Sei sulla pagina 1di 24

Project: CONSTRUCTION OF NEW PIPELINE FROM

GUEBIBA TO CFTP
HAZID/HAZOP/SIL/ TOR

HAZID/HAZOP/SIL TOR

CONSTRUCTION OF NEW PIPELINE FROM GUEBIBA/TB TO CFTP

001/AR03/13

03/12

HAZID/HAZOP/SIL TOR

PAGE: 2 /24

TABLE OF CONTENTS
1.

INTRODUCTION..........................................................................................3
1.1
ABBREVIATIONS............................................................................................................ 4
Compagnie Franco-Tunisienne des Ptroles.........................................................................4

2.

HAZID STUDY............................................................................................ 5
2.1
2.2
2.3

3.

HAZOP STUDY........................................................................................... 7
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10

4.

SCOPE & OBJECTIVES OF THE HAZID STUDY.........................................................................5


HAZID TECHNIQUE....................................................................................................... 5
HAZID RECORDING....................................................................................................... 6
SCOPE & OBJECTIVES OF THE HAZOP STUDY.....................................................................7
HAZOP METHODOLOGY................................................................................................. 7
HAZOP TECHNIQUE................................................................................................... 8
HAZOP RECORDING.................................................................................................... 11
HAZOP NODES......................................................................................................... 11
HAZOP TEAM........................................................................................................... 11
HAZOP FOLLOW UP................................................................................................... 11
HAZOP RECOMMENDATIONS......................................................................................12
PROCESS SYSTEMS / FACILITIES.......................................................................................12
REPORT.................................................................................................................. 12
SAFETY INTEGRITY LEVEL (SIL).....................................................................13

4.1
SCOPE & OBJECTIVES OF THE SIL STUDY........................................................................13
4.2
PROBABILITY OF FAILURE............................................................................................... 13
4.3
SIL CLASSIFICATION..................................................................................................... 14
1.1.1 RISK GRAPH TECHNIQUE...........................................................................................14
1.1.2 LAYER OF PROTECTION ANALYSIS..................................................................................15
4.4
RISK MATRIX.............................................................................................................. 15
4.5
RISK REDUCTION........................................................................................................ 16
4.6
RISK ANALYSIS TEAM.................................................................................................... 16
4.7
SIL RECORDING......................................................................................................... 17
5.

APPENDICES............................................................................................ 18
5.1
PROCESS SAFETY RISK GRAPH......................................................................................... 18
5.2
COMMERCIAL RISK GRAPH............................................................................................. 20
5.3
ENVIRONMENTAL RISK GRAPH......................................................................................... 21
5.4
TYPICAL PROBABILITIES OF FAILURE ON DEMAND (PFODS) FOR MENTIONED TYPES OF
INDEPENDENT PROTECTION LAYERS (IPLS)............................................................................23

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
REV. 0
PAGE: 3 / 24

1. INTRODUCTION
This document provides significant aspects and considerations of HAZID, HAZOP, and SIL study related to
the construction of new pipeline from guebiba/tb to cftp project.

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
REV. 0
PAGE: 4 / 24

2. Abbreviations
The following abbreviations will be used:
CFTP

Compagnie Franco-Tunisienne des Ptroles

HAZID

Hazard Identification

HAZOP

Hazard & Operability

SIL

Safety Integrity Level

SIF

Safety Instrumented Function

P&ID

Piping & Instrumentation Diagrams

SLC

Safety Life Cycle

LOPA

Layer of Protection Analysis

CIL

Commercial Integrity Levels

E/E/PES

Electrical/electronical/programmable electronical systems

IPF

Instrumented Protective Function

IEC

International Electrotechnical Commission

EIL

Environmental Integrity Levels

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
REV. 0
PAGE: 5 / 24

3. HAZID Study
3.1 SCOPE & OBJECTIVES OF THE HAZID STUDY
For this project, HAZID (Hazard Identification) analysis is required: the overall objective is to produce a
facility in respect of which all risks to the human, Environment, company reputation and the assets
have to be identified and minimized.
The HAZID worksheet objectives are:

To systematically analyse the Project for potential hazards identification.

To list all the needed documents about the project, that must be prepared in the following basic or
detail design phase.

