits and shall be tested at 375 psig


air pressure under water. The coil shall be encased in a
steel frame and the entire assembly hot-dip galvanized
after fabrication. For use with ammonia refrigerant, coil
shall be complete with purge connection for oil
maintenance.

Insulation - Expanded polystyrene insulation shall be

Exterior Panels - Exterior panels shall be sealed at


all seams to provide a complete vapor barrier and to
protect the insulation. They shall be furnished with a
thermosetting hybrid polymer.
Covers -The ICE CHILLER Unit(s) shall be provided

with sectional, rain shedding, interlocking and insulated


steel covers provided with a thermosetting hybrid
polymer.

A multi-point adjustable, solid state, electronic resistivity


type ice thickness control shall be provided. The sensing
probe shall be mounted on the coil, and a control relay
to deactivate the refrigeration system shall be installed in
a NEMA 4 box mounted on the unit.

ICE Thickness Control

Refrigeration

shown on plans, factory-assembled ICE CHILLER


Thermal Storage Unit(s) with all water-touched steel
components hot-dip galvanized, all exposed edges and
welds fully coated with zinc-rich compound, and
exterior panels protected from corrosion with a
thermosetting hybrid polymer.

Air Blower - A centrifugal regenerative blower for field


mounting shall supply low pressure air for agitation of the
water. Blower shall be furnished with inline air filter,
check valve and rain shield for field installation.
Air Distributor - Low pressure air shall be

distributed through multiple perforated Schedule 40


PVC pipes.

Unit Size - Unit plan dimensions shall not exceed


approximately
feet(m) by
feet(m) with an overall
height not exceeding
feet(m). The operating weight
shall not exceed
pounds(kg).

The ICE CHILLER Thermal Storage Unit(s) shall be


Baltimore Aircoil Company Model TSU-

provided between the tank and the exterior panels. The


insulation shall be three inches thick (R-13) on the tank
sides and ends, two inches thick (R-8) on the bottom and
one inch inside the covers.

...because temperature matters

J13

Channel Island Power Station


Project Report

Opts for Ice Thermal Storage System


A dramatic increase in the city of Darwin, Australias
power demand since the early 1990s has been met
by the introduction of an ammonia ice thermal
storage system at its Channel Island Power Station.

The power station was built in 1985, and is operated


by the Northern Territory Government utility - the
Power and Water Authority (PAWA). The electricity
consumption by Darwin has been steadily monitored
over the years by PAWA. An assessment in 1995
clearly showed that demand was growing at a
faster rate than earlier projections had identified,
and that a solution was needed.

The decision to use an ice thermal storage system


has not only eased the pressure, but also resulted in
considerable savings for PAWA and the Government. The actual cost is one-third the installation cost of an
extra turbine. The final system chosen by PAWA employs an ammonia ice thermal storage system plant,
supplying ice water during peak periods to wet air coolers on the inlets of the three turbines.
The first stage of the project includes the following major equipment:
Five 500 kW screw compressors, 1,500 kW (426 tons) each
Five BAC Model CXV Evaporative Condensers

96 BAC ice coils, building 1,400 metric tons of ice that will provide 130,000 kWh
(36,932 ton-hours) of storage
Three BAC wet air cooler modules, cooling inlet air from 37C to 9C
(98.6F to 48.2F)
Two concrete tanks 15m (49) x 15m (49) x 7m (23) high

The system is remarkable in its simplicity and efficiency of operation. During the night and morning off-peak
periods, the refrigeration plant builds ice on the ice coils. At peak demand, ice water is pumped from the
storage tanks and across a direct contact heat exchanger medium to cool air before it enters the turbine.

The ice build period is off-peak, with no effect on the daily maximum demand, John Rule Marketing Manager
BAC Australia stated. Also, the control of ice build can be coordinated with spinning reserve needs. The wet
air cooler provides extra benefits in washing the air, removing dust, insects and smoke. The dirt is collected in
an easily accessible basin for filtration cleaning. There are no finned coils to clog.

Using ammonia is a highly energy-efficient process, as well as being greenhouse friendly, and has essentially
no affect on the ozone layer. This, combined with the piped natural gas system, means that greenhouse gas
production is much less than that from a coal-fired power station.

J14

Baltimore Aircoil Company

Potrebbero piacerti anche