Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
5242-C-53000
CONSTRUCTION SCHEDULE
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
495
15-10-2012 A
29-06-2014
371579
494
15-10-2012 A
27-06-2014
15-10-2012 A
A1000
100%
A1020
03-01-2013 A
100%
A3390
27-09-2013 A
100%
A1010
BSDG Installed
24-03-2014
95
0%
A1030
Project Complete
27-06-2014*
0%
16-01-2013 A
55
21-12-2012 A
21-12-2012 A
100%
A4270
Completion of Mobilisation
16-01-2013 A
100%
27-09-2013 A
27-09-2013 A
11-03-2014
108
A4290
27-09-2013 A
0
19
20-02-2014
A4260
100%
A4300
20-02-2014
127
0%
A4310
11-03-2014
108
0%
12-06-2014
15
71
02-04-2014
A4320
02-04-2014
86
0%
A4360
11-04-2014
77
0%
A4340
15-04-2014
73
0%
A4350
05-05-2014
53
0%
A22860
11-05-2014
47
0%
A4330
16-05-2014
42
0%
A4370
12-06-2014
15
0%
YARNIMA.5 PRELIMINARIES
21
15-10-2012 A
21-12-2012 A
A4400
Lodgement of Securities
14
15-10-2012 A
21-12-2012 A
100%
A4410
14
15-10-2012 A
07-11-2012 A
100%
A4420
21
15-10-2012 A
16-11-2012 A
100%
A4440
Construction Schedule
21
15-10-2012 A
15-11-2012 A
100%
Construction Schedule
A4450
HSEP
21
15-10-2012 A
12-11-2012 A
100%
HSEP
A4460
HSMP
21
15-10-2012 A
12-11-2012 A
100%
A4470
21
15-10-2012 A
07-11-2012 A
100%
A4480
21
15-10-2012 A
12-11-2012 A
100%
A4490
21
15-10-2012 A
07-11-2012 A
100%
A4510
TNA
21
15-10-2012 A
12-11-2012 A
100%
TNA
A4590
21
15-10-2012 A
12-11-2012 A
100%
A4600
21
15-10-2012 A
12-11-2012 A
100%
A4620
CRAW
21
15-10-2012 A
06-11-2012 A
100%
A4610
14
02-11-2012 A
16-11-2012 A
100%
23
02-01-2013 A
28-01-2013 A
Lodgement of Securities
Cert of Currency for Insurances
HSMP
Quality Management Plan
A1500
Site Access
02-01-2013 A
100%
A1510
18
02-01-2013 A
18-01-2013 A
100%
A1510-1
Mobilization Personal
02-01-2013 A
28-01-2013 A
100%
A1510-2
06-01-2013 A
09-01-2013 A
100%
A1510-3
10-01-2013 A
13-01-2013 A
100%
A1510-6
VOC Training
10-01-2013 A
20-01-2013 A
100%
A1530-1
Main Office
11-01-2013 A
12-01-2013 A
100%
Main Office
A1510-5
12-01-2013 A
15-01-2013 A
100%
A1510-4
13-01-2013 A
16-01-2013 A
100%
A1530-2
2 * Cribs Huts
13-01-2013 A
14-01-2013 A
100%
2 * Cribs Huts
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 1 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Site Access
Mobilise Construction Personnel & Equipment
Mobilization Personal
VOC Training
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A1520
14-01-2013 A
100%
A1530-3
Toilet Block
14-01-2013 A
15-01-2013 A
100%
Toilet Block
A1530
16-01-2013 A
17-01-2013 A
100%
A1530-4
17-01-2013 A
18-01-2013 A
100%
A2140
18-01-2013 A
19-01-2013 A
100%
256
14-03-2013 A
01-12-2013 A
139
30-07-2013 A
01-12-2013 A
NCR-S166
30-07-2013 A
31-07-2013 A
100%
NCR-S170
BOP: KBE DN1000 SDR13.6 12m Pipe Length Does Not Meet AS4130 (internal)
13
01-08-2013 A
14-08-2013 A
100%
HP1050
Delayed access for Hamon _ Foundation and Plynths North of Cooling Towers
09-09-2013 A
100%
NCR-S347
15-11-2013 A
21-11-2013 A
100%
NCR-S362
27-11-2013 A
01-12-2013 A
100%
29-11-2013 A
29-11-2013 A
29-11-2013 A
14-03-2013 A
26-04-2013 A
14-03-2013 A
26-04-2013 A
09-03-2013 A
25-11-2013 A
10157
192
12-04-2013 A
25-11-2013 A
6779
BOP: KBE DN1000 SDR13.6 12m Pipe Length Does Not Meet AS4130 (internal)
100%
311
100%
A19690
Electrical Pre-commissioning
02-07-2013 A
19-07-2013 A
130
100%
Electrical Pre-commissioning
A19790
Mechanical Pre-Commissioning
16-07-2013 A
19-07-2013 A
260
100%
Mechanical Pre-Commissioning
VEGPRS100
VE GPRS - Commission Assistance, Install 00DB060 and 00BJA60, Install FOC and Pipe
31 Support
19-07-2013 A
16-08-2013 A
901
100%
VEGPRS110
VE GPRS -RMWS 80 Install PTFE Insulation Strips on the sections of piping requiring 2U bolts 28-08-2013 A
29-08-2013 A
50
100%
VEGPRS120
VE GPRS - Install temporary earth for spark gap arrestor. MWR 131 and commissioning
13 support
10-09-2013 A
24-09-2013 A
69
100%
VE GPRS - Install temporary earth for spark gap arrestor. MWR 131 and c
VEGPRS130
30-09-2013 A
13-10-2013 A
104
100%
VEGPRS140
VE GPRS - GPRS mods, Cathodic Protection Installation, provide scaffolding access, Mods
13 to PLatforms)
25-10-2013 A
07-11-2013 A
246
100%
VEGPRS150
VE GPRS - Punchlist - Cable Ladder Cover and Sealing conduits, and Cathodic Protection
3
Installation
23-11-2013 A
25-11-2013 A
48
100%
116
15
03-05-2013 A
03-05-2013 A
02-09-2013 A
07-07-2013 A
1517
670
100%
184
100%
A19670
14-05-2013 A
25-06-2013 A
A19630
22-05-2013 A
22-05-2013 A
61
100%
A19650
24-05-2013 A
16-07-2013 A
141
100%
NCR-S104
13
04-06-2013 A
17-06-2013 A
100%
NCR-S105
Posy junction box is not suitable for the size of cable in GPRS area
25
04-06-2013 A
30-06-2013 A
100%
NCR-S106
GPRS: The light fitting does not suit the pole light
13
04-06-2013 A
17-06-2013 A
100%
A19680
19-06-2013 A
19-07-2013 A
275
100%
A19660
08-07-2013 A
18-07-2013 A
186
100%
NCR-S150
08-07-2013 A
11-07-2013 A
100%
NCR-S199
25-08-2013 A
02-09-2013 A
100%
102
43
12-04-2013 A
12-04-2013 A
04-08-2013 A
27-05-2013 A
2897
0
100%
A19730
Fit Up Pipework
07-06-2013 A
26-06-2013 A
1417
100%
NCR-S108
08-06-2013 A
14-06-2013 A
100%
A19700
09-06-2013 A
10-06-2013 A
560
100%
A19710
Install Crossover 1
09-06-2013 A
09-06-2013 A
28
100%
Install Crossover 1
A19740
Weld Pipework
09-06-2013 A
09-06-2013 A
132
100%
Weld Pipework
NCR-S112
21
09-06-2013 A
01-07-2013 A
100%
A19720
Install Crossover 2
10-06-2013 A
28-06-2013 A
112
100%
Install Crossover 2
NCR-S121
18
16-06-2013 A
04-07-2013 A
100%
NCR-S122
16-06-2013 A
20-06-2013 A
100%
A19750
NDT
26-06-2013 A
10-07-2013 A
100%
NDT
A20860
07-07-2013 A
15-07-2013 A
518
100%
A19640
Painting
08-07-2013 A
15-07-2013 A
130
100%
Painting
A19770
Pneumatic Testing
10-07-2013 A
17-07-2013 A
100%
Pneumatic Testing
NCR-S160
11
24-07-2013 A
04-08-2013 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 2 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Fit Up Pipework
GPRS Area Handrails & Gridmesh Non Compliant
Activity ID
Activity Name
YARNIMA.4.3.3 Civil Works
A19760
Grouting
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
64
3
12-06-2013 A
12-06-2013 A
15-07-2013 A
10-07-2013 A
557
210
100%
Civil Works
18-06-2013 A
15-07-2013 A
347
100%
NCR-S133
13
21-06-2013 A
04-07-2013 A
100%
220
09-03-2013 A
30-07-2013 A
3378
09-03-2013 A
13-05-2013 A
818
100%
09-04-2013 A
30-07-2013 A
2560
100%
360
15-10-2012 A
03-12-2013 A
37907
30
15-10-2012 A
01-02-2013 A
30
0
0
15-10-2012 A
24-11-2012 A
24-11-2012 A
01-02-2013 A
24-11-2012 A
0
0
0
100%
24-11-2012 A
100%
0
0
17-10-2012 A
17-10-2012 A
0
0
100%
17-10-2012 A
100%
YARNIMA.11.5.1.3 STRUCTURAL
A5380
Stage 1 Piperack Dwgs AFC
0
0
15-10-2012 A
15-10-2012 A
15-10-2012 A
0
0
100%
YARNIMA.11.5.1.4 MECHANICAL
A5450
Stage 1 Valve List Issued
42
0
01-11-2012 A
01-11-2012 A
01-02-2013 A
0
0
100%
A5970
YARNIMA.11.5.1.2 CIVIL
A5360
Stage 1 Buried ServicesTrench Layout Dwgs AFC
A5840
17-10-2012 A
A5430
01-02-2013 A
100%
A5870
01-02-2013 A
100%
2
0
30-10-2012 A
30-10-2012 A
0
0
100%
A5470
04-11-2012 A
100%
A13620
04-11-2012 A
100%
YARNIMA.11.5.1.6 INSTRUMENTATION
A5540
GT3 Instrument Data Sheets & Cable Sched AFC
22
0
19-11-2012 A
19-11-2012 A
0
0
100%
19-11-2012 A
100%
35
0
0
30-11-2012 A
30-11-2012 A
30-11-2012 A
0
0
0
25-01-2013 A
30-11-2012 A
100%
A5700
30-11-2012 A
100%
A5710
Stage 1 Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip 0
30-11-2012 A
100%
0
0
25-01-2013 A
25-01-2013 A
25-01-2013 A
0
0
Stage 1 Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip
YARNIMA.11.5.2.2 ELECTRICAL WORKS
100%
77
05-11-2012 A
11-03-2013 A
77
0
05-11-2012 A
05-11-2012 A
11-03-2013 A
0
0
100%
13-02-2013 A
100%
A1140
GT3 Switchroom
11-03-2013 A
100%
A1150
11-03-2013 A
100%
21
0
14-02-2013 A
14-02-2013 A
0
0
100%
01-03-2013 A
100%
127
15-10-2012 A
23-04-2013 A
127
64
21
15-10-2012 A
17-10-2012 A
17-10-2012 A
27-03-2013 A
08-03-2013 A
15-11-2012 A
0
0
0
100%
A1760
YARNIMA.11.6 PROCUREMENT
YARNIMA.11.6.2 MECHANICAL
YARNIMA.11.6.2.5 PIPE SUPPORTS
A10260
Finalise tender package for Stage 1 Pipe Supports
01-03-2013 A
A1130
A10280
14
15-12-2012 A
05-03-2013 A
100%
A10270
17
02-01-2013 A
01-03-2013 A
100%
A10290
17
16-01-2013 A
07-03-2013 A
100%
A10300
04-03-2013 A
08-03-2013 A
100%
92
21
15-10-2012 A
15-10-2012 A
12-03-2013 A
12-11-2012 A
0
0
100%
YARNIMA.11.6.2.1 PIPERACK
A1340
Finalise tender package for Stage 1 Piperack
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 3 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
100%
21-12-2012 A
A5550
YARNIMA.11 PHASE 1
19-11-2012 A
04-11-2012 A
VO's #2, #5
A5400
YARNIMA.11.5.1.5 ELECTRICAL
A5520
Stage 1 Common Cable Sched & Electrical MTO Issued
VO's #2, #5
Civil Works
A23000
Grouting
A23010
YARNIMA.11 PHASE 1
A20850
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A5610
28
14-12-2012 A
07-02-2013 A
100%
A5580
19
14-01-2013 A
05-02-2013 A
100%
A5920
13
05-02-2013 A
12-03-2013 A
100%
A5930
22
10-02-2013 A
10-03-2013 A
100%
58
21
21-10-2012 A
21-10-2012 A
27-03-2013 A
17-12-2012 A
0
0
100%
18-12-2012 A
100%
Confirm Vendor
Confirm Vendor
A8620
18-12-2012 A
24-12-2012 A
100%
A8630
Include Comments
01-01-2013 A
04-01-2013 A
100%
Include Comments
A8640
04-01-2013 A
100%
A8650
05-01-2013 A
12-01-2013 A
100%
A8660
Issue PO
13-01-2013 A
14-01-2013 A
100%
Issue PO
A8670
16
14-01-2013 A
27-03-2013 A
100%
127
7
01-11-2012 A
01-11-2012 A
02-03-2013 A
21-12-2012 A
0
0
100%
21-12-2012 A
100%
Confirm Vendor
A8700
21-12-2012 A
21-12-2012 A
100%
A8710
Include Comments
21-12-2012 A
21-12-2012 A
100%
Include Comments
A8720
21-12-2012 A
100%
A8730
21-12-2012 A
20-01-2013 A
100%
A8740
Issue PO
01-02-2013 A
02-02-2013 A
100%
A8750
103
02-02-2013 A
02-03-2013 A
100%
56
56
15-12-2012 A
15-12-2012 A
21-03-2013 A
21-03-2013 A
0
0
100%
107
16
16
11-11-2012 A
11-11-2012 A
11-11-2012 A
23-04-2013 A
02-03-2013 A
02-03-2013 A
0
0
0
100%
125
28
26-11-2012 A
26-11-2012 A
08-03-2013 A
06-03-2013 A
0
0
100%
90
30-12-2012 A
08-03-2013 A
100%
99
7
19-11-2012 A
19-11-2012 A
23-04-2013 A
21-12-2012 A
0
0
Stage 1 VSD & Other Specialist Cable (Review- Procure & Deliver)
YARNIMA.11.6.3.4 STAGE 1 INSTRUMENTATION
100%
21-12-2012 A
100%
Confirm Vendor
Stage 1 VSD & Other Specialist Cable (Review- Procure & Deliver)
A8770
Confirm Vendor
A8780
21-12-2012 A
21-12-2012 A
100%
A8790
Include Comments
21-12-2012 A
21-12-2012 A
100%
Include Comments
A8800
21-12-2012 A
100%
A8810
21-12-2012 A
21-12-2012 A
100%
A8820
Issue PO
22-12-2012 A
08-01-2013 A
100%
A8830
80
26-01-2013 A
23-04-2013 A
100%
342
02-01-2013 A
03-12-2013 A
37907
52
52
0
02-01-2013 A
02-01-2013 A
02-01-2013 A
11-03-2013 A
31-01-2013 A
0
0
0
Issue PO
Manufacture & Deliver Stage 1 Instr & Controls
YARNIMA.11.8 PHASE 1 CONSTRUCTION
YARNIMA.11.8.5 PRELIMINARIES
YARNIMA.11.8.5.1 SERVICES
100%
Receipt Verification of Stage 1 Culverts & Fnds (Switchroom & Battery Room)
A7810
02-01-2013 A
100%
A9020
03-01-2013 A
100%
A9110
31-01-2013 A
100%
52
0
02-01-2013 A
02-01-2013 A
0
0
YARNIMA.11.8.5.2 GT3
A1540
Receipt Verification of GT3 Fnd
11-03-2013 A
100%
A1550
06-01-2013 A
100%
A1870
14-02-2013 A
100%
A1880
11-03-2013 A
100%
A1890
11-03-2013 A
100%
52
0
03-01-2013 A
03-01-2013 A
0
0
100%
19-01-2013 A
100%
YARNIMA.11.8.5.3 HRSG 3
A7800
Receipt Verification of HRSG3 Fnd
A9360
Receipt Verification of HRSG 3 Free Issue Bypass Stack & Assoc Equip
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 4 of 38
Data Date 07-02-2014
02-03-2013 A
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Confirm Vendor
YARNIMA.11.6.3 ELECTRICAL
YARNIMA.11.6.3.1 STAGE 1 ELECTRICAL EQUIPMENT
A5620
GT3 Electrical Equip (Review- Procure & Deliver)
A8690
Activity ID
Activity Name
A9370
YARNIMA.11.8.2 SERVICES
YARNIMA.11.8.2.3 GAS PIPELINE (UNDERGROUND)
YARNIMA.11.8.2.3.1 Excavation and Bedding
A7650
Trenching & Excavation for Underground Gas Pipework & Crossovers
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
02-03-2013 A
100%
230
33
31
12
25-01-2013 A
08-04-2013 A
08-04-2013 A
08-04-2013 A
09-09-2013 A
26-06-2013 A
25-05-2013 A
25-05-2013 A
4500
1393
162
162
100%
100%
A17020
08-04-2013 A
10-04-2013 A
A17010
08-04-2013 A
24-05-2013 A
100%
4
4
12-04-2013 A
12-04-2013 A
31-05-2013 A
31-05-2013 A
1050
1050
100%
16
16
16-04-2013 A
16-04-2013 A
12-06-2013 A
12-06-2013 A
0
0
100%
YARNIMA.11.8.2.3.3 Backfilling
A7680
Backfill & Compaction
7
7
24-04-2013 A
24-04-2013 A
26-06-2013 A
26-06-2013 A
181
181
100%
156
121
8
08-03-2013 A
08-03-2013 A
08-03-2013 A
12-08-2013 A
05-07-2013 A
27-05-2013 A
1675
399
399
100%
NCR-S071
11-05-2013 A
100%
NCR-S135
12
23-06-2013 A
05-07-2013 A
100%
156
25
15-04-2013 A
15-04-2013 A
12-08-2013 A
19-07-2013 A
559
559
100%
A17510
10
16-04-2013 A
17-07-2013 A
100%
A7701
10
21-04-2013 A
19-07-2013 A
100%
NCR-S129
11
20-06-2013 A
01-07-2013 A
100%
NCR-S134
48
22-06-2013 A
12-08-2013 A
100%
NCR-S147
06-07-2013 A
08-07-2013 A
100%
99
13
22-04-2013 A
22-04-2013 A
02-08-2013 A
26-07-2013 A
717
717
100%
22-04-2013 A
25-04-2013 A
100%
A17450
NCR-S069
22-04-2013 A
25-04-2013 A
100%
A17340
10
28-04-2013 A
24-07-2013 A
100%
A17360
22-05-2013 A
24-05-2013 A
100%
A17430
25-06-2013 A
26-06-2013 A
100%
NCR-S161
25-07-2013 A
02-08-2013 A
100%
5
5
23-07-2013 A
23-07-2013 A
28-07-2013 A
28-07-2013 A
0
0
100%
146
13
01-04-2013 A
01-04-2013 A
01-09-2013 A
12-07-2013 A
200
60
100%
A7740
34
04-04-2013 A
26-07-2013 A
100
100%
A7760
20
30-04-2013 A
31-07-2013 A
40
100%
NCR-S197
10
22-08-2013 A
01-09-2013 A
100%
211
14
25-01-2013 A
25-01-2013 A
09-09-2013 A
05-07-2013 A
902
80
100%
A9010
Install Conduits
13
27-01-2013 A
12-07-2013 A
772
100%
Install Conduits
A9030
13
27-01-2013 A
11-07-2013 A
50
100%
NCR-S228
09-09-2013 A
09-09-2013 A
100%
64
2
04-04-2013 A
04-04-2013 A
30-06-2013 A
29-04-2013 A
330
55
100%
A1680
03-05-2013 A
10-05-2013 A
55
100%
A1840
14-05-2013 A
19-05-2013 A
110
100%
A1860
06-06-2013 A
30-06-2013 A
110
100%
342
147
13
16-01-2013 A
22-01-2013 A
22-01-2013 A
03-12-2013 A
25-11-2013 A
04-02-2013 A
33407
6038
0
100%
NCR-S008
13
22-01-2013 A
04-04-2013 A
100%
NCR-S023
13
22-01-2013 A
04-02-2013 A
100%
NCR-S026
GTG3: Cast in plates embedded to the GT3 Generator are in wrong orientation
13
22-01-2013 A
04-02-2013 A
100%
GTG3: Cast in plates embedded to the GT3 Generator are in wrong orientation
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 5 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
13
Total
Float
Activity % S
Complete
NCR-S003
GTG3 Diffuser expansion joint does not fit to the diffuser ring
30-01-2013 A
04-04-2013 A
100%
GTG3 Diffuser expansion joint does not fit to the diffuser ring
NCR-S004
GTG3: Length of Structural bolts on the Lube Oil Cooler supports does not comply with
13Aus. Standards
30-01-2013 A
04-04-2013 A
100%
GTG3: Length of Structural bolts on the Lube Oil Cooler supports does not comply with Aus. Standard
NCR-S005
GTG3: The Stair on the GT-Room supplied does not fit onto the platform
13
02-02-2013 A
04-04-2013 A
100%
GTG3: The Stair on the GT-Room supplied does not fit onto the platform
NCR-S006
GTG3: The supplied platform in between the GT3 and Starter Motor is 50mm too wide13
08-02-2013 A
04-04-2013 A
100%
GTG3: The supplied platform in between the GT3 and Starter Motor is 50mm too wide
NCR-S007
13
08-02-2013 A
04-04-2013 A
100%
NCR-S009
GTG3: 6 holes missing from walkway platform on the top of the Steel Enclosure
13
08-02-2013 A
04-04-2013 A
100%
GTG3: 6 holes missing from walkway platform on the top of the Steel Enclosure
NCR-S010
13
10-02-2013 A
15-04-2013 A
100%
NCR-S012
The mounting foot on electrical motor 3GV1210878154003 on top of GTG3 lube oil cooler
13 is cracked
14-02-2013 A
15-04-2013 A
100%
The mounting foot on electrical motor 3GV1210878154003 on top of GTG3 lube oil cooler is cracked
NCR-S013
GTG3: Hand Rails, Kick Plates, Ladders, Cages, Hoists are not paint Yellow Y14 as per
125SPEC-000-S-00061
18-02-2013 A
02-07-2013 A
100%
NCR-S014
13
19-02-2013 A
19-02-2013 A
100%
NCR-S015
13
19-02-2013 A
04-03-2013 A
100%
NCR-S019
14
21-02-2013 A
07-03-2013 A
100%
NCR-S020
GTG3: Item not paint yellow Y14 as per SPEC-000-S-00061- lifting beam
13
22-02-2013 A
07-03-2013 A
100%
GTG3: Item not paint yellow Y14 as per SPEC-000-S-00061- lifting beam
NCR-S021
13
24-02-2013 A
09-03-2013 A
100%
NCR-S022
25-02-2013 A
02-03-2013 A
100%
NCR-S024
13
02-03-2013 A
15-03-2013 A
100%
NCR-S025
13
03-03-2013 A
16-03-2013 A
100%
NCR-S027
13
03-03-2013 A
16-03-2013 A
100%
NCR-S031
13
11-03-2013 A
24-03-2013 A
100%
NCR-S032
GTG3: GT3 Installation of Wall Cladding: Clashing of the wall Cladding and Slurry Wall13
11-03-2013 A
24-03-2013 A
100%
GTG3: GT3 Installation of Wall Cladding: Clashing of the wall Cladding and Slurry Wall
NCR-S036
GTG3: GT3 Lube Oil Cooler: Current Cabling does not comply with AS/BHPBIO Standards
20
21-03-2013 A
11-04-2013 A
100%
NCR-S038
13
22-03-2013 A
04-04-2013 A
100%
NCR-S039
71
22-03-2013 A
06-06-2013 A
100%
NCR-S041
GTG3: The Air Intake platform have been fabricated to superseded drawings
24
25-03-2013 A
18-04-2013 A
100%
GTG3: The Air Intake platform have been fabricated to superseded drawings
NCR-S043
GTG3: The Supplied 2 x Beams for the Air Intake Step Platform 50mm too long.