Considering the simplicity of the design, the risk-ranking for the recommendations has been limited to
cases where a clear critical consequence was specified and the recommendation is proposed as a
choice between different solutions.

For all the recommendations requiring further analysis, design and / or engineering studies /
documents, operating procedures development, or other efforts that however must be done or
prepared, the risk ranking will be considered superfluous.
3.2 HAZID TECHNIQUE

The HAZID Review will be conducted as a guided brainstorming, by means of guidewords applied to the
project.
The specific intention of this Hazards review is to highlight and estimate hazards deriving from the new
pipeline from Guebiba/TB to CFTP, not only at normal operation phase but also during construction,
commissioning and maintenance activities.
The analysis is concentrated on the inherent external and internal hazards for the project, and is focussed
on specific parts of the selected process, philosophies and operational concepts.
A part is dedicated to the environmental aspect where potential impacts, corresponding causes,
consequences and associated protections are identified, this analysis enables quick and yet trustful setting
of documented Environmental Protection and regulatory compliance measures.
With the help of guidewords, hazards will be identified together with potential means of control and
mitigation.
For each hazard, a qualitative assessment of the expected likelihood and severity of consequences will be
given, on the basis of the risk assessment documents.
The minutes of the HAZID Review detailing the hazards, causes and consequences, risk-ranking,
recommendations and residual risk ranking will be recorded in HAZID Worksheets.

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
REV. 0
PAGE: 6 / 24

Figure 1: HAZID PROCEDURE


3.3 HAZID RECORDING
The discussion will be recorded by the HAZID Secretary using dedicated software: LEADER 2015
version.

NO.
REV. 0
PAGE: 7 / 24

HAZOP/HAZID/SIL/SIMOPS ToR

4. HAZOP Study
4.1 SCOPE & OBJECTIVES

OF

THE HAZOP STUDY

HAZOP (Hazard and Operability Study) is a qualitative methodology that identifies possible deviations from
the correct functioning of the process, analyzing moreover the consequences of such anomalies and the
actions to be taken in order to limit them to the smallest possible areas.
The HAZOPs targets are:
-

To identify possible deviations from the intended operation that can cause personnel or

equipment harm as well as operation disturbances (accidental events),


To establish how deviations from the design intent can arise,
To assess whether such deviations and their consequences can have a negative effect upon

the safe and efficient operation of the system,


To recommend actions, whenever is necessary, in order to remedy to the deviations.

4.2 HAZOP METHODOLOGY


The method used for the HAZOP is a systematic review of the process; therefore the primary words will be
the process parameters: Flow, Pressure, Temperature, Composition, and Level.
And the secondary words, which are combined with a primary keyword, are the different HAZOP
guidewords permit to suggest possible deviations: No, Less, More, Part of, As well as, Reverse, Other
thanetc.
In practice, the process parameters are combined with standard guidewords to set down a list of
deviations from the normal operation of the system under review. The following combinations were used
in this Study:
Table 1: Deviations represented by Parameters and Guidewords
Parameters

Guidewords

Flow

No
Reverse
More
Less

Temperature

More
Less

Pressure
Composition

Level

More
Less
As well as
Part of

More
Less

Deviations
No Flow (complete lack of flow)
Reverse Flow (flow in the opposite direction than the normal operation)
More Flow (higher flow rate than expected)
Less Flow (lower flow rate than expected)
Higher Temperature (than expected)
Lower Temperature (than expected)
Higher Pressure (than expected)
Lower Pressure (than expected)
Contamination
Composition Change (fluid composition different than expected, e.g. offspec feed, incorrect chemical dosing, etc.)
Higher Level (higher liquid level in a vessel or tank, up to overfilling
condition)
Lower Level (lower liquid level in a vessel or tank, up to a complete loss
of level)

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
REV. 0
PAGE: 8 / 24

Parameters

Guidewords

Deviations

Other

Other

Other (any other cause of upset or unsafe condition identified during the
HAZOP but not linked to an identified parameter)

4.3 HAZOP TECHNIQUE


HAZOP is a systematic procedure used to review the process design for identification of potential hazards
and operability problems caused by deviation from the design intent of both new and existing process
facilities. The methodological approach is to identify deviations from the design intent using parameters
and appropriate guidewords, and to define any actions necessary to reduce the probability of occurrence
and/or eliminate/mitigate the consequences.
The system will be divided into discrete Nodes (a "node" is a sub-system or a portion of a systems which
can be analyzed alone, e.g. a tank, a header, a pump, even a single line, together with the relevant
connections to the interfaces), and the methodology will be applied thoroughly to each node until all the
system be fully analyzed.
The method involves the following steps for each Node:

