Sei sulla pagina 1di 38

YARNIMA POWER STATION

5242-C-53000
CONSTRUCTION SCHEDULE
Activity ID

Activity Name

YARNIMA YARNIMA PS ACTUALISED Draft CP Rev 02


YARNIMA.1 PROJECT MILESTONES

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

495

15-10-2012 A

29-06-2014

371579

YARNIMA YARNIMA PS ACTUA

494

15-10-2012 A

27-06-2014

YARNIMA.1 PROJECT MILEST

15-10-2012 A

A1000

Approval of Preliminary Work

100%

A1020

Full Award of Contract

03-01-2013 A

100%

A3390

Stage 1 Complete (GT3 Pre-Commissioned)

27-09-2013 A

100%

A1010

BSDG Installed

24-03-2014

95

0%

A1030

Project Complete

27-06-2014*

0%

16-01-2013 A

55

YARNIMA.1.1 PAYMENT MILESTONES 1

21-12-2012 A

Schedule 4 Deliverables Approved Prior to Mobilisation to Site

21-12-2012 A

100%

A4270

Completion of Mobilisation

16-01-2013 A

100%

27-09-2013 A

27-09-2013 A

11-03-2014

108

A4290

GTG3 Pre-Commissioning Complete

27-09-2013 A

0
19

YARNIMA.1.3 PAYMENT MILESTONES 3

20-02-2014

Approval of Preliminary Work


Full Award of Contract
Stage 1 Complete (GT3 Pre-Commissioned)
BSDG Installed
Project Complete
YARNIMA.1.1 PAYMENT MILESTONES 1

A4260

YARNIMA.1.2 PAYMENT MILESTONES 2

Schedule 4 Deliverables Approved Prior to Mobilisation to Site


Completion of Mobilisation
YARNIMA.1.2 PAYMENT MILESTONES 2

100%

GTG3 Pre-Commissioning Complete


YARNIMA.1.3 PAYMENT MILESTONES 3

A4300

Finish Installation of Gas Turbine Generator (GTG) - 2

20-02-2014

127

0%

A4310

Finish Installation of Gas Turbine Generator (GTG) - 1

11-03-2014

108

0%

12-06-2014

15

Finish Installation of Gas Turbine Generator (GTG


YARNIMA.1.4 PAYMENT MILEST

Finish Installation of Heat Recovery Steam Ge

71

YARNIMA.1.4 PAYMENT MILESTONES 4

02-04-2014

Finish Installation of Gas Turbine Generator (GTG) -

A4320

Finish Installation of Heat Recovery Steam Generator (HRSG) - 3

02-04-2014

86

0%

A4360

Finish Installation of Cooling Tower 2

11-04-2014

77

0%

Finish Installation of Cooling Tower 2

A4340

Finish Installation of Heat Recovery Steam Generator (HRSG) - 2

15-04-2014

73

0%

Finish Installation of Heat Recovery Steam G

A4350

Finish Installation of Steam Turbine Generator (STG) - 1

05-05-2014

53

0%

Finish Installation of Steam Turbine Gene

A22860

Finish Installation of Cooling Tower 1

11-05-2014

47

0%

Finish Installation of Cooling Tower 1

A4330

Finish Installation of Heat Recovery Steam Generator (HRSG) - 1

16-05-2014

42

0%

Finish Installation of Heat Recovery Ste

A4370

Finish Installation of Steam Turbine Generator (STG) - 2

12-06-2014

15

0%

YARNIMA.5 PRELIMINARIES

21

15-10-2012 A

21-12-2012 A

Finish Installation of Steam Turbine


YARNIMA.5 PRELIMINARIES

A4400

Lodgement of Securities

14

15-10-2012 A

21-12-2012 A

100%

A4410

Cert of Currency for Insurances

14

15-10-2012 A

07-11-2012 A

100%

A4420

Construction Management Plan

21

15-10-2012 A

16-11-2012 A

100%

Construction Management Plan

A4440

Construction Schedule

21

15-10-2012 A

15-11-2012 A

100%

Construction Schedule

A4450

HSEP

21

15-10-2012 A

12-11-2012 A

100%

HSEP

A4460

HSMP

21

15-10-2012 A

12-11-2012 A

100%

A4470

Quality Management Plan

21

15-10-2012 A

07-11-2012 A

100%

A4480

MDR Index & Contents Prep

21

15-10-2012 A

12-11-2012 A

100%

MDR Index & Contents Prep

A4490

Engineering Management Plan

21

15-10-2012 A

07-11-2012 A

100%

Engineering Management Plan

A4510

TNA

21

15-10-2012 A

12-11-2012 A

100%

TNA

A4590

Environmental Management Plan

21

15-10-2012 A

12-11-2012 A

100%

Environmental Management Plan

A4600

HR/IR/ER Management Plan

21

15-10-2012 A

12-11-2012 A

100%

A4620

CRAW

21

15-10-2012 A

06-11-2012 A

100%

A4610

Contractor Contracts & Procurement Plan

14

02-11-2012 A

16-11-2012 A

100%

23

02-01-2013 A

28-01-2013 A

YARNIMA.12 MOBILISATION & SITE SETUP

Lodgement of Securities
Cert of Currency for Insurances

HSMP
Quality Management Plan

HR/IR/ER Management Plan


CRAW
Contractor Contracts & Procurement Plan
YARNIMA.12 MOBILISATION & SITE SETUP

A1500

Site Access

02-01-2013 A

100%

A1510

Mobilise Construction Personnel & Equipment

18

02-01-2013 A

18-01-2013 A

100%

A1510-1

Mobilization Personal

02-01-2013 A

28-01-2013 A

100%

A1510-2

Unloading of 400T Crawler Crane

06-01-2013 A

09-01-2013 A

100%

Unloading of 400T Crawler Crane

A1510-3

Unloading and Set-Up of Site Facilities

10-01-2013 A

13-01-2013 A

100%

Unloading and Set-Up of Site Facilities

A1510-6

VOC Training

10-01-2013 A

20-01-2013 A

100%

A1530-1

Main Office

11-01-2013 A

12-01-2013 A

100%

Main Office

A1510-5

Unloading Plant and Equipment

12-01-2013 A

15-01-2013 A

100%

Unloading Plant and Equipment

A1510-4

Assembly of 400T Crawler Crane

13-01-2013 A

16-01-2013 A

100%

Assembly of 400T Crawler Crane

A1530-2

2 * Cribs Huts

13-01-2013 A

14-01-2013 A

100%

2 * Cribs Huts

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 1 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Site Access
Mobilise Construction Personnel & Equipment
Mobilization Personal

VOC Training

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A1520

Commence Major Works

14-01-2013 A

100%

Commence Major Works

A1530-3

Toilet Block

14-01-2013 A

15-01-2013 A

100%

Toilet Block

A1530

Establish Site Facilities (priliminaries)

16-01-2013 A

17-01-2013 A

100%

Establish Site Facilities (priliminaries)

A1530-4

Temporary Crib Huts

17-01-2013 A

18-01-2013 A

100%

Temporary Crib Huts

A2140

Survey (to Commence Works)

18-01-2013 A

19-01-2013 A

100%

Survey (to Commence Works)

256

14-03-2013 A

01-12-2013 A

YARNIMA.2 Delay Events

139

30-07-2013 A

01-12-2013 A

YARNIMA.2.3 Cooling Tower

YARNIMA.2 Delay Events


YARNIMA.2.3 Cooling Tower

NCR-S166

BOP: STG Trench Set Out

30-07-2013 A

31-07-2013 A

100%

NCR-S170

BOP: KBE DN1000 SDR13.6 12m Pipe Length Does Not Meet AS4130 (internal)

13

01-08-2013 A

14-08-2013 A

100%

HP1050

Delayed access for Hamon _ Foundation and Plynths North of Cooling Towers

09-09-2013 A

100%

NCR-S347

Cable Ladder Tie in - Piperack to BSDG Switchroom

15-11-2013 A

21-11-2013 A

100%

Cable Ladder Tie in - Piperack to BSDG Switchroom

NCR-S362

Cooling Tower Fan Gearbox Non-Conformance

27-11-2013 A

01-12-2013 A

100%

29-11-2013 A

29-11-2013 A

Cooling Tower Fan Gearbox Non-Conformance


YARNIMA.2.4 Civil Works by Others

YARNIMA.2.4 Civil Works by Others


HP1040

Access to complete Cable Tray Support Structures at all HRSG's North

YARNIMA.2.1 Cooling Water Piping


DE1000

Delayed Access to Allow Excavation

YARNIMA.4 Variation Works


YARNIMA.4.3 GPRS Installation

29-11-2013 A

14-03-2013 A

26-04-2013 A

14-03-2013 A

26-04-2013 A

09-03-2013 A

25-11-2013 A

10157

192

12-04-2013 A

25-11-2013 A

6779

BOP: KBE DN1000 SDR13.6 12m Pipe Length Does Not Meet AS4130 (internal)

Delayed access for Hamon _ Foundation and Plynths Nor

100%

Access to complete Cable Tray Support Structures at all H


YARNIMA.2.1 Cooling Water Piping

311

BOP: STG Trench Set Out

100%

Delayed Access to Allow Excavation


YARNIMA.4 Variation Works
YARNIMA.4.3 GPRS Installation

A19690

Electrical Pre-commissioning

02-07-2013 A

19-07-2013 A

130

100%

Electrical Pre-commissioning

A19790

Mechanical Pre-Commissioning

16-07-2013 A

19-07-2013 A

260

100%

Mechanical Pre-Commissioning

VEGPRS100

VE GPRS - Commission Assistance, Install 00DB060 and 00BJA60, Install FOC and Pipe
31 Support
19-07-2013 A

16-08-2013 A

901

100%

VE GPRS - Commission Assistance, Install 00DB060 and 00BJA60, Install FOC a

VEGPRS110

VE GPRS -RMWS 80 Install PTFE Insulation Strips on the sections of piping requiring 2U bolts 28-08-2013 A

29-08-2013 A

50

100%

VE GPRS -RMWS 80 Install PTFE Insulation Strips on the sections of piping re

VEGPRS120

VE GPRS - Install temporary earth for spark gap arrestor. MWR 131 and commissioning
13 support
10-09-2013 A

24-09-2013 A

69

100%

VE GPRS - Install temporary earth for spark gap arrestor. MWR 131 and c

VEGPRS130

VE GPRS - Punchlisting items Worley Parson Directed, and commissioning support 12

30-09-2013 A

13-10-2013 A

104

100%

VE GPRS - Punchlisting items Worley Parson Directed, and commission

VEGPRS140

VE GPRS - GPRS mods, Cathodic Protection Installation, provide scaffolding access, Mods
13 to PLatforms)
25-10-2013 A

07-11-2013 A

246

100%

VE GPRS - GPRS mods, Cathodic Protection Installation, provide sc

VEGPRS150

VE GPRS - Punchlist - Cable Ladder Cover and Sealing conduits, and Cathodic Protection
3
Installation
23-11-2013 A

25-11-2013 A

48

100%

VE GPRS - Punchlist - Cable Ladder Cover and Sealing conduits,


YARNIMA.4.3.1 Electrical Works

YARNIMA.4.3.1 Electrical Works


A19620
Site Earthing Installation

116
15

03-05-2013 A
03-05-2013 A

02-09-2013 A
07-07-2013 A

1517
670

100%

Site Earthing Installation

184

100%

EI&C LV Cable Installation

A19670

EI&C LV Cable Installation

14-05-2013 A

25-06-2013 A

A19630

Cable Ladder Installation

22-05-2013 A

22-05-2013 A

61

100%

A19650

Lighting & Small Power Installation

24-05-2013 A

16-07-2013 A

141

100%

NCR-S104

Conduit and cable ladder installation in GPRS area

13

04-06-2013 A

17-06-2013 A

100%

NCR-S105

Posy junction box is not suitable for the size of cable in GPRS area

25

04-06-2013 A

30-06-2013 A

100%

NCR-S106

GPRS: The light fitting does not suit the pole light

13

04-06-2013 A

17-06-2013 A

100%

A19680

EI&C LV Cable Termination

19-06-2013 A

19-07-2013 A

275

100%

EI&C LV Cable Termination

A19660

Electrical Equipment / Instrumentation Installation

08-07-2013 A

18-07-2013 A

186

100%

Electrical Equipment / Instrumentation Installation

NCR-S150

Light Pole Washers In GPRS Area Do Not Comply With AS4100

08-07-2013 A

11-07-2013 A

100%

NCR-S199

GPRS: Location of Surge Divertor

25-08-2013 A

02-09-2013 A

100%

YARNIMA.4.3.2 Mechanical and Piping


NCR-S066
GPRS: Water Baths Heater Skid Mounting holes Incorrect

102
43

12-04-2013 A
12-04-2013 A

04-08-2013 A
27-05-2013 A

2897
0

100%

Cable Ladder Installation


Lighting & Small Power Installation
Conduit and cable ladder installation in GPRS area
Posy junction box is not suitable for the size of cable in GPRS area
GPRS: The light fitting does not suit the pole light

Light Pole Washers In GPRS Area Do Not Comply With AS4100


GPRS: Location of Surge Divertor
YARNIMA.4.3.2 Mechanical and Piping
GPRS: Water Baths Heater Skid Mounting holes Incorrect

A19730

Fit Up Pipework

07-06-2013 A

26-06-2013 A

1417

100%

NCR-S108

GPRS Area Handrails & Gridmesh Non Compliant

08-06-2013 A

14-06-2013 A

100%

A19700

Install PVC Skid Stairs

09-06-2013 A

10-06-2013 A

560

100%

Install PVC Skid Stairs

A19710

Install Crossover 1

09-06-2013 A

09-06-2013 A

28

100%

Install Crossover 1

A19740

Weld Pipework

09-06-2013 A

09-06-2013 A

132

100%

Weld Pipework

NCR-S112

GPRS - Company Supplied Piping Cleanliness

21

09-06-2013 A

01-07-2013 A

100%

GPRS - Company Supplied Piping Cleanliness

A19720

Install Crossover 2

10-06-2013 A

28-06-2013 A

112

100%

Install Crossover 2

NCR-S121

GPRS Area Missing Equipment

18

16-06-2013 A

04-07-2013 A

100%

GPRS Area Missing Equipment

NCR-S122

GPRS Area - Pipe Support Required

16-06-2013 A

20-06-2013 A

100%

GPRS Area - Pipe Support Required

A19750

NDT

26-06-2013 A

10-07-2013 A

100%

NDT

A20860

Install Control Hut

07-07-2013 A

15-07-2013 A

518

100%

Install Control Hut

A19640

Painting

08-07-2013 A

15-07-2013 A

130

100%

Painting

A19770

Pneumatic Testing

10-07-2013 A

17-07-2013 A

100%

Pneumatic Testing

NCR-S160

GPRS Water Bath Heater Switchboard Roof

11

24-07-2013 A

04-08-2013 A

100%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 2 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Fit Up Pipework
GPRS Area Handrails & Gridmesh Non Compliant

GPRS Water Bath Heater Switchboard Roof


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name
YARNIMA.4.3.3 Civil Works
A19760
Grouting

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

64
3

12-06-2013 A
12-06-2013 A

15-07-2013 A
10-07-2013 A

557
210

100%

Civil Works

18-06-2013 A

15-07-2013 A

347

100%

NCR-S133

Verticality of Control Hut @ GPRS

13

21-06-2013 A

04-07-2013 A

100%

220

09-03-2013 A

30-07-2013 A

3378

09-03-2013 A

13-05-2013 A

818

100%

VO's #10, #11

09-04-2013 A

30-07-2013 A

2560

100%

360

15-10-2012 A

03-12-2013 A

37907

30

15-10-2012 A

01-02-2013 A

30
0
0

15-10-2012 A
24-11-2012 A
24-11-2012 A

01-02-2013 A
24-11-2012 A

0
0
0

100%

24-11-2012 A

100%

0
0

17-10-2012 A
17-10-2012 A

0
0

HRSG 3 GA & Detailed Assembly Dwgs


YARNIMA.11.5.1.2 CIVIL

100%

Stage 1 Buried ServicesTrench Layout Dwgs AFC

17-10-2012 A

100%

YARNIMA.11.5.1.3 STRUCTURAL
A5380
Stage 1 Piperack Dwgs AFC

0
0

15-10-2012 A
15-10-2012 A

15-10-2012 A

0
0

Stage 1 Buried Pit Dwgs AFC


YARNIMA.11.5.1.3 STRUCTURAL

100%

YARNIMA.11.5.1.4 MECHANICAL
A5450
Stage 1 Valve List Issued

42
0

01-11-2012 A
01-11-2012 A

01-02-2013 A

0
0

Stage 1 Piperack Dwgs AFC


YARNIMA.11.5.1.4 MECHANICAL

100%

A5970

HRSG 3 GA & Detailed Assembly Dwgs

YARNIMA.11.5.1.2 CIVIL
A5360
Stage 1 Buried ServicesTrench Layout Dwgs AFC
A5840

Stage 1 Buried Pit Dwgs AFC

17-10-2012 A

Stage 1 Valve List Issued

A5430

Stage 1 GAs & Mechanical Sections Issued

01-02-2013 A

100%

A5870

Stage 1 Ancillary Services Piping Isometrics Issued

01-02-2013 A

100%

2
0

30-10-2012 A
30-10-2012 A

0
0

Stage 1 Ancillary Services Piping Isometrics Issued


YARNIMA.11.5.1.5 ELECTRICAL

Stage 1 Gas Pipe Isometrics Issued


Stage 1 GAs & Mechanical Sections Issued

100%

Stage 1 Common Cable Sched & Electrical MTO Issued

A5470

GT3 Electrical Dwgs AFC

04-11-2012 A

100%

GT3 Electrical Dwgs AFC

A13620

HRSG3 Electrical Dwgs AFC

04-11-2012 A

100%

YARNIMA.11.5.1.6 INSTRUMENTATION
A5540
GT3 Instrument Data Sheets & Cable Sched AFC

22
0

19-11-2012 A
19-11-2012 A

0
0

HRSG3 Electrical Dwgs AFC


YARNIMA.11.5.1.6 INSTRUMENTATION

100%

GT3 Instrument Data Sheets & Cable Sched AFC

19-11-2012 A

100%

35
0
0

30-11-2012 A
30-11-2012 A
30-11-2012 A

0
0
0

GT3 Instrument Location & Termination Information Issued


YARNIMA.11.5.2 CONSTRUCTION DELIVERABLES
YARNIMA.11.5.2.1 CIVIL WORKS

25-01-2013 A
30-11-2012 A

100%

GT3 Fnd Ready for Equip

A5700

HRSG3 Fnd Ready for Equip

30-11-2012 A

100%

HRSG3 Fnd Ready for Equip

A5710

Stage 1 Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip 0

30-11-2012 A

100%

0
0

25-01-2013 A
25-01-2013 A

25-01-2013 A

0
0

Stage 1 Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip
YARNIMA.11.5.2.2 ELECTRICAL WORKS

100%

77

05-11-2012 A

11-03-2013 A

77
0

05-11-2012 A
05-11-2012 A

11-03-2013 A

0
0

100%

YARNIMA.11.5.2.2 ELECTRICAL WORKS


A1110
Stage 1 MV Cables Supplied

YARNIMA.11.7 COMPANY SUPPLIED ITEMS


YARNIMA.11.7.2 GAS TURBINE 3 & ASSOCIATED EQUIPMENT
A1120
GT3 & Assoc Equipment
GT3 Auxillary 1.5 MVA Transformer

13-02-2013 A

100%

A1140

GT3 Switchroom

11-03-2013 A

100%

A1150

GT3 Battery Room

11-03-2013 A

100%

21
0

14-02-2013 A
14-02-2013 A

0
0

100%

01-03-2013 A

100%

127

15-10-2012 A

23-04-2013 A

127
64
21

15-10-2012 A
17-10-2012 A
17-10-2012 A

27-03-2013 A
08-03-2013 A
15-11-2012 A

0
0
0

100%

A1760

HRSG3 Instruments- Sampling- CEMS & Heat Exchangers

YARNIMA.11.6 PROCUREMENT
YARNIMA.11.6.2 MECHANICAL
YARNIMA.11.6.2.5 PIPE SUPPORTS
A10260
Finalise tender package for Stage 1 Pipe Supports

01-03-2013 A

Stage 1 MV Cables Supplied


YARNIMA.11.7 COMPANY SUPPLIED ITEMS
YARNIMA.11.7.2 GAS TURBINE 3 & ASSOCIATED EQUIPMENT

A1130

YARNIMA.11.7.3 HRSG 3 BYPASS STACK


A1300
HRSG3 Bypass Stack

GT3 & Assoc Equipment


GT3 Auxillary 1.5 MVA Transformer
GT3 Switchroom
GT3 Battery Room
YARNIMA.11.7.3 HRSG 3 BYPASS STACK
HRSG3 Bypass Stack
HRSG3 Instruments- Sampling- CEMS & Heat Exchangers
YARNIMA.11.6 PROCUREMENT
YARNIMA.11.6.2 MECHANICAL
YARNIMA.11.6.2.5 PIPE SUPPORTS
Finalise tender package for Stage 1 Pipe Supports

A10280

Shop Detailing Stage 1 Pipe Supports

14

15-12-2012 A

05-03-2013 A

100%

Shop Detailing Stage 1 Pipe Supports

A10270

Fabricate Stage 1 Pipe Supports

17

02-01-2013 A

01-03-2013 A

100%

Fabricate Stage 1 Pipe Supports

A10290

Surface Treatment Stage 1 Pipe Supports

17

16-01-2013 A

07-03-2013 A

100%

Surface Treatment Stage 1 Pipe Supports

A10300

Delivery Stage 1 Pipe Supports

04-03-2013 A

08-03-2013 A

100%

92
21

15-10-2012 A
15-10-2012 A

12-03-2013 A
12-11-2012 A

0
0

Delivery Stage 1 Pipe Supports


YARNIMA.11.6.2.1 PIPERACK

100%

YARNIMA.11.6.2.1 PIPERACK
A1340
Finalise tender package for Stage 1 Piperack
Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 3 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

GT 3 GA & Detailed Assembly Dwgs

100%

YARNIMA.11.5.2 CONSTRUCTION DELIVERABLES


YARNIMA.11.5.2.1 CIVIL WORKS
A5690
GT3 Fnd Ready for Equip

YARNIMA.11.5.1 ENGINEERING DELIVERABLES


YARNIMA.11.5.1.1 GA & DETAILED ASSEMBLY DWGS

GT3 Instrument Location & Termination Information Issued

YARNIMA.11.5 COMPANY DELIVERABLES

21-12-2012 A

A5550

YARNIMA.11 PHASE 1

19-11-2012 A

VO's #10, #11

Stage 1 Gas Pipe Isometrics Issued

04-11-2012 A

VO's #2, #5

A5400

YARNIMA.11.5.1.5 ELECTRICAL
A5520
Stage 1 Common Cable Sched & Electrical MTO Issued

Verticality of Control Hut @ GPRS


YARNIMA.4.4 Approved Events

VO's #2, #5

YARNIMA.11.5.1 ENGINEERING DELIVERABLES


YARNIMA.11.5.1.1 GA & DETAILED ASSEMBLY DWGS
A5960
GT 3 GA & Detailed Assembly Dwgs

Civil Works

A23000

YARNIMA.11.5 COMPANY DELIVERABLES

Grouting

A23010

YARNIMA.11 PHASE 1

YARNIMA.4.3.3 Civil Works

A20850

YARNIMA.4.4 Approved Events

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Finalise tender package for Stage 1 Piperack


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A5610

Shop Detailing Stage 1 Piperack

28

14-12-2012 A

07-02-2013 A

100%

Shop Detailing Stage 1 Piperack

A5580

Fabricate Stage 1 Piperack

19

14-01-2013 A

05-02-2013 A

100%

Fabricate Stage 1 Piperack

A5920

Surface Treatment Stage 1 Piperack

13

05-02-2013 A

12-03-2013 A

100%

Surface Treatment Stage 1 Piperack

A5930

Delivery Stage 1 Piperack

22

10-02-2013 A

10-03-2013 A

100%

58
21

21-10-2012 A
21-10-2012 A

27-03-2013 A
17-12-2012 A

0
0

Delivery Stage 1 Piperack


YARNIMA.11.6.2.3 GAS PIPE & FITTINGS

100%

Finalise Vendor Design Deliverables

18-12-2012 A

100%

Confirm Vendor

YARNIMA.11.6.2.3 GAS PIPE & FITTINGS


A8600
Finalise Vendor Design Deliverables
A8610

Confirm Vendor

A8620

Client Review & Comment

18-12-2012 A

24-12-2012 A

100%

A8630

Include Comments

01-01-2013 A

04-01-2013 A

100%

Include Comments

A8640

Submit For Final Approval

04-01-2013 A

100%

Submit For Final Approval

A8650

Client Final Approval

05-01-2013 A

12-01-2013 A

100%

Client Final Approval

A8660

Issue PO

13-01-2013 A

14-01-2013 A

100%

Issue PO

A8670

Manufacture & Deliver Gas Piping & Fittings

16

14-01-2013 A

27-03-2013 A

100%

127
7

01-11-2012 A
01-11-2012 A

02-03-2013 A
21-12-2012 A

0
0

100%

Finalise Vendor Design Deliverables

21-12-2012 A

100%

Confirm Vendor

YARNIMA.11.6.2.4 GAS VALVES


A8680
Finalise Vendor Design Deliverables

A8700

Client Review & Comment

21-12-2012 A

21-12-2012 A

100%

Client Review & Comment

A8710

Include Comments

21-12-2012 A

21-12-2012 A

100%

Include Comments

A8720

Submit For Final Approval

21-12-2012 A

100%

Submit For Final Approval

A8730

Client Final Approval

21-12-2012 A

20-01-2013 A

100%

A8740

Issue PO

01-02-2013 A

02-02-2013 A

100%

A8750

Manufacture & Deliver Gas Valves

103

02-02-2013 A

02-03-2013 A

100%

56
56

15-12-2012 A
15-12-2012 A

21-03-2013 A
21-03-2013 A

0
0

Manufacture & Deliver Gas Valves


YARNIMA.11.6.2.8 HDPE PIPING

100%

107
16
16

11-11-2012 A
11-11-2012 A
11-11-2012 A

23-04-2013 A
02-03-2013 A
02-03-2013 A

0
0
0

Stage 1 HDPE Piping (Review- Procure & Deliver)


YARNIMA.11.6.3 ELECTRICAL
YARNIMA.11.6.3.1 STAGE 1 ELECTRICAL EQUIPMENT

100%

125
28

26-11-2012 A
26-11-2012 A

08-03-2013 A
06-03-2013 A

0
0

GT3 Electrical Equip (Review- Procure & Deliver)


YARNIMA.11.6.3.2 STAGE 1 CABLE

100%

Stage 1 Cable & Elec Equip (Review- Procure & Deliver)

90

30-12-2012 A

08-03-2013 A

100%

99
7

19-11-2012 A
19-11-2012 A

23-04-2013 A
21-12-2012 A

0
0

Stage 1 VSD & Other Specialist Cable (Review- Procure & Deliver)
YARNIMA.11.6.3.4 STAGE 1 INSTRUMENTATION

100%

Finalise Vendor Design Deliverables

21-12-2012 A

100%

Confirm Vendor

YARNIMA.11.6.3.2 STAGE 1 CABLE


A5630
Stage 1 Cable & Elec Equip (Review- Procure & Deliver)
A7950

Stage 1 VSD & Other Specialist Cable (Review- Procure & Deliver)

YARNIMA.11.6.3.4 STAGE 1 INSTRUMENTATION


A8760
Finalise Vendor Design Deliverables

Client Final Approval


Issue PO

A8770

Confirm Vendor

A8780

Client Review & Comment

21-12-2012 A

21-12-2012 A

100%

Client Review & Comment

A8790

Include Comments

21-12-2012 A

21-12-2012 A

100%

Include Comments

A8800

Submit For Final Approval

21-12-2012 A

100%

Submit For Final Approval

A8810

Client Final Approval

21-12-2012 A

21-12-2012 A

100%

Client Final Approval

A8820

Issue PO

22-12-2012 A

08-01-2013 A

100%

A8830

Manufacture & Deliver Stage 1 Instr & Controls

80

26-01-2013 A

23-04-2013 A

100%

342

02-01-2013 A

03-12-2013 A

37907

52
52
0

02-01-2013 A
02-01-2013 A
02-01-2013 A

11-03-2013 A
31-01-2013 A

0
0
0

YARNIMA.11.8 PHASE 1 CONSTRUCTION


YARNIMA.11.8.5 PRELIMINARIES
YARNIMA.11.8.5.1 SERVICES
A1950
Receipt Verification of Stage 1 Culverts & Fnds (Switchroom & Battery Room)

Issue PO
Manufacture & Deliver Stage 1 Instr & Controls
YARNIMA.11.8 PHASE 1 CONSTRUCTION
YARNIMA.11.8.5 PRELIMINARIES
YARNIMA.11.8.5.1 SERVICES

100%

Receipt Verification of Stage 1 Culverts & Fnds (Switchroom & Battery Room)

A7810

Receipt Verification of Stage 1 Culverts

02-01-2013 A

100%

Receipt Verification of Stage 1 Culverts

A9020

Receipt Verification of Stage 1 Piperack Fnds

03-01-2013 A

100%

Receipt Verification of Stage 1 Piperack Fnds

A9110

Receipt Verification of Stage 1 MV Cables

31-01-2013 A

100%

52
0

02-01-2013 A
02-01-2013 A

0
0

YARNIMA.11.8.5.2 GT3
A1540
Receipt Verification of GT3 Fnd

11-03-2013 A

Receipt Verification of Stage 1 MV Cables


YARNIMA.11.8.5.2 GT3

100%

Receipt Verification of GT3 Fnd

A1550

Receipt Verification of GT3 Free Issue Material & Equip

06-01-2013 A

100%

Receipt Verification of GT3 Free Issue Material & Equip

A1870

Receipt Verification of GT3 Auxillary 1.5 MVA Transformer

14-02-2013 A

100%

A1880

Receipt Verification of GT3 Switchroom

11-03-2013 A

100%

Receipt Verification of GT3 Switchroom

A1890

Receipt Verification of GT3 Battery Room

11-03-2013 A

100%

52
0

03-01-2013 A
03-01-2013 A

0
0

Receipt Verification of GT3 Battery Room


YARNIMA.11.8.5.3 HRSG 3

100%

19-01-2013 A

100%

YARNIMA.11.8.5.3 HRSG 3
A7800
Receipt Verification of HRSG3 Fnd
A9360

Receipt Verification of HRSG 3 Free Issue Bypass Stack & Assoc Equip

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 4 of 38
Data Date 07-02-2014

02-03-2013 A

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Manufacture & Deliver Gas Piping & Fittings


YARNIMA.11.6.2.4 GAS VALVES

Confirm Vendor

YARNIMA.11.6.3 ELECTRICAL
YARNIMA.11.6.3.1 STAGE 1 ELECTRICAL EQUIPMENT
A5620
GT3 Electrical Equip (Review- Procure & Deliver)

Client Review & Comment

A8690

YARNIMA.11.6.2.8 HDPE PIPING


A8590
Stage 1 HDPE Piping (Review- Procure & Deliver)

Receipt Verification of GT3 Auxillary 1.5 MVA Transformer

Receipt Verification of HRSG3 Fnd


Receipt Verification of HRSG 3 Free Issue Bypass Stack & Assoc Equip
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name
A9370

Receipt Verification of HRSG 3 Instruments- Sampling- CEMS & Heat Exchangers

YARNIMA.11.8.2 SERVICES
YARNIMA.11.8.2.3 GAS PIPELINE (UNDERGROUND)
YARNIMA.11.8.2.3.1 Excavation and Bedding
A7650
Trenching & Excavation for Underground Gas Pipework & Crossovers

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

02-03-2013 A

100%

230
33
31
12

25-01-2013 A
08-04-2013 A
08-04-2013 A
08-04-2013 A

09-09-2013 A
26-06-2013 A
25-05-2013 A
25-05-2013 A

4500
1393
162
162

100%

100%

A17020

Excavation and Bedding (Section 3 & 4)

08-04-2013 A

10-04-2013 A

A17010

Excavation and Bedding (Section 1 & 2)

08-04-2013 A

24-05-2013 A

100%

YARNIMA.11.8.2.3.2 Installation and Welding


A7660
Weld & Install Underground Gas Pipework

4
4

12-04-2013 A
12-04-2013 A

31-05-2013 A
31-05-2013 A

1050
1050

100%

YARNIMA.11.8.2.3.4 Pipe Testing


A7670
Test Gas Pipeline

16
16

16-04-2013 A
16-04-2013 A

12-06-2013 A
12-06-2013 A

0
0

100%

YARNIMA.11.8.2.3.3 Backfilling
A7680
Backfill & Compaction

7
7

24-04-2013 A
24-04-2013 A

26-06-2013 A
26-06-2013 A

181
181

100%

156
121
8

08-03-2013 A
08-03-2013 A
08-03-2013 A

12-08-2013 A
05-07-2013 A
27-05-2013 A

1675
399
399

100%

NCR-S071

GTG3: C1034-NCR-S071-Line 3- Pipe Support is clashing with Exhaust Diffuser support


13 leg 28-04-2013 A

11-05-2013 A

100%

NCR-S135

BOP: Pipe Supports without Build Concrete Foundation on-site

YARNIMA.11.8.2.1 GAS PIPELINE (ABOVEGROUND & IN CULVERTS)


YARNIMA.11.8.2.1.2 Install Piperack
A7690
Install Piperack

YARNIMA.11.8.2.1.3 Installlation and Welding of Pipes in Piperack


A7700
Weld & Install Gas Pipeline & Valves in Piperack

12

23-06-2013 A

05-07-2013 A

100%

156
25

15-04-2013 A
15-04-2013 A

12-08-2013 A
19-07-2013 A

559
559

Receipt Verification of HRSG 3 Instruments- Sampling- CEMS & Heat Exchangers


YARNIMA.11.8.2 SERVICES
YARNIMA.11.8.2.3 GAS PIPELINE (UNDERGROUND)
YARNIMA.11.8.2.3.1 Excavation and Bedding
Trenching & Excavation for Underground Gas Pipework & Crossovers
Excavation and Bedding (Section 3 & 4)
Excavation and Bedding (Section 1 & 2)
YARNIMA.11.8.2.3.2 Installation and Welding
Weld & Install Underground Gas Pipework
YARNIMA.11.8.2.3.4 Pipe Testing
Test Gas Pipeline
YARNIMA.11.8.2.3.3 Backfilling
Backfill & Compaction
YARNIMA.11.8.2.1 GAS PIPELINE (ABOVEGROUND & IN CULVERTS)
YARNIMA.11.8.2.1.2 Install Piperack
Install Piperack
GTG3: C1034-NCR-S071-Line 3- Pipe Support is clashing with Exhaust Diffuser support leg
BOP: Pipe Supports without Build Concrete Foundation on-site
YARNIMA.11.8.2.1.3 Installlation and Welding of Pipes in Piperack

100%

Weld & Install Gas Pipeline & Valves in Piperack

A17510

1- Weld and Install EKG Gas Piping (North / South)

10

16-04-2013 A

17-07-2013 A

100%

1- Weld and Install EKG Gas Piping (North / South)

A7701

2- Weld and Install EKG Gas Piping (East/West)

10

21-04-2013 A

19-07-2013 A

100%

NCR-S129

GTG3: Pipe supports ST-02-C-258-350,ST-02-A-258-350 are 258mm high.

11

20-06-2013 A

01-07-2013 A

100%

NCR-S134

GTG3: Gasket Kits Not Available for Connecting SS to Carbon Steel

48

22-06-2013 A

12-08-2013 A

100%

NCR-S147

ByPass 3: ByPass Stack Mounted Pipe Supports - Incorrect Northing

06-07-2013 A

08-07-2013 A

100%

99
13

22-04-2013 A
22-04-2013 A

02-08-2013 A
26-07-2013 A

717
717

100%

22-04-2013 A

25-04-2013 A

100%

1- Install Pipe Support in the Culvert


BOP: Culvert too Short and sitting at incorrect RL

YARNIMA.11.8.2.1.5 Installlation and Welding of Pipes in Culvert


A7720
Weld & Install Gas Pipeline & Valves in Culverts (Culverts Installed by Others)

2- Weld and Install EKG Gas Piping (East/West)


GTG3: Pipe supports ST-02-C-258-350,ST-02-A-258-350 are 258mm high.
GTG3: Gasket Kits Not Available for Connecting SS to Carbon Steel
ByPass 3: ByPass Stack Mounted Pipe Supports - Incorrect Northing
YARNIMA.11.8.2.1.5 Installlation and Welding of Pipes in Culvert
Weld & Install Gas Pipeline & Valves in Culverts (Culverts Installed by Others)

A17450

1- Install Pipe Support in the Culvert

NCR-S069

BOP: Culvert too Short and sitting at incorrect RL

22-04-2013 A

25-04-2013 A

100%

A17340

2- Install EKG Gas Pipe in the Culvert

10

28-04-2013 A

24-07-2013 A

100%

A17360

4- Grout Gas Pipe Supports in Culverts

22-05-2013 A

24-05-2013 A

100%

A17430

3- Weld EKG Gas Piping

25-06-2013 A

26-06-2013 A

100%

NCR-S161

BOP: Culvert on S. Side of HRSG #2 Incorrect Northing

25-07-2013 A

02-08-2013 A

100%

5
5

23-07-2013 A
23-07-2013 A

28-07-2013 A
28-07-2013 A

0
0

BOP: Culvert on S. Side of HRSG #2 Incorrect Northing


YARNIMA.11.8.2.1.4 Pipe Testing

100%

146
13

01-04-2013 A
01-04-2013 A

01-09-2013 A
12-07-2013 A

200
60

Test Gas Pipeline


YARNIMA.11.8.2.2 UNDERGROUND PITS

100%

YARNIMA.11.8.2.1.4 Pipe Testing


A7710
Test Gas Pipeline
YARNIMA.11.8.2.2 UNDERGROUND PITS
A7730
Trenching & Excavation for Underground Pits

2- Install EKG Gas Pipe in the Culvert


4- Grout Gas Pipe Supports in Culverts
3- Weld EKG Gas Piping

Trenching & Excavation for Underground Pits

A7740

Install Underground Pits

34

04-04-2013 A

26-07-2013 A

100

100%

Install Underground Pits

A7760

Backfill & Compaction

20

30-04-2013 A

31-07-2013 A

40

100%

Backfill & Compaction

NCR-S197

BOP: Natural Ground Level on-site

10

22-08-2013 A

01-09-2013 A

100%

211
14

25-01-2013 A
25-01-2013 A

09-09-2013 A
05-07-2013 A

902
80

100%

YARNIMA.11.8.2.4 UNDERGROUND ELECTRICAL CONDUITS


A9000
Trenching & Excavation for Conduits

BOP: Natural Ground Level on-site


YARNIMA.11.8.2.4 UNDERGROUND ELECTRICAL CONDUITS
Trenching & Excavation for Conduits

A9010

Install Conduits

13

27-01-2013 A

12-07-2013 A

772

100%

Install Conduits

A9030

Backfill & Compaction

13

27-01-2013 A

11-07-2013 A

50

100%

Backfill & Compaction

NCR-S228

GTG1: Conduits Entry to Cable Pit

YARNIMA.11.8.2.5 DIRECT BURIED 11KV CABLE TRENCHES


A1660
Cable Trench Excavation- GT 3 to GT3 Switchroom

09-09-2013 A

09-09-2013 A

100%

64
2

04-04-2013 A
04-04-2013 A

30-06-2013 A
29-04-2013 A

330
55

100%

A1680

Backfill & Compact GT3 to GT3 Switchroom

03-05-2013 A

10-05-2013 A

55

100%

A1840

Cable Trench Excavation GT3 Switchroom to GT3 Step Up Transformer

14-05-2013 A

19-05-2013 A

110

100%

A1860

Backfill & Compact GT3 Switchroom to GT3 Step Up Transfor mer

06-06-2013 A

30-06-2013 A

110

100%

342
147
13

16-01-2013 A
22-01-2013 A
22-01-2013 A

03-12-2013 A
25-11-2013 A
04-02-2013 A

33407
6038
0

100%

YARNIMA.11.8.1 GAS TURBINE 3 & ASSOCIATED EQUIPMENT


YARNIMA.11.8.1.6 GTG3 - ACTUAL VARIATIONS & NON SCOPE WORKS
NCR-S001
GTG3: GT3 exhaust diffuser parts incorrect

GTG1: Conduits Entry to Cable Pit


YARNIMA.11.8.2.5 DIRECT BURIED 11KV CABLE TRENCHES
Cable Trench Excavation- GT 3 to GT3 Switchroom
Backfill & Compact GT3 to GT3 Switchroom
Cable Trench Excavation GT3 Switchroom to GT3 Step Up Transformer

Backfill & Compact GT3 Switchroom to GT3 Step Up Transfor mer


YARNIMA.11.8.1 GAS TURBINE 3 & ASSOCIATED EQUIPMEN
YARNIMA.11.8.1.6 GTG3 - ACTUAL VARIATIONS & NON SCOP
GTG3: GT3 exhaust diffuser parts incorrect

NCR-S008

GTG3: The angle cross bracing have been damaged

13

22-01-2013 A

04-04-2013 A

100%

NCR-S023

GTG3: Vendor Supplied WEICON Primer S 300 hardened

13

22-01-2013 A

04-02-2013 A

100%

GTG3: Vendor Supplied WEICON Primer S 300 hardened

NCR-S026

GTG3: Cast in plates embedded to the GT3 Generator are in wrong orientation

13

22-01-2013 A

04-02-2013 A

100%

GTG3: Cast in plates embedded to the GT3 Generator are in wrong orientation

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 5 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

GTG3: The angle cross bracing have been damaged

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

13

Total
Float

Activity % S
Complete

NCR-S003

GTG3 Diffuser expansion joint does not fit to the diffuser ring

30-01-2013 A

04-04-2013 A

100%

GTG3 Diffuser expansion joint does not fit to the diffuser ring

NCR-S004

GTG3: Length of Structural bolts on the Lube Oil Cooler supports does not comply with
13Aus. Standards
30-01-2013 A

04-04-2013 A

100%

GTG3: Length of Structural bolts on the Lube Oil Cooler supports does not comply with Aus. Standard

NCR-S005

GTG3: The Stair on the GT-Room supplied does not fit onto the platform

13

02-02-2013 A

04-04-2013 A

100%

GTG3: The Stair on the GT-Room supplied does not fit onto the platform

NCR-S006

GTG3: The supplied platform in between the GT3 and Starter Motor is 50mm too wide13

08-02-2013 A

04-04-2013 A

100%

GTG3: The supplied platform in between the GT3 and Starter Motor is 50mm too wide

NCR-S007

GTG3: Missing 4No x bolt holes on the beam -004

13

08-02-2013 A

04-04-2013 A

100%

GTG3: Missing 4No x bolt holes on the beam -004

NCR-S009

GTG3: 6 holes missing from walkway platform on the top of the Steel Enclosure

13

08-02-2013 A

04-04-2013 A

100%

GTG3: 6 holes missing from walkway platform on the top of the Steel Enclosure

NCR-S010

GTG3: The centreline of the column no. 1011027 is out by 17mm

13

10-02-2013 A

15-04-2013 A

100%

GTG3: The centreline of the column no. 1011027 is out by 17mm

NCR-S012

The mounting foot on electrical motor 3GV1210878154003 on top of GTG3 lube oil cooler
13 is cracked
14-02-2013 A

15-04-2013 A

100%

The mounting foot on electrical motor 3GV1210878154003 on top of GTG3 lube oil cooler is cracked

NCR-S013

GTG3: Hand Rails, Kick Plates, Ladders, Cages, Hoists are not paint Yellow Y14 as per
125SPEC-000-S-00061
18-02-2013 A

02-07-2013 A

100%

NCR-S014

GTG3 Clashing of conduits and platform support legs

13

19-02-2013 A

19-02-2013 A

100%

NCR-S015

GTG3 Clashing of support leg with lube oil bund

13

19-02-2013 A

04-03-2013 A

100%

GTG3 Clashing of support leg with lube oil bund

NCR-S019

GTG3: C02 Fire Extinguisher Skid Grout

14

21-02-2013 A

07-03-2013 A

100%

GTG3: C02 Fire Extinguisher Skid Grout

NCR-S020

GTG3: Item not paint yellow Y14 as per SPEC-000-S-00061- lifting beam

13

22-02-2013 A

07-03-2013 A

100%

GTG3: Item not paint yellow Y14 as per SPEC-000-S-00061- lifting beam

NCR-S021

GTG3: Short Supplied of Bolt Qty's

13

24-02-2013 A

09-03-2013 A

100%

GTG3: Short Supplied of Bolt Qty's

NCR-S022

GTG3: Sixteen Diffuser instrument require modification

25-02-2013 A

02-03-2013 A

100%

NCR-S024

GTG3: GT3 Stainless Steel Pipe Clashing to the Gridmesh

13

02-03-2013 A

15-03-2013 A

100%

GTG3: GT3 Stainless Steel Pipe Clashing to the Gridmesh

NCR-S025

GTG3: Bolt holes on the Stud beam is out by 30mm

13

03-03-2013 A

16-03-2013 A

100%

GTG3: Bolt holes on the Stud beam is out by 30mm

NCR-S027

GTG3: Duel Fuel Platform Incorrect frame

13

03-03-2013 A

16-03-2013 A

100%

GTG3: Duel Fuel Platform Incorrect frame

NCR-S031

GTG3: Bolt holes in GT3 Air Intake non-compliant with AS4100

13

11-03-2013 A

24-03-2013 A

100%

GTG3: Bolt holes in GT3 Air Intake non-compliant with AS4100

NCR-S032

GTG3: GT3 Installation of Wall Cladding: Clashing of the wall Cladding and Slurry Wall13

11-03-2013 A

24-03-2013 A

100%

GTG3: GT3 Installation of Wall Cladding: Clashing of the wall Cladding and Slurry Wall

NCR-S036

GTG3: GT3 Lube Oil Cooler: Current Cabling does not comply with AS/BHPBIO Standards
20

21-03-2013 A

11-04-2013 A

100%

NCR-S038

GTG3: GTG Generator Ventilation Inlet Duct Obstructing Electrical Cabinet

13

22-03-2013 A

04-04-2013 A

100%

NCR-S039

GTG3: GT3 FAIST Air Inlet Roof Penetration

71

22-03-2013 A

06-06-2013 A

100%

NCR-S041

GTG3: The Air Intake platform have been fabricated to superseded drawings

24

25-03-2013 A

18-04-2013 A

100%

GTG3: The Air Intake platform have been fabricated to superseded drawings

NCR-S043

GTG3: The Supplied 2 x Beams for the Air Intake Step Platform 50mm too long.