13
28-03-2013 A
10-04-2013 A
100%
GTG3: The Supplied 2 x Beams for the Air Intake Step Platform 50mm too long.
NCR-S045
13
30-03-2013 A
18-04-2013 A
100%
NCR-S046
01-04-2013 A
10-04-2013 A
100%
NCR-S047
36
01-04-2013 A
09-05-2013 A
100%
NCR-S042
13
05-04-2013 A
18-04-2013 A
100%
NCR-S050
GTG3: Kick plate welded in wrong direction and bolt holes in wrong orientation
13
05-04-2013 A
18-04-2013 A
100%
GTG3: Kick plate welded in wrong direction and bolt holes in wrong orientation
NCR-S075
13
09-05-2013 A
01-07-2013 A
100%
NCR-S077
10-05-2013 A
14-05-2013 A
100%
NCR-S086
21-05-2013 A
27-05-2013 A
100%
NCR-S087
GTG3: The propane cabinet clashing to the cast-in conduits from the foundation
13
22-05-2013 A
04-06-2013 A
100%
GTG3: The propane cabinet clashing to the cast-in conduits from the foundation
NCR-S088
13
22-05-2013 A
04-06-2013 A
100%
NCR-S092
GTG3: GT-3 Generator cooling duct doesn't line up with inlet duct - 55mm too high
17
29-05-2013 A
16-06-2013 A
100%
GTG3: GT-3 Generator cooling duct doesn't line up with inlet duct - 55mm too high
NCR-S090
13
02-06-2013 A
15-06-2013 A
100%
NCR-S107
04-06-2013 A
10-06-2013 A
100%
NCR-S109
19
08-06-2013 A
27-06-2013 A
100%
NCR-S110
08-06-2013 A
14-06-2013 A
100%
NCR-S111
70
09-06-2013 A
22-08-2013 A
100%
NCR-S115
22
09-06-2013 A
02-07-2013 A
100%
NCR-S118
11-06-2013 A
17-06-2013 A
100%
NCR-S119
60
13-06-2013 A
16-08-2013 A
100%
NCR-S130
GTG3: GT3- Lube Oil Unit Piping showing signs of rusting internally
21
20-06-2013 A
11-07-2013 A
100%
NCR-S131
21-06-2013 A
27-06-2013 A
100%
NCR-S146
60
05-07-2013 A
06-09-2013 A
100%
NCR-S152
19
11-07-2013 A
31-07-2013 A
100%
RMW025
17
14-07-2013 A
01-08-2013 A
76
100%
VEGT3000
VE GTG 3 - Install extra cables for GT's, commissioning assist for switchroom, punchlists
44
17-07-2013 A
30-08-2013 A
1275
100%
NCR-S162
12
26-07-2013 A
07-08-2013 A
100%
NCR-S163
28-07-2013 A
04-08-2013 A
100%
NCR-S180
07-08-2013 A
14-08-2013 A
100%
NCR-S205
28-08-2013 A
01-09-2013 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 6 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
GTG3: Hand Rails, Kick Plates, Ladders, Cages, Hoists are not paint Yellow Y14 as per
GTG3 Clashing of conduits and platform support legs
GTG3: GT3 Lube Oil Cooler: Current Cabling does not comply with AS/BHPBIO Standards
GTG3: GTG Generator Ventilation Inlet Duct Obstructing Electrical Cabinet
GTG3: GT3 FAIST Air Inlet Roof Penetration
VE GTG 3 - Install extra cables for GT's, commissioning assist for switchroom, p
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
VEGT3010
15-10-2013 A
3073
100%
NCR-S210
14
31-08-2013 A
14-09-2013 A
100%
NCR-S212
28
31-08-2013 A
29-09-2013 A
100%
33
31-08-2013 A
04-10-2013 A
309
100%
15-09-2013 A
15-09-2013 A
100%
VE GTG 3 -Punchlisting Electrical, outage items, commissioning support, Evap drain mods
11
30-10-2013 A
10-11-2013 A
679
100%
19-11-2013 A
25-11-2013 A
626
100%
192
5
16-01-2013 A
16-01-2013 A
18-09-2013 A
19-01-2013 A
10624
100
100%
A2060
16-01-2013 A
20-01-2013 A
250
100%
A2070
Placement of GT
17-01-2013 A
21-01-2013 A
190
100%
Placement of GT
A2150
Placement of Diffuser
18-01-2013 A
24-01-2013 A
190
100%
Placement of Diffuser
A2330
22-01-2013 A
31-05-2013 A
300
100%
A2370
22-01-2013 A
12-06-2013 A
150
100%
A2170
23-01-2013 A
06-03-2013 A
450
100%
A2250
Placement of Generator
23-01-2013 A
26-01-2013 A
190
100%
A2300
24-01-2013 A
31-05-2013 A
250
100%
A2160
26-01-2013 A
23-02-2013 A
500
100%
A2310
12
26-01-2013 A
21-05-2013 A
1120
100%
A2270
28-01-2013 A
20-05-2013 A
400
100%
A2190
Connect Diffuser
05-02-2013 A
03-03-2013 A
380
100%
A2180
12-02-2013 A
16-03-2013 A
550
100%
A2200
19
24-02-2013 A
10-07-2013 A
2590
100%
A2230
20
04-03-2013 A
26-07-2013 A
312
100%
A2240
13
10-03-2013 A
19-04-2013 A
275
100%
A2260
11-03-2013 A
26-04-2013 A
300
100%
A2340
16-03-2013 A
19-07-2013 A
500
100%
A2380
17-03-2013 A
26-07-2013 A
250
100%
A2290
26-04-2013 A
31-05-2013 A
750
100%
A2220
20-05-2013 A
19-07-2013 A
250
100%
A2350
09-06-2013 A
28-08-2013 A
190
100%
A2390
20-07-2013 A
18-09-2013 A
187
100%
107
56
13
13-02-2013 A
14-04-2013 A
14-04-2013 A
06-08-2013 A
11-07-2013 A
11-07-2013 A
3281
990
990
100%
Connect Diffuser
Placement of Steel Enclosure
Install Enclusure Pannels and Cladding Around Piping Penetrations
Install Ventilation Ducts- Platform & Access Ladder
A18010
14-04-2013 A
22-04-2013 A
100%
A18000
10
02-05-2013 A
11-07-2013 A
100%
A18030
10
20-05-2013 A
11-07-2013 A
100%
64
24
13-02-2013 A
13-02-2013 A
19-07-2013 A
19-07-2013 A
1200
1200
100%
A17970
13-02-2013 A
14-07-2013 A
100%
A18020
10
11-05-2013 A
19-07-2013 A
100%
A18040
15
20-05-2013 A
19-07-2013 A
100%
17
6
27-06-2013 A
27-06-2013 A
05-07-2013 A
05-07-2013 A
125
125
100%
A17990
27-06-2013 A
05-07-2013 A
100%
A17980
27-06-2013 A
05-07-2013 A
100%
28
28
02-04-2013 A
02-04-2013 A
30-04-2013 A
30-04-2013 A
32
32
100%
02-04-2013 A
30-04-2013 A
100%
18
11
22-06-2013 A
22-06-2013 A
06-08-2013 A
02-08-2013 A
934
934
YARNIMA.11.8.1.3.5 Insulation
A2400
Install Piping Insulation
100%
A18050
22-06-2013 A
06-08-2013 A
100%
A18060
22-06-2013 A
04-08-2013 A
100%
314
17-02-2013 A
11-10-2013 A
10000
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 7 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
VEGT3030
VEGT3020
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
YARNIMA.11.8.1.2.1 Cable Ladder
A1630
Cable Ladder - Culverts Switchroom to GTG No.3
A1620
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
23
12
17-02-2013 A
17-02-2013 A
29-03-2013 A
06-03-2013 A
1295
333
100%
10
24-03-2013 A
29-03-2013 A
962
100%
314
2
18-02-2013 A
18-02-2013 A
11-10-2013 A
19-02-2013 A
719
98
100%
Install GT 3 Switchroom
06-03-2013 A
12-04-2013 A
314
100%
A1600
07-03-2013 A
05-07-2013 A
307
100%
NCR-S072
154
29-04-2013 A
11-10-2013 A
100%
NCR-S065
30-07-2013 A
03-08-2013 A
100%
254
28
24-03-2013 A
24-03-2013 A
31-08-2013 A
26-07-2013 A
1692
1692
100%
NCR-S064
131
12-04-2013 A
30-08-2013 A
100%
NCR-S095
11
03-06-2013 A
13-06-2013 A
100%
NCR-S120
19
15-06-2013 A
04-07-2013 A
100%
NCR-S126
70
18-06-2013 A
31-08-2013 A
100%
NCR-S124
13
18-06-2013 A
01-07-2013 A
100%
NCR-S063
GTG3: Replacement of Siemens power outlet in turbine enclosure - not a standard power
5 outlet
30-07-2013 A
YARNIMA.11.8.1.2.4 Cabling
A1640
LV-C & I Cabling
A1590
03-08-2013 A
100%
254
28
16-03-2013 A
16-03-2013 A
31-08-2013 A
20-06-2013 A
4276
2544
100%
A2130
02-04-2013 A
15-04-2013 A
535
100%
A1670
14
03-04-2013 A
11-05-2013 A
327
100%
A1930
23-04-2013 A
30-04-2013 A
201
100%
NCR-S070
120
24-04-2013 A
30-08-2013 A
100%
A1850
13
21-05-2013 A
05-07-2013 A
669
100%
NCR-S089
BOP: The conduits coming out of the substation install by others at an incorrect depth 7
23-05-2013 A
29-05-2013 A
100%
NCR-S103
83
03-06-2013 A
30-08-2013 A
100%
NCR-S096
03-06-2013 A
08-06-2013 A
100%
NCR-S097
GTG3: Gland plate provided is not suited to the amount of the cable
20
03-06-2013 A
23-06-2013 A
100%
NCR-S098
28
03-06-2013 A
02-07-2013 A
100%
NCR-S099
19
03-06-2013 A
22-06-2013 A
100%
NCR-S100
13
03-06-2013 A
16-06-2013 A
100%
NCR-S101
64
03-06-2013 A
09-08-2013 A
100%
NCR-S113
21
09-06-2013 A
01-07-2013 A
100%
NCR-S114
13
09-06-2013 A
22-06-2013 A
100%
NCR-S117
13
09-06-2013 A
22-06-2013 A
100%
NCR-S137
61
27-06-2013 A
31-08-2013 A
100%
NCR-S171
01-08-2013 A
06-08-2013 A
100%
156
57
01-04-2013 A
01-04-2013 A
27-07-2013 A
31-05-2013 A
1589
0
100%
35
10-04-2013 A
27-07-2013 A
1129
100%
A1690
29
24-04-2013 A
20-07-2013 A
460
100%
NCR-S127
18-06-2013 A
21-06-2013 A
100%
NCR-S142
13
02-07-2013 A
03-07-2013 A
100%
134
31
06-05-2013 A
06-05-2013 A
16-08-2013 A
30-07-2013 A
0
0
100%
100%
13
03-06-2013 A
16-06-2013 A
NCR-S138
46
29-06-2013 A
16-08-2013 A
100%
21
21
10-04-2013 A
10-04-2013 A
25-07-2013 A
25-07-2013 A
408
408
100%
14
14
09-07-2013 A
09-07-2013 A
02-08-2013 A
02-08-2013 A
21
21
100%
7
7
17-07-2013 A
17-07-2013 A
24-07-2013 A
24-07-2013 A
11
11
100%
145
10
09-03-2013 A
09-03-2013 A
03-12-2013 A
03-12-2013 A
3453
0
100%
YARNIMA.11.8.1.4 INSTRUMENTS
A9040
Install Stage 1 Instruments
YARNIMA.11.8.1.5 PHASE 1 PRE-COMMISSIONING
A22990
Mechanical and Electrical Pre-Commissioning and punchlisting B & C-Items
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 8 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
NCR-S067
13
12-04-2013 A
25-04-2013 A
100%
A1570
21
31-05-2013 A
25-09-2013 A
532
100%
A3220
14
20-06-2013 A
26-09-2013 A
50
100%
A2040
10
28-06-2013 A
24-09-2013 A
80
100%
A1740
33
29-06-2013 A
27-09-2013 A
650
100%
VEGT3523
101
09-08-2013 A
25-11-2013 A
2141
100%
A2080
Construction Verification
27-09-2013 A
100%
YARNIMA.10 PHASE 2
YARNIMA.10.10 COMPANY DELIVERABLES
YARNIMA.10.10.1 ENGINEERING DELIVERABLES
YARNIMA.10.10.1.1 GA & DETAILED ASSEMBLY DWGS
A7770
GT2 & GT1 GA & Detailed Assembly Dwgs
YARNIMA.10 PHASE 2
323515
216
15-10-2012 A
28-07-2013 A
216
164
0
15-10-2012 A
01-02-2013 A
01-02-2013 A
28-07-2013 A
28-07-2013 A
0
0
0
05-04-2013 A
100%
A5980
28-07-2013 A
100%
A5990
28-07-2013 A
100%
0
0
21-12-2012 A
21-12-2012 A
21-12-2012 A
0
0
21-12-2012 A
21-12-2012 A
108
0
15-10-2012 A
15-10-2012 A
YARNIMA.10.10.1.3 STRUCTURAL
A5390
Stage 2 Piperack Dwgs AFC
YARNIMA.10.10.1.4 MECHANICAL
A5600
Pump Data Sheets Issued
Construction Verification
27-06-2014
15-10-2012 A
A5860
495
A7780
YARNIMA.10.10.1.2 CIVIL
A5370
Stage 2 Buried Services Trench Layout Dwgs AFC
21-12-2012 A
0
0
100%
100%
21-12-2012 A
0
0
100%
30-03-2013 A
0
0
100%
A5420
05-11-2012 A
100%
A5460
17-12-2012 A
100%
A5560
21-12-2012 A
100%
A5410
01-01-2013 A
100%
A6440
04-01-2013 A
100%
A5440
30-03-2013 A
100%
216
0
15-10-2012 A
15-10-2012 A
0
0
100%
YARNIMA.10.10.1.5 ELECTRICAL
A5510
BSDG Electrical Dwgs AFC
25-07-2013 A
A7940
15-10-2012 A
100%
A5500
04-11-2012 A
100%
A5480
28-11-2012 A
100%
A5490
28-11-2012 A
100%
A5530
25-07-2013 A
100%
0
0
21-12-2012 A
21-12-2012 A
21-12-2012 A
0
0
100%
72
72
0
22-02-2013 A
22-02-2013 A
22-02-2013 A
08-05-2013 A
08-05-2013 A
0
0
0
100%
A5750
GT2 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip
0
24-02-2013 A
100%
GT2 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip
A5730
24-03-2013 A
100%
A5720
GT1 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip
0
06-04-2013 A
100%
A7920
01-05-2013 A
100%
A7750
02-05-2013 A
100%
A5770
03-05-2013 A
100%
A5760
08-05-2013 A
100%
0
0
01-03-2013 A
01-03-2013 A
01-03-2013 A
0
0
100%
273
02-02-2013 A
16-11-2013 A
59
0
18-03-2013 A
18-03-2013 A
10-06-2013 A
0
0
100%
A1170
25-05-2013 A
100%
A1190
06-06-2013 A
100%
A1180
GT-2 Switchroom
10-06-2013 A
100%
GT-2 Switchroom
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 9 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
YARNIMA.10.11.11 BLACK START GENERATOR ASSOCIATED EQUIPMENT
A1480
BSG 0.5MVA Auxillary Transformer
A1490
BSDG Switchroom
Original
Duration
Start
Finish
Budgeted
Labor Units
107
0
30-06-2013 A
30-06-2013 A
16-11-2013 A
0
0
100%
16-11-2013 A
100%
59
0
15-04-2013 A
15-04-2013 A
0
0
BSDG Switchroom
YARNIMA.10.11.3 GAS TURBINE 1 & ASSOCIATED EQUIPMENT
100%
26-06-2013 A
Total
Float
Activity % S
Complete
A1210
25-05-2013 A
100%
A1220
GT1 Switchroom
25-06-2013 A
100%
GT1 Switchroom
A1230
26-06-2013 A
100%
0
0
100%
164
02-02-2013 A
28-06-2013 A
YARNIMA.10.11.4 HRSG 3 & ASSOCIATED EQUIPMENT
A1310
HRSG-3 Main Stack- Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork
0
02-02-2013
& Spooled Piping
A
HRSG-3 Main Stack- Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork & Spooled Piping
A1320
07-05-2013 A
100%
A1750
28-06-2013 A
100%
A1770
28-06-2013 A
100%
0
0
100%
165
06-02-2013 A
18-07-2013 A
YARNIMA.10.11.6 HRSG 2 & ASSOCIATED EQUIPMENT
A1280
HRSG-2 Main Stack- Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork
0
06-02-2013
& Spooled Piping
A
HRSG-2 Main Stack- Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork & Spooled Pipin
A1270
09-04-2013 A
100%
A1290
27-04-2013 A
100%
A1780
28-06-2013 A
100%
A1790
28-06-2013 A
100%
A1800
28-06-2013 A
100%
NCR-S151
09-07-2013 A
18-07-2013 A
100%
112
24-03-2013 A
YARNIMA.10.11.5 HRSG 1 & ASSOCIATED EQUIPMENT
A1250
HRSG-1 Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork & Spooled
0
Piping
24-03-2013 A
12-07-2013 A
0
0
100%
A1240
16-04-2013 A
100%
A1260
27-04-2013 A
100%
A1810
02-07-2013 A
100%
A1820
04-07-2013 A
100%
A1830
12-07-2013 A
100%
67
0
19-06-2013 A
19-06-2013 A
0
0
100%
15-09-2013 A
A1380
STG MV Switchroom
06-09-2013 A
100%
A1360
15-09-2013 A
100%
A1370
15-09-2013 A
100%
74
0
20-05-2013 A
20-05-2013 A
0
0
100%
15-09-2013 A
STG MV Switchroom
A1390
STG LV Switchroom
06-09-2013 A
100%
A1410
15-09-2013 A
100%
A1420
15-09-2013 A
100%
87
0
07-05-2013 A
07-05-2013 A
0
0
100%
07-05-2013 A
100%
28-06-2013 A
STG LV Switchroom
STG-2 Auxillary 2.5 MVA Transformer
STG-2 Main 8 MVA Transformer
YARNIMA.10.11.10 STG'S ANCILLARY ITEMS
A1560
A1450
Steam Silencers (5 of: 2xStart up- 2xHigh Energy Drain Vessels-1xSteam Blow Silencer)
0
28-06-2013 A
100%
Steam Silencers (5 of: 2xStart up- 2xHigh Energy Drain Vessels-1xSteam Blow Silencer)
A1460
28-06-2013 A
100%
A1610
28-06-2013 A
100%
0
0
28-07-2013 A
28-07-2013 A
28-07-2013 A
0
0
100%
177
02-02-2013 A
04-10-2013 A
11-09-2013 A
126
30
02-02-2013 A
02-02-2013 A
100%
23-07-2013 A
23-05-2013 A
0
0
100%
02-05-2013 A
100%
A3430
A3440
08-05-2013 A
26-06-2013 A
100%
A3470
09-07-2013 A
16-07-2013 A
100%
A3450
Include Comments
17-07-2013 A
23-07-2013 A
100%
Include Comments
A3460
19-07-2013 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 10 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
YARNIMA.10.14.2 AUXILLARY COOLING WATER PUMPS FOUNDATIONS
A3410
Prepare Engineering Design Dwgs for Aux Cooling Water Pumps Fnds
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
126
30
02-02-2013 A
02-02-2013 A
09-08-2013 A
30-04-2013 A
0
0
100%
Prepare Engineering Design Dwgs for Aux Cooling Water Pumps Fnds
30-04-2013 A
100%
A7820
A7830
30-05-2013 A
06-06-2013 A
100%
A7840
Include Comments
06-07-2013 A
09-07-2013 A
100%
A7850
19-07-2013 A
100%
A7860
02-08-2013 A
09-08-2013 A
100%
127
30
02-02-2013 A
02-02-2013 A
15-08-2013 A
30-04-2013 A
0
0
100%
30-05-2013 A
100%
04-07-2013 A
100%
30-07-2013 A
100%
A7870
A7880
A7900
A7910
01-08-2013 A
15-08-2013 A
100%
A7890
Include Comments
02-08-2013 A
09-08-2013 A
100%
47
30
10-05-2013 A
10-05-2013 A
02-10-2013 A
04-08-2013 A
0
0
100%
31-07-2013 A
100%
30-05-2013 A
A11510
A11520
01-08-2013 A
07-08-2013 A
100%
A11530
Include Comments
01-08-2013 A
07-08-2013 A