Define a Node of the process on the P&IDs;

Clarify the design intent and the normal operating conditions of the Node;

Identify a Deviation from the intent or operating conditions by applying parameter and a
Guidewords;

List possible Causes and Consequences of the Deviation (a Deviation can be considered
meaningful if it has credible causes and can result in harmful consequences);

Identify the Safeguards (if any), as shown in project documentation;

Formulate Recommendations (and identify the responsible for implementation/action) if no


sufficient Safeguards are provided.

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
REV. 0
PAGE: 9 / 24

The following figure summarizes the HAZOP Procedure that has been applied.

Figure 2: HAZOP PROCEDURE


If a deviation and/or event are found to be realistically possible and to give rise to a significant
consequence, it is discussed in the HAZOP Study Worksheets.
The cases where there are no credible causes of deviation, and/or no events giving rise to significant
consequences, will not been recorded on the Worksheets.
The keyword combinations will be discussed following an iterative process in order to identify potential
problems, as the diagram mentioned below:

NO.
REV. 0
PAGE: 10 / 24

HAZOP/HAZID/SIL/SIMOPS ToR

Describe process section

Select a Node and describe design intent

Have all relevant Parameter for this plant section


been considered?

Yes

No

Select a parameter not previously considered (e.g.


Pressure)

Have all relevant guideword for this parameter


been considered?

Yes

No

Select a guideword previously considered


(e.g. More)

Determine cause of deviation from design intent;


assess potential hazard/operational problem
associated with the defined cause

Are there any causes for this deviation not


previously discussed and recorded?

Yes

Record the new cause

No

Are associated consequences of any significance?

Yes

Record the consequence/s

Record any Safeguards identified

No

Having regard to the consequences and


Safeguards, is an Action necessary?

Yes

Record the agree Action

No

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
Rev. 0
PAGE: 11 /24

4.4 HAZOP RECORDING


The HAZOP discussion will be recorded by the HAZOP Secretary using dedicated software: LEADER
2015 VERSION.
This software leads to:
-

A complete sets of topics added instantly;


A vast Leader Library, puts hundreds of standard HAZOP deviations;
Add own custom topics to any section, to the library, or to the project template that can be

created;
Copy, reorder, and renumber topics.

The record will be made during the session using laptop, and will be projected onto a suitable screen
so that all team members can see inputs to the record as it is produced.
4.5 HAZOP NODES
In order to perform the analysis and focus the teams attention on a specific area, the different process
systems will be divided into a convenient number of discrete nodes. Each node represents a section of
the system that can be composed by one or more items with homogeneous characteristics in terms of
pressure, temperature or service. A new node starts when main process parameters change or isolation
is present.
4.6 HAZOP TEAM
The HAZOP shall be carried out by a multidisciplinary team to ensure all aspects of the plant and its
operations are covered. The team members specialists include process design, instrumentation and
control, mechanical engineering, safety and operation.
The chairman has to:

Select the teams members

Plan and prepare the study,

Chair the HAZOP meetings: Trigger the discussion using guidewords and parameters,

Follow up progress, Ensure completeness of the analysis.

The team will include a nominated scribe, responsible for recording discussion and findings.
4.7 HAZOP FOLLOW UP
The HAZOP Actions Coordinator will be responsible for ensuring the Action Items are forwarded to the
parties responsible for action implementation, and for recording the status of the actions.
The relevant discipline specialists should close-out the addressed actions, indicating the resolution and
providing references and evidence of implementation. The action sheet completed with close-out