13

28-03-2013 A

10-04-2013 A

100%

GTG3: The Supplied 2 x Beams for the Air Intake Step Platform 50mm too long.

NCR-S045

GTG3 generator and hold down bolts washers deflected

13

30-03-2013 A

18-04-2013 A

100%

NCR-S046

GTG3: GT3 Lube Oil Cooler Platform not Level

01-04-2013 A

10-04-2013 A

100%

NCR-S047

GTG3: GT3 Grid mesh clashes

36

01-04-2013 A

09-05-2013 A

100%

NCR-S042

GTG3: Lube Oil Piperack clashes on the GT3 Access Ladder

13

05-04-2013 A

18-04-2013 A

100%

GTG3: Lube Oil Piperack clashes on the GT3 Access Ladder

NCR-S050

GTG3: Kick plate welded in wrong direction and bolt holes in wrong orientation

13

05-04-2013 A

18-04-2013 A

100%

GTG3: Kick plate welded in wrong direction and bolt holes in wrong orientation

NCR-S075

GTG3: GT3 Air Intake Dissimilar Metals Contact

13

09-05-2013 A

01-07-2013 A

100%

NCR-S077

GTG3 Air Intake Evaporative Cooler Bottom Pan Clash

10-05-2013 A

14-05-2013 A

100%

NCR-S086

GTG3 Filter House Module Misalignment

21-05-2013 A

27-05-2013 A

100%

NCR-S087

GTG3: The propane cabinet clashing to the cast-in conduits from the foundation

13

22-05-2013 A

04-06-2013 A

100%

GTG3: The propane cabinet clashing to the cast-in conduits from the foundation

NCR-S088

GTG3: Enclosure Ventilation Fan Outlet Clash with Pipe Support

13

22-05-2013 A

04-06-2013 A

100%

GTG3: Enclosure Ventilation Fan Outlet Clash with Pipe Support

NCR-S092

GTG3: GT-3 Generator cooling duct doesn't line up with inlet duct - 55mm too high

17

29-05-2013 A

16-06-2013 A

100%

GTG3: GT-3 Generator cooling duct doesn't line up with inlet duct - 55mm too high

NCR-S090

GTG3: GT3 Air intake support structure bolt holes misalignment

13

02-06-2013 A

15-06-2013 A

100%

GTG3: GT3 Air intake support structure bolt holes misalignment

NCR-S107

GTG3: GT3 Bleed Air Piping - Unable to Install Insulation

04-06-2013 A

10-06-2013 A

100%

GTG3: GT3 Bleed Air Piping - Unable to Install Insulation

NCR-S109

GTG3: Air Intake Water Piping Clash with Steelwork

19

08-06-2013 A

27-06-2013 A

100%

GTG3: Air Intake Water Piping Clash with Steelwork

NCR-S110

GTG3 C02 Piping - Reroute to Avoid Clashing with the Crane

08-06-2013 A

14-06-2013 A

100%

NCR-S111

GTG3: GT3 Ladder Non-conformances

70

09-06-2013 A

22-08-2013 A

100%

NCR-S115

GTG3: Conduits have not been installed as per drawings

22

09-06-2013 A

02-07-2013 A

100%

NCR-S118

GTG3 Air Intake Electrical Panel Bolting

11-06-2013 A

17-06-2013 A

100%

NCR-S119

GTG3 Enclosure - Bent Members

60

13-06-2013 A

16-08-2013 A

100%

NCR-S130

GTG3: GT3- Lube Oil Unit Piping showing signs of rusting internally

21

20-06-2013 A

11-07-2013 A

100%

NCR-S131

GTG3: GT3 Exhaust Diffuser Piping Flange Connections Clashing

21-06-2013 A

27-06-2013 A

100%

NCR-S146

GTG3: GTG Lube Oil Pipework Welding - Lack of Penetration

60

05-07-2013 A

06-09-2013 A

100%

NCR-S152

GTG3: Pipe Supports Baseplate is clashing with Diffuser baseplate

19

11-07-2013 A

31-07-2013 A

100%

GTG3: Pipe Supports Baseplate is clashing with Diffuser baseplate

RMW025

Provide Temporary 11kV supply from Substation

17

14-07-2013 A

01-08-2013 A

76

100%

Provide Temporary 11kV supply from Substation

VEGT3000

VE GTG 3 - Install extra cables for GT's, commissioning assist for switchroom, punchlists
44

17-07-2013 A

30-08-2013 A

1275

100%

NCR-S162

GTG3 Enclosure Internal Panels Too Short

12

26-07-2013 A

07-08-2013 A

100%

GTG3 Enclosure Internal Panels Too Short

NCR-S163

GTG3 Turbine Coupling Bolts Supplied Damaged

28-07-2013 A

04-08-2013 A

100%

GTG3 Turbine Coupling Bolts Supplied Damaged

NCR-S180

GTG Compressor Wash Down System SDB Clash

07-08-2013 A

14-08-2013 A

100%

NCR-S205

STG1 - missing WN Flanges on Valve

28-08-2013 A

01-09-2013 A

100%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 6 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

GTG3: Hand Rails, Kick Plates, Ladders, Cages, Hoists are not paint Yellow Y14 as per
GTG3 Clashing of conduits and platform support legs

GTG3: Sixteen Diffuser instrument require modification

GTG3: GT3 Lube Oil Cooler: Current Cabling does not comply with AS/BHPBIO Standards
GTG3: GTG Generator Ventilation Inlet Duct Obstructing Electrical Cabinet
GTG3: GT3 FAIST Air Inlet Roof Penetration

GTG3 generator and hold down bolts washers deflected


GTG3: GT3 Lube Oil Cooler Platform not Level
GTG3: GT3 Grid mesh clashes

GTG3: GT3 Air Intake Dissimilar Metals Contact


GTG3 Air Intake Evaporative Cooler Bottom Pan Clash
GTG3 Filter House Module Misalignment

GTG3 C02 Piping - Reroute to Avoid Clashing with the Crane


GTG3: GT3 Ladder Non-conformances
GTG3: Conduits have not been installed as per drawings
GTG3 Air Intake Electrical Panel Bolting
GTG3 Enclosure - Bent Members
GTG3: GT3- Lube Oil Unit Piping showing signs of rusting internally
GTG3: GT3 Exhaust Diffuser Piping Flange Connections Clashing
GTG3: GTG Lube Oil Pipework Welding - Lack of Penetration

VE GTG 3 - Install extra cables for GT's, commissioning assist for switchroom, p

GTG Compressor Wash Down System SDB Clash


STG1 - missing WN Flanges on Valve
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

VEGT3010

VE GTG 3 - Punchlisting Mechanical, Earthing, replacing cables, Remedial works HV S/Board


44
30-08-2013 A

15-10-2013 A

3073

100%

NCR-S210

GTG3 Enclosure - Panels Buckle During C02 Dump Test

14

31-08-2013 A

14-09-2013 A

100%

NCR-S212

GTG3 Lube Oil Cooler Internal Cleanliness

28

31-08-2013 A

29-09-2013 A

100%

NCR-S212-936 Clean GTG3 Lube Oil Cooler Internals - A2040

33

31-08-2013 A

04-10-2013 A

309

100%

NCR-S210-954 GTG3 Enclosure Panels - repair

15-09-2013 A

15-09-2013 A

100%

GTG3 Lube Oil Cooler Internal Cleanliness


Clean GTG3 Lube Oil Cooler Internals - A2040
GTG3 Enclosure Panels - repair

VE GTG 3 -Punchlisting Electrical, outage items, commissioning support, Evap drain mods
11

30-10-2013 A

10-11-2013 A

679

100%

VE GTG 3 - Relocate Emergency stop, outage items, commissioning support

19-11-2013 A

25-11-2013 A

626

100%

192
5

16-01-2013 A
16-01-2013 A

18-09-2013 A
19-01-2013 A

10624
100

100%

Prepare Foundations & Fixators

VE GTG 3 -Punchlisting Electrical, outage items, commissioning supp

VE GTG 3 - Relocate Emergency stop, outage items, commission


YARNIMA.11.8.1.1 MECHANICAL GT3

A2060

Placement of Gear Box & Remove Transport Protection

16-01-2013 A

20-01-2013 A

250

100%

Placement of Gear Box & Remove Transport Protection

A2070

Placement of GT

17-01-2013 A

21-01-2013 A

190

100%

Placement of GT

A2150

Placement of Diffuser

18-01-2013 A

24-01-2013 A

190

100%

Placement of Diffuser

A2330

Install Liquid Fuel Unit

22-01-2013 A

31-05-2013 A

300

100%

A2370

Place Starter Motor

22-01-2013 A

12-06-2013 A

150

100%

A2170

Assemble Steel Enclosure

23-01-2013 A

06-03-2013 A

450

100%

A2250

Placement of Generator

23-01-2013 A

26-01-2013 A

190

100%

A2300

Install CO2 Module

24-01-2013 A

31-05-2013 A

250

100%

Install CO2 Module

A2160

Preliminary Alignment of Modules

26-01-2013 A

23-02-2013 A

500

100%

Preliminary Alignment of Modules

A2310

Install Oil Coolers (Including Handrails- Ladders)

12

26-01-2013 A

21-05-2013 A

1120

100%

Install Oil Coolers (Including Handrails- Ladders)

A2270

Install Platforms & Access Stairways

28-01-2013 A

20-05-2013 A

400

100%

Install Platforms & Access Stairways

A2190

Connect Diffuser

05-02-2013 A

03-03-2013 A

380

100%

A2180

Placement of Steel Enclosure

12-02-2013 A

16-03-2013 A

550

100%

A2200

Install Enclusure Pannels and Cladding Around Piping Penetrations

19

24-02-2013 A

10-07-2013 A

2590

100%

A2230

Install Ventilation Ducts- Platform & Access Ladder

20

04-03-2013 A

26-07-2013 A

312

100%

A2240

Assemble Intake Support Structure

13

10-03-2013 A

19-04-2013 A

275

100%

Assemble Intake Support Structure

A2260

Lift Air Intake Structure into Place

11-03-2013 A

26-04-2013 A

300

100%

Lift Air Intake Structure into Place

A2340

Final GTG Alignment

16-03-2013 A

19-07-2013 A

500

100%

Final GTG Alignment

A2380

Install Fire Extinguisher & Equipment

17-03-2013 A

26-07-2013 A

250

100%

A2290

Lift & Install Remaining Air Intake Modules

26-04-2013 A

31-05-2013 A

750

100%

A2220

Install Fuel Gas Skid (Valve Train and Propane)

20-05-2013 A

19-07-2013 A

250

100%

A2350

Install Coupling Units

09-06-2013 A

28-08-2013 A

190

100%

A2390

Install Air Filters & evaporator media

20-07-2013 A

18-09-2013 A

187

100%

107
56
13

13-02-2013 A
14-04-2013 A
14-04-2013 A

06-08-2013 A
11-07-2013 A
11-07-2013 A

3281
990
990

Install Air Filters & evaporator media


YARNIMA.11.8.1.3 PIPING GT3
YARNIMA.11.8.1.3.1 Connect Piping in Enclosure

100%

Connect Piping In Enclosure

Install Liquid Fuel Unit


Place Starter Motor
Assemble Steel Enclosure
Placement of Generator

Connect Diffuser
Placement of Steel Enclosure
Install Enclusure Pannels and Cladding Around Piping Penetrations
Install Ventilation Ducts- Platform & Access Ladder

Install Fire Extinguisher & Equipment


Lift & Install Remaining Air Intake Modules
Install Fuel Gas Skid (Valve Train and Propane)
Install Coupling Units

A18010

1. SDB Wash Water

14-04-2013 A

22-04-2013 A

100%

A18000

2. SDB Drain Water

10

02-05-2013 A

11-07-2013 A

100%

2. SDB Drain Water

A18030

3. QFA Instrument Air

10

20-05-2013 A

11-07-2013 A

100%

64
24

13-02-2013 A
13-02-2013 A

19-07-2013 A
19-07-2013 A

1200
1200

3. QFA Instrument Air


YARNIMA.11.8.1.3.2 Install Inter Skid Piping

YARNIMA.11.8.1.3.2 Install Inter Skid Piping


A2320
Install Inter Skid Piping

1. SDB Wash Water

100%

Install Inter Skid Piping

A17970

1. MBV Lube Oil Piping

13-02-2013 A

14-07-2013 A

100%

1. MBV Lube Oil Piping

A18020

2. MBN Liquid Fuel

10

11-05-2013 A

19-07-2013 A

100%

2. MBN Liquid Fuel

A18040

3. SGJ CO2 Piping

15

20-05-2013 A

19-07-2013 A

100%

17
6

27-06-2013 A
27-06-2013 A

05-07-2013 A
05-07-2013 A

125
125

3. SGJ CO2 Piping


YARNIMA.11.8.1.3.3 Install Fuel Gas Piping/Valve Train

YARNIMA.11.8.1.3.3 Install Fuel Gas Piping/Valve Train


A15620
Install Fuel Gas Skid Piping

100%

Install Fuel Gas Skid Piping

A17990

2. MBP Ignition Gas

27-06-2013 A

05-07-2013 A

100%

2. MBP Ignition Gas

A17980

1. MBP Gas Vent

27-06-2013 A

05-07-2013 A

100%

28
28

02-04-2013 A
02-04-2013 A

30-04-2013 A
30-04-2013 A

32
32

1. MBP Gas Vent


YARNIMA.11.8.1.3.4 Install Bleed Air Pipes

100%

Install Bleed Airpipes

02-04-2013 A

30-04-2013 A

100%

18
11

22-06-2013 A
22-06-2013 A

06-08-2013 A
02-08-2013 A

934
934

MBH Bleed Air Piping


YARNIMA.11.8.1.3.5 Insulation

YARNIMA.11.8.1.3.4 Install Bleed Air Pipes


A14800
Install Bleed Airpipes
A17960

MBH Bleed Air Piping

YARNIMA.11.8.1.3.5 Insulation
A2400
Install Piping Insulation

100%

Install Piping Insulation

A18050

1. Insulate Bleed Air Pipe

22-06-2013 A

06-08-2013 A

100%

1. Insulate Bleed Air Pipe

A18060

2. Insulate Gas Pipe

22-06-2013 A

04-08-2013 A

100%

314

17-02-2013 A

11-10-2013 A

10000

2. Insulate Gas Pipe


YARNIMA.11.8.1.2 ELECTRICAL GT3

YARNIMA.11.8.1.2 ELECTRICAL GT3


Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 7 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

VE GTG 3 - Punchlisting Mechanical, Earthing, replacing cables, Remed

VEGT3030

YARNIMA.11.8.1.3 PIPING GT3


YARNIMA.11.8.1.3.1 Connect Piping in Enclosure
A2210
Connect Piping In Enclosure

GTG3 Enclosure - Panels Buckle During C02 Dump Test

VEGT3020

YARNIMA.11.8.1.1 MECHANICAL GT3


A2050
Prepare Foundations & Fixators

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name
YARNIMA.11.8.1.2.1 Cable Ladder
A1630
Cable Ladder - Culverts Switchroom to GTG No.3
A1620

Cable Ladder - Underneath Switchroom & Battery Room

YARNIMA.11.8.1.2.2 Switch Room and Equipment


A1580
Install GT-3 Auxillary 1.5 MVA Transformer

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

23
12

17-02-2013 A
17-02-2013 A

29-03-2013 A
06-03-2013 A

1295
333

100%

10

24-03-2013 A

29-03-2013 A

962

100%

314
2

18-02-2013 A
18-02-2013 A

11-10-2013 A
19-02-2013 A

719
98

100%

Install GT 3 Switchroom

06-03-2013 A

12-04-2013 A

314

100%

A1600

Install GT 3 Battery Room & Battery System

07-03-2013 A

05-07-2013 A

307

100%

NCR-S072

GTG3: Line 3- Switch Room Walkway foundation support columns

154

29-04-2013 A

11-10-2013 A

100%

NCR-S065

GTG3: GT3 Switchroom Emergency Stop does not exist

30-07-2013 A

03-08-2013 A

100%

254
28

24-03-2013 A
24-03-2013 A

31-08-2013 A
26-07-2013 A

1692
1692

100%

NCR-S064

GTG3: Reconnection of external lighting in GT3

131

12-04-2013 A

30-08-2013 A

100%

NCR-S095

GTG3: Donalson power outlets do not comply with BHP SPEC

11

03-06-2013 A

13-06-2013 A

100%

NCR-S120

GTG3: GT3 Air Filter Unit

19

15-06-2013 A

04-07-2013 A

100%

NCR-S126

GTG3: Minimax Smoke & Flame Detectors

70

18-06-2013 A

31-08-2013 A

100%

NCR-S124

GTG3: The minimax emergency brake glass

13

18-06-2013 A

01-07-2013 A

100%

NCR-S063

GTG3: Replacement of Siemens power outlet in turbine enclosure - not a standard power
5 outlet
30-07-2013 A

YARNIMA.11.8.1.2.4 Cabling
A1640
LV-C & I Cabling

YARNIMA.11.8.1.2.1 Cable Ladder

A1590

YARNIMA.11.8.1.2.3 On Skid Works


A2030
Install GT3 On-Skid Electrical Equip

03-08-2013 A

100%

254
28

16-03-2013 A
16-03-2013 A

31-08-2013 A
20-06-2013 A

4276
2544

100%

Cable Ladder - Culverts Switchroom to GTG No.3


Cable Ladder - Underneath Switchroom & Battery Room
YARNIMA.11.8.1.2.2 Switch Room and Equipment
Install GT-3 Auxillary 1.5 MVA Transformer
Install GT 3 Switchroom
Install GT 3 Battery Room & Battery System
GTG3: Line 3- Switch Room Walkway foundation support columns
GTG3: GT3 Switchroom Emergency Stop does not exist
YARNIMA.11.8.1.2.3 On Skid Works
Install GT3 On-Skid Electrical Equip
GTG3: Reconnection of external lighting in GT3
GTG3: Donalson power outlets do not comply with BHP SPEC
GTG3: GT3 Air Filter Unit
GTG3: Minimax Smoke & Flame Detectors
GTG3: The minimax emergency brake glass

GTG3: Replacement of Siemens power outlet in turbine enclosure - not a standard


YARNIMA.11.8.1.2.4 Cabling
LV-C & I Cabling

A2130

Install VSD Cable

02-04-2013 A

15-04-2013 A

535

100%

A1670

11kV Cabling - GT 3 to Switchroom

14

03-04-2013 A

11-05-2013 A

327

100%

A1930

Install HV/LV Cabling GT 3 Switchroom to Aux Transformer

23-04-2013 A

30-04-2013 A

201

100%

NCR-S070

GTG3: HV cable drum No GT H-3C240-01 has unacceptable resistance level.

120

24-04-2013 A

30-08-2013 A

100%

A1850

11kV Cabling GT3 Switchroom to Step Up Transformer

13

21-05-2013 A

05-07-2013 A

669

100%

NCR-S089

BOP: The conduits coming out of the substation install by others at an incorrect depth 7

23-05-2013 A

29-05-2013 A

100%

NCR-S103

GTG3: Damaged tank heater on fuel system

83

03-06-2013 A

30-08-2013 A

100%

NCR-S096

GTG3: Supplied cables by Donalson not comply with BHP SPEC

03-06-2013 A

08-06-2013 A

100%

NCR-S097

GTG3: Gland plate provided is not suited to the amount of the cable

20

03-06-2013 A

23-06-2013 A

100%

NCR-S098

GTG3: Mounting bracket needed for gas detector

28

03-06-2013 A

02-07-2013 A

100%

NCR-S099

GTG3: Relocate cable to air lock

19

03-06-2013 A

22-06-2013 A

100%

NCR-S100

GTG3: Insufficient terminals in the HV room

13

03-06-2013 A

16-06-2013 A

100%

NCR-S101

GTG3: The temperature sensor has not been provided

64

03-06-2013 A

09-08-2013 A

100%

NCR-S113

GTG3: Cable Replacement

21

09-06-2013 A

01-07-2013 A

100%

NCR-S114

GTG3: Additional Cable Ladder required

13

09-06-2013 A

22-06-2013 A

100%

GTG3: Additional Cable Ladder required

NCR-S117

GTG3: GT3 Fin Fan Area Lighting

13

09-06-2013 A

22-06-2013 A

100%

GTG3: GT3 Fin Fan Area Lighting

NCR-S137

GTG3: Missing Items Donaldson Generator Air Intake

61

27-06-2013 A

31-08-2013 A

100%

GTG3: Missing Items Donaldson Generator Air Intake

NCR-S171

GTG3: GT3 Switchroom Cabling & GT3 Areas 3 Phase Socket

01-08-2013 A

06-08-2013 A

100%

156
57

01-04-2013 A
01-04-2013 A

27-07-2013 A
31-05-2013 A

1589
0

GTG3: GT3 Switchroom Cabling & GT3 Areas 3 Phase Socket


YARNIMA.11.8.1.2.5 Cable Terminations

100%

YARNIMA.11.8.1.2.5 Cable Terminations


NCR-S048
GTG3: No Holes Punched for Termination
A1650

LV- C & I Cable Terminations

35

10-04-2013 A

27-07-2013 A

1129

100%

A1690

11kV Cable Terminations

29

24-04-2013 A

20-07-2013 A

460

100%

NCR-S127

GTG3: GT3 Step Up Transformer Terminals

18-06-2013 A

21-06-2013 A

100%

NCR-S142

GTG3: GT3BFA10 Circuit Breaker modification

13

02-07-2013 A

03-07-2013 A

100%

134
31

06-05-2013 A
06-05-2013 A

16-08-2013 A
30-07-2013 A

0
0

100%

100%

YARNIMA.11.8.1.2.6 Earthing and Lighting Protection


A1700
Earthing & Lightning Protection
NCR-S102

GTG3: Earthing tags and earthing locations miss-alignment

13

03-06-2013 A

16-06-2013 A

NCR-S138

GTG3: GT3 Generator Earthing incorrectly installed

Install VSD Cable


11kV Cabling - GT 3 to Switchroom
Install HV/LV Cabling GT 3 Switchroom to Aux Transformer
GTG3: HV cable drum No GT H-3C240-01 has unacceptable resistance level.
11kV Cabling GT3 Switchroom to Step Up Transformer
BOP: The conduits coming out of the substation install by others at an incorrect depth
GTG3: Damaged tank heater on fuel system
GTG3: Supplied cables by Donalson not comply with BHP SPEC
GTG3: Gland plate provided is not suited to the amount of the cable
GTG3: Mounting bracket needed for gas detector
GTG3: Relocate cable to air lock
GTG3: Insufficient terminals in the HV room
GTG3: The temperature sensor has not been provided
GTG3: Cable Replacement

GTG3: No Holes Punched for Termination


LV- C & I Cable Terminations
11kV Cable Terminations
GTG3: GT3 Step Up Transformer Terminals
GTG3: GT3BFA10 Circuit Breaker modification
YARNIMA.11.8.1.2.6 Earthing and Lighting Protection
Earthing & Lightning Protection
GTG3: Earthing tags and earthing locations miss-alignment

46

29-06-2013 A

16-08-2013 A

100%

YARNIMA.11.8.1.2.7 Lighting and Small Power


A1720
Lighting & Small Power

21
21

10-04-2013 A
10-04-2013 A

25-07-2013 A
25-07-2013 A

408
408

GTG3: GT3 Generator Earthing incorrectly installed


YARNIMA.11.8.1.2.7 Lighting and Small Power

100%

YARNIMA.11.8.1.2.8 Field Equipment


A1730
Field Equipment (LCS's- J.B's- HDG conduits etc...)

14
14

09-07-2013 A
09-07-2013 A

02-08-2013 A
02-08-2013 A

21
21

Lighting & Small Power


YARNIMA.11.8.1.2.8 Field Equipment

100%

7
7

17-07-2013 A
17-07-2013 A

24-07-2013 A
24-07-2013 A

11
11

Field Equipment (LCS's- J.B's- HDG conduits etc...)


YARNIMA.11.8.1.4 INSTRUMENTS

100%

145
10

09-03-2013 A
09-03-2013 A

03-12-2013 A
03-12-2013 A

3453
0

Install Stage 1 Instruments


YARNIMA.11.8.1.5 PHASE 1 PRE-COMMISSIONING

100%

YARNIMA.11.8.1.4 INSTRUMENTS
A9040
Install Stage 1 Instruments
YARNIMA.11.8.1.5 PHASE 1 PRE-COMMISSIONING
A22990
Mechanical and Electrical Pre-Commissioning and punchlisting B & C-Items
Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 8 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Mechanical and Electrical Pre-Commissioning and punchlisting B


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

NCR-S067

GTG3: GT3 lube oil cooler headers, several plugs leaking

13

12-04-2013 A

25-04-2013 A

100%

A1570

Electrical Pre-Commissioning and punchlisting A-Items

21

31-05-2013 A

25-09-2013 A

532

100%

A3220

NDT & QA Documentation

14

20-06-2013 A

26-09-2013 A

50

100%

NDT & QA Documentation

A2040

Lube Oil Flush

10

28-06-2013 A

24-09-2013 A

80

100%

Lube Oil Flush

A1740

Mechanical Pre-Commissioning and punchlisting A-Items

33

29-06-2013 A

27-09-2013 A

650

100%

Mechanical Pre-Commissioning and punchlisting A-Items

VEGT3523

VE GTG 3 - Commissioning Assistance for Switchroom

101

09-08-2013 A

25-11-2013 A

2141

100%

A2080

Construction Verification

27-09-2013 A

100%

YARNIMA.10 PHASE 2
YARNIMA.10.10 COMPANY DELIVERABLES
YARNIMA.10.10.1 ENGINEERING DELIVERABLES
YARNIMA.10.10.1.1 GA & DETAILED ASSEMBLY DWGS
A7770
GT2 & GT1 GA & Detailed Assembly Dwgs

YARNIMA.10 PHASE 2

323515

216

15-10-2012 A

28-07-2013 A

YARNIMA.10.10 COMPANY DELIVERABLES

216
164
0

15-10-2012 A
01-02-2013 A
01-02-2013 A

28-07-2013 A
28-07-2013 A

0
0
0

YARNIMA.10.10.1 ENGINEERING DELIVERABLES


YARNIMA.10.10.1.1 GA & DETAILED ASSEMBLY DWGS
100%

05-04-2013 A

100%

A5980

ST1 & 2 GA & Detailed Assembly Dwgs

28-07-2013 A

100%

A5990

Cooling Towers 1 & 2 GA & Detailed Assembly Dwgs

28-07-2013 A

100%

0
0

21-12-2012 A
21-12-2012 A

21-12-2012 A

0
0

21-12-2012 A
21-12-2012 A

108
0

15-10-2012 A
15-10-2012 A

YARNIMA.10.10.1.3 STRUCTURAL
A5390
Stage 2 Piperack Dwgs AFC
YARNIMA.10.10.1.4 MECHANICAL
A5600
Pump Data Sheets Issued

Construction Verification

27-06-2014

Stage 2 Buried Pit Dwgs AFC

VE GTG 3 - Commissioning Assistance for Switchroom

15-10-2012 A

HRSG2 & HRSG1 GA & Detailed Assembly Dwgs

A5860

Electrical Pre-Commissioning and punchlisting A-Items

495

A7780

YARNIMA.10.10.1.2 CIVIL
A5370
Stage 2 Buried Services Trench Layout Dwgs AFC

GTG3: GT3 lube oil cooler headers, several plugs leaking

21-12-2012 A

GT2 & GT1 GA & Detailed Assembly Dwgs


HRSG2 & HRSG1 GA & Detailed Assembly Dwgs
ST1 & 2 GA & Detailed Assembly Dwgs
Cooling Towers 1 & 2 GA & Detailed Assembly Dwgs
YARNIMA.10.10.1.2 CIVIL

0
0

100%

Stage 2 Buried Services Trench Layout Dwgs AFC

100%

21-12-2012 A

0
0

Stage 2 Buried Pit Dwgs AFC


YARNIMA.10.10.1.3 STRUCTURAL

100%

30-03-2013 A

0
0

Stage 2 Piperack Dwgs AFC


YARNIMA.10.10.1.4 MECHANICAL

100%

Pump Data Sheets Issued

A5420

Large Bore HP Steam Main Isometrics Issued

05-11-2012 A

100%

A5460

Stage 2 Valve List (Stage 2) Issued

17-12-2012 A

100%

Stage 2 Valve List (Stage 2) Issued

A5560

Stage 2 Piping Isometrics Issued for CW Piping Info

21-12-2012 A

100%

Stage 2 Piping Isometrics Issued for CW Piping Info

A5410

Stage 2 Pipe Isometrics Issued

01-01-2013 A

100%

Stage 2 Pipe Isometrics Issued

A6440

Steam Valve List Issued

04-01-2013 A

100%

Steam Valve List Issued

A5440

Stage 2 GAs & Mechanical Sections Issued

30-03-2013 A

100%

216
0

15-10-2012 A
15-10-2012 A

0
0

100%

BSDG Electrical Dwgs AFC


BSDG Datasheets & Specifications

YARNIMA.10.10.1.5 ELECTRICAL
A5510
BSDG Electrical Dwgs AFC

25-07-2013 A

Large Bore HP Steam Main Isometrics Issued

Stage 2 GAs & Mechanical Sections Issued


YARNIMA.10.10.1.5 ELECTRICAL

A7940

BSDG Datasheets & Specifications

15-10-2012 A

100%

A5500

HRSG 2 & 1 Electrical Dwgs AFC

04-11-2012 A

100%

A5480

GT1 & GT2 Electrical Dwgs AFC

28-11-2012 A

100%

GT1 & GT2 Electrical Dwgs AFC

A5490

ST1 & ST2 Electrical Dwgs AFC

28-11-2012 A

100%

ST1 & ST2 Electrical Dwgs AFC

A5530

Stage 2 Common Cable Sched & Electrical MTO Issued

25-07-2013 A

100%

0
0

21-12-2012 A
21-12-2012 A

21-12-2012 A

0
0

Stage 2 Common Cable Sched & Electrical MTO Issued


YARNIMA.10.10.1.6 INSTRUMENTATION & CONTROL

100%

72
72
0

22-02-2013 A
22-02-2013 A
22-02-2013 A

08-05-2013 A
08-05-2013 A

0
0
0

Stage 2 Instrument & Control Information AFC


YARNIMA.10.10.2 CONSTRUCTION DELIVERABLES
YARNIMA.10.10.2.1 CIVIL WORKS

YARNIMA.10.10.1.6 INSTRUMENTATION & CONTROL


A5570
Stage 2 Instrument & Control Information AFC
YARNIMA.10.10.2 CONSTRUCTION DELIVERABLES
YARNIMA.10.10.2.1 CIVIL WORKS
A5740
HRSG2 Fnd Ready for Equip

HRSG 2 & 1 Electrical Dwgs AFC

100%

HRSG2 Fnd Ready for Equip

A5750

GT2 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip
0

24-02-2013 A

100%

GT2 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip

A5730

HRSG1 Fnd Ready for Equip

24-03-2013 A

100%

A5720

GT1 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip
0

06-04-2013 A

100%

A7920

BSDG Aux Transformer Fnd Ready for Equip

01-05-2013 A

100%

BSDG Aux Transformer Fnd Ready for Equip

A7750

BSDG Switchroom Fnd Ready for Equip

02-05-2013 A

100%

BSDG Switchroom Fnd Ready for Equip

A5770

Cooling Tower Fnds Ready for Equip

03-05-2013 A

100%

Cooling Tower Fnds Ready for Equip

A5760

ST1 & ST2 Fnds Ready for Equip

08-05-2013 A

100%

0
0

01-03-2013 A
01-03-2013 A

01-03-2013 A

0
0

ST1 & ST2 Fnds Ready for Equip


YARNIMA.10.10.2.2 ELECTRICAL WORKS

100%

Stage 2 MV Cables Supplied

273

02-02-2013 A

16-11-2013 A

59
0

18-03-2013 A
18-03-2013 A

10-06-2013 A

0
0

100%

YARNIMA.10.10.2.2 ELECTRICAL WORKS


A1440
Stage 2 MV Cables Supplied

YARNIMA.10.11 COMPANY SUPPLIED ITEMS


YARNIMA.10.11.2 GAS TURBINE 2 & ASSOCIATED EQUIPMENT
A1160
GT2 & Assoc Equipment

HRSG1 Fnd Ready for Equip


GT1 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for Equip

YARNIMA.10.11 COMPANY SUPPLIED ITEMS


YARNIMA.10.11.2 GAS TURBINE 2 & ASSOCIATED EQUIPMENT
GT2 & Assoc Equipment

A1170

GT2 Auxillary 1.5 MVA Transformer

25-05-2013 A

100%

A1190

GT-2 Battery Room

06-06-2013 A

100%

GT-2 Battery Room

A1180

GT-2 Switchroom

10-06-2013 A

100%

GT-2 Switchroom

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 9 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

GT2 Auxillary 1.5 MVA Transformer

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name
YARNIMA.10.11.11 BLACK START GENERATOR ASSOCIATED EQUIPMENT
A1480
BSG 0.5MVA Auxillary Transformer
A1490

BSDG Switchroom

YARNIMA.10.11.3 GAS TURBINE 1 & ASSOCIATED EQUIPMENT


A1200
GT1 & Assoc Equipment

Original
Duration

Start

Finish

Budgeted
Labor Units

107
0

30-06-2013 A
30-06-2013 A

16-11-2013 A

0
0

100%

BSG 0.5MVA Auxillary Transformer

16-11-2013 A

100%

59
0

15-04-2013 A
15-04-2013 A

0
0

BSDG Switchroom
YARNIMA.10.11.3 GAS TURBINE 1 & ASSOCIATED EQUIPMENT

100%

26-06-2013 A

Total
Float

Activity % S
Complete

YARNIMA.10.11.11 BLACK START GENERATOR ASSOCIATED E

GT1 & Assoc Equipment

A1210

GT1 Auxillary 1.5 MVA Transformer

25-05-2013 A

100%

A1220

GT1 Switchroom

25-06-2013 A

100%

GT1 Switchroom

A1230

GT1 Battery Room

26-06-2013 A

100%

0
0

GT1 Battery Room


YARNIMA.10.11.4 HRSG 3 & ASSOCIATED EQUIPMENT

100%

164
02-02-2013 A
28-06-2013 A
YARNIMA.10.11.4 HRSG 3 & ASSOCIATED EQUIPMENT
A1310
HRSG-3 Main Stack- Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork
0
02-02-2013
& Spooled Piping
A

GT1 Auxillary 1.5 MVA Transformer

HRSG-3 Main Stack- Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork & Spooled Piping

A1320

HRSG-3 Switchroom (incl Control Systems- BMS & Panels)

07-05-2013 A

100%

A1750

HRSG-3 Valves- Combustion Equipment & Vent Silencers

28-06-2013 A

100%

HRSG-3 Valves- Combustion Equipment & Vent Silencers

A1770

HRSG-3 Wet Racks

28-06-2013 A

100%

0
0

HRSG-3 Wet Racks


YARNIMA.10.11.6 HRSG 2 & ASSOCIATED EQUIPMENT

100%

165
06-02-2013 A
18-07-2013 A
YARNIMA.10.11.6 HRSG 2 & ASSOCIATED EQUIPMENT
A1280
HRSG-2 Main Stack- Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork
0
06-02-2013
& Spooled Piping
A

HRSG-3 Switchroom (incl Control Systems- BMS & Panels)

HRSG-2 Main Stack- Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork & Spooled Pipin

A1270

HRSG-2 Bypass Stack

09-04-2013 A

100%

A1290

HRSG-2 Switchroom (incl Control Systems- BMS & Panels)

27-04-2013 A

100%

A1780

HRSG-2 Valves- Combustion Equipment & Vent Silencers

28-06-2013 A

100%

HRSG-2 Valves- Combustion Equipment & Vent Silencers

A1790

HRSG-2 Instruments- Sampling- CEMS & Heat Exchangers

28-06-2013 A

100%

HRSG-2 Instruments- Sampling- CEMS & Heat Exchangers

A1800

HRSG-2 Wet Racks

28-06-2013 A

100%

HRSG-2 Wet Racks

NCR-S151

HRSG1: HRSG-1 Main Stack Platform

09-07-2013 A

18-07-2013 A

100%

112
24-03-2013 A
YARNIMA.10.11.5 HRSG 1 & ASSOCIATED EQUIPMENT
A1250
HRSG-1 Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork & Spooled
0
Piping
24-03-2013 A

12-07-2013 A

0
0

100%

HRSG-2 Bypass Stack


HRSG-2 Switchroom (incl Control Systems- BMS & Panels)

HRSG1: HRSG-1 Main Stack Platform


YARNIMA.10.11.5 HRSG 1 & ASSOCIATED EQUIPMENT
HRSG-1 Pressure Part Modules- Steam Drum- DA Vessel- Fabricated Steelwork & Spooled Piping

A1240

HRSG-1 Bypass Stack

16-04-2013 A

100%

A1260

HRSG-1 Switchroom (incl Control Systems- BMS & Panels)

27-04-2013 A

100%

A1810

HRSG-1 Valves- Combustion Equipment & Vent Silencers

02-07-2013 A

100%

HRSG-1 Valves- Combustion Equipment & Vent Silencers

A1820

HRSG-1 Instruments- Sampling- CEMS & Heat Exchangers

04-07-2013 A

100%

HRSG-1 Instruments- Sampling- CEMS & Heat Exchangers

A1830

HRSG-1 Wet Racks

12-07-2013 A

100%

67
0

19-06-2013 A
19-06-2013 A

0
0

100%

YARNIMA.10.11.8 STEAM TURBINE 1 & ASSOCIATED EQUIPMENT


A1350
Steam Turbine Generator 1& Assoc Equipment

15-09-2013 A

HRSG-1 Bypass Stack


HRSG-1 Switchroom (incl Control Systems- BMS & Panels)

HRSG-1 Wet Racks


YARNIMA.10.11.8 STEAM TURBINE 1 & ASSOCIATED EQUIPMENT
Steam Turbine Generator 1& Assoc Equipment

A1380

STG MV Switchroom

06-09-2013 A

100%

A1360

STG-1 Auxillary 2.5 MVA Transformer

15-09-2013 A

100%

STG-1 Auxillary 2.5 MVA Transformer

A1370

STG-1 Main 8 MVA Transformer

15-09-2013 A

100%

74
0

20-05-2013 A
20-05-2013 A

0
0

STG-1 Main 8 MVA Transformer


YARNIMA.10.11.9 STEAM TURBINE 2 & ASSOCIATED EQUIPMENT

100%

YARNIMA.10.11.9 STEAM TURBINE 2 & ASSOCIATED EQUIPMENT


A1400
Steam Turbine Generator 2 & Assoc Equipment

15-09-2013 A

STG MV Switchroom

Steam Turbine Generator 2 & Assoc Equipment

A1390

STG LV Switchroom

06-09-2013 A

100%

A1410

STG-2 Auxillary 2.5 MVA Transformer

15-09-2013 A

100%

A1420

STG-2 Main 8 MVA Transformer

15-09-2013 A

100%

87
0

07-05-2013 A
07-05-2013 A

0
0

100%

High Energy Drain Vessels

07-05-2013 A

100%

Super Heated Steam Valves

YARNIMA.10.11.10 STG'S ANCILLARY ITEMS


A1470
High Energy Drain Vessels

28-06-2013 A

STG LV Switchroom
STG-2 Auxillary 2.5 MVA Transformer
STG-2 Main 8 MVA Transformer
YARNIMA.10.11.10 STG'S ANCILLARY ITEMS

A1560

Super Heated Steam Valves

A1450

Steam Silencers (5 of: 2xStart up- 2xHigh Energy Drain Vessels-1xSteam Blow Silencer)
0

28-06-2013 A

100%

Steam Silencers (5 of: 2xStart up- 2xHigh Energy Drain Vessels-1xSteam Blow Silencer)

A1460

Cooling Tower 1 & Assoc Equip

28-06-2013 A

100%

Cooling Tower 1 & Assoc Equip

A1610

Cooling Tower 2 & Assoc Equip

28-06-2013 A

100%

0
0

28-07-2013 A
28-07-2013 A

28-07-2013 A

0
0

Cooling Tower 2 & Assoc Equip


YARNIMA.10.11.7 MAIN COOLING WATER PUMP STRAINERS

100%

177

02-02-2013 A

04-10-2013 A

Main Cooling Water Strainers (TBC)


YARNIMA.10.14 ENGINEERING & DESIGN
Stage 2 Piping Isometrics Issued for Procurement
YARNIMA.10.14.1 COOLING WATER PUMPS FOUNDATIONS

YARNIMA.10.11.7 MAIN COOLING WATER PUMP STRAINERS


A11490
Main Cooling Water Strainers (TBC)