100%
Include Comments
A11540
01-08-2013 A
100%
A11550
16-08-2013 A
02-10-2013 A
100%
50
30
05-05-2013 A
05-05-2013 A
04-10-2013 A
30-07-2013 A
0
0
100%
30-07-2013 A
04-10-2013 A
100%
A11580
A11600
01-08-2013 A
100%
A11570
06-08-2013 A
100%
A11590
Include Comments
08-08-2013 A
09-08-2013 A
100%
Include Comments
A11610
17-08-2013 A
01-10-2013 A
100%
57
30
01-08-2013 A
01-08-2013 A
05-08-2013 A
05-08-2013 A
0
0
100%
A11640
01-08-2013 A
05-08-2013 A
100%
A11650
Include Comments
01-08-2013 A
05-08-2013 A
100%
Include Comments
A11670
01-08-2013 A
05-08-2013 A
100%
A11630
05-08-2013 A
100%
A11660
05-08-2013 A
100%
29-01-2014 A
315
YARNIMA.10.8 PROCUREMENT
YARNIMA.10.8.1 STRUCTURAL
A22840
Supply, Fabricate, Deliver STG 2 External Platforms
15-10-2012 A
59
48
08-08-2013 A
08-08-2013 A
14-11-2013 A
02-11-2013 A
0
0
YARNIMA.10.8 PROCUREMENT
YARNIMA.10.8.1 STRUCTURAL
100%
A22820
54
08-08-2013 A
03-11-2013 A
100%
A22810
13
21-08-2013 A
05-11-2013 A
100%
A22830
48
21-08-2013 A
02-11-2013 A
100%
A11690
21
24-08-2013 A
13-11-2013 A
100%
A22850
21
24-08-2013 A
14-11-2013 A
100%
A11700
21
30-08-2013 A
13-11-2013 A
100%
A11680
10
01-10-2013 A
02-11-2013 A
100%
315
308
21
15-10-2012 A
15-10-2012 A
15-10-2012 A
29-01-2014 A
09-12-2013 A
21-12-2012 A
0
0
0
100%
21-12-2012 A
100%
Confirm Vendor
YARNIMA.10.8.2 MECHANICAL
YARNIMA.10.8.2.15 COOLING WATER PUMPS
A8430
Finalise Vendor Design Deliverables
A8440
Confirm Vendor
A8450
21-12-2012 A
21-12-2012 A
100%
A8460
Include Comments
21-12-2012 A
21-12-2012 A
100%
Include Comments
A8470
21-12-2012 A
100%
A8480
21-12-2012 A
21-12-2012 A
100%
A8490
Issue PO
21-12-2012 A
21-12-2012 A
100%
Issue PO
A8500
306
05-01-2013 A
06-12-2013 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 11 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A8930
Deliver to Perth CW Pump Base Plates, Motors & Dummy Pump Frame
06-12-2013 A
100%
A8940
09-12-2013 A
100%
A8950
Deliver to Site CW Pump Base Plates, Motors & Dummy Pump Frames
09-12-2013 A
100%
10-01-2014 A
21-12-2012 A
0
0
100%
21-12-2012 A
100%
Confirm Vendor
241
21
15-10-2012 A
15-10-2012 A
A8520
Confirm Vendor
A8530
21-12-2012 A
21-12-2012 A
100%
A8540
Include Comments
21-12-2012 A
21-12-2012 A
100%
Include Comments
A8550
21-12-2012 A
100%
A8560
21-12-2012 A
21-12-2012 A
100%
A8570
Issue PO
21-12-2012 A
21-12-2012 A
100%
Issue PO
A8580
146
20-01-2013 A
12-12-2013 A
100%
A8970
10-01-2014 A
100%
29-01-2014 A
21-12-2012 A
0
0
100%
21-12-2012 A
100%
Confirm Vendor
0
315
21
YARNIMA.10.8.2.4 BSDG
A1100
Finalise Vendor Design Deliverables
10-12-2012 A
10-12-2012 A
A1940
Confirm Vendor
A2020
21-12-2012 A
21-12-2012 A
100%
A2090
Include Comments
21-12-2012 A
21-12-2012 A
100%
Include Comments
A2100
21-12-2012 A
100%
A2110
21-12-2012 A
21-12-2012 A
100%
A2120
Issue PO
21-12-2012 A
21-12-2012 A
100%
Issue PO
A1330
314
10-01-2013 A
29-01-2014 A
100%
213
21
02-11-2012 A
02-11-2012 A
25-09-2013 A
21-12-2012 A
0
0
100%
22-01-2013 A
01-02-2013 A
100%
23-01-2013 A
100%
05-02-2013 A
100%
Include Comments
05-02-2013 A
100%
A8070
A8060
Confirm Vendor
A8080
Include Comments
A8090
A8100
06-02-2013 A
15-02-2013 A
100%
A8110
Issue PO
16-02-2013 A
18-02-2013 A
100%
Issue PO
A8120
177
17-02-2013 A
25-09-2013 A
100%
267
21
02-11-2012 A
02-11-2012 A
29-11-2013 A
21-12-2012 A
0
0
100%
05-02-2013 A
100%
01-02-2013 A
A8140
Confirm Vendor
A8150
19-02-2013 A
25-02-2013 A
100%
A8160
Include Comments
25-02-2013 A
28-02-2013 A
100%
Include Comments
A8170
01-03-2013 A
100%
A8180
02-03-2013 A
05-03-2013 A
100%
A8190
Issue PO
06-03-2013 A
07-03-2013 A
100%
Issue PO
A8200
177
20-04-2013 A
29-11-2013 A
100%
246
21
02-11-2012 A
02-11-2012 A
29-11-2013 A
21-12-2012 A
0
0
100%
15-01-2013 A
100%
Confirm Vendor
Client Review & Comment
Confirm Vendor
A8220
Confirm Vendor
A8230
15-01-2013 A
20-01-2013 A
100%
A8240
Include Comments
01-02-2013 A
03-02-2013 A
100%
Include Comments
A8250
06-02-2013 A
100%
A8260
07-02-2013 A
09-02-2013 A
100%
A8270
Issue PO
10-02-2013 A
11-02-2013 A
100%
Issue PO
A8280
44
06-04-2013 A
29-11-2013 A
100%
A8960
Deliver to Perth
12-06-2013 A
100%
A8980
Deliver to Site
168
21
A8300
Confirm Vendor
A8310
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
02-11-2012 A
02-11-2012 A
21-12-2012 A
Page 12 of 38
Data Date 07-02-2014
29-11-2013 A
100%
25-09-2013 A
21-12-2012 A
0
0
100%
21-12-2012 A
100%
Confirm Vendor
21-12-2012 A
100%
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Deliver to Site
YARNIMA.10.8.2.5 LARGE BORE HP STEAM PIPING
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
21-12-2012 A
21-12-2012 A
100%
Include Comments
21-12-2012 A
100%
A8320
Include Comments
A8330
A8340
21-12-2012 A
21-12-2012 A
100%
A8350
Issue PO
30-01-2013 A
01-02-2013 A
100%
A8360
112
09-03-2013 A
25-09-2013 A
100%
108
108
07-06-2013 A
07-06-2013 A
25-09-2013 A
25-09-2013 A
0
0
100%
YARNIMA.10.8.2.1 PIPERACK
A1430
Finalise Tender Package for Stage 2 Piperack
243
21
15-10-2012 A
15-10-2012 A
11-09-2013 A
12-11-2012 A
0
0
100%
14-12-2012 A
08-02-2013 A
100%
A5590
24
14-01-2013 A
20-02-2013 A
100%
A5940
14
01-03-2013 A
29-08-2013 A
100%
A5950
10-03-2013 A
08-09-2013 A
100%
A5950-a
10
01-09-2013 A
11-09-2013 A
100%
69
60
21-12-2012 A
21-12-2012 A
20-04-2013 A
25-03-2013 A
0
0
100%
45
25-01-2013 A
20-04-2013 A
100%
122
7
25-01-2013 A
25-01-2013 A
10-03-2013 A
04-02-2013 A
0
0
100%
04-02-2013 A
100%
Confirm Vendor
A12210
Confirm Vendor
A12220
05-02-2013 A
11-02-2013 A
100%
A12230
Include Comments
12-02-2013 A
14-02-2013 A
100%
Include Comments
A12240
14-02-2013 A
100%
A12250
15-02-2013 A
21-02-2013 A
100%
A12260
Issue PO
22-02-2013 A
22-02-2013 A
100%
Issue PO
A12200
103
23-02-2013 A
10-03-2013 A
100%
126
126
15-01-2013 A
15-01-2013 A
30-06-2013 A
30-06-2013 A
0
0
100%
102
102
25-01-2013 A
25-01-2013 A
06-03-2013 A
06-03-2013 A
0
0
100%
101
21
17-12-2012 A
17-12-2012 A
25-03-2013 A
05-01-2013 A
0
0
100%
05-01-2013 A
100%
Confirm Vendor
A12130
Confirm Vendor
A12140
05-01-2013 A
12-01-2013 A
100%
A12150
Include Comments
10-01-2013 A
13-01-2013 A
100%
Include Comments
A12160
14-01-2013 A
100%
A12170
15-01-2013 A
20-01-2013 A
100%
A12180
Issue PO
21-01-2013 A
21-01-2013 A
100%
Issue PO
A12120
60
23-01-2013 A
25-03-2013 A
100%
173
21
02-02-2013 A
02-02-2013 A
16-09-2013 A
21-02-2013 A
0
0
100%
14
A8920
Issue PO
A5900
A12080
21
05-06-2013 A
02-07-2013 A
100%
A12070
24
30-07-2013 A
13-09-2013 A
100%
A12100
24
27-08-2013 A
16-09-2013 A
100%
24
24
09-08-2013 A
09-08-2013 A
14-10-2013 A
14-10-2013 A
0
0
100%
136
136
29-03-2013 A
29-03-2013 A
25-09-2013 A
25-09-2013 A
0
0
100%
163
110
40
26-02-2013 A
30-04-2013 A
30-04-2013 A
06-12-2013 A
06-12-2013 A
30-05-2013 A
0
0
0
100%
YARNIMA.10.8.3 ELECTRICAL
YARNIMA.10.8.3.1 STAGE 2 ELECTRICAL EQUIPMENT
A5640
GT1 & GT2 Electrical Equip (Review- Procure & Deliver)
A5650
40
30-07-2013 A
01-09-2013 A
100%
A5660
40
01-08-2013 A
13-09-2013 A
100%
A5670
40
04-08-2013 A
06-12-2013 A
100%
98
98
28-04-2013 A
28-04-2013 A
30-06-2013 A
30-06-2013 A
0
0
100%
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 13 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Stage 2 VSD & Other Specialist Cable (Review- Procure & Deliver)
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
A5680
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
30
30-04-2013 A
30-06-2013 A
100%
163
21
26-02-2013 A
26-02-2013 A
23-11-2013 A
02-04-2013 A
0
0
100%
05-03-2013 A
100%
Confirm Vendor
Client Review & Comment
A8860
06-03-2013 A
08-03-2013 A
100%
A8870
Include Comments
11-03-2013 A
14-03-2013 A
100%
A8880
21-03-2013 A
100%
A8890
22-03-2013 A
28-03-2013 A
100%
A8900
Issue PO
29-03-2013 A
30-03-2013 A
100%
Issue PO
A8910
149
22-05-2013 A
23-11-2013 A
100%
462
02-01-2013 A
27-06-2014
323515
32
0
24-03-2014
27-04-2014
24-03-2014
0
0
57
89
0%
27-04-2014
57
0%
19-11-2013 A
03-07-2013 A
0
0
0
100%
100%
0
0
100%
A13960
YARNIMA.10.15.10 PRELIMINARIES
YARNIMA.10.15.10.1 SERVICES
A10420
Receipt Verification of Stage 2 MV Cables
A10430
YARNIMA.10.15.10.11 HRSG 3
A10360
Receipt Verification of HRSG3 Fnd
288
168
0
02-01-2013 A
01-03-2013 A
01-03-2013 A
03-07-2013 A
288
0
02-01-2013 A
02-01-2013 A
30-06-2013 A
Include Comments
Submit For Final Approval
A10370
02-02-2013 A
100%
A10380
03-03-2013 A
100%
A10680
Receipt Verification of HRSG3 Switchroom (incl Control Systems- BMS & Panels)
09-05-2013 A
100%
A10650
15-05-2013 A
100%
A10660
15-05-2013 A
100%
A10670
30-06-2013 A
100%
0
0
100%
107
24-02-2013 A
10-06-2013 A
YARNIMA.10.15.10.2 GT2
A9380
Receipt Verification of GT2 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery
0 Rooms)
24-02-2013
Ready forAEquip
A9430
20-03-2013 A
100%
A9590
25-05-2013 A
100%
A9560
06-06-2013 A
100%
A9530
10-06-2013 A
100%
189
0
03-05-2013 A
03-05-2013 A
0
0
100%
YARNIMA.10.15.10.13 BSDG
A13200
Receipt Verification of BSDG Aux Transformer Fnd
19-11-2013 A
A13630
04-05-2013 A
100%
A13660
01-07-2013 A
100%
A13670
19-11-2013 A
100%
0
0
100%
62
07-04-2013 A
26-06-2013 A
YARNIMA.10.15.10.5 GT1
A9460
Receipt Verification of GT1 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery
0 Rooms)
07-04-2013
Ready forAEquip
Receipt Verification of GT1 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Rea
A9470
17-04-2013 A
100%
A12290
25-05-2013 A
100%
A12270
25-06-2013 A
100%
A12280
26-06-2013 A
100%
233
0
25-03-2013 A
25-03-2013 A
0
0
100%
YARNIMA.10.15.10.6 HRSG 1
A9490
Receipt Verification of HRSG1 Free Issue Material & Equip
13-07-2013 A
Confirm Vendor
A8850
A9480
08-04-2013 A
100%
A13650
17-04-2013 A
100%
A12320
Receipt Verification of HRSG1 Switchroom (incl Control Systems- BMS & Panels)
28-04-2013 A
100%
A12310
04-07-2013 A
100%
A9500
05-07-2013 A
100%
A12300
13-07-2013 A
100%
150
0
06-02-2013 A
06-02-2013 A
0
0
100%
YARNIMA.10.15.10.3 HRSG 2
A9440
Receipt Verification of HRSG2 Free Issue Material & Equip
22-05-2013 A
A9390
22-02-2013 A
100%
A13640
10-04-2013 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 14 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A10220
Receipt Verification of HRSG2 Switchroom (incl Control Systems- BMS & Panels)
28-04-2013 A
100%
A9450
22-05-2013 A
100%
A10170
22-05-2013 A
100%
A10180
22-05-2013 A
100%
146
0
11-05-2013 A
11-05-2013 A
0
0
100%
YARNIMA.10.15.10.7 ST1
A9510
Receipt Verification of ST1 Fnd
16-09-2013 A
Receipt Verification of HRSG2 Switchroom (incl Control Systems- BMS & Panels)
A9520
19-06-2013 A
100%
A12370
02-07-2013 A
100%
A12380
05-07-2013 A
100%
A10410
07-09-2013 A
100%
A10250
16-09-2013 A
100%
A10400
16-09-2013 A
100%
146
0
07-05-2013 A
07-05-2013 A
0
0
100%
YARNIMA.10.15.10.8 ST2
A12390
Receipt Verification of ST2 High Energy Drain Vessels
16-09-2013 A
A9540
11-05-2013 A
100%
A9550
20-05-2013 A
100%
A12360
02-07-2013 A
100%
A12350
08-09-2013 A
100%
A12330
16-09-2013 A
100%
A12340
16-09-2013 A
100%
142
0
06-05-2013 A
06-05-2013 A
0
0
100%
15-07-2013 A
100%
71
0
06-05-2013 A
06-05-2013 A
0
0
100%
15-07-2013 A
100%
0
0
29-07-2013 A
29-07-2013 A
29-07-2013 A
0
0
323
13
13
22-03-2013 A
21-07-2013 A
21-07-2013 A
27-04-2014
03-08-2013 A
03-08-2013 A
58127
0
0
101
12
29-07-2013 A
29-07-2013 A
25-11-2013 A
09-08-2013 A
2663
0
100%
02-08-2013 A
09-08-2013 A
100%
11-08-2013 A
12-08-2013 A
52
100%
NCR-S196
HRSG3: The kickplate of the Burner platform of the HRSG-3 is clashing to the stiffener3beam of20-08-2013
the HRSG A
22-08-2013 A
100%
NCR-S201
25-08-2013 A
01-09-2013 A
100%
VESITE1000
VE SITE - make good defective welds on lub oil system, corridor deliniation for HV Line5Energisation
01-09-2013 A
05-09-2013 A
128
100%
VE SITE - make good defective welds on lub oil system, corridor deliniation for
15-07-2013 A
15-07-2013 A
100%
57
100%
HRSG3: The kickplate of the Burner platform of the HRSG-3 is clashing to the st
79
02-09-2013 A
19-11-2013 A
100%
NCR-S274
06-10-2013 A
14-10-2013 A
100%
VESITE1234
14-10-2013 A
14-10-2013 A
256
100%
18
15-10-2013 A
03-11-2013 A
38
100%
VESITE1321
27-10-2013 A
28-10-2013 A
604
100%
VESITE1010
VE SITE - Design clash Blowdown pit/GRE piping, Waiting on permits to be signed by20
WP, and05-11-2013
intermittent Arain events
25-11-2013 A
510
100%
VESITE1446
100%
17-11-2013 A
18-11-2013 A
1075
295
295
22-03-2013 A
22-03-2013 A
18-03-2014
18-03-2014
16098
0
172
145
28
27-04-2013 A
27-04-2013 A
27-04-2013 A
17-12-2013 A
24-10-2013 A
14-09-2013 A
6588
6006
836
100%
30
20-05-2013 A
13-09-2013 A
4208
100%
Install Pipes
12
21-07-2013 A
02-08-2013 A
100%
BOP: HDPE Pipe Clashes with Pedestals Behind the Cooling Tower
NCR-S169 BOP: No openings in Culvert or Discharge Pit - Demin water line (HRSG lines 1,2 &3) 8
31-07-2013 A
07-08-2013 A
100%
BOP: No openings in Culvert or Discharge Pit - Demin water line (HRSG lines 1,2 &
A13610
28
07-08-2013 A
08-10-2013 A
620
100%
A13920
Hydrotest
14
02-10-2013 A
24-10-2013 A
342
100%
Install Pipes
NCR-S156 BOP: HDPE Pipe Clashes with Pedestals Behind the Cooling Tower
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 15 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
94
94
0%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
30
30
17-08-2013 A
17-08-2013 A
20-10-2013 A
20-10-2013 A
81
81
100%
15-09-2013 A
15-10-2013 A
100%
25
25
17-08-2013 A
17-08-2013 A
01-12-2013 A
01-12-2013 A
361
105
100%
21
22-08-2013 A
17-10-2013 A
256
100%
18
18
02-10-2013 A
02-10-2013 A
17-12-2013 A
17-12-2013 A
140
140
100%
08-10-2013 A
13-12-2013 A
100%
15-08-2013 A
30-08-2013 A
30-08-2013 A
16-01-2014 A
27-11-2013 A
27-11-2013 A
2235
1325
120
100%
21
04-09-2013 A
27-11-2013 A
1205
100%
31
31
15-08-2013 A
15-08-2013 A
20-10-2013 A
20-10-2013 A
110
110
100%
10
23-09-2013 A
06-10-2013 A
100%
30
10
08-10-2013 A
08-10-2013 A
28-11-2013 A
26-11-2013 A
120
0
100%
30
22-10-2013 A
28-11-2013 A
120
100%
69
69
15-09-2013 A
15-09-2013 A
26-11-2013 A
20-11-2013 A
430
130
100%
54
26-09-2013 A
26-11-2013 A
300
100%
55
55
01-09-2013 A
01-09-2013 A
19-09-2013 A
11-09-2013 A
140
140
100%
10
04-09-2013 A
19-09-2013 A
100%
20
20
09-10-2013 A
09-10-2013 A
16-01-2014 A
16-01-2014 A
110
110
100%
14-10-2013 A
15-01-2014 A
100%
30
29
29
02-08-2013 A
07-08-2013 A
07-08-2013 A
06-03-2014
20-02-2014
20-02-2014
2604
1646
165
105
118
118
90%
21
09-08-2013 A
17-02-2014
1481
118
90%
20
20
07-08-2013 A
07-08-2013 A
26-11-2013 A
26-11-2013 A
425
120
100%
12
13-08-2013 A
25-11-2013 A
305
100%
27
27
02-08-2013 A
02-08-2013 A
04-09-2013 A
30-08-2013 A
80
80
100%
16
06-08-2013 A
04-09-2013 A
100%
17
17
06-08-2013 A
06-08-2013 A
16-10-2013 A
16-10-2013 A
140
