Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Network Diagram
A network diagram is a sequence of steps (activities) that
are linked together in the logical sequence they need to
be carried out.
Provides the project team a consensus of understanding
of how the project should be implemented
Planning should not be done alone, it's a group activity,
The following activity starts when the previous one has been
finished
Default type of dependency (e.g. in MS Project)
Software
development
Acceptance testing
SS
1 day
Document
Amendments
FF
2 days
You could use these with lags.
E.g. documentation of the changes to the
prototype starts 1 day after the testing and
finishes 2 days after testing has been completed
Operate temporary
system
Acceptance test
of new system
Cutover to new
system
Nature of dependency
Mandatory dependency
Discretionary dependency
External dependency
Backward pass
activity
Latest start
= LF - duration
Earliest start = day 5
Earliest finish = ?
Latest start = ?
Activities
Earliest
start
Duration
Earliest
finish
11
Total Float
Latest
finish
Forward pass
When there is more than one previous activity, take the latest
earliest finish
EF = day 7
ES
ES == day10
day 7
EF = day10
12
13
11
10
10
13
Backward pass
LF = day 67
LS = day 7
LS = day 6
14
15
11
11
11
11
13
10
10
13
10
10
10
13
16
0
3
0
0
17
10
10
9
2
11
8
11
11
10
10
10
11
2
13
13
13
Critical path
18
0
3
0
0
19
10
10
9
2
11
8
11
11
10
10
10
11
2
13
13
13
20
21
Consider activity D.
The starting date can be delayed 3 weeks without
affecting the project end day.
However, the start date of H will be affected
(4+3+4=11).
6
9
2
7
22
11
8
11
11
11
2
13
CPM vs PERT
23
24
te = (a + 4m +b) / 6
25
s = (b-a)/6
Example
26
27
Task B
Example
Task A
Task C
Task
10
12
16
10
14
20
24
38
te
Task B
Task A
Task C
Task
te
10
12
16
12.66
10
14
10.33
20
24
38
25.66
29
38.32
30
31
z = (T te)/s
= (42-38.32)/3.16
= 1.164
38.82
42
Graph of z values
Schedule development
34
Gantt chart
35
Project milestones
36
Major milestones
37
Milestone
Milestone Goal
Concept approval
Requirements review
Product operational
http://www.chambers.com.au/glossary/milestone.php
Minor milestones
38
Milestone
Milestone Goal
Document complete
Compile complete
39
Crashing
For each task in the critical path, look for the task that
could be done faster if more resources were added.
Goal:
40
Look for the task that would deliver the most compression for
the least incremental cost
Duration =
Work
Resource unit
41
Duration is
shortened by 1
day
Fast tracking
42
43
44
Reward/Recognition
Tangible (e.g. cash, gifts)
Intangible (e.g. praise, favorably mention in monthly report or meetings, training)
Training
45
46
Factors
47
References
48
Chapter 6