YARNIMA.10.14 ENGINEERING & DESIGN


A14000

Stage 2 Piping Isometrics Issued for Procurement

YARNIMA.10.14.1 COOLING WATER PUMPS FOUNDATIONS


A3400
Prepare Engineering Design Dwgs for Cooling Water Pumps Fnds

11-09-2013 A

126
30

02-02-2013 A
02-02-2013 A

100%

23-07-2013 A
23-05-2013 A

0
0

100%

02-05-2013 A

100%

Prepare Engineering Design Dwgs for Cooling Water Pumps Fnds

A3430

Submit for Review & Comment

A3440

Client Review & Comment

08-05-2013 A

26-06-2013 A

100%

A3470

Client Approve Dwgs AFC

09-07-2013 A

16-07-2013 A

100%

A3450

Include Comments

17-07-2013 A

23-07-2013 A

100%

Include Comments

A3460

Submit For Approval

19-07-2013 A

100%

Submit For Approval

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 10 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Submit for Review & Comment


Client Review & Comment
Client Approve Dwgs AFC

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name
YARNIMA.10.14.2 AUXILLARY COOLING WATER PUMPS FOUNDATIONS
A3410
Prepare Engineering Design Dwgs for Aux Cooling Water Pumps Fnds

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

126
30

02-02-2013 A
02-02-2013 A

09-08-2013 A
30-04-2013 A

0
0

100%

Prepare Engineering Design Dwgs for Aux Cooling Water Pumps Fnds

30-04-2013 A

100%

Submit for Review & Comment

YARNIMA.10.14.2 AUXILLARY COOLING WATER PUMPS FOUNDATIONS

A7820

Submit for Review & Comment

A7830

Client Review & Comment

30-05-2013 A

06-06-2013 A

100%

A7840

Include Comments

06-07-2013 A

09-07-2013 A

100%

A7850

Submit For Approval

19-07-2013 A

100%

A7860

Client Approve Dwgs AFC

02-08-2013 A

09-08-2013 A

100%

YARNIMA.10.14.3 BSDG FOUNDATIONS


A3420
Prepare Engineering Design Dwgs for BSDG Fnds

127
30

02-02-2013 A
02-02-2013 A

15-08-2013 A
30-04-2013 A

0
0

100%

30-05-2013 A

100%

Submit for Review & Comment

04-07-2013 A

100%

Client Review & Comment

30-07-2013 A

100%

Client Review & Comment


Include Comments
Submit For Approval
Client Approve Dwgs AFC
YARNIMA.10.14.3 BSDG FOUNDATIONS
Prepare Engineering Design Dwgs for BSDG Fnds

A7870

Submit for Review & Comment

A7880

Client Review & Comment

A7900

Submit For Approval

A7910

Client Approve Dwgs AFC

01-08-2013 A

15-08-2013 A

100%

A7890

Include Comments

02-08-2013 A

09-08-2013 A

100%

47
30

10-05-2013 A
10-05-2013 A

02-10-2013 A
04-08-2013 A

0
0

100%

Prepare Engineering Design Dwgs for ST Drain Pits Support Structures

31-07-2013 A

100%

Submit for Review & Comment

YARNIMA.10.14.4 ST DRAIN PITS STRUCTURAL STEEL


A11500
Prepare Engineering Design Dwgs for ST Drain Pits Support Structures

30-05-2013 A

Submit For Approval


Client Approve Dwgs AFC
Include Comments
YARNIMA.10.14.4 ST DRAIN PITS STRUCTURAL STEEL

A11510

Submit for Review & Comment

A11520

Client Review & Comment

01-08-2013 A

07-08-2013 A

100%

A11530

Include Comments

01-08-2013 A

07-08-2013 A

100%

Include Comments

A11540

Submit For Approval

01-08-2013 A

100%

Submit For Approval

A11550

Client Approve Dwgs AFC

YARNIMA.10.14.5 HRSG DRAIN PITS STRUCTURAL STEEL


A11560
Prepare Engineering Design Dwgs for HRSG Drain Pits Support Structures

16-08-2013 A

02-10-2013 A

100%

50
30

05-05-2013 A
05-05-2013 A

04-10-2013 A
30-07-2013 A

0
0

100%

30-07-2013 A

04-10-2013 A

100%

Client Review & Comment

Client Approve Dwgs AFC


YARNIMA.10.14.5 HRSG DRAIN PITS STRUCTURAL STEEL
Prepare Engineering Design Dwgs for HRSG Drain Pits Support Structures

A11580

Client Review & Comment

A11600

Submit For Approval

01-08-2013 A

100%

A11570

Submit for Review & Comment

06-08-2013 A

100%

Submit for Review & Comment

A11590

Include Comments

08-08-2013 A

09-08-2013 A

100%

Include Comments

A11610

Client Approve Dwgs AFC

17-08-2013 A

01-10-2013 A

100%

57
30

01-08-2013 A
01-08-2013 A

05-08-2013 A
05-08-2013 A

0
0

Client Approve Dwgs AFC


YARNIMA.10.14.6 OW DRAIN SUMPS STRUCTURAL STEEL

YARNIMA.10.14.6 OW DRAIN SUMPS STRUCTURAL STEEL


A11620
Prepare Engineering Design Dwgs for OW Drain Sumps Support Structures

Client Review & Comment


Submit For Approval

100%

Prepare Engineering Design Dwgs for OW Drain Sumps Support Structures

A11640

Client Review & Comment (requirements to be confirmed)

01-08-2013 A

05-08-2013 A

100%

Client Review & Comment (requirements to be confirmed)

A11650

Include Comments

01-08-2013 A

05-08-2013 A

100%

Include Comments

A11670

Client Approve Dwgs AFC

01-08-2013 A

05-08-2013 A

100%

Client Approve Dwgs AFC

A11630

Submit for Review & Comment

05-08-2013 A

100%

Submit for Review & Comment

A11660

Submit For Approval

05-08-2013 A

100%

Submit For Approval

29-01-2014 A

315

YARNIMA.10.8 PROCUREMENT
YARNIMA.10.8.1 STRUCTURAL
A22840
Supply, Fabricate, Deliver STG 2 External Platforms

15-10-2012 A

59
48

08-08-2013 A
08-08-2013 A

14-11-2013 A
02-11-2013 A

0
0

YARNIMA.10.8 PROCUREMENT
YARNIMA.10.8.1 STRUCTURAL
100%

Supply, Fabricate, Deliver STG 2 External Platforms

A22820

Supply, Fabricate, Deliver STG 1 External Platforms

54

08-08-2013 A

03-11-2013 A

100%

Supply, Fabricate, Deliver STG 1 External Platforms

A22810

Supply, Fabricate, Deliver STG 1 Internal Platforms

13

21-08-2013 A

05-11-2013 A

100%

Supply, Fabricate, Deliver STG 1 Internal Platforms

A22830

Supply, Fabricate, Deliver STG 2 Internal Platforms

48

21-08-2013 A

02-11-2013 A

100%

Supply, Fabricate, Deliver STG 2 Internal Platforms

A11690

HRSG Drain Pits SSteel (Review- Procure & Deliver)

21

24-08-2013 A

13-11-2013 A

100%

A22850

Supply, Fabricate, Deliver Chemical Dosing Platforms

21

24-08-2013 A

14-11-2013 A

100%

Supply, Fabricate, Deliver Chemical Dosing Platforms

A11700

ST Drain Pits SSteel (Review- Procure & Deliver)

21

30-08-2013 A

13-11-2013 A

100%

ST Drain Pits SSteel (Review- Procure & Deliver)

A11680

Drain Sumps SSteel (Review- Procure & Deliver)

10

01-10-2013 A

02-11-2013 A

100%

315
308
21

15-10-2012 A
15-10-2012 A
15-10-2012 A

29-01-2014 A
09-12-2013 A
21-12-2012 A

0
0
0

100%

Finalise Vendor Design Deliverables

21-12-2012 A

100%

Confirm Vendor

YARNIMA.10.8.2 MECHANICAL
YARNIMA.10.8.2.15 COOLING WATER PUMPS
A8430
Finalise Vendor Design Deliverables

HRSG Drain Pits SSteel (Review- Procure & Deliver)

Drain Sumps SSteel (Review- Procure & Deliver)


YARNIMA.10.8.2 MECHANICAL
YARNIMA.10.8.2.15 COOLING WATER PUMPS

A8440

Confirm Vendor

A8450

Client Review & Comment

21-12-2012 A

21-12-2012 A

100%

Client Review & Comment

A8460

Include Comments

21-12-2012 A

21-12-2012 A

100%

Include Comments

A8470

Submit For Final Approval

21-12-2012 A

100%

Submit For Final Approval

A8480

Client Final Approval

21-12-2012 A

21-12-2012 A

100%

Client Final Approval

A8490

Issue PO

21-12-2012 A

21-12-2012 A

100%

Issue PO

A8500

Manufacture- Air Freight & Deliver Cooling Water Pumps

306

05-01-2013 A

06-12-2013 A

100%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 11 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Manufacture- Air Freight & Deliver Cooling Water Pumps


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A8930

Deliver to Perth CW Pump Base Plates, Motors & Dummy Pump Frame

06-12-2013 A

100%

Deliver to Perth CW Pump Base Plates, Motors & Dummy Pump

A8940

Deliver to Site CW Pumps

09-12-2013 A

100%

Deliver to Site CW Pumps

A8950

Deliver to Site CW Pump Base Plates, Motors & Dummy Pump Frames

09-12-2013 A

100%

10-01-2014 A
21-12-2012 A

0
0

Deliver to Site CW Pump Base Plates, Motors & Dummy Pump


YARNIMA.10.8.2.16 AUXILIARY COOLING WATER PUM

100%

Finalise Vendor Design Deliverables

21-12-2012 A

100%

Confirm Vendor

241
21

YARNIMA.10.8.2.16 AUXILIARY COOLING WATER PUMPS


A8510
Finalise Vendor Design Deliverables

15-10-2012 A
15-10-2012 A

A8520

Confirm Vendor

A8530

Client Review & Comment

21-12-2012 A

21-12-2012 A

100%

Client Review & Comment

A8540

Include Comments

21-12-2012 A

21-12-2012 A

100%

Include Comments

A8550

Submit For Final Approval

21-12-2012 A

100%

Submit For Final Approval

A8560

Client Final Approval

21-12-2012 A

21-12-2012 A

100%

Client Final Approval

A8570

Issue PO

21-12-2012 A

21-12-2012 A

100%

Issue PO

A8580

Manufacture & Deliver Aux Cooling Water Pumps

146

20-01-2013 A

12-12-2013 A

100%

A8970

Deliver to Site - Auxiliary Cooling Water Pumps

10-01-2014 A

100%

29-01-2014 A
21-12-2012 A

0
0

100%

Finalise Vendor Design Deliverables

21-12-2012 A

100%

Confirm Vendor

0
315
21

YARNIMA.10.8.2.4 BSDG
A1100
Finalise Vendor Design Deliverables

10-12-2012 A
10-12-2012 A

Manufacture & Deliver Aux Cooling Water Pumps


Deliver to Site - Auxiliary Cooling Water Pumps
YARNIMA.10.8.2.4 BSDG

A1940

Confirm Vendor

A2020

Client Review & Comment

21-12-2012 A

21-12-2012 A

100%

Client Review & Comment

A2090

Include Comments

21-12-2012 A

21-12-2012 A

100%

Include Comments

A2100

Submit For Final Approval

21-12-2012 A

100%

Submit For Final Approval

A2110

Client Final Approval

21-12-2012 A

21-12-2012 A

100%

Client Final Approval

A2120

Issue PO

21-12-2012 A

21-12-2012 A

100%

Issue PO

A1330

Manufacture & Deliver BSDG

314

10-01-2013 A

29-01-2014 A

100%

213
21

02-11-2012 A
02-11-2012 A

25-09-2013 A
21-12-2012 A

0
0

100%

22-01-2013 A

01-02-2013 A

100%

23-01-2013 A

100%

05-02-2013 A

100%

Include Comments

05-02-2013 A

100%

Submit For Final Approval

YARNIMA.10.8.2.12 HRSG DRAINS PIT PUMPS


A8050
Finalise Vendor Design Deliverables

Manufacture & Deliver BSDG


YARNIMA.10.8.2.12 HRSG DRAINS PIT PUMPS
Finalise Vendor Design Deliverables

A8070

Client Review & Comment

A8060

Confirm Vendor

A8080

Include Comments

A8090

Submit For Final Approval

A8100

Client Final Approval

06-02-2013 A

15-02-2013 A

100%

Client Final Approval

A8110

Issue PO

16-02-2013 A

18-02-2013 A

100%

Issue PO

A8120

Manufacture & Deliver HRSG Pumps

177

17-02-2013 A

25-09-2013 A

100%

267
21

02-11-2012 A
02-11-2012 A

29-11-2013 A
21-12-2012 A

0
0

100%

05-02-2013 A

100%

YARNIMA.10.8.2.13 STG DRAINS PIT PUMPS


A8130
Finalise Vendor Design Deliverables

01-02-2013 A

Client Review & Comment


Confirm Vendor

Manufacture & Deliver HRSG Pumps


YARNIMA.10.8.2.13 STG DRAINS PIT PUMPS
Finalise Vendor Design Deliverables

A8140

Confirm Vendor

A8150

Client Review & Comment

19-02-2013 A

25-02-2013 A

100%

Client Review & Comment

A8160

Include Comments

25-02-2013 A

28-02-2013 A

100%

Include Comments

A8170

Submit For Final Approval

01-03-2013 A

100%

Submit For Final Approval

A8180

Client Final Approval

02-03-2013 A

05-03-2013 A

100%

Client Final Approval

A8190

Issue PO

06-03-2013 A

07-03-2013 A

100%

Issue PO

A8200

Manufacture & Deliver STG Pumps

177

20-04-2013 A

29-11-2013 A

100%

YARNIMA.10.8.2.14 SUMP PUMPS


A8210
Finalise Vendor Design Deliverables

246
21

02-11-2012 A
02-11-2012 A

29-11-2013 A
21-12-2012 A

0
0

100%

15-01-2013 A

100%

Confirm Vendor
Client Review & Comment

Confirm Vendor

Manufacture & Deliver STG Pumps


YARNIMA.10.8.2.14 SUMP PUMPS
Finalise Vendor Design Deliverables

A8220

Confirm Vendor

A8230

Client Review & Comment

15-01-2013 A

20-01-2013 A

100%

A8240

Include Comments

01-02-2013 A

03-02-2013 A

100%

Include Comments

A8250

Submit For Final Approval

06-02-2013 A

100%

Submit For Final Approval

A8260

Client Final Approval

07-02-2013 A

09-02-2013 A

100%

Client Final Approval

A8270

Issue PO

10-02-2013 A

11-02-2013 A

100%

Issue PO

A8280

Manufacture & Deliver Sump Pumps

44

06-04-2013 A

29-11-2013 A

100%

A8960

Deliver to Perth

12-06-2013 A

100%

A8980

Deliver to Site

YARNIMA.10.8.2.5 LARGE BORE HP STEAM PIPING


A8290
Finalise Vendor Design Deliverables

168
21

A8300

Confirm Vendor

A8310

Client Review & Comment

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

02-11-2012 A
02-11-2012 A
21-12-2012 A

Page 12 of 38
Data Date 07-02-2014

Manufacture & Deliver Sump Pumps


Deliver to Perth

29-11-2013 A

100%

25-09-2013 A
21-12-2012 A

0
0

100%

Finalise Vendor Design Deliverables

21-12-2012 A

100%

Confirm Vendor

21-12-2012 A

100%

Client Review & Comment

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Deliver to Site
YARNIMA.10.8.2.5 LARGE BORE HP STEAM PIPING

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

21-12-2012 A

21-12-2012 A

100%

Include Comments

21-12-2012 A

100%

Submit For Final Approval


Client Final Approval

A8320

Include Comments

A8330

Submit For Final Approval

A8340

Client Final Approval

21-12-2012 A

21-12-2012 A

100%

A8350

Issue PO

30-01-2013 A

01-02-2013 A

100%

A8360

Manufacture & Deliver Steam Piping (Initial Delivery)

112

09-03-2013 A

25-09-2013 A

100%

YARNIMA.10.8.2.9 ALLOY/SSTEEL PIPING


A8390
Alloy/SSteel Piping (Review- Procure & Deliver)

108
108

07-06-2013 A
07-06-2013 A

25-09-2013 A
25-09-2013 A

0
0

100%

YARNIMA.10.8.2.1 PIPERACK
A1430
Finalise Tender Package for Stage 2 Piperack

243
21

15-10-2012 A
15-10-2012 A

11-09-2013 A
12-11-2012 A

0
0

100%

Finalise Tender Package for Stage 2 Piperack

14-12-2012 A

08-02-2013 A

100%

Shop Detailing Stage 2 Piperack

A5590

Fabricate Stage 2 Piperack

24

14-01-2013 A

20-02-2013 A

100%

Fabricate Stage 2 Piperack

A5940

Surface Treatment Stage 2 Piperack

14

01-03-2013 A

29-08-2013 A

100%

A5950

Deliver Stage 2 Piperack (North-South)

10-03-2013 A

08-09-2013 A

100%

A5950-a

Deliver Stage 2 Piperack (East-West)

10

01-09-2013 A

11-09-2013 A

100%

69
60

21-12-2012 A
21-12-2012 A

20-04-2013 A
25-03-2013 A

0
0

100%

45

25-01-2013 A

20-04-2013 A

100%

122
7

25-01-2013 A
25-01-2013 A

10-03-2013 A
04-02-2013 A

0
0

100%

Finalise Vendor Design Deliverables

04-02-2013 A

100%

Confirm Vendor

YARNIMA.10.8.2.19 GAS VALVES


A12190
Finalise Vendor Design Deliverables

Surface Treatment Stage 2 Piperack


Deliver Stage 2 Piperack (North-South)
Deliver Stage 2 Piperack (East-West)
YARNIMA.10.8.2.8 HDPE PIPING
Stage 2 HDPE Cooling Water Piping (Review- Procure & Deliver)
Stage 2 HDPE Piping (Review- Procure & Deliver)
YARNIMA.10.8.2.19 GAS VALVES

A12210

Confirm Vendor

A12220

Client Review & Comment

05-02-2013 A

11-02-2013 A

100%

Client Review & Comment

A12230

Include Comments

12-02-2013 A

14-02-2013 A

100%

Include Comments

A12240

Submit For Final Approval

14-02-2013 A

100%

Submit For Final Approval

A12250

Client Final Approval

15-02-2013 A

21-02-2013 A

100%

Client Final Approval

A12260

Issue PO

22-02-2013 A

22-02-2013 A

100%

Issue PO

A12200

Manufacture & Deliver Gas Valves

103

23-02-2013 A

10-03-2013 A

100%

YARNIMA.10.8.2.2 REMAINING VALVES STAGE 2


A8420
Remaining Stage 2 Valves (Review- Procure & Deliver)

126
126

15-01-2013 A
15-01-2013 A

30-06-2013 A
30-06-2013 A

0
0

Manufacture & Deliver Gas Valves


YARNIMA.10.8.2.2 REMAINING VALVES STAGE 2

100%

YARNIMA.10.8.2.11 STANDARD AIR VALVES


A8410
Standard Air Valves ( Review- Procure & Deliver)

102
102

25-01-2013 A
25-01-2013 A

06-03-2013 A
06-03-2013 A

0
0

Remaining Stage 2 Valves (Review- Procure & Deliver)


YARNIMA.10.8.2.11 STANDARD AIR VALVES

100%

YARNIMA.10.8.2.18 GAS PIPE & FITTINGS


A12110
Finalise Vendor Design Deliverables

101
21

17-12-2012 A
17-12-2012 A

25-03-2013 A
05-01-2013 A

0
0

Standard Air Valves ( Review- Procure & Deliver)


YARNIMA.10.8.2.18 GAS PIPE & FITTINGS

100%

Finalise Vendor Design Deliverables

05-01-2013 A

100%

Confirm Vendor

A12130

Confirm Vendor

A12140

Client Review & Comment

05-01-2013 A

12-01-2013 A

100%

Client Review & Comment

A12150

Include Comments

10-01-2013 A

13-01-2013 A

100%

Include Comments

A12160

Submit For Final Approval

14-01-2013 A

100%

Submit For Final Approval

A12170

Client Final Approval

15-01-2013 A

20-01-2013 A

100%

Client Final Approval

A12180

Issue PO

21-01-2013 A

21-01-2013 A

100%

Issue PO

A12120

Manufacture & Deliver Gas Piping & Fittings

60

23-01-2013 A

25-03-2013 A

100%

173
21

02-02-2013 A
02-02-2013 A

16-09-2013 A
21-02-2013 A

0
0

100%

YARNIMA.10.8.2.17 PIPE SUPPORTS


A12060
Finalise Tender Package for Stage 2 Pipe Supports

Alloy/SSteel Piping (Review- Procure & Deliver)


YARNIMA.10.8.2.1 PIPERACK

14

Stage 2 HDPE Piping (Review- Procure & Deliver)

Manufacture & Deliver Steam Piping (Initial Delivery)


YARNIMA.10.8.2.9 ALLOY/SSTEEL PIPING

Shop Detailing Stage 2 Piperack

A8920

Issue PO

A5900

YARNIMA.10.8.2.8 HDPE PIPING


A8380
Stage 2 HDPE Cooling Water Piping (Review- Procure & Deliver)

Manufacture & Deliver Gas Piping & Fittings


YARNIMA.10.8.2.17 PIPE SUPPORTS
Finalise Tender Package for Stage 2 Pipe Supports

A12080

Shop Detailing Stage 2 Pipe Supports

21

05-06-2013 A

02-07-2013 A

100%

A12070

Fabricate Stage 2 Pipe Supports

24

30-07-2013 A

13-09-2013 A

100%

Fabricate Stage 2 Pipe Supports

A12100

Delivery Stage 2 Pipe Supports

24

27-08-2013 A

16-09-2013 A

100%

YARNIMA.10.8.2.6 CARBON STEEL PIPING < DN50


A8370
Carbon Steel Piping < DN50 (Review- Procure & Deliver)

24
24

09-08-2013 A
09-08-2013 A

14-10-2013 A
14-10-2013 A

0
0

Delivery Stage 2 Pipe Supports


YARNIMA.10.8.2.6 CARBON STEEL PIPING < DN50

100%

YARNIMA.10.8.2.7 CARBON STEEL PIPING > DN50


A8400
Carbon Steel Piping > DN50 (Review- Procure & Deliver)

136
136

29-03-2013 A
29-03-2013 A

25-09-2013 A
25-09-2013 A

0
0

Carbon Steel Piping < DN50 (Review- Procure & Deliver)


YARNIMA.10.8.2.7 CARBON STEEL PIPING > DN50

100%

163
110
40

26-02-2013 A
30-04-2013 A
30-04-2013 A

06-12-2013 A
06-12-2013 A
30-05-2013 A

0
0
0

Carbon Steel Piping > DN50 (Review- Procure & Deliver)


YARNIMA.10.8.3 ELECTRICAL
YARNIMA.10.8.3.1 STAGE 2 ELECTRICAL EQUIPMENT

100%

YARNIMA.10.8.3 ELECTRICAL
YARNIMA.10.8.3.1 STAGE 2 ELECTRICAL EQUIPMENT
A5640
GT1 & GT2 Electrical Equip (Review- Procure & Deliver)

Shop Detailing Stage 2 Pipe Supports

GT1 & GT2 Electrical Equip (Review- Procure & Deliver)

A5650

ST1 & ST2 Equip (Review- Procure & Deliver)

40

30-07-2013 A

01-09-2013 A

100%

A5660

HRSG Electrical Equip (Review- Procure & Deliver)

40

01-08-2013 A

13-09-2013 A

100%

HRSG Electrical Equip (Review- Procure & Deliver)

A5670

BSDG Electrical Equip (Review- Procure & Deliver)

40

04-08-2013 A

06-12-2013 A

100%

98
98

28-04-2013 A
28-04-2013 A

30-06-2013 A
30-06-2013 A

0
0

BSDG Electrical Equip (Review- Procure & Deliver)


YARNIMA.10.8.3.2 STAGE 2 CABLE

100%

YARNIMA.10.8.3.2 STAGE 2 CABLE


A7960
Stage 2 VSD & Other Specialist Cable (Review- Procure & Deliver)
Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 13 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

ST1 & ST2 Equip (Review- Procure & Deliver)

Stage 2 VSD & Other Specialist Cable (Review- Procure & Deliver)
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name
A5680

Stage 2 Cable & Elec Equip (Review- Procure & Deliver)

YARNIMA.10.8.3.4 STAGE 2 INSTRUMENTATION


A8840
Finalise Vendor Design Deliverables

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

30

30-04-2013 A

30-06-2013 A

100%

163
21

26-02-2013 A
26-02-2013 A

23-11-2013 A
02-04-2013 A

0
0

100%

05-03-2013 A

100%

Confirm Vendor
Client Review & Comment

A8860

Client Review & Comment

06-03-2013 A

08-03-2013 A

100%

A8870

Include Comments

11-03-2013 A

14-03-2013 A

100%

A8880

Submit For Final Approval

21-03-2013 A

100%

A8890

Client Final Approval

22-03-2013 A

28-03-2013 A

100%

Client Final Approval

A8900

Issue PO

29-03-2013 A

30-03-2013 A

100%

Issue PO

A8910

Manufacture & Deliver Stage 2 Instr & Controls

149

22-05-2013 A

23-11-2013 A

100%

462

02-01-2013 A

27-06-2014

323515

32
0

24-03-2014

27-04-2014
24-03-2014

0
0

57
89

0%

27-04-2014

57

0%

19-11-2013 A
03-07-2013 A

0
0
0

100%

100%

0
0

100%

A13960

Aboveground Piping Complete

YARNIMA.10.15.10 PRELIMINARIES
YARNIMA.10.15.10.1 SERVICES
A10420
Receipt Verification of Stage 2 MV Cables
A10430

Receipt Verification of Stage 2 Super Heated Steam Valves

YARNIMA.10.15.10.11 HRSG 3
A10360
Receipt Verification of HRSG3 Fnd

288
168
0

02-01-2013 A
01-03-2013 A
01-03-2013 A

03-07-2013 A

288
0

02-01-2013 A
02-01-2013 A

30-06-2013 A

Include Comments
Submit For Final Approval

Manufacture & Deliver Stage 2 Instr & Controls


YARNIMA.10.15 PHASE 2 CON

YARNIMA.10.15.16 PHASE 2 MILESTON


Underground Services Complete
Aboveground Piping Complete
YARNIMA.10.15.10 PRELIMINARIES
YARNIMA.10.15.10.1 SERVICES
Receipt Verification of Stage 2 MV Cables
Receipt Verification of Stage 2 Super Heated Steam Valves
YARNIMA.10.15.10.11 HRSG 3
Receipt Verification of HRSG3 Fnd

A10370

Receipt Verification of HRSG3 Free Issue Material & Equip

02-02-2013 A

100%

A10380

Receipt Verification of HRSG3 Instruments- Sampling & Heat Exchangers

03-03-2013 A

100%

A10680

Receipt Verification of HRSG3 Switchroom (incl Control Systems- BMS & Panels)

09-05-2013 A

100%

A10650

Receipt Verification of HRSG3 Wet Racks

15-05-2013 A

100%

Receipt Verification of HRSG3 Wet Racks

A10660

Receipt Verification of HRSG3 Valves & Combustion Equipment

15-05-2013 A

100%

Receipt Verification of HRSG3 Valves & Combustion Equipment

A10670

Receipt Verification of HRSG3 Silencers

30-06-2013 A

100%

0
0

100%

107
24-02-2013 A
10-06-2013 A
YARNIMA.10.15.10.2 GT2
A9380
Receipt Verification of GT2 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery
0 Rooms)
24-02-2013
Ready forAEquip

Receipt Verification of HRSG3 Free Issue Material & Equip


Receipt Verification of HRSG3 Instruments- Sampling & Heat Exchangers
Receipt Verification of HRSG3 Switchroom (incl Control Systems- BMS & Panels)

Receipt Verification of HRSG3 Silencers


YARNIMA.10.15.10.2 GT2
Receipt Verification of GT2 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Ready for

A9430

Receipt Verification of GT2 Free Issue Material & Equip

20-03-2013 A

100%

A9590

Receipt Verification of GT2 Aux 1.5 MVA Transformer

25-05-2013 A

100%

A9560

Receipt Verification of GT2 Battery Room

06-06-2013 A

100%

Receipt Verification of GT2 Battery Room

A9530

Receipt Verification of GT2 Switchroom

10-06-2013 A

100%

189
0

03-05-2013 A
03-05-2013 A

0
0

Receipt Verification of GT2 Switchroom


YARNIMA.10.15.10.13 BSDG

100%

Receipt Verification of BSDG Aux Transformer Fnd


Receipt Verification of BSDG Switchroom Fnd

YARNIMA.10.15.10.13 BSDG
A13200
Receipt Verification of BSDG Aux Transformer Fnd

19-11-2013 A

A13630

Receipt Verification of BSDG Switchroom Fnd

04-05-2013 A

100%

A13660

Receipt Verification of BSDG 0.5MVA Auxillary Transformer

01-07-2013 A

100%

A13670

Receipt Verification of BSDG Switchroom

19-11-2013 A

100%

0
0

100%

62
07-04-2013 A
26-06-2013 A
YARNIMA.10.15.10.5 GT1
A9460
Receipt Verification of GT1 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery
0 Rooms)
07-04-2013
Ready forAEquip

Receipt Verification of GT2 Free Issue Material & Equip


Receipt Verification of GT2 Aux 1.5 MVA Transformer

Receipt Verification of BSDG 0.5MVA Auxillary Transformer


Receipt Verification of BSDG Switchroom
YARNIMA.10.15.10.5 GT1

Receipt Verification of GT1 Fnd Incl Culverts & Fnds (Switchrooms- Piperacks & Battery Rooms) Rea

A9470

Receipt Verification of GT1 Free Issue Material & Equip

17-04-2013 A

100%

A12290

Receipt Verification of GT1 Aux 1.5 MVA Transformer

25-05-2013 A

100%

A12270

Receipt Verification of GT1 Switchroom

25-06-2013 A

100%

Receipt Verification of GT1 Switchroom

A12280

Receipt Verification of GT1 Battery Room

26-06-2013 A

100%

233
0

25-03-2013 A
25-03-2013 A

0
0

Receipt Verification of GT1 Battery Room


YARNIMA.10.15.10.6 HRSG 1

100%

YARNIMA.10.15.10.6 HRSG 1
A9490
Receipt Verification of HRSG1 Free Issue Material & Equip

13-07-2013 A

Finalise Vendor Design Deliverables

Confirm Vendor

YARNIMA.10.15.16 PHASE 2 MILESTONES


A13950
Underground Services Complete

Stage 2 Cable & Elec Equip (Review- Procure & Deliver)


YARNIMA.10.8.3.4 STAGE 2 INSTRUMENTATION

A8850

YARNIMA.10.15 PHASE 2 CONSTRUCTION

Receipt Verification of GT1 Free Issue Material & Equip


Receipt Verification of GT1 Aux 1.5 MVA Transformer

Receipt Verification of HRSG1 Free Issue Material & Equip

A9480

Receipt Verification of HRSG1 Fnd

08-04-2013 A

100%

A13650

Receipt Verification of HRSG1 Bypass Stack

17-04-2013 A

100%

A12320

Receipt Verification of HRSG1 Switchroom (incl Control Systems- BMS & Panels)

28-04-2013 A

100%

A12310

Receipt Verification of HRSG1 Valves- Combustion Equip & Vent Silencers

04-07-2013 A

100%

Receipt Verification of HRSG1 Valves- Combustion Equip & Vent Silencers

A9500

Receipt Verification of HRSG1 Instruments- Sampling- CEMS & Heat Exchangers

05-07-2013 A

100%

Receipt Verification of HRSG1 Instruments- Sampling- CEMS & Heat Exchangers

A12300

Receipt Verification of HRSG1 Wet Racks

13-07-2013 A

100%

150
0

06-02-2013 A
06-02-2013 A

0
0

100%

YARNIMA.10.15.10.3 HRSG 2
A9440
Receipt Verification of HRSG2 Free Issue Material & Equip

22-05-2013 A

A9390

Receipt Verification of HRSG2 Fnd

22-02-2013 A

100%

A13640

Receipt Verification of HRSG2 Bypass Stack

10-04-2013 A

100%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 14 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Receipt Verification of HRSG1 Fnd


Receipt Verification of HRSG1 Bypass Stack
Receipt Verification of HRSG1 Switchroom (incl Control Systems- BMS & Panels)

Receipt Verification of HRSG1 Wet Racks


YARNIMA.10.15.10.3 HRSG 2
Receipt Verification of HRSG2 Free Issue Material & Equip
Receipt Verification of HRSG2 Fnd
Receipt Verification of HRSG2 Bypass Stack
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A10220

Receipt Verification of HRSG2 Switchroom (incl Control Systems- BMS & Panels)

28-04-2013 A

100%

A9450

Receipt Verification of HRSG2 Instruments- Sampling- CEMS & Heat Exchangers

22-05-2013 A

100%

Receipt Verification of HRSG2 Instruments- Sampling- CEMS & Heat Exchangers

A10170

Receipt Verification of HRSG2 Wet Racks

22-05-2013 A

100%

Receipt Verification of HRSG2 Wet Racks

A10180

Receipt Verification of HRSG2 Valves- Combustion Equip & Vent Silencers

22-05-2013 A

100%

146
0

11-05-2013 A
11-05-2013 A

0
0

Receipt Verification of HRSG2 Valves- Combustion Equip & Vent Silencers


YARNIMA.10.15.10.7 ST1

100%

YARNIMA.10.15.10.7 ST1
A9510
Receipt Verification of ST1 Fnd

16-09-2013 A

Receipt Verification of HRSG2 Switchroom (incl Control Systems- BMS & Panels)

Receipt Verification of ST1 Fnd

A9520

Receipt Verification of ST1 Free Issue Material & Equip

19-06-2013 A

100%

A12370

Receipt Verification of ST1 Steam Silencers

02-07-2013 A

100%

Receipt Verification of ST1 Steam Silencers

A12380

Receipt Verification of ST1 High Energy Drain Vessels

05-07-2013 A

100%

Receipt Verification of ST1 High Energy Drain Vessels

A10410

Receipt Verification of ST MV Switchroom (1)

07-09-2013 A

100%

A10250

Receipt Verification of ST1 Aux 2.5 MVA Transformer

16-09-2013 A

100%

Receipt Verification of ST1 Aux 2.5 MVA Transformer

A10400

Receipt Verification of ST1 Main 8 MVA Transformer

16-09-2013 A

100%

146
0

07-05-2013 A
07-05-2013 A

0
0

Receipt Verification of ST1 Main 8 MVA Transformer


YARNIMA.10.15.10.8 ST2

100%

Receipt Verification of ST2 High Energy Drain Vessels


Receipt Verification of ST2 Fnd

YARNIMA.10.15.10.8 ST2
A12390
Receipt Verification of ST2 High Energy Drain Vessels

16-09-2013 A

Receipt Verification of ST1 Free Issue Material & Equip

Receipt Verification of ST MV Switchroom (1)

A9540

Receipt Verification of ST2 Fnd

11-05-2013 A

100%

A9550

Receipt Verification of ST2 Free Issue Material & Equip

20-05-2013 A

100%

A12360

Receipt Verification of ST2 Steam Silencers

02-07-2013 A

100%

A12350

Receipt Verification of ST LV Switchroom (1)

08-09-2013 A

100%

A12330

Receipt Verification of ST2 Aux 2.5 MVA Transformer

16-09-2013 A

100%

A12340

Receipt Verification of ST2 Main 8 MVA Transformer

16-09-2013 A

100%

142
0

06-05-2013 A
06-05-2013 A

0
0

100%

15-07-2013 A

100%

71
0

06-05-2013 A
06-05-2013 A

0
0

100%

15-07-2013 A

100%

0
0

29-07-2013 A
29-07-2013 A

29-07-2013 A

0
0

323
13
13

22-03-2013 A
21-07-2013 A
21-07-2013 A

27-04-2014
03-08-2013 A
03-08-2013 A

58127
0
0

101
12

29-07-2013 A
29-07-2013 A

25-11-2013 A
09-08-2013 A

2663
0

100%

HRSG Underground Services Clash with Plinth

02-08-2013 A

09-08-2013 A

100%

HDPE Line is clashing with GRE concrete sleeve

11-08-2013 A

12-08-2013 A

52

100%

Resolve Clashing of HDPE Line and GRE Concrete sleeve

NCR-S196

HRSG3: The kickplate of the Burner platform of the HRSG-3 is clashing to the stiffener3beam of20-08-2013
the HRSG A

22-08-2013 A

100%

NCR-S201

Missing Misc Footings

25-08-2013 A

01-09-2013 A

100%

Missing Misc Footings

VESITE1000

VE SITE - make good defective welds on lub oil system, corridor deliniation for HV Line5Energisation
01-09-2013 A

05-09-2013 A

128

100%

VE SITE - make good defective welds on lub oil system, corridor deliniation for

YARNIMA.10.15.10.9 COOLING TOWER 1


A9570
Receipt Verification of Cooling Tower 1 Fnd
A9580

Receipt Verification of Cooling Tower 1 Free Issue Material & Equip

YARNIMA.10.15.10.10 COOLING TOWER 2


A9600
Receipt Verification of Cooling Tower 2 Fnd
A9610

Receipt Verification of Cooling Tower 2 Free Issue Material & Equip

YARNIMA.10.15.10.12 COOLING WATER SYSTEM


A12400
Receipt Verification of Main Cooling Water Pump Strainers
YARNIMA.10.15.8 SERVICES
YARNIMA.10.15.8.3 PIPE RACKS
NCR-S157
BOP: Pipe Rack Fabrication Issues
YARNIMA.10.15.8.1 SERVICES - ACTUAL VARIATIONS & NON SCOPE WORKS
NCR-S165
HRSG Underground Services Clash with Plinth
NCR-S174

HDPE Line is clashing with GRE concrete sleeve

NCR-S174-803 Resolve Clashing of HDPE Line and GRE Concrete sleeve

15-07-2013 A

15-07-2013 A

Receipt Verification of ST2 Free Issue Material & Equip


Receipt Verification of ST2 Steam Silencers
Receipt Verification of ST LV Switchroom (1)
Receipt Verification of ST2 Aux 2.5 MVA Transformer
Receipt Verification of ST2 Main 8 MVA Transformer
YARNIMA.10.15.10.9 COOLING TOWER 1
Receipt Verification of Cooling Tower 1 Fnd
Receipt Verification of Cooling Tower 1 Free Issue Material & Equip
YARNIMA.10.15.10.10 COOLING TOWER 2
Receipt Verification of Cooling Tower 2 Fnd
Receipt Verification of Cooling Tower 2 Free Issue Material & Equip
YARNIMA.10.15.10.12 COOLING WATER SYSTEM

100%

Receipt Verification of Main Cooling Water Pump Strainers


YARNIMA.10.15.8 SERVICES
YARNIMA.10.15.8.3 PIPE RACKS

57
100%

BOP: Pipe Rack Fabrication Issues


YARNIMA.10.15.8.1 SERVICES - ACTUAL VARIATIONS & NON

HRSG3: The kickplate of the Burner platform of the HRSG-3 is clashing to the st

NCR-S201-920 Access to complete North to South Pipe Rack (Last Foundation)

79

02-09-2013 A

19-11-2013 A

100%

NCR-S274

Missing Cleat on South Pipe Rack - Column YPR C01015

06-10-2013 A

14-10-2013 A

100%

Missing Cleat on South Pipe Rack - Column YPR C01015

VESITE1234

VE SITE - Inclement Weather

Access to complete North to South Pipe Rack (Last Foundation)

VE SITE - Inclement Weather

14-10-2013 A

14-10-2013 A

256

100%

NCR-S274-1179 Corrective Action for missing cleats - NCR-S274

18

15-10-2013 A

03-11-2013 A

38

100%

VESITE1321

VE SITE - Inclement Weather

27-10-2013 A

28-10-2013 A

604

100%

VESITE1010

VE SITE - Design clash Blowdown pit/GRE piping, Waiting on permits to be signed by20
WP, and05-11-2013
intermittent Arain events
25-11-2013 A

510

100%

VE SITE - Design clash Blowdown pit/GRE piping, Waiting on per

VESITE1446

VE SITE - Inclement Weather

100%

VE SITE - Inclement Weather


YARNIMA.10.15.8.8 UNDERGROUND SERVIC

Corrective Action for missing cleats - NCR-S274


VE SITE - Inclement Weather

17-11-2013 A

18-11-2013 A

1075

295
295

22-03-2013 A
22-03-2013 A

18-03-2014
18-03-2014

16098
0

172
145
28

27-04-2013 A
27-04-2013 A
27-04-2013 A

17-12-2013 A
24-10-2013 A
14-09-2013 A

6588
6006
836

100%

Trenching & Excavation for Pipes

30

20-05-2013 A

13-09-2013 A

4208

100%

Install Pipes

12

21-07-2013 A

02-08-2013 A

100%

BOP: HDPE Pipe Clashes with Pedestals Behind the Cooling Tower

NCR-S169 BOP: No openings in Culvert or Discharge Pit - Demin water line (HRSG lines 1,2 &3) 8

31-07-2013 A

07-08-2013 A

100%

BOP: No openings in Culvert or Discharge Pit - Demin water line (HRSG lines 1,2 &

A13610

Backfill & Compaction

28

07-08-2013 A

08-10-2013 A

620

100%

A13920

Hydrotest

14

02-10-2013 A

24-10-2013 A

342

100%

YARNIMA.10.15.8.8 UNDERGROUND SERVICES


A9060
Phase 2 Underground Piping WBS Summary
YARNIMA.10.15.8.8.1 Green Phase (Refer to Marked up Burried Services Drawing)
YARNIMA.10.15.8.8.1.13 01-COOLING WATER PIPING
A13590
Trenching & Excavation for Pipes
A13600

Install Pipes

NCR-S156 BOP: HDPE Pipe Clashes with Pedestals Behind the Cooling Tower

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 15 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

94
94

0%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Phase 2 Underground Piping WBS Summary


YARNIMA.10.15.8.8.1 Green Phase (Refer to Marked up Bur
YARNIMA.10.15.8.8.1.13 01-COOLING WATER PIPING

Backfill & Compaction


Hydrotest
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

30
30

17-08-2013 A
17-08-2013 A

20-10-2013 A
20-10-2013 A

81
81

100%

15-09-2013 A

15-10-2013 A

100%

25
25

17-08-2013 A
17-08-2013 A

01-12-2013 A
01-12-2013 A

361
105

100%

21

22-08-2013 A

17-10-2013 A

256

100%

18
18

02-10-2013 A
02-10-2013 A

17-12-2013 A
17-12-2013 A

140
140

100%

Excavation & Backfilling for Underground Services - BSDG Eas

08-10-2013 A

13-12-2013 A

100%

15-08-2013 A
30-08-2013 A
30-08-2013 A

16-01-2014 A
27-11-2013 A
27-11-2013 A

2235
1325
120

Install Underground Services (Conduits) - BSDG East


YARNIMA.10.15.8.8.2 Orange Phase (Refer to Marked u
YARNIMA.10.15.8.8.2.6 04-DTMT Area (cannot be completed u

100%

Excavation & Backfilling for Underground Services

21

04-09-2013 A

27-11-2013 A

1205

100%

31
31

15-08-2013 A
15-08-2013 A

20-10-2013 A
20-10-2013 A

110
110

Install Underground Services


YARNIMA.10.15.8.8.2.1 09-STG 11kV North

100%

Excavation & Backfilling for Underground Services

Install Underground Services

10

23-09-2013 A

06-10-2013 A

100%

YARNIMA.10.15.8.8.2.2 12-HRSG1 11kV


A22470
Install Underground Services

30
10

08-10-2013 A
08-10-2013 A

28-11-2013 A
26-11-2013 A

120
0

100%

Install Underground Services

Excavation & Backfilling for Underground Services

30

22-10-2013 A

28-11-2013 A

120

100%

YARNIMA.10.15.8.8.2.3 14-GRE (started, partially complete)