140
100%
10
20-08-2013 A
03-10-2013 A
100%
26
24
06-08-2013 A
06-08-2013 A
06-03-2014
06-03-2014
313
110
105
105
90%
21
08-08-2013 A
03-03-2014
203
105
90%
238
34
34
22-03-2013 A
09-09-2013 A
09-09-2013 A
25-02-2014
20-12-2013 A
20-12-2013 A
4576
199
135
112
21
15-09-2013 A
19-12-2013 A
64
100%
48
10
04-07-2013 A
04-07-2013 A
13-11-2013 A
20-10-2013 A
405
190
100%
24-07-2013 A
13-11-2013 A
215
100%
21
21
09-09-2013 A
09-09-2013 A
19-02-2014
19-02-2014
185
185
119
119
90%
10
10-09-2013 A
16-02-2014
119
90%
21
10
25-08-2013 A
25-08-2013 A
11-12-2013 A
09-12-2013 A
180
0
100%
105
YARNIMA.10.15.8.8.2 Orange Phase (Refer to Marked up Burried Services Drawing)
YARNIMA.10.15.8.8.2.6 04-DTMT Area (cannot be completed until DTMT are out of this area)31
A22190
Excavation & Backfilling for Underground Services
31
A22450
A22210
A22480
A22520
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 16 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Total
Float
Activity % S
Complete
100%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
21
06-09-2013 A
11-12-2013 A
180
65
25
28-08-2013 A
28-08-2013 A
25-02-2014
25-02-2014
287
120
NCR-S213 BOP: Line 3- Drain Pit on West Side of Lube Oil Cooler Installed In Wrong Orientation2
01-09-2013 A
02-09-2013 A
A3520
15
05-09-2013 A
21-02-2014
167
53
31
22-03-2013 A
22-03-2013 A
29-01-2014 A
29-01-2014 A
2095
190
100%
24
27-03-2013 A
27-01-2014 A
1905
100%
NCR-S083 BOP: Potable water Line - Incorrect SDR used for 63nb & 90nb HDPE pipe
16
19-05-2013 A
04-06-2013 A
100%
BOP: Potable water Line - Incorrect SDR used for 63nb & 90nb HDPE pipe
NCR-S091 STG1: Conduit on the North side of STG is clashing to the Pipe Riser
12
28-05-2013 A
09-06-2013 A
100%
30
30
09-11-2013 A
09-11-2013 A
07-01-2014 A
07-01-2014 A
769
105
STG1: Conduit on the North side of STG is clashing to the Pipe Riser
YARNIMA.10.15.8.8.3.7 21-Firewater
100%
21
11-11-2013 A
06-01-2014 A
664
100%
30
30
14-01-2014 A
14-01-2014 A
31-01-2014 A
31-01-2014 A
456
125
100%
21
16-01-2014 A
30-01-2014 A
331
100%
20
20
20
26-02-2014
26-02-2014
26-02-2014*
18-03-2014
18-03-2014
18-03-2014
95
95
95
94
94
94
0%
10
03-03-2014
13-03-2014
99
0%
260
20
30-06-2013 A
15-07-2013 A
27-04-2014
26-09-2013 A
36569
1533
57
13
12-08-2013 A
25-08-2013 A
A22350
YARNIMA.10.15.8.8.3.7 21-Firewater
A22310
Excavation & Backfilling for Underground Services
A22560
A13530-a
Total
Float
Activity % S
Complete
100%
94
94
90%
100%
100%
517
03-03-2014
30-06-2013 A
0
0
13-08-2013 A
100%
100%
Condensate Piping-LCA
100%
100%
Condensate Piping-LCA
16-07-2013 A
A13530-a70
24-10-2013 A
A13530-a10
11-09-2013 A
10-07-2013 A
30-06-2013 A
30-06-2013 A
BOP: Line 3- Drain Pit on West Side of Lube Oil Cooler Installed In Wrong Orie
90%
21
209
0
A13530-a60
100%
94
100%
108
100%
Gas Piping-EKG
Compressed Air Piping-QFB
16-07-2013 A
43
23-09-2013 A
A13530-a20
06-12-2013 A
100%
A13530-a40
06-12-2013 A
100%
A13530-a80
06-12-2013 A
100%
A13530-a90
03-03-2014*
78
0%
185
70
01-10-2013 A
01-10-2013 A
03-04-2014
24-03-2014
18860
14392
79
79
44%
16-01-2014 A
A13540-a
30
03-03-2014
03-04-2014
4468
79
0%
A13550
25-03-2014
29-03-2014
79
0%
159
35
15-08-2013 A
15-08-2013 A
27-03-2014
21-03-2014
909
909
86
86
68.5%
23-03-2014
27-03-2014
86
0%
138
30
18-09-2013 A
18-09-2013 A
19-03-2014
14-03-2014
1088
1088
93
93
Test Pipelines
YARNIMA.10.15.8.6.5 Demineralization Piping-
67%
15-03-2014
19-03-2014
93
0%
186
25
15-08-2013 A
15-08-2013 A
28-03-2014
23-03-2014
1554
1554
85
85
Test Pipelines
YARNIMA.10.15.8.6.6 Diesel Fuel Supply Pipin
64%
Test Pipelines
Test Pipelines
29-08-2013 A
01-09-2013 A
NCR-S285
A16320
Test Pipelines
100%
14-10-2013 A
27-10-2013 A
24-03-2014
28-03-2014
85
178
9
21-07-2013 A
21-07-2013 A
28-02-2014
30-07-2013 A
2209
0
111
100%
0%
Test Pipelines
YARNIMA.10.15.8.6.7 Compressed Air Piping-QFB
100%
A16280
26-07-2013 A
23-02-2014
2209
111
53%
A16330
Test Pipelines
24-02-2014
28-02-2014
111
0%
133
64
26-09-2013 A
26-09-2013 A
19-03-2014
14-03-2014
1439
1439
93
93
Test Pipelines
YARNIMA.10.15.8.6.8 Permeate System Piping
58%
01-11-2013 A
01-11-2013 A
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 17 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
100%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
NCR-S388
02-01-2014 A
02-01-2014 A
A16590
Test Pipelines
15-03-2014
19-03-2014
93
0%
179
40
03-11-2013 A
03-11-2013 A
27-04-2014
22-04-2014
1949
1949
57
57
34%
23-04-2014
27-04-2014
57
0%
146
70
16-07-2013 A
16-07-2013 A
13-02-2014
17-01-2014 A
1391
1391
125
09-02-2014
13-02-2014
125
0%
201
25
17-09-2013 A
17-09-2013 A
26-04-2014
22-04-2014
4085
4085
58
58
50%
22-04-2014
26-04-2014
58
0%
30
25
03-03-2014
03-03-2014
04-04-2014
30-03-2014
0
0
78
78
Test Pipelines
YARNIMA.10.15.8.6.10 Chemical Dosing (Va
0%
30-03-2014
04-04-2014
78
0%
182
25
17-09-2013 A
17-09-2013 A
06-04-2014
01-04-2014
1035
1035
77
77
Test Pipelines
YARNIMA.10.15.8.6.11 Miscellaneous UGP
24%
01-04-2014
06-04-2014
77
0%
40
30
03-07-2013 A
03-07-2013 A
17-01-2014 A
15-01-2014 A
427
130
100%
Test Pipelines
Test Pipelines
Test Pipelines
Test Pipelines
100%
30
23-07-2013 A
07-01-2014 A
207
100%
A9270
30
30-07-2013 A
17-01-2014 A
90
100%
208
28
20-05-2013 A
20-05-2013 A
24-03-2014
03-03-2014
2370
130
89
89
45%
A9290
Install Conduits
28
30-05-2013 A
16-03-2014
2150
89
83.5%
A9300
30
06-06-2013 A
24-03-2014
90
89
40%
NCR-S202
25-08-2013 A
31-08-2013 A
TQ540-A9300
YARNIMA.10.15.14 CIVILS
YARNIMA.10.15.14.3 BSDG FOUNDATIONS
A2940
Excavation - BSDG Foundations
03-11-2013 A
04-11-2013 A
111
77
4
18-07-2013 A
31-10-2013 A
31-10-2013 A
16-02-2014
16-02-2014
08-01-2014 A
2127
674
13
Test Pipelines
YARNIMA.10.15.8.6.2 Cooling Water Pip
100%
A9260
Test Pipelines
YARNIMA.10.15.8.2 UNDERGROUND PITS
Excavation for Underground Pits
Install Underground Pits
100%
100%
91
91
100%
A15840
05-11-2013 A
13-01-2014 A
21
100%
A15850
06-11-2013 A
16-01-2014 A
241
100%
A15860
27-01-2014 A
16-02-2014
394
91
100%
A2820
28-01-2014 A
09-02-2014
94
95%
20
4
01-10-2013 A
01-10-2013 A
05-11-2013 A
05-10-2013 A
1221
35
100%
Excavation
A15880
06-10-2013 A
08-10-2013 A
11
100%
A15890
08-10-2013 A
15-10-2013 A
177
100%
A15900
16-10-2013 A
30-10-2013 A
985
100%
A2930
20-10-2013 A
05-11-2013 A
13
100%
14
1
18-07-2013 A
18-07-2013 A
31-08-2013 A
24-07-2013 A
232
3
100%
A15920
25-07-2013 A
30-07-2013 A
100%
A15930
01-08-2013 A
17-08-2013 A
177
100%
A15940
19-08-2013 A
27-08-2013 A
47
100%
A2990
28-08-2013 A
31-08-2013 A
100%
311
115
1
02-03-2013 A
20-07-2013 A
20-07-2013 A
14-03-2014
10-12-2013 A
21-07-2013 A
26774
2444
28
VEGT2000
VE GTG 2 - (electircal modifications, Pipe fitting for Siemens pipework outside & inside38
GT2 enclosure)
11-08-2013 A
19-09-2013 A
701
100%
NCR-S234
13-09-2013 A
19-09-2013 A
100%
NCR-S246
19
18-09-2013 A
08-10-2013 A
100%
NCR-S247
18-09-2013 A
27-09-2013 A
100%
VEGT2010
GTG 2 (Pipe fitting outside GT2 enclosure, Install Donaldson Elect Equip, Install HV Terminal
57
Box,
26-09-2013
ElectricalAworks)25-11-2013 A
1695
100%
NCR-S345
24
15-11-2013 A
10-12-2013 A
100%
NCR-S346
24
15-11-2013 A
10-12-2013 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 18 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
98
100%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Modify Client Supply Material - Diffuser leg bolts and location pin holes
Activity ID
Activity Name
NCR-S363
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
01-12-2013 A
03-12-2013 A
100%
04-12-2013 A
04-12-2013 A
20
100%
NCR-S365
06-12-2013 A
07-12-2013 A
100%
257
257
02-03-2013 A
02-03-2013 A
17-01-2014 A
17-01-2014 A
10924
0
100%
11
5
02-03-2013 A
02-03-2013 A
16-03-2013 A
16-03-2013 A
100
100
100%
02-03-2013 A
05-03-2013 A
100%
A18080
07-03-2013 A
10-03-2013 A
100%
A18090
11-03-2013 A
16-03-2013 A
100%
4
21-07-2013
YARNIMA.10.15.2.1.3 Placement of Gear Box & Remove Transport Protection (GT, Gearbox, Generator
& Diffuser) A
A14520
Placement of Gear Box & Remove Transport Protection
4
21-07-2013 A
25-07-2013 A
25-07-2013 A
250
250
100%
139
9
10-05-2013 A
10-05-2013 A
06-10-2013 A
27-06-2013 A
190
190
100%
Placement of GT
10-05-2013 A
26-06-2013 A
100%
1. Place GT skid on foundation tooling- plumb to XY axis- grout once skid is aligned
2. Once GT is aligned & grouted- lift lube oil skid into position
A18110
1. Place GT skid on foundation tooling- plumb to XY axis- grout once skid is aligned
A18120
2. Once GT is aligned & grouted- lift lube oil skid into position
11-05-2013 A
27-06-2013 A
100%
NCR-S258
14
22-09-2013 A
06-10-2013 A
100%
65
5
15-07-2013 A
15-07-2013 A
02-09-2013 A
02-09-2013 A
190
190
100%
15-07-2013 A
28-07-2013 A
100%
42
28-07-2013 A
31-08-2013 A
100%
A18140
30-07-2013 A
31-07-2013 A
100%
A18150
3. Lower diffuser onto foundation- plumb centreline & flange face- place on pedastals 3
30-07-2013 A
02-08-2013 A
100%
21
9
29-07-2013 A
29-07-2013 A
12-08-2013 A
08-08-2013 A
380
380
3. Lower diffuser onto foundation- plumb centreline & flange face- place on pedasta
YARNIMA.10.15.2.1.6 Connect Diffuser
1. Mark out foundation axis- and distance from turbine flange to diffuser flange
100%
Connect Diffuser
A18160
1. Install and torque inner and outer diffuser rings (Require Scaffold)
02-08-2013 A
05-08-2013 A
100%
1. Install and torque inner and outer diffuser rings (Require Scaffold)
NCR-S179
05-08-2013 A
12-08-2013 A
100%
A18170
06-08-2013 A
06-08-2013 A
100%
A18180
07-08-2013 A
08-08-2013 A
100%
14
2
26-07-2013 A
26-07-2013 A
02-08-2013 A
02-08-2013 A
300
300
100%
28-07-2013 A
29-07-2013 A
100%
A18200
30-07-2013 A
02-08-2013 A
100%
156
6
17-05-2013 A
17-05-2013 A
04-11-2013 A
04-08-2013 A
190
190
100%
Placement of Generator
A18210
17-05-2013 A
01-06-2013 A
100%
A18220
28-07-2013 A
29-07-2013 A
100%
A18230
29-07-2013 A
31-07-2013 A
100%
A18240
01-08-2013 A
04-08-2013 A
100%
NCR-S298
18-10-2013 A
23-10-2013 A
100%
NCR-S334
03-11-2013 A
04-11-2013 A
100%
33
12
28-07-2013 A
28-07-2013 A
13-09-2013 A
03-08-2013 A
500
500
100%
A18250
28-07-2013 A
05-08-2013 A
100%
A18260
28-07-2013 A
30-07-2013 A
100%
A18270
03-08-2013 A
04-08-2013 A
100%
NCR-S211
13
31-08-2013 A
13-09-2013 A
100%
66
6
19-05-2013 A
19-05-2013 A
24-09-2013 A
24-09-2013 A
150
150
100%
A18280
01-08-2013 A
03-08-2013 A
100%
A18290
04-08-2013 A
04-08-2013 A
100%
A18300
3. Lift motor- install and set mounting feet- mount motor in correct orientation
05-08-2013 A
20-08-2013 A
100%
A18310
11-08-2013 A
24-09-2013 A
100%
4
2
29-07-2013 A
29-07-2013 A
15-09-2013 A
15-09-2013 A
250
250
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 19 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
3. Lift motor- install and set mounting feet- mount motor in correct orientation
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A18320
1. Mark out foundation- install and survey packers- anchor feet to foundation
29-07-2013 A
04-08-2013 A
100%
A18330
05-08-2013 A
15-09-2013 A
100%
67
18
20-05-2013 A
20-05-2013 A
22-09-2013 A
22-09-2013 A
1120
1120
100%
1. Mark out foundation- install and survey packers- anchor feet to foundation
2. Install module onto feet
YARNIMA.10.15.2.1.12 Install Oil Coolers (Including Handrails, Ladders)
Install Oil Coolers
A18340
20-05-2013 A
21-05-2013 A
100%
A18350
22-05-2013 A
23-05-2013 A
100%
A18370
24-05-2013 A
20-07-2013 A
100%
A18360
3. Welding feet
08-08-2013 A
20-08-2013 A
100%
A18380
14-08-2013 A
22-09-2013 A
100%
80
52
23-07-2013 A
23-07-2013 A
11-12-2013 A
11-12-2013 A
400
400
100%
A18390
27-07-2013 A
23-08-2013 A
100%
NCR-S182
07-08-2013 A
16-08-2013 A
100%
A18400
23-08-2013 A
11-12-2013 A
100%
11 ground)
20-05-2013 A
YARNIMA.10.15.2.1.14 Assemble Steel Enclosure (Pre-assemble steel enclosure modules on the
A14580
Assemble Steel Enclosure (Pre-assemble steel enclosure modules on the ground)
11
20-05-2013 A
12-09-2013 A
12-09-2013 A
450
450
100%
14
04-09-2013 A
YARNIMA.10.15.2.1.15 Placement of Steel Enclosure (Place and connect pre-assembled steel modules)
A14590
Placement of Steel Enclosure
14
04-09-2013 A
23-10-2013 A
23-10-2013 A
550
550
100%
59
3
13-10-2013 A
13-10-2013 A
11-12-2013 A
25-10-2013 A
2890
0
100%
A14610
26
14-10-2013 A
11-12-2013 A
2890
100%
A18440
2. Mark out foundation and install lower wall panel channel mounts
16-10-2013 A
25-10-2013 A
100%
A18450
3. Install slurry wall mounting items and slurry wall between GT and Generator
20-10-2013 A
31-10-2013 A
100%
3. Install slurry wall mounting items and slurry wall between GT and G
A18460
23-10-2013 A
04-12-2013 A
100%
A18470
07-11-2013 A
11-12-2013 A
100%
65
28
04-09-2013 A
04-09-2013 A
11-12-2013 A
11-12-2013 A
312
312
100%
A18480
1. Assemble and install generator cooling ducts and elbow within enclosure
04-09-2013 A
10-09-2013 A
100%
A18490
09-09-2013 A
16-09-2013 A
100%
A18520
10
15-09-2013 A
20-09-2013 A
100%
A18530
22-09-2013 A
03-11-2013 A
100%
A18500
05-10-2013 A
03-12-2013 A
100%
A18510
25-10-2013 A
11-12-2013 A
100%
3
3
25-09-2013 A
25-09-2013 A
30-10-2013 A
30-10-2013 A
250
250
100%
100%
25-09-2013 A
26-09-2013 A
A18550
26-09-2013 A
30-10-2013 A
100%
27-08-2013 A
YARNIMA.10.15.2.1.19 Assemble Intake Support Structure (Assemble support structure on the51
ground)
A14660
Assemble Intake Support Structure
13
27-08-2013 A
20-11-2013 A
20-11-2013 A
275
275
100%
1. Assemble and install generator cooling ducts and elbow within enclosure
NCR-S269
GTG2: Multiple mods to Air Intake Support Structure - Misaligned Holes/Clashing & Cleat
2 Welded
30-09-2013
in WrongAPosition
01-10-2013 A
100%
NCR-S271
GTG2: Air Intake Inlet Hood - Damaged Louvers on Inlet Hood after being removed from
4 Packaging
01-10-2013 A
04-10-2013 A
100%
GTG2: Air Intake Inlet Hood - Damaged Louvers on Inlet Hood after being
NCR-S277
GTG3: GT2 -Air intake fitment issues- GT Ventilation Inlet holes not drilled
18
08-10-2013 A
26-10-2013 A
100%
GTG3: GT2 -Air intake fitment issues- GT Ventilation Inlet holes not dri
NCR-S289
GTG2: GT2 Air Intake Support Structure - End Plate Clashing with the Gridmesh
14-10-2013 A
16-10-2013 A
100%
GTG2: GT2 Air Intake Support Structure - End Plate Clashing with the G
NCR-S309
15
23-10-2013 A
07-11-2013 A
100%
NCR-S335
GTG2: GT2 Assembly Intake - Unable to Fit Assembly Line into Module
06-11-2013 A
09-11-2013 A
100%
7
7
23-10-2013 A
23-10-2013 A
21-11-2013 A
21-11-2013 A
300
300
GTG2: GT2 Assembly Intake - Unable to Fit Assembly Line into Mod
YARNIMA.10.15.2.1.20 Lift Air Intake Structure into Place
100%
22
22
12-10-2013 A
12-10-2013 A
23-11-2013 A
