Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
HAZOP
EP 95-0313
HSE MANUAL
Rev.
No.
0
Chapter
Nos.
All
Description of amendment
Date
Amended by
dd/mm/yy
Original hard copy and CD-ROM issue
13/10/95
EPO/61
SUMMARY
The EP HSE Manual replaces the previous Safety Manual, EP 55000 and EP 92-0100, Users Guide to the Structure of
SMS and Safety Cases. It is expanded to include the management of all three issues of Health, Safety and the Environment
(HSE). The Manual comprises three volumes, each including a number of separate sections of which this is one. The
Manual describes the elements necessary to develop, implement and maintain an HSE Management System for
Exploration and Production activities and describes the tools and techniques available to do this. The HSE Manual follows
the guidelines described in the document 'HSE Management System' issued in September 1994 by the Shell HSE
Committee and endorsed by the Committee of Managing Directors (CMD). In line with the Shell strategy to adopt Industry
or International Standards wherever possible, the HSE Management System in this Manualhas been based on the
Copyright
The copyright of this Manual is vested in Shell International Exploration and Production B.V. (SIEP), The Hague, the
Netherlands. The Manual is issued as guidance to companies of the Royal Dutch/Shell Group and associated companies
under service agreements with SIEP. These companies may give copies of the Manual to their contractors for the purpose
of implementing a relevant contract but such copies should be accompanied by an explanatory note on the manner in which
the Manual is to be used. Thesecompanies may also provide a copy for information to other third parties with the prior
consent of SIEP. Contractors and other third parties should not disclose the Manual outside their own organisation and
return their copy after an appropriate period.
Disclaimer
No liability is accepted by SIEP or any other company or person involved in the preparation of the Manual for any
consequences whatsoever resulting directly or indirectly from the use of the Manual or any error or omission therein even if
caused by a failure to exercise reasonable care.
*E&P FORUM
The Oil Industry International Exploration and Production Forum (E&P Forum) is an international association of oil
companies and petroleum industry organisations formed in 1974. The Forum has presently 52 members from the oil
industry in 60 different countries. Shell participated in a task force set up by the E&P Forum to develop guidelines for the
development and application of Health, Safety and Environmental Management Systems. These were published in July
1994.
a reference of first resort for line managers and senior staff needing guidance in the essential HSE
requirements of any area of EP operations
The Safety Management System (SMS) approach was developed as a way of fully implementing the elements of
Enhanced Safety Management (ESM) in a structured manner, to ensure that the organisation, procedures and
practices are in place and can be shown to be working effectively. This methodology is based upon the principle
thatall hazards within the business must be understood and either eliminated or suitably controlled. This requires
an assessment of all the activities that the Opco is engaged in to determine the ones which have an HSE-critical
element. Understanding and control is achieved by applying the Hazards and Effects Management Process
(HEMP) in progressively more detail as more information becomes available.
EP BUSINESS MODEL
The EP Business Model (EPBM) describes all the activities, data and relationships within EP and has been
utilised as an aid for ensuring outline coverage of the HSE issues in each of the main business processes (see
Figure 2). The structure and layout within each document reflects the most practical way of presenting the HSE
issues in that process. The link to the Safety Case or HSE Case is provided in the hazards, effects and activity
matrices relating to the individual processes.
FIGURE 2 EP BUSINESS MODEL
E&P FORUM
The HSE MS for this Manual follows the structure of the E&P Forum Guidelines on HSE MS. The system is fully
compatible with the Shell Group Guidelines. The E&P Forum document is an industry document, known to
international contractors and operating companies in Exploration and Production. The standardisation in
terminology and approach introduces significant efficiency into the management of HSE.
CONTENTS
10
Contents
1
OVERVIEW
1.1
1.2
2.1
2.2
PARAMETERS
2.3
GUIDE WORDS
11
2.4
DEVIATIONS
12
2.5
CAUSES
13
2.6
CONSEQUENCES
14
2.7
ACTION RECOMMENDATIONS
16
2.8
2.9
17
20
21
21
21
23
19
25
3.1
3.2
COARSE HAZOP
27
27
27
3.2.3 RESULTS
27
MAIN HAZOP
28
28
31
3.3.3 RESULTS
31
FINAL HAZOP
32
32
3.3
3.4
25
11
32
3.4.3 RESULTS
32
3.5
33
3.6
EXISTING PLANT
34
34
3.7
4.1
4.2
4.3
36
4.1.1 MINUTING
39
41
COMPUTER TECHNOLOGY
45
45
45
47
4.3.1 INTRODUCTION
47
48
48
48
48
48
48
4.4
4.3.9 APPENDICES
48
FOLLOW-UP
50
4.4.1 IMPLEMENTATION/REJECTION
50
50
50
4.4.4 CONFIRMATION
50
4.5
4.6
ACTION RESPONSE
4.7
12
48
52
54
Contents
4.8
5.1
HAZOP LEADER
57
5.1.1 PREPARATION
57
57
58
58
5.2
SECRETARY
59
5.3
COMPETENCE
59
6.1
BATCH PROCESSES
63
6.2
65
6.3
PROCEDURES HAZOP
66
GLOSSARY
55
69
13
OVERVIEW
This manual is intended to provide an overall understanding of the HAZOP process and
its optimum application within a project. The document outlines a recommended
practice for undertaking studies which HAZOP leaders, secretaries and team members
will find a useful reference. It is also applicable to project managers, engineers and
anyone involved in the decision to hold a HAZOP or the planning, scheduling and followup of a study. In order to retain clarity and focus, some detailed information specific to
the leadership of studies is excluded here. It is contained in the P-282 Leading HAZOPs
training course manual.
1.1
Safety and its management is a primary issue for all plant, driven both by company
philosophy and external requirements. New technologies and the trend towards complex
integrated designs have identified the need for more searching and systematic methods
to identify and assess hazards.
HAZOP is a structured hazard identification tool using a multi-disciplined team. It has
become accepted as the main technique for the identification of process hazards in the
design and operation of a facility. Other identification techniques by discipline review or
compliance with checklists are limited by their reliance on previous experience and
constrained by their narrow approach. HAZOP is based on brainstorming and has
important advantages over other techniques for non-standard designs.
One formal definition would be 'The application of a formal systematic examination to
the process and engineering intentions of new or existing facilities to assess the
potential of maloperation or malfunction of individual items of equipment and their
consequential effects on the facility as a whole'.