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
Rev. 0
PAGE: 12 /24

information shall be returned to the HAZOP Actions Coordinator. The HAZOP Actions Coordinator should
review the responses and proceed until full resolution of all pending issues.
When an action is closed, the HAZOP Actions Coordinator should mark the action as CLOSED in the
action status column. When all actions will be closed, the Coordinator can issue the close-out report
(i.e. the collection of all the resolutions and action close-outs). All Actions shall be ideally closed
before the end of the Engineering Phase.
4.8 HAZOP RECOMMENDATIONS
The analysis results of the HAZOP study shall be represented by a series of recommendations which
take the form of suggested design changes, requirements of verification and additional studies or
suggestions for specific operational procedures to be implemented. The recommendations will be
managed in the activity of follow-up and implemented during the project development.
4.9 PROCESS SYSTEMS / FACILITIES
To ensure process integrity and to identify process hazards and operational problems for process
systems or facilities, a systematic review of the P&IDs shall be made.
4.10

REPORT

The HAZOP Report is a key document pertaining to the safety of the plant. It should provide sufficient
information on each element so that, either read alone or together with available and clearly cross
referenced documents, an assessment can be made of the adequacy of the HAZOP study carried out.
The contents of such a summary might typically be:
-

Introduction;

System definition and delimitation;

Documents (on which the analysis is based);

Methodology;

Team members;

HAZOP results:

Reporting principles,

Classification of recordings,

Main results;

HAZOP study worksheet.

Appendices:
P&IDs (marked),

HAZOP/HAZID/SIL/SIMOPS ToR

List of participants.

NO.
Rev. 0
PAGE: 13 /24

NO.
Rev. 0
PAGE: 14 /24

HAZOP/HAZID/SIL/SIMOPS ToR

5. Safety Integrity Level (SIL)


5.1 SCOPE & OBJECTIVES OF THE SIL STUDY
The analysis of hazards and risks gives rise to the need to reduce the risk and within the SLC of the
standards this is identified as the derivation of the safety requirements. There may be some overall
methods and mechanisms described in the safety requirements but also these requirements are then
broken down into specific safety functions to achieve a defined task.
In parallel with this allocation of the overall safety requirements to specific safety functions, a
measure of the dependability or integrity of those safety functions is required.
What is the confidence that the safety function will perform when called upon?
This measure is the SIL. More precisely, the safety integrity of a system can be defined as:
"The probability (likelihood) of a safety-related system performing the required safety functions
under all the stated conditions within a stated period of time."
Thus the specification of the safety function includes both the actions to be taken in response to the
existence of particular conditions and also the time for that response to take place. The SIL is a
measure of the reliability of the safety function performing to specification.
5.2 PROBABILITY

OF FAILURE

To categorise the safety integrity of a safety function the probability of failure is considered in effect
the inverse of the SIL definition, looking at failure to perform rather than success.
It is easier to identify and quantify possible conditions and causes leading to failure of a safety function
than to guarantee the desired action of a safety function when called upon.
Two classes of SIL are identified, depending on the service provided by the safety function

For safety functions that are activated when required (on demand mode) the probability of

failure to perform correctly is given, whilst


For safety functions that are in place continuously the probability of a dangerous failure is
expressed in terms of a given period of time (per hour) (continuous mode).

The probabilities of failure are related to one of four safety integrity levels, as shown in Table 1:
Table 2: Probability of failure

Probability of failure
Safety Integrity
Level (SIL)
b
4
3
2
1
a

Mode of operation on demand (average


probability of failure to perform its design
function upon demand)

Mode of operation continuous


(probability of dangerous failure per
hour)

A single E/E/PES is not sufficient


10-5 to < 10-4
10-9
10-4 to < 10-3
10-8
10-3 to < 10-2
10-7
10-2 to < 10-1
10-6
No special safety requirements

to
to
to
to

<
<
<
<

10-8
10-7
10-6
10-5

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
Rev. 0
PAGE: 15 /24

5.3 SIL CLASSIFICATION


The following methods will be used for Target Safety Integrity:
Risk Graph
Layer of Protection Analysis (LOPA)
Both these methods are included in the IEC61508 and IEC61511 standard. The risk graph is a qualitative
technique, the results tend to be quite subjective and lead to SIL levels biased on the high side. The
Layers of protection analysis technique is quantitative and more accurate and it is becoming the widely
accepted technique for SIL determination.
5.3.1

RISK GRAPH TECHNIQUE

The risk graph method is a qualitative approach to determine the level of integrity required for the
identified Instrumented Protective Functions (IPF) for the project. The approach is based on the
International Electro technical Commission standard, IEC61511.
Risk graph analysis uses four parameters to make a SIL selection. These parameters are consequence
(C), occupancy (F), probability of avoiding the hazard (P), and demand rate (W).
-