23-11-2013 A
750
750
100%
A18580
02-11-2013 A
06-11-2013 A
100%
A18590
07-11-2013 A
23-11-2013 A
100%
5
5
01-10-2013 A
01-10-2013 A
20-12-2013 A
20-12-2013 A
187
187
100%
29
21
30-10-2013 A
30-10-2013 A
14-01-2014 A
14-01-2014 A
250
250
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 20 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A18610
01-11-2013 A
29-11-2013 A
100%
A18620
2. Remove nozzles- horns- cap and pressure test- reinstall nozzles and horns
07-11-2013 A
29-11-2013 A
100%
A18630
12-11-2013 A
16-12-2013 A
100%
39
8
16-10-2013 A
16-10-2013 A
17-01-2014 A
20-12-2013 A
500
0
100%
22-11-2013 A
17-01-2014 A
500
100%
A18790
26-11-2013 A
20-12-2013 A
100%
3
3
28-10-2013 A
28-10-2013 A
22-12-2013 A
22-12-2013 A
190
190
100%
155
152
18
21-06-2013 A
21-06-2013 A
21-06-2013 A
20-12-2013 A
20-12-2013 A
09-07-2013 A
3281
990
0
100%
GTG2: GT2- Lube Oil Unit Piping showing signs of rusting internally
A14620
03-07-2013 A
20-12-2013 A
990
100%
A18710
03-07-2013 A
14-12-2013 A
100%
A18720
02-08-2013 A
14-12-2013 A
100%
A18730
08-10-2013 A
20-12-2013 A
100%
139
2
30-06-2013 A
30-06-2013 A
18-12-2013 A
01-07-2013 A
1200
0
100%
A14760
17
24-07-2013 A
18-12-2013 A
1200
100%
A18670
24-07-2013 A
18-12-2013 A
100%
NCR-S183
07-08-2013 A
12-08-2013 A
100%
A18700
12-08-2013 A
17-12-2013 A
100%
A18680
18-09-2013 A
17-12-2013 A
100%
16
16
08-10-2013 A
08-10-2013 A
19-12-2013 A
19-12-2013 A
125
125
100%
A18640
09-10-2013 A
16-10-2013 A
100%
A18650
13-10-2013 A
18-10-2013 A
100%
A18660
16-10-2013 A
22-10-2013 A
100%
100
42
14-08-2013 A
14-08-2013 A
03-10-2013 A
09-09-2013 A
32
32
100%
14-08-2013 A
09-09-2013 A
100%
NCR-S236
19
14-09-2013 A
03-10-2013 A
100%
12
12
08-10-2013 A
08-10-2013 A
18-12-2013 A
18-12-2013 A
934
934
100%
A18740
09-10-2013 A
12-10-2013 A
100%
A18750
10-10-2013 A
13-10-2013 A
100%
A18760
12-10-2013 A
15-10-2013 A
100%
A18770
14-10-2013 A
18-10-2013 A
100%
284
284
02-03-2013 A
02-03-2013 A
20-02-2014
20-02-2014
8746
0
23
11
02-03-2013 A
02-03-2013 A
03-03-2013 A
02-03-2013 A
1319
986
100%
12
03-03-2013 A
03-03-2013 A
333
100%
112
2
28-05-2013 A
28-05-2013 A
06-01-2014 A
16-12-2013 A
719
98
100%
98
98
0%
A12420
14-06-2013 A
06-01-2014 A
314
100%
A12430
12
15-06-2013 A
06-01-2014 A
307
100%
NCR-S243
13
18-09-2013 A
01-10-2013 A
100%
NCR-S255
12
20-09-2013 A
02-10-2013 A
100%
NCR-S287
12
14-10-2013 A
26-10-2013 A
100%
106
40
07-08-2013 A
07-08-2013 A
04-01-2014 A
19-12-2013 A
1185
1185
100%
17-10-2013 A
17-10-2013 A
100%
15-12-2013 A
02-01-2014 A
100%
NCR-S380-1319
Rectify Misalignment of holes and miscellaneous nonconformities on GT2 Donaldson Equipment
2
03-01-2014 A
04-01-2014 A
100%
13-02-2014
3701
NCR-S380
YARNIMA.10.15.2.2.4 Cabling
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
13-03-2013 A
Page 21 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
105
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
98
Activity % S
Complete
A12460
33
13-03-2013 A
13-02-2014
2178
A12580
04-05-2013 A
01-12-2013 A
266
100%
A12630
07-06-2013 A
23-11-2013 A
239
100%
A12480
04-08-2013 A
07-11-2013 A
342
100%
A12570
11-08-2013 A
07-11-2013 A
676
100%
NCR-S189
12-08-2013 A
15-08-2013 A
100%
NCR-S296
11
17-10-2013 A
28-10-2013 A
100%
NCR-S352
32
18-11-2013 A
02-01-2014 A
100%
NCR-S378
GTG2: Clarification on Missing Earths back to Main Earth bar on Siemens Panels GT28
13-12-2013 A
02-01-2014 A
100%
NCR-S382
Clarification on GT2 MPB55 propane cabinet cabling due to wrong location of conduit 4
16-12-2013 A
19-12-2013 A
100%
04-06-2013 A
04-06-2013 A
20-02-2014
20-02-2014
1056
1056
112
25
98
98
98%
93%
NCR-S230
GTG1: Cables GT1/2 BFA10GS012D001 could not terminate becasue of size of the lug6
10-09-2013 A
15-09-2013 A
100%
NCR-S231
10-09-2013 A
12-09-2013 A
100%
NCR-S235
GTG2: The HV panels GS006 and GS007 in GT2BBA10 have missing duct lid
13-09-2013 A
15-09-2013 A
100%
GTG2: The HV panels GS006 and GS007 in GT2BBA10 have missing duct li
NCR-S257
13
20-09-2013 A
03-10-2013 A
100%
NCR-S266
GTG2: Cable Modifications to GT2 - Cable is too large for Terminal size
28-09-2013 A
28-09-2013 A
100%
A12490
100%
14
08-11-2013 A
02-12-2013 A
12
12
06-03-2013 A
06-03-2013 A
17-01-2014 A
17-01-2014 A
0
0
18
18
14-08-2013 A
14-08-2013 A
10-02-2014
10-02-2014
740
740
2
2
20-11-2013 A
20-11-2013 A
16-01-2014 A
16-01-2014 A
26
26
YARNIMA.10.15.2.4 INSTRUMENTS
A12640
Install Stage 2 Instruments - GTG 2
2
2
12-09-2013 A
12-09-2013 A
02-01-2014 A
02-01-2014 A
349
349
84
15
20-11-2013 A
20-11-2013 A
14-03-2014
20-02-2014
1030
532
350
100%
A12990
21
01-12-2013 A
21-12-2013 A
NCR-S375
108
108
98
98
100%
90%
100%
100%
95%
10-12-2013 A
13-12-2013 A
100%
15-12-2013 A
15-12-2013 A
18
100%
A12960
10
16-12-2013 A
20-02-2014
50
A12970
10
16-12-2013 A
09-01-2014 A
80
A22940
20
23-12-2013 A
14-03-2014
98
90%
A12980
20-02-2014
98
0%
293
135
1
01-04-2014
13-01-2014 A
08-08-2013 A
25190
868
24
81
02-04-2013 A
08-08-2013 A
08-08-2013 A
98
95%
100%
100%
VEGT1000
VE GTG 1 - work on: A/C around Switchroom, Siemens pipework outside enclosure, electrical
42
in
09-08-2013
generator Aetc
23-09-2013 A
577
100%
NCR-S220
NCR-S239
NCR-S242
04-09-2013 A
11-09-2013 A
100%
GTG2 & GTG1 - Enclosure Steelwork Clashes with Platform - A14580 and A14880
15-09-2013 A
19-09-2013 A
100%
19
18-09-2013 A
08-10-2013 A
100%
NCR-S244
19
18-09-2013 A
08-10-2013 A
100%
NCR-S245
19
18-09-2013 A
08-10-2013 A
100%
VEGT1010
VE GTG 1 - work on A/C around Switchroom, Lube oil cooler cable ladder
01-10-2013 A
03-10-2013 A
36
100%
VE GTG 1 - work on A/C around Switchroom, Lube oil cooler cable ladder
VEGT1020
VE GTG 1 - Delaied access to 132kV switchyard, work on A/C around Switchroom, Switchroom
9
10-10-2013
Access Platform
A
Issues
20-10-2013 A
100
100%
VEGT1030
VE GTG 1 - Pipe-fitting and fabrication for Siemens pipework outside enclosure, Install1Donaldson
30-10-2013
ElectricalAEquipment
31-10-2013 A
21
100%
VEGT1040
VE GTG 1 - Delaied access to 132kV switchyard, Replacement cables for Siemens Ex11
circuits MWR
10-11-2013
132, Mods
A to21-11-2013
Gen enclosure
A
110
100%
NCR-S372
100%
21
10-12-2013 A
13-01-2014 A
238
238
21-05-2013 A
21-05-2013 A
17-02-2014
17-02-2014
10924
0
17
5
28-07-2013 A
28-07-2013 A
01-08-2013 A
01-08-2013 A
100
100
111
101
GTG2 & GTG1 - Enclosure Steelwork Clashes with Platform - A14580 and A
0%
100%
A18840
29-07-2013 A
29-07-2013 A
100%
A18850
30-07-2013 A
30-07-2013 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 22 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
Finish
31-07-2013 A
01-08-2013 A
100%
4
17-07-2013
YARNIMA.10.15.3.1.3 Placement of Gear Box & Remove Transport Protection (GT, Gearbox, Generator
& Diffuser) A
A14820
Placement of Gear Box & Remove Transport Protection
4
17-07-2013 A
05-08-2013 A
05-08-2013 A
250
250
A18860
Budgeted
Labor Units
Total
Float
Activity % S
Complete
100%
88
9
22-05-2013 A
22-05-2013 A
23-08-2013 A
07-08-2013 A
190
190
100%
Placement of GT
A18880
1. Place GT skid on foundation tooling- plumb to XY axis- grout once skid is aligned
02-08-2013 A
23-08-2013 A
100%
A18890
2. Once GT is aligned & grouted- lift lube oil skid into position
04-08-2013 A
07-08-2013 A
100%
27
5
07-08-2013 A
07-08-2013 A
25-09-2013 A
10-09-2013 A
190
190
100%
1. Place GT skid on foundation tooling- plumb to XY axis- grout once skid is align
2. Once GT is aligned & grouted- lift lube oil skid into position
YARNIMA.10.15.3.1.5 Placement and alignment of Diffuser
Placement of Diffuser
A18900
1. Mark out foundation axis- and distance from turbine flange to diffuser flange
08-08-2013 A
13-08-2013 A
100%
A18910
14-08-2013 A
25-09-2013 A
100%
A18920
3. Lower diffuser onto foundation- plumb centreline & flange face- place on pedastals 3
17-08-2013 A
10-09-2013 A
100%
3. Lower diffuser onto foundation- plumb centreline & flange face- place on pe
NCR-S194
GTG1: Exhaust diffuser locating Pinholes and keys udersize A repeat of NCR C1034-NCR-S164
22
18-08-2013 A
GTG1: Exhaust diffuser locating Pinholes and keys udersize A repeat of NCR
YARNIMA.10.15.3.1.6 Connect Diffuser
10-09-2013 A
100%
9
9
11-09-2013 A
11-09-2013 A
20-09-2013 A
19-09-2013 A
380
380
1. Mark out foundation axis- and distance from turbine flange to diffuser flange
2. Lift diffuser- mount legs and plates
100%
Connect Diffuser
A18930
1. Install and torque inner and outer diffuser rings (Require Scaffold)
11-09-2013 A
19-09-2013 A
100%
1. Install and torque inner and outer diffuser rings (Require Scaffold)
A18940
18-09-2013 A
19-09-2013 A
100%
A18950
18-09-2013 A
20-09-2013 A
100%
2
2
15-08-2013 A
15-08-2013 A
30-08-2013 A
30-08-2013 A
300
300
100%
15-08-2013 A
26-08-2013 A
100%
A18970
16-08-2013 A
30-08-2013 A
100%
69
6
21-07-2013 A
21-07-2013 A
24-10-2013 A
25-09-2013 A
190
190
100%
Placement of Generator
A18980
05-08-2013 A
08-08-2013 A
100%
A18990
06-08-2013 A
07-08-2013 A
100%
A19000
08-08-2013 A
08-08-2013 A
100%
A19010
17-08-2013 A
25-09-2013 A
100%
NCR-S311
24-10-2013 A
24-10-2013 A
100%
26
10
05-08-2013 A
05-08-2013 A
08-10-2013 A
08-10-2013 A
500
500
100%
05-08-2013 A
06-08-2013 A
100%
A19040
06-08-2013 A
08-10-2013 A
100%
A19030
08-08-2013 A
08-10-2013 A
100%
9
6
26-07-2013 A
26-07-2013 A
26-09-2013 A
26-09-2013 A
150
150
100%
A19050
26-07-2013 A
06-08-2013 A
100%
A19060
07-08-2013 A
22-08-2013 A
100%
A19070
3. Lift motor- install and set mounting feet- mount motor in correct orientation
23-08-2013 A
24-09-2013 A
100%
A19080
25-08-2013 A
26-09-2013 A
100%
2
2
17-08-2013 A
17-08-2013 A
18-09-2013 A
18-09-2013 A
250
250
100%
18-08-2013 A
13-09-2013 A
100%
1. Mark out foundation- install and survey packers- anchor feet to foundation
1. Mark out foundation- install and survey packers- anchor feet to foundation
A19100
14-09-2013 A
18-09-2013 A
100%
94
18
21-05-2013 A
21-05-2013 A
05-09-2013 A
05-09-2013 A
1120
1120
3. Lift motor- install and set mounting feet- mount motor in correct orientatio
4. Carry out alignment- starter motor to Gearbox - Weld Feet
YARNIMA.10.15.3.1.11 Install CO2 Module
100%
A19110
21-05-2013 A
22-05-2013 A
100%
A19120
22-05-2013 A
23-05-2013 A
100%
A19140
28-05-2013 A
10-08-2013 A
100%
A19130
3. Welding feet
03-08-2013 A
08-08-2013 A
100%
3. Welding feet
A19150
01-09-2013 A
05-09-2013 A
100%
52
52
22-08-2013 A
22-08-2013 A
06-01-2014 A
02-01-2014 A
400
400
100%
A19160
23-08-2013 A
06-01-2014 A
100%
A19170
10-09-2013 A
06-01-2014 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 23 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Finish
Budgeted
Labor Units
11 ground)
03-09-2013 A
YARNIMA.10.15.3.1.14 Assemble Steel Enclosure (Pre-assemble steel enclosure modules on the
A14880
Assemble Steel Enclosure
11
03-09-2013 A
22-09-2013 A
22-09-2013 A
450
450
100%
14
24-09-2013 A
YARNIMA.10.15.3.1.15 Placement of Steel Enclosure (Place and connect pre-assembled steel modules)
A14900
Placement of Steel Enclosure
14
24-09-2013 A
13-11-2013 A
13-11-2013 A
550
550
100%
Start
Total
Float
Activity % S
Complete
26
26
19-10-2013 A
19-10-2013 A
30-01-2014 A
30-01-2014 A
2890
2890
100%
A19200
19-10-2013 A
25-10-2013 A
100%
A19210
2. Mark out foundation and install lower wall panel channel mounts
26-10-2013 A
31-10-2013 A
100%
2. Mark out foundation and install lower wall panel channel mounts
A19220
3. Install slurry wall mounting items and slurry wall between GT and Generator
29-10-2013 A
03-11-2013 A
100%
3. Install slurry wall mounting items and slurry wall between GT and G
A19230
10-11-2013 A
01-12-2013 A
100%
A19240
20-11-2013 A
14-12-2013 A
100%
28
28
13-09-2013 A
13-09-2013 A
06-01-2014 A
02-01-2014 A
312
312
100%
1. Assemble and install generator cooling ducts and elbow within enclosure
13-09-2013 A
10-10-2013 A
100%
A19260
13-09-2013 A
25-10-2013 A
100%
A19300
18-09-2013 A
11-10-2013 A
100%
A19270
23-10-2013 A
14-12-2013 A
100%
A19290
10
06-11-2013 A
28-12-2013 A
100%
A19280
07-11-2013 A
06-01-2014 A
100%
3
3
25-09-2013 A
25-09-2013 A
20-01-2014 A
20-01-2014 A
250
250
1. Assemble and install generator cooling ducts and elbow within enclosur
2. Install remaining generator cooling ducts and supports
4. Generator Enclosure Inlet and Outlet
5. Install generator cooling unit- platform and access ladder
3. Install enclosure ventilation outlet - GTG1
6. Install enclosure ventilation inlet - GTG1
YARNIMA.10.15.3.1.18 Install Fuel Gas Skid
100%
A19310
25-09-2013 A
12-10-2013 A
100%
A19320
26-09-2013 A
16-12-2013 A
100%
18-10-2013 A
YARNIMA.10.15.3.1.19 Assemble Intake Support Structure (Assemble support structure on the15
ground)
A14970
Assemble Intake Support Structure
13
18-10-2013 A
24-11-2013 A
24-11-2013 A
275
275
100%
18-11-2013 A
19-11-2013 A
100%
3
3
13-11-2013 A
13-11-2013 A
26-11-2013 A
26-11-2013 A
300
300
100%
15
10
07-11-2013 A
07-11-2013 A
27-11-2013 A
27-11-2013 A
750
750
NCR-S351
100%
A19350
07-11-2013 A
12-11-2013 A
100%
A19360
07-11-2013 A
27-11-2013 A
100%
6
6
20-12-2013 A
20-12-2013 A
13-02-2014
13-02-2014
187
187
105
105
20%
56
14
27-11-2013 A
27-11-2013 A
11-02-2014
03-02-2014 A
250
250
107
27-11-2013 A
27-01-2014 A
100%
A19380
A19390
2. Remove nozzles- horns- cap and pressure test- reinstall nozzles and horns - GTG1 3
28-11-2013 A
28-01-2014 A
A19400
29-01-2014 A
11-02-2014
63
8
24-11-2013 A
24-11-2013 A
02-02-2014 A
12-12-2013 A
500
0
100%
101
100%
60%
A15070
02-12-2013 A
02-02-2014 A
500
100%
A19560
26-01-2014 A
27-01-2014 A
100%
3
3
03-12-2013 A
03-12-2013 A
17-02-2014
17-02-2014
190
190
101
101
94
13
13
25-07-2013 A
25-08-2013 A
25-08-2013 A
13-02-2014
03-01-2014 A
02-01-2014 A
3281
990
990
105
100%
1. Pre-Alignment of GTG 1
Final Alignment - GTG1
2. Place Coupling Units Inside Enclosure - GTG1
YARNIMA.10.15.3.1.25 Install Coupling Units
95%
100%
A19480
25-08-2013 A
03-01-2014 A
100%
A19490
25-08-2013 A
03-01-2014 A
100%
A19500
25-08-2013 A
03-01-2014 A
100%
71
17
25-07-2013 A
25-07-2013 A
04-12-2013 A
04-12-2013 A
1200
1200
100%
A19440
25-07-2013 A
04-12-2013 A
100%
A19470
11-08-2013 A
04-12-2013 A
100%
A19450
26-08-2013 A
04-12-2013 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 24 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
21
21
07-10-2013 A
07-10-2013 A
13-02-2014
27-01-2014 A
125
125
105
08-10-2013 A
03-11-2013 A
A19420
14-10-2013 A
22-10-2013 A
A19430
18-10-2013 A
13-02-2014
72
37
18-09-2013 A
18-09-2013 A
23-10-2013 A
23-10-2013 A
Activity % S
Complete
100%
100%
10%
32
32
100%
105
A19460
19-09-2013 A
23-10-2013 A
100%
NCR-S270
03-10-2013 A
04-10-2013 A
100%
12
12
15-10-2013 A