The method is equally applicable to major green-field developments, brown-field projects,
small plant modifications or operating procedures. The concept is to break the plant into
small sections and then to identify hazards by examining each section and using a series
of parameter and guide word filters to structure the brainstorming process.
Team approach
The HAZOP team is multi-disciplined and the brainstorming procedure relies on the
broad experience of the team to identify potential hazards and operability problems.
Individual or discipline reviews are unlikely to be able to identify all the possible interdepartmental interfaces which are recognised as critical to the safety of complex plant.
The HAZOP technique's strength is that it allows personnel from all disciplines to
interact and question aspects of the facilities beyond their usual sphere of activity.
Method
The HAZOP process is the systematic application of combinations of parameters (flow,
pressure and temperature) and guide words (no, more, less) to produce deviations (no
14
1 Overview
flow, less pressure) from the design intent or intended operational mode of the plant.
Credible causes of deviations are identified for each plant section (called node). The
consequences arising are then discussed, assessed and minuted with actions or requests
for further consideration by the project team.
Results
There are two main deliverables from a HAZOP study. The first is a set of detailed
minutes, presented on worksheets for each node. These show the summary of the team's
discussions with action recommendations. The minutes should be a complete record of
the meeting including issues that have been discussed but have no action
recommendations.
The second deliverable is a detailed Leader's Report containing an appraisal of the
success of the meeting, and a summary of the main action points.
Strengths
HAZOP is the principal method for identifying hazards and operating problems. It is
applicable throughout a large project and is particularly effective at revealing hazards at
an early stage in the design process. The technique is often lengthy but it is cost
effective. If used early enough HAZOP may remove the need for expensive plant
alterations later in the design process or operating experience.
Brainstorming is an effective meeting technique. One of its strengths is that, when well
led, it breaks down rivalries and the static defence of a narrow view.
Weaknesses
An effective HAZOP study is dependent on the team's technical knowledge and
experience as well as the competence of the Leader. This major weakness is best
summed up in the phrase 'You do not know what you do not know'. The HAZOP team
cannot identify hazards or foresee causes that are outside their knowledge. This
limitation is an important factor to be considered in the selection of the team.
1.2
Step-by-step methodology
The HAZOP process is best understood if divided into the following steps:
apply the first/next guide word, which when combined with the parameter will
give the deviation
15
assess the protection provided against the causes and its consequences
apply the next parameter until they have all been considered
move onto the next node of the system until the whole study has been examined.
The HAZOP methodology is described schematically in Figure 1.1 and each aspect is
described in the following text.
FIGURE 1.1 THE HAZOP PROCESS
Nodes
The division of the plant into appropriately sized nodes containing process lines and/or
equipment is made by the Leader prior to the study. Conceptual HAZOPs will tend to
have larger nodes than detailed studies where more design information is available.
Parameters
The usual parameters applied to all nodes are flow, pressure and temperature.
Additional ones include level, phase, composition, operation, etc and may be applied
as required by the contents of each node.
Guide words
The usual guide words include no, more, and less but there are a number of others
commonly used. Not all guide words are applicable to each parameter. Figure 1.2 shows
the usually accepted combinations.
Deviations
The combination of parameters and guide words, in sequence, will identify all the
deviations (no flow, more temperature, etc). There may be significant overlap between
the deviations considered (no flow may have the same effect as more pressure). These
will be identified and excluded during the team discussion.
Causes
The team will brainstorm to find all the potential causes of the deviation. There is
frequently more than one cause, for example no flow would be caused by a blockage, but
there may be several different causes of that blockage. All potential causes should be
identified and discussed. If only the generic cause is covered, methods of prevention and
operational issues will be missed.
16
1 Overview
Consequences and protection
The potential consequences for each deviation are discussed and assessed within the
limits of the information available and the expertise of the team. There may be several
consequences involving escalation to other pieces of equipment. The protection against
each of the consequences is assessed to give the net overall effect. If the protection is
inadequate then recommendations are made to rectify the situation.
Likelihood
The team have to assess the likelihood of the net effect of the consequences and the
protection provided by the design and operating procedures. This is at best a semiquantitative exercise as the HAZOP study will not have any detailed quantitative risk
assessment (QRA) data. The normal procedure is to allocate a number of arbitrary
bands, relevant to the project from say once per year through to once in the lifetime of
the installation or once in the whole groups operating experience. The tolerability of
the risk may then be determined using a tool such as the risk matrix (see Figure 2.2).
Recommendations
The recommendations can take the form of closed or open actions. Closed actions
(instructions) will be made when the team agree the solution and it is within their level
of competency. Open actions, calling for further work outside the study, will be made for
those cases where the situation is complex and the solution is not obvious. Wherever
possible the number of open actions should be minimised but the Leader must balance
this with the requirement not to unduly lengthen the discussion of complex issues.
17
18
1 Overview
This page intentionally left blank
19
A HAZOP study progresses through the plant node by node. The selection of the node
sizes and the route through the plant is made before the study by the Leader. This
section describes how the HAZOP technique is applied within each node.
20
2.1
The Leader will select the nodes based on the stage of the project and the amount of
information available. The guidelines for the Leader to follow are based on changing
nodes at a major piece of equipment or where a critical parameter (flow, pressure,
temperature) changes. The objective being to focus on appropriately sized sections of the
plant for the team to be able to clearly identify all the design and operation issues. A
Conceptual HAZOP with little information will have larger nodes (including more
equipment) than a more detailed Main HAZOP.
The node intention defines how the process is expected to perform and it should be
recorded for all plant operating cases. It is important to give the full range of operating
and design conditions.
Before the study meeting, the process engineer should record the data on a node detail
form. During the study, he should give a brief description of the design intent at the
beginning of each node. This will be recorded in the minutes. Similarly the operator
should give a brief step by step description of start-up and shutdown actions before these
topics are addressed.
Operating Modes
All potential operating modes should be identified and included in the study. Each mode
may impose different maxima in the operating envelope and some nodes are used for
different purposes under the various operating modes for the plant. For example flow
rates and direction may change in wellhead lines during well kill or injection. Process
conditions may also change significantly during start-up or upset conditions, eg ESD and
blowdown. Maintenance isolation of individual trains or equipment sections may have
significant effects on other parts of the process by changing the flow rates or
temperatures/pressures/phases within the surrounding sections.
