13/08/2015
Rev
Date
Purpose of Issue
Ansari Mohammad
Rehan
Prepared By
Irshad Ali
V. K. Gajinkar
Checked By
Approved By
COMMISSIONING
PROCEDURE OF SAGAR
SAMRAT CONVERSION
PROJECT
Project No.
MR/OW/MM/SSCP/10/2011 (P855C11004)
Document No.
MLL-MOG-GEN-SSCP-GEN-PRM-004-003
Rev
Table of Contents
1. PURPOSE...........................................................................................................................................3
2. SCOPE (System No- 18)....................................................................................................................3
3. REFERENCE.......................................................................................................................................3
4. DEFINATION.......................................................................................................................................4
5. PROCEDURE......................................................................................................................................4
5.1 SYSTEM DESCRIPTION................................................................................................................4
5.2 SYSTEM LIMITS.............................................................................................................................4
5.3 SYSTEM DOCUMENTATION.........................................................................................................5
5.4 SYSTEM PRE-REQUISITES...........................................................................................................5
5.5 SAFETY..........................................................................................................................................6
5.6 TEST EQUIPMENT AND SPECIAL TOOLS...................................................................................7
5.7 VENDOR ASSISTANCE.................................................................................................................7
5.8 COMMISSIONING ACTIVITES.......................................................................................................7
5.9 SYSTEM TEST COMPLETION AND HANDOVER.....................................................................12
6. ATTACHMENT..................................................................................................................................12
Page
2 of 11
COMMISSIONING
PROCEDURE OF SAGAR
SAMRAT CONVERSION
PROJECT
1.
Project No.
MR/OW/MM/SSCP/10/2011 (P855C11004)
Document No.
MLL-MOG-GEN-SSCP-GEN-PRM-004-003
Rev
PURPOSE
The purpose of the sewage treatment System commissioning procedure is to identify and
describe the activities required for the commissioning of the system including storage and
distribution pipework. The commissioning of the sewage treatment System is based on vendor
site test and commissioning Procedures and PCS One check sheets.
2.
3. REFERENCE
In the preparation of the procedure and the execution of pre-commissioning/ commissioning
activities, MOGL shall refer to relevant Technical Specification, Code and standard in gathering
the information Listed below are major Technical Specification, Code and Standard referred in
addition to the approved Construction drawings.
3 of 11
COMMISSIONING
PROCEDURE OF SAGAR
SAMRAT CONVERSION
PROJECT
Project No.
MR/OW/MM/SSCP/10/2011 (P855C11004)
Document No.
MLL-MOG-GEN-SSCP-GEN-PRM-004-003
Rev
Basis of Design
UFD's
4. DEFINATION
ONGC
CA
LOTO
MC
MCC
RFC
5. PROCEDURE
5.1 SYSTEM DESCRIPTION
The sewage system is comprised of the following sub-system
Sewage treatment unit(ST-6600A/B)
Sewage pump (P-6600A/B)
Sewage holding tank
5.2 SYSTEM LIMITS
The sewage treatment system is comprised of the following sub system:
System no
System name
31
Sewage system
4 of 11
COMMISSIONING
PROCEDURE OF SAGAR
SAMRAT CONVERSION
PROJECT
Project No.
MR/OW/MM/SSCP/10/2011 (P855C11004)
Document No.
MLL-MOG-GEN-SSCP-GEN-PRM-004-003
Rev
Type
Drawing / Doc. No
P&ID
SSCP-1381-GLND-PI-DWG-005
P&ID
SSCP-1381-GLND-PI-DWG-011
P&ID
SSCP-1381-GLND-PI-DWG-002
No.
1.
2.
3.
4.
Description
Checked
Yes
Yes
Yes
completed
Confirm that System Cause and effect check has been completed.
Yes
Page
5 of 11
COMMISSIONING
PROCEDURE OF SAGAR
SAMRAT CONVERSION
PROJECT
5.
Project No.
MR/OW/MM/SSCP/10/2011 (P855C11004)
Document No.
MLL-MOG-GEN-SSCP-GEN-PRM-004-003
Rev
Yes
Date
5.5 SAFETY
The system commissioning engineer is responsible for ensuring that all safety
aspects associated with the proposed commissioning activities have been
addressed. These include but are not limited to: Personnel working within the commissioning
team must be fully aware of their duties, responsibilities and potential hazards associated with
the systems to be tested.
Restriction of access notices and barriers must be posted in accordance with the permit to
work system.
Appropriate firefighting equipment must be available at the worksite.
On handover from construction to commissioning, all electrical and mechanical isolations will
be made by the commissioning group using commissioning locks. These locks will be
controlled under the Permit to Work system.