15-10-2013 A
06-12-2013 A
06-12-2013 A
934
934
100%
23-10-2013 A
100%
A19510
15-10-2013 A
A19520
23-10-2013 A
01-11-2013 A
100%
A19530
01-11-2013 A
06-12-2013 A
100%
A19540
06-11-2013 A
06-12-2013 A
100%
264
264
02-04-2013 A
02-04-2013 A
07-03-2014
07-03-2014
9075
0
82
11
02-04-2013 A
02-04-2013 A
31-07-2013 A
31-07-2013 A
1318
985
100%
12
25-05-2013 A
10-07-2013 A
333
100%
NCR-S144
GTG1: GT1 & GT2 Switchrooms do not have holes to connect cable ladder support
84
84
0%
03-07-2013 A
04-07-2013 A
100%
135
2
28-05-2013 A
28-05-2013 A
06-01-2014 A
06-01-2014 A
719
98
100%
A12690
11
25-06-2013 A
29-10-2013 A
314
100%
A12700
14
26-06-2013 A
06-01-2014 A
307
100%
NCR-S140
42
30-06-2013 A
13-08-2013 A
100%
NCR-S232
GTG1: Two substation earth bars under GT1 switch room have wrong tag number
11-09-2013 A
12-09-2013 A
100%
NCR-S288
12
14-10-2013 A
26-10-2013 A
100%
38
35
26-08-2013 A
26-08-2013 A
17-01-2014 A
17-01-2014 A
1288
1185
100%
10-12-2013 A
02-01-2014 A
100%
NCR-S374-1506
Rectify Misalignment of holes and miscellaneous non-conformities on GT1 Donaldson Equipment
5
03-01-2014 A
100%
YARNIMA.10.15.3.2.2 Cabling
A12850
Install HV/LV Cabling GT1 Switchroom to Aux Transformer
07-01-2014 A
103
196
3
04-05-2013 A
04-05-2013 A
21-02-2014
15-02-2014
3436
263
91
103
GTG1: Two substation earth bars under GT1 switch room have wrong tag nu
STG1: ST-1 Switchrooms - Walkway foundation Missing Anchor Bolts
YARNIMA.10.15.3.2.3 On Skid Works
Install GT1 On-Skid Electrical Equip
100%
A12730
Pull LV-C & I Cabling - GTG 1 (Incl Cable from GTG1 to HRSG S/Room)
33
23-05-2013 A
21-02-2014
2180
81
80%
A12900
07-06-2013 A
21-02-2014
106
97
100%
NCR-S139
GTG1: GT1 INC45 Conduit does not pentrate through culwert wall
46
29-06-2013 A
16-08-2013 A
100%
A12750
11
17-08-2013 A
07-11-2013 A
342
100%
A12840
11
14-09-2013 A
01-10-2013 A
545
100%
43
25
27-08-2013 A
27-08-2013 A
07-03-2014
07-03-2014
1548
1548
13
15-11-2013 A
16-01-2014 A
12
12
01-08-2013 A
01-08-2013 A
14-02-2014
14-02-2014
0
0
88
88
90%
21
21
17-08-2013 A
17-08-2013 A
01-03-2014
01-03-2014
740
740
90
90
85%
2
2
05-09-2013 A
05-09-2013 A
16-01-2014 A
16-01-2014 A
26
26
100%
YARNIMA.10.15.3.4 INSTRUMENTS
A12910
Install GT1 Instruments
2
2
15-12-2013 A
15-12-2013 A
10-02-2014
10-02-2014
30
30
108
108
10%
44
21
03-12-2013 A
03-12-2013 A
01-04-2014
11-03-2014
1012
350
81
81
84
81
74%
100%
90%
A13000
21
05-12-2013 A
11-03-2014
532
81
85%
A13010
14
18-12-2013 A
11-03-2014
50
81
65%
A22930
20
01-01-2014 A
01-04-2014
81
40%
A13020
10
30-01-2014 A
30-03-2014
80
83
80%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 25 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
A13030
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
11-03-2014
81
253
31
31
21-04-2013 A
26-07-2013 A
26-07-2013 A
15-05-2014
09-08-2013 A
09-08-2013 A
16598
208
208
40
253
7
05-05-2013 A
05-05-2013 A
24-03-2014
27-08-2013 A
7070
549
89
Activity % S
Complete
100%
100%
17-09-2013 A
05-11-2013 A
84
A2870
30
13-10-2013 A
15-03-2014
1421
89
35%
A1900
12
24-10-2013 A
20-02-2014
1080
63
63%
NCR-S331
31-10-2013 A
03-11-2013 A
A2880
20-11-2013 A
24-03-2014
389
A2890
20-11-2013 A
20-12-2013 A
A2840
07-12-2013 A
10-02-2014*
128
NCR-S370
11
10-12-2013 A
02-01-2014 A
NCR-S371
11
10-12-2013 A
02-01-2014 A
A2830
12
07-02-2014 A
27-02-2014
3281
89
25%
A2900
10
11-02-2014
20-02-2014
110
0%
A2910
11-02-2014
14-02-2014
135
116
0%
A1910
21-02-2014
02-03-2014
101
0%
A2920
15-03-2014
15-03-2014
89
0%
113
10
04-06-2013 A
04-06-2013 A
31-03-2014
31-03-2014
5198
564
82
82
100%
100%
2%
100%
110
89
0%
A2850
90%
100%
100%
4%
A3130
05-07-2013 A
15-03-2014
3945
89
98%
A3110
13
09-02-2014
21-02-2014
509
89
0%
A3120
Trenching & excavations for underground pit and conduit system for perimeter road lighting
11
23-02-2014
05-03-2014
90
89
0%
A3140
16-03-2014
19-03-2014
90
89
0%
YARNIMA.10.15.12.10 INSTRUMENTS
A5830
Install Instruments (Stage 2)
17
17
23-11-2013 A
23-11-2013 A
26-02-2014
26-02-2014
32
32
113
113
100%
147
7
21-04-2013 A
21-04-2013 A
15-05-2014
15-05-2014
4090
268
40
40
20%
20-02-2014
1292
63
80%
98
53.3%
A20880
12
27-09-2013 A
A20900
Steam Silencers
15
28-09-2013 A
24-02-2014
450
A20910
10
12-10-2013 A
23-11-2013 A
2080
A20920
Installtaion of Bollards
YARNIMA.10.15.4 HRSG-3
YARNIMA.10.15.4.2 HRSG3 - ACTUAL VARIATIONS & NON SCOPE WORKS
NCR-S149-680 Modify Client Supply Material - DA Structure Fitment
16-03-2014
24-03-2014
89
417
123
1
22-01-2013 A
17-07-2013 A
17-07-2013 A
17-04-2014
19-12-2013 A
18-07-2013 A
40491
1279
38
66
0%
Installtaion of Bollards
YARNIMA.10.15.4 HRSG-3
YARNIMA.10.15.4.2 HRSG3 - ACTUAL VARIATIONS & NON
100%
27
31-07-2013 A
28-08-2013 A
100%
NCR-S175
02-08-2013 A
05-08-2013 A
100%
NCR-S176
32
03-08-2013 A
05-09-2013 A
100%
NCR-S184
17
08-08-2013 A
26-08-2013 A
100%
NCR-S185
35
09-08-2013 A
15-09-2013 A
100%
NCR-S187
12-08-2013 A
19-08-2013 A
100%
NCR-S193
16
17-08-2013 A
02-09-2013 A
100%
VEHRSG3000
VE HRSG3 - Replace Burner Studs, modify Top Burner Platform and clean inside of piping
4
17-08-2013 A
20-08-2013 A
78
100%
NCR-S198
25-08-2013 A
31-08-2013 A
100%
53
27-08-2013 A
22-10-2013 A
274
100%
VEHRSG3010
30-08-2013 A
31-08-2013 A
30
100%
17
01-09-2013 A
18-09-2013 A
70
100%
100%
NCR-S168
VE HRSG3 - Replace Burner Studs, modify Top Burner Platform and clean insid
HRSG3 De-aerator/ Boiler FW Pumps pipework - supports not supplied
Deaerator Piping - HRSG 3
VE HRSG3 - DA Piping - Flange Out of Tolerance
Modifications to Deaerator Piping Supports - HRSG 3 - A15480
VEHRSG3020
VE HRSG3 - Replace Burner Studs, modify Top Burner Platform and clean inside of piping
19
08-09-2013 A
27-09-2013 A
240
100%
NCR-S229
10-09-2013 A
14-09-2013 A
100%
NCR-S229-1028 Weld Drum Bearing Plates to Saddle Base plate - Steam Drum A15400
13-09-2013 A
17-09-2013 A
110
100%
Weld Drum Bearing Plates to Saddle Base plate - Steam Drum A15400
NCR-S251
16
19-09-2013 A
06-10-2013 A
100%
NCR-S268
21
28-09-2013 A
20-10-2013 A
100%
VEHRSG3030
08-10-2013 A
12-10-2013 A
82
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 26 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
VE HRSG3 - Replace Burner Studs, modify Top Burner Platform and clean
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
VEHRSG3040
VE HRSG3 - Cat Ladder Gridmesh Access Issues, S/heater Tube Bank Thermocouple18Attachments,
18-10-2013
PipingAMods,06-11-2013
Steelwork mods
A
263
100%
NCR-S316
51
26-10-2013 A
19-12-2013 A
100%
NCR-S337
10
11-11-2013 A
21-11-2013 A
20
100%
NCR-S343
13
14-11-2013 A
27-11-2013 A
12
100%
NCR-S348
04-12-2013 A
100%
VEHRSG3050
VE HRSG3 - Missing Bolt Holes on Column HD, Economiser Feedwater Piping Supports
4 Non-Conformance,Tundish
17-11-2013 A
20-11-2013
ET-1 Fabricated
A
62
100%
NCR-S360
100%
25-11-2013 A
29-11-2013 A
335
335
24-01-2013 A
24-01-2013 A
23-02-2014
23-02-2014
16755
0
116
116
96.1%
A15410-a
24-01-2013 A
25-01-2013 A
100%
A15380-a
02-02-2013 A
04-02-2013 A
100%
A15390-a
02-02-2013 A
05-02-2013 A
100%
A15540-a
04-02-2013 A
05-02-2013 A
100%
A15370
32
23-03-2013 A
30-01-2014 A
2500
100%
A15460
21
17-04-2013 A
07-08-2013 A
1085
100%
NCR-S073
HRSG3 boiler inlet duct roof section between HX and HZ line, 30mm off
87
30-04-2013 A
01-08-2013 A
100%
NCR-S081
17
17-05-2013 A
04-06-2013 A
100%
NCR-S084
38
19-05-2013 A
27-06-2013 A
100%
NCR-S093
14
31-05-2013 A
14-06-2013 A
100%
A15470
11-06-2013 A
23-08-2013 A
50
100%
NCR-S128
19-06-2013 A
23-06-2013 A
100%
NCR-S145
04-07-2013 A
05-07-2013 A
100%
NCR-S149
07-07-2013 A
09-07-2013 A
100%
A15450
09-07-2013 A
08-10-2013 A
700
100%
A15500
16-07-2013 A
25-09-2013 A
100
100%
A22670
16-07-2013 A
21-09-2013 A
100%
NCR-S159
23-07-2013 A
29-07-2013 A
100%
A21340
24-07-2013 A
25-07-2013 A
220
100%
A15380
Remove Shipping Bracing and Install FLoor and Side Panels Module 1-2
16
28-07-2013 A
24-09-2013 A
2130
100%
NCR-S172
43
01-08-2013 A
15-09-2013 A
100%
A15420
18
07-08-2013 A
01-11-2013 A
1540
100%
NCR-S181
07-08-2013 A
14-08-2013 A
100%
A21290
10-08-2013 A
29-01-2014 A
160
100%
A21350
11-08-2013 A
02-01-2014 A
350
100%
NCR-S186
34
11-08-2013 A
15-09-2013 A
100%
A15430
13-08-2013 A
09-10-2013 A
420
100%
A15510
13-08-2013 A
19-11-2013 A
100
100%
A21280
11
13-08-2013 A
25-09-2013 A
600
100%
A15390
Remove Shipping Bracing and Install FLoor and Side Panels Module 2-3 - HRSG 3 16
14-08-2013 A
28-12-2013 A
2100
100%
A15410
10
14-08-2013 A
27-01-2014 A
650
100%
A15540
11
14-08-2013 A
26-09-2013 A
600
100%
A21330
28
15-08-2013 A
27-09-2013 A
1660
100%
A21300
16-08-2013 A
01-10-2013 A
250
100%
NCR-S192
10
17-08-2013 A
27-08-2013 A
100%
A15490
26-08-2013 A
08-10-2013 A
100
100%
A15440
10
26-08-2013 A
10-12-2013 A
150
100%
NCR-S206
30-08-2013 A
100%
A15400
31-08-2013 A
27-09-2013 A
80
A21320
12
04-09-2013 A
23-02-2014
800
NCR-S217
04-09-2013 A
05-09-2013 A
100%
NCR-S221
HRSG3: Incorrect Hole Centre of the Beam for the HRSG Steam Drums Silencer
05-09-2013 A
05-09-2013 A
100%
HRSG3: Incorrect Hole Centre of the Beam for the HRSG Steam Drums Silen
NCR-S223
05-09-2013 A
06-09-2013 A
100%
NCR-S224
HRSG3: HRSG Stair Tower Landing, Handrail Gaps & Stair Treads Rise
06-09-2013 A
12-09-2013 A
100%
NCR-S226
HRSG3: Incorrect Location of the Bolt Holes for the Knee Brace (Grid HG) of the Top 20
Platform08-09-2013 A
28-09-2013 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 27 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
100%
116
98%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
HRSG3: HRSG Stair Tower Landing, Handrail Gaps & Stair Treads Rise
HRSG3: Incorrect Location of the Bolt Holes for the Knee Brace (Grid HG)
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
NCR-S256
20-09-2013 A
20-09-2013 A
100%
A21310
21-09-2013 A
19-10-2013 A
200
100%
NCR-S261
24-09-2013 A
30-09-2013 A
100%
NCR-S297
17-10-2013 A
22-10-2013 A
100%
NCR-S314
25-10-2013 A
25-10-2013 A
100%
NCR-S317
13
26-10-2013 A
08-11-2013 A
100%
NCR-S319
27-10-2013 A
01-11-2013 A
100%
NCR-S322
HRSG3 Kick Plates in the Way of Welding Soppers for Deaerator Support
13
27-10-2013 A
09-11-2013 A
100%
NCR-S349
HRSG3 Tundish ET-1 Fabricated Not in Compliance with the Construction Drawing 5
17-11-2013 A
21-11-2013 A
100%
NCR-S356
22-11-2013 A
22-11-2013 A
100%
A21360
11-12-2013 A
18-12-2013 A
210
100%
201
169
20
28-07-2013 A
05-08-2013 A
05-08-2013 A
29-03-2014
10-03-2014
16-02-2014
8314
2514
960
84
84
75
95%
A16350
18
10-08-2013 A
16-01-2014 A
930
100%
NCR-S190
12
15-08-2013 A
27-08-2013 A
100%
NCR-S203
20
26-08-2013 A
15-09-2013 A
100%
NCR-S218
04-09-2013 A
05-09-2013 A
100%
NCR-S240
16-09-2013 A
17-09-2013 A
100%
NCR-S249
18-09-2013 A
24-09-2013 A
100%
NCR-S272
01-10-2013 A
02-10-2013 A
100%
NCR-S299
23-10-2013 A
25-10-2013 A
100%
NCR-S326
29-10-2013 A
01-11-2013 A
100%
NCR-S333
01-11-2013 A
01-11-2013 A
100%
NCR-S333-1361
HRSG3 Wet Rack Drain Lines (1361)
01-11-2013 A
04-11-2013 A
34
100%
NCR-S387
19-12-2013 A
19-12-2013 A
100%
A22700
18
08-01-2014 A
10-03-2014
500
84
40%
A22690-a
18-02-2014
23-02-2014
90
84
0%
193
18
28-07-2013 A
28-07-2013 A
29-03-2014
27-01-2014 A
4340
320
84
75
100%
A16390
25
18-08-2013 A
21-02-2014
1350
A16620
13
18-08-2013 A
16-01-2014 A
280
100%
A16610
16
22-08-2013 A
29-01-2014 A
350
100%
A16600
16
23-08-2013 A
29-01-2014 A
200
100%
NCR-S222
13
05-09-2013 A
18-09-2013 A
100%
NCR-S259
22-09-2013 A
29-09-2013 A
100%
NCR-S262
24-09-2013 A
25-09-2013 A
100%
A16340
16
06-10-2013 A
14-01-2014 A
200
100%
A16400
13
11-10-2013 A
29-01-2014 A
500
100%
NCR-S302
HRGS3: Vendor Fabricated Piping Spools Not in Compliance with Design Drawings 10
21-10-2013 A
30-10-2013 A
100%
NCR-S313
25-10-2013 A
28-10-2013 A
100%
NCR-S323
28-10-2013 A
30-10-2013 A
100%
NCR-S367
07-12-2013 A
15-12-2013 A
100%
NCR-S384
HRSG Missing Design of Drain Piping Connecting Steam Drum Safety Valve Discharge1 Piping 18-12-2013
and Vent A
18-12-2013 A
100%
A22710
23-02-2014
27-02-2014
90
94
0%
A22720
18
11-03-2014
29-03-2014
1050
84
0%
43
10
21-08-2013 A
21-08-2013 A
01-03-2014
10-01-2014 A
1460
300
110
98%
100%
A16380
10
23-08-2013 A
29-01-2014 A
220
100%
A16370
10
15-09-2013 A
16-01-2014 A
120
100%
A15530
18
21-09-2013 A
01-03-2014
500
110
90%
A16410
27-11-2013 A
17-02-2014
230
110
80%
A16380-N2_Sys
HRSG N2 system. New Drawings: Runs from ground to Steam Drum level on each HRSG
1
09-02-2014*
09-02-2014
122
0%
A6400
18-02-2014
23-02-2014
90
110
0%
244
23-05-2013 A
26-03-2014
6953
73
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 28 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A2460
23-05-2013 A
23-02-2014
1148
66
24%
A10690
244
23-05-2013 A
26-03-2014
73
0%
A2460-a
14
23-05-2013 A
17-02-2014
71
65%
NCR-S116
77
09-06-2013 A
30-08-2013 A
100%
A2450
19-08-2013 A
08-10-2013 A
425
100%
NCR-S200
HRSG3: Inconsistencies of the Supply and Designed of Cable Ladder Supports for the7HRSG 25-08-2013 A
31-08-2013 A
100%
NCR-S208
16
30-08-2013 A
15-09-2013 A
100%
A2510-a
17-09-2013 A
06-03-2014
A2430
20-09-2013 A
14-10-2013 A
168
NCR-S254
BOP: The conduit (H3LVC01-04) is too small for the amount of cables
20-09-2013 A
25-09-2013 A
A2510
25
24-09-2013 A
12-03-2014
294
86
15%
A2470
25
29-09-2013 A
11-03-2014
1856
66
1%
NCR-S278
10-10-2013 A
16-10-2013 A
A2530
35
11-10-2013 A
24-03-2014
2563
NCR-S292
13
16-10-2013 A
29-10-2013 A
A2480
28
04-11-2013 A
26-03-2014
422
66
0.5%
A2490
27-01-2014 A
19-02-2014
105
50%
A2520
10
09-02-2014
106
0%
191
22-01-2013 A
YARNIMA.10.15.4.7 HRSG3 BYPASS STACK & DAMPERS
NCR-S030
ByPass 3: GT3 Bypass Stack: The Vendor Supplier have not included the supply of handrail
13
bolts
22-01-2013 A
91
15%
100%
100%
BOP: The conduit (H3LVC01-04) is too small for the amount of cables
100%
75
90%
100%
18-02-2014
77
10-10-2013 A
04-02-2013 A
4740
0
100%
A5350
21
05-02-2013 A
11-05-2013 A
1160
100%
A6420
21
16-02-2013 A
20-07-2013 A
850
100%
A6450
18-02-2013 A
10-04-2013 A
735
100%
NCR-S016
13
20-02-2013 A
05-03-2013 A
100%
NCR-S017
GTG3: GT3- Steel Work For Platform And Cross Bracing For Enclosure
13
21-02-2013 A
06-03-2013 A
100%
GTG3: GT3- Steel Work For Platform And Cross Bracing For Enclosure
NCR-S018
ByPass 3: Bypass Stack - Silencer Outlet Transition - Remove and refit cladding
13
21-02-2013 A
06-03-2013 A
100%
ByPass 3: Bypass Stack - Silencer Outlet Transition - Remove and refit cladding
A6430
23-02-2013 A
27-04-2013 A
720
100%
A6460
05-03-2013 A
27-04-2013 A
550
100%
NCR-S029
ByPass 3: Bypass Stack Platform: Incorrect Supply of Gridmesh, Wrong Location of Bolt
13 Holes,05-03-2013
Handrails gaps.