A22220
Excavation & Backfilling for Underground Services

69
69

15-09-2013 A
15-09-2013 A

26-11-2013 A
20-11-2013 A

430
130

Excavation & Backfilling for Underground Services


YARNIMA.10.15.8.8.2.3 14-GRE (started, partially complete)

100%

54

26-09-2013 A

26-11-2013 A

300

100%

55
55

01-09-2013 A
01-09-2013 A

19-09-2013 A
11-09-2013 A

140
140

100%

10

04-09-2013 A

19-09-2013 A

100%

20
20

09-10-2013 A
09-10-2013 A

16-01-2014 A
16-01-2014 A

110
110

100%

Excavation & Backfilling for Underground Services - BSDG

14-10-2013 A

15-01-2014 A

100%

30
29
29

02-08-2013 A
07-08-2013 A
07-08-2013 A

06-03-2014
20-02-2014
20-02-2014

2604
1646
165

105
118
118

Install Underground Services (Conduits) - BSDG


YARNIMA.10.15.8.8.4 Yellow Phase (Refer to Ma
YARNIMA.10.15.8.8.4.1 03-Cooling Tower East

90%

Install Underground Services - CT East

21

09-08-2013 A

17-02-2014

1481

118

90%

YARNIMA.10.15.8.8.4.2 06-STG Area (started, partially complete)


A22270
Excavation & Backfilling for Underground Services

20
20

07-08-2013 A
07-08-2013 A

26-11-2013 A
26-11-2013 A

425
120

Install Underground Services - CT East


YARNIMA.10.15.8.8.4.2 06-STG Area (started, partially complete

100%

Excavation & Backfilling for Underground Services

12

13-08-2013 A

25-11-2013 A

305

100%

27
27

02-08-2013 A
02-08-2013 A

04-09-2013 A
30-08-2013 A

80
80

100%

16

06-08-2013 A

04-09-2013 A

100%

17
17

06-08-2013 A
06-08-2013 A

16-10-2013 A
16-10-2013 A

140
140

100%

10

20-08-2013 A

03-10-2013 A

100%

26
24

06-08-2013 A
06-08-2013 A

06-03-2014
06-03-2014

313
110

105
105

90%

Excavation & Backfilling for Underground Services

21

08-08-2013 A

03-03-2014

203

105

90%

238
34
34

22-03-2013 A
09-09-2013 A
09-09-2013 A

25-02-2014
20-12-2013 A
20-12-2013 A

4576
199
135

112

Install Underground Services - GTG1


YARNIMA.10.15.8.8.3 Purple Phase (Refer to Mar
YARNIMA.10.15.8.8.3.1 08-Tank Area and Culverts

21

15-09-2013 A

19-12-2013 A

64

100%

48
10

04-07-2013 A
04-07-2013 A

13-11-2013 A
20-10-2013 A

405
190

100%

24-07-2013 A

13-11-2013 A

215

100%

21
21

09-09-2013 A
09-09-2013 A

19-02-2014
19-02-2014

185
185

119
119

90%

Excavation & Backfilling for Underground Services -

10

10-09-2013 A

16-02-2014

119

90%

21
10

25-08-2013 A
25-08-2013 A

11-12-2013 A
09-12-2013 A

180
0

Install Underground Services - HRSG 2 Switchroom


YARNIMA.10.15.8.8.3.4 18-HRSG3 Switchroom

100%

Install Underground Services

YARNIMA.10.15.8.8.1.3 10-STG 11KV South


A22150
Excavation & Backfilling for Underground Services
A22420

Install Underground Services

YARNIMA.10.15.8.8.1.4 19-GT2 Services


A22160
Excavation & Backfilling for Underground Services
A22430

Install Underground Services

YARNIMA.10.15.8.8.1.5 22-BSDG East


A22170
Excavation & Backfilling for Underground Services - BSDG East
A22440

Install Underground Services (Conduits) - BSDG East

105
YARNIMA.10.15.8.8.2 Orange Phase (Refer to Marked up Burried Services Drawing)
YARNIMA.10.15.8.8.2.6 04-DTMT Area (cannot be completed until DTMT are out of this area)31
A22190
Excavation & Backfilling for Underground Services
31
A22450

Install Underground Services

YARNIMA.10.15.8.8.2.1 09-STG 11kV North


A22200
Excavation & Backfilling for Underground Services
A22460

A22210

A22480

Install Underground Services

YARNIMA.10.15.8.8.2.4 15-GT2 11kV (started, partially complete)


A22230
Excavation & Backfilling for Underground Services
A22490

Install Underground Services

YARNIMA.10.15.8.8.2.5 23-BSDG Area


A22240
Excavation & Backfilling for Underground Services - BSDG
A22500

Install Underground Services (Conduits) - BSDG

YARNIMA.10.15.8.8.4 Yellow Phase (Refer to Marked up Burried Services Drawing)


YARNIMA.10.15.8.8.4.1 03-Cooling Tower East
A22260
Excavation & Backfilling for Underground Services - CT East
A22510

A22520

Install Underground Services

YARNIMA.10.15.8.8.4.3 07-STG Switchroom


A22280
Excavation & Backfilling for Underground Services
A22530

Install Underground Services

YARNIMA.10.15.8.8.4.4 13-GT1 11kV (started, partially complete)


A22290
Excavation & Backfilling for Underground Services
A22540

Install Underground Services

YARNIMA.10.15.8.8.4.5 16-GT1 Services


A15720
Excavation & Backfilling for Underground Services - GTG1
A15730

Install Underground Services - GTG1

YARNIMA.10.15.8.8.3 Purple Phase (Refer to Marked up Burried Services Drawing)


YARNIMA.10.15.8.8.3.1 08-Tank Area and Culverts
A22320
Excavation & Backfilling for Underground Services
A22570

Install Underground Services

YARNIMA.10.15.8.8.3.2 11-HRSG1 Switchroom


A22330
Excavation & Backfilling for Underground Services
A22580

Install Underground Services

YARNIMA.10.15.8.8.3.3 17-HRSG2 Switchroom


A22340
Excavation & Backfilling for Underground Services - HRSG 2 Switchroom
A22590

Install Underground Services - HRSG 2 Switchroom

YARNIMA.10.15.8.8.3.4 18-HRSG3 Switchroom


A22600
Install Underground Services

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 16 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Total
Float

Activity % S
Complete

YARNIMA.10.15.8.8.1.3 10-STG 11KV South


Excavation & Backfilling for Underground Services
Install Underground Services
YARNIMA.10.15.8.8.1.4 19-GT2 Services
Excavation & Backfilling for Underground Services
Install Underground Services
YARNIMA.10.15.8.8.1.5 22-BSDG East

Install Underground Services


YARNIMA.10.15.8.8.2.2 12-HRSG1 11kV

Excavation & Backfilling for Underground Services


Install Underground Services
YARNIMA.10.15.8.8.2.4 15-GT2 11kV (started, partially complete)
Excavation & Backfilling for Underground Services
Install Underground Services
YARNIMA.10.15.8.8.2.5 23-BSDG Area

Excavation & Backfilling for Underground Services -

Install Underground Services


YARNIMA.10.15.8.8.4.3 07-STG Switchroom
Excavation & Backfilling for Underground Services
Install Underground Services
YARNIMA.10.15.8.8.4.4 13-GT1 11kV (started, partially complete)
Excavation & Backfilling for Underground Services
Install Underground Services
YARNIMA.10.15.8.8.4.5 16-GT1 Services

100%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Excavation & Backfilling for Underground Services


Install Underground Services
YARNIMA.10.15.8.8.3.2 11-HRSG1 Switchroom
Excavation & Backfilling for Underground Services
Install Underground Services
YARNIMA.10.15.8.8.3.3 17-HRSG2 Switchroom

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Excavation & Backfilling for Underground Services

21

06-09-2013 A

11-12-2013 A

180

YARNIMA.10.15.8.8.3.5 20-GT3 Services


A3340
Excavation & Backfilling for Underground Services

65
25

28-08-2013 A
28-08-2013 A

25-02-2014
25-02-2014

287
120

NCR-S213 BOP: Line 3- Drain Pit on West Side of Lube Oil Cooler Installed In Wrong Orientation2

01-09-2013 A

02-09-2013 A

A3520

15

05-09-2013 A

21-02-2014

167

53
31

22-03-2013 A
22-03-2013 A

29-01-2014 A
29-01-2014 A

2095
190

100%

24

27-03-2013 A

27-01-2014 A

1905

100%

NCR-S083 BOP: Potable water Line - Incorrect SDR used for 63nb & 90nb HDPE pipe

16

19-05-2013 A

04-06-2013 A

100%

BOP: Potable water Line - Incorrect SDR used for 63nb & 90nb HDPE pipe

NCR-S091 STG1: Conduit on the North side of STG is clashing to the Pipe Riser

12

28-05-2013 A

09-06-2013 A

100%

30
30

09-11-2013 A
09-11-2013 A

07-01-2014 A
07-01-2014 A

769
105

STG1: Conduit on the North side of STG is clashing to the Pipe Riser
YARNIMA.10.15.8.8.3.7 21-Firewater

100%

21

11-11-2013 A

06-01-2014 A

664

100%

30
30

14-01-2014 A
14-01-2014 A

31-01-2014 A
31-01-2014 A

456
125

100%

Excavation & Backfilling for Underground Services

21

16-01-2014 A

30-01-2014 A

331

100%

20
20
20

26-02-2014
26-02-2014
26-02-2014*

18-03-2014
18-03-2014
18-03-2014

95
95
95

94
94
94

Install Underground Services


YARNIMA.10.15.8.8.5 Blue Phase (Refer to Ma
YARNIMA.10.15.8.8.5.1 02-Lighting (side wide,

0%

10

03-03-2014

13-03-2014

99

0%

260
20

30-06-2013 A
15-07-2013 A

27-04-2014
26-09-2013 A

36569
1533

57

13

12-08-2013 A

25-08-2013 A

A22350

Install Underground Services

YARNIMA.10.15.8.8.3.6 24-West Services Trench


A15680
Excavation & Backfilling for Underground Services
A15690

Install Underground Services

YARNIMA.10.15.8.8.3.7 21-Firewater
A22310
Excavation & Backfilling for Underground Services
A22560

Install Underground Services

YARNIMA.10.15.8.8.3.8 05-Firewater East


A22140
Excavation & Backfilling for Underground Services
A22410

Install Underground Services

YARNIMA.10.15.8.8.5 Blue Phase (Refer to Marked up Burried Services Drawing)


YARNIMA.10.15.8.8.5.1 02-Lighting (side wide, done by electrical using ditch witch)
A22380
Excavation & Backfilling for Underground Services
A22630

Install Underground Services for Site lighting

YARNIMA.10.15.8.6 ABOVEGROUND PIPING


A13530
Install Phase 2 Piperack (North-South)
NCR-S188

BOP: United Industries Beams Missing Bolt Holes

A13530-a

Install Phase 2 Piperack (East-West)

YARNIMA.10.15.8.6.1 Delivery of Pipes


A13530-a30 Gas Piping-EKG

Total
Float

Activity % S
Complete

100%
94
94

90%

Excavation & Backfilling for Underground Services


Install Underground Services
YARNIMA.10.15.8.8.3.8 05-Firewater East

Excavation & Backfilling for Underground Service

Install Underground Services for Site lighting


YARNIMA.10.15.8.6 ABOVEGROUND PI

100%

Install Phase 2 Piperack (North-South)

100%

BOP: United Industries Beams Missing Bolt Holes

517

03-03-2014
30-06-2013 A

0
0

13-08-2013 A

100%

100%

Condensate Piping-LCA

100%

Diesel Fuel Supply Pipign-EGD

100%

Condensate Piping-LCA

16-07-2013 A

A13530-a70

Excavation & Backfilling for Underground Services

24-10-2013 A

A13530-a10

Install Underground Services

11-09-2013 A

10-07-2013 A

Install Underground Services


YARNIMA.10.15.8.8.3.6 24-West Services Trench

30-06-2013 A
30-06-2013 A

BOP: Line 3- Drain Pit on West Side of Lube Oil Cooler Installed In Wrong Orie

90%

21

Compressed Air Piping-QFB

Excavation & Backfilling for Underground Services

209
0

A13530-a60

Excavation & Backfilling for Underground Services


YARNIMA.10.15.8.8.3.5 20-GT3 Services

100%
94

100%

Install Phase 2 Piperack (East-West)


YARNIMA.10.15.8.6.1 Delivery of Pipes

108
100%

Gas Piping-EKG
Compressed Air Piping-QFB

Diesel Fuel Supply Pipign-EGD

16-07-2013 A

A13530-a100 Delivery of High Pressure Steam Piping-LBA

43

23-09-2013 A

A13530-a20

Delivery of Permeate System Piping-GCF

06-12-2013 A

100%

Delivery of Permeate System Piping-GCF

A13530-a40

Delivery of Cooling Water Piping-PCB-PCA

06-12-2013 A

100%

Delivery of Cooling Water Piping-PCB-PCA

A13530-a80

Delivery of Demineralization Piping-GCK

06-12-2013 A

100%

Delivery of Demineralization Piping-GCK

A13530-a90

Delivery of Chemical Dosing Piping

03-03-2014*

78

0%

185
70

01-10-2013 A
01-10-2013 A

03-04-2014
24-03-2014

18860
14392

79
79

44%

YARNIMA.10.15.8.6.3 High Pressure Steam Piping-LBA


A13540
Install High Pressure Steam Pipe Supports- Pipelines & Valves

16-01-2014 A

Delivery of High Pressure Steam Piping-LBA

Delivery of Chemical Dosing Piping


YARNIMA.10.15.8.6.3 High Pressure Steam

Install High Pressure Steam Pipe Supports- Pip

A13540-a

Insulation of the Pipes (Post Steam Blow)

30

03-03-2014

03-04-2014

4468

79

0%

A13550

Test Pipelines (Pre Steam Blow)

25-03-2014

29-03-2014

79

0%

159
35

15-08-2013 A
15-08-2013 A

27-03-2014
21-03-2014

909
909

86
86

68.5%

Install Condensate Pipe Supports Pipelines & V

23-03-2014

27-03-2014

86

0%

138
30

18-09-2013 A
18-09-2013 A

19-03-2014
14-03-2014

1088
1088

93
93

Test Pipelines
YARNIMA.10.15.8.6.5 Demineralization Piping-

67%

Install Demineralization Pipe Supports Pipelines &

15-03-2014

19-03-2014

93

0%

186
25

15-08-2013 A
15-08-2013 A

28-03-2014
23-03-2014

1554
1554

85
85

Test Pipelines
YARNIMA.10.15.8.6.6 Diesel Fuel Supply Pipin

64%

YARNIMA.10.15.8.6.4 Condensate Piping-LCA


A16950
Install Condensate Pipe Supports Pipelines & Valves
A16300

Test Pipelines

YARNIMA.10.15.8.6.5 Demineralization Piping-GCK


A13980
Install Demineralization Pipe Supports Pipelines & Valves
A13990

Test Pipelines

YARNIMA.10.15.8.6.6 Diesel Fuel Supply Piping-EGD


A16270
Install Diesel Fuel Pipe Supports Pipelines & Valves
NCR-S207

BOP: Diesel Line EKD requires an additional support

29-08-2013 A

01-09-2013 A

NCR-S285

BOP: C1034-NCR-S285-EGD-Damaged Flange Face on Diesel Line - T2174 Yarnima


13

A16320

Test Pipelines

YARNIMA.10.15.8.6.7 Compressed Air Piping-QFB


NCR-S154
HRSG3: HRSG Pipe Supports

Insulation of the Pipes (Post Steam Blow)

Test Pipelines (Pre Steam Blow)


YARNIMA.10.15.8.6.4 Condensate Piping-LCA

Install Diesel Fuel Pipe Supports Pipelines & Va

100%

14-10-2013 A

27-10-2013 A

24-03-2014

28-03-2014

85

178
9

21-07-2013 A
21-07-2013 A

28-02-2014
30-07-2013 A

2209
0

111

BOP: Diesel Line EKD requires an additional support

100%

BOP: C1034-NCR-S285-EGD-Damaged Flange Face on Diesel Line

0%

Test Pipelines
YARNIMA.10.15.8.6.7 Compressed Air Piping-QFB

100%

HRSG3: HRSG Pipe Supports

A16280

Install Compressed Air Pipe Supports Pipelines & Valves

26-07-2013 A

23-02-2014

2209

111

53%

Install Compressed Air Pipe Supports Pipelines & Va

A16330

Test Pipelines

24-02-2014

28-02-2014

111

0%

133
64

26-09-2013 A
26-09-2013 A

19-03-2014
14-03-2014

1439
1439

93
93

Test Pipelines
YARNIMA.10.15.8.6.8 Permeate System Piping

58%

Install Permeate Pipe Supports Pipelines & Valve

01-11-2013 A

01-11-2013 A

YARNIMA.10.15.8.6.8 Permeate System Piping-GCF


A16580
Install Permeate Pipe Supports Pipelines & Valves
NCR-S332

GTG3 Permeate Water Line Tie In

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 17 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

100%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

GTG3 Permeate Water Line Tie In


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

NCR-S388

GTG1 & GTG2 Permeate Water Line Tie-in

02-01-2014 A

02-01-2014 A

A16590

Test Pipelines

15-03-2014

19-03-2014

93

0%

179
40

03-11-2013 A
03-11-2013 A

27-04-2014
22-04-2014

1949
1949

57
57

34%

23-04-2014

27-04-2014

57

0%

146
70

16-07-2013 A
16-07-2013 A

13-02-2014
17-01-2014 A

1391
1391

125

09-02-2014

13-02-2014

125

0%

201
25

17-09-2013 A
17-09-2013 A

26-04-2014
22-04-2014

4085
4085

58
58

50%

22-04-2014

26-04-2014

58

0%

30
25

03-03-2014
03-03-2014

04-04-2014
30-03-2014

0
0

78
78

Test Pipelines
YARNIMA.10.15.8.6.10 Chemical Dosing (Va

0%

Install Chemical Dosing Pipe Supports Pipeline

30-03-2014

04-04-2014

78

0%

182
25

17-09-2013 A
17-09-2013 A

06-04-2014
01-04-2014

1035
1035

77
77

Test Pipelines
YARNIMA.10.15.8.6.11 Miscellaneous UGP

24%

Install Miscellaneous UGP

01-04-2014

06-04-2014

77

0%

40
30

03-07-2013 A
03-07-2013 A

17-01-2014 A
15-01-2014 A

427
130

100%

YARNIMA.10.15.8.6.2 Cooling Water Piping-PAB


A21460
Install Cooling Pipe Supports Pipelines & Valves
A21470

Test Pipelines

YARNIMA.10.15.8.6.9 Gas Piping-EKG


A21480
Install Gas Pipe Supports Pipelines & Valves
A21490

Test Gas Pipelines - EKG

YARNIMA.10.15.8.6.12 Drain Piping-PCB-MAL


A22970
Install Drain Water Piping - All Areas
A22980

Test Pipelines

YARNIMA.10.15.8.6.10 Chemical Dosing (Variation)


A21500
Install Chemical Dosing Pipe Supports Pipelines & Valves
A21510

Test Pipelines

YARNIMA.10.15.8.6.11 Miscellaneous UGP


A22950
Install Miscellaneous UGP
A22960

Test Pipelines

YARNIMA.10.15.8.2 UNDERGROUND PITS


A9250
Excavation for Underground Pits

100%

Install Underground Pits

30

23-07-2013 A

07-01-2014 A

207

100%

A9270

Backfill & Compaction

30

30-07-2013 A

17-01-2014 A

90

100%

208
28

20-05-2013 A
20-05-2013 A

24-03-2014
03-03-2014

2370
130

89
89

45%

A9290

Install Conduits

28

30-05-2013 A

16-03-2014

2150

89

83.5%

A9300

Backfill & Compaction

30

06-06-2013 A

24-03-2014

90

89

40%

NCR-S202

BOP: Water Treatment Plant Underground Services Drawings

25-08-2013 A

31-08-2013 A

TQ540-A9300

TQ540 Use of Stabilised Sand as Backfill Material

YARNIMA.10.15.14 CIVILS
YARNIMA.10.15.14.3 BSDG FOUNDATIONS
A2940
Excavation - BSDG Foundations

03-11-2013 A

04-11-2013 A

111
77
4

18-07-2013 A
31-10-2013 A
31-10-2013 A

16-02-2014
16-02-2014
08-01-2014 A

2127
674
13

Test Pipelines
YARNIMA.10.15.8.6.2 Cooling Water Pip

Install Cooling Pipe Supports Pipelines & Va


Test Pipelines
YARNIMA.10.15.8.6.9 Gas Piping-EKG

100%

A9260

YARNIMA.10.15.8.4 UNDERGROUND ELECTRICAL CONDUITS


A9280
Trenching & Excavation for Conduits

GTG1 & GTG2 Permeate Water Line Tie-in

Install Gas Pipe Supports Pipelines & Valves

Test Gas Pipelines - EKG


YARNIMA.10.15.8.6.12 Drain Piping-PCB
Install Drain Water Piping - All Areas

Test Pipelines
YARNIMA.10.15.8.2 UNDERGROUND PITS
Excavation for Underground Pits
Install Underground Pits

Backfill & Compaction


YARNIMA.10.15.8.4 UNDERGROUND ELECT
Trenching & Excavation for Conduits
Install Conduits
Backfill & Compaction

100%

BOP: Water Treatment Plant Underground Services Drawings

100%

TQ540 Use of Stabilised Sand as Backfill Material


YARNIMA.10.15.14 CIVILS
YARNIMA.10.15.14.3 BSDG FOUNDATIONS

91
91
100%

Excavation - BSDG Foundations

A15840

S15 Lean Concrete Blinding - BSDG Foundations

05-11-2013 A

13-01-2014 A

21

100%

S15 Lean Concrete Blinding - BSDG Foundations

A15850

Reinforcement and Shuttering - BSDG Foundations

06-11-2013 A

16-01-2014 A

241

100%

Reinforcement and Shuttering - BSDG Foundations

A15860

N32 Concrete for Foundation and Curing - BSDG Foundations

27-01-2014 A

16-02-2014

394

91

100%

A2820

Backfill and Compaction - BSDG Foundations

28-01-2014 A

09-02-2014

94

95%

YARNIMA.10.15.14.1 COOLING WATER PUMP FOUNDATIONS


A15870
Excavation

20
4

01-10-2013 A
01-10-2013 A

05-11-2013 A
05-10-2013 A

1221
35

N32 Concrete for Foundation and Curing - BSDG Fo


Backfill and Compaction - BSDG Foundations
YARNIMA.10.15.14.1 COOLING WATER PUMP FOUNDATIONS

100%

Excavation

A15880

S15 Lean Concrete Blinding

06-10-2013 A

08-10-2013 A

11

100%

S15 Lean Concrete Blinding

A15890

Reinforcement and Shuttering

08-10-2013 A

15-10-2013 A

177

100%

A15900

N32 Concrete for Foundation and Curing

16-10-2013 A

30-10-2013 A

985

100%

A2930

Backfill and Compaction

20-10-2013 A

05-11-2013 A

13

100%

14
1

18-07-2013 A
18-07-2013 A

31-08-2013 A
24-07-2013 A

232
3

100%

YARNIMA.10.15.14.2 AUXILIARY COOLING WATER PUMP FOUNDATIONS


A15910
Excavation

Reinforcement and Shuttering


N32 Concrete for Foundation and Curing

Backfill and Compaction


YARNIMA.10.15.14.2 AUXILIARY COOLING WATER PUMP FOUNDATIONS
Excavation

A15920

S15 Lean Concrete Blinding

25-07-2013 A

30-07-2013 A

100%

A15930

Reinforcement and Shuttering

01-08-2013 A

17-08-2013 A

177

100%

A15940

N32 Concrete for Foundation and Curing

19-08-2013 A

27-08-2013 A

47

100%

N32 Concrete for Foundation and Curing

A2990

Backfill and Compaction

28-08-2013 A

31-08-2013 A

100%

Backfill and Compaction

311
115
1

02-03-2013 A
20-07-2013 A
20-07-2013 A

14-03-2014
10-12-2013 A
21-07-2013 A

26774
2444
28

VEGT2000

VE GTG 2 - (electircal modifications, Pipe fitting for Siemens pipework outside & inside38
GT2 enclosure)
11-08-2013 A

19-09-2013 A

701

100%

VE GTG 2 - (electircal modifications, Pipe fitting for Siemens pipework outsid

NCR-S234

GTG2 Enclosure Structure - Fitment Issues

13-09-2013 A

19-09-2013 A

100%

GTG2 Enclosure Structure - Fitment Issues

NCR-S246

GTG2 Fitment Issues

19

18-09-2013 A

08-10-2013 A

100%

NCR-S247

GTG2 Pipe Support Fitment Issues

18-09-2013 A

27-09-2013 A

100%

VEGT2010

GTG 2 (Pipe fitting outside GT2 enclosure, Install Donaldson Elect Equip, Install HV Terminal
57
Box,
26-09-2013
ElectricalAworks)25-11-2013 A

1695

100%

NCR-S345

GTG2 Silencer Duct Clash with Enclosure Steelwork

24

15-11-2013 A

10-12-2013 A

100%

NCR-S346

GTG2 Enclosure Roof Flashing

24

15-11-2013 A

10-12-2013 A

100%

YARNIMA.10.15.2 GAS TURBINE 2 & ASSOCIATED EQUIPMENT


YARNIMA.10.15.2.3 GTG2 - ACTUAL VARIATIONS & NON SCOPE WORKS
NCR-S164
Modify Client Supply Material - Diffuser leg bolts and location pin holes

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 18 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

S15 Lean Concrete Blinding


Reinforcement and Shuttering

YARNIMA.10.15.2 GAS TURBINE 2 & ASSOCIA


YARNIMA.10.15.2.3 GTG2 - ACTUAL VARIATIONS & NON SC

98
100%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Modify Client Supply Material - Diffuser leg bolts and location pin holes

GTG2 Fitment Issues


GTG2 Pipe Support Fitment Issues

GTG 2 (Pipe fitting outside GT2 enclosure, Install Donaldson Elect


GTG2 Silencer Duct Clash with Enclosure Steelwork
GTG2 Enclosure Roof Flashing
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name
NCR-S363

Original
Duration

Start

Finish

GTG2 Ventilation Outlet Unit - No Allowance for Grout

Budgeted
Labor Units

Total
Float

Activity % S
Complete

01-12-2013 A

03-12-2013 A

100%

GTG2 Ventilation Outlet Unit - No Allowance for Grout

NCR-S363-1522 GTG2 Ventilation Outlet Unit - No Allowance for Grout - Rectification

04-12-2013 A

04-12-2013 A

20

100%

GTG2 Ventilation Outlet Unit - No Allowance for Grout - Rectifica

NCR-S365

06-12-2013 A

07-12-2013 A

100%

257
257

02-03-2013 A
02-03-2013 A

17-01-2014 A
17-01-2014 A

10924
0

GTG1: GT1 Air Intake Platform seeking mods


YARNIMA.10.15.2.1 MECHANICAL GT2

100%

11
5

02-03-2013 A
02-03-2013 A

16-03-2013 A
16-03-2013 A

100
100

100%

GTG1: GT1 Air Intake Platform seeking mods

YARNIMA.10.15.2.1 MECHANICAL GT2


A12660
GT2 Installation WBS Summary
YARNIMA.10.15.2.1.2 Prepare Foundations & Fixators
A14510
Prepare Foundations & Fixators
A18070

1. Clean the concrete- steel embeds and grout pockets

02-03-2013 A

05-03-2013 A

100%

A18080

2. Setup GT skid support tools as per drawing and set heights

07-03-2013 A

10-03-2013 A

100%

A18090

3. Mark out XY axis for plump bob

11-03-2013 A

16-03-2013 A

100%

4
21-07-2013
YARNIMA.10.15.2.1.3 Placement of Gear Box & Remove Transport Protection (GT, Gearbox, Generator
& Diffuser) A
A14520
Placement of Gear Box & Remove Transport Protection
4
21-07-2013 A

25-07-2013 A
25-07-2013 A

250
250

100%

YARNIMA.10.15.2.1.4 Placement of GT & Lube oil Skid


A14530
Placement of GT

GT2 Installation WBS Summary


YARNIMA.10.15.2.1.2 Prepare Foundations & Fixators
Prepare Foundations & Fixators
1. Clean the concrete- steel embeds and grout pockets
2. Setup GT skid support tools as per drawing and set heights
3. Mark out XY axis for plump bob
YARNIMA.10.15.2.1.3 Placement of Gear Box & Remove Transport Protection (GT,
Placement of Gear Box & Remove Transport Protection
YARNIMA.10.15.2.1.4 Placement of GT & Lube oil Skid

139
9

10-05-2013 A
10-05-2013 A

06-10-2013 A
27-06-2013 A

190
190

100%

Placement of GT

10-05-2013 A

26-06-2013 A

100%

1. Place GT skid on foundation tooling- plumb to XY axis- grout once skid is aligned
2. Once GT is aligned & grouted- lift lube oil skid into position

A18110

1. Place GT skid on foundation tooling- plumb to XY axis- grout once skid is aligned

A18120

2. Once GT is aligned & grouted- lift lube oil skid into position

11-05-2013 A

27-06-2013 A

100%

NCR-S258

GTG3: Misalignment Fin Fan Drives

14

22-09-2013 A

06-10-2013 A

100%

65
5

15-07-2013 A
15-07-2013 A

02-09-2013 A
02-09-2013 A

190
190

100%

15-07-2013 A

28-07-2013 A

100%

NCR-S164-731GTG2 Diffuser Leg Bolts and Location Pin Holes

42

28-07-2013 A

31-08-2013 A

100%

A18140

2. Lift diffuser- mount legs and plates

30-07-2013 A

31-07-2013 A

100%

2. Lift diffuser- mount legs and plates

A18150

3. Lower diffuser onto foundation- plumb centreline & flange face- place on pedastals 3

30-07-2013 A

02-08-2013 A

100%

21
9

29-07-2013 A
29-07-2013 A

12-08-2013 A
08-08-2013 A

380
380

3. Lower diffuser onto foundation- plumb centreline & flange face- place on pedasta
YARNIMA.10.15.2.1.6 Connect Diffuser

YARNIMA.10.15.2.1.5 Placement and alignment of Diffuser


A14540
Placement of Diffuser
A18130

1. Mark out foundation axis- and distance from turbine flange to diffuser flange

YARNIMA.10.15.2.1.6 Connect Diffuser


A14600
Connect Diffuser

GTG3: Misalignment Fin Fan Drives


YARNIMA.10.15.2.1.5 Placement and alignment of Diffuser
Placement of Diffuser
1. Mark out foundation axis- and distance from turbine flange to diffuser flange
GTG2 Diffuser Leg Bolts and Location Pin Holes

100%

Connect Diffuser

A18160

1. Install and torque inner and outer diffuser rings (Require Scaffold)

02-08-2013 A

05-08-2013 A

100%

1. Install and torque inner and outer diffuser rings (Require Scaffold)

NCR-S179

GTG2: Bleed Air System Piping Components Dimensional Mismatch

05-08-2013 A

12-08-2013 A

100%

GTG2: Bleed Air System Piping Components Dimensional Mismatch

A18170

2. Carry out fine alignments of diffuser

06-08-2013 A

06-08-2013 A

100%

2. Carry out fine alignments of diffuser

A18180

3. Weld diffuser pedestals and feet

07-08-2013 A

08-08-2013 A

100%

14
2

26-07-2013 A
26-07-2013 A

02-08-2013 A
02-08-2013 A

300
300

3. Weld diffuser pedestals and feet


YARNIMA.10.15.2.1.7 Install Liquid Fuel Unit

100%

Install Liquid Fuel Unit

28-07-2013 A

29-07-2013 A

100%

1. Place packers and survey heights- mark X-Y axis


2. Place LFU on foundation and fix with dynabolts
YARNIMA.10.15.2.1.8 Placement of Generator

YARNIMA.10.15.2.1.7 Install Liquid Fuel Unit


A14720
Install Liquid Fuel Unit
A18190

1. Place packers and survey heights- mark X-Y axis

A18200

2. Place LFU on foundation and fix with dynabolts

YARNIMA.10.15.2.1.8 Placement of Generator


A14550
Placement of Generator

30-07-2013 A

02-08-2013 A

100%

156
6

17-05-2013 A
17-05-2013 A

04-11-2013 A
04-08-2013 A

190
190

100%

Placement of Generator

A18210

1. Position generator feet- shims & wedges as per drawings

17-05-2013 A

01-06-2013 A

100%

A18220

2. Mark X-Y axis on foundation- set feet to correct height

28-07-2013 A

29-07-2013 A

100%

2. Mark X-Y axis on foundation- set feet to correct height

A18230

3. Place generator on feet- plumb to X-Y axis

29-07-2013 A

31-07-2013 A

100%

3. Place generator on feet- plumb to X-Y axis

A18240

4. Weld generator alignment tools to steel embeds

01-08-2013 A

04-08-2013 A

100%

4. Weld generator alignment tools to steel embeds

NCR-S298

GTG2 Generator Sole Plates Cast at Incorrect Level

18-10-2013 A

23-10-2013 A

100%

NCR-S334

GTG2 HV Terminal Box Installation

03-11-2013 A

04-11-2013 A

100%

33
12

28-07-2013 A
28-07-2013 A

13-09-2013 A
03-08-2013 A

500
500

YARNIMA.10.15.2.1.9 Preliminary Alignment of Modules


A14560
Preliminary Alignment of Modules

1. Position generator feet- shims & wedges as per drawings

GTG2 Generator Sole Plates Cast at Incorrect Level


GTG2 HV Terminal Box Installation
YARNIMA.10.15.2.1.9 Preliminary Alignment of Modules

100%

Preliminary Alignment of Modules

A18250

1. Align GT skid and check gearbox splitline flatness prior to grouting

28-07-2013 A

05-08-2013 A

100%

1. Align GT skid and check gearbox splitline flatness prior to grouting

A18260

2. Check alingment GT to Gearbox

28-07-2013 A

30-07-2013 A

100%

A18270

3. Carry out preliminary alignment Generator to Gearbox

03-08-2013 A

04-08-2013 A

100%

NCR-S211

GTG2 Generator Feet - Cast in Steel Plates Not Level

13

31-08-2013 A

13-09-2013 A

100%

66
6

19-05-2013 A
19-05-2013 A

24-09-2013 A
24-09-2013 A

150
150

100%

YARNIMA.10.15.2.1.10 Place Starter Motor


A14570
Place Starter Motor

2. Check alingment GT to Gearbox


3. Carry out preliminary alignment Generator to Gearbox
GTG2 Generator Feet - Cast in Steel Plates Not Level
YARNIMA.10.15.2.1.10 Place Starter Motor
Place Starter Motor

A18280

1. Lower starter onto plynth- 90 degrees out

01-08-2013 A

03-08-2013 A

100%

1. Lower starter onto plynth- 90 degrees out

A18290

2. Install coupling hub using Siemens special tool

04-08-2013 A

04-08-2013 A

100%

2. Install coupling hub using Siemens special tool

A18300

3. Lift motor- install and set mounting feet- mount motor in correct orientation

05-08-2013 A

20-08-2013 A

100%

A18310

4. Carry out alignment- starter motor to Gearbox - Weld Feet

11-08-2013 A

24-09-2013 A

100%

4
2

29-07-2013 A
29-07-2013 A

15-09-2013 A
15-09-2013 A

250
250

4. Carry out alignment- starter motor to Gearbox - Weld Feet


YARNIMA.10.15.2.1.11 Install CO2 Module

100%

Install CO2 Module

YARNIMA.10.15.2.1.11 Install CO2 Module


A14710
Install CO2 Module

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 19 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

3. Lift motor- install and set mounting feet- mount motor in correct orientation

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A18320

1. Mark out foundation- install and survey packers- anchor feet to foundation

29-07-2013 A

04-08-2013 A

100%

A18330

2. Install module onto feet

05-08-2013 A

15-09-2013 A

100%

67
18

20-05-2013 A
20-05-2013 A

22-09-2013 A
22-09-2013 A

1120
1120

100%

YARNIMA.10.15.2.1.12 Install Oil Coolers (Including Handrails, Ladders)


A14730
Install Oil Coolers

1. Mark out foundation- install and survey packers- anchor feet to foundation
2. Install module onto feet
YARNIMA.10.15.2.1.12 Install Oil Coolers (Including Handrails, Ladders)
Install Oil Coolers

A18340

1. Mark out foundation- install packers and survey

20-05-2013 A

21-05-2013 A

100%

1. Mark out foundation- install packers and survey

A18350

2. Place oil cooler unit on foundation

22-05-2013 A

23-05-2013 A

100%

2. Place oil cooler unit on foundation

A18370

4. Install handrails and access ladders

24-05-2013 A

20-07-2013 A

100%

A18360

3. Welding feet

08-08-2013 A

20-08-2013 A

100%

A18380

5. Install motors and fan blades

14-08-2013 A

22-09-2013 A

100%

80
52

23-07-2013 A
23-07-2013 A

11-12-2013 A
11-12-2013 A

400
400

100%

YARNIMA.10.15.2.1.13 Install Platforms & Access Stairways


A14690
Install Platforms and Access Stairways - GTG 2

4. Install handrails and access ladders


3. Welding feet
5. Install motors and fan blades
YARNIMA.10.15.2.1.13 Install Platforms & Access Stairways
Install Platforms and Access Stairways - GTG 2

A18390

1. Install internal platforms and access ladders/stair

27-07-2013 A

23-08-2013 A

100%

1. Install internal platforms and access ladders/stair

NCR-S182

GTG2 Enclosure Ladder Locating Brackets Incorrect

07-08-2013 A

16-08-2013 A

100%

GTG2 Enclosure Ladder Locating Brackets Incorrect

A18400

2. After installation of enclosure- install external access platforms- ladders/stairs

23-08-2013 A

11-12-2013 A

100%

11 ground)
20-05-2013 A
YARNIMA.10.15.2.1.14 Assemble Steel Enclosure (Pre-assemble steel enclosure modules on the
A14580
Assemble Steel Enclosure (Pre-assemble steel enclosure modules on the ground)
11
20-05-2013 A

12-09-2013 A
12-09-2013 A

450
450

2. After installation of enclosure- install external access platform


YARNIMA.10.15.2.1.14 Assemble Steel Enclosure (Pre-assemble steel enclo

100%

14
04-09-2013 A
YARNIMA.10.15.2.1.15 Placement of Steel Enclosure (Place and connect pre-assembled steel modules)
A14590
Placement of Steel Enclosure
14
04-09-2013 A

23-10-2013 A
23-10-2013 A

550
550

Assemble Steel Enclosure (Pre-assemble steel enclosure modules on the gro


YARNIMA.10.15.2.1.15 Placement of Steel Enclosure (Place and conn

YARNIMA.10.15.2.1.16 Install Cladding


A18430
1. Install upper angle brackets and intermediate "Z" sections

100%

59
3

13-10-2013 A
13-10-2013 A

11-12-2013 A
25-10-2013 A

2890
0

Placement of Steel Enclosure


YARNIMA.10.15.2.1.16 Install Cladding

100%

1. Install upper angle brackets and intermediate "Z" sections

A14610

Install Enclusure Pannels and Cladding Around Piping Penetrations

26

14-10-2013 A

11-12-2013 A

2890

100%

A18440

2. Mark out foundation and install lower wall panel channel mounts

16-10-2013 A

25-10-2013 A

100%

A18450

3. Install slurry wall mounting items and slurry wall between GT and Generator

20-10-2013 A

31-10-2013 A

100%

3. Install slurry wall mounting items and slurry wall between GT and G

A18460

4. Install outer wall panels- door frames- doors and flashing

23-10-2013 A

04-12-2013 A

100%

4. Install outer wall panels- door frames- doors and flashing

A18470

5. Install roof cladding - GTG 2

07-11-2013 A

11-12-2013 A

100%

65
28

04-09-2013 A
04-09-2013 A

11-12-2013 A
11-12-2013 A

312
312

5. Install roof cladding - GTG 2


YARNIMA.10.15.2.1.17 Install Ventilation Ducts, Platform & Acc

100%

Install Ventilation Ducts- Platform & Access Ladder - GTG 2

YARNIMA.10.15.2.1.17 Install Ventilation Ducts, Platform & Access Ladder


A14650
Install Ventilation Ducts- Platform & Access Ladder - GTG 2

Install Enclusure Pannels and Cladding Around Piping Penetrati


2. Mark out foundation and install lower wall panel channel mounts

A18480

1. Assemble and install generator cooling ducts and elbow within enclosure

04-09-2013 A

10-09-2013 A

100%

A18490

2. Install remaining generator cooling ducts and supports

09-09-2013 A

16-09-2013 A

100%

2. Install remaining generator cooling ducts and supports

A18520

3. Install enclosure ventilation outlet

10

15-09-2013 A

20-09-2013 A

100%

3. Install enclosure ventilation outlet

A18530

4. Generator Enclosure Inlet and Outlet

22-09-2013 A

03-11-2013 A

100%

A18500

5. Install generator cooling unit- platform and access ladder

05-10-2013 A

03-12-2013 A

100%

A18510

6. Install enclosure ventilation inlet - GTG 2

25-10-2013 A

11-12-2013 A

100%

3
3

25-09-2013 A
25-09-2013 A

30-10-2013 A
30-10-2013 A

250
250

100%

100%

YARNIMA.10.15.2.1.18 Install Fuel Gas Skid


A14630
Install Fuel Gas Skid
A18540

1. Install packers- survey and mark out foundation.

25-09-2013 A

26-09-2013 A

A18550

2. Place and anchor fuel gas skid.

26-09-2013 A

30-10-2013 A

100%

27-08-2013 A
YARNIMA.10.15.2.1.19 Assemble Intake Support Structure (Assemble support structure on the51
ground)
A14660
Assemble Intake Support Structure
13
27-08-2013 A

20-11-2013 A
20-11-2013 A

275
275

100%

1. Assemble and install generator cooling ducts and elbow within enclosure

4. Generator Enclosure Inlet and Outlet


5. Install generator cooling unit- platform and access ladder
6. Install enclosure ventilation inlet - GTG 2
YARNIMA.10.15.2.1.18 Install Fuel Gas Skid
Install Fuel Gas Skid
1. Install packers- survey and mark out foundation.