Process Safety Risk Analysis

Each loop shall be reviewed on the following basis:

Consequence Severity

Personnel Exposure

Alternatives to Avoid Danger

Demand Rate

The SIL rating is calculated using the response to the 4 questions and the appropriate SIL level is
generated using the IEC risk graph attached in Appendix (6.1).
-

Commercial Risk Analysis

Each of the loops reviewed shall be subjected to an Asset Protection Review. This shall be carried out
on the following basis:

Consequence Severity

Demand Rate

The risk graph for asset / economic loss is provided in Appendix. Before this chart is used, it must be
calibrated for the specific plant it is used on. Consequence severity should represent the meaningful
range of negative impacts towards important asset or economic objectives (e.g. reliability,
replacement or repair costs)

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
Rev. 0
PAGE: 16 /24

The equivalent CIL rating is calculated using the response to the 2 questions and the appropriate
equivalent CIL level is generated using the IEC risk graph attached in Appendix (6.2).
-

Environmental Risk Analysis

Each of the loops reviewed shall be subjected to an Environmental Review. This shall be carried out on
the following basis:

Consequence Severity

Demand Rate

Environmental protective functions should be assessed against a risk graph that provides the range of
negative consequences with respect to important environmental objectives for the specific plant, area
of operation and local legislative requirements. For example, violation of discharge permits or flare
consents spills of varying magnitude.
The equivalent EIL rating is calculated using the response to the 2 questions and the appropriate
equivalent EIL level is generated using the IEC risk graph attached in Appendix (6.3).
5.3.2

LAYER

OF

PROTECTION ANALYSIS

LOPA is one of the techniques developed in response to a requirement within the process industry to be
able to assess the adequacy of the layers of protection provided for an activity. Initially this was driven
by industry codes of practice or guidance and latterly by the development of international standards
such as IEC61508 and IEC61511.
Once the tolerable frequency for a SIF is established, all causes of the initiating event are listed. For
each cause of the initiating event, its likelihood is established. The layers of protection and associated
PFD for each cause are then listed. The mitigated event frequency for each cause is determined. After
each cause is analyzed the total event frequency due to all causes for the initiating event is
determined. The SIL is determined by comparing the established tolerable frequency (goal) with the
total mitigated event frequency.
5.4

RISK MATRIX

The risk matrix is a method categorizing the frequency or likelihood and severity of a risk event using
multiple qualitative levels. The risk matrix tolerance will represented with risk matrix. The OMV risk
matrix is shown below:

Frequency (Cases Per Year)


E
Frequent (> 1*10^-2/year)
D Probable (1*10^-2 to 1*10^-4/year)
C Seldom (1*10^-4 to 1*10^-5/year)

Intolerable Region
Tolerable if ALARP Region

NO.
Rev. 0
PAGE: 17 /24

HAZOP/HAZID/SIL/SIMOPS ToR

B
A

Unlikely (1*10^-5 to)


Improbable (<1*10^-7/year)

Broadly Acceptable Region


1

Consequence Level

Low

5
High

Figure 3: RISK MATRIX

5.5 RISK REDUCTION


Its important to ensure that the risk reduction achieved for E/E/PES protective layer and other
technologies are sufficient so that the necessary risk reduction is achieved and that risk is reduced to
tolerable levels shown in the Figure below:

Figure 4: IEC - Risk Reduction Model ALARP Reduction

5.6 RISK ANALYSIS TEAM


The typical SIL classification Team should include the following personnel:

SIL Facilitator;

Secretary;

Process Engineer;

Safety Engineer;

Instrument Engineer;

Operations Personnel;

Specialist Engineers and Technicians (for example HVAC and Rotating Machinery).

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
Rev. 0
PAGE: 18 /24

5.7 SIL RECORDING


SIL software tools may be used to facilitate the documentation of the classification process and the
calculation of the IPF loop reliabilities.
The SIL discussion will recorded by the SIL Secretary using dedicated software LOPA, Its a tool
integrated in the HAZARD REVIEW SOFTWARE 2015 VERSION.
This software leads to:
-

A vast integrated Library puts many scenarios (causes, consequences...);


Various Types of Independent Protection Layers (IPLs);
Typical Probabilities of Failure on Demand from Literature and Industry;
Typical Frequencies for Various Types of Initiating Events;
Complete sets of topics added instantly....