Life-cycle Issues
There are often substantial changes to well fluids throughout the life of a well as for
example the GOR changes and the water cut increases. Some equipment will only be
required for individual phases and temporary by-passes may be introduced.
2.2
PARAMETERS
Definition
There are seven specific parameters: Flow, Pressure, Temperature, Level, Phase,
Composition, and Operation, the first three of which are usually regarded as the
main parameters. Additional parameters may be selected for some of the nodes in a
study as appropriate.
Application
Not all parameters are applicable to each node. A parameter may only be left out if the
Leader thinks fit. He should tell the team why it is not relevant, eg level on a flowline.
Flow
Flow is usually applied as the first parameter as it is the easiest parameter to visualise
and for which to determine the effects of changes.
Pressure
Pressure is important because it leads to many of the most common hazards. Areas
causing common pressure related problems are:
HP/LP interfaces
isolation philosophy
vessel protection
Temperature
High and low temperatures may exceed the design parameters of the equipment or cause
hazards to the personnel. Phase changes may also occur due to freezing, boiling and
GOR changes. Low temperature may lead to waxing or hydration, causing blockages.
Level
Level is usually only relevant inside vessels where level control issues may arise,
including flooding or gas blowby. Sometimes there may be elevation issues (multideck
offshore platforms) where level is the most appropriate parameter. Many level hazards
overlap other deviations, eg 'more flow' gives 'more level'. In such cases level may be
easier for the team to visualise, and for vessels the Leader may decide to use level as the
first parameter, rather than flow.
Phase
Another 'minor' parameter which will often cover phase changes caused by the pressure/
temperature envelope. It is sometimes relevant for a plant where phase changes can be
caused by extreme operating conditions, eg solids, flashing or slugging in flowlines.
22
isolation philosophy
maintenance access
blowdown
noise.
2.3
GUIDE WORDS
Definition
Guide words are simple words or phrases used to qualify or quantify the intention and
associated parameters in order to suggest deviations.
Applicability
There are seven standard guide words; No, More, Less, As Well As, Part of, Reverse
and Other Than, but not all are applicable to each parameter, eg 'no' or 'part of' do not
apply to the parameter of temperature (see Figure 1.2).
Other Than is very popular as a 'catch all' guide word at the end of each parameter.
There is a significant amount of overlap in parameter guide-word combinations. If some
deviations appear to be already covered, eg 'more flow' may lead to 'more level', then
the decision to move on should be made specifically for each guide word and not by
assuming that a whole parameter is already covered. A minute saying 'see more flow'
should be added in the 'more level' section of the worksheet. Care is, however, required,
as it is possible to overlook possible hazards. For example, more flow resulting in
'more level may not cause additional level problems, but may result in velocity issues.
FIGURE 2.1 CONTINUOUS PLANT GUIDE WORDS
GUIDE WORD
MEANING
COMMENT
NO
MORE
Quantitative increase
LESS
Quantitative decrease
AS WELL AS
Qualitative increase
PART OF
Qualitative decrease
REVERSE
OTHER THAN
24
2.4
DEVIATIONS
Definition
Deviations are the key to the HAZOP process. They are departures from the design
intent of the process and are identified by the systematic application of the appropriate
parameter/guide word combinations (See Figure 1.2).
In some cases the parameter and guide word when combined make a well understood
deviation, eg less flow. In other cases explanations may need to be developed for the
deviation, eg as well as flow may more easily be described as 'additional component,
and part of flow arises when an element of the flow composition is missing.
2.5
CAUSES
There may be many causes identified for each deviation, and all potential causes should
be discussed, as the consequences and recommendations for action may be different. It is
not sufficient to refer to generic causes, eg blockage, since the method of prevention and
operational issues cannot be adequately defined.
Credible causes
Causes have to be credible, eg impact damage from the explosion of the neighbouring
vessel is only possible if the vessel contains flammable material or is at great pressure.
If incredible or highly unlikely causes are considered by the team this might lead to
expensive and unnecessary modifications to the plant.
The three major categories of causes in decreasing probability are:
human error
equipment failure
external events.
26
2.6
CONSEQUENCES
Having identified the credible causes of the deviation, discussion should move on to
analyse and assess the significance of the consequences. The role of HAZOP is to
determine the net effect of the potential consequences and the mitigating effect of all the
protective measures.
Protective Measures
Most hazards will be protected against by a combination of hardware, instrumentation
and operating practices. Protection may be provided by a combination of the following:
human failure
Operators may fail to prevent a hazard by inappropriate response to an alarm due
to wrong procedure/instruction, inadequate time, or inadequate data for the
diagnosis of the problem. The manning philosophy and associated reaction time
should always be analysed when hazards are mitigated by alarm and operator
intervention. Operator action should normally follow the activation of a pre-alarm,
giving time to intervene before major executive action by the control system is
required.
Hardware failures
Hardware failures can be of two types:
patent failure
A patent failure is one where the failure is immediately apparent (self-revealing),
eg a normally open control valve fails shut and the process flow stops. These types
of failure are normally easily identified as causes of deviations.
latent failure
28
2.7
ACTION RECOMMENDATIONS
Scope
The purpose of the HAZOP meeting is to discover potential hazards of the process and
its operation. It is generally not within its scope to try to solve the sometimes complex
problems and stipulate detailed actions. A prescriptive action recommendation may be
counter-productive in that it may inhibit the engineer from considering an alternative,
and perhaps better, solution.
Closed (simple) actions
It is preferable for the team to agree and recommend simple actions, which can be
defined as closed, because they do not ask the responding engineer to consider options.
The team should be of sufficient experience and seniority in order to make design
decisions for the project. A HAZOP which produces too many inconclusive
recommendations in the 'study', 'consider' or 'investigate' categories is unlikely to be
effective. Furthermore their subsequent outcome is unknown to the HAZOP team and
may not address the root of problems. The team should therefore be able to take
decisions whilst not spending undue time developing solutions to complex problems.
Open (complex) actions
If the team are divided in view, or if there is not enough time available to complete the
discussion, an open action (recommendation for further work) may be appropriate. It is
most important that the team's concern is clearly established in the worksheet so that
the responding engineer knows the scope of study required and the objective he is trying
to achieve. It is often helpful to offer a preferred solution whilst giving the responding
engineer scope to suggest alternatives.