2. Place and anchor fuel gas skid.


YARNIMA.10.15.2.1.19 Assemble Intake Support Structure (Asse
Assemble Intake Support Structure

NCR-S269

GTG2: Multiple mods to Air Intake Support Structure - Misaligned Holes/Clashing & Cleat
2 Welded
30-09-2013
in WrongAPosition
01-10-2013 A

100%

GTG2: Multiple mods to Air Intake Support Structure - Misaligned Holes/Cl

NCR-S271

GTG2: Air Intake Inlet Hood - Damaged Louvers on Inlet Hood after being removed from
4 Packaging
01-10-2013 A

04-10-2013 A

100%

GTG2: Air Intake Inlet Hood - Damaged Louvers on Inlet Hood after being

NCR-S277

GTG3: GT2 -Air intake fitment issues- GT Ventilation Inlet holes not drilled

18

08-10-2013 A

26-10-2013 A

100%

GTG3: GT2 -Air intake fitment issues- GT Ventilation Inlet holes not dri

NCR-S289

GTG2: GT2 Air Intake Support Structure - End Plate Clashing with the Gridmesh

14-10-2013 A

16-10-2013 A

100%

GTG2: GT2 Air Intake Support Structure - End Plate Clashing with the G

NCR-S309

GTG2 Air Intake Beam Welded Splice Join

15

23-10-2013 A

07-11-2013 A

100%

GTG2 Air Intake Beam Welded Splice Join

NCR-S335

GTG2: GT2 Assembly Intake - Unable to Fit Assembly Line into Module

06-11-2013 A

09-11-2013 A

100%

YARNIMA.10.15.2.1.20 Lift Air Intake Structure into Place


A14670
Lift Air Intake Structure into Place

7
7

23-10-2013 A
23-10-2013 A

21-11-2013 A
21-11-2013 A

300
300

GTG2: GT2 Assembly Intake - Unable to Fit Assembly Line into Mod
YARNIMA.10.15.2.1.20 Lift Air Intake Structure into Place

100%

YARNIMA.10.15.2.1.21 Lift & Install Remaining Air Intake Modules


A14700
Lift & Install Remaining Air Intake Modules

22
22

12-10-2013 A
12-10-2013 A

23-11-2013 A
23-11-2013 A

750
750

Lift Air Intake Structure into Place


YARNIMA.10.15.2.1.21 Lift & Install Remaining Air Intake Module

100%

Lift & Install Remaining Air Intake Modules

A18580

1. Lift & Install Remaining Air Intake Modules

02-11-2013 A

06-11-2013 A

100%

1. Lift & Install Remaining Air Intake Modules

A18590

2. Install Evaporative Cooler Pipe Work/Pumps etc.

07-11-2013 A

23-11-2013 A

100%

YARNIMA.10.15.2.1.22 Install Air Filters and Evaporative Cooling Media


A14680
Install Air Filters & Evaporator Media - GTG 2

5
5

01-10-2013 A
01-10-2013 A

20-12-2013 A
20-12-2013 A

187
187

2. Install Evaporative Cooler Pipe Work/Pumps etc.


YARNIMA.10.15.2.1.22 Install Air Filters and Evaporative Coo

100%

YARNIMA.10.15.2.1.23 Install Fire Extinguisher & Equipment


A14750
Install Fire Extinguisher & Equipment - GTG 2

29
21

30-10-2013 A
30-10-2013 A

14-01-2014 A
14-01-2014 A

250
250

Install Air Filters & Evaporator Media - GTG 2


YARNIMA.10.15.2.1.23 Install Fire Extinguisher & Equipm

100%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 20 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Install Fire Extinguisher & Equipment - GTG 2


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A18610

1. Install CO2 bottles in skid.

01-11-2013 A

29-11-2013 A

100%

1. Install CO2 bottles in skid.

A18620

2. Remove nozzles- horns- cap and pressure test- reinstall nozzles and horns

07-11-2013 A

29-11-2013 A

100%

2. Remove nozzles- horns- cap and pressure test- reinstall nozzle

A18630

3. Setup counterweights and connect hoses - GTG 2

12-11-2013 A

16-12-2013 A

100%

39
8

16-10-2013 A
16-10-2013 A

17-01-2014 A
20-12-2013 A

500
0

3. Setup counterweights and connect hoses - GTG 2


YARNIMA.10.15.2.1.24 Final GTG Alignment

100%

1. Final GTG Alignment - GTG 2

YARNIMA.10.15.2.1.24 Final GTG Alignment


A18810
1. Final GTG Alignment - GTG 2
A14770

Final Alignment - GTG 2

22-11-2013 A

17-01-2014 A

500

100%

A18790

2. Place Coupling Units Inside Enclosure - GTG 2

26-11-2013 A

20-12-2013 A

100%

3
3

28-10-2013 A
28-10-2013 A

22-12-2013 A
22-12-2013 A

190
190

2. Place Coupling Units Inside Enclosure - GTG 2


YARNIMA.10.15.2.1.25 Install Coupling Units

100%

155
152
18

21-06-2013 A
21-06-2013 A
21-06-2013 A

20-12-2013 A
20-12-2013 A
09-07-2013 A

3281
990
0

Install Coupling Units - GTG 2


YARNIMA.10.15.2.26 PIPING GT2
YARNIMA.10.15.2.26.1 Connect Piping in Enclosure

100%

YARNIMA.10.15.2.1.25 Install Coupling Units


A14780
Install Coupling Units - GTG 2
YARNIMA.10.15.2.26 PIPING GT2
YARNIMA.10.15.2.26.1 Connect Piping in Enclosure
NCR-S132
GTG2: GT2- Lube Oil Unit Piping showing signs of rusting internally

Final Alignment - GTG 2

GTG2: GT2- Lube Oil Unit Piping showing signs of rusting internally

A14620

Connect Piping In Enclosure - GTG 2

03-07-2013 A

20-12-2013 A

990

100%

A18710

1. SDB Drain Water - GTG 2

03-07-2013 A

14-12-2013 A

100%

1. SDB Drain Water - GTG 2

A18720

2. SDB Wash Water - GTG 2

02-08-2013 A

14-12-2013 A

100%

2. SDB Wash Water - GTG 2

A18730

3. QFA Instrument Air - GTG 2

08-10-2013 A

20-12-2013 A

100%

YARNIMA.10.15.2.26.2 Install Inter Skid Piping


NCR-S141
GTG2 Damaged Pipe on Lube Oil Auxiliary Skid

139
2

30-06-2013 A
30-06-2013 A

18-12-2013 A
01-07-2013 A

1200
0

3. QFA Instrument Air - GTG 2


YARNIMA.10.15.2.26.2 Install Inter Skid Piping

100%

Connect Piping In Enclosure - GTG 2

GTG2 Damaged Pipe on Lube Oil Auxiliary Skid

A14760

Install Inter Skid Piping - GTG 2

17

24-07-2013 A

18-12-2013 A

1200

100%

A18670

1. MBV Lube Oil Piping - GTG 2

24-07-2013 A

18-12-2013 A

100%

NCR-S183

GTG2 SDB System Flange Clash with Diffuser Plate

07-08-2013 A

12-08-2013 A

100%

A18700

3. Install CO2 pipework- supports- brackets- nozzles and horns - GTG 2

12-08-2013 A

17-12-2013 A

100%

3. Install CO2 pipework- supports- brackets- nozzles and horn

A18680

2. MBN Liquid Fuel - GTG 2

18-09-2013 A

17-12-2013 A

100%

16
16

08-10-2013 A
08-10-2013 A

19-12-2013 A
19-12-2013 A

125
125

2. MBN Liquid Fuel - GTG 2


YARNIMA.10.15.2.26.3 Install Fuel Gas Piping/Valve Train

100%

YARNIMA.10.15.2.26.3 Install Fuel Gas Piping/Valve Train


A15600
Install Fuel Gas Skid Piping - GTG 2

Install Inter Skid Piping - GTG 2


1. MBV Lube Oil Piping - GTG 2
GTG2 SDB System Flange Clash with Diffuser Plate

Install Fuel Gas Skid Piping - GTG 2

A18640

1. Install Propane Cabinet

09-10-2013 A

16-10-2013 A

100%

1. Install Propane Cabinet

A18650

2. MBP Gas Vent

13-10-2013 A

18-10-2013 A

100%

2. MBP Gas Vent

A18660

3. MBP Ignition Gas

16-10-2013 A

22-10-2013 A

100%

100
42

14-08-2013 A
14-08-2013 A

03-10-2013 A
09-09-2013 A

32
32

100%

Install Bleed Airpipes


1. MBH Bleed Air Piping

YARNIMA.10.15.2.26.4 Install Bleed Air Pipes


A14790
Install Bleed Airpipes
A18690

1. MBH Bleed Air Piping

14-08-2013 A

09-09-2013 A

100%

NCR-S236

GTG2 Bleed Air Drain - Damaged Fitting

19

14-09-2013 A

03-10-2013 A

100%

12
12

08-10-2013 A
08-10-2013 A

18-12-2013 A
18-12-2013 A

934
934

100%

YARNIMA.10.15.2.26.6 Install Piping Insulation


A15580
Install Piping Insulation - GTG 2

3. MBP Ignition Gas


YARNIMA.10.15.2.26.4 Install Bleed Air Pipes

GTG2 Bleed Air Drain - Damaged Fitting


YARNIMA.10.15.2.26.6 Install Piping Insulation
Install Piping Insulation - GTG 2

A18740

1. Insulate Bleed Air Pipe

09-10-2013 A

12-10-2013 A

100%

1. Insulate Bleed Air Pipe

A18750

2. Insulate Gas Pipe

10-10-2013 A

13-10-2013 A

100%

2. Insulate Gas Pipe

A18760

3. Insulate Liquid Fuel Pipe

12-10-2013 A

15-10-2013 A

100%

3. Insulate Liquid Fuel Pipe

A18770

4. Insulate Generator Lube Oil Supply Pipes

14-10-2013 A

18-10-2013 A

100%

284
284

02-03-2013 A
02-03-2013 A

20-02-2014
20-02-2014

8746
0

4. Insulate Generator Lube Oil Supply Pipes


YARNIMA.10.15.2.2 ELECTRICAL GT2

23
11

02-03-2013 A
02-03-2013 A

03-03-2013 A
02-03-2013 A

1319
986

100%

Cable Ladder - Underneath Switchroom & Battery Room

12

03-03-2013 A

03-03-2013 A

333

100%

Cable Ladder - Culverts Switchroom to GTG 2

112
2

28-05-2013 A
28-05-2013 A

06-01-2014 A
16-12-2013 A

719
98

100%

YARNIMA.10.15.2.2 ELECTRICAL GT2


A12670
GT2 Electrical WBS Summary
YARNIMA.10.15.2.2.1 Cable Ladder
A12440
Cable Ladder - Underneath Switchroom & Battery Room
A12450

Cable Ladder - Culverts Switchroom to GTG 2

YARNIMA.10.15.2.2.2 Switch Room and Equipment


A12410
Install GT2 Auxillary 1.5 MVA Transformer - GTG 2

98
98

0%

GT2 Electrical WBS Summary


YARNIMA.10.15.2.2.1 Cable Ladder

YARNIMA.10.15.2.2.2 Switch Room and Equipment


Install GT2 Auxillary 1.5 MVA Transformer - GTG 2

A12420

Install GT2 Switchroom - GTG 2

14-06-2013 A

06-01-2014 A

314

100%

Install GT2 Switchroom - GTG 2

A12430

Install GT 2 Battery Room & Battery System - GTG 2

12

15-06-2013 A

06-01-2014 A

307

100%

Install GT 2 Battery Room & Battery System - GTG 2

NCR-S243

GTG2: Damaged on the Airconditioning Units for the GT2 Switchrooms

13

18-09-2013 A

01-10-2013 A

100%

GTG2: Damaged on the Airconditioning Units for the GT2 Switchrooms

NCR-S255

GTG2: The HV panel's lock is broken

12

20-09-2013 A

02-10-2013 A

100%

GTG2: The HV panel's lock is broken

NCR-S287

STG2: ST-2 Switchrooms - Walkway foundation Missing Anchor Bolts

12

14-10-2013 A

26-10-2013 A

100%

106
40

07-08-2013 A
07-08-2013 A

04-01-2014 A
19-12-2013 A

1185
1185

100%

17-10-2013 A

17-10-2013 A

100%

15-12-2013 A

02-01-2014 A

100%

Misalignment of holes and miscellaneous nonconformities on

NCR-S380-1319
Rectify Misalignment of holes and miscellaneous nonconformities on GT2 Donaldson Equipment
2
03-01-2014 A

04-01-2014 A

100%

13-02-2014

3701

Rectify Misalignment of holes and miscellaneous nonconform


YARNIMA.10.15.2.2.4 Cabling

YARNIMA.10.15.2.2.3 On Skid Works


A12620
Install GT2 On-Skid Electrical Equip - GTG 2
NCR-S295

GTG2: GT2 liquid fuel heater studs is broken

NCR-S380

Misalignment of holes and miscellaneous nonconformities on GT2 Donaldson Equipment


7
198

YARNIMA.10.15.2.2.4 Cabling
Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

13-03-2013 A

Page 21 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

STG2: ST-2 Switchrooms - Walkway foundation Missing Anchor Bolts


YARNIMA.10.15.2.2.3 On Skid Works
Install GT2 On-Skid Electrical Equip - GTG 2
GTG2: GT2 liquid fuel heater studs is broken

105

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float
98

Activity % S
Complete

A12460

Pull LV-C & I Cabling - GTG 2

33

13-03-2013 A

13-02-2014

2178

A12580

Install HV/LV Cabling GT 2 Switchroom to Aux Transformer

04-05-2013 A

01-12-2013 A

266

100%

A12630

Install VSD Cable

07-06-2013 A

23-11-2013 A

239

100%

A12480

11kV Cabling - GT2 to Switchroom

04-08-2013 A

07-11-2013 A

342

100%

A12570

11kV Cabling Switchroom to Step Up Transformer

11-08-2013 A

07-11-2013 A

676

100%

NCR-S189

BOP: Instrumentation Cable Schedule Stage 2

12-08-2013 A

15-08-2013 A

100%

NCR-S296

GTG2: GT2 Switchroom missing components

11

17-10-2013 A

28-10-2013 A

100%

NCR-S352

GTG2: Minimax emergency brake glass on GT2 was broken in transport

32

18-11-2013 A

02-01-2014 A

100%

NCR-S378

GTG2: Clarification on Missing Earths back to Main Earth bar on Siemens Panels GT28

13-12-2013 A

02-01-2014 A

100%

GTG2: Clarification on Missing Earths back to Main Earth ba

NCR-S382

Clarification on GT2 MPB55 propane cabinet cabling due to wrong location of conduit 4

16-12-2013 A

19-12-2013 A

100%

04-06-2013 A
04-06-2013 A

20-02-2014
20-02-2014

1056
1056

Clarification on GT2 MPB55 propane cabinet cabling due to w


YARNIMA.10.15.2.2.5 Cable Terminations

112
25

YARNIMA.10.15.2.2.5 Cable Terminations


A12470
Terminate LV- C & I Cable - GTG 2

98
98

98%

Pull LV-C & I Cabling - GTG 2


Install HV/LV Cabling GT 2 Switchroom to Aux Transformer
Install VSD Cable
11kV Cabling - GT2 to Switchroom
11kV Cabling Switchroom to Step Up Transformer
BOP: Instrumentation Cable Schedule Stage 2
GTG2: GT2 Switchroom missing components

GTG2: Minimax emergency brake glass on GT2 was broken

93%

Terminate LV- C & I Cable - GTG 2

NCR-S230

GTG1: Cables GT1/2 BFA10GS012D001 could not terminate becasue of size of the lug6

10-09-2013 A

15-09-2013 A

100%

GTG1: Cables GT1/2 BFA10GS012D001 could not terminate becasue of size

NCR-S231

GTG2: No gland plate has been installed in the GT2 switchroom

10-09-2013 A

12-09-2013 A

100%

GTG2: No gland plate has been installed in the GT2 switchroom

NCR-S235

GTG2: The HV panels GS006 and GS007 in GT2BBA10 have missing duct lid

13-09-2013 A

15-09-2013 A

100%

GTG2: The HV panels GS006 and GS007 in GT2BBA10 have missing duct li

NCR-S257

GTG2: The circuit breaker in GT2BTM20 is broken

13

20-09-2013 A

03-10-2013 A

100%

NCR-S266

GTG2: Cable Modifications to GT2 - Cable is too large for Terminal size

28-09-2013 A

28-09-2013 A

100%

A12490

11kV Cable Terminations

100%

14

08-11-2013 A

02-12-2013 A

YARNIMA.10.15.2.2.6 Earthing and Lighting Protection


A12500
Earthing & Lightning Protection - GTG 2

12
12

06-03-2013 A
06-03-2013 A

17-01-2014 A
17-01-2014 A

0
0

YARNIMA.10.15.2.2.7 Lighting and Small Power


A12510
Lighting & Small Power - GTG 2

18
18

14-08-2013 A
14-08-2013 A

10-02-2014
10-02-2014

740
740

YARNIMA.10.15.2.2.8 Field Equipment


A12520
Field Equipment (LCS's- J.B's- HDG conduits etc...) - GTG 2

2
2

20-11-2013 A
20-11-2013 A

16-01-2014 A
16-01-2014 A

26
26

YARNIMA.10.15.2.4 INSTRUMENTS
A12640
Install Stage 2 Instruments - GTG 2

2
2

12-09-2013 A
12-09-2013 A

02-01-2014 A
02-01-2014 A

349
349

YARNIMA.10.15.2.5 GT2 PRE-COMMISSIONING


A12950
Electrical Pre-Commissioning - GTG 2

84
15

20-11-2013 A
20-11-2013 A

14-03-2014
20-02-2014

1030
532
350

100%

A12990

Mechanical Pre-Commissioning - GTG 2

21

01-12-2013 A

21-12-2013 A

NCR-S375

GTG2 Oil Tank Not Supplied Clean

108
108

98
98

GTG2: The circuit breaker in GT2BTM20 is broken


GTG2: Cable Modifications to GT2 - Cable is too large for Terminal size
11kV Cable Terminations
YARNIMA.10.15.2.2.6 Earthing and Lighting Protection

100%

Earthing & Lightning Protection - GTG 2


YARNIMA.10.15.2.2.7 Lighting and Small Power

90%

Lighting & Small Power - GTG 2


YARNIMA.10.15.2.2.8 Field Equipment

100%

Field Equipment (LCS's- J.B's- HDG conduits etc...) - GTG


YARNIMA.10.15.2.4 INSTRUMENTS

100%

Install Stage 2 Instruments - GTG 2


YARNIMA.10.15.2.5 GT2 PRE-COMMISSIONIN

95%

Electrical Pre-Commissioning - GTG 2


Mechanical Pre-Commissioning - GTG 2

10-12-2013 A

13-12-2013 A

100%

GTG2 Oil Tank Not Supplied Clean

NCR-S375-1523 GTG2 clean Oil Tank

15-12-2013 A

15-12-2013 A

18

100%

GTG2 clean Oil Tank

A12960

NDT & QA Documentation - GTG 2

10

16-12-2013 A

20-02-2014

50

A12970

Lube Oil Flush (During Commissioning) - GTG 2

10

16-12-2013 A

09-01-2014 A

80

A22940

Punchlisting B and C Items - GTG 2

20

23-12-2013 A

14-03-2014

98

90%

A12980

Construction Verification - GTG 2

20-02-2014

98

0%

YARNIMA.10.15.3 GAS TURBINE 1 & ASSOCIATED EQUIPMENT


YARNIMA.10.15.3.6 GTG1 - ACTUAL VARIATIONS & NON SCOPE WORKS
RMWS49
Painting on GTG1 and GTG2

293
135
1

01-04-2014
13-01-2014 A
08-08-2013 A

25190
868
24

81

02-04-2013 A
08-08-2013 A
08-08-2013 A

98

95%

NDT & QA Documentation - GTG 2

100%

Lube Oil Flush (During Commissioning) - GTG 2


Punchlisting B and C Items - GTG 2

Construction Verification - GTG 2


YARNIMA.10.15.3 GAS TURBINE 1 & ASSOC
YARNIMA.10.15.3.6 GTG1 - ACTUAL VARIATIONS & NO

100%

VEGT1000

VE GTG 1 - work on: A/C around Switchroom, Siemens pipework outside enclosure, electrical
42
in
09-08-2013
generator Aetc

23-09-2013 A

577

100%

NCR-S220

GTG1 & GTG2 Enclosure Internal Platforms Clash

NCR-S239
NCR-S242

Painting on GTG1 and GTG2

VE GTG 1 - work on: A/C around Switchroom, Siemens pipework outside e

04-09-2013 A

11-09-2013 A

100%

GTG2 & GTG1 - Enclosure Steelwork Clashes with Platform - A14580 and A14880

15-09-2013 A

19-09-2013 A

100%

GTG1 Fitment Issues - A18930 (Diffuser Rings)

19

18-09-2013 A

08-10-2013 A

100%

GTG1 Fitment Issues - A18930 (Diffuser Rings)

NCR-S244

GTG1 Pipe Supports Fitment Issues

19

18-09-2013 A

08-10-2013 A

100%

GTG1 Pipe Supports Fitment Issues

NCR-S245

ByPass Stack 1 Fitment Issues

19

18-09-2013 A

08-10-2013 A

100%

ByPass Stack 1 Fitment Issues

VEGT1010

VE GTG 1 - work on A/C around Switchroom, Lube oil cooler cable ladder

01-10-2013 A

03-10-2013 A

36

100%

VE GTG 1 - work on A/C around Switchroom, Lube oil cooler cable ladder

VEGT1020

VE GTG 1 - Delaied access to 132kV switchyard, work on A/C around Switchroom, Switchroom
9
10-10-2013
Access Platform
A
Issues
20-10-2013 A

100

100%

VE GTG 1 - Delaied access to 132kV switchyard, work on A/C around S

VEGT1030

VE GTG 1 - Pipe-fitting and fabrication for Siemens pipework outside enclosure, Install1Donaldson
30-10-2013
ElectricalAEquipment
31-10-2013 A

21

100%

VE GTG 1 - Pipe-fitting and fabrication for Siemens pipework outside

VEGT1040

VE GTG 1 - Delaied access to 132kV switchyard, Replacement cables for Siemens Ex11
circuits MWR
10-11-2013
132, Mods
A to21-11-2013
Gen enclosure
A

110

100%

NCR-S372

GTG1 Lube Oil cooler fin fans alignment

100%

YARNIMA.10.15.3.1 MECHANICAL GT1


A12930
GT1 Installation WBS Summary
YARNIMA.10.15.3.1.26 Prepare Foundations & Fixators
A14810
Prepare Foundations & Fixators

21

10-12-2013 A

13-01-2014 A

238
238

21-05-2013 A
21-05-2013 A

17-02-2014
17-02-2014

10924
0

17
5

28-07-2013 A
28-07-2013 A

01-08-2013 A
01-08-2013 A

100
100

111
101

GTG1 & GTG2 Enclosure Internal Platforms Clash

GTG2 & GTG1 - Enclosure Steelwork Clashes with Platform - A14580 and A

VE GTG 1 - Delaied access to 132kV switchyard, Replacement cab


GTG1 Lube Oil cooler fin fans alignment
YARNIMA.10.15.3.1 MECHANICAL GT1

0%

GT1 Installation WBS Summary


YARNIMA.10.15.3.1.26 Prepare Foundations & Fixators

100%

Prepare Foundations & Fixators

A18840

1. Clean the concrete- steel embeds and grout pockets

29-07-2013 A

29-07-2013 A

100%

1. Clean the concrete- steel embeds and grout pockets

A18850

2. Setup GT skid support tools as per drawing and set heights

30-07-2013 A

30-07-2013 A

100%

2. Setup GT skid support tools as per drawing and set heights

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 22 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

31-07-2013 A

01-08-2013 A

100%

4
17-07-2013
YARNIMA.10.15.3.1.3 Placement of Gear Box & Remove Transport Protection (GT, Gearbox, Generator
& Diffuser) A
A14820
Placement of Gear Box & Remove Transport Protection
4
17-07-2013 A

05-08-2013 A
05-08-2013 A

250
250

3. Mark out XY axis for plump bob


YARNIMA.10.15.3.1.3 Placement of Gear Box & Remove Transport Protection (GT

A18860

3. Mark out XY axis for plump bob

YARNIMA.10.15.3.1.4 Placement of GT & Lube oil Skid


A14830
Placement of GT

Budgeted
Labor Units

Total
Float

Activity % S
Complete

100%

88
9

22-05-2013 A
22-05-2013 A

23-08-2013 A
07-08-2013 A

190
190

Placement of Gear Box & Remove Transport Protection


YARNIMA.10.15.3.1.4 Placement of GT & Lube oil Skid

100%

Placement of GT

A18880

1. Place GT skid on foundation tooling- plumb to XY axis- grout once skid is aligned

02-08-2013 A

23-08-2013 A

100%

A18890

2. Once GT is aligned & grouted- lift lube oil skid into position

04-08-2013 A

07-08-2013 A

100%

27
5

07-08-2013 A
07-08-2013 A

25-09-2013 A
10-09-2013 A

190
190

100%

YARNIMA.10.15.3.1.5 Placement and alignment of Diffuser


A14840
Placement of Diffuser

1. Place GT skid on foundation tooling- plumb to XY axis- grout once skid is align
2. Once GT is aligned & grouted- lift lube oil skid into position
YARNIMA.10.15.3.1.5 Placement and alignment of Diffuser
Placement of Diffuser

A18900

1. Mark out foundation axis- and distance from turbine flange to diffuser flange

08-08-2013 A

13-08-2013 A

100%

A18910

2. Lift diffuser- mount legs and plates

14-08-2013 A

25-09-2013 A

100%

A18920

3. Lower diffuser onto foundation- plumb centreline & flange face- place on pedastals 3

17-08-2013 A

10-09-2013 A

100%

3. Lower diffuser onto foundation- plumb centreline & flange face- place on pe

NCR-S194

GTG1: Exhaust diffuser locating Pinholes and keys udersize A repeat of NCR C1034-NCR-S164
22
18-08-2013 A

GTG1: Exhaust diffuser locating Pinholes and keys udersize A repeat of NCR
YARNIMA.10.15.3.1.6 Connect Diffuser

YARNIMA.10.15.3.1.6 Connect Diffuser


A14910
Connect Diffuser

10-09-2013 A

100%

9
9

11-09-2013 A
11-09-2013 A

20-09-2013 A
19-09-2013 A

380
380

1. Mark out foundation axis- and distance from turbine flange to diffuser flange
2. Lift diffuser- mount legs and plates

100%

Connect Diffuser

A18930

1. Install and torque inner and outer diffuser rings (Require Scaffold)

11-09-2013 A

19-09-2013 A

100%

1. Install and torque inner and outer diffuser rings (Require Scaffold)

A18940

2. Carry out fine alignments of diffuser

18-09-2013 A

19-09-2013 A

100%

2. Carry out fine alignments of diffuser

A18950

3. Weld diffuser pedestals and feet

18-09-2013 A

20-09-2013 A

100%

2
2

15-08-2013 A
15-08-2013 A

30-08-2013 A
30-08-2013 A

300
300

3. Weld diffuser pedestals and feet


YARNIMA.10.15.3.1.7 Install Liquid Fuel Unit

100%

Install Liquid Fuel Unit

15-08-2013 A

26-08-2013 A

100%

1. Place packers and survey heights- mark X-Y axis


2. Place LFU on foundation and fix with dynabolts
YARNIMA.10.15.3.1.8 Placement of Generator

YARNIMA.10.15.3.1.7 Install Liquid Fuel Unit


A15030
Install Liquid Fuel Unit
A18960

1. Place packers and survey heights- mark X-Y axis

A18970

2. Place LFU on foundation and fix with dynabolts

YARNIMA.10.15.3.1.8 Placement of Generator


A14850
Placement of Generator

16-08-2013 A

30-08-2013 A

100%

69
6

21-07-2013 A
21-07-2013 A

24-10-2013 A
25-09-2013 A

190
190

100%

Placement of Generator

A18980

1. Position generator feet- shims & wedges as per drawings

05-08-2013 A

08-08-2013 A

100%

1. Position generator feet- shims & wedges as per drawings

A18990

2. Mark X-Y axis on foundation- set feet to correct height

06-08-2013 A

07-08-2013 A

100%

2. Mark X-Y axis on foundation- set feet to correct height

A19000

3. Place generator on feet- plumb to X-Y axis

08-08-2013 A

08-08-2013 A

100%

3. Place generator on feet- plumb to X-Y axis

A19010

4. Weld generator alignment tools to steel embeds

17-08-2013 A

25-09-2013 A

100%

NCR-S311

GTG1: Generator Sole Plates Cast at Incorrect Levels

24-10-2013 A

24-10-2013 A

100%

26
10

05-08-2013 A
05-08-2013 A

08-10-2013 A
08-10-2013 A

500
500

100%

YARNIMA.10.15.3.1.9 Preliminary Alignment of Modules


A14860
Preliminary Alignment of Modules
A19020

1. Align GT skid and check gearbox splitline flatness prior to grouting

05-08-2013 A

06-08-2013 A

100%

A19040

3. Carry out preliminary alignment Generator to Gearbox

06-08-2013 A

08-10-2013 A

100%

A19030

2. Check alingment GT to Gearbox

08-08-2013 A

08-10-2013 A

100%

9
6

26-07-2013 A
26-07-2013 A

26-09-2013 A
26-09-2013 A

150
150

100%

YARNIMA.10.15.3.1.10 Place Starter Motor


A14870
Place Starter Motor

4. Weld generator alignment tools to steel embeds


GTG1: Generator Sole Plates Cast at Incorrect Levels
YARNIMA.10.15.3.1.9 Preliminary Alignment of Modules
Preliminary Alignment of Modules
1. Align GT skid and check gearbox splitline flatness prior to grouting
3. Carry out preliminary alignment Generator to Gearbox
2. Check alingment GT to Gearbox
YARNIMA.10.15.3.1.10 Place Starter Motor
Place Starter Motor

A19050

1. Lower starter onto plynth- 90 degrees out

26-07-2013 A

06-08-2013 A

100%

A19060

2. Install coupling hub using Siemens special tool

07-08-2013 A

22-08-2013 A

100%

A19070

3. Lift motor- install and set mounting feet- mount motor in correct orientation

23-08-2013 A

24-09-2013 A

100%

A19080

4. Carry out alignment- starter motor to Gearbox - Weld Feet

25-08-2013 A

26-09-2013 A

100%

2
2

17-08-2013 A
17-08-2013 A

18-09-2013 A
18-09-2013 A

250
250

100%

Install CO2 Module

18-08-2013 A

13-09-2013 A

100%

1. Mark out foundation- install and survey packers- anchor feet to foundation

YARNIMA.10.15.3.1.11 Install CO2 Module


A15020
Install CO2 Module
A19090

1. Mark out foundation- install and survey packers- anchor feet to foundation

A19100

2. Install module onto feet

YARNIMA.10.15.3.1.12 Install Oil Coolers (Including Handrails, Ladders)


A15050
Install Oil Coolers

14-09-2013 A

18-09-2013 A

100%

94
18

21-05-2013 A
21-05-2013 A

05-09-2013 A
05-09-2013 A

1120
1120

1. Lower starter onto plynth- 90 degrees out


2. Install coupling hub using Siemens special tool

3. Lift motor- install and set mounting feet- mount motor in correct orientatio
4. Carry out alignment- starter motor to Gearbox - Weld Feet
YARNIMA.10.15.3.1.11 Install CO2 Module

2. Install module onto feet


YARNIMA.10.15.3.1.12 Install Oil Coolers (Including Handrails, Ladders)

100%

Install Oil Coolers

A19110

1. Mark out foundation- install packers and survey

21-05-2013 A

22-05-2013 A

100%

1. Mark out foundation- install packers and survey

A19120

2. Place oil cooler unit on foundation

22-05-2013 A

23-05-2013 A

100%

2. Place oil cooler unit on foundation

A19140

4. Install handrails and access ladders

28-05-2013 A

10-08-2013 A

100%

4. Install handrails and access ladders

A19130

3. Welding feet

03-08-2013 A

08-08-2013 A

100%

3. Welding feet

A19150

5. Install motors and fan blades

01-09-2013 A

05-09-2013 A

100%

52
52

22-08-2013 A
22-08-2013 A

06-01-2014 A
02-01-2014 A

400
400

YARNIMA.10.15.3.1.13 Install Platforms & Access Stairways


A15000
Install Platforms and Access Stairways

5. Install motors and fan blades


YARNIMA.10.15.3.1.13 Install Platforms & Access Stairway

100%

Install Platforms and Access Stairways

A19160

1. Install internal platforms and access ladders/stair

23-08-2013 A

06-01-2014 A

100%

1. Install internal platforms and access ladders/stair

A19170

2. After installation of enclosure- install external access platforms- ladders/stairs

10-09-2013 A

06-01-2014 A

100%

2. After installation of enclosure- install external access platf

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 23 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Finish

Budgeted
Labor Units

11 ground)
03-09-2013 A
YARNIMA.10.15.3.1.14 Assemble Steel Enclosure (Pre-assemble steel enclosure modules on the
A14880
Assemble Steel Enclosure
11
03-09-2013 A

22-09-2013 A
22-09-2013 A

450
450

100%

14
24-09-2013 A
YARNIMA.10.15.3.1.15 Placement of Steel Enclosure (Place and connect pre-assembled steel modules)
A14900
Placement of Steel Enclosure
14
24-09-2013 A

13-11-2013 A
13-11-2013 A

550
550

100%

YARNIMA.10.15.3.1.16 Install Cladding


A14920
Install Enclusure Pannels and Cladding Around Piping Penetrations

Start

Total
Float

Activity % S
Complete

YARNIMA.10.15.3.1.14 Assemble Steel Enclosure (Pre-assemble steel enc

26
26

19-10-2013 A
19-10-2013 A

30-01-2014 A
30-01-2014 A

2890
2890

100%

Assemble Steel Enclosure


YARNIMA.10.15.3.1.15 Placement of Steel Enclosure (Place and c
Placement of Steel Enclosure
YARNIMA.10.15.3.1.16 Install Cladding

Install Enclusure Pannels and Cladding Around Piping P

A19200

1. Install upper angle brackets and intermediate "Z" sections

19-10-2013 A

25-10-2013 A

100%

A19210

2. Mark out foundation and install lower wall panel channel mounts

26-10-2013 A

31-10-2013 A

100%

2. Mark out foundation and install lower wall panel channel mounts

A19220

3. Install slurry wall mounting items and slurry wall between GT and Generator

29-10-2013 A

03-11-2013 A

100%

3. Install slurry wall mounting items and slurry wall between GT and G

A19230

4. Install outer wall panels- door frames- doors and flashing

10-11-2013 A

01-12-2013 A

100%

A19240

5. Install roof cladding

20-11-2013 A

14-12-2013 A

100%

28
28

13-09-2013 A
13-09-2013 A

06-01-2014 A
02-01-2014 A

312
312

100%

YARNIMA.10.15.3.1.17 Install Ventilation Ducts, Platform & Access Ladder


A14960
Install Ventilation Ducts- Platform & Access Ladder
A19250

1. Assemble and install generator cooling ducts and elbow within enclosure

13-09-2013 A

10-10-2013 A

100%

A19260

2. Install remaining generator cooling ducts and supports

13-09-2013 A

25-10-2013 A

100%

A19300

4. Generator Enclosure Inlet and Outlet

18-09-2013 A

11-10-2013 A

100%

A19270

5. Install generator cooling unit- platform and access ladder

23-10-2013 A

14-12-2013 A

100%

A19290

3. Install enclosure ventilation outlet - GTG1

10

06-11-2013 A

28-12-2013 A

100%

A19280

6. Install enclosure ventilation inlet - GTG1

07-11-2013 A

06-01-2014 A

100%

3
3

25-09-2013 A
25-09-2013 A

20-01-2014 A
20-01-2014 A

250
250

YARNIMA.10.15.3.1.18 Install Fuel Gas Skid


A14940
Install Fuel Gas Skid

1. Install upper angle brackets and intermediate "Z" sections

4. Install outer wall panels- door frames- doors and flashing

5. Install roof cladding


YARNIMA.10.15.3.1.17 Install Ventilation Ducts, Platform &
Install Ventilation Ducts- Platform & Access Ladder

1. Assemble and install generator cooling ducts and elbow within enclosur
2. Install remaining generator cooling ducts and supports
4. Generator Enclosure Inlet and Outlet
5. Install generator cooling unit- platform and access ladder
3. Install enclosure ventilation outlet - GTG1
6. Install enclosure ventilation inlet - GTG1
YARNIMA.10.15.3.1.18 Install Fuel Gas Skid

100%

Install Fuel Gas Skid

A19310

1. Install packers- survey and mark out foundation.

25-09-2013 A

12-10-2013 A

100%

1. Install packers- survey and mark out foundation.

A19320

2. Place and anchor fuel gas skid

26-09-2013 A

16-12-2013 A

100%

18-10-2013 A
YARNIMA.10.15.3.1.19 Assemble Intake Support Structure (Assemble support structure on the15
ground)
A14970
Assemble Intake Support Structure
13
18-10-2013 A

24-11-2013 A
24-11-2013 A

275
275

2. Place and anchor fuel gas skid


YARNIMA.10.15.3.1.19 Assemble Intake Support Structure (Asse

100%

Assemble Intake Support Structure

GTG1 Air Intake Beam - Welded Splice Join

18-11-2013 A

19-11-2013 A

100%

YARNIMA.10.15.3.1.20 Lift Air Intake Structure into Place


A14980
Lift Air Intake Structure into Place

3
3

13-11-2013 A
13-11-2013 A

26-11-2013 A
26-11-2013 A

300
300

GTG1 Air Intake Beam - Welded Splice Join


YARNIMA.10.15.3.1.20 Lift Air Intake Structure into Place

100%

YARNIMA.10.15.3.1.21 Lift & Install Remaining Air Intake Modules


A15010
Lift & Install Remaining Air Intake Modules

15
10

07-11-2013 A
07-11-2013 A

27-11-2013 A
27-11-2013 A

750
750

Lift Air Intake Structure into Place


YARNIMA.10.15.3.1.21 Lift & Install Remaining Air Intake Module

NCR-S351

100%

Lift & Install Remaining Air Intake Modules

A19350

1. Lift & Install Remaining Air Intake Modules

07-11-2013 A

12-11-2013 A

100%

1. Lift & Install Remaining Air Intake Modules

A19360

2. Install Evaporative Cooler Pipe Work/Pumps etc. - GTG1

07-11-2013 A

27-11-2013 A

100%

YARNIMA.10.15.3.1.22 Install Air Filters and Evaporative Cooling Media


A14990
Install Air Filters - GTG1

6
6

20-12-2013 A
20-12-2013 A

13-02-2014
13-02-2014

187
187

105
105

2. Install Evaporative Cooler Pipe Work/Pumps etc. - GTG1


YARNIMA.10.15.3.1.22 Install Air Filters and Evapora

20%

YARNIMA.10.15.3.1.23 Install Fire Extinguisher & Equipment


A15090
Install Fire Fighting Equipment - GTG1

56
14

27-11-2013 A
27-11-2013 A

11-02-2014
03-02-2014 A

250
250

107

Install Air Filters - GTG1


YARNIMA.10.15.3.1.23 Install Fire Extinguisher & Eq

27-11-2013 A

27-01-2014 A

100%

A19380

1. Install CO2 bottles in skid. - GTG1

A19390

2. Remove nozzles- horns- cap and pressure test- reinstall nozzles and horns - GTG1 3

28-11-2013 A

28-01-2014 A

A19400

3. Setup counterweights and connect hoses - GTG1

29-01-2014 A

11-02-2014

63
8

24-11-2013 A
24-11-2013 A

02-02-2014 A
12-12-2013 A

500
0

100%

YARNIMA.10.15.3.1.24 Final GTG Alignment


A19580
1. Pre-Alignment of GTG 1

101

1. Install CO2 bottles in skid. - GTG1

100%

2. Remove nozzles- horns- cap and pressure test- reins

60%

3. Setup counterweights and connect hoses - GTG1


YARNIMA.10.15.3.1.24 Final GTG Alignment

A15070

Final Alignment - GTG1

02-12-2013 A

02-02-2014 A

500

100%

A19560

2. Place Coupling Units Inside Enclosure - GTG1

26-01-2014 A

27-01-2014 A

100%

3
3

03-12-2013 A
03-12-2013 A

17-02-2014
17-02-2014

190
190

101
101

94
13
13

25-07-2013 A
25-08-2013 A
25-08-2013 A

13-02-2014
03-01-2014 A
02-01-2014 A

3281
990
990

105

YARNIMA.10.15.3.1.25 Install Coupling Units


A15080
Install Coupling Units
YARNIMA.10.15.3.3 PIPING GT1
YARNIMA.10.15.3.3.1 Connect Piping in Enclosure
A14930
Connect Piping In Enclosure - GTG1

Install Fire Fighting Equipment - GTG1

100%

1. Pre-Alignment of GTG 1
Final Alignment - GTG1
2. Place Coupling Units Inside Enclosure - GTG1
YARNIMA.10.15.3.1.25 Install Coupling Units

95%

Install Coupling Units


YARNIMA.10.15.3.3 PIPING GT1
YARNIMA.10.15.3.3.1 Connect Piping in Enclosure

100%

Connect Piping In Enclosure - GTG1

A19480

1. SDB Drain Water - GTG1

25-08-2013 A

03-01-2014 A

100%

1. SDB Drain Water - GTG1

A19490

2. SDB Wash Water - GTG1

25-08-2013 A

03-01-2014 A

100%

2. SDB Wash Water - GTG1

A19500

3. QFA Instrument Air - GTG1

25-08-2013 A

03-01-2014 A

100%

71
17

25-07-2013 A
25-07-2013 A

04-12-2013 A
04-12-2013 A

1200
1200

3. QFA Instrument Air - GTG1


YARNIMA.10.15.3.3.2 Install Inter Skid Piping

YARNIMA.10.15.3.3.2 Install Inter Skid Piping


A15060
Install Inter Skid Piping - GTG1

100%

Install Inter Skid Piping - GTG1

A19440

1. MBV Lube Oil Piping - GTG1

25-07-2013 A

04-12-2013 A

100%

1. MBV Lube Oil Piping - GTG1

A19470

3. Install CO2 pipework- supports- brackets- nozzles and horns - GTG1

11-08-2013 A

04-12-2013 A

100%

3. Install CO2 pipework- supports- brackets- nozzles and horns -

A19450

2. MBN Liquid Fuel - GTG1

26-08-2013 A

04-12-2013 A

100%

2. MBN Liquid Fuel - GTG1

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 24 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

21
21

07-10-2013 A
07-10-2013 A

13-02-2014
27-01-2014 A

125
125

105

YARNIMA.10.15.3.3.3 Install Fuel Gas Piping/Valve Train


A15610
Install Fuel Gas Skid Piping - GTG1
A19410

1. Install Propane Cabinet

08-10-2013 A

03-11-2013 A

A19420

2. MBP Gas Vent

14-10-2013 A

22-10-2013 A

A19430

3. MBP Ignition Gas - GTG1

18-10-2013 A

13-02-2014

72
37

18-09-2013 A
18-09-2013 A

23-10-2013 A
23-10-2013 A

YARNIMA.10.15.3.3.4 Install Bleed Air Pipes


A14890
Install Bleed Airpipes

Activity % S
Complete

YARNIMA.10.15.3.3.3 Install Fuel Gas Piping/Valve T


100%

Install Fuel Gas Skid Piping - GTG1

100%

1. Install Propane Cabinet

100%

2. MBP Gas Vent

10%

32
32

3. MBP Ignition Gas - GTG1


YARNIMA.10.15.3.3.4 Install Bleed Air Pipes

100%

Install Bleed Airpipes

105

A19460

1. MBH Bleed Air Piping

19-09-2013 A

23-10-2013 A

100%

NCR-S270

GTG1: GT1 Bleed Air System - Piping Components Dimensional Mismatch

03-10-2013 A

04-10-2013 A

100%

12
12

15-10-2013 A
15-10-2013 A

06-12-2013 A
06-12-2013 A

934
934

100%

23-10-2013 A

100%

YARNIMA.10.15.3.3.6 Install Piping Insulation


A15590
Install Piping Insulation

1. MBH Bleed Air Piping

GTG1: GT1 Bleed Air System - Piping Components Dimensional Mismatch


YARNIMA.10.15.3.3.6 Install Piping Insulation
Install Piping Insulation

A19510

1. Insulate Bleed Air Pipe

15-10-2013 A

A19520

2. Insulate Gas Pipe

23-10-2013 A

01-11-2013 A

100%

A19530

3. Insulate Liquid Fuel Pipe

01-11-2013 A

06-12-2013 A

100%

3. Insulate Liquid Fuel Pipe

A19540

4. Insulate Generator Lube Oil Supply Pipes

06-11-2013 A

06-12-2013 A

100%

264
264

02-04-2013 A
02-04-2013 A

07-03-2014
07-03-2014

9075
0

4. Insulate Generator Lube Oil Supply Pipes


YARNIMA.10.15.3.2 ELECTRICAL GT1

82
11

02-04-2013 A
02-04-2013 A

31-07-2013 A
31-07-2013 A

1318
985

100%

12

25-05-2013 A

10-07-2013 A

333

100%

Cable Ladder - Culverts Switchroom to GTG1


GTG1: GT1 & GT2 Switchrooms do not have holes to connect cable ladder support
YARNIMA.10.15.3.2.6 Switch Room and Equipment