NO.
Rev. 0
PAGE: 19 /24

HAZOP/HAZID/SIL/SIMOPS ToR

6. Appendices
6.1 PROCESS SAFETY RISK GRAPH

Figure 1 : IEC Process Safety Risk Graph

- = No safety requirements
NR = Not recommended. Consider alternatives
Table 1: IEC Process Safety Risk Graph Data

Risk Parameter
C1
C2
C3
Consequence (C)
C4

Classification
Comments
1. The classification system has been developed to
Slight Injury
Serious injury or 1 death deal with injury and death to people.
Death to several people
2. For the interpretation of C1, C2, C3 and C4, the
Very many people killed

consequences of the accident and normal healing


shall be taken into account.

Frequency

of,

and

exposure

time

in,

hazardous
(F)

F1

the
zone F2

Rare to often exposure


in the hazardous zone
Frequent to permanent 3. See comment 1 above.
exposure

in

hazardous zone

the

NO.
Rev. 0
PAGE: 20 /24

HAZOP/HAZID/SIL/SIMOPS ToR

Risk Parameter

Classification
4.

This

Comments
parameter
takes

into

account:

- operation of a process (supervised (i.e. operated


P1

Possible under certain by skilled or unskilled persons) or unsupervised);


conditions

- rate of development of the hazardous event (for


example suddenly, quickly or slowly);

Possibility
avoiding

of

- ease of recognition of danger (for example seen

the

immediately, detected by technical measures or

hazardous event

detected

(P)

without

technical

measures);

- avoidance of the hazardous event (for example


P2

Almost impossible

escape routes possible, not possible or possible


under

certain

conditions);

- actual safety experience (such experience may


exist with an identical EUC or a similar EUC or may
not exist)
W1

W2
Probability f the

Demand Rate once in


every 30 years or more.

5. The purpose of the W factor is to estimate the


frequency of the unwanted occurrence taking place

Demand Rate between 3 without the addition of any safety-related systems


30 years.

(E/E/PES or other technology) but including any


external

unwanted

risk

reduction

facilities

6. If little or no experience exists of the EUC, or

occurrence (W)
W3

Demand Rate between


0.3 3 years

the EUC control system, or of a similar EUC and


EUC control system, the estimation of the W factor
may be made by calculation. In such an event a
worst case prediction shall be made.

6.2 COMMERCIAL RISK GRAPH

NO.
Rev. 0
PAGE: 21 /24

HAZOP/HAZID/SIL/SIMOPS ToR

Figure 2 : Commercial Risk Graph

- = No safety requirements
NR = Not recommended. Consider alternatives
Table 2: Commercial Risk Graph Data

Risk Parameter

Classification
C0
C1

Consequence

C2
C3

Possibility of
avoiding the
hazardous event
(P)

Comments

No operational upset or
equipment damage
Minor operational upset or

1. Each facility will have specific economic

equipment damage.
Moderate operational upset

consequences which should be considered. These

or equipment damage
Major operational upset or

commences. Risk graphs should be selected and

equipment damage.
Damage to essential

consequences and the local business model.

should be established before the classification


calibrated to suit the specific economic

C4

equipment, major economic

P1

loss or loss of containment


Possible under certain

2. While not used in this example the risk graph

conditions

may be adapted to include this requirement


3. This parameter takes into account:
- operation of a process (supervised (i.e. operated

NO.
Rev. 0
PAGE: 22 /24

HAZOP/HAZID/SIL/SIMOPS ToR

by skilled or unskilled persons) or unsupervised);


- rate of development of the hazardous event (for
example suddenly, quickly or slowly);
- ease of recognition of danger (for example seen
immediately, detected by technical measures or
P2

Almost impossible

detected without technical measures);


- avoidance of the hazardous event (for example
escape routes possible, not possible or possible
under certain conditions);
- actual safety experience (such experience may
exist with an identical EUC or a similar EUC or may

W1

Demand Rate once in every

not exist)
7. The purpose of the W factor is to estimate the

30 years or more.

frequency of the unwanted occurrence taking place


without the addition of any safety-related systems

Probability f the

W2

Demand Rate between 3 30


years.

