Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1.0 Introduction
Government of Karnataka (GOK) has proposed two lane sub way
due to up gradation of Karwar- Ilkal State Highway 6. As the TVU is
less than 1 lakh, hence the cost is fully borne by GOK. The scope of
work was construction of subway including approaches. This subway
was of 2x5. 0x5.0 m road under bridge (RUB) to be provided for
elimination of level crossing no. 261 at km 423/1-2 between Gudgeri
and Yelvigi stations in Hubli-Davangere section. This bridge involved
2200 Cum of Reinforced concrete of M30 grade with 330 tons of
steel reinforcement. The construction was done by box pushing
technique involving 180 tonne capacity hydraulic jacks. The RCC
box was cast in segments of 8.5 to 11.00m length. A drag sheet was
used to avoid the friction between the formation earth and the box
during pushing operation.
This work of RUB will also eliminate the Manned Level Crossing No.
261 which will ensure safety of running trains as well as saving of
man power as 3 men are deputed for the gate.
* Chief Engineer (Construction), South Western Railway, Hubli
** Dy. Chief Engineer (Construction), South Western Railway, Hubli
262
Box size
- 2x 5.00x5.00 meters
Number of RCC segments - 4 numbers on Hubli end and 5
numbers on Bangalore end.
Box length - 43.00 m Hubli end and 53.50 m Bangalore end.
Top and bottom slab thickness
- 500 mm
Side walls thickness
- 500 mm
Quantity of RCC in boxes
- 1100 cum
Quantity of RCC in road works
- 800 cum.
Quantity of RCC in retaining walls - 300 cum.
Quantity of total steel involved
- 330 Tonnes.
263
Fig. 2
264
265
266
5.15
0.50
0.30
0.31
2.30
6.00
5.00
6.15
5.15
267
268
DRAG SHEET 3
LAYERS, 4 ROWS
G. I PIPES SUPPORTING
DRAG SHEETS
20 MM SLOT 1.00 LONG
TO GUIDE DRAG SHEET
(SLOTS 4 NO.)
STIFFENERS
20 MM PLATE
BOX
SEGMENT
PILOT
SEGMENT
269
CUTTING EDGE
WITH 20 MM
STEEL PLATES
Auxiliary beds are also provided for casting of the other segments
with thin film of grease and plastic. Segments are then brought in
alignment of pushing as and when required as pushing progresses.
With the progress of jacking, the front unit with shield penetrates
into the embankment. There after excavation within the shield is
done either manually or mechanically and the excavated stuff is
transported outside the working area.
The progress of pushing is kept continuous and the system of shifting
of remaining box segments from auxiliary bed and bringing them
into alignment is adopted till total length is pushed.
270
Box segment
Box segment
6.15
Movement of box
20 mm plate embeded
in concrete
1.00
6.15
Steel pin
Jacks 180 Ton capacity
Thurst bed
2.50
2.50
2.50
271
272
6.3 Leading segment shall be pushed at least 10cm less than the
length of the rear shield in one operation.
6.4 To prevent caving of earth during excavation quantity of earth
shall be removed to barest minimum duly following the slop of
cutting edge.
6.5 Guide channels to be provided in the thrust bed to guide the
segments to ensure straight alignment.
7.0 Conclusion
The box pushing method adopted for elimination of this Level
Crossing is found suitable and convenient as per the site conditions.
Numbers of construction joints in this method are reduced compare
to cut and cover method. Requirement of Mega Line Block could
also be avoided by adopting this technique. Though the cost of
construction in this method is more, it is adopted mainly due to nonavailability of Mega Line Block and due to non-availability of longer
temporary girders (R. H. Girders). The box pushing work has been
successfully completed without disturbance to track as Drag Sheet
has facilitated for smooth insertion of Box through formation.
*****
273