Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Table of Contents
1.
Electricity
Generated
Up
2.
Installed
Capacity
&
Transmission
to
date
Network
2
2015-2039
4
(GWh
)
Growth
Rate (%)
*Net
Losses
Generation
Peak
Growth
(MW)
Rate (%)
(%)
(GWh)
4.5%
4.3%
6.8%
6.8%
6.8%
2401
2483
2631
2788
2954
6.8%
4.9%
4.9%
5.0%
5.0%
3131
3259
3394
3534
3681
11516
12015
12842
13726
14671
4.1%
4.3%
6.9%
6.9%
6.9%
10.73
10.68
10.62
10.57
10.51
2020
2021
2022
2023
2024
15681
16465
17288
18155
19069
6.9%
5.0%
5.0%
5.0%
5.0%
10.46
10.40
10.35
10.29
10.23
12901**
13451**
1436
8
1534
8
17512
18376
19283
20238
21243
2025
2026
2027
2028
2029
20033
21050
22125
23243
24402
5.1%
5.1%
5.1%
5.1%
5.0%
10.18
10.12
10.07
10.01
9.96
22303
23421
24601
25829
27100
5.0%
5.0%
5.0%
5.0%
4.9%
3836
4014
4203
4398
4599
2030
2031
2032
2033
2034
25598
26827
28087
29395
30759
4.9%
4.8%
4.7%
4.7%
4.6%
9.90
9.84
9.79
9.73
9.68
28410
29756
31135
32565
34055
4.8%
4.7%
4.6%
4.6%
4.6%
4805
5018
5235
5459
5692
2035
2036
2037
2038
2039
32184
33673
35231
36862
38569
4.6%
4.6%
4.6%
4.6%
4.6%
9.62
9.57
9.51
9.46
9.40
35611
37235
38934
40711
42571
4.6%
4.6%
4.6%
4.6%
4.6%
5934
6187
6451
6726
7013
5 Year
Average
Growth
10
Year
6.24%
6.17%
5.32%
5.76%
5.70%
4.86%
5.31%
5.24%
4.65%
5.17%
5.10%
4.57%
Average
Growth
20
Year
Average
Growth
25
Year
Average
Growth
* Net losses include losses at the Transmission & Distribution levels and any non-technical losses,
Generation (Including auxiliary consumption) losses are excluded.
**Generation fixed for Energy Marketing Branch Energy Demand Forecast 2015-2016, prepared
based on values provided by each Distribution Division
YEAR
2015
2016
35 MW Broadlands HPP
120 MW Uma Oya HPP
2017
2018
2019*
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
THERMAL
ADDITIONS
4x15 MW CEB Barge
Power
Plant
-
THERMAL
RETIREMENT
S Power Plant
4x15 MW Colombo
14x7.11 MW ACE Power
Embilipitiya
-
LOLP
%
0.077
0.150
0.175
0.299
1.140
0.164
2x250 MW Coal
Power Plants
Trincomalee Power
Company Limited
2x300 MW New Coal
Plant
Trincomalee -2, Phase
163 MW Combined Cycle
Plant
+
(KPS 2)
0.360
0.015
0.096
0.040
0.028
0.003
0.002
0.010
0.007
0.005
0.029
0.003
0.142
2034
Notes:
Discount rate 10%, Exchange Rate as an average of January 2015 (US$ 1 = LKR. 131.55)
Committed plants are shown in Italics. All plant capacities are given in gross values.
+
PV cost includes the cost of Projected Committed NCRE, US$ 1527.9 million based on economic
cost, and an additional
Spinning Reserve requirement is kept considering the intermittency of NCRE plants with a cost
of US$ 471.5 million.
*
In year 2019, minimum Reserve Margin criteria of 2.5% is violated due to generation capacity
limitation, and the minimum
RM is kept at -1.3%.
** Thalpitigala and Gin Ganga multipurpose hydro power plants proposed by Ministry of Irrigation
are forced considering secured Cabinet approval for the implementation of the Projects.
*** Seethawaka HPP and PSPP units are forced in 2022, 2025 and 2026 respectively.
++ IPP AES Kelanitissa scheduled to retire in 2023 will be operated as a CEB power plant from 2023 to
2033.
Moragahakanda HPP will be added in to the system by 2017, 2020 and 2022 with capacities of 10
MW, 7.5 MW and 7.5
MW respectively.
6. Reference
I.
II.
III.
IV.
V.
Electricity Generation
: http://www.ceb.lk/ and http://www.ceb.lk/yesterdayelectricity/
Status of NCRE Sector
: http://www.ceb.lk/do-business-with-us/#tab1439815407733-3-3
Installed Capacity & TX Network
: http://www.ceb.lk/knowledge-center/#tab1442494789429-6-6
Base Load Forecast
: Long Term Generation Expansion Plan 2015-2034
Page E-4
Base Case Plan 2015-2034
: Long Term Generation Expansion Plan 2015-2034
Page E-5