YARNIMA.10.15.3.2 ELECTRICAL GT1


A12940
GT1 Electrical WBS Summary
YARNIMA.10.15.3.2.1 Cable Ladder
A12710
Cable Ladder - Underneath Switchroom & Battery Room
A12720

Cable Ladder - Culverts Switchroom to GTG1

NCR-S144

GTG1: GT1 & GT2 Switchrooms do not have holes to connect cable ladder support

YARNIMA.10.15.3.2.6 Switch Room and Equipment


A12680
Install GT1 Auxillary 1.5 MVA Transformer

84
84

1. Insulate Bleed Air Pipe


2. Insulate Gas Pipe

0%

03-07-2013 A

04-07-2013 A

100%

135
2

28-05-2013 A
28-05-2013 A

06-01-2014 A
06-01-2014 A

719
98

100%

GT1 Electrical WBS Summary


YARNIMA.10.15.3.2.1 Cable Ladder
Cable Ladder - Underneath Switchroom & Battery Room

Install GT1 Auxillary 1.5 MVA Transformer

A12690

Install GT1 Switchroom

11

25-06-2013 A

29-10-2013 A

314

100%

A12700

Install GT1 Battery Room & Battery System

14

26-06-2013 A

06-01-2014 A

307

100%

NCR-S140

GTG1 Switchroom Access Platform Issues

42

30-06-2013 A

13-08-2013 A

100%

NCR-S232

GTG1: Two substation earth bars under GT1 switch room have wrong tag number

11-09-2013 A

12-09-2013 A

100%

NCR-S288

STG1: ST-1 Switchrooms - Walkway foundation Missing Anchor Bolts

12

14-10-2013 A

26-10-2013 A

100%

38
35

26-08-2013 A
26-08-2013 A

17-01-2014 A
17-01-2014 A

1288
1185

100%

10-12-2013 A

02-01-2014 A

100%

Misalignment of holes and miscellaneous non-conformities o

NCR-S374-1506
Rectify Misalignment of holes and miscellaneous non-conformities on GT1 Donaldson Equipment
5
03-01-2014 A

100%

Rectify Misalignment of holes and miscellaneous non-confo


YARNIMA.10.15.3.2.2 Cabling

YARNIMA.10.15.3.2.3 On Skid Works


A12890
Install GT1 On-Skid Electrical Equip
NCR-S374

Misalignment of holes and miscellaneous non-conformities on GT1 Donaldson Equipment


11

YARNIMA.10.15.3.2.2 Cabling
A12850
Install HV/LV Cabling GT1 Switchroom to Aux Transformer

07-01-2014 A

103

196
3

04-05-2013 A
04-05-2013 A

21-02-2014
15-02-2014

3436
263

91
103

Install GT1 Switchroom


Install GT1 Battery Room & Battery System
GTG1 Switchroom Access Platform Issues

GTG1: Two substation earth bars under GT1 switch room have wrong tag nu
STG1: ST-1 Switchrooms - Walkway foundation Missing Anchor Bolts
YARNIMA.10.15.3.2.3 On Skid Works
Install GT1 On-Skid Electrical Equip

100%

Install HV/LV Cabling GT1 Switchroom to Aux Transfo

A12730

Pull LV-C & I Cabling - GTG 1 (Incl Cable from GTG1 to HRSG S/Room)

33

23-05-2013 A

21-02-2014

2180

81

80%

Pull LV-C & I Cabling - GTG 1 (Incl Cable from GTG

A12900

Install VSD Cable - GTG 1

07-06-2013 A

21-02-2014

106

97

100%

NCR-S139

GTG1: GT1 INC45 Conduit does not pentrate through culwert wall

46

29-06-2013 A

16-08-2013 A

100%

A12750

11kV Cabling - GT 1 to Switchroom

11

17-08-2013 A

07-11-2013 A

342

100%

A12840

11kV Cabling Switchroom to Step Up Transformer

11

14-09-2013 A

01-10-2013 A

545

100%

43
25

27-08-2013 A
27-08-2013 A

07-03-2014
07-03-2014

1548
1548

13

15-11-2013 A

16-01-2014 A

YARNIMA.10.15.3.2.5 Earthing and Lighting Protection


A12770
Earthing & Lightning Protection - GTG 1

12
12

01-08-2013 A
01-08-2013 A

14-02-2014
14-02-2014

0
0

88
88

90%

YARNIMA.10.15.3.2.7 Lighting and Small Power


A12780
Lighting & Small Power - GTG 1

21
21

17-08-2013 A
17-08-2013 A

01-03-2014
01-03-2014

740
740

90
90

85%

YARNIMA.10.15.3.2.17 Field Equipment


A12790
Field Equipment (LCS's- J.B's- HDG conduits etc...) - GTG 1

2
2

05-09-2013 A
05-09-2013 A

16-01-2014 A
16-01-2014 A

26
26

Lighting & Small Power - GTG 1


YARNIMA.10.15.3.2.17 Field Equipment

100%

YARNIMA.10.15.3.4 INSTRUMENTS
A12910
Install GT1 Instruments

2
2

15-12-2013 A
15-12-2013 A

10-02-2014
10-02-2014

30
30

108
108

Field Equipment (LCS's- J.B's- HDG conduits etc...) - GTG


YARNIMA.10.15.3.4 INSTRUMENTS

10%

YARNIMA.10.15.3.5 GT1 PRE-COMMISSIONING


A13040
Mechanical Pre-Commissioning - GTG 1

44
21

03-12-2013 A
03-12-2013 A

01-04-2014
11-03-2014

1012
350

81
81

Install GT1 Instruments


YARNIMA.10.15.3.5 GT1 PRE-COMMISSION

YARNIMA.10.15.3.2.4 Cable Terminations


A12740
LV- C & I Cable Terminations - GTG 1 (Incl Cable from GTG1 to HRSG S/Room)
A12760

11kV Cable Terminations - GTG 1

84
81

Install VSD Cable - GTG 1


GTG1: GT1 INC45 Conduit does not pentrate through culwert wall
11kV Cabling - GT 1 to Switchroom
11kV Cabling Switchroom to Step Up Transformer
YARNIMA.10.15.3.2.4 Cable Terminations

74%

LV- C & I Cable Terminations - GTG 1 (Incl Cable

100%

11kV Cable Terminations - GTG 1


YARNIMA.10.15.3.2.5 Earthing and Lighting Protecti
Earthing & Lightning Protection - GTG 1
YARNIMA.10.15.3.2.7 Lighting and Small Power

90%

Mechanical Pre-Commissioning - GTG 1

A13000

Electrical Pre-Commissioning - GTG 1

21

05-12-2013 A

11-03-2014

532

81

85%

Electrical Pre-Commissioning - GTG 1

A13010

NDT & QA Documentation - GTG 1

14

18-12-2013 A

11-03-2014

50

81

65%

NDT & QA Documentation - GTG 1

A22930

Punchlisting B&C Items - GTG 1

20

01-01-2014 A

01-04-2014

81

40%

Punchlisting B&C Items - GTG 1

A13020

Lube Oil Flush (During Commissioning) - GTG 1

10

30-01-2014 A

30-03-2014

80

83

80%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 25 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Lube Oil Flush (During Commissioning) - GTG


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name
A13030

Original
Duration

Construction Verification - GTG 1

Start

Finish

YARNIMA.10.15.12 BSDG and GENERAL


YARNIMA.10.15.12.3 BSDG - ACTUAL VARIATIONS & NON SCOPE WORKS
VEGN1000
VE Site - Lube pipe welding and encasement of cooling water pipes
YARNIMA.10.15.12.1 BLACK START DIESEL GENERATORS
A2860
Cable Ladder - Switchroom

Budgeted
Labor Units

Total
Float

11-03-2014

81

253
31
31

21-04-2013 A
26-07-2013 A
26-07-2013 A

15-05-2014
09-08-2013 A
09-08-2013 A

16598
208
208

40

253
7

05-05-2013 A
05-05-2013 A

24-03-2014
27-08-2013 A

7070
549

89

Activity % S
Complete

100%

VE Site - Lube pipe welding and encasement of cooling water pipes


YARNIMA.10.15.12.1 BLACK START DIESEL

100%

17-09-2013 A

05-11-2013 A

84

A2870

Pull LV Cabling - BSDG

30

13-10-2013 A

15-03-2014

1421

89

35%

A1900

Pull 11kV Cabling GTG Switchrooms to BSDG Switchroom

12

24-10-2013 A

20-02-2014

1080

63

63%

NCR-S331

Modifications to the BSDG Switchroom Cable Ladders

31-10-2013 A

03-11-2013 A

A2880

LV Cable Terminations - BSDG

20-11-2013 A

24-03-2014

389

A2890

Earth Grid - BSDG

20-11-2013 A

20-12-2013 A

A2840

Install BSDG Switchroom

07-12-2013 A

10-02-2014*

128

NCR-S370

BSDG Switchroom Walkway Platform

11

10-12-2013 A

02-01-2014 A

NCR-S371

BSDG Switchroom Flashing

11

10-12-2013 A

02-01-2014 A

A2830

Install Black Start Generators

12

07-02-2014 A

27-02-2014

3281

89

25%

A2900

Above Ground Earthing & L.Protection - BSDG

10

11-02-2014

20-02-2014

110

0%

A2910

Lighting & Small Power - BSDG

11-02-2014

14-02-2014

135

116

0%

A1910

11KV Cable terminations - BSDG

21-02-2014

02-03-2014

101

0%

A2920

Field Equipment (LCS's- J.B's- HDG conduits etc...) - BSDG

15-03-2014

15-03-2014

89

0%

113
10

04-06-2013 A
04-06-2013 A

31-03-2014
31-03-2014

5198
564

82
82

Cable Ladder - Switchroom

100%

Install BSDG Auxiliary Transformer - BSDG


Pull LV Cabling - BSDG

Pull 11kV Cabling GTG Switchrooms to BSDG Switch

100%

Modifications to the BSDG Switchroom Cable Ladders

2%

LV Cable Terminations - BSDG

100%
110

Construction Verification - GTG 1


YARNIMA.10.15.12 BSDG and GENER
YARNIMA.10.15.12.3 BSDG - ACTUAL VARIATIONS & NON SCOPE WORKS

Install BSDG Auxiliary Transformer - BSDG

89

0%

A2850

YARNIMA.10.15.12.6 PERIMETER ROAD LIGHTING


A3150
Install lighting columns- fittings and associated equipment

Earth Grid - BSDG

90%

Install BSDG Switchroom

100%

BSDG Switchroom Walkway Platform

100%

BSDG Switchroom Flashing


Install Black Start Generators
Above Ground Earthing & L.Protection - BSDG
Lighting & Small Power - BSDG
11KV Cable terminations - BSDG

Field Equipment (LCS's- J.B's- HDG conduits etc


YARNIMA.10.15.12.6 PERIMETER ROAD LI

4%

Install lighting columns- fittings and associated

A3130

Install pits- conduits & earthing for perimeter road lighting

05-07-2013 A

15-03-2014

3945

89

98%

Install pits- conduits & earthing for perimeter road

A3110

Fire Retardant Coating and Penetration Seal to Cables

13

09-02-2014

21-02-2014

509

89

0%

Fire Retardant Coating and Penetration Seal to Cab

A3120

Trenching & excavations for underground pit and conduit system for perimeter road lighting
11

23-02-2014

05-03-2014

90

89

0%

Trenching & excavations for underground pit and c

A3140

Backfill & compaction - After Road Lighting

16-03-2014

19-03-2014

90

89

0%

YARNIMA.10.15.12.10 INSTRUMENTS
A5830
Install Instruments (Stage 2)

17
17

23-11-2013 A
23-11-2013 A

26-02-2014
26-02-2014

32
32

113
113

100%

YARNIMA.10.15.12.2 Miscellaneous Items


A20890
Type Masterflow 830 or Approved Equivalent (Cooling Water Valve Platforms)

147
7

21-04-2013 A
21-04-2013 A

15-05-2014
15-05-2014

4090
268

40
40

20%

20-02-2014

1292

63

80%

98

53.3%

A20880

Cable Tray on Pipe Racks

12

27-09-2013 A

A20900

Steam Silencers

15

28-09-2013 A

24-02-2014

450

A20910

Steam Turbine Drain Expansion Vessel

10

12-10-2013 A

23-11-2013 A

2080

A20920

Installtaion of Bollards

YARNIMA.10.15.4 HRSG-3
YARNIMA.10.15.4.2 HRSG3 - ACTUAL VARIATIONS & NON SCOPE WORKS
NCR-S149-680 Modify Client Supply Material - DA Structure Fitment

16-03-2014

24-03-2014

89

417
123
1

22-01-2013 A
17-07-2013 A
17-07-2013 A

17-04-2014
19-12-2013 A
18-07-2013 A

40491
1279
38

66

Type Masterflow 830 or Approved Equi


Cable Tray on Pipe Racks
Steam Silencers
Steam Turbine Drain Expansion Vessel

0%

Installtaion of Bollards
YARNIMA.10.15.4 HRSG-3
YARNIMA.10.15.4.2 HRSG3 - ACTUAL VARIATIONS & NON

100%

HRSG3 Burner Platform Structural Steel Issues

27

31-07-2013 A

28-08-2013 A

100%

NCR-S175

Grating Modification HRSG3 Platforms

02-08-2013 A

05-08-2013 A

100%

NCR-S176

HRSG Compressed Air Piping Material Non Compliance

32

03-08-2013 A

05-09-2013 A

100%

NCR-S184

HRSG Piping Internal Cleanliness

17

08-08-2013 A

26-08-2013 A

100%

NCR-S185

HRSG3 Feedwater Pump Valve Clash

35

09-08-2013 A

15-09-2013 A

100%

NCR-S187

HRSG3 DA Piping - Flange Out of Tolerance

12-08-2013 A

19-08-2013 A

100%

NCR-S193

Missing Footings & Pipe Supports on the South Side of HRSG3

16

17-08-2013 A

02-09-2013 A

100%

VEHRSG3000

VE HRSG3 - Replace Burner Studs, modify Top Burner Platform and clean inside of piping
4

17-08-2013 A

20-08-2013 A

78

100%

NCR-S198

HRSG3 De-aerator/ Boiler FW Pumps pipework - supports not supplied

25-08-2013 A

31-08-2013 A

100%

NCR-S184-854 Deaerator Piping - HRSG 3

53

27-08-2013 A

22-10-2013 A

274

100%

VEHRSG3010

30-08-2013 A

31-08-2013 A

30

100%

17

01-09-2013 A

18-09-2013 A

70

100%

NCR-S198-917 Modifications to Deaerator Piping Supports - HRSG 3 - A15480

Install Instruments (Stage 2)


YARNIMA.10.15.12.2 Miscellaneous Ite

100%

NCR-S168

VE HRSG3 - DA Piping - Flange Out of Tolerance

Backfill & compaction - After Road Lighting


YARNIMA.10.15.12.10 INSTRUMENTS

Modify Client Supply Material - DA Structure Fitment


HRSG3 Burner Platform Structural Steel Issues
Grating Modification HRSG3 Platforms
HRSG Compressed Air Piping Material Non Compliance
HRSG Piping Internal Cleanliness
HRSG3 Feedwater Pump Valve Clash
HRSG3 DA Piping - Flange Out of Tolerance
Missing Footings & Pipe Supports on the South Side of HRSG3

VE HRSG3 - Replace Burner Studs, modify Top Burner Platform and clean insid
HRSG3 De-aerator/ Boiler FW Pumps pipework - supports not supplied
Deaerator Piping - HRSG 3
VE HRSG3 - DA Piping - Flange Out of Tolerance
Modifications to Deaerator Piping Supports - HRSG 3 - A15480

VEHRSG3020

VE HRSG3 - Replace Burner Studs, modify Top Burner Platform and clean inside of piping
19

08-09-2013 A

27-09-2013 A

240

100%

NCR-S229

Steam Drum-Bearing plates are not welded onto saddle baseplate

10-09-2013 A

14-09-2013 A

100%

Steam Drum-Bearing plates are not welded onto saddle baseplate

NCR-S229-1028 Weld Drum Bearing Plates to Saddle Base plate - Steam Drum A15400

13-09-2013 A

17-09-2013 A

110

100%

Weld Drum Bearing Plates to Saddle Base plate - Steam Drum A15400

NCR-S251

HRSG 1, 2, & 3 - Burner Header connection details

16

19-09-2013 A

06-10-2013 A

100%

NCR-S268

No Stub Pipe Welded to Main Pipe

21

28-09-2013 A

20-10-2013 A

100%

VEHRSG3030

VE HRSG3 - Gas train Skid painting and bolting

08-10-2013 A

12-10-2013 A

82

100%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 26 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

VE HRSG3 - Replace Burner Studs, modify Top Burner Platform and clean

HRSG 1, 2, & 3 - Burner Header connection details


No Stub Pipe Welded to Main Pipe
VE HRSG3 - Gas train Skid painting and bolting
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

VEHRSG3040

VE HRSG3 - Cat Ladder Gridmesh Access Issues, S/heater Tube Bank Thermocouple18Attachments,
18-10-2013
PipingAMods,06-11-2013
Steelwork mods
A

263

100%

NCR-S316

HRSG3 Steam Drum Internal Inspection Non Conformances

51

26-10-2013 A

19-12-2013 A

100%

NCR-S337

HRSG3 Missing Bolt Hole on Column HD

10

11-11-2013 A

21-11-2013 A

20

100%

NCR-S343

HRSG3 Economiser Feedwater Piping Supports Non-Conformance

13

14-11-2013 A

27-11-2013 A

12

100%

NCR-S348

HRSG3 Non-Conformance-Clash between Economiser Feedwater Piping and Feedwater


17 RV 17-11-2013
Vent Piping A

04-12-2013 A

100%

HRSG3 Non-Conformance-Clash between Economiser Feedwa

VEHRSG3050

VE HRSG3 - Missing Bolt Holes on Column HD, Economiser Feedwater Piping Supports
4 Non-Conformance,Tundish
17-11-2013 A
20-11-2013
ET-1 Fabricated
A
62

100%

VE HRSG3 - Missing Bolt Holes on Column HD, Economiser Feed

NCR-S360

HRSG 50mm P22 Pipe Supplied Unpainted

100%

YARNIMA.10.15.4.1 HRSG3 MECHANICAL


A10640
HRSG3 Installation WBS Summary

25-11-2013 A

29-11-2013 A

335
335

24-01-2013 A
24-01-2013 A

23-02-2014
23-02-2014

16755
0

116
116

VE HRSG3 - Cat Ladder Gridmesh Access Issues, S/heater Tube Ba


HRSG3 Steam Drum Internal Inspection Non Conformances
HRSG3 Missing Bolt Hole on Column HD

HRSG3 Economiser Feedwater Piping Supports Non-Conforman

HRSG 50mm P22 Pipe Supplied Unpainted


YARNIMA.10.15.4.1 HRSG3 MECHANICAL

96.1%

HRSG3 Installation WBS Summary

A15410-a

Install Main Stack Lower Half

24-01-2013 A

25-01-2013 A

100%

A15380-a

Install Boiler Module 1

02-02-2013 A

04-02-2013 A

100%

Install Boiler Module 1

A15390-a

Install Boiler Module 2

02-02-2013 A

05-02-2013 A

100%

Install Boiler Module 2

A15540-a

Install Boiler Module 3

04-02-2013 A

05-02-2013 A

100%

Install Boiler Module 3

A15370

Install Boiler Inlet Duct - HRSG 3

32

23-03-2013 A

30-01-2014 A

2500

100%

A15460

Pre-assemble Install Deaerator Main Structure

21

17-04-2013 A

07-08-2013 A

1085

100%

NCR-S073

HRSG3 boiler inlet duct roof section between HX and HZ line, 30mm off

87

30-04-2013 A

01-08-2013 A

100%

NCR-S081

HRSG3 DA Structure Level 3 Bolt-Up Issues

17

17-05-2013 A

04-06-2013 A

100%

NCR-S084

Vertical misalignment was recorded on the HRSG3 Inlet Duct Columns

38

19-05-2013 A

27-06-2013 A

100%

NCR-S093

HRSG3: Pipe Conduits on the HRSG-3 clashes with the Baseplates

14

31-05-2013 A

14-06-2013 A

100%

A15470

Install Heat Exchanger within Deaerator Structure

11-06-2013 A

23-08-2013 A

50

100%

NCR-S128

ByPass 3: Grouting of the ByPass Stack and Diverter

19-06-2013 A

23-06-2013 A

100%

NCR-S145

HRSG3 DA Structure Packers

04-07-2013 A

05-07-2013 A

100%

HRSG3 DA Structure Packers

NCR-S149

HRSG3 DA Structural Steel Fitment Issues

07-07-2013 A

09-07-2013 A

100%

HRSG3 DA Structural Steel Fitment Issues

A15450

Install Platform Structure Above Deaerator

09-07-2013 A

08-10-2013 A

700

100%

A15500

Install CEMS - Skids (Temporary Location)

16-07-2013 A

25-09-2013 A

100

100%

Install CEMS - Skids (Temporary Location)

A22670

Insulation and Liner Plates for Inlet-Outlet Duct and Pannels

16-07-2013 A

21-09-2013 A

100%

Insulation and Liner Plates for Inlet-Outlet Duct and Pannels

NCR-S159

HRSG3: HRSG Feedwater Pump Grout

23-07-2013 A

29-07-2013 A

100%

A21340

Install Deaerator Vessel

24-07-2013 A

25-07-2013 A

220

100%

A15380

Remove Shipping Bracing and Install FLoor and Side Panels Module 1-2

16

28-07-2013 A

24-09-2013 A

2130

100%

NCR-S172

GTG2: Cast In conduits for GT2 Fuel Oil Skid Incorrect

43

01-08-2013 A

15-09-2013 A

100%

A15420

Install Upper Platforms around Steam Drum

18

07-08-2013 A

01-11-2013 A

1540

100%

NCR-S181

HRSG3 Platform Kickplates Spacing & Colour

07-08-2013 A

14-08-2013 A

100%

A21290

Install Duct Burner Structure & Baffles

10-08-2013 A

29-01-2014 A

160

100%

Install Duct Burner Structure & Baffles

A21350

Install Boiler Feedwater Pumps - HRSG 3

11-08-2013 A

02-01-2014 A

350

100%

Install Boiler Feedwater Pumps - HRSG 3

NCR-S186

HRSG3 Natural Gas Train Skid - Painting & Bolting

34

11-08-2013 A

15-09-2013 A

100%

A15430

Install Duct Burner Gas Train Skid

13-08-2013 A

09-10-2013 A

420

100%

A15510

Install Wet Racks

13-08-2013 A

19-11-2013 A

100

100%

A21280

Install Roof Panels Module 2-3

11

13-08-2013 A

25-09-2013 A

600

100%

A15390

Remove Shipping Bracing and Install FLoor and Side Panels Module 2-3 - HRSG 3 16

14-08-2013 A

28-12-2013 A

2100

100%

Remove Shipping Bracing and Install FLoor and Side Panels

A15410

Main Stack Access Ladders and Platform - HRSG3

10

14-08-2013 A

27-01-2014 A

650

100%

Main Stack Access Ladders and Platform - HRSG3

A15540

Install Roof Panels Module 1-2

11

14-08-2013 A

26-09-2013 A

600

100%

Install Roof Panels Module 1-2

A21330

Pre-assemble and Install Stair Tower (South Side)

28

15-08-2013 A

27-09-2013 A

1660

100%

Pre-assemble and Install Stair Tower (South Side)

A21300

Install Duct Burners

16-08-2013 A

01-10-2013 A

250

100%

NCR-S192

HRSG3: HRSG Duct Burner to Boiler - mounting-bolt misalignment

10

17-08-2013 A

27-08-2013 A

100%

A15490

Install Blowdown Tank

26-08-2013 A

08-10-2013 A

100

100%

A15440

Install Platform and Valve Silencers

10

26-08-2013 A

10-12-2013 A

150

100%

NCR-S206

HRSG3: HRSG 3- Deaerator Vessel- Misalignment of connecting flanges on the deaerator


3
pressure
28-08-2013
vesselA

30-08-2013 A

100%

A15400

Install Steam Drum

31-08-2013 A

27-09-2013 A

80

A21320

Install Outlet Duct & Expansion Joint - HRSG 3

12

04-09-2013 A

23-02-2014

800

NCR-S217

HRSG3 Operating Platform Gridmesh Clash

04-09-2013 A

05-09-2013 A

100%

HRSG3 Operating Platform Gridmesh Clash

NCR-S221

HRSG3: Incorrect Hole Centre of the Beam for the HRSG Steam Drums Silencer

05-09-2013 A

05-09-2013 A

100%

HRSG3: Incorrect Hole Centre of the Beam for the HRSG Steam Drums Silen

NCR-S223

HRSG3: Missing Holes for the HRSG RHS Escape Ladder

05-09-2013 A

06-09-2013 A

100%

HRSG3: Missing Holes for the HRSG RHS Escape Ladder

NCR-S224

HRSG3: HRSG Stair Tower Landing, Handrail Gaps & Stair Treads Rise

06-09-2013 A

12-09-2013 A

100%

NCR-S226

HRSG3: Incorrect Location of the Bolt Holes for the Knee Brace (Grid HG) of the Top 20
Platform08-09-2013 A

28-09-2013 A

100%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 27 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Install Main Stack Lower Half

Install Boiler Inlet Duct - HRSG 3


Pre-assemble Install Deaerator Main Structure
HRSG3 boiler inlet duct roof section between HX and HZ line, 30mm off
HRSG3 DA Structure Level 3 Bolt-Up Issues
Vertical misalignment was recorded on the HRSG3 Inlet Duct Columns
HRSG3: Pipe Conduits on the HRSG-3 clashes with the Baseplates
Install Heat Exchanger within Deaerator Structure
ByPass 3: Grouting of the ByPass Stack and Diverter

Install Platform Structure Above Deaerator

HRSG3: HRSG Feedwater Pump Grout


Install Deaerator Vessel
Remove Shipping Bracing and Install FLoor and Side Panels Module 1-2
GTG2: Cast In conduits for GT2 Fuel Oil Skid Incorrect
Install Upper Platforms around Steam Drum
HRSG3 Platform Kickplates Spacing & Colour

HRSG3 Natural Gas Train Skid - Painting & Bolting


Install Duct Burner Gas Train Skid
Install Wet Racks
Install Roof Panels Module 2-3

Install Duct Burners


HRSG3: HRSG Duct Burner to Boiler - mounting-bolt misalignment
Install Blowdown Tank
Install Platform and Valve Silencers

HRSG3: HRSG 3- Deaerator Vessel- Misalignment of connecting flanges on the

100%
116

Install Steam Drum

98%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Install Outlet Duct & Expansion Joint - HRSG 3

HRSG3: HRSG Stair Tower Landing, Handrail Gaps & Stair Treads Rise

HRSG3: Incorrect Location of the Bolt Holes for the Knee Brace (Grid HG)
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

NCR-S256

HRSG 1, 2, & 3 - Steam Drum hold-down bolts

20-09-2013 A

20-09-2013 A

100%

A21310

Install Main Stack Upper Half

21-09-2013 A

19-10-2013 A

200

100%

NCR-S261

HRSG3 Steam Drum Area Ladder Landing Modifications

24-09-2013 A

30-09-2013 A

100%

NCR-S297

HRSG3 Clash of flexible hose and steel

17-10-2013 A

22-10-2013 A

100%

HRSG3 Clash of flexible hose and steel

NCR-S314

HRSG HP Feedwater Pump Cooling Water Piping Flow Switch Installation

25-10-2013 A

25-10-2013 A

100%

HRSG HP Feedwater Pump Cooling Water Piping Flow Switch Installa

NCR-S317

HRSG3 Stair Tower Steel Structure Non-Conformance

13

26-10-2013 A

08-11-2013 A

100%

NCR-S319

Removal of Coupling from HRSG3 Boiler Feed Pump No.2

27-10-2013 A

01-11-2013 A

100%

NCR-S322

HRSG3 Kick Plates in the Way of Welding Soppers for Deaerator Support

13

27-10-2013 A

09-11-2013 A

100%

NCR-S349

HRSG3 Tundish ET-1 Fabricated Not in Compliance with the Construction Drawing 5

17-11-2013 A

21-11-2013 A

100%

HRSG3 Tundish ET-1 Fabricated Not in Compliance with the Con

NCR-S356

HRSG3 Stack Drain Piping Construction Drawing Design Errors

22-11-2013 A

22-11-2013 A

100%

HRSG3 Stack Drain Piping Construction Drawing Design Errors

A21360

Install Chemical Dosing Facility - HRSG 3

11-12-2013 A

18-12-2013 A

210

100%

201
169
20

28-07-2013 A
05-08-2013 A
05-08-2013 A

29-03-2014
10-03-2014
16-02-2014

8314
2514
960

YARNIMA.10.15.4.6 HRSG3 PIPING


YARNIMA.10.15.4.6.2 Boiler Feed Water System
A15480
Deaerator Piping - HRSG 3

84
84
75

HRSG 1, 2, & 3 - Steam Drum hold-down bolts


Install Main Stack Upper Half
HRSG3 Steam Drum Area Ladder Landing Modifications

HRSG3 Stair Tower Steel Structure Non-Conformance


Removal of Coupling from HRSG3 Boiler Feed Pump No.2

HRSG3 Kick Plates in the Way of Welding Soppers for Deaerator S

Install Chemical Dosing Facility - HRSG 3


YARNIMA.10.15.4.6 HRSG3 PIPING
YARNIMA.10.15.4.6.2 Boiler Feed Water System

95%

Deaerator Piping - HRSG 3

A16350

Boiler Feedwater Piping - HRSG 3

18

10-08-2013 A

16-01-2014 A

930

100%

NCR-S190

HRSG3 Valve Packaging

12

15-08-2013 A

27-08-2013 A

100%

NCR-S203

HRSG3 De-aerator Pipework. Orifice plate assy wrong material

20

26-08-2013 A

15-09-2013 A

100%

NCR-S218

HRSG3 DA Expansion Chamber

04-09-2013 A

05-09-2013 A

100%

NCR-S240

HRSG3 DA Piping Fabrication Non Conformance

16-09-2013 A

17-09-2013 A

100%

NCR-S249

HRSG 1, 2, & 3 - Small-bore P/W - Missing Material/painting requirements

18-09-2013 A

24-09-2013 A

100%

NCR-S272

HRSG3: Cooling Water System Reducer

01-10-2013 A

02-10-2013 A

100%

NCR-S299

HRSG3: HRSG 3 - High Pressure Steam Valve Machining

23-10-2013 A

25-10-2013 A

100%

NCR-S326

HRSG3 HP Feedwater RV Vent Piping Support Non-Conformance

29-10-2013 A

01-11-2013 A

100%

HRSG3 HP Feedwater RV Vent Piping Support Non-Conformance

NCR-S333

HRSG3 Wet Rack Drain Lines

01-11-2013 A

01-11-2013 A

100%

HRSG3 Wet Rack Drain Lines

NCR-S333-1361
HRSG3 Wet Rack Drain Lines (1361)

01-11-2013 A

04-11-2013 A

34

100%

HRSG3 Wet Rack Drain Lines (1361)

NCR-S387

HRSG Wrong Bolting Materials for Deaerator Safety Valves

19-12-2013 A

19-12-2013 A

100%

A22700

Install Insulation (BFW & Deaerator piping) - HRSG 3

18

08-01-2014 A

10-03-2014

500

84

40%

Install Insulation (BFW & Deaerator piping) - HRS

A22690-a

Hydrotest (BFW & Deaerator piping) - HRSG 3

18-02-2014

23-02-2014

90

84

0%

193
18

28-07-2013 A
28-07-2013 A

29-03-2014
27-01-2014 A

4340
320

84

Hydrotest (BFW & Deaerator piping) - HRSG 3


YARNIMA.10.15.4.6.3 Boiler Water & Steam S

75

YARNIMA.10.15.4.6.3 Boiler Water & Steam System


A16360
Boiler Circulation Piping - HRSG 3

Boiler Feedwater Piping - HRSG 3


HRSG3 Valve Packaging
HRSG3 De-aerator Pipework. Orifice plate assy wrong material
HRSG3 DA Expansion Chamber
HRSG3 DA Piping Fabrication Non Conformance

HRSG 1, 2, & 3 - Small-bore P/W - Missing Material/painting requirements


HRSG3: Cooling Water System Reducer
HRSG3: HRSG 3 - High Pressure Steam Valve Machining

HRSG Wrong Bolting Materials for Deaerator Safety Valves

100%

Boiler Circulation Piping - HRSG 3

A16390

Main Steam Line Piping - HRSG 3

25

18-08-2013 A

21-02-2014

1350

A16620

HRSG Economiser Feedwater Piping - HRSG 3

13

18-08-2013 A

16-01-2014 A

280

100%

A16610

HRSG Vents & Drains - Drum Safety Valve 1 Vent - HRSG 3

16

22-08-2013 A

29-01-2014 A

350

100%

A16600

HRSG Vents & Drains - Drum Safety Valve 2 Vent - HRSG 3

16

23-08-2013 A

29-01-2014 A

200

100%

NCR-S222

HRSG3: Valve H1LAD21AA002 Wrong Bore Size

13

05-09-2013 A

18-09-2013 A

100%

NCR-S259

HRSG 1, 2, & 3 - HP Sat. Steam lines Missing Pipe Shoes

22-09-2013 A

29-09-2013 A

100%

HRSG 1, 2, & 3 - HP Sat. Steam lines Missing Pipe Shoes

NCR-S262

HRSG3 Economiser Feedwater Piping Check Valve Modification

24-09-2013 A

25-09-2013 A

100%

HRSG3 Economiser Feedwater Piping Check Valve Modification

A16340

Steam & Water Sampling Piping

16

06-10-2013 A

14-01-2014 A

200

100%

A16400

Blow Down System Piping - HRSG 3

13

11-10-2013 A

29-01-2014 A

500

100%

NCR-S302

HRGS3: Vendor Fabricated Piping Spools Not in Compliance with Design Drawings 10

21-10-2013 A

30-10-2013 A

100%

HRGS3: Vendor Fabricated Piping Spools Not in Compliance with De

NCR-S313

HRSG Blowdown Tank Piping H1LCQ86BR714 Clash with Support

25-10-2013 A

28-10-2013 A

100%

HRSG Blowdown Tank Piping H1LCQ86BR714 Clash with Support

NCR-S323

HRSG3 Dry Panel-Wrong Materials on Dwg E-0002252-H1QUL40BR730

28-10-2013 A

30-10-2013 A

100%

HRSG3 Dry Panel-Wrong Materials on Dwg E-0002252-H1QUL40BR

NCR-S367

HRSG Boiler Drain Reducer Non-conformance

07-12-2013 A

15-12-2013 A

100%

HRSG Boiler Drain Reducer Non-conformance

NCR-S384

HRSG Missing Design of Drain Piping Connecting Steam Drum Safety Valve Discharge1 Piping 18-12-2013
and Vent A

18-12-2013 A

100%

HRSG Missing Design of Drain Piping Connecting Steam Drum

A22710

Hydrotest (Main Steam) - HRSG 3

23-02-2014

27-02-2014

90

94

0%

Hydrotest (Main Steam) - HRSG 3

A22720

Install Insulation (Main Steam) - HRSG 3

18

11-03-2014

29-03-2014

1050

84

0%

43
10

21-08-2013 A
21-08-2013 A

01-03-2014
10-01-2014 A

1460
300

110

Install Insulation (Main Steam) - HRSG 3


YARNIMA.10.15.4.6.4 Boiler BOP Systems

YARNIMA.10.15.4.6.4 Boiler BOP Systems


A15520
Instrument Air Supply and Plant Air Piping - HRSG 3

98%

Main Steam Line Piping - HRSG 3


HRSG Economiser Feedwater Piping - HRSG 3

HRSG Vents & Drains - Drum Safety Valve 1 Vent - HR

HRSG Vents & Drains - Drum Safety Valve 2 Vent - HR


HRSG3: Valve H1LAD21AA002 Wrong Bore Size

Steam & Water Sampling Piping


Blow Down System Piping - HRSG 3

100%

Instrument Air Supply and Plant Air Piping - HRSG 3

A16380

Gas Piping - HRSG 3

10

23-08-2013 A

29-01-2014 A

220

100%

A16370

Ignition & Cooling Air Supply Piping - HRSG 3

10

15-09-2013 A

16-01-2014 A

120

100%

A15530

Install Insulation - Steam Sampling Piping - HRSG 3

18

21-09-2013 A

01-03-2014

500

110

90%

Install Insulation - Steam Sampling Piping - HRSG

A16410

Chemical Dosing and Steam Sampling Tubing - HRSG 3

27-11-2013 A

17-02-2014

230

110

80%

Chemical Dosing and Steam Sampling Tubing - HRS

A16380-N2_Sys
HRSG N2 system. New Drawings: Runs from ground to Steam Drum level on each HRSG
1

09-02-2014*

09-02-2014

122

0%

HRSG N2 system. New Drawings: Runs from ground

A6400

18-02-2014

23-02-2014

90

110

0%

244

23-05-2013 A

26-03-2014

6953

73

Leak Test of Gas and Air supply Piping - HRSG 3


YARNIMA.10.15.4.13 HRSG3 ELECTRICAL

Leak Test of Gas and Air supply Piping - HRSG 3

YARNIMA.10.15.4.13 HRSG3 ELECTRICAL


Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 28 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Gas Piping - HRSG 3


Ignition & Cooling Air Supply Piping - HRSG 3

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A2460

Cable Ladder - HRSG structure North - HRSG 3

23-05-2013 A

23-02-2014

1148

66

24%

A10690

HRSG3 Electrical WBS Summary

244

23-05-2013 A

26-03-2014

73

0%

A2460-a

Cable Ladder - HRSG structure South - HRSG 3

14

23-05-2013 A

17-02-2014

71

65%

NCR-S116

GTG3: Conduits direction

77

09-06-2013 A

30-08-2013 A

100%

A2450

Cable Ladder - Switchroom

19-08-2013 A

08-10-2013 A

425

100%

NCR-S200

HRSG3: Inconsistencies of the Supply and Designed of Cable Ladder Supports for the7HRSG 25-08-2013 A

31-08-2013 A

100%

NCR-S208

HRSG3 Stair Towers Swivel Poles

16

30-08-2013 A

15-09-2013 A

100%

A2510-a

Install Lighting & Small Power South - HRSG 3

17-09-2013 A

06-03-2014

A2430

Install HRSG3 Switchroom

20-09-2013 A

14-10-2013 A

168

NCR-S254

BOP: The conduit (H3LVC01-04) is too small for the amount of cables

20-09-2013 A

25-09-2013 A

A2510

Lighting & Small Power North - HRSG 3

25

24-09-2013 A

12-03-2014

294

86

15%

Lighting & Small Power North - HRSG 3

A2470

Pull LV-C&I Cabling - HRSG 3

25

29-09-2013 A

11-03-2014

1856

66

1%

Pull LV-C&I Cabling - HRSG 3

NCR-S278

HRSG3: 3 Switchroom Support Beams

10-10-2013 A

16-10-2013 A

A2530

Install On-Skid Elec Equipment & Instruments - HRSG 3

35

11-10-2013 A

24-03-2014

2563

NCR-S292

Non-Conformities within the HRSG3 Switchroom

13

16-10-2013 A

29-10-2013 A

A2480

LV-C&I Cable Terminations - HRSG 3

28

04-11-2013 A

26-03-2014

422

66

0.5%

A2490

Earthing Systems - HRSG 3

27-01-2014 A

19-02-2014

105

50%

A2520

Field Equipment (LCS's- J.B's- HDG conduits etc...) - HRSG 3

10

09-02-2014

106

0%

191
22-01-2013 A
YARNIMA.10.15.4.7 HRSG3 BYPASS STACK & DAMPERS
NCR-S030
ByPass 3: GT3 Bypass Stack: The Vendor Supplier have not included the supply of handrail
13
bolts
22-01-2013 A

91

Cable Ladder - HRSG structure North - HRSG 3


HRSG3 Electrical WBS Summary
Cable Ladder - HRSG structure South - HRSG 3
GTG3: Conduits direction
Cable Ladder - Switchroom

HRSG3: Inconsistencies of the Supply and Designed of Cable Ladder Supports


HRSG3 Stair Towers Swivel Poles

15%

Install Lighting & Small Power South - HRSG 3

100%

Install HRSG3 Switchroom

100%

BOP: The conduit (H3LVC01-04) is too small for the amount of cables

100%
75

HRSG3: 3 Switchroom Support Beams

90%

Install On-Skid Elec Equipment & Instruments -

100%

18-02-2014

77

10-10-2013 A
04-02-2013 A

4740
0

100%

Non-Conformities within the HRSG3 Switchroom


LV-C&I Cable Terminations - HRSG 3
Earthing Systems - HRSG 3
Field Equipment (LCS's- J.B's- HDG conduits etc...)
YARNIMA.10.15.4.7 HRSG3 BYPASS STACK & DAMPERS
ByPass 3: GT3 Bypass Stack: The Vendor Supplier have not included the supply of handrail bolts

A5350

Install Bottom Section (Damper + Duct)

21

05-02-2013 A

11-05-2013 A

1160

100%

A6420

Install By-Pass Structural Supports

21

16-02-2013 A

20-07-2013 A

850

100%

A6450

Install By-Pass Silencer Assembly

18-02-2013 A

10-04-2013 A

735

100%

NCR-S016

ByPass 3: Missing Bypass Stack Bolts

13

20-02-2013 A

05-03-2013 A

100%

ByPass 3: Missing Bypass Stack Bolts

NCR-S017

GTG3: GT3- Steel Work For Platform And Cross Bracing For Enclosure

13

21-02-2013 A

06-03-2013 A

100%

GTG3: GT3- Steel Work For Platform And Cross Bracing For Enclosure

NCR-S018

ByPass 3: Bypass Stack - Silencer Outlet Transition - Remove and refit cladding

13

21-02-2013 A

06-03-2013 A

100%

ByPass 3: Bypass Stack - Silencer Outlet Transition - Remove and refit cladding

A6430

Stack Tube Lower Section

23-02-2013 A

27-04-2013 A

720

100%

Stack Tube Lower Section

A6460

Stack Tube Upper Section

05-03-2013 A

27-04-2013 A

550

100%

Stack Tube Upper Section

NCR-S029

ByPass 3: Bypass Stack Platform: Incorrect Supply of Gridmesh, Wrong Location of Bolt
13 Holes,05-03-2013
Handrails gaps.
A
18-03-2013 A

100%

ByPass 3: Bypass Stack Platform: Incorrect Supply of Gridmesh, Wrong Location of Bolt Holes, Handrails

NCR-S037

ByPass 3: Bypass Stack Ladder and Platform Support Assembly : 2 x Beams were supplied
13
too22-03-2013
long
A

04-04-2013 A

100%

ByPass 3: Bypass Stack Ladder and Platform Support Assembly : 2 x Beams were supplied too long

A9050

Install By-Pass Access Ladders & Platforms

23-03-2013 A

26-07-2013 A

725

100%

NCR-S044

ByPass 3: Mounting for the Seal Air Unit Fans for HRSG-3 have been damaged.

13

29-03-2013 A

11-04-2013 A

100%

ByPass 3: Mounting for the Seal Air Unit Fans for HRSG-3 have been damaged.

NCR-S049

ByPass 3: Guillotine mounting bracket us out of alignment.

13

01-04-2013 A

14-04-2013 A

100%

ByPass 3: Guillotine mounting bracket us out of alignment.