(E/E/PES or other technology) but including any


external risk reduction facilities

unwanted

8. If little or no experience exists of the EUC, or

occurrence (W)
W3

Demand Rate between 0.3


3 years

the EUC control system, or of a similar EUC and


EUC control system, the estimation of the W factor
may be made by calculation. In such an event a
worst case prediction shall be made.

6.3 ENVIRONMENTAL RISK GRAPH

Figure 3 : Environmental Risk Graph

- = No safety requirements
NR = Not recommended. Consider alternatives

HAZOP/HAZID/SIL/SIMOPS ToR

NO.
Rev. 0
PAGE: 23 /24

Table 3: Environmental Risk Graph Data

Risk Parameter
C0
C1
Consequence

C2
C3

C4

P1

Classification
No release or a negligible

Comments
1. Each facility will have specific

environmental impact
Release with minor impact on

environmental; consequences /

environmental reportable
Release with moderate impact on the

considered. These should be

environment.
Release with temporary major impact

commences. Risk graphs should be

on the environment.
Release with permanent major impact
on the environment

Possible under certain conditions

regulations which should be


established before the classification
selected and calibrated to suit the
specific environmental
consequences and the local business
model.
2. While not used in this example
the risk graph may be adapted to
include this requirement.
3. This parameter takes into
account:
- operation of a process (supervised
(i.e. operated by skilled or unskilled
persons) or unsupervised);
- rate of development of the
hazardous event (for example
suddenly, quickly or slowly);

Possibility of avoiding

- ease of recognition of danger (for

the hazardous event

example seen immediately,

(P)
P2

Almost impossible

detected by technical measures or


detected without technical
measures);
- avoidance of the hazardous event
(for example escape routes
possible, not possible or possible
under certain conditions);
- actual safety experience (such
experience may exist with an
identical EUC or a similar EUC or

Probability f the
unwanted occurrence

W1

(W)

W2

Demand Rate once in every 30 years

may not exist)


9. The purpose of the W factor is to

or more.

estimate the frequency of the

Demand Rate between 3 30 years.

unwanted occurrence taking place


without the addition of any safetyrelated systems (E/E/PES or other

NO.
Rev. 0
PAGE: 24 /24

HAZOP/HAZID/SIL/SIMOPS ToR

Risk Parameter

Classification

W3

Comments

Demand Rate between 0.3 3 years

technology) but including any


external risk reduction facilities
10. If little or no experience exists
of the EUC, or the EUC control
system, or of a similar EUC and EUC

control system, the estimation of


6.4 TYPICAL PROBABILITIES OF FAILURE ON DEMAND (PFODS) FOR MENTIONED TYPES OF
INDEPENDENT PROTECTION LAYERS (IPLS)

IPL Type

Description

BPCS

Basic process control system;


automatic control loop
independent of the initiating
event

Human
response
(10 min
available)

PFOD from
Literature and
Industry

PFOD
Chosen
for LOPA

10-1 to 10-2

1.00E-01

Human response with 10 minutes


available for response;
notification must be independent
of initiating event and other IPLs,
and operator training must
include required response

1 to 10-1

1.00E+00

Human
response
(40 min
available)

Human response with 40 minutes


available for response;
notification must be independent
of initiating event and other IPLs,
and operator training must
include required response

10-1 to 10-2

1.00E-01

Passive

Passive device (e.g., a dike with


good control over drains) that is
not required to take an action in
order for it to achieve its
function in reducing risk

10-1 to 10-3

1.00E-02

Relief
device

Relief valve or rupture disk


(effectiveness is sensitive to
service and experience)

10-1 to 10-5

1.00E-03

Typical Comment for PFOD


Used typical value for an
automatic control loop in a
basic process control system,
independent of the initiating
event
Used typical value for human
response with 10 minutes
available for response;
notification is independent of
initiating event and other IPLs,
and operator training includes
required response
Used typical value for human
response with 40 minutes
available for response;
notification is independent of
initiating event and other IPLs,
and operator training includes
required response
Used typical value for a passive
device that is not required to
take an action in order for it to
achieve its function in reducing
risk
Used typical value for a relief
valve or rupture disk in clean,
non-corrosive service; assumes
maintenance per industry
standards

Potrebbero piacerti anche