Conditional recommendations
The team will occasionally propose changes to one node that are conditional on the
acceptance of recommendations made on another node considered earlier. These will be
invalidated if the earlier recommendations are rejected by the project manager and
hence the link between the two recommendations must be explicit in the minutes. It is
often difficult to write a complete (stand-alone) minute in such cases which gives the full
background such that the combined action is clear. Hence the use of conditional
recommendations should be minimised as there is a real danger that, in the course of
HAZOP follow-up, the teams primary concern may be lost.
2.8
30
2.9
It is important for each team member to follow the study on their own drawings. In
addition, a master set of full-size drawings should be displayed on the wall and markedup to show progress through the study.
Highlighting and colour coding to identify nodes and record progress
A system of highlight colours should be used to ensure that the limits of the node are
fully understood by the team and that at the end of the study the coverage (covered,
excluded, duplicate section) is clear.
Highlighting techniques are often particular to a Leader, but all are based on
demonstrating the extent of the node as it is studied, and marking the progress. Lines
and equipment not covered by the study because they are duplicates should be
highlighted using an individual colour or technique, eg dashed lines. Lines outside the
scope of the study on revamp or minor changes HAZOPs should also be identified by a
unique colour.
The master drawings should be archived with the study. To make subsequent review of
the HAZOP easier a drawing with the individual nodes highlighted in different colours
should be made.
32
Process Engineer
The role of the process engineer is to provide expertise on the process design and
intended operation of the plant. It is important that the individual has a full
knowledge of the design history of the part of the plant being studied as well as a
deep overall understanding of the whole plant. For large projects it may be
advisable to include the process discipline supervisor who has knowledge of the
whole plant, supported by the appropriate package lead engineers who may have
more detailed knowledge of the area under study for each session.
Project Engineer
The project engineer's role is to ensure that the objectives of the project are
recognised throughout the study. These may include commercial as well as
technical constraints on the plant.
34
Part-time members
It is inefficient to have a big team containing people waiting for a specific node.
Specialist engineering disciplines may be called upon to attend specific sessions as
required.
Safety Engineer
For many studies the safety engineer is included in the core team. If the project or
process engineer is responsible for undertaking the QRA studies and assessing the
overall level of process risk, then part-time involvement of the safety engineer is
adequate.
He may provide the expertise to the team on consequence assessment (flame
length, etc) and on historical failure probabilities.
machinery specialists
Machinery and packaged equipment issues rarely extend far beyond the machine
itself, hence the machinery engineer is only required whilst the individual
equipment issues are discussed.
Vendor's representatives
Once vendor designs are available it is advisable that a vendor representative is
present whilst the package is studied. The level of representation will depend on
the size and complexity of the package. It is often advisable to hold Mini-HAZOPs
of complex packages during the vendor's design rather than wait to review a
completed design.
Civil/Structural Engineers
In most HAZOP studies the requirement for civil engineers is limited and it is
usual for them to be called upon when only required or for specific sections of the
plant, eg drainage routing.
36
38
3.1
HAZOP studies are an integral part of the project activity. Planned HAZOP studies
should be included in the Project Schedule on the critical path, with the timing
determined by the availability of the main drawings of the correct quality. It is the
responsibility of the project manager to determine whether HAZOPs are needed, when
they are required, and which type of study is appropriate. He also has to plan the
resources required, duration and information needs. Figure 3.1 shows the general
sequence of HAZOP studies through a project. The applicability of these studies is
dependent on the type of project under consideration.
FIGURE 3.1 SEQUENCE OF HAZOP STUDIES THROUGH A PROJECT
For a large project a sequence of HAZOP studies should be planned, varying in scope
from conceptual to detailed. The conceptual studies look at the plant in less detail but at
a time when the cost and schedule impact of major changes is minimised.
HSE-HAZID
This is a hazards and effects identification technique using similar analysis and
brainstorming techniques to HAZOP, but designed to be used at a much earlier
stage in the project. Described in EP 95-0312, HSE-HAZID concentrates on wider
health, safety and environmental issues with less of a process focus. HSE-HAZID is
included here because it is complementary to Coarse HAZOP and in certain
circumstances the two study types can be combined.
Coarse HAZOP
This uses the full HAZOP methodology but is intended to be used early in a
project's life where there is still the 'ability to change the design, operating and
maintenance policy'. The plant is divided into a small number of large nodes
appropriate for an early stage in the design development.
Main HAZOP
This study should be held at the end of the project specification phase (front end
engineering phase) of a project. Its objective is the assurance of the safety of the
current design ('Will it Work?') rather than making radical recommendations for
change.
Final HAZOP
This study is held at the end of the detailed design stage when drawings are ready
to Approve for Construction. The technique is the same as the Main HAZOP except
that the study focuses on changes since the Main HAZOP, rather than reviewing
the agreed design.
3.2
COARSE HAZOP
This study has the objective of making the plant inherently safe before many detailed
engineering decisions have been made. It may be of particular use prior to the letting of
a design contract to ensure that the consultant/contractor is provided with a sound
design.
plot layout
safety philosophy
All drawings should be supplied with full legends for symbols and guides to the meaning
of line numbering, etc.
3.2.3 RESULTS
This project stage is the most appropriate time to call for detailed QRA studies or other
supporting investigations. Qualitative Risk Analysis is helpful in identifying the issues
giving major concern.
3.3
MAIN HAZOP
This is the primary HAZOP study for any project using the full technique and
addressing all the details of the plant.
The objective is to look in detail at all aspects of the design, and the main HAZOP will
be the most comprehensive HAZOP study within the project.
Table 3.1
Meeting details
Team member details
Proposed node list
Drawings to be studied
Lists of the guide words and other HAZOP technique notes which
will be of use to team members who are less familiar with the
study method
Copies of documents produced by software If computerised minutes are to be taken it is useful if the team are
aids
able to see the format of the worksheets that will be produced
Commonly the computer display ,which may be projected for the
team to see, will only show part of the worksheet
Project description document
Optional - if available
This is an advance version of the presentation to be given at the
beginning of the meeting by the Process Engineer
Where applicable
If the HAZOP is part of a series of meetings on the same project it
is sometimes appropriate to discuss previous action points that
have not been understood or actioned.
the mass balance (separate document required if not shown on the PFS)
Plot Plans
These are essential for considering escape routes and interaction between
equipment items. A single large copy for general reference is usually sufficient.
legend details
The explanation of piping, mechanical and instrument symbols is important, as
there are many different standards, and client, contractor and vendors may use
different notation.