NCR-S074

ByPass 3: HRSG3 ByPass Stack Handrails have no Caps

08-05-2013 A

09-05-2013 A

100%

NCR-S082

ByPass 3: HRSG3 Bypass Stack cast-in hold down bolts and baseplates misalignment17

17-05-2013 A

04-06-2013 A

100%

ByPass 3: HRSG3 Bypass Stack cast-in hold down bolts and baseplates misalignment

NCR-S085

HRSG3 Modules and ByPass Stack Structure Vertical misalignment

16

19-05-2013 A

04-06-2013 A

100%

HRSG3 Modules and ByPass Stack Structure Vertical misalignment

NCR-S125

ByPass 3: Liner Panels too long

13

17-06-2013 A

30-06-2013 A

100%

NCR-S148

ByPass 3: GTG3 to ByPass Stack Expansion Joint Area - Studs Don't Line Up

06-07-2013 A

09-07-2013 A

100%

A21080

Final punchlisting A-Items and Construciton Verification

19

14-07-2013 A

10-10-2013 A

100%

NCR-S173

ByPass 3: ByPass Stack 3 CEMS Flange Alignment

28

01-08-2013 A

30-08-2013 A

100%

NCR-S177

ByPass 2: ByPass Stack 2 Ladder Mounts

19

03-08-2013 A

22-08-2013 A

100%

NCR-S195

STG1-Lube-Oil Outlet - Flange Misalignment at Oil Tank

17

19-08-2013 A

05-09-2013 A

100%

79
20

16-12-2013 A
16-12-2013 A

17-04-2014
01-03-2014

2450
1050

66
110

STG1-Lube-Oil Outlet - Flange Misalignment at Oil Tank


YARNIMA.10.15.4.5 HRSG3 PRECOMMIS

YARNIMA.10.15.4.5 HRSG3 PRECOMMISSIONING


A10320
Mechanical Pre-Commissioning and punchlisting A-Items - HRSG 3

Install Bottom Section (Damper + Duct)


Install By-Pass Structural Supports
Install By-Pass Silencer Assembly

Install By-Pass Access Ladders & Platforms

ByPass 3: HRSG3 ByPass Stack Handrails have no Caps

ByPass 3: Liner Panels too long


ByPass 3: GTG3 to ByPass Stack Expansion Joint Area - Studs Don't Line Up
Final punchlisting A-Items and Construciton Verification
ByPass 3: ByPass Stack 3 CEMS Flange Alignment
ByPass 2: ByPass Stack 2 Ladder Mounts

55%

Mechanical Pre-Commissioning and punchlisting A-

A10330

NDT & QA Documentation - HRSG 3

14

01-01-2014 A

01-03-2014

280

110

80%

NDT & QA Documentation - HRSG 3

A22870

Punchlisting B&C Items - HRSG 3

14

05-02-2014 A

17-04-2014

651

66

10%

A10310

Electrical Pre-Commissioning and punchlisting A-Items - HRSG 3

20

13-03-2014

02-04-2014

469

66

0%

Electrical Pre-Commissioning and punchlisting

A10350

Construction Verification - HRSG 3

02-04-2014

80

0%

61

Construction Verification - HRSG 3


YARNIMA.10.15.5 HRSG-2
YARNIMA.10.15.5.3 HRSG2 - ACTUAL VARIATIONS & NON

YARNIMA.10.15.5 HRSG-2
YARNIMA.10.15.5.3 HRSG2 - ACTUAL VARIATIONS & NON SCOPE WORKS
NCR-S215
HRSG2 DA Pipework - Flange Misaligned on Line # HILCA30BR010/015

343
102
7

05-02-2013 A
01-09-2013 A
01-09-2013 A

23-04-2014
19-12-2013 A
08-09-2013 A

39666
307
0

Punchlisting B&C Items - HRSG 3

100%

HRSG2 DA Pipework - Flange Misaligned on Line # HILCA30BR010/015

NCR-S216

HRSG2 DA Pipework - Bowed Spool on #HIGHC20BR070/BR071

02-09-2013 A

11-09-2013 A

100%

HRSG2 DA Pipework - Bowed Spool on #HIGHC20BR070/BR071

NCR-S219

HRSG2 Inlet Duct Roof Misalignment

05-09-2013 A

09-09-2013 A

100%

HRSG2 Inlet Duct Roof Misalignment

VEHRSG2010

VE HRSG2 - Temporary supports for HRSG Boiler Module, Inlet Duct Roof Misaligned,4 DA Struct
13-09-2013
Upper Level
A Fitment
16-09-2013
Issue A

115

100%

70

100%

NCR-S219-1003 HRSG2 Inlet Duct Roof Misalignment -Rework


Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

15-09-2013 A

Page 29 of 38
Data Date 07-02-2014

18-09-2013 A

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

VE HRSG2 - Temporary supports for HRSG Boiler Module, Inlet Duct Roof M
HRSG2 Inlet Duct Roof Misalignment -Rework
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

26

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

NCR-S294

HRSG2 Modification on Dearator nozzle N10 flange raised face

17-10-2013 A

13-11-2013 A

100%

VEHRSG2000

VE HRSG2 - Modify Dearator Structure Cleat, spool underside deaerator silencer, LAA90BR704
5
24-10-2013
spool 1&2A

28-10-2013 A

116

100%

VE HRSG2 - Modify Dearator Structure Cleat, spool underside deaera

NCR-S318

HRSG2 Deaerator Piping Flange Damage LAA90BR704 Spool 1 & 2

HRSG2 Deaerator Piping Flange Damage LAA90BR704 Spool 1 &

HRSG2 Modification on Dearator nozzle N10 flange raised face

13

27-10-2013 A

09-11-2013 A

100%

NCR-S294-1252 Deaerator Piping - HRSG2

18-11-2013 A

18-11-2013 A

100%

NCR-S354

29

19-11-2013 A

19-12-2013 A

100%

296
296

05-02-2013 A
05-02-2013 A

11-03-2014
11-03-2014

16821
0

HRSG2 Steam Drum Internal Inspection Non Conformances


YARNIMA.10.15.5.2 HRSG2 MECHANICAL

0%

HRSG2 Installation WBS Summary

HRSG2 Steam Drum Internal Inspection Non Conformances

YARNIMA.10.15.5.2 HRSG2 MECHANICAL


A10980
HRSG2 Installation WBS Summary

94
94

Deaerator Piping - HRSG2

A13090-a

Install Main Stack Lower Half

05-02-2013 A

07-02-2013 A

100%

Install Main Stack Lower Half

A13940-a

Install Boiler Module 2

05-02-2013 A

08-02-2013 A

100%

Install Boiler Module 2

A15550-a

Install Boiler Module 3

05-02-2013 A

08-02-2013 A

100%

Install Boiler Module 3

A13060-a

Install Boiler Module 1

14-02-2013 A

15-02-2013 A

100%

A13060

Remove Shipping Bracing and Install FLoor and Side Panels Module 1-2

13

01-08-2013 A

28-10-2013 A

2130

100%

A13090

Main Stack Access Ladders and Platform - HRSG 2

10

04-08-2013 A

11-02-2014

650

A13050

Install Boiler Inlet Duct - HRSG 2

22

15-08-2013 A

29-01-2014 A

2500

100%

Install Boiler Inlet Duct - HRSG 2

A13940

Remove Shipping Bracing and Install FLoor and Side Panels 2 Module 2-3 - HRSG 2 13

18-08-2013 A

29-01-2014 A

2100

100%

Remove Shipping Bracing and Install FLoor and Side Pa

A13110

Pre-assemble Install Deaerator Main Structure

12

22-08-2013 A

24-09-2013 A

1085

100%

A13120

Install Platform Structure Above Deaerator - HRSG 2

25-08-2013 A

14-12-2013 A

700

100%

A21220

Install Heat Exchanger within Deaerator Structure

27-08-2013 A

12-09-2013 A

50

100%

Install Heat Exchanger within Deaerator Structure

A13080

Install Duct Burner Gas Train Skid

28-08-2013 A

11-09-2013 A

420

100%

Install Duct Burner Gas Train Skid

A13140

Install Deaerator Vessel

28-08-2013 A

26-09-2013 A

220

100%

A13160

Install Blowdown Tank

29-08-2013 A

11-09-2013 A

100

100%

NCR-S214

HRSG2 Module Beams Incorrect Colour

01-09-2013 A

01-09-2013 A

100%

NCR-S225

HRSG2 DA Structure Upper Level Fitment Issues

06-09-2013 A

12-09-2013 A

100%

A15550

Install Roof Panels Module 1-2 - HRSG 2

10-09-2013 A

29-01-2014 A

600

100%

NCR-S225-1016 HRSG2 DA Structure Upper Level Fitment Adjustments

13-09-2013 A

13-09-2013 A

11

100%

A21170

Install Duct Burner Structure & Baffles - HRSG 2

14-09-2013 A

06-02-2014 A

160

100%

NCR-S237

HRSG2 - Panels Incorrect Length

14-09-2013 A

14-09-2013 A

100%

HRSG2 - Panels Incorrect Length

NCR-S237-1060 HRSG2 - Trim upper Panels LWP1A, LWP2A, RWP1A and RWP2A to enable panels to
1 fit

14-09-2013 A

15-09-2013 A

15

100%

HRSG2 - Trim upper Panels LWP1A, LWP2A, RWP1A and RWP2A to enab

NCR-S238

HRSG2 Dearator - Not enough space for bolt installation

15-09-2013 A

15-09-2013 A

100%

HRSG2 Dearator - Not enough space for bolt installation

NCR-S241

HRSG2: Incorrect Alignment of the Stiffener welded to the Column for the Cross Bracing
1

18-09-2013 A

18-09-2013 A

100%

HRSG2: Incorrect Alignment of the Stiffener welded to the Column for the C

NCR-S263

HRSG2 Modifications on Inlet Duct Casing Plate

24-09-2013 A

25-09-2013 A

100%

A21160

Install Roof Panels Module 2-3 - HRSG 2

26-09-2013 A

29-01-2014 A

600

100%

NCR-S265

HRSG2 Dearator Structure Cleat Modification

29

26-09-2013 A

26-10-2013 A

100%

A21230

Install Boiler Feedwater Pumps - HRSG 2

27-09-2013 A

20-12-2013 A

350

100%

A22680

Insulation and Liner Plates for Inlet-Outlet Duct and Pannels - HRSG 2

25

27-09-2013 A

20-02-2014

A21190

Install Main Stack Upper Half

30-09-2013 A

08-10-2013 A

200

A21200

Install Outlet Duct - HRSG 2

12

01-10-2013 A

20-02-2014

800

A21180

Install Duct Burners - HRSG 2

02-10-2013 A

02-01-2014 A

250

100%

A21210

Pre-assemble and Install Stair Tower (South Side)

21

02-10-2013 A

29-10-2013 A

1660

100%

09-10-2013 A

10-10-2013 A

20

100%

NCR-S248-1670 ByPass 2: ByPass Stack 2 realign CEMS flange


A13130

Install Wet Racks - HRSG 2

11-10-2013 A

15-01-2014 A

100

A13100

Install Upper Platforms around Steam Drum - HRSG 2

12

20-10-2013 A

27-02-2014

1540

NCR-S310

HRSG2: Stair Tower Painting Not in Compliance with Painting Specification

23-10-2013 A

26-10-2013 A

NCR-S265-1151 HRSG2 Dearator Structure Cleat Reposition cleat

27-10-2013 A

NCR-S327

HRSG2 Duct Burner to Boiler - Mounting Bolt Misalignment

30-10-2013 A

A13180

Install Platform and Valve Silencers - HRSG 2

10

A13170

Install CEMS - Skids - HRSG 2

A13070
A21240

52

86

Install Boiler Module 1

Remove Shipping Bracing and Install FLoor and Side Panels Module 1

95%

Main Stack Access Ladders and Platform - HRSG 2

Pre-assemble Install Deaerator Main Structure


Install Platform Structure Above Deaerator - HRSG 2

Install Deaerator Vessel


Install Blowdown Tank
HRSG2 Module Beams Incorrect Colour
HRSG2 DA Structure Upper Level Fitment Issues
Install Roof Panels Module 1-2 - HRSG 2
HRSG2 DA Structure Upper Level Fitment Adjustments
Install Duct Burner Structure & Baffles - HRSG 2

HRSG2 Modifications on Inlet Duct Casing Plate


Install Roof Panels Module 2-3 - HRSG 2
HRSG2 Dearator Structure Cleat Modification
Install Boiler Feedwater Pumps - HRSG 2

50%

Insulation and Liner Plates for Inlet-Outlet Duct and P

100%
43

Install Main Stack Upper Half

95%

Install Outlet Duct - HRSG 2


Install Duct Burners - HRSG 2
Pre-assemble and Install Stair Tower (South Side)
ByPass 2: ByPass Stack 2 realign CEMS flange

100%

Install Wet Racks - HRSG 2

95%

Install Upper Platforms around Steam Drum - HRS

100%

HRSG2: Stair Tower Painting Not in Compliance with Painting Specific

28-10-2013 A

20

100%

HRSG2 Dearator Structure Cleat Reposition cleat

31-10-2013 A

100%

HRSG2 Duct Burner to Boiler - Mounting Bolt Misalignment

23-11-2013 A

03-03-2014

150

05-01-2014 A

02-02-2014 A

100

Install Steam Drum - HRSG 2

06-01-2014 A

10-02-2014

80

Install Chemical Dosing - HRSG 2

04-03-2014

11-03-2014

210

148
106
20

01-09-2013 A
01-09-2013 A
01-09-2013 A

15-04-2014
16-03-2014
20-02-2014

YARNIMA.10.15.5.6 HRSG2 PIPING


YARNIMA.10.15.5.6.1 Boiler Feed Water System
A13150
Deaerator Piping - HRSG2

25%

Install Steam Drum - HRSG 2

94

0%

8320
2520
960

61
61
68

70%

61

70%

21-09-2013 A

24-02-2014

930

NCR-S321

HRSG2: Deaerator Expansion Chamber EC-3B

27-10-2013 A

29-10-2013 A

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Page 30 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Install Platform and Valve Silencers - HRSG 2

52

18

Summary

50%

Install CEMS - Skids - HRSG 2

Boiler Feedwater Piping - HRSG2

Primary Baseline

94

100%

A16630

Actual Work

43

Install Chemical Dosing - HRSG 2


YARNIMA.10.15.5.6 HRSG2 PIPING
YARNIMA.10.15.5.6.1 Boiler Feed Water Syste
Deaerator Piping - HRSG2
Boiler Feedwater Piping - HRSG2

100%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

HRSG2: Deaerator Expansion Chamber EC-3B


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float
61

Activity % S
Complete

25%

A22740

Install Insulation BFW & Deaerator piping) - HRSG2

14

27-11-2013 A

16-03-2014

500

NCR-S376

HRSG2 Deaerator Piping Fabrication Non-Conformance

11-12-2013 A

13-12-2013 A

100%

HRSG2 Deaerator Piping Fabrication Non-Conformance

NCR-S376-1569
HRSG2 Deaerator Piping Fabrication rectification

15-12-2013 A

17-12-2013 A

40

100%

HRSG2 Deaerator Piping Fabrication rectification

A22730

Hydrotest (BFW & Deaerator piping) - HRSG2

25-02-2014

01-03-2014

90

61

0%

YARNIMA.10.15.5.6.3 Boiler Water & Steam System


A16720
HRSG Economiser Feedwater Piping - HRSG2

97
12

06-09-2013 A
06-09-2013 A

31-03-2014
18-02-2014

4340
280

61
65

Install Insulation BFW & Deaerator piping) - HRS

Hydrotest (BFW & Deaerator piping) - HRSG2


YARNIMA.10.15.5.6.3 Boiler Water & Steam

55%

HRSG Economiser Feedwater Piping - HRSG2

A16640

Boiler Circulation Piping - HRSG2

18

11-10-2013 A

18-02-2014

320

65

70%

Boiler Circulation Piping - HRSG2

A16670

Main Steam Line Piping - HRSG2

20

04-11-2013 A

09-03-2014

1350

63

65%

Main Steam Line Piping - HRSG2

A16700

HRSG Vents & Drains - Drum Safety Valve 2 Vent - HRSG2

10

25-11-2013 A

10-03-2014

200

62

45%

HRSG Vents & Drains - Drum Safety Valve 2 Ven

A16710

HRSG Vents & Drains - Drum Safety Valve 1 Vent - HRSG2

10

27-11-2013 A

10-03-2014

350

62

45%

HRSG Vents & Drains - Drum Safety Valve 1 Ven

A16680

Blow Down System Piping - HRSG2

28-11-2013 A

15-03-2014

500

62

65%

A16420

Steam & Water Sampling Piping - HRSG2

10

28-01-2014 A

25-03-2014

200

62

25%

A22760

Hydrotest (Main Steam) - HRSG2

10-03-2014

14-03-2014

90

63

0%

A22750

Install Insulation (Main Steam) - HRSG2

14

17-03-2014

31-03-2014

1050

61

0%

62
5

02-10-2013 A
02-10-2013 A

15-04-2014
19-03-2014

1460
120

61
62

YARNIMA.10.15.5.6.4 Boiler BOP Systems


A16650
Ignition & Cooling Air Supply Piping - HRSG2

Blow Down System Piping - HRSG2


Steam & Water Sampling Piping - HRSG2
Hydrotest (Main Steam) - HRSG2

Install Insulation (Main Steam) - HRSG2


YARNIMA.10.15.5.6.4 Boiler BOP Systems

50%

Ignition & Cooling Air Supply Piping - HRSG2

A13190

Instrument Air Supply Piping - HRSG2

10

16-12-2013 A

15-03-2014

300

62

40%

Instrument Air Supply Piping - HRSG2

A16660

Gas Piping - HRSG2

10

06-01-2014 A

19-03-2014

220

62

25%

Gas Piping - HRSG2

A16690

Chemical Dosing and Steam Sampling Tubing - HRSG2

20-03-2014

25-03-2014

230

62

0%

Chemical Dosing and Steam Sampling Tubing -

A13320

Leak Test of Gas and Air supply Piping - HRSG2

26-03-2014

30-03-2014

90

62

0%

Leak Test of Gas and Air supply Piping - HRSG

A13220

Install Insulation - Steam Sampling Piping - HRSG2

14

01-04-2014

15-04-2014

500

61

0%

198
198

16-08-2013 A
16-08-2013 A

04-04-2014
04-04-2014

7028
0

71
71

Install Insulation - Steam Sampling Piping - H


YARNIMA.10.15.5.13 HRSG2 ELECTRICAL

0%

HRSG2 Electrical WBS Summary

62

5%

YARNIMA.10.15.5.13 HRSG2 ELECTRICAL


A11010
HRSG2 Electrical WBS Summary
A13270

Lighting & Small Power North - HRSG 2

20

16-08-2013 A

15-03-2014

294

A13230

Cable Ladder - Switchroom

20-08-2013 A

17-10-2013 A

431

A13250

Cable Ladder - HRSG structure North - HRSG 2

15-09-2013 A

21-02-2014

1144

62

25%

A13250-a

Cable Ladder - HRSG structure South - HRSG 2

14

15-09-2013 A

14-03-2014

43

25%

A13290

Install HRSG2 Switchroom

22-09-2013 A

21-10-2013 A

168

A13300

Pull LV-C&I Cabling - HRSG 2

19

23-09-2013 A

03-04-2014

1906

43

2%

Pull LV-C&I Cabling - HRSG 2

A13310

LV-C&I Cable Terminations - HRSG 2

18

23-09-2013 A

02-04-2014

445

71

2%

LV-C&I Cable Terminations - HRSG 2

A13240

Install On-Skid Elec Equipment & Instruments - HRSG 2

30

16-12-2013 A

27-03-2014

2563

75

50%

Install On-Skid Elec Equipment & Instruments -

A13260

Field Equipment (LCS's- J.B's- HDG conduits etc...) - HRSG 2

10

28-02-2014

10-03-2014

77

95

0%

Field Equipment (LCS's- J.B's- HDG conduits etc.

A13280

Earthing Systems - HRSG 2

15-03-2014

18-03-2014

87

0%

A13270-a

Lighting & Small Power South - HRSG 2

20

15-03-2014

04-04-2014

71

0%

YARNIMA.10.15.5.5 HRSG2 BYPASS STACK & DAMPERS


A11340
Install Bottom Section (Damper + Duct)

123
42

04-05-2013 A
04-05-2013 A

29-01-2014 A
09-10-2013 A

4740
1160

100%

Cable Ladder - Switchroom


Cable Ladder - HRSG structure North - HRSG 2

Cable Ladder - HRSG structure South - HRSG 2

100%

A11350

Install By-Pass Structural Supports

42

06-05-2013 A

28-08-2013 A

850

100%

NCR-S076

ByPass 2: HRSG2 ByPass Stack Column Brackets not shown on the AFC Drawings 13

10-05-2013 A

23-05-2013 A

100%

A11360

Install By-Pass Silencer

28

15-05-2013 A

15-05-2013 A

735

100%

A11370

Install Stack Tube (Lower Section + Upper Section)

28

16-05-2013 A

10-10-2013 A

1270

100%

NCR-S080

ByPass 2: HRSG2 ByPass Stack Bolt Holes 10mm offset

13

16-05-2013 A

29-05-2013 A

100%

A11380

Install By-Pass Access Ladders & Platforms

14

23-05-2013 A

12-09-2013 A

725

100%

NCR-S248

ByPass 2: ByPass Stack 2 Fitment Issues

19

18-09-2013 A

08-10-2013 A

100%

A21120

Final punchlisting A-Items and Construciton Verification

10

04-10-2013 A

29-01-2014 A

100%

36
28

16-03-2014
16-03-2014

23-04-2014
14-04-2014

2450
469

61
62

YARNIMA.10.15.5.1 HRSG2 PRECOMMISSIONING


A13340
Electrical Pre-Commissioning and punchlisting A-Items - HRSG 2

Lighting & Small Power North - HRSG 2

100%

Install HRSG2 Switchroom

Earthing Systems - HRSG 2

Lighting & Small Power South - HRSG 2


YARNIMA.10.15.5.5 HRSG2 BYPASS STACK & DAMP
Install Bottom Section (Damper + Duct)
Install By-Pass Structural Supports
ByPass 2: HRSG2 ByPass Stack Column Brackets not shown on the AFC Drawings
Install By-Pass Silencer
Install Stack Tube (Lower Section + Upper Section)
ByPass 2: HRSG2 ByPass Stack Bolt Holes 10mm offset
Install By-Pass Access Ladders & Platforms
ByPass 2: ByPass Stack 2 Fitment Issues

Final punchlisting A-Items and Construciton Verification


YARNIMA.10.15.5.1 HRSG2 PRECOMMI

0%

Electrical Pre-Commissioning and punchlistin

A13330

Mechanical Pre-Commissioning and punchlisting A-Items - HRSG 2

25

20-03-2014

15-04-2014

1050

61

0%

Mechanical Pre-Commissioning and punchli

A13350

NDT & QA Documentation - HRSG 2

14

01-04-2014

15-04-2014

280

68

0%

NDT & QA Documentation - HRSG 2

A10860

Construction Verification - HRSG 2

15-04-2014

68

0%

Construction Verification - HRSG 2

A22880

Punchlisting B&C Items - HRSG 2

16-04-2014

23-04-2014

651

61

0%

336
36
10

07-04-2013 A
11-11-2013 A
11-11-2013 A

16-05-2014
19-12-2013 A
21-11-2013 A

39355
40
0

39

YARNIMA.10.15.6 HRSG-1
YARNIMA.10.15.6.2 HRSG1 - ACTUAL VARIATIONS & NON SCOPE WORKS
NCR-S339
HRSG1 Missing Bolt Holes on Column HD

100%

NCR-S353

HRSG1 Steam Drum Internal Inspection Non Conformances

29

19-11-2013 A

19-12-2013 A

100%

NCR-S364

HRSG1: HRSG-1 Dearator Top Level Platform

04-12-2013 A

10-12-2013 A

100%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 31 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Punchlisting B&C Items - HRSG 2


YARNIMA.10.15.6 HRSG-1
YARNIMA.10.15.6.2 HRSG1 - ACTUAL VARIATIONS & NON

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

HRSG1 Missing Bolt Holes on Column HD


HRSG1 Steam Drum Internal Inspection Non Conformances
HRSG1: HRSG-1 Dearator Top Level Platform
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

HRSG1: HRSG-1 Dearator Platform Missing Cleats on the Column

06-12-2013 A

07-12-2013 A

100%

HRSG1: HRSG-1 Dearator Platform Missing Cleats on the Colu

NCR-S366-1536 HRSG1: HRSG-1 Dearator Platform Missing Cleats on the Column

08-12-2013 A

09-12-2013 A

20

100%

HRSG1: HRSG-1 Dearator Platform Missing Cleats on the Colu

NCR-S364-1528 HRSG1: HRSG-1 Dearator Top Level Platform rectify Multiple misalignment of structural
1 members
11-12-2013 A

11-12-2013 A

20

100%

HRSG1: HRSG-1 Dearator Top Level Platform rectify Multiple m


YARNIMA.10.15.6.3 HRSG1 MECHANICAL

NCR-S366

YARNIMA.10.15.6.3 HRSG1 MECHANICAL


A11300
HRSG1 Installation WBS Summary

Budgeted
Labor Units

211
211

07-04-2013 A
07-04-2013 A

21-03-2014
21-03-2014

16785
0

Total
Float

91
89

Activity % S
Complete

23%

HRSG1 Installation WBS Summary

A13770-a

Install Boiler Module 1

07-04-2013 A

08-04-2013 A

100%

Install Boiler Module 1

A15570-a

Install Boiler Module 2

08-04-2013 A

09-04-2013 A

100%

Install Boiler Module 2

A15560-a

Install Boiler Module 3

09-04-2013 A

10-04-2013 A

100%

Install Boiler Module 3

A13800-a

Install Main Stack Lower Half

10-04-2013 A

11-04-2013 A

100%

Install Main Stack Lower Half

NCR-S153

HRSG3: Incorrect Gridmesh Clips and Gridmesh Spacing is more than 10mm

13

11-07-2013 A

24-07-2013 A

100%

A13800

Main Stack Access Ladders and Platform - HRSG 1

10

03-09-2013 A

02-01-2014 A

650

100%

Main Stack Access Ladders and Platform - HRSG 1

A13760

Install Boiler Inlet Duct - HRSG 1

22

07-09-2013 A

06-01-2014 A

2500

100%

Install Boiler Inlet Duct - HRSG 1

A13770

Remove Shipping Bracing and Install FLoor and Side Panels Module 1-2 - HRSG 1 13

08-09-2013 A

09-01-2014 A

2130

100%

Remove Shipping Bracing and Install FLoor and Side Pane

A15570

Remove Shipping Bracing and Install FLoor and Side Panels Module 2-3 - HRSG 1 13

15-09-2013 A

09-01-2014 A

2100

100%

Remove Shipping Bracing and Install FLoor and Side Pane

A21020

Install Heat Exchanger within Deaerator Structure - HRSG 1

10

28-09-2013 A

10-01-2014 A

50

100%

Install Heat Exchanger within Deaerator Structure - HRSG

A20990

Install Main Stack Upper Half

02-10-2013 A

28-10-2013 A

200

100%

A13830

Pre-assemble Install Deaerator Main Structure - HRSG 1

12

04-10-2013 A

13-02-2014

1085

39

80%

A20970

Install Duct Burner Structure & Baffles - HRSG 1

15-10-2013 A

12-02-2014

160

40

85%

A21010

Pre-assemble and Install Stair Tower (South Side) - HRSG 1

21

20-10-2013 A

04-02-2014 A

1660

100%

NCR-S301

Bolt Holes between Lower Section of HRSG Main Stack and Damper Not Match

21-10-2013 A

22-10-2013 A

100%

NCR-S328

HRSG1 Duct Burner to Boiler - Mounting Bolt Misalignment

30-10-2013 A

31-10-2013 A

100%

A21000

Install Outlet Duct - HRSG1

01-11-2013 A

20-02-2014

800

01-11-2013 A

03-11-2013 A

30

NCR-S328-1343 HRSG1 Duct Burner to Boiler - Mounting Bolt Re-aligned

41

HRSG3: Incorrect Gridmesh Clips and Gridmesh Spacing is more than 10mm

Install Main Stack Upper Half

Pre-assemble Install Deaerator Main Structure - HRS


Install Duct Burner Structure & Baffles - HRSG 1

Pre-assemble and Install Stair Tower (South Side) - H

Bolt Holes between Lower Section of HRSG Main Stack and Damper N
HRSG1 Duct Burner to Boiler - Mounting Bolt Misalignment

97%

Install Outlet Duct - HRSG1

100%

HRSG1 Duct Burner to Boiler - Mounting Bolt Re-aligned


Install Roof Panels Module 2-3 - HRSG 1

A20960

Install Roof Panels Module 2-3 - HRSG 1

10-11-2013 A

13-02-2014

600

39

90%

A13810

Install Upper Platforms around Steam Drum - HRSG 1

12

13-11-2013 A

03-03-2014

1540

39

45%

Install Upper Platforms around Steam Drum - HRS

NCR-S342

HRSG1 Stair Tower Painting Not in Compliance with Painting Specification

32

13-11-2013 A

17-12-2013 A

100%

HRSG1 Stair Tower Painting Not in Compliance with Painting S

A15560

Install Roof Panels Module 1-2 - HRSG 1

20-11-2013 A

20-02-2014

600

39

85%

Install Roof Panels Module 1-2 - HRSG 1

A20980

Install Duct Burners - HRSG 1

21-11-2013 A

17-02-2014

250

44

90%

Install Duct Burners - HRSG 1

NCR-S379

HRSG1 Deaerator Platform Handrails have been fabricated incorrectly

15-12-2013 A

18-12-2013 A

A13780

Install Steam Drum - HRSG 1

23-12-2013 A

23-02-2014

80

A21030

Install Boiler Feedwater Pumps - HRSG 1

13-01-2014 A

06-02-2014 A

350

A13880

Install CEMS - Skids - HRSG 1

14-01-2014 A

27-02-2014

100

108

10%

A13890

Install Wet Racks - HRSG 1

15-01-2014 A

01-03-2014

100

108

80%

Install Wet Racks - HRSG 1

A13790

Install Duct Burner Gas Train Skid - HRSG 1

16-01-2014 A

27-02-2014

420

108

25%

Install Duct Burner Gas Train Skid - HRSG 1

A13840

Install Platform Structure Above Deaerator - HRSG 1

05-02-2014 A

23-02-2014

700

39

20%

A13850

Install Deaerator Vessel - HRSG 1

05-02-2014 A

16-02-2014

220

39

20%

A22690

Insulation and Liner Plates for Inlet-Outlet Duct and Pannels - HRSG 1

14

09-02-2014

23-02-2014

86

0%

A13870

Install Blowdown Tank - HRSG 1

28-02-2014

01-03-2014

100

108

0%

A13820

Install Platform and Valve Silencers - HRSG 1

10

04-03-2014

14-03-2014

150

67

0%

Install Platform and Valve Silencers - HRSG 1

A21040

Install Chemical Dosing - HRSG 1

15-03-2014

21-03-2014

210

89

0%

203
163
2

08-09-2013 A
08-09-2013 A
08-09-2013 A

25-04-2014
13-03-2014
09-09-2013 A

8284
2484
0

57
83

Install Chemical Dosing - HRSG 1


YARNIMA.10.15.6.1 HRSG1 PIPING
YARNIMA.10.15.6.1.1 Boiler Feed Water System

NCR-S227-1021
HRSG1 DA Piping - Reestablish gramophone finish on Flange Face

10-09-2013 A

10-09-2013 A

A13860

Deaerator Piping - HRSG 1

20

27-09-2013 A

04-03-2014

960

72

25%

Deaerator Piping - HRSG 1

A16730

Boiler Feedwater Piping - HRSG 1

15

27-09-2013 A

02-03-2014

930

72

25%

Boiler Feedwater Piping - HRSG 1

A22770

Install Insulation (BFW & Deaerator piping) - HRSG 1

14

27-02-2014

13-03-2014

500

83

0%

Install Insulation (BFW & Deaerator piping) - HR

A22780

Hydrotest (BFW & Deaerator piping)

03-03-2014

07-03-2014

90

83

0%

97
18

23-11-2013 A
23-11-2013 A

14-04-2014
12-03-2014

4340
320

48
51

Hydrotest (BFW & Deaerator piping)


YARNIMA.10.15.6.1.2 Boiler Water & Steam

10%

YARNIMA.10.15.6.1 HRSG1 PIPING


YARNIMA.10.15.6.1.1 Boiler Feed Water System
NCR-S227
HRSG1 DA Piping - Flange Face Damaged

YARNIMA.10.15.6.1.2 Boiler Water & Steam System


A16740
Boiler Circulation Piping - HRSG 1

100%
39

HRSG1 Deaerator Platform Handrails have been fabricated in

40%

Install Steam Drum - HRSG 1

100%

Install Boiler Feedwater Pumps - HRSG 1


Install CEMS - Skids - HRSG 1

Install Platform Structure Above Deaerator - HRSG


Install Deaerator Vessel - HRSG 1
Insulation and Liner Plates for Inlet-Outlet Duct and
Install Blowdown Tank - HRSG 1

100%

HRSG1 DA Piping - Flange Face Damaged

100%

HRSG1 DA Piping - Reestablish gramophone finish on Flange Face

Boiler Circulation Piping - HRSG 1

A16820

HRSG Economiser Feedwater Piping - HRSG 1

12

24-11-2013 A

05-03-2014

280

51

15%

A16770

Main Steam Line Piping - HRSG 1

20

25-11-2013 A

14-03-2014

1350

39

20%

Main Steam Line Piping - HRSG 1

A16500

Steam & Water Sampling Piping - HRSG 1

10

26-11-2013 A

14-03-2014

200

77

10%

Steam & Water Sampling Piping - HRSG 1

A16780

Blow Down System Piping - HRSG 1

27-11-2013 A

28-02-2014

500

80

20%

A16800

HRSG Vents & Drains - Drum Safety Valve 2 Vent - HRSG 1

10

29-11-2013 A

25-03-2014

200

57

15%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 32 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

HRSG Economiser Feedwater Piping - HRSG 1

Blow Down System Piping - HRSG 1

HRSG Vents & Drains - Drum Safety Valve 2 Ve


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A16810

HRSG Vents & Drains - Drum Safety Valve 1 Vent - HRSG 1

10

29-11-2013 A

25-03-2014

350

39

15%

A22800

Hydrotest (Main Steam) - HRSG 1

26-03-2014

30-03-2014

90

39

0%

A22790

Install Insulation (Main Steam) - HRSG 1

14

31-03-2014

14-04-2014

1050

39

0%

YARNIMA.10.15.6.1.3 Boiler BOP Systems


A16750
Ignition & Cooling Air Supply Piping - HRSG 1 BOP System

87
5

24-11-2013 A
24-11-2013 A

25-04-2014
09-03-2014

1460
120

57
77

Install Insulation (Main Steam) - HRSG 1


YARNIMA.10.15.6.1.3 Boiler BOP System

10%

Ignition & Cooling Air Supply Piping - HRSG 1 BO


Chemical Dosing and Steam Sampling Tubing -

HRSG Vents & Drains - Drum Safety Valve 1 Ve


Hydrotest (Main Steam) - HRSG 1

A16790

Chemical Dosing and Steam Sampling Tubing - HRSG 1 BOP System

25-11-2013 A

14-03-2014

230

77

10%

A13900

Instrument Air Supply Piping - HRSG 1 BOP System

10

26-11-2013 A

25-03-2014

300

67

15%

A16760

Gas Piping - HRSG 1 BOP System

10

27-11-2013 A

04-04-2014

220

57

15%

A11150

Leak Test of Gas and Air supply Piping - HRSG 1

06-04-2014

10-04-2014

90

57

0%

Leak Test of Gas and Air supply Piping - HRS

A13910

Install Insulation - Steam Sampling Piping - HRSG 1 BOP System

14

11-04-2014

25-04-2014

500

57

0%

212
6

19-08-2013 A
19-08-2013 A

06-05-2014
21-03-2014

7056
1140

47
74

Install Insulation - Steam Sampling Piping


YARNIMA.10.15.6.13 HRSG1 ELECTR

YARNIMA.10.15.6.13 HRSG1 ELECTRICAL


A11070
Cable Ladder - HRSG structure North - HRSG 1

Instrument Air Supply Piping - HRSG 1 BOP Sy


Gas Piping - HRSG 1 BOP System

11%

Cable Ladder - HRSG structure North - HRSG

A11330

HRSG1 Electrical WBS Summary

212

19-08-2013 A

06-05-2014

47

0%

HRSG1 Electrical WBS Summary

A11110

Lighting & Small Power North - HRSG 1

20

26-08-2013 A

07-04-2014

300

74

12%

A11060

Cable Ladder - Switchroom

02-09-2013 A

22-10-2013 A

432

A11050

Install HRSG1 Switchroom

15-09-2013 A

21-10-2013 A

168

A11080

Pull LV - C&I Cabling - HRSG 1

17

23-09-2013 A

30-04-2014

1931

NCR-S303

Non Conformities Within the HRSG1 Switchroom

13

21-10-2013 A

03-11-2013 A

A11090

LV - C&I Cable Terminations - HRSG 1

18

04-11-2013 A

06-05-2014

445

NCR-S381

Clarification on installation of cable ladder bracket on HRSG1,2,3

15-12-2013 A

02-01-2014 A

A11120

Field Equipment (LCS's- J.B's - HDG conduits etc...) - HRSG 1

10

04-03-2014

14-03-2014

77

96

0%

A13700

Install On-Skid Elec Equipment & Instruments - HRSG 1

30

10-03-2014

10-04-2014

2563

64

0%

Install On-Skid Elec Equipment & Instruments

A11070-a

Cable Ladder - HRSG structure South - HRSG 1

14

15-03-2014

29-03-2014

48

0%

Cable Ladder - HRSG structure South - HRSG

A11100

Earthing Systems - HRSG 1

30-03-2014

02-04-2014

78

0%

Earthing Systems - HRSG 1

A11110-a

Lighting & Small Power South - HRSG 1

21

30-03-2014

21-04-2014

61

0%

YARNIMA.10.15.6.4 HRSG1 BYPASS STACK & DAMPERS


A13710
Install Bottom Section (Damper + Duct)

265
36

04-05-2013 A
04-05-2013 A

01-03-2014
24-09-2013 A

4740
1160

110

43

Lighting & Small Power North - HRSG 1

100%

Cable Ladder - Switchroom

100%

Install HRSG1 Switchroom

10%

Pull LV - C&I Cabling - HRSG 1

100%
43

Non Conformities Within the HRSG1 Switchroom

0%

LV - C&I Cable Terminations - HRSG 1

100%

Clarification on installation of cable ladder bracket on HRSG

Field Equipment (LCS's- J.B's - HDG conduits etc

Lighting & Small Power South - HRSG 1


YARNIMA.10.15.6.4 HRSG1 BYPASS STACK & D

100%

Install Bottom Section (Damper + Duct)

A13720

Install By-Pass Structural Supports

36

12-05-2013 A

27-08-2013 A

850

100%

A13730

Install By-Pass Silencer

28

15-05-2013 A

04-08-2013 A

735

100%

A13740

Install Stack Tube (Lower Section + Upper Section) - HRSG 1

28

16-05-2013 A

03-01-2014 A

1270

100%

Install Stack Tube (Lower Section + Upper Section) - HRSG

A13750

Install By-Pass Access Ladders & Platforms - HRSG 1

20

21-05-2013 A

06-01-2014 A

725

100%

Install By-Pass Access Ladders & Platforms - HRSG 1

NCR-S361

Liner Plates Fabricated Incorrectly

26-11-2013 A

28-11-2013 A

100%

A21110

Final punchlisting A-Items and Construciton Verification - HRSG 1

20

09-02-2014

01-03-2014

110

0%

YARNIMA.10.15.6.5 HRSG1 PRECOMMISSIONING


A11160
Electrical Pre-Commissioning and punchlisting A-Items - HRSG 1

34
28

11-04-2014
11-04-2014

16-05-2014
10-05-2014

2450
469

39
43

Final punchlisting A-Items and Construciton Verifica


YARNIMA.10.15.6.5 HRSG1 PRECOM

Install By-Pass Structural Supports


Install By-Pass Silencer

Liner Plates Fabricated Incorrectly

0%

Electrical Pre-Commissioning and punch

A11190

Mechanical Pre-Commissioning and punchlisting A-Items - HRSG 1

28

15-04-2014

14-05-2014

1050

39

0%

Mechanical Pre-Commissioning and pu

A22890

Punchlisting B&C Items - HRSG 1

14

30-04-2014

14-05-2014

651

41

0%

Punchlisting B&C Items - HRSG 1

A11750

NDT & QA Documentation - HRSG 1

14

02-05-2014

16-05-2014

280

39

0%

NDT & QA Documentation - HRSG 1

A11180

Construction Verification - HRSG 1

16-05-2014

39

0%

72
86
86

Construction Verification - HRSG 1


YARNIMA.10.15.11 COOLING TOWER 2
YARNIMA.10.15.11.1 MECHANICAL , PIPING

0%

Cooling Tower 2 Installation WBS Summary


YARNIMA.10.15.11.1.1 PRE-ASSEMBLY

YARNIMA.10.15.11 COOLING TOWER 2


YARNIMA.10.15.11.1 MECHANICAL , PIPING & ELECTRICAL
A11810
Cooling Tower 2 Installation WBS Summary
YARNIMA.10.15.11.1.1 PRE-ASSEMBLY
NCR-S250
CT2: Damaged Fibreglass Materials for the Cooling Tower
YARNIMA.10.15.11.1.2 INSTALLATION
A15140
Assemble Upper & Lower Transverse Frames - CT2

179
152
152

15-09-2013 A
15-09-2013 A
15-09-2013 A

11-04-2014
27-03-2014
27-03-2014

7940
6840
0

5
5

19-09-2013 A
19-09-2013 A

24-09-2013 A
24-09-2013 A

0
0

114
15

15-09-2013 A
15-09-2013 A

27-03-2014
19-12-2013 A

6180
1460

100%

CT2: Damaged Fibreglass Materials for the Cooling Tower


YARNIMA.10.15.11.1.2 INSTALLATION

69
100%

Assemble Upper & Lower Transverse Frames - CT2

A15300

Install Anchors

28-09-2013 A

04-11-2013 A

160

100%

A15150

Install Longitudinal Girts & assemble into modules - CT2

10

03-10-2013 A

19-12-2013 A

1040

100%

Install Longitudinal Girts & assemble into modules - CT2

A15160

Lift new tower modules into basin - CT2

24-10-2013 A

19-12-2013 A

380

100%

Lift new tower modules into basin - CT2

A15220

Install handrails - CT2

01-11-2013 A

08-01-2014 A

340

100%

A15170

Install Staircase & walkway to Tower 2 - CT2

12-11-2013 A

27-01-2014 A

460

100%

A15240

Install Eliminator - CT2

13-11-2013 A

18-12-2013 A

360

100%

A15180

Install Fan decks - CT2

26-11-2013 A

28-01-2014 A

120

100%

A15200

Install Ladders and Landings - CT2

16

12-12-2013 A

27-03-2014

780

69

90%

A15280

Install Noise Attenduators in Basin - CT2

13

16-12-2013 A

17-03-2014

160

69

85%

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 33 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Install Anchors

Install handrails - CT2

Install Staircase & walkway to Tower 2 - CT2


Install Eliminator - CT2
Install Fan decks - CT2
Install Ladders and Landings - CT2
Install Noise Attenduators in Basin - CT2
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A15320