During the Commissioning phase a Permit to Work must be obtained prior to performing any
activity and must remain in force throughout the duration of that work.
5.6 TEST EQUIPMENT AND SPECIAL TOOLS
Not required
5.7 VENDOR ASSISTANCE
Page
6 of 11
COMMISSIONING
PROCEDURE OF SAGAR
SAMRAT CONVERSION
PROJECT
Project No.
MR/OW/MM/SSCP/10/2011 (P855C11004)
Document No.
MLL-MOG-GEN-SSCP-GEN-PRM-004-003
Rev
Vendor for sewage treatment system shall be mobilized to assist in package precommissioning and commissioning activities.
5.8 COMMISSIONING ACTIVITES
Scope of work
A brief description of the total scope of work is as follows: To verify the functionality of the
Sewage treatment system. Use these to treat the sewage from the plant.
Line Up
All valve positions to be maintained as specified in drawing except below mentioned line up. All
control and tripping signals shall be in place except for those mentioned for override below.
Description
P&ID no. SSCP-1381-GLND-PI-DWG-005
Status
Remark
Closed
Yes
Closed
Yes
As per P&ID
Yes
Closed
Yes
Closed
Yes
As per P&ID
Yes
Open
Yes
Open
Yes
2.
3.
4.
5.
6.
7.
8.
Page
7 of 11
COMMISSIONING
PROCEDURE OF SAGAR
SAMRAT CONVERSION
PROJECT
9.
10.
Project No.
MR/OW/MM/SSCP/10/2011 (P855C11004)
Document No.
MLL-MOG-GEN-SSCP-GEN-PRM-004-003
Rev
11.
12.
13.
14.
Open
Yes
As per P&ID
Yes
Closed
Yes
Closed
Yes
Closed
Yes
As per P&ID
Yes
Commissioning steps
The following activities must be carried out in order to successfully commission the new
equipment and pipe work associated with the sewage treatment system. The sewage treatment
unit will be commissioned by the commissioning group with vendor assistance.
No
STEP
Checked
Confirm that the system is lined up for service as per the latest P&IDs, all
1.
Yes
All checks to be carried out under the supervision of the System Engineer.
Page
Yes
8 of 11
COMMISSIONING
PROCEDURE OF SAGAR
SAMRAT CONVERSION
PROJECT
Project No.
MR/OW/MM/SSCP/10/2011 (P855C11004)
Document No.
MLL-MOG-GEN-SSCP-GEN-PRM-004-003
Rev
Perform a walk down of each vent line of the system from origin to
3.
Yes
5.
6.
Perform a walk down of black and grey water discharge lines to ensure
Ensure the availability of seawater and utility air supply to consumers. And
Set all hand valves to their correct positions based on the units flow
8.
11.
12.
13.
Yes
diagram.
Turn ON electrical power supply to the Unit.
10.
Yes
7.
9.
Yes
Yes
Yes
Yes
Yes
valve.
START and OPERATE Sewage Treatment pump (P-6600A/B) As per
Yes
14.
tank and discharge to sewage treatment plant unit (ST-6600) for further
Yes
processing.
Page
9 of 11
COMMISSIONING
PROCEDURE OF SAGAR
SAMRAT CONVERSION
PROJECT
15.
16.
17.
18.
19.
Project No.
MR/OW/MM/SSCP/10/2011 (P855C11004)
Document No.
MLL-MOG-GEN-SSCP-GEN-PRM-004-003
Rev
Fill the sewage treatment units with seawater to the top of the sewage
Yes
holding Tank. Hold for 1 hr and examine for leaks. If found repair the leaks.
Open 3 ST-011 isolation valve on line 3-ST-006-A1 to Overboard
Yes
discharge
Open 3 ST-008 isolation valve on line 3-ST-008-A1 to Overboard
Yes
discharge
Treated sewage water discharge to overboard ( SSCP-1381-GLND-PI-
Yes
DWG-002)
Open 1 ST-014 on line 1-ST-007-A1 (ON Shore Disposal)
Yes
Date:
On satisfactory completion of all the described commissioning test activities, the system
commissioning dossier shall be completed by including the following documents,
Signed commissioning test procedure
B Check sheets/ records
Agreed outstanding punch list items
commissioning completion certificate
Page
10 of 11
COMMISSIONING
PROCEDURE OF SAGAR
SAMRAT CONVERSION
PROJECT
Project No.
MR/OW/MM/SSCP/10/2011 (P855C11004)
Document No.
MLL-MOG-GEN-SSCP-GEN-PRM-004-003
Rev
6. ATTACHMENT
Mark-up P&IDs
Page
11 of 11