Explanation of line numbering with particular reference to process fluid content,
pressure class, material specification and insulation details is also required.
others
If there is a significant risk to third parties from fire and explosion or pollution
then other information may be required such as:
Philosophies
Operating Philosophy
The basis of operation of the facilities needs to be clearly stated, especially where
there are multiple operating modes.
Safety Philosophy
The basis of protection of life, the installation and the environment following a
hazardous event should be available to the team.
Evacuation Philosophy
This is required for offshore installations. Personnel escape routes should be shown.
If there is a significant third-party risk, accommodation and local population
densities may also be appropriate.
Other documents
minutes
The minutes of any previous HAZOP studies should be available. This helps to
minimise duplication of studies.
action lists
Action lists from any previous HAZOP studies should be available, with an
indication of the current status of each of the actions.
3.3.3 RESULTS
The detailed report of the study should catalogue all the hazards identified and all areas
where there was insufficient information or gaps in the knowledge of the team. It should
be remembered that the Main HAZOP is usually too late to start challenging basic
concepts in the design of the plant.
3.4
FINAL HAZOP
The final study is required to look at changes made to the Approved For Design (AFD)
drawings resulting from the contractor's detailed design effort and the availability of
vendor's information. The technique is the same as the Main study but the team is
limited to looking at changes rather than reviewing the agreed design.
3.4.3 RESULTS
At the end of this meeting the design should be frozen and the HAZOP exercise
complete. The AFC drawings should be frozen once the recommendations of this study
have been reviewed and incorporated.
3.5
It is necessary to carry out formally HAZOP studies for minor changes to the drawings
following the Main HAZOP. Such a meeting would not require the full team used for the
Main HAZOP but just the core members involved in that area of the plant.
Minor Plant changes
A safety statement should be issued on each change to confirm that it does not affect the
safety of the main plant. Several minor changes can be studied together once the net
effect is seen to have a significant effect on the design or operation of the plant. Figure
3.2 shows a format for a change matrix which should be adopted to determine if a
HAZOP is required.
FIGURE 3.2 CHANGE MATRIX
3.6
EXISTING PLANT
node selection
The selection of the nodes for a modification HAZOP should reflect the interfaces
with, and allow analysis of, the effects on the surrounding systems.
Sufficient design and operating information must be available for all common
systems (vents, drains, etc) as well as the existing plant local to the tie-in points
liable to be affected by the new development.
3.7
There is a relationship between a HAZOP study (or any other HEMP study) and an HSE
Case. This is best considered separately for existing facilities and new developments.
New developments
An HSE Case is likely to be planned for any significant new development. As a means of
commencing the process of compiling the HSE Case, but particularly part 5 - the Hazard
Register - an HSE-HAZID study may have been performed. Alternatively during the
initial design phase a separate study or process may have been put in place specifically
to collect information for the Hazard Register.
This information may thus be available to the HAZOP team as part of the information
pack, ie as an inventory of the HSE hazards pertinent to the development. It should be
noted however that the Hazard Register may not at this stage have identified all the
hazards inherent in the design, nor assessed hazards in any significant depth.
There are no specific guidelines on the process of documenting the HSE Case as a
project design matures, however it is most likely that the HSE Case will evolve either
progressively or step-wise throughout the engineering phase, and be published around
the time of plant start-up. The HSE Case (Hazard Register) may then contain reference
to HAZOP study findings, and/or transcribe/summarise from the HAZOP report
information on the safety critical equipment, systems and procedures, in order to
comprehensively demonstrate management of hazards. It may include such items as the
sequential analysis and protection measures discussed in the HAZOP report for a
particular deviation from design intent, ie where the consequence of that deviation
presents significant risk. The HAZOP study therefore performs the function of one of the
information sources to complete the HSE Case.
Existing Facilities
For existing facilities the compilation of a HSE Case may indeed be the cause of the
HAZOP study, ie as a means to demonstrate adequate assessment of the hazards
inherent to the process. In such situations the HSE Case will also refer to or transcribe
information from the HAZOP report. Even if this is not the case, the relationship
between HSE Case and HAZOP report is similar.
Modification Projects
Where a plant is undergoing modification or revamp, the HAZOP study should draw on
the HSE Case as part of the information pack, and similarly on completion of the study
the results of the HAZOP should be incorporated into the HSE Case.
Figure 3.3
Predicting the time required for a HAZOP study depends to a large extent on the particular circumstances of the study. This
calculation method will give a first approximation suitable for schedule planning and budgeting purposes.
Total Time Required = Preparation + Study + Report (Tp + Ts + Tr)
Factors affecting time estimation = Size of the team, Leader's experience, No of nodes
Size of the Team (Factor S) - The size of the team is usually a factor of the complexity of the study but also includes the
involvement of engineering contractors, subcontractors and vendors.
A major green/brown-field
team>12
development with contractor/vendor
involvement
S = 1.25
S=1
S = 0.75
team < 5
Inexperienced
equivalent studies)
(lead 0 to 2
L=2
Average
equivalent studies)
(lead 2 to 5
L=1
Experienced
than 5 equivalent studies)
(lead more
L = 0.75
Number of Nodes (Factor N) - Experience has shown that the number of nodes is often difficult to predict. The best approximation
comes from assessing the number of engineering packages being studied. For complex packages Pc (process trains, packaged
equipment, major utility systems) an average number of nodes per system is 8. For simple packages Ps (minor utilities, distributed
injection systems, etc) an average number is 3.
N = Pc*8 + Ps*3
Total Study Time (Ts) - The average time per node over a large study has been found to be 1.5 hours. The first node always takes
much longer (four times as long), as a number of general issues are discussed and the team has to become established. Apart
from the smallest studies it is also normal to allow 3 hours at the beginning of the meeting for the project and the HAZOP
procedure to be introduced.
Ts = 3 +(N+3)*1.5*S*L
Preparation Time (Tp) - The preparation time for the Leader is estimated as a base load of 20 hours with an additional load based
on the number of systems.
Tp = 20+ Pc*2 + Ps*1
Report Time (Tr) - The report preparation time for the Leader and the Secretary is also estimated as a base load (15 hours) and
as a function of the number of systems in the study.