Install Fill Packing - CT2

12

16-12-2013 A

16-02-2014

200

61

65%

Install Fill Packing - CT2

A15250

Install Mechanical Equipment - CT2

17-02-2014

19-02-2014

240

61

0%

Install Mechanical Equipment - CT2

A15260

Install Fan Cylinders - CT2

20-02-2014

01-03-2014

320

61

0%

A15270

Install Cable Trays - CT2

02-03-2014

10-03-2014

160

69

0%

YARNIMA.10.15.11.1.6 PIPING
A15230
Install Distribution Pipework & Pads - CT2

78
13

03-11-2013 A
03-11-2013 A

13-03-2014
02-01-2014 A

660
440

77

11

02-03-2014

13-03-2014

220

61

0%

50
5

17-02-2014
17-02-2014

11-04-2014
21-02-2014

1100
100

72
95

0%

A15290

Install Piping / Oil Lines - CT2

YARNIMA.10.15.11.3 PRECOMMISSIONING
A11850
Testing - CT2

Install Fan Cylinders - CT2


Install Cable Trays - CT2
YARNIMA.10.15.11.1.6 PIPING

100%

Install Distribution Pipework & Pads - CT2

Install Piping / Oil Lines - CT2


YARNIMA.10.15.11.3 PRECOMMISSIONIN
Testing - CT2

A11840

Electrical & Mechanical Pre-Commissioning - CT2

21

14-03-2014

11-04-2014

800

61

0%

Electrical & Mechanical Pre-Commissioning

A11770

NDT & QA Documentation - CT2

10

26-03-2014

11-04-2014

200

61

0%

NDT & QA Documentation - CT2

A11830

Construction Verification - CT2

11-04-2014

72

0%

44
59
59

Construction Verification - CT2


YARNIMA.10.15.1 COOLING TOWER
YARNIMA.10.15.1.1 MECHANICAL, PIPI

0%

YARNIMA.10.15.1 COOLING TOWER 1


YARNIMA.10.15.1.1 MECHANICAL, PIPING & ELECTRICAL
A11710
Cooling Tower 1 Installation WBS Summary
YARNIMA.10.15.1.1.1 PRE-ASSEMBLY
A15130
Site Mobilization

218
203
203

26-08-2013 A
26-08-2013 A
26-08-2013 A

11-05-2014
25-04-2014
25-04-2014

10060
8960
0

80
1

26-08-2013 A
26-08-2013 A

25-09-2013 A
10-09-2013 A

2120
100

Cooling Tower 1 Installation WBS Summ


YARNIMA.10.15.1.1.1 PRE-ASSEMBLY

100%

Site Mobilization

A15100

Site Induction

27-08-2013 A

13-09-2013 A

140

100%

Site Induction

A15110

Cooling Tower Assembly Area and Handover

28-08-2013 A

24-09-2013 A

280

100%

Cooling Tower Assembly Area and Handover

A15330

Basin Survey

30-08-2013 A

25-09-2013 A

280

100%

Basin Survey

A15360

Set up Frame Assembly Area

01-09-2013 A

25-09-2013 A

920

100%

Set up Frame Assembly Area

A15350

Cooling Tower 2 Ready to Start

10

09-09-2013 A

17-09-2013 A

200

100%

Cooling Tower 2 Ready to Start

A15120

Cooling Tower 1 Ready to Start

10

12-09-2013 A

19-09-2013 A

200

100%

Cooling Tower 1 Ready to Start

108
10

07-10-2013 A
07-10-2013 A

22-04-2014
26-01-2014 A

6180
1460

YARNIMA.10.15.1.1.2 INSTALLATION
A3070
Assemble Upper & Lower Transverse Frames - CT1

YARNIMA.10.15.1.1.2 INSTALLATION

52
100%

Assemble Upper & Lower Transverse Frames - CT1

A3080

Install Longitudinal Girts & assemble into modules - CT1

20

13-10-2013 A

23-01-2014 A

1040

100%

A3310

Install Anchors - CT1

04-11-2013 A

16-12-2013 A

160

100%

A3240

Install Staircase & walkway to Tower 1 - CT1

06-11-2013 A

10-03-2014

460

38

75%

A3300

Install Ladders and Landings - CT1

13-11-2013 A

06-03-2014

780

38

10%

NCR-S359

Cooling Tower Bed Frame Butt Welds

21

22-11-2013 A

13-12-2013 A

A3250

Install Fill Packing - CT1

12

21-12-2013 A

25-03-2014

200

38

15%

Install Fill Packing - CT1

A3270

Install Eliminator - CT1

21-12-2013 A

27-03-2014

360

41

25%

Install Eliminator - CT1

A3510

Install Noise Attenuators in Basin - CT1

22-12-2013 A

19-02-2014

160

38

30%

A3090

Lift new tower modules into basin - CT1

08-02-2014

13-02-2014

380

38

0%

A3490

Install Handrails - CT1

11-03-2014

12-03-2014

340

38

0%

A3100

Install Fan decks - CT1

26-03-2014

05-04-2014

120

38

0%

Install Fan decks - CT1

A3280

Install Mechanical Equipment - CT1

07-04-2014

09-04-2014

240

38

0%

Install Mechanical Equipment - CT1

A3290

Install Fan Cylinders - CT1

10-04-2014

13-04-2014

320

38

0%

Install Fan Cylinders - CT1

A3320

Install Cable Trays - CT1

14-04-2014

22-04-2014

160

52

0%

YARNIMA.10.15.1.1.6 PIPING
A3260
Install Distribution Pipework & Pads - CT1

113
15

03-11-2013 A
03-11-2013 A

25-04-2014
17-04-2014

660
440

48
55

Install Longitudinal Girts & assemble into modules - C


Install Anchors - CT1

Install Staircase & walkway to Tower 1 Install Ladders and Landings - CT1

100%

Cooling Tower Bed Frame Butt Welds

Install Noise Attenuators in Basin - CT1


Lift new tower modules into basin - CT1
Install Handrails - CT1

Install Cable Trays - CT1


YARNIMA.10.15.1.1.6 PIPING

20%

Install Distribution Pipework & Pads - CT1

NCR-S358

Cooling Tower Water Distribution PVC Couplings

13

20-11-2013 A

03-12-2013 A

100%

A3330

Install Piping / Oil Lines - CT1

11

14-04-2014

25-04-2014

220

43

0%

YARNIMA.10.15.1.3 PRECOMMISSIONING
A11720
Electrical & Mechanical Pre-Commissioning - CT1

26
21

14-04-2014
14-04-2014

11-05-2014
11-05-2014

1100
800

44
38

Install Piping / Oil Lines - CT1


YARNIMA.10.15.1.3 PRECOMMISSION

0%

Electrical & Mechanical Pre-Commission

A11170

NDT & QA Documentation - CT1

10

26-04-2014

11-05-2014

200

38

0%

A11740

Testing - CT1

26-04-2014

30-04-2014

100

43

0%

A11730

Construction Verification - CT1

11-05-2014

44

0%

33

261
118
1

21-07-2013 A
21-07-2013 A
21-07-2013 A

23-05-2014
13-12-2013 A
29-07-2013 A

26841
1846
0

29

16-08-2013 A

15-09-2013 A

100%

89

20-08-2013 A

23-11-2013 A

143

100%

VESTG1000

VE STG 1 - Condenser Grout Pockets Location, Generator terminal box support feet mods,
6
more
20-08-2013
room for A630mm2
26-08-2013
HV cables
A

219

100%

VESTG1010

VE STG 1 - Insufficient room for the 630mm2 HV cables on ST1 & ST2

205

100%

YARNIMA.10.15.7 STEAM TURBINE GENERATOR STG 1


YARNIMA.10.15.7.5 STG1 - ACTUAL VARIATIONS & NON SCOPE WORKS
NCR-S158
STG1 and STG2 Pedestals
NCR-S191

Generator terminal box support feet modification

NCR-S191-886 Modify Terminal Box Support Feet - STG1

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

01-09-2013 A

Page 34 of 38
Data Date 07-02-2014

06-09-2013 A

Date
19-Dec-12
21-11-2013
07-02-2014

Cooling Tower Water Distribution PVC Couplings

NDT & QA Documentation - CT1


Testing - CT1

Construction Verification - CT1


YARNIMA.10.15.7 STEAM TURBINE
YARNIMA.10.15.7.5 STG1 - ACTUAL VARIATIONS & NON S

100%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

STG1 and STG2 Pedestals


Generator terminal box support feet modification
Modify Terminal Box Support Feet - STG1

VE STG 1 - Condenser Grout Pockets Location, Generator terminal box suppor


VE STG 1 - Insufficient room for the 630mm2 HV cables on ST1 & ST2
Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

12-09-2013 A

19-09-2013 A

100%

56

20-09-2013 A

19-11-2013 A

405

100%

VESTG1020

VE STG 1 - Rectify Enclosure St/work, STG Condenser & Transition Piece Weld Prep,4 Weld Hotwell
20-09-2013
to Condenser
A
24-09-2013
Flange A

113

100%

NCR-S267

Condensate Piping Supports Clash - A13560

28-09-2013 A

04-10-2013 A

100%

NCR-S276

SGT1 and SGT2: Existing Condenser Weld Preparation for Welding onto T-Piece

07-10-2013 A

13-10-2013 A

100%

39

08-10-2013 A

18-11-2013 A

324

100%

Repair Weld Prep for weld to T-Piece at STG's 1 and 2- A13210 an

VESTG1030

VE STG 1 - Rectify Enclosure St/work, Cable Ladder Route mod, Modify leakage steam
10 pipe 15-10-2013 A

25-10-2013 A

149

100%

VE STG 1 - Rectify Enclosure St/work, Cable Ladder Route mod, Mod

NCR-S305

STG1 Enclosure Fabrication Error

22-10-2013 A

30-10-2013 A

100%

STG1 Enclosure Fabrication Error

NCR-S312

STG1 Enclosure Error Strutural Beam

24-10-2013 A

30-10-2013 A

100%

STG1 Enclosure Error Strutural Beam

NCR-S312-1302 Correct Structural Beam - STG 1 - A12820 (Incomplete)

25-10-2013 A

29-10-2013 A

90

100%

Correct Structural Beam - STG 1 - A12820 (Incomplete)

NCR-S325

STG1 Enclosure Frame Installation

29-10-2013 A

01-11-2013 A

100%

STG1 Enclosure Frame Installation

VESTG1040

VE STG 1 - Rectify Enclosure St/work, STG Cond.&Trans Piece Weld Prep, Weld Hotwell
8
to Cond
09-11-2013
Flge, cable
A ladder
17-11-2013
mods etc
A

189

100%

NCR-S368

STG1 and 2 - NDT on Hot-well to Condenser Weld

08-12-2013 A

09-12-2013 A

100%

STG1 and 2 - NDT on Hot-well to Condenser Weld

NCR-S369

STG1&2 Condensate line - fittings size mismatch

09-12-2013 A

13-12-2013 A

100%

173
173

24-07-2013 A
24-07-2013 A

16-03-2014
16-03-2014

6487
0

STG1&2 Condensate line - fittings size mismatch


YARNIMA.10.15.7.2 MECHANICAL STG1

NCR-S233

STG Condenser and Transition Piece Weld Prep Quality

NCR-S233-1043 Repair of Weld Prep Quality - STG1 - A21550-a

NCR-S276-1191 Repair Weld Prep for weld to T-Piece at STG's 1 and 2- A13210 and A14240

YARNIMA.10.15.7.2 MECHANICAL STG1


A11860
STG1 Mech & Piping Install WBS Summary

Budgeted
Labor Units

Total
Float

79
79

Activity % S
Complete

STG Condenser and Transition Piece Weld Prep Quality


Repair of Weld Prep Quality - STG1 - A21550-a

VE STG 1 - Rectify Enclosure St/work, STG Condenser & Transition Piece


Condensate Piping Supports Clash - A13560

SGT1 and SGT2: Existing Condenser Weld Preparation for Welding ont

VE STG 1 - Rectify Enclosure St/work, STG Cond.&Trans Piece W

55.26%

STG1 Mech & Piping Install WBS Summary

A21530-a

Unpacking and Verifying Siemen Supply

24-07-2013 A

21-10-2013 A

280

100%

A11970

Prepare Foundation

25-07-2013 A

22-08-2013 A

120

100%

A12000

Measure & Mark Axis

25-07-2013 A

03-08-2013 A

100

100%

A12020

Tapping & Levelling of Fixator Points

27-07-2013 A

16-08-2013 A

120

100%

A12090

Installation of Foundation Supports - Fixators

28-07-2013 A

20-08-2013 A

150

100%

A13430

Lift Generator- Gearbox Skid & Turbine into Position

28-07-2013 A

03-08-2013 A

120

100%

Lift Generator- Gearbox Skid & Turbine into Position

NCR-S178-780 STG1 Relocate Grout Pockets and Base Plates

15

29-07-2013 A

21-08-2013 A

116

100%

STG1 Relocate Grout Pockets and Base Plates

NCR-S167

STG1: STG Gearbox Locating Pins

25

31-07-2013 A

26-08-2013 A

100%

STG1: STG Gearbox Locating Pins

NCR-S178

STG1 Grout Pockets and Base Plates

15

04-08-2013 A

19-08-2013 A

100%

STG1 Grout Pockets and Base Plates

A14150

Install Couplings & Covers

08-08-2013 A

13-11-2013 A

60

100%

A13680

Install Gland Steam Condensor and Vacuum Pump

13-08-2013 A

13-09-2013 A

112

100%

Install Gland Steam Condensor and Vacuum Pump

A14140

Install Emergency Stop Valve

20-08-2013 A

10-09-2013 A

160

100%

Install Emergency Stop Valve

A12550

Dismantle Transport Protection of Turboset

21-08-2013 A

11-09-2013 A

240

100%

Dismantle Transport Protection of Turboset

A14010

Install HP Oil Skid

21-08-2013 A

10-09-2013 A

120

100%

Install HP Oil Skid

A14020

Install Condensate Pumps

22-08-2013 A

13-09-2013 A

120

100%

Install Condensate Pumps

A14080

Install Generator Cabinets - STG1

23-08-2013 A

19-12-2013 A

120

100%

A13210

Place hot well and Condensor

25-08-2013 A

06-10-2013 A

80

100%

A13450

Preparation of Front & Rear Turbine Bearings

27-08-2013 A

13-09-2013 A

120

100%

Preparation of Front & Rear Turbine Bearings

A14090

Final Alignment - STG1

28-08-2013 A

13-02-2014

275

33

95%

Final Alignment - STG1

A14100

Final Grouting - STG1

28-08-2013 A

15-02-2014

140

86

90%

Final Grouting - STG1

A21550-a

Install and Weld Condensor Exhaust Neck - STG1

30-08-2013 A

11-03-2014

190

33

60%

A12820

Build Enclosure Structure (Complete)

18

31-08-2013 A

23-11-2013 A

800

100%

A13460

Setup Generator Magnetic Pole Position

31-08-2013 A

13-09-2013 A

90

100%

A13490

Pre-Alignment & Levelling of Turboset

02-09-2013 A

04-09-2013 A

160

100%

NCR-S252

STG1: STG Enclosure Steelworks

22-09-2013 A

24-09-2013 A

100%

NCR-S264

STG1 & STG2 Condenser Pumps

25-09-2013 A

29-09-2013 A

100%

STG1 & STG2 Condenser Pumps

NCR-S253

STG1 Drawings and Documents Required.

26-09-2013 A

27-09-2013 A

100%

STG1 Drawings and Documents Required.

NCR-S275

SGT1 and SGT2: Condenser Support Pedestals Missing Details & General Material Substitution
3
06-10-2013 A

Unpacking and Verifying Siemen Supply


Prepare Foundation
Measure & Mark Axis
Tapping & Levelling of Fixator Points
Installation of Foundation Supports - Fixators

Install Couplings & Covers

Install Generator Cabinets - STG1


Place hot well and Condensor

Install and Weld Condensor Exhaust Neck - STG


Build Enclosure Structure (Complete)
Setup Generator Magnetic Pole Position
Pre-Alignment & Levelling of Turboset
STG1: STG Enclosure Steelworks

08-10-2013 A

100%

SGT1 and SGT2: Condenser Support Pedestals Missing Details & Gener

NCR-S275-1187 SGT1 and SGT2: Condenser Support Pedestal Installation

09-10-2013 A

11-10-2013 A

24

100%

SGT1 and SGT2: Condenser Support Pedestal Installation

NCR-S280

STG1: Clashing of the STG Roof Frame

11-10-2013 A

16-10-2013 A

100%

STG1: Clashing of the STG Roof Frame

NCR-S281

STG1 & STG2 Clashing with Electrical Floor Plate Cover

12-10-2013 A

16-10-2013 A

100%

STG1 & STG2 Clashing with Electrical Floor Plate Cover

NCR-S282

STG1 Door Jamb on the South-West of the Steel Enclosure

12-10-2013 A

16-10-2013 A

100%

STG1 Door Jamb on the South-West of the Steel Enclosure

NCR-S283

STG1 & STG2 Side Cover Drain Pipe Tripping Hazard

12-10-2013 A

15-10-2013 A

100%

STG1 & STG2 Side Cover Drain Pipe Tripping Hazard

A14160

Complete Installation of Walls & Roof (Complete with Gantry Crane) - STG1

10

19-10-2013 A

01-03-2014

1200

NCR-S304

STG1 and STG2: STGs Leakage Steam Pipe Reorientate Existing Pipe by 90 Degree.2

22-10-2013 A

23-10-2013 A

NCR-S306

BOP: Damaged Precast Footings

13

22-10-2013 A

04-11-2013 A

A14170

Install Primary Internal Pipe Rack- Pipe Supports and Platforms - STG1

21

27-10-2013 A

28-02-2014

820

NCR-S320

STG1: STG's Enclosure Additional Issues

27-10-2013 A

30-10-2013 A

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 35 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

93

80%

Complete Installation of Walls & Roof (Complete w

100%

STG1 and STG2: STGs Leakage Steam Pipe Reorientate Existing Pipe

100%
32

BOP: Damaged Precast Footings

95%

Install Primary Internal Pipe Rack- Pipe Supports a

100%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

STG1: STG's Enclosure Additional Issues


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

NCR-S315

STG1: STG's Enclosure Additional Issue 11

28-10-2013 A

01-11-2013 A

100%

STG1: STG's Enclosure Additional Issue 11

NCR-S324

STG1 Enclosure Prefabricated Steel Weld Quality

29-10-2013 A

29-10-2013 A

100%

STG1 Enclosure Prefabricated Steel Weld Quality

NCR-S329

STG1: STGs Enclosure Additional Issues III

31-10-2013 A

01-11-2013 A

100%

STG1: STGs Enclosure Additional Issues III

A21540-a

Install External Pipe Rack-Pipe Supports and Platforms - STG1

21

05-11-2013 A

16-03-2014

650

NCR-S340

STG1 Damage to Flange At Hotwell Connection

12-11-2013 A

14-11-2013 A

100%

STG1 Damage to Flange At Hotwell Connection

NCR-S341

STG1: Pipe Shoe Support Clash with the STG Enclosure wall

14-11-2013 A

14-11-2013 A

100%

STG1: Pipe Shoe Support Clash with the STG Enclosure wall

NCR-S344

STG1 & STG2: STG Internal Platform Earthing Cable Clash to Baseplate.

14-11-2013 A

17-11-2013 A

100%

STG1 & STG2: STG Internal Platform Earthing Cable Clash to Bas

NCR-S383

STG1 Structural Column C1005 Clash with Enclosure Southern Frame

17-12-2013 A

18-12-2013 A

100%

STG1 Structural Column C1005 Clash with Enclosure Souther

A23020

Delivery of Free Issue Gantry Crane - STG1

15-02-2014*

165
12

13-08-2013 A
13-08-2013 A

YARNIMA.10.15.7.4 PIPING STG1


A14040
Installation of Oil System Pipework - STG1

45

94

02-05-2014
01-02-2014 A

5464
716

35

90%

Install External Pipe Rack-Pipe Supports and Pla

0%

Delivery of Free Issue Gantry Crane - STG1


YARNIMA.10.15.7.4 PIPING STG1

100%

Installation of Oil System Pipework - STG1

A14070

Install Condensate System Piping - STG1

10

21-08-2013 A

27-03-2014

600

35

80%

Install Condensate System Piping - STG1

A14050

Install Drain System Pipework - STG1

24

23-08-2013 A

12-04-2014

980

49

95%

Install Drain System Pipework - STG1

A14060

Install Gland Steam and Vacuum System Piping - STG1

18

05-10-2013 A

22-04-2014

340

45

85%

A13690

Install Drainage Tank - STG1

24-10-2013 A

05-02-2014 A

120

NCR-S308

STG1 & STG2: STG1 and STG2 isometric drawings dimension conflict

26-10-2013 A

27-10-2013 A

A13580

Install Steam By-Pass Piping - STG1

14

27-10-2013 A

11-04-2014

279

NCR-S330

STG1: STG's Piping Fabrication and Clash Issue 1

31-10-2013 A

01-11-2013 A

A13570

Install Main Steam Pipework to Turbine & Compensator - STG1

14

11-11-2013 A

11-04-2014

800

NCR-S377

STG : STG1&2 Condensate line - fittings missing

11-12-2013 A

13-12-2013 A

100%

NCR-S377-1567 STG : STG1&2 Condensate line - fittings missing lead time and delivery

15-12-2013 A

19-12-2013 A

100%

STG : STG1&2 Condensate line - fittings missing lead time an

A13560

Grout Pipe rack and Supports - STG1

10

16-12-2013 A

10-03-2014

200

51

10%

Grout Pipe rack and Supports - STG1

A14110

Connect Inlet & Outlet Cooling Water Piping - STG1

06-01-2014 A

19-03-2014

530

36

15%

A14740

Install Piping Insulation - STG1

20

12-04-2014

02-05-2014

600

35

0%

A21560-a

Hydrotest - STG1

13-04-2014

17-04-2014

299

49

0%

186
20

11-08-2013 A
11-08-2013 A

05-05-2014
16-02-2014

11034
748

33
74

90%

YARNIMA.10.15.7.3 ELECTRICAL STG1


A2690
Cable Ladder STG MV Switchroom - STG1

Install Gland Steam and Vacuum System P

100%

Install Drainage Tank - STG1

100%
49

STG1 & STG2: STG1 and STG2 isometric drawings dimension conflict

50%

Install Steam By-Pass Piping - STG1

100%
35

STG1: STG's Piping Fabrication and Clash Issue 1

60%

Install Main Steam Pipework to Turbine & Co


STG : STG1&2 Condensate line - fittings missing

Connect Inlet & Outlet Cooling Water Piping - ST


Install Piping Insulation - STG1

Hydrotest - STG1
YARNIMA.10.15.7.3 ELECTRICAL STG
Cable Ladder STG MV Switchroom - STG1

A2740

Pull 11kV Cabling STG1 to STG Switchroom - STG1

12

17-08-2013 A

20-02-2014

827

65

85%

A2570

Install STG Switchroom (1) - STG1

07-09-2013 A

09-02-2014

193

74

95%

A2560

Install STG-1 Main 8 MVA Transformer - STG1

15-09-2013 A

10-02-2014

159

75

95%

Install STG-1 Main 8 MVA Transformer - STG1

A2550

Install STG-1 Auxillary 2.5 MVA Transformer - STG1

17-09-2013 A

09-02-2014

186

75

95%

Install STG-1 Auxillary 2.5 MVA Transformer - STG1

A2700

Cable Ladder - Steam Turbines - STG1

27-09-2013 A

01-04-2014

657

33

50%

A2710

Pull LV-C&I Cabling - STG1 (To CWP - CT Fans - Water Treatment - HRSG Pmps) 42

28-09-2013 A

20-04-2014

3727

33

35%

NCR-S273

STG1 & STG2: Cable Ladder Route Modification Under ST LV Switchrooms

02-10-2013 A

03-10-2013 A

100%

NCR-S279

STG1 & STG2: STG Switchroom Cable Ladders

10-10-2013 A

11-10-2013 A

100%

STG1 & STG2: STG Switchroom Cable Ladders

NCR-S293

STG1 & STG2: Inadequate Clearance Between CTs and Gland Plates

14-10-2013 A

14-10-2013 A

100%

STG1 & STG2: Inadequate Clearance Between CTs and Gland Plates

NCR-S293-1249 STG1 & STG2: increase clearance Between CTs and Gland Plates

14-10-2013 A

16-10-2013 A

40

100%

STG1 & STG2: increase clearance Between CTs and Gland Plates

NCR-S290

STG1: Incorrect Dimensions for the HV Cable Supports STG Switchroom

15-10-2013 A

15-10-2013 A

100%

STG1: Incorrect Dimensions for the HV Cable Supports STG Switchroom

NCR-S291

STG1: Inoperative Locking Mechanism ST2BBB10GS008

15-10-2013 A

22-10-2013 A

100%

A2720

LV-C&I Cable Terminations - STG1

14

18-10-2013 A

05-05-2014

882

33

13%

A3210

Pull 11kV Cabling STG Switchroom to STG1 StepUp Transformer - STG1

22

23-10-2013 A

10-03-2014

1850

65

40%

NCR-S336

Non Conformant STG1&2 Supplied Equipment

13

10-11-2013 A

23-11-2013 A

100%

NCR-S350

Cable Ladder Supports Foundation North of the STG Switchroom

17-11-2013 A

17-11-2013 A

100%

A3230

11kV Cable Terminations - STG1

17

03-12-2013 A

21-03-2014

25

NCR-S373

Clarification to run the cable from ST1 to Switch yard through broken conduit

11

10-12-2013 A

02-01-2014 A

NCR-S385

Clarification on glanding and termination of cables on electrical fire pump control panel 4on water18-12-2013
treatment A

02-01-2014 A

A23030

Pull Power Cables from STG to Cooling Tower 1 (Resource in STG Works)

18

20-12-2013 A

21-02-2014

98

A7420

Install On-skid Elec Equipment & Instruments - STG1

20

08-01-2014 A

25-03-2014

1046

A2770

Earth Grid & Lightning Protection - STG1

23-03-2014

31-03-2014

A2800

Field Equipment (LCS's- J.B's- HDG conduits etc...) - STG1

02-04-2014

A2790

Lighting & Small Power - STG1

YARNIMA.10.15.7.1 PRECOMMISSIONING STG1


A14030
Fill Oil Tank (during commissioning)
A11870

Lube Oil Flush (during commissioning) - STG1

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

65

Pull 11kV Cabling STG1 to STG Switchroom - STG1


Install STG Switchroom (1) - STG1

Cable Ladder - Steam Turbines - STG1

Pull LV-C&I Cabling - STG1 (To CWP - CT

STG1 & STG2: Cable Ladder Route Modification Under ST LV Switchroom

STG1: Inoperative Locking Mechanism ST2BBB10GS008


LV-C&I Cable Terminations - STG1

Pull 11kV Cabling STG Switchroom to STG1 Ste


Non Conformant STG1&2 Supplied Equipment
Cable Ladder Supports Foundation North of the STG Switchroom

52%

11kV Cable Terminations - STG1

100%

Clarification to run the cable from ST1 to Switch yard throug

100%

Clarification on glanding and termination of cables on electri

30%

Pull Power Cables from STG to Cooling Tower 1 (R

71

25%

Install On-skid Elec Equipment & Instruments -

65

0%

Earth Grid & Lightning Protection - STG1

03-04-2014

40

40

0%

Field Equipment (LCS's- J.B's- HDG conduits

04-04-2014

12-04-2014

654

40

0%

51
2

23-09-2013 A
23-09-2013 A

23-05-2014
02-10-2013 A

2010
80

33

10

16-10-2013 A

23-05-2014

150

33

Page 36 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Lighting & Small Power - STG1


YARNIMA.10.15.7.1 PRECOMMISSIO

100%

Fill Oil Tank (during commissioning)

13%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Lube Oil Flush (during commissioning)


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A2680

Electrical Pre-Commissioning - STG1

28

06-04-2014

05-05-2014

616

33

0%

Electrical Pre-Commissioning - STG1

A7610

Mechanical Pre-Commissioning - STG1

20

14-04-2014

05-05-2014

640

33

0%

Mechanical Pre-Commissioning - STG1

A7270

NDT & QA Documentation - STG1

14

21-04-2014

05-05-2014

80

33

0%

NDT & QA Documentation - STG1

A22900

Punchlisting B&C Items - STG1

30-04-2014

05-05-2014

41

0%

Punchlisting B&C Items - STG1

A7620

Construction Verification and punchlisting A-Items - STG1

05-05-2014

33

0%

Construction Verification and punchlisting

A14120

Pipe System Flushing (during commissioning) - STG1

13-05-2014

20-05-2014

444

36

0%

284
88
5

02-08-2013 A
15-08-2013 A
15-08-2013 A

27-06-2014
18-11-2013 A
19-08-2013 A

25696
783
78

20

25-09-2013 A

YARNIMA.10.15.9 STEAM TURBINE GENERATOR STG 2


YARNIMA.10.15.9.5 STG2 - ACTUAL VARIATIONS & NON SCOPE WORKS
VESTG2000
VE STG 2 - Condenser Grout Pockets

Pipe System Flushing (during commiss


YARNIMA.10.15.9 STEAM TUR
YARNIMA.10.15.9.5 STG2 - ACTUAL VARIATIONS & NON SCOP

100%

VE STG 2 - Condenser Grout Pockets

VESTG2010

VE STG1&2 - paint bellows, valves and reducers for piping

15-10-2013 A

443

100%

VESTG2020

VE STG1&2 - paint bellows, valves and reducers for piping, set up temp elect suppy to8HV switch
30-10-2013
room, Wait
A for drill
07-11-2013
rig
A

226

100%

VE STG1&2 - paint bellows, valves and reducers for piping, set up te

VESTG2030

VE STG 2 - Labour assistance for Global Testing Services as requested from Worley Parsons
2
15-11-2013 A

18-11-2013 A

36

100%

VE STG 2 - Labour assistance for Global Testing Services as reque


YARNIMA.10.15.9.2 MECHANICAL STG2

YARNIMA.10.15.9.2 MECHANICAL STG2


A21570-a
Unpacking and Verifying Siemen Supply

178
5

02-08-2013 A
02-08-2013 A

02-04-2014
22-10-2013 A

6347
280

VE STG1&2 - paint bellows, valves and reducers for piping

51
100%

Unpacking and Verifying Siemen Supply

A14210

Installation of Foundation Supports - Fixators

03-08-2013 A

10-09-2013 A

150

100%

A14180

Prepare Foundation

06-08-2013 A

02-09-2013 A

120

100%

A14190

Measure & Mark Axis

09-08-2013 A

08-09-2013 A

100

A14320

Install Gland Steam Condensor and Vacuum Pump - STG2

12-08-2013 A

12-02-2014

112

A14200

Tapping & Levelling of Fixator Points

13-08-2013 A

09-09-2013 A

120

100%

Tapping & Levelling of Fixator Points

A14360

Install Condensate Pumps

14-08-2013 A

06-09-2013 A

120

100%

Install Condensate Pumps

A14220

Dismantle Transport Protection of Turboset

21-08-2013 A

11-09-2013 A

240

100%

Dismantle Transport Protection of Turboset

A14240

Place hot well and Condensor

25-08-2013 A

09-10-2013 A

80

100%

A14250

Lift Generator- Gearbox Skid & Turbine into Position

27-08-2013 A

01-09-2013 A

120

100%

A14350

Install HP Oil Skid

29-08-2013 A

10-09-2013 A

120

100%

A14420

Final Alignment - STG2

30-08-2013 A

12-02-2014

275

95%

A14430

Final Grouting - STG2

30-08-2013 A

16-02-2014

140

59

90%

NCR-S209

STG2 Turbine Pin - Grout Pocket Not in Correct Location

30-08-2013 A

31-08-2013 A

A14230

Build Enclosure Structure (Complete) - STG2

18

03-09-2013 A

02-04-2014

800

A14480

Install Emergency Stop Valve

04-09-2013 A

22-09-2013 A

160

100%

A14260

Preparation of Front & Rear Turbine Bearings

10-09-2013 A

20-09-2013 A

120

100%

Preparation of Front & Rear Turbine Bearings

A14280

Pre-Alignment & Levelling of Turboset

10-09-2013 A

15-09-2013 A

160

100%

Pre-Alignment & Levelling of Turboset

A14270

Setup Generator Magnetic Pole Position

11-09-2013 A

16-09-2013 A

90

100%

Setup Generator Magnetic Pole Position

A14410

Install Generator Cabinets - STG2

13-10-2013 A

07-01-2014 A

120

100%

A21770-a

Install and Weld Condensor Exhaust Neck - STG2

15-10-2013 A

23-03-2014

190

55%

A14490

Install Couplings & Covers - STG2

16-10-2013 A

20-02-2014

60

59

80%

A21690-a

Install External Pipe Rack-Pipe Supports and Platforms - STG2

05-11-2013 A

07-03-2014

650

65

70%

Install External Pipe Rack-Pipe Supports and Platf

A14440

Install Primary Internal Pipe Rack-Pipe Supports and Platforms - STG2

14

10-11-2013 A

28-02-2014

820

32

70%

Install Primary Internal Pipe Rack-Pipe Supports an

NCR-S357

STG2 Weld Prep Quality - Condenser to Transition-Piece FW5 & Transition-Piece to Turbine
23
FW6
20-11-2013 A

100%

STG2 Weld Prep Quality - Condenser to Transition-Piece FW5

A14500

Complete Installation of Walls & Roof - STG2

Installation of Foundation Supports - Fixators


Prepare Foundation

100%
97

Measure & Mark Axis

90%

Install Gland Steam Condensor and Vacuum Pump -

Place hot well and Condensor


Lift Generator- Gearbox Skid & Turbine into Position
Install HP Oil Skid
Final Alignment - STG2
Final Grouting - STG2

100%
0

STG2 Turbine Pin - Grout Pocket Not in Correct Location

60%

Build Enclosure Structure (Complete) - STG2


Install Emergency Stop Valve

Install Generator Cabinets - STG2

Install and Weld Condensor Exhaust Neck - ST


Install Couplings & Covers - STG2

13-12-2013 A

30

05-02-2014 A

20-03-2014

1200

59

221
7

28-08-2013 A
28-08-2013 A

04-05-2014
03-09-2013 A

6236
0

38
100%

STG1 & 2 Valves and Flanges surface treatment

NCR-S204-985 STG1 & 2 Valves and Flanges painting

63

04-09-2013 A

11-11-2013 A

772

100%

STG1 & 2 Valves and Flanges painting

A14380

Installation of Oil System Pipework - STG2

12

13-09-2013 A

01-02-2014 A

716

100%

A14300

Install Main Steam Pipework to Turbine & Compensator - STG2

21

16-09-2013 A

14-04-2014

800

51

48%

Install Main Steam Pipework to Turbine & Co

A14330

Install Drain System Pipework - STG2

24

20-09-2013 A

12-04-2014

980

38

90%

Install Drain System Pipework - STG2

A14400

Install Condensate System Piping - STG2

10

03-10-2013 A

07-04-2014

600

38

70%

Install Condensate System Piping - STG2

A14390

Install Gland Steam and Vacuum System Piping - STG2

18

14-10-2013 A

09-04-2014

340

53

55%

A14340

Install Drainage Tank - STG2

23-10-2013 A

06-02-2014 A

120

A14310

Install Steam By-Pass Piping - STG2

14

27-10-2013 A

11-04-2014

279

38

40%

A14290

Grout Pipe rack and Supports - STG2

10

24-03-2014

02-04-2014

200

62

0%

Grout Pipe rack and Supports - STG2

A14450

Connect Inlet & Outlet Cooling Water Piping - STG2

24-03-2014

31-03-2014

530

38

0%

Connect Inlet & Outlet Cooling Water Piping -

A15630

Install Piping Insulation - STG2

20

13-04-2014

04-05-2014

600

38

0%

A21910-a

Hydrotest - STG2

15-04-2014

20-04-2014

299

51

0%

224
9

18-08-2013 A
18-08-2013 A

12-06-2014
17-02-2014

10320
631

1
49

80%

YARNIMA.10.15.9.4 PIPING STG2


NCR-S204
STG1 & 2 Valves and Flanges surface treatment

YARNIMA.10.15.9.3 ELECTRICAL STG2


A13420
Pull 11kV Cabling- STG2 to STG Switchroom - STG2
Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 37 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

10%

Complete Installation of Walls & Roof - STG2


YARNIMA.10.15.9.4 PIPING STG2

Installation of Oil System Pipework - STG2

Install Gland Steam and Vacuum System Pipi

100%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Install Drainage Tank - STG2


Install Steam By-Pass Piping - STG2

Install Piping Insulation - STG2

Hydrotest - STG2
YARNIMA.10.15.9.3 ELECTRICAL

Pull 11kV Cabling- STG2 to STG Switchroom - STG2


Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Activity ID

Activity Name

Original
Duration

Start

Finish

Budgeted
Labor Units

Total
Float

Activity % S
Complete

A13510

Pull 11kV Cabling- STG Switchroom to STG2 StepUp Transformer - STG2

13

10-09-2013 A

28-02-2014

2201

49

80%

A13410

Install STG LV Switchroom - STG2

14-09-2013 A

09-02-2014

193

57

95%

A13480

Pull LV-C&I Cabling - STG2 (To CWP - CT Fans - Water Treatment - HRSG Pmps) 38

22-09-2013 A

28-05-2014

3727

35%

A13360

Install STG2 Auxillary 2.5 MVA Transformer - STG2

25-09-2013 A

09-02-2014

105

100

95%

Install STG2 Auxillary 2.5 MVA Transformer - STG2

A13370

Install STG2 Main 8 MVA Transformer - STG2

25-09-2013 A

10-02-2014

159

100

95%

Install STG2 Main 8 MVA Transformer - STG2

A13380

Install Cable Ladder - Steam Turbines - STG2

14

25-09-2013 A

21-04-2014

657

50%

NCR-S286

STG1 & STG2: TG1 and STG2 Walkway HV/LV switchrooms Missing Anchor Bolts on12
the Plinth14-10-2013 A

26-10-2013 A

A13500

LV-C&I Cable Terminations - STG2

14

18-10-2013 A

12-06-2014

882

13%

A13520

11kV Cable Terminations - STG2

21

13-11-2013 A

23-03-2014

25

49

52%

A23040

Pull Power Cables from STG to Cooling Tower 2 (Resource in STG Works)

11

20-12-2013 A

19-02-2014

103

0%

A13390

Field Equipment (LCS's- J.B's- HDG conduits etc...) - STG2

22-04-2014

28-04-2014

40

20

0%

A13440

Install Onskid Elec Equipment & Instruments - STG2

25

22-04-2014

18-05-2014

1046

21

0%

A13400

Lighting & Small Power - STG2

29-04-2014

07-05-2014

654

20

0%

A13470

Earth Grid & Lightning Protection - STG2

15

08-05-2014

23-05-2014

20

0%

65
2

22-09-2013 A
22-09-2013 A

27-06-2014
01-10-2013 A

2010
80

YARNIMA.10.15.9.1 PRECOMMISSIONING STG2


A22060-a
Fill Oil Tank (during commissioning)

Pull 11kV Cabling- STG Switchroom to STG2 Step


Install STG LV Switchroom - STG2

Pull LV-C&I Cabling - STG2 (To CWP

Install Cable Ladder - Steam Turbines - ST

100%

STG1 & STG2: TG1 and STG2 Walkway HV/LV switchrooms Missing A

LV-C&I Cable Terminations - STG2


11kV Cable Terminations - STG2

Pull Power Cables from STG to Cooling Tower 2 (Re

Field Equipment (LCS's- J.B's- HDG cond

Install Onskid Elec Equipment & Instrum


Lighting & Small Power - STG2

Earth Grid & Lightning Protection - ST


YARNIMA.10.15.9.1 PRECOMM

100%

Fill Oil Tank (during commissioning)

A22090

Mechanical Pre-Commissioning - STG2

34

09-05-2014

13-06-2014

640

0%

Mechanical Pre-Commissioning - S

A22110

Electrical Pre-Commissioning - STG2

28

15-05-2014

13-06-2014

616

0%

Electrical Pre-Commissioning - STG

A22100

NDT & QA Documentation - STG2

14

30-05-2014

13-06-2014

80

0%

NDT & QA Documentation - STG2

A22640

Construction Verification and punchlisting A-Items - STG2

13-06-2014

0%

Construction Verification and punch

A22080

Lube Oil Flush (during commissioning) - STG2

10

15-06-2014

24-06-2014

150

0%

Lube Oil Flush (during commissio

A22910

Punchlisting B&C Items - STG2

13

15-06-2014

27-06-2014

0%

A22070-a

Pipe System Flushing (during commissioning) - STG2

17-06-2014

23-06-2014

444

0%

190
15
15

09-11-2013 A
13-01-2014 A
13-01-2014 A

24-04-2014
13-02-2014
13-02-2014

4650
672
672

60
125
125

50%

125
14

12-11-2013 A
12-11-2013 A

25-03-2014
25-03-2014

2559
2367

88
40

43%

Install STG Drains Pit Structural Steelwork

09-02-2014*

13-02-2014

192

125

0%

13
13

26-03-2014
26-03-2014

08-04-2014
08-04-2014

192
0

75
60

Install ST Sump Pumps (2)


YARNIMA.10.15.15.4 HRSG DRAINS PIT P

0%

Install HRSG Drains Pit Structural Steelwork

10

26-03-2014

04-04-2014

192

78

0%

15
15

09-04-2014
09-04-2014

24-04-2014
24-04-2014

687
624

60
60

Install HRSG Sump Pumps (2)


YARNIMA.10.15.15.5 SUMP PUMPS (13)

0%

15

09-04-2014

24-04-2014

63

60

0%

13
13

09-11-2013 A
09-11-2013 A

18-02-2014
18-11-2013 A

540
0

120

YARNIMA.10.15.15 COOLING WATER PUMPS


YARNIMA.10.15.15.2 AUXILIARY COOLING WATER PUMPS
A10230
Install Auxillary Cooling Water Pumps (4)
YARNIMA.10.15.15.3 STEAM TURBINE DRAINS PIT PUMPS (2)
A10240
Install STG Drains Pit Structural Steelwork
A10340

Install ST Sump Pumps (2)

YARNIMA.10.15.15.4 HRSG DRAINS PIT PUMPS (2)


A11460
Install HRSG Drains Pit Structural Steelwork
A11470

Install HRSG Sump Pumps (2)

YARNIMA.10.15.15.5 SUMP PUMPS (13)


A5780
Install Sump Pumps (13)
A11480

Install Sumps Structural Steelwork

YARNIMA.10.15.15.1 MAIN COOLING WATER PUMPS


A10210
Cooling Water Valve Platforms (9 off) (Removed From Scope)
A10200

Cooling Water Pump Platforms (3 off) (Removed From Scope)

13

09-11-2013 A

18-11-2013 A

A10190

Install Main Cooling Water Pumps (3)

10

09-12-2013 A

18-02-2014

540

120

29-06-2014

29-06-2014

29-06-2014

YARNIMA.6 DEMOBILISATION
A3190

Demobilise Cimeco Personnel and Equipment

Actual Work

Primary Baseline

Remaining Work

Baseline Milestone

Critical Remaining Work

Milestone

Summary

Page 38 of 38
Data Date 07-02-2014

Date
19-Dec-12
21-11-2013
07-02-2014

Punchlisting B&C Items - STG2

Pipe System Flushing (during com


YARNIMA.10.15.15 COOLING WATER P
YARNIMA.10.15.15.2 AUXILIARY COOLING WATER

Install Auxillary Cooling Water Pumps (4)


YARNIMA.10.15.15.3 STEAM TURBINE DRA

Install Sump Pumps (13)

Install Sumps Structural Steelwork


YARNIMA.10.15.15.1 MAIN COOLING WATER PU

100%

Cooling Water Valve Platforms (9 off) (Removed From Scope)

100%

Cooling Water Pump Platforms (3 off) (Removed From Scope)

70%

Install Main Cooling Water Pumps (3)


YARNIMA.6 DEMOBILISATION

0%

Revision
APPROVED CONSTR SCHED BASELINE REV O
APPROVED ACP Rev 01
Updated Construction Schedule

Demobilise Cimeco Personnel an

Checked
Approved
WC
KU
KU
TL

Document Number: C1034-22.1-00PRJ-PL-001d


Project ID: YAR - PROGRAM-1

Potrebbero piacerti anche