Sei sulla pagina 1di 2

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST

SAIC NUMBER

Exhaust Fan Receiving, Handling and Preservation

SAIC K-4001

PROJECT TITLE

WBS / BI / JO NUMBER

EQUIPMENT ID NUMBER(S)

EQUIPMENT DESCRIPTION

LAYOUT DRAWING NUMBER

REV. NO.

SCHEDULED INSPECTION DATE & TIME

ACTUAL INSPECTION DATE & TIME

HVAC

CONTRACTOR / SUBCONTRACTOR

SYSTEM ID.

PURCHASE ORDER NUMBER

PLANT NO.

EC / PMCC / MCC NO.


QUANTITY INSP.

MH's SPENT

TRAVEL TIME

SAUDI ARAMCO USE ONLY

SAUDI ARAMCO ACTIVITY NUMBER

SAUDI ARAMCO INSPECTION LEVEL

CONTRACTOR INSPECTION LEVEL

ACCEPTANCE CRITERIA

REFERENCE

Receiving

A1

Fans shall be air-foiled, backward-inclined, backward curved, or forwardcurved.*

SAES-K-001
Para 4.8.9.1

A2

Fans shall meet the requirements of AMCA 210 "Laboratory of testing


fans for aerodynamic performance rating".
Note: Certification by the manufacturer is required upon Saudi Aramco
request

SAES-K-001
Para 4.8.9.1

A3

Fans shall conform to AMCA 99 "Standards Handbook"


Note: Certification by the manufacturer is required upon Saudi Aramco
request

SAES-K-001
Para 4.8.9.1

A4

Variable speed fan shall be provided in variable air volume (VAV)


systems.

SAES-K-001
Para 4.8.9.1

A5

Parts of fans in contact with explosive or flammable vapors, fumes or


dusts shall be of nonferrous or nonsparking materials or their casing
shall be lined or constructed of such material. (UMC Para 503.2)*

SAES-K-100
Section 1

A6

Equipment (Fans) used to exhaust explosive or flammable vapors, fume


or dusts shall bear identification plate stating the ventilation rate for
which the system was designed for. (UMC 503.2.1)

SAES-K-100
Section 1

A7

Fans located in systems conveying Corrosive shall be of material that


are resistant to the Corrosive or shall be coated with corrosion resistant
material. (UMC 503.2.2)

SAES-K-100
Section 1

A8

An identification tag or name plate made of 316 stainless steel or better,


shall be attached to each equipment unit, securely with stainless steel or
Monel fasteners.

SAES-K-001
Para 4.8.1.2.1

A9

The tag or name plate shall be marked by raised letters or die-stamping


with at least the following information:
a) Purchase Order Number b) Manufacturer c) Part/Model No. d) Serial
No. e) Date of Manufacture f) Mark/Tag No.

SAES-K-001
Para 4.8.1.2.2

Handling, Storage, and Preservation

B1

Verify that Approved procedures for handling, storage and preservation


of Fans, lists all the required inspection schedules for maintaining the
quality of the material and /or equipment.

WORK PERMIT REQUIRED?

PASS

Schedule Q
Section 5, Att. IV

* Verification is required by checking the equipment submittal if verification is not possible by visual inspection

Page 1 of 2

QR NUMBER

15-Dec-09

EQPT CODE

SAUDI ARAMCO TIP NUMBER

ITEM
No.

30-Jun-08
DATE APPROVED

FAIL

N/A

RE-INSP DATE

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008)

Rev 3

SAUDI ARAMCO INSPECTION CHECKLIST

SAIC NUMBER

Exhaust Fan Receiving, Handling and Preservation

SAIC K-4001

PROJECT TITLE

30-Jun-08
DATE APPROVED

WBS / BI / JO NUMBER

QR NUMBER

15-Dec-09

HVAC

CONTRACTOR / SUBCONTRACTOR

REMARKS:

REFERENCE DOCUMENTS:
1-SAES-K-001 -- Heating, Ventilating and Air Conditioning (HVAC), 25 November, 2006
2-SAES-K-100 -- Saudi Aramco Mechanical (HVAC) Code, 31 May, 2004
3-Schedule "Q" -- Saudi Aramco Quality Requirements
4-Uniform Mechanical Code (UMC), 1997

Contractor / Third-Party

Saudi Aramco

Construction Representative*

PMT Representative

Work is Complete and Ready for Inspection:


Name, Initials and Date:

T&I Witnessed

QC Record Reviewed

Work Verified

T&I Witnessed

QC Record Reviewed

Work Verified

T&I Witnessed

QC Record Reviewed

Work Verified

Name, Initials and Date:

QC Inspector

PID Representative
Performed Inspection

Work / Rework May Proceed

Name, Initials and Date:

Name, Initials and Date:

QC Supervisor

Proponent and Others


Quality Record Approved:

Name, Sign and Date:

Name, Organization,
Initials and Date:

*Person Responsible for Completion of Quality Work / Test

Y = YES

Page 2 of 2

N = NO F = FAILED

Potrebbero piacerti anche