Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
construction industry causing long drawn-out litigations over contractual claims, the Government
prompted the creation of an arbitration machinery in the construction industry./
Let me introduce to you EXECUTIVE ORDER NO. 1008,/ also known as the CONSTRUCTION
INDUSTRY ARBITRATION LAW.
SEC.2 It is the policy and objective of this law to provide a fair and expeditious resolution of
construction disputes as an alternative to judicial proceedings, with the aim to restore the
harmonious relationships among the parties.
Arbitration is considered a more reasonable alternative to court action. Only persons who are
knowledgeable of the construction business are appointed as arbitrators to act upon the cases.
Hence, this guarantees that prompt decisions can be easily reached.
These have always been the aim of the earlier topics we had, from the ADR to the Domestic
Arbitration, the bottom line is, to avoid the corridors of the courts waiting for maybe 2, if not, 3, or
so on and so forth years just to finally put an end to a dispute./
SEC.3 On February 4, 1985, Executive Order No. 1008, creating the CIAC and vesting it with
original and exclusive jurisdiction over claims and disputes arising from or connected with public
and private construction contracts in the Philippines, was signed by Pres. Ferdinand E. Marcos. And
CIAC shall be under the administrative supervision of the PDCB./
PDCB is PHILIPPINE DOMESTIC CONSTRUCTION BOARD, created on November 28, 1980 under P.D.
1746.
The PDCB is tasked, among others, to adjudicate and settle claims and disputes in the
implementation of public construction contracts and to formulate and recommend rules and
procedures for the adjudication and settlement of claims and disputes in the implementation of
contracts in private construction./
SEC.4 The CIAC shall have original and exclusive jurisdiction over construction/ disputes,/ which
arose from,/ or is connected with/ contracts/ entered into by parties involved in construction in the
Philippines whether the dispute arose before or after the completion of the contract, or after the
abandonment or breach thereof./
These disputes/ may involve government/ or/ private contracts.
The jurisdiction of the CIAC may include but is not limited to/ violation of specifications for
materials and workmanship;/ violation of the terms of agreement;/ interpretation and or
application of contractual provisions;/ amount of damages and penalties;/ commencement time
and delays;/ maintenance and defects;/ payment default of employer or contractor/ and changes
in contract cost.
Construction dispute shall include those between or among parties to, or who are otherwise bound
by, an arbitration agreement, directly or by reference, whether such parties are/ project owner/,
contractor,/ subcontractor/, fabricator,/ project manager,/ design professional/, consultant,/
quantity surveyor,/ bondsman or issuer of an insurance policy in a construction project./
Excluded from the coverage of this Rules are disputes arising from employer-employee
relationships, which shall continue to be covered by the Labor Code of the Philippines./
HOW DOES THE CIAC ACQUIRES JURISDICTION?
It is an essential requisite for the exercise of jurisdiction by the CIAC over construction disputes
that the parties thereto are bound by an arbitration agreement in their contract/
Any party to a construction contract who desires to avail of the arbitration shall file its REQUEST
FOR ARBITRATION in the prescribed form and number of copies to the SECRETARIAT of the CIAC.
What shall accompany the documents required?
a. The names and addresses of the parties; b. A statement of the case/narration of the facts; c.
The issues of the case;
d. The list of nominees for arbitrator(s) in order of preference; e. Construction contract; f.
Agreement to arbitrate;
g. Documents establishing the circumstances of the case; and h. In case of government contracts,
communications made with the highest authority for exhaustion of administrative remedies.
But, what about if the CLAIM is against the government, are there any conditions?
Well, there are PRECONDITIONS before CIAC can take cognizance of the claim.
The claimant against the government, in a government construction contract, shall state in the
complaint/request for arbitration that
1) all administrative remedies have been exhausted, or
2) there is unreasonable delay in acting upon the claim by the government office or officer to
whom appeal is made, or
3) due to the application for interim relief, exhaustion of administrative remedies is not
practicable.
So, if any of the aforementioned preconditions have taken place, the claim against the government
can now be properly made through the CIAC.
The Claimant in a private construction contract has the same obligation as the above to show
similar good faith compliance with all preconditions imposed therein or exemptions therefrom.
In case of non-compliance with the precondition contractually imposed, absent a showing of
justifiable reasons, exemption, or a waiver thereof, the tribunal shall suspend arbitration
proceedings pending compliance therewith within a reasonable period directed by the Tribunal.
The CIAC Secretariat shall within three (3) days from filing, transmit to the Respondent a request
for his Answer, attaching thereto a copy of the complaint and the Request for Arbitration together
with the annexed documents.
Submission to CIAC jurisdiction- An arbitration clause in a construction contract or a submission to
arbitration of a construction dispute shall be deemed an agreement to submit an existing or future
controversy to CIAC jurisdiction, notwithstanding the reference to a different arbitration institution
or arbitral body in such contract or submission.
When a contract contains a clause for the submission of a future controversy to arbitration, it is
not necessary for the parties to enter into a submission agreement before the Claimant may
invoke the jurisdiction of CIAC.
What if the RESPONDENT fails or refuses to arbitrate?
- Where the jurisdiction of CIAC is properly invoked by the filing of a Request for Arbitration in ac
cordance with these Rules, the failure despite due notice which amounts to a refusal of the
Respondent
to arbitrate, shall not stay the proceedings notwithstanding the absence or lack of participation of
the Respondent. In such case, CIAC shall appoint the arbitrator/s in accordance with these
Rules. Arbitration proceedings shall continue, and the award shall be made after receiving the