Tr = 15+ Pc*2 + Ps*1
Throughout the study, the Leader and Secretary will spend 33% more time than the team in reviewing the team's comments on the
draft minutes and updating the worksheets to formal issue status. For example, if the team meet for 6 hours a day, the Leader and
Secretary will work for 8 hours in order to maintain progress issuing agreed/approved minutes throughout the study. If the minutes
are not issued for review by the team at the end of each day but produced as a batch at the end of the study, this time, Ts*0.33 will
have to be added to the report preparation time.
4.1
4.1.1 MINUTING
Roles and responsibilities
It is the Secretary's role to record the minutes of the HAZOP study meetings. The
Leader may provide support and guidance to ensure that full concise minutes are
produced. The main requirement is that someone not at the meeting should be able to
read the minutes and fully understand all the potential hazards discussed by the team
(including those where the protection is adequate) and especially the concerns and
recommendations of the team. During the study, each member of the team should review
the draft minutes to ensure that they are an accurate record of their comments; however,
responsibility for the accuracy of the minutes lies ultimately with the study leader.
Worksheet
The structure of the worksheet follows the sequence of the HAZOP brainstorming and
analysis technique. Each of the technique stages is recorded in columns of the
worksheet. The deviation is described, causes are identified by brainstorming, and
then the consequences and protection are assessed, leading to recommendations for
action. A typical worksheet is shown in Figure 4.1. The final columns show who will
respond to the action, the priority and the number of each action point.
Responding individuals
Allocation of action points to individuals or departments for resolution is usually left to
the project team after the meeting but may be allocated by the team during the study as
follows:
companies
The widest allocation of responsibilities is to companies, eg contractor, client,
construction subcontractor, etc.
departments
The most usual method is for action points to be allocated to departments within
the design engineering company or Opco.
individuals
It is unusual to give ownership of the action points to specific individuals. They will
usually be selected by the project manager after the meeting.
Priority
The priority of any action is usually allocated between 1 = major, 2 = important and 3 =
minor. This is a qualitative judgement based on the importance of any issue as
recognised by the team or the urgency of the action response.
serious risks
decisions that affect the design of the whole plant and may have a general
application should be minuted as general issues.
DEVIATION
Flow
The team are discussing the parameter Flow and the deviation No Flow.
Intention
The first item to be established is the intention of the parameter as it applies to the
node. This should be minuted during the initial discussions describing the node. If
relevant the following information should be included:
PARAMETER
FLOW
INTENTION
Tank 29-TA-301 is used as a hold-up facility for off-spec condensate and also as
a receptacle for hydrocarbon liquids collected in the knock-out pots and
maintenance flare.
Causes
All the potential causes of the deviation should be identified by the team brainstorming.
The Secretary will record each separate cause as it is identified by creating new rows on
the worksheet. Typically, causes will fall into one of three categories:
human error
equipment failure
external events.
CAUSES
High level trip in tank 29-TA-301 shutting inlet due
to excessive off spec production or operator failure to
drain tank and recycle liquid.
In this example the cause is a possible combination of a primary human error (failed to
regularly recycle the off-spec hydrocarbon) or an equipment error (excessive production
of off-spec hydrocarbon).
Consequences
The consequences should be defined in terms of the potential hazards and operability
problems. If appropriate a chronological sequence of events following the initial cause
should be recorded.
CONSEQUENCES
Possibly unable to blowdown
plant as liquids cannot be
removed from flare knock-out
drum via route to 29-TA-301.
The consequences can be inside the node or, as in this case, elsewhere in the plant. A full
off-spec storage tank closes the route from the knock-out drum, giving a potential
problem during blowdown.
Protection
The protection column should describe the team's evaluation of the hazard or operability
problem presented by the consequences. It typically describes the protection that is
already in place. Typical existing protective measures may include:
By
It is usual to allocate the actions either to individuals or departments. It is easier to
record the minutes using an initial type system, eg PE for Process Engineering.
Priority (P)
It is possible to set priorities on each of the recommendations. This can be done based on
the severity of the consequences and the potential likelihood of the occurrence (see 2.8).
BY
No:
PE
Number (No:)
It is essential to provide a unique number for each recommendation to allow adequate
Quality Assurance measures to be applied to the action responses.
Response
The response to HAZOP action recommendations is discussed in 4.6. Figure 4.3 shows
the response to this example minute.
4.2
COMPUTER TECHNOLOGY
HAZOP preparation
The software is able to create the session details and node lists and then include
the node details and process parameters for each node.
minute-taking
The main scope of the packages is to provide a clear method of recording the
minutes of the meeting. If the Secretary is unfamiliar with the commercial
packages, or finds them difficult to use, then a simple word-processing application
may be preferable.
4.3
The HAZOP report is an important document describing the objectives and success of
the whole study. The report should form the basis of a reviewer's understanding of the
completeness of the study and the confidence that can be put in the results.
HAZOP meetings can be very long and complex. Important issues can be lost in a
formidable pile of worksheets and the report serves to highlight the important issues
that need to be addressed quickly.
The draft final report should be reviewed by team members prior to formal, timely issue.
The HAZOP report should contain the following sections:
introduction
4.3.1 INTRODUCTION
The introduction to the HAZOP report should contain short descriptions of the following:
background
The background to the project and the scope of the HAZOP.
purpose
The purpose and achievements of the meeting should be described.
terms of reference
The terms of reference given prior to the HAZOP and other safety studies or
HAZOP minutes used for reference.
team composition
The composition and affiliation of the team including the attendance of part-time
members at each session.
study method
4.3.9 APPENDICES
The appendices should contain the following information:
node list
worksheets
4.4
FOLLOW-UP
4.4.1 IMPLEMENTATION/REJECTION
Follow-up is the responsibility of the project manager. Compliance with HAZOP
recommendations is not mandatory but an auditable, fully documented record of all
actions taken, decisions and alternative solutions is required.
As follow-up may continue quite some time after the study, and may also involve parties
not involved in the study, it is imperative that the minutes adequately describe issues.
installed.
Use of the word installed is an example of a lack of reference point being given. A
drawing reference and revision number or a drawing change notice, etc are required.
Passing the recommendation forward, eg 'will be included in detail design', is also not
acceptable as it does not close the action and hence is not auditable.