A
18-03-2013 A
100%
ByPass 3: Bypass Stack Platform: Incorrect Supply of Gridmesh, Wrong Location of Bolt Holes, Handrails
NCR-S037
ByPass 3: Bypass Stack Ladder and Platform Support Assembly : 2 x Beams were supplied
13
too22-03-2013
long
A
04-04-2013 A
100%
ByPass 3: Bypass Stack Ladder and Platform Support Assembly : 2 x Beams were supplied too long
A9050
23-03-2013 A
26-07-2013 A
725
100%
NCR-S044
ByPass 3: Mounting for the Seal Air Unit Fans for HRSG-3 have been damaged.
13
29-03-2013 A
11-04-2013 A
100%
ByPass 3: Mounting for the Seal Air Unit Fans for HRSG-3 have been damaged.
NCR-S049
13
01-04-2013 A
14-04-2013 A
100%
NCR-S074
08-05-2013 A
09-05-2013 A
100%
NCR-S082
ByPass 3: HRSG3 Bypass Stack cast-in hold down bolts and baseplates misalignment17
17-05-2013 A
04-06-2013 A
100%
ByPass 3: HRSG3 Bypass Stack cast-in hold down bolts and baseplates misalignment
NCR-S085
16
19-05-2013 A
04-06-2013 A
100%
NCR-S125
13
17-06-2013 A
30-06-2013 A
100%
NCR-S148
ByPass 3: GTG3 to ByPass Stack Expansion Joint Area - Studs Don't Line Up
06-07-2013 A
09-07-2013 A
100%
A21080
19
14-07-2013 A
10-10-2013 A
100%
NCR-S173
28
01-08-2013 A
30-08-2013 A
100%
NCR-S177
19
03-08-2013 A
22-08-2013 A
100%
NCR-S195
17
19-08-2013 A
05-09-2013 A
100%
79
20
16-12-2013 A
16-12-2013 A
17-04-2014
01-03-2014
2450
1050
66
110
55%
A10330
14
01-01-2014 A
01-03-2014
280
110
80%
A22870
14
05-02-2014 A
17-04-2014
651
66
10%
A10310
20
13-03-2014
02-04-2014
469
66
0%
A10350
02-04-2014
80
0%
61
YARNIMA.10.15.5 HRSG-2
YARNIMA.10.15.5.3 HRSG2 - ACTUAL VARIATIONS & NON SCOPE WORKS
NCR-S215
HRSG2 DA Pipework - Flange Misaligned on Line # HILCA30BR010/015
343
102
7
05-02-2013 A
01-09-2013 A
01-09-2013 A
23-04-2014
19-12-2013 A
08-09-2013 A
39666
307
0
100%
NCR-S216
02-09-2013 A
11-09-2013 A
100%
NCR-S219
05-09-2013 A
09-09-2013 A
100%
VEHRSG2010
VE HRSG2 - Temporary supports for HRSG Boiler Module, Inlet Duct Roof Misaligned,4 DA Struct
13-09-2013
Upper Level
A Fitment
16-09-2013
Issue A
115
100%
70
100%
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
15-09-2013 A
Page 29 of 38
Data Date 07-02-2014
18-09-2013 A
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
VE HRSG2 - Temporary supports for HRSG Boiler Module, Inlet Duct Roof M
HRSG2 Inlet Duct Roof Misalignment -Rework
Checked
Approved
WC
KU
KU
TL
Activity ID
Activity Name
Original
Duration
Start
26
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
NCR-S294
17-10-2013 A
13-11-2013 A
100%
VEHRSG2000
VE HRSG2 - Modify Dearator Structure Cleat, spool underside deaerator silencer, LAA90BR704
5
24-10-2013
spool 1&2A
28-10-2013 A
116
100%
NCR-S318
13
27-10-2013 A
09-11-2013 A
100%
18-11-2013 A
18-11-2013 A
100%
NCR-S354
29
19-11-2013 A
19-12-2013 A
100%
296
296
05-02-2013 A
05-02-2013 A
11-03-2014
11-03-2014
16821
0
0%
94
94
A13090-a
05-02-2013 A
07-02-2013 A
100%
A13940-a
05-02-2013 A
08-02-2013 A
100%
A15550-a
05-02-2013 A
08-02-2013 A
100%
A13060-a
14-02-2013 A
15-02-2013 A
100%
A13060
Remove Shipping Bracing and Install FLoor and Side Panels Module 1-2
13
01-08-2013 A
28-10-2013 A
2130
100%
A13090
10
04-08-2013 A
11-02-2014
650
A13050
22
15-08-2013 A
29-01-2014 A
2500
100%
A13940
Remove Shipping Bracing and Install FLoor and Side Panels 2 Module 2-3 - HRSG 2 13
18-08-2013 A
29-01-2014 A
2100
100%
A13110
12
22-08-2013 A
24-09-2013 A
1085
100%
A13120
25-08-2013 A
14-12-2013 A
700
100%
A21220
27-08-2013 A
12-09-2013 A
50
100%
A13080
28-08-2013 A
11-09-2013 A
420
100%
A13140
28-08-2013 A
26-09-2013 A
220
100%
A13160
29-08-2013 A
11-09-2013 A
100
100%
NCR-S214
01-09-2013 A
01-09-2013 A
100%
NCR-S225
06-09-2013 A
12-09-2013 A
100%
A15550
10-09-2013 A
29-01-2014 A
600
100%
13-09-2013 A
13-09-2013 A
11
100%
A21170
14-09-2013 A
06-02-2014 A
160
100%
NCR-S237
14-09-2013 A
14-09-2013 A
100%
NCR-S237-1060 HRSG2 - Trim upper Panels LWP1A, LWP2A, RWP1A and RWP2A to enable panels to
1 fit
14-09-2013 A
15-09-2013 A
15
100%
HRSG2 - Trim upper Panels LWP1A, LWP2A, RWP1A and RWP2A to enab
NCR-S238
15-09-2013 A
15-09-2013 A
100%
NCR-S241
HRSG2: Incorrect Alignment of the Stiffener welded to the Column for the Cross Bracing
1
18-09-2013 A
18-09-2013 A
100%
HRSG2: Incorrect Alignment of the Stiffener welded to the Column for the C
NCR-S263
24-09-2013 A
25-09-2013 A
100%
A21160
26-09-2013 A
29-01-2014 A
600
100%
NCR-S265
29
26-09-2013 A
26-10-2013 A
100%
A21230
27-09-2013 A
20-12-2013 A
350
100%
A22680
Insulation and Liner Plates for Inlet-Outlet Duct and Pannels - HRSG 2
25
27-09-2013 A
20-02-2014
A21190
30-09-2013 A
08-10-2013 A
200
A21200
12
01-10-2013 A
20-02-2014
800
A21180
02-10-2013 A
02-01-2014 A
250
100%
A21210
21
02-10-2013 A
29-10-2013 A
1660
100%
09-10-2013 A
10-10-2013 A
20
100%
11-10-2013 A
15-01-2014 A
100
A13100
12
20-10-2013 A
27-02-2014
1540
NCR-S310
23-10-2013 A
26-10-2013 A
27-10-2013 A
NCR-S327
30-10-2013 A
A13180
10
A13170
A13070
A21240
52
86
Remove Shipping Bracing and Install FLoor and Side Panels Module 1
95%
50%
100%
43
95%
100%
95%
100%
28-10-2013 A
20
100%
31-10-2013 A
100%
23-11-2013 A
03-03-2014
150
05-01-2014 A
02-02-2014 A
100
06-01-2014 A
10-02-2014
80
04-03-2014
11-03-2014
210
148
106
20
01-09-2013 A
01-09-2013 A
01-09-2013 A
15-04-2014
16-03-2014
20-02-2014
25%
94
0%
8320
2520
960
61
61
68
70%
61
70%
21-09-2013 A
24-02-2014
930
NCR-S321
27-10-2013 A
29-10-2013 A
Remaining Work
Baseline Milestone
Milestone
Page 30 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
52
18
Summary
50%
Primary Baseline
94
100%
A16630
Actual Work
43
100%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
61
Activity % S
Complete
25%
A22740
14
27-11-2013 A
16-03-2014
500
NCR-S376
11-12-2013 A
13-12-2013 A
100%
NCR-S376-1569
HRSG2 Deaerator Piping Fabrication rectification
15-12-2013 A
17-12-2013 A
40
100%
A22730
25-02-2014
01-03-2014
90
61
0%
97
12
06-09-2013 A
06-09-2013 A
31-03-2014
18-02-2014
4340
280
61
65
55%
A16640
18
11-10-2013 A
18-02-2014
320
65
70%
A16670
20
04-11-2013 A
09-03-2014
1350
63
65%
A16700
10
25-11-2013 A
10-03-2014
200
62
45%
A16710
10
27-11-2013 A
10-03-2014
350
62
45%
A16680
28-11-2013 A
15-03-2014
500
62
65%
A16420
10
28-01-2014 A
25-03-2014
200
62
25%
A22760
10-03-2014
14-03-2014
90
63
0%
A22750
14
17-03-2014
31-03-2014
1050
61
0%
62
5
02-10-2013 A
02-10-2013 A
15-04-2014
19-03-2014
1460
120
61
62
50%
A13190
10
16-12-2013 A
15-03-2014
300
62
40%
A16660
10
06-01-2014 A
19-03-2014
220
62
25%
A16690
20-03-2014
25-03-2014
230
62
0%
A13320
26-03-2014
30-03-2014
90
62
0%
A13220
14
01-04-2014
15-04-2014
500
61
0%
198
198
16-08-2013 A
16-08-2013 A
04-04-2014
04-04-2014
7028
0
71
71
0%
62
5%
20
16-08-2013 A
15-03-2014
294
A13230
20-08-2013 A
17-10-2013 A
431
A13250
15-09-2013 A
21-02-2014
1144
62
25%
A13250-a
14
15-09-2013 A
14-03-2014
43
25%
A13290
22-09-2013 A
21-10-2013 A
168
A13300
19
23-09-2013 A
03-04-2014
1906
43
2%
A13310
18
23-09-2013 A
02-04-2014
445
71
2%
A13240
30
16-12-2013 A
27-03-2014
2563
75
50%
A13260
10
28-02-2014
10-03-2014
77
95
0%
A13280
15-03-2014
18-03-2014
87
0%
A13270-a
20
15-03-2014
04-04-2014
71
0%
123
42
04-05-2013 A
04-05-2013 A
29-01-2014 A
09-10-2013 A
4740
1160
100%
100%
A11350
42
06-05-2013 A
28-08-2013 A
850
100%
NCR-S076
ByPass 2: HRSG2 ByPass Stack Column Brackets not shown on the AFC Drawings 13
10-05-2013 A
23-05-2013 A
100%
A11360
28
15-05-2013 A
15-05-2013 A
735
100%
A11370
28
16-05-2013 A
10-10-2013 A
1270
100%
NCR-S080
13
16-05-2013 A
29-05-2013 A
100%
A11380
14
23-05-2013 A
12-09-2013 A
725
100%
NCR-S248
19
18-09-2013 A
08-10-2013 A
100%
A21120
10
04-10-2013 A
29-01-2014 A
100%
36
28
16-03-2014
16-03-2014
23-04-2014
14-04-2014
2450
469
61
62
100%
0%
A13330
25
20-03-2014
15-04-2014
1050
61
0%
A13350
14
01-04-2014
15-04-2014
280
68
0%
A10860
15-04-2014
68
0%
A22880
16-04-2014
23-04-2014
651
61
0%
336
36
10
07-04-2013 A
11-11-2013 A
11-11-2013 A
16-05-2014
19-12-2013 A
21-11-2013 A
39355
40
0
39
YARNIMA.10.15.6 HRSG-1
YARNIMA.10.15.6.2 HRSG1 - ACTUAL VARIATIONS & NON SCOPE WORKS
NCR-S339
HRSG1 Missing Bolt Holes on Column HD
100%
NCR-S353
29
19-11-2013 A
19-12-2013 A
100%
NCR-S364
04-12-2013 A
10-12-2013 A
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 31 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
06-12-2013 A
07-12-2013 A
100%
08-12-2013 A
09-12-2013 A
20
100%
NCR-S364-1528 HRSG1: HRSG-1 Dearator Top Level Platform rectify Multiple misalignment of structural
1 members
11-12-2013 A
11-12-2013 A
20
100%
NCR-S366
Budgeted
Labor Units
211
211
07-04-2013 A
07-04-2013 A
21-03-2014
21-03-2014
16785
0
Total
Float
91
89
Activity % S
Complete
23%
A13770-a
07-04-2013 A
08-04-2013 A
100%
A15570-a
08-04-2013 A
09-04-2013 A
100%
A15560-a
09-04-2013 A
10-04-2013 A
100%
A13800-a
10-04-2013 A
11-04-2013 A
100%
NCR-S153
HRSG3: Incorrect Gridmesh Clips and Gridmesh Spacing is more than 10mm
13
11-07-2013 A
24-07-2013 A
100%
A13800
10
03-09-2013 A
02-01-2014 A
650
100%
A13760
22
07-09-2013 A
06-01-2014 A
2500
100%
A13770
Remove Shipping Bracing and Install FLoor and Side Panels Module 1-2 - HRSG 1 13
08-09-2013 A
09-01-2014 A
2130
100%
A15570
Remove Shipping Bracing and Install FLoor and Side Panels Module 2-3 - HRSG 1 13
15-09-2013 A
09-01-2014 A
2100
100%
A21020
10
28-09-2013 A
10-01-2014 A
50
100%
A20990
02-10-2013 A
28-10-2013 A
200
100%
A13830
12
04-10-2013 A
13-02-2014
1085
39
80%
A20970
15-10-2013 A
12-02-2014
160
40
85%
A21010
21
20-10-2013 A
04-02-2014 A
1660
100%
NCR-S301
Bolt Holes between Lower Section of HRSG Main Stack and Damper Not Match
21-10-2013 A
22-10-2013 A
100%
NCR-S328
30-10-2013 A
31-10-2013 A
100%
A21000
01-11-2013 A
20-02-2014
800
01-11-2013 A
03-11-2013 A
30
41
HRSG3: Incorrect Gridmesh Clips and Gridmesh Spacing is more than 10mm
Bolt Holes between Lower Section of HRSG Main Stack and Damper N
HRSG1 Duct Burner to Boiler - Mounting Bolt Misalignment
97%
100%
A20960
10-11-2013 A
13-02-2014
600
39
90%
A13810
12
13-11-2013 A
03-03-2014
1540
39
45%
NCR-S342
32
13-11-2013 A
17-12-2013 A
100%
A15560
20-11-2013 A
20-02-2014
600
39
85%
A20980
21-11-2013 A
17-02-2014
250
44
90%
NCR-S379
15-12-2013 A
18-12-2013 A
A13780
23-12-2013 A
23-02-2014
80
A21030
13-01-2014 A
06-02-2014 A
350
A13880
14-01-2014 A
27-02-2014
100
108
10%
A13890
15-01-2014 A
01-03-2014
100
108
80%
A13790
16-01-2014 A
27-02-2014
420
108
25%
A13840
05-02-2014 A
23-02-2014
700
39
20%
A13850
05-02-2014 A
16-02-2014
220
39
20%
A22690
Insulation and Liner Plates for Inlet-Outlet Duct and Pannels - HRSG 1
14
09-02-2014
23-02-2014
86
0%
A13870
28-02-2014
01-03-2014
100
108
0%
A13820
10
04-03-2014
14-03-2014
150
67
0%
A21040
15-03-2014
21-03-2014
210
89
0%
203
163
2
08-09-2013 A
08-09-2013 A
08-09-2013 A
25-04-2014
13-03-2014
09-09-2013 A
8284
2484
0
57
83
NCR-S227-1021
HRSG1 DA Piping - Reestablish gramophone finish on Flange Face
10-09-2013 A
10-09-2013 A
A13860
20
27-09-2013 A
04-03-2014
960
72
25%
A16730
15
27-09-2013 A
02-03-2014
930
72
25%
A22770
14
27-02-2014
13-03-2014
500
83
0%
A22780
03-03-2014
07-03-2014
90
83
0%
97
18
23-11-2013 A
23-11-2013 A
14-04-2014
12-03-2014
4340
320
48
51
10%
100%
39
40%
100%
100%
100%
A16820
12
24-11-2013 A
05-03-2014
280
51
15%
A16770
20
25-11-2013 A
14-03-2014
1350
39
20%
A16500
10
26-11-2013 A
14-03-2014
200
77
10%
A16780
27-11-2013 A
28-02-2014
500
80
20%
A16800
10
29-11-2013 A
25-03-2014
200
57
15%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 32 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A16810
10
29-11-2013 A
25-03-2014
350
39
15%
A22800
26-03-2014
30-03-2014
90
39
0%
A22790
14
31-03-2014
14-04-2014
1050
39
0%
87
5
24-11-2013 A
24-11-2013 A
25-04-2014
09-03-2014
1460
120
57
77
10%
A16790
25-11-2013 A
14-03-2014
230
77
10%
A13900
10
26-11-2013 A
25-03-2014
300
67
15%
A16760
10
27-11-2013 A
04-04-2014
220
57
15%
A11150
06-04-2014
10-04-2014
90
57
0%
A13910
14
11-04-2014
25-04-2014
500
57
0%
212
6
19-08-2013 A
19-08-2013 A
06-05-2014
21-03-2014
7056
1140
47
74
11%
A11330
212
19-08-2013 A
06-05-2014
47
0%
A11110
20
26-08-2013 A
07-04-2014
300
74
12%
A11060
02-09-2013 A
22-10-2013 A
432
A11050
15-09-2013 A
21-10-2013 A
168
A11080
17
23-09-2013 A
30-04-2014
1931
NCR-S303
13
21-10-2013 A
03-11-2013 A
A11090
18
04-11-2013 A
06-05-2014
445
NCR-S381
15-12-2013 A
02-01-2014 A
A11120
10
04-03-2014
14-03-2014
77
96
0%
A13700
30
10-03-2014
10-04-2014
2563
64
0%
A11070-a
14
15-03-2014
29-03-2014
48
0%
A11100
30-03-2014
02-04-2014
78
0%
A11110-a
21
30-03-2014
21-04-2014
61
0%
265
36
04-05-2013 A
04-05-2013 A
01-03-2014
24-09-2013 A
4740
1160
110
43
100%
100%
10%
100%
43
0%
100%
100%
A13720
36
12-05-2013 A
27-08-2013 A
850
100%
A13730
28
15-05-2013 A
04-08-2013 A
735
100%
A13740
28
16-05-2013 A
03-01-2014 A
1270
100%
A13750
20
21-05-2013 A
06-01-2014 A
725
100%
NCR-S361
26-11-2013 A
28-11-2013 A
100%
A21110
20
09-02-2014
01-03-2014
110
0%
34
28
11-04-2014
11-04-2014
16-05-2014
10-05-2014
2450
469
39
43
0%
A11190
28
15-04-2014
14-05-2014
1050
39
0%
A22890
14
30-04-2014
14-05-2014
651
41
0%
A11750
14
02-05-2014
16-05-2014
280
39
0%
A11180
16-05-2014
39
0%
72
86
86
0%
179
152
152
15-09-2013 A
15-09-2013 A
15-09-2013 A
11-04-2014
27-03-2014
27-03-2014
7940
6840
0
5
5
19-09-2013 A
19-09-2013 A
24-09-2013 A
24-09-2013 A
0
0
114
15
15-09-2013 A
15-09-2013 A
27-03-2014
19-12-2013 A
6180
1460
100%
69
100%
A15300
Install Anchors
28-09-2013 A
04-11-2013 A
160
100%
A15150
10
03-10-2013 A
19-12-2013 A
1040
100%
A15160
24-10-2013 A
19-12-2013 A
380
100%
A15220
01-11-2013 A
08-01-2014 A
340
100%
A15170
12-11-2013 A
27-01-2014 A
460
100%
A15240
13-11-2013 A
18-12-2013 A
360
100%
A15180
26-11-2013 A
28-01-2014 A
120
100%
A15200
16
12-12-2013 A
27-03-2014
780
69
90%
A15280
13
16-12-2013 A
17-03-2014
160
69
85%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 33 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Install Anchors
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A15320
12
16-12-2013 A
16-02-2014
200
61
65%
A15250
17-02-2014
19-02-2014
240
61
0%
A15260
20-02-2014
01-03-2014
320
61
0%
A15270
02-03-2014
10-03-2014
160
69
0%
YARNIMA.10.15.11.1.6 PIPING
A15230
Install Distribution Pipework & Pads - CT2
78
13
03-11-2013 A
03-11-2013 A
13-03-2014
02-01-2014 A
660
440
77
11
02-03-2014
13-03-2014
220
61
0%
50
5
17-02-2014
17-02-2014
11-04-2014
21-02-2014
1100
100
72
95
0%
A15290
YARNIMA.10.15.11.3 PRECOMMISSIONING
A11850
Testing - CT2
100%
A11840
21
14-03-2014
11-04-2014
800
61
0%
A11770
10
26-03-2014
11-04-2014
200
61
0%
A11830
11-04-2014
72
0%
44
59
59
0%
218
203
203
26-08-2013 A
26-08-2013 A
26-08-2013 A
11-05-2014
25-04-2014
25-04-2014
10060
8960
0
80
1
26-08-2013 A
26-08-2013 A
25-09-2013 A
10-09-2013 A
2120
100
100%
Site Mobilization
A15100
Site Induction
27-08-2013 A
13-09-2013 A
140
100%
Site Induction
A15110
28-08-2013 A
24-09-2013 A
280
100%
A15330
Basin Survey
30-08-2013 A
25-09-2013 A
280
100%
Basin Survey
A15360
01-09-2013 A
25-09-2013 A
920
100%
A15350
10
09-09-2013 A
17-09-2013 A
200
100%
A15120
10
12-09-2013 A
19-09-2013 A
200
100%
108
10
07-10-2013 A
07-10-2013 A
22-04-2014
26-01-2014 A
6180
1460
YARNIMA.10.15.1.1.2 INSTALLATION
A3070
Assemble Upper & Lower Transverse Frames - CT1
YARNIMA.10.15.1.1.2 INSTALLATION
52
100%
A3080
20
13-10-2013 A
23-01-2014 A
1040
100%
A3310
04-11-2013 A
16-12-2013 A
160
100%
A3240
06-11-2013 A
10-03-2014
460
38
75%
A3300
13-11-2013 A
06-03-2014
780
38
10%
NCR-S359
21
22-11-2013 A
13-12-2013 A
A3250
12
21-12-2013 A
25-03-2014
200
38
15%
A3270
21-12-2013 A
27-03-2014
360
41
25%
A3510
22-12-2013 A
19-02-2014
160
38
30%
A3090
08-02-2014
13-02-2014
380
38
0%
A3490
11-03-2014
12-03-2014
340
38
0%
A3100
26-03-2014
05-04-2014
120
38
0%
A3280
07-04-2014
09-04-2014
240
38
0%
A3290
10-04-2014
13-04-2014
320
38
0%
A3320
14-04-2014
22-04-2014
160
52
0%
YARNIMA.10.15.1.1.6 PIPING
A3260
Install Distribution Pipework & Pads - CT1
113
15
03-11-2013 A
03-11-2013 A
25-04-2014
17-04-2014
660
440
48
55
Install Staircase & walkway to Tower 1 Install Ladders and Landings - CT1
100%
20%
NCR-S358
13
20-11-2013 A
03-12-2013 A
100%
A3330
11
14-04-2014
25-04-2014
220
43
0%
YARNIMA.10.15.1.3 PRECOMMISSIONING
A11720
Electrical & Mechanical Pre-Commissioning - CT1
26
21
14-04-2014
14-04-2014
11-05-2014
11-05-2014
1100
800
44
38
0%
A11170
10
26-04-2014
11-05-2014
200
38
0%
A11740
Testing - CT1
26-04-2014
30-04-2014
100
43
0%
A11730
11-05-2014
44
0%
33
261
118
1
21-07-2013 A
21-07-2013 A
21-07-2013 A
23-05-2014
13-12-2013 A
29-07-2013 A
26841
1846
0
29
16-08-2013 A
15-09-2013 A
100%
89
20-08-2013 A
23-11-2013 A
143
100%
VESTG1000
VE STG 1 - Condenser Grout Pockets Location, Generator terminal box support feet mods,
6
more
20-08-2013
room for A630mm2
26-08-2013
HV cables
A
219
100%
VESTG1010
VE STG 1 - Insufficient room for the 630mm2 HV cables on ST1 & ST2
205
100%
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
01-09-2013 A
Page 34 of 38
Data Date 07-02-2014
06-09-2013 A
Date
19-Dec-12
21-11-2013
07-02-2014
100%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
12-09-2013 A
19-09-2013 A
100%
56
20-09-2013 A
19-11-2013 A
405
100%
VESTG1020
VE STG 1 - Rectify Enclosure St/work, STG Condenser & Transition Piece Weld Prep,4 Weld Hotwell
20-09-2013
to Condenser
A
24-09-2013
Flange A
113
100%
NCR-S267
28-09-2013 A
04-10-2013 A
100%
NCR-S276
SGT1 and SGT2: Existing Condenser Weld Preparation for Welding onto T-Piece
07-10-2013 A
13-10-2013 A
100%
39
08-10-2013 A
18-11-2013 A
324
100%
VESTG1030
VE STG 1 - Rectify Enclosure St/work, Cable Ladder Route mod, Modify leakage steam
10 pipe 15-10-2013 A
25-10-2013 A
149
100%
NCR-S305
22-10-2013 A
30-10-2013 A
100%
NCR-S312
24-10-2013 A
30-10-2013 A
100%
25-10-2013 A
29-10-2013 A
90
100%
NCR-S325
29-10-2013 A
01-11-2013 A
100%
VESTG1040
VE STG 1 - Rectify Enclosure St/work, STG Cond.&Trans Piece Weld Prep, Weld Hotwell
8
to Cond
09-11-2013
Flge, cable
A ladder
17-11-2013
mods etc
A
189
100%
NCR-S368
08-12-2013 A
09-12-2013 A
100%
NCR-S369
09-12-2013 A
13-12-2013 A
100%
173
173
24-07-2013 A
24-07-2013 A
16-03-2014
16-03-2014
6487
0
NCR-S233
NCR-S276-1191 Repair Weld Prep for weld to T-Piece at STG's 1 and 2- A13210 and A14240
Budgeted
Labor Units
Total
Float
79
79
Activity % S
Complete
SGT1 and SGT2: Existing Condenser Weld Preparation for Welding ont
55.26%
A21530-a
24-07-2013 A
21-10-2013 A
280
100%
A11970
Prepare Foundation
25-07-2013 A
22-08-2013 A
120
100%
A12000
25-07-2013 A
03-08-2013 A
100
100%
A12020
27-07-2013 A
16-08-2013 A
120
100%
A12090
28-07-2013 A
20-08-2013 A
150
100%
A13430
28-07-2013 A
03-08-2013 A
120
100%
15
29-07-2013 A
21-08-2013 A
116
100%
NCR-S167
25
31-07-2013 A
26-08-2013 A
100%
NCR-S178
15
04-08-2013 A
19-08-2013 A
100%
A14150
08-08-2013 A
13-11-2013 A
60
100%
A13680
13-08-2013 A
13-09-2013 A
112
100%
A14140
20-08-2013 A
10-09-2013 A
160
100%
A12550
21-08-2013 A
11-09-2013 A
240
100%
A14010
21-08-2013 A
10-09-2013 A
120
100%
A14020
22-08-2013 A
13-09-2013 A
120
100%
A14080
23-08-2013 A
19-12-2013 A
120
100%
A13210
25-08-2013 A
06-10-2013 A
80
100%
A13450
27-08-2013 A
13-09-2013 A
120
100%
A14090
28-08-2013 A
13-02-2014
275
33
95%
A14100
28-08-2013 A
15-02-2014
140
86
90%
A21550-a
30-08-2013 A
11-03-2014
190
33
60%
A12820
18
31-08-2013 A
23-11-2013 A
800
100%
A13460
31-08-2013 A
13-09-2013 A
90
100%
A13490
02-09-2013 A
04-09-2013 A
160
100%
NCR-S252
22-09-2013 A
24-09-2013 A
100%
NCR-S264
25-09-2013 A
29-09-2013 A
100%
NCR-S253
26-09-2013 A
27-09-2013 A
100%
NCR-S275
SGT1 and SGT2: Condenser Support Pedestals Missing Details & General Material Substitution
3
06-10-2013 A
08-10-2013 A
100%
SGT1 and SGT2: Condenser Support Pedestals Missing Details & Gener
09-10-2013 A
11-10-2013 A
24
100%
NCR-S280
11-10-2013 A
16-10-2013 A
100%
NCR-S281
12-10-2013 A
16-10-2013 A
100%
NCR-S282
12-10-2013 A
16-10-2013 A
100%
NCR-S283
12-10-2013 A
15-10-2013 A
100%
A14160
Complete Installation of Walls & Roof (Complete with Gantry Crane) - STG1
10
19-10-2013 A
01-03-2014
1200
NCR-S304
STG1 and STG2: STGs Leakage Steam Pipe Reorientate Existing Pipe by 90 Degree.2
22-10-2013 A
23-10-2013 A
NCR-S306
13
22-10-2013 A
04-11-2013 A
A14170
Install Primary Internal Pipe Rack- Pipe Supports and Platforms - STG1
21
27-10-2013 A
28-02-2014
820
NCR-S320
27-10-2013 A
30-10-2013 A
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 35 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
93
80%
100%
STG1 and STG2: STGs Leakage Steam Pipe Reorientate Existing Pipe
100%
32
95%
100%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
NCR-S315
28-10-2013 A
01-11-2013 A
100%
NCR-S324
29-10-2013 A
29-10-2013 A
100%
NCR-S329
31-10-2013 A
01-11-2013 A
100%
A21540-a
21
05-11-2013 A
16-03-2014
650
NCR-S340
12-11-2013 A
14-11-2013 A
100%
NCR-S341
STG1: Pipe Shoe Support Clash with the STG Enclosure wall
14-11-2013 A
14-11-2013 A
100%
STG1: Pipe Shoe Support Clash with the STG Enclosure wall
NCR-S344
STG1 & STG2: STG Internal Platform Earthing Cable Clash to Baseplate.
14-11-2013 A
17-11-2013 A
100%
STG1 & STG2: STG Internal Platform Earthing Cable Clash to Bas
NCR-S383
17-12-2013 A
18-12-2013 A
100%
A23020
15-02-2014*
165
12
13-08-2013 A
13-08-2013 A
45
94
02-05-2014
01-02-2014 A
5464
716
35
90%
0%
100%
A14070
10
21-08-2013 A
27-03-2014
600
35
80%
A14050
24
23-08-2013 A
12-04-2014
980
49
95%
A14060
18
05-10-2013 A
22-04-2014
340
45
85%
A13690
24-10-2013 A
05-02-2014 A
120
NCR-S308
STG1 & STG2: STG1 and STG2 isometric drawings dimension conflict
26-10-2013 A
27-10-2013 A
A13580
14
27-10-2013 A
11-04-2014
279
NCR-S330
31-10-2013 A
01-11-2013 A
A13570
14
11-11-2013 A
11-04-2014
800
NCR-S377
11-12-2013 A
13-12-2013 A
100%
NCR-S377-1567 STG : STG1&2 Condensate line - fittings missing lead time and delivery
15-12-2013 A
19-12-2013 A
100%
A13560
10
16-12-2013 A
10-03-2014
200
51
10%
A14110
06-01-2014 A
19-03-2014
530
36
15%
A14740
20
12-04-2014
02-05-2014
600
35
0%
A21560-a
Hydrotest - STG1
13-04-2014
17-04-2014
299
49
0%
186
20
11-08-2013 A
11-08-2013 A
05-05-2014
16-02-2014
11034
748
33
74
90%
100%
100%
49
STG1 & STG2: STG1 and STG2 isometric drawings dimension conflict
50%
100%
35
60%
Hydrotest - STG1
YARNIMA.10.15.7.3 ELECTRICAL STG
Cable Ladder STG MV Switchroom - STG1
A2740
12
17-08-2013 A
20-02-2014
827
65
85%
A2570
07-09-2013 A
09-02-2014
193
74
95%
A2560
15-09-2013 A
10-02-2014
159
75
95%
A2550
17-09-2013 A
09-02-2014
186
75
95%
A2700
27-09-2013 A
01-04-2014
657
33
50%
A2710
Pull LV-C&I Cabling - STG1 (To CWP - CT Fans - Water Treatment - HRSG Pmps) 42
28-09-2013 A
20-04-2014
3727
33
35%
NCR-S273
02-10-2013 A
03-10-2013 A
100%
NCR-S279
10-10-2013 A
11-10-2013 A
100%
NCR-S293
STG1 & STG2: Inadequate Clearance Between CTs and Gland Plates
14-10-2013 A
14-10-2013 A
100%
STG1 & STG2: Inadequate Clearance Between CTs and Gland Plates
NCR-S293-1249 STG1 & STG2: increase clearance Between CTs and Gland Plates
14-10-2013 A
16-10-2013 A
40
100%
STG1 & STG2: increase clearance Between CTs and Gland Plates
NCR-S290
15-10-2013 A
15-10-2013 A
100%
NCR-S291
15-10-2013 A
22-10-2013 A
100%
A2720
14
18-10-2013 A
05-05-2014
882
33
13%
A3210
22
23-10-2013 A
10-03-2014
1850
65
40%
NCR-S336
13
10-11-2013 A
23-11-2013 A
100%
NCR-S350
17-11-2013 A
17-11-2013 A
100%
A3230
17
03-12-2013 A
21-03-2014
25
NCR-S373
Clarification to run the cable from ST1 to Switch yard through broken conduit
11
10-12-2013 A
02-01-2014 A
NCR-S385
Clarification on glanding and termination of cables on electrical fire pump control panel 4on water18-12-2013
treatment A
02-01-2014 A
A23030
Pull Power Cables from STG to Cooling Tower 1 (Resource in STG Works)
18
20-12-2013 A
21-02-2014
98
A7420
20
08-01-2014 A
25-03-2014
1046
A2770
23-03-2014
31-03-2014
A2800
02-04-2014
A2790
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
65
52%
100%
100%
30%
71
25%
65
0%
03-04-2014
40
40
0%
04-04-2014
12-04-2014
654
40
0%
51
2
23-09-2013 A
23-09-2013 A
23-05-2014
02-10-2013 A
2010
80
33
10
16-10-2013 A
23-05-2014
150
33
Page 36 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
100%
13%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A2680
28
06-04-2014
05-05-2014
616
33
0%
A7610
20
14-04-2014
05-05-2014
640
33
0%
A7270
14
21-04-2014
05-05-2014
80
33
0%
A22900
30-04-2014
05-05-2014
41
0%
A7620
05-05-2014
33
0%
A14120
13-05-2014
20-05-2014
444
36
0%
284
88
5
02-08-2013 A
15-08-2013 A
15-08-2013 A
27-06-2014
18-11-2013 A
19-08-2013 A
25696
783
78
20
25-09-2013 A
100%
VESTG2010
15-10-2013 A
443
100%
VESTG2020
VE STG1&2 - paint bellows, valves and reducers for piping, set up temp elect suppy to8HV switch
30-10-2013
room, Wait
A for drill
07-11-2013
rig
A
226
100%
VESTG2030
VE STG 2 - Labour assistance for Global Testing Services as requested from Worley Parsons
2
15-11-2013 A
18-11-2013 A
36
100%
178
5
02-08-2013 A
02-08-2013 A
02-04-2014
22-10-2013 A
6347
280
51
100%
A14210
03-08-2013 A
10-09-2013 A
150
100%
A14180
Prepare Foundation
06-08-2013 A
02-09-2013 A
120
100%
A14190
09-08-2013 A
08-09-2013 A
100
A14320
12-08-2013 A
12-02-2014
112
A14200
13-08-2013 A
09-09-2013 A
120
100%
A14360
14-08-2013 A
06-09-2013 A
120
100%
A14220
21-08-2013 A
11-09-2013 A
240
100%
A14240
25-08-2013 A
09-10-2013 A
80
100%
A14250
27-08-2013 A
01-09-2013 A
120
100%
A14350
29-08-2013 A
10-09-2013 A
120
100%
A14420
30-08-2013 A
12-02-2014
275
95%
A14430
30-08-2013 A
16-02-2014
140
59
90%
NCR-S209
30-08-2013 A
31-08-2013 A
A14230
18
03-09-2013 A
02-04-2014
800
A14480
04-09-2013 A
22-09-2013 A
160
100%
A14260
10-09-2013 A
20-09-2013 A
120
100%
A14280
10-09-2013 A
15-09-2013 A
160
100%
A14270
11-09-2013 A
16-09-2013 A
90
100%
A14410
13-10-2013 A
07-01-2014 A
120
100%
A21770-a
15-10-2013 A
23-03-2014
190
55%
A14490
16-10-2013 A
20-02-2014
60
59
80%
A21690-a
05-11-2013 A
07-03-2014
650
65
70%
A14440
14
10-11-2013 A
28-02-2014
820
32
70%
NCR-S357
STG2 Weld Prep Quality - Condenser to Transition-Piece FW5 & Transition-Piece to Turbine
23
FW6
20-11-2013 A
100%
A14500
100%
97
90%
100%
0
60%
13-12-2013 A
30
05-02-2014 A
20-03-2014
1200
59
221
7
28-08-2013 A
28-08-2013 A
04-05-2014
03-09-2013 A
6236
0
38
100%
63
04-09-2013 A
11-11-2013 A
772
100%
A14380
12
13-09-2013 A
01-02-2014 A
716
100%
A14300
21
16-09-2013 A
14-04-2014
800
51
48%
A14330
24
20-09-2013 A
12-04-2014
980
38
90%
A14400
10
03-10-2013 A
07-04-2014
600
38
70%
A14390
18
14-10-2013 A
09-04-2014
340
53
55%
A14340
23-10-2013 A
06-02-2014 A
120
A14310
14
27-10-2013 A
11-04-2014
279
38
40%
A14290
10
24-03-2014
02-04-2014
200
62
0%
A14450
24-03-2014
31-03-2014
530
38
0%
A15630
20
13-04-2014
04-05-2014
600
38
0%
A21910-a
Hydrotest - STG2
15-04-2014
20-04-2014
299
51
0%
224
9
18-08-2013 A
18-08-2013 A
12-06-2014
17-02-2014
10320
631
1
49
80%
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 37 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
10%
100%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Hydrotest - STG2
YARNIMA.10.15.9.3 ELECTRICAL
Activity ID
Activity Name
Original
Duration
Start
Finish
Budgeted
Labor Units
Total
Float
Activity % S
Complete
A13510
13
10-09-2013 A
28-02-2014
2201
49
80%
A13410
14-09-2013 A
09-02-2014
193
57
95%
A13480
Pull LV-C&I Cabling - STG2 (To CWP - CT Fans - Water Treatment - HRSG Pmps) 38
22-09-2013 A
28-05-2014
3727
35%
A13360
25-09-2013 A
09-02-2014
105
100
95%
A13370
25-09-2013 A
10-02-2014
159
100
95%
A13380
14
25-09-2013 A
21-04-2014
657
50%
NCR-S286
STG1 & STG2: TG1 and STG2 Walkway HV/LV switchrooms Missing Anchor Bolts on12
the Plinth14-10-2013 A
26-10-2013 A
A13500
14
18-10-2013 A
12-06-2014
882
13%
A13520
21
13-11-2013 A
23-03-2014
25
49
52%
A23040
Pull Power Cables from STG to Cooling Tower 2 (Resource in STG Works)
11
20-12-2013 A
19-02-2014
103
0%
A13390
22-04-2014
28-04-2014
40
20
0%
A13440
25
22-04-2014
18-05-2014
1046
21
0%
A13400
29-04-2014
07-05-2014
654
20
0%
A13470
15
08-05-2014
23-05-2014
20
0%
65
2
22-09-2013 A
22-09-2013 A
27-06-2014
01-10-2013 A
2010
80
100%
STG1 & STG2: TG1 and STG2 Walkway HV/LV switchrooms Missing A
100%
A22090
34
09-05-2014
13-06-2014
640
0%
Mechanical Pre-Commissioning - S
A22110
28
15-05-2014
13-06-2014
616
0%
A22100
14
30-05-2014
13-06-2014
80
0%
A22640
13-06-2014
0%
A22080
10
15-06-2014
24-06-2014
150
0%
A22910
13
15-06-2014
27-06-2014
0%
A22070-a
17-06-2014
23-06-2014
444
0%
190
15
15
09-11-2013 A
13-01-2014 A
13-01-2014 A
24-04-2014
13-02-2014
13-02-2014
4650
672
672
60
125
125
50%
125
14
12-11-2013 A
12-11-2013 A
25-03-2014
25-03-2014
2559
2367
88
40
43%
09-02-2014*
13-02-2014
192
125
0%
13
13
26-03-2014
26-03-2014
08-04-2014
08-04-2014
192
0
75
60
0%
10
26-03-2014
04-04-2014
192
78
0%
15
15
09-04-2014
09-04-2014
24-04-2014
24-04-2014
687
624
60
60
0%
15
09-04-2014
24-04-2014
63
60
0%
13
13
09-11-2013 A
09-11-2013 A
18-02-2014
18-11-2013 A
540
0
120
13
09-11-2013 A
18-11-2013 A
A10190
10
09-12-2013 A
18-02-2014
540
120
29-06-2014
29-06-2014
29-06-2014
YARNIMA.6 DEMOBILISATION
A3190
Actual Work
Primary Baseline
Remaining Work
Baseline Milestone
Milestone
Summary
Page 38 of 38
Data Date 07-02-2014
Date
19-Dec-12
21-11-2013
07-02-2014
100%
100%
70%
0%
Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule
Checked
Approved
WC
KU
KU
TL