Poor minutes can also compound this problem, eg 'check size of relief valve' can instigate
the response 'checked' or 'being checked' where it is not clear what the outcome was. The
minute should read 'confirm the size of the relief valve (RV-123) for the maximum
operating case of 10,000 bbl/day' and the response 'relief valve RV-123 confirmed for
maximum flow rate as quoted'.
4.4.4 CONFIRMATION
It is important to get formal acceptance of the response from the responsible parties. In
the case of a design contractor on a major project it is usual for a number of specified
signatures to be required.
4.5
In the past, HAZOP action points have often been regarded as an increase in scope for
vendor or contractor. This is obviously unsatisfactory. From the point of view of the
project, compliance with agreed HAZOP recommendations should be included in the
vendors original scope of supply. From the point of view of the HAZOP, contractual
issues should not be allowed to interfere with the development of recommendations.
4.6
ACTION RESPONSE
4.7
All HAZOP and response documentation should give a full audit trail from the meeting
through to the implementation or rejection of the action points.
An internal project verification system should be developed to confirm the quality of the
HAZOP process and periodically audit the HAZOP follow up. This should form the basis
of an audit/review either as part of an HSE audit or as part of the normal project quality
verification. The review of the process should typically address the following points:
are the actions consistent with the intent of the original basis for design, and
operating and maintenance philosophies?
have the project change control procedures been applied to the actions?
have full or partial HAZOPs been performed on significant changes resulting from
the main HAZOP?
4.8
A formal system of review and authorisation should be instigated for the close-out of
HAZOP action recommendations. As well as the engineer who prepared the response
(HAZOP action party), this may include elements of the following hierarchy:
The HAZOP Action Party Supervisor
He is required to sign to indicate that the normal departmental quality assurance has
been achieved.
The Project Manager
He is required to approve the action taken, to provide the funds if necessary and to
confirm that it has been (rather than will be) implemented on the project.
Implementation usually means inclusion on the relevant master drawings rather than
actually built and installed. For a HAZOP action on an existing plant, implementation
should mean actually built and installed.
Asset Holder
For modifications to existing plant, the approval of the asset holder may be required.
Client Representative (if appropriate)
For a HAZOP with design contractor (or vendor) and client involvement, the client
representative should also agree that the response is acceptable. This may involve
approval to release funds for additional scope. The Client HAZOP Co-ordinator may also
act as the focal point to ensure co-ordination between all the parties involved in the
close-out of the action.
HAZOP Leader
An approval is required to show that the action taken actually does address the
intention of the action point and deals with the concern of the team. Ideally this will
come from the HAZOP Leader, but in some cases this may not be possible. In these cases
the Project Manager should liaise with the HAZOP team to ensure the issues have been
addressed.
5.1
HAZOP LEADER
The role of the HAZOP Leader can be broken down into the following sections:
preparation
approval of actions.
5.1.1 PREPARATION
The HAZOP Leader's responsibility for the study starts significantly before the meetings
occur. For a large study, the preparation usually starts approximately one month before
the study. The aim of the Leader's preparation work is to ensure that the team has
access to all the information required and to make sure that the study is conducted in
appropriate detail. The objectives are to:
establish the scope/definition of the HAZOP study with the project manager
ensure all the relevant drawings and background documents are available
ensure all the relevant documentation has been made available to the team in a
pre-reading information pack
plan the individual sessions and the overall timing of the study
the position and importance of the study within the overall project
each of the team members has made appropriate contribution to the study
if necessary, the number of operating cases and life-cycle issues to be discussed has
been identified at the start of the meeting and the method of handling agreed.
responsible for the construction, operation and abandonment of the plant. The
information will subsequently be incorporated in the HSE Case for the facility.
Therefore, HAZOP findings which are considered to be in this category shall be recorded
in the Hazards Register which will be referred to in the preparation of the HSE Case.
The Project Manager will state in the Action Response Form whether the finding will be
incorporated in the Hazards Register.
5.2
SECRETARY
The major role for the Secretary is to record the minutes of the meetings on the
worksheet. This requires significant skill and engineering knowledge because the
important points for the minutes need to be distilled from the wide-ranging discussion.
The record of each point must be complete and unambiguous and the action point, if
there is one, clear. Use of purpose-developed word-processing software and overhead
screen projection has eased the secretarial task in recent years. The Secretary should
give careful consideration to the following:
timing
The minutes for that day should be issued by the Secretary at the end of the day or
at the start of the next to allow the team to make any comments whilst the
arguments are fresh in their minds. By this means, effective and essential approval
of the minutes by the team is achievable.
quality
Minutes must provide a complete record of points discussed (not just a record of the
recommendations). The minutes should be of sufficient quality to provide
unambiguous information and recommendations on identified hazards, their effects
and management within the project. If something is discussed and found not to be a
concern, but is not minuted, there is no way of later knowing if the point was
missed or discussed and rejected, and if so, why.
5.3
COMPETENCE
HAZOP Leader
The role of HAZOP Leader is a complex one combining technical knowledge and
experience with man-management skills. In order to ensure that HAZOP Leaders are
competent and efficient the following selection criteria should be adopted:
experience
training
A Leader should have had adequate training in both the HAZOP and management
techniques. This should have been gained on a recognised HAZOP leadership
course. Formal training should also be supplemented by on-the-job coaching under
the supervision of a competent Leader. This may not be practicable for external
HAZOP consultants, in which case previous experience should be reviewed and
their performance observed by company mentors.
In order to assess the competence of a HAZOP Leader consideration should be given to:
HAZOP skills
These include correct application of the parameter and guide word combinations;
acting as a facilitator for the team; checking that complex problems are fully
understood by all members; ensuring full use is made of all the expertise and
knowledge within the team; getting the appropriate person to give details and then
summarising for the others.
communications/motivation skills
The Leader must be able to keep the team working together and motivate all
members of the team. The Leader should form a good working relationship with the
Secretary and supervise the Secretary's work to ensure that adequate minutes are
recorded. The Leader should also be able to produce a full Leader's report.
The competence of potential HAZOP Leaders should be judged using the criteria
described above. A scheme should also be developed for formal training, on-the-job
coaching, registering and monitoring the competencies of Leaders. The register of
competent HAZOP Leaders and secretaries should be established and maintained
within the Opco.
Appropriate selection for each study
The competency management system will include the level of expertise for each Leader.
This will vary from being approved to lead small studies within the local Opco to being
nominated as suitable to lead major studies for any Opcos. External consultants should
also be registered using a similar classification. The project manager is responsible for
specifying the level of independence required for the Leader, which will depend on the
size and importance of the project. In all cases the Leader should be selected from
outside the project team and, in a project involving a design contractor, from outside the
contractor's team.
The selection of a Leader for a given HAZOP should be based on:
SIPM specialist
HAZOP Secretary
HAZOP secretaries should have training and experience similar to that required by the
Leader. The Secretary should also be able to take minutes in a concise, accurate manner
using plain language.
6.1
BATCH PROCESSES
The HAZOP method for batch processes deals with each part of the plant in exactly the
same manner as the more familiar method for continuous processes. Differences occur
when the team examines the changes in plant configuration as the steps in the batch
process are progressed.
Preparation
The preparation for the meeting involves considerably more effort than for a continuous
process. The status of the system changes frequently and in order to perform an
adequate study, the valve positions and process conditions must be adequately described
for each separate stage. As these are normally cyclical operations, a simple line diagram
alone gives a very incomplete picture and it may be necessary to prepare diagrams
showing the status of each line and vessel throughout the process. Operating
instructions, including logic diagrams or instrument sequence diagrams, are essential in
understanding the steps. For operator actions or procedures where they are physically
involved in the process (eg in charging vessels), rather than simply controlling the
process, their activities should be represented by means of process flow charts.
Timing
This is a variance on the meeting style only and should be undertaken at the same time
as the normal HAZOP studies of the plant.
Scope and purpose
As for Main HAZOP with the following additions: the processes are usually multi-stage;
the individual units multi-purpose; and the plant as a whole multi-product. Therefore
there is likely to be a large number of possible interconnections between units. The
operators may take part physically in some of the process activities such as removing
product from filters.
Documentation
As for a main HAZOP but including operations, valve configurations, and control issues
for the batch processes. Operating instructions are vital. Tables are required giving the
operation sequence, with charts showing the states of equipment during the cycle and
flow charts showing the operator's movements.
Sequence diagrams (batch processes)
For batch processes or where some complex procedures are being examined, it may be
appropriate for several copies of some PEFSs to be available. These should be marked up
to show the configuration of the valving, etc during the phases of a batch process or the
stages of the process.
Techniques
Time-dependent concepts (sooner/later) are added to the guide words. The method is
the same as normal but examines the changes in plant configuration as the steps in the
batch process are progressed.
Other additional general parameters which may be used include:
addition
maintenance
instrumentation
reaction
testing
sampling
service.
Team
As for Main HAZOP but with increased operator involvement.
Results
As for Main HAZOP.
FIGURE 6.1 BATCH PLANT GUIDE WORDS
GUIDE WORD
MEANING
EXAMPLE
NO
MORE
LEES
AS WELL AS
PART OF
Missing component
REVERSE
SOONER/LATER THAN
OTHER THAN
6.2
Definition
The activity HAZOP technique consists of the systematic critical search for deviations
and hazards applied to activities and the facilities involved in operations. The technique
examines sequences of mechanical and manual handling operations.
Timing
This is a type of meeting that can be held at any time in the project, the level of detail
and meeting technique being dependent on the timing selected.
Scope and purpose
Most EP facilities are continuous processes with relatively little operator control.
Activity-based studies may however be required for the small number of potentially
difficult activities that are not continuous, and do not form a part of the daily operations
workload. Such activities may be:
drilling
unloading at a jetty
well workover
shutdown.
Documentation
Drawings of the same quality as the Coarse or Main HAZOP are required, including,
where appropriate, PEFS and Cause and Effect diagrams. Descriptions of the
mechanical actions and operator activities for each phase of the operation will also be
needed.
Technique
The basic technique is the same as for other HAZOPs. Specific activity guide words, etc
are used. These include incorrect activity and the time/movement elements of movement
and early/late operation. Additional parameters included are: time, decision and
position.
Team
The core team is essentially the same as for normal HAZOP, although the Project,
Process and Instrument engineers may not be required full time and more operating
specialists are required.
Results
The recommendations from an activity HAZOP are not necessarily limited to the
operating procedures. Changes both to the design of the equipment and the operating
procedures may be suggested.
6.3
PROCEDURES HAZOP
Definition
The inclusion of procedures into a HAZOP study can be done either implicitly or
explicitly. During a normal study, procedures are considered implicitly as causes of
deviations along with other physical causes. Certain procedures can also be considered
as part of the protection (allowing for human error). This inclusion of procedures in a
normal study is not exhaustive and may lead to potential hazards and operability
problems being overlooked. Safety-critical procedures should be explicitly studied as a
primary document, with guide words applied directly to the steps in the procedure.
Timing
Procedures are unlikely to be available in sufficient detail until the Main or even Final
HAZOP. Procedures HAZOPs may be particularly beneficial for an existing (older) plant.
Scope and purpose
Procedures HAZOP meetings may include any operating procedure written for a plant
and may be conducted in addition to the normal HAZOP for that equipment item or
dealt with separately. They are usually conducted however on the activities such as:
commissioning
pigging
inspections
start-up
maintenance
plant testing
The standard guide words of No, More, Less, As Well As, Part of, Reverse and Other
Than take slightly different meanings. These are described in Figure 6.2.
Team
The core team is essentially the same as for normal HAZOP but all the operating
specialists are required.
Results
The results will specifically affect the operating procedures and in some cases may have
an impact on the design of the equipment.
MEANING
The step in the procedure is not done
MORE
LESS
AS WELL AS
Other activities are carried out as well (eg several valves are opened
instead of one)
PART OF
The procedure is not fully performed (eg only single block is used
instead of double block)
REVERSE
OTHER THAN
Procedures have a time element which is not explicit when considering continuous
operations. It may be necessary to increase the parameters and guide words that are
used to ensure that full consideration is given to the procedures under study (Figure
6.3).
FIGURE 6.3 ADDITIONAL PROCEDURES GUIDE WORDS
GUIDE WORD
MEANING
HOW
WHY
WHEN
WHO
CHECK
GLOSSARY
A glossary of commonly used terms in HSE is given in both EP 95-0100 HSE
Management Systems and EP 95-0300 Overview Hazards and Effects Management
Process.