Sei sulla pagina 1di 31

Dr Khairuddin Abdul Rashid

Session 2
PWD Form DB/T (2002)
Articles of Agreement
Conditions of Contract
Clause 1 – 15

1
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Prepared by a Technical
Committee set up in 1996

Chair – JKR

Members – representatives
from JKR, JPS, DBKL, JPN,
KKR, Treasury and MAMPU

1st – 2000

2nd Edition – 2002

2
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Contents

 Articles of Agreement
 First to Fourth Recital
 Article 1 to 4
 Conditions of Contract
 Clause 1 to 58
 Special Conditions Clause
59 to 62
 Appendices

3
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Subsidiary forms

 Form of Tender PWD Form


DB/T-A2002
 Addendum No 1 (Amendments
no. 1 to 10)
 Addendum No 2 (Amendments
no. 1 to 25) for Deferred
Payment only

Also a guide on the use of the form

4
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Salient points
 Old concepts
Turnkey – contractor design &
supervise
D & B – contractor design,
JKR supervise
 New concepts
Turnkey – contractor design,
supervise & equipt
D & B – contractor design &
supervise

5
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Salient points
 Design bond no longer required
 DLP 24 months
 30% Bumi participation
 Bumi consultants only if project value
<RM50 m
 Bumi + Non-Bumi JV of local
consultants if project value >RM50 m
 Direct payment to contractor’s
consultants
 Used when:
No expertise in JKR
Specialist design
Emergency
 Requires Treasury’s approval if to be
called on direct negotiation or selective
tender

6
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Articles of Agreement

 Contract No / Expenditure
 Date of signing
 Parties – Government & the
contractor
 1st Recital – project title
 2nd Recital – Contractor’s
Proposal
 3rd Recital – Contract Sum
Analysis
 4th Recital – meeting the
Government’s requirements

7
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Articles of Agreement

 Article 1 – Contractor agrees to


design and construct
 Article 2 – Government agrees
to pay … Contract Sum
 Article 3 – Government’s
requirements, the Contractor’s
Proposal, the Contract Sum
Analysis, the Contract
Schedule of Rates… signed
and appended

8
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002


Articles of Agreement
 Article 4 – Contract documents

i. Articles of Agreement
ii. Conditions of Contract and
Appendices
iii. Government’s Requirements
iv. Contractor’s Proposal
v. Contract Sum Analysis
vi. Schedule of Rates
vii. Form of Tender
viii. Letter of Acceptance

9
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Articles of Agreement

 Signature of parties

i. Contractor and witness

ii. Government and witness

10
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 1

 Interpretation, definitions
 Reference to clauses of the
conditions
 Documents read as a whole
 Definitions – see Cl. 1.3 (a) to (r),
p1-3
 New sub-clauses (s) to (x) on
‘deferred payment’

11
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 2 Contractor’s Obligations
Key obligations

 Cl. 2.1(a) Design, construct


and complete the works
 Cl. 2.2 Fully responsible for
the design, execution and
maintenance and guarantee
the Government
 Cl. 2.3.2 Novation
 Cl. 2.4.1 QA System

12
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 2 Contractor’s Obligations
Key obligations
Cl. 2.7.1 Care of the works up to
Practical Completion or Partial
Occupation subject to Cl. 2.7.2
(a) to (f) ‘excepted risks’
 Cl. 2.9 Employ local, regd
consultants (PD’s consent)
 Cl. 2.10 Engage Bumiputera as
sub-contractors (30% [40%] of
CS)
 Cl. 2.11 Submit programme

13
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 3 PD’s Rights to Take
Action

 Cl. 3 (i) any matter related to:


 Cl. 40 (mutual termination)
 Cl. 45 (Delay and EoT)
 Cl. 54 (Determination)
 Cl. 55 (War or Earthquake) or
 Cl. 56 (Arbitration)
is reserved for the Officer
named in Appendix 1

14
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
 Clause 3 (ii) PD’s rights to
issue instructions requiring a
variation under Cl. 27.2 is
subject to the financial limits as
set out in Appendix 1

(Treasury Instructions 202)

15
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 4 PD’s Instructions

 Cl 4.3 must be in writing


 Cl. 4.1 Contractor shall comply
in 7 days… see Cl 4.2 (non-
compliance), Cl. 27.1
(contractor object with reasons)
 Cl. 4.2 If within 7 days, the
contractor fails to comply, PD
may employ and pay others
(deduct monies due to the
contractor)

16
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 5 Notices

 Cl. 5 Written notices to be left


at the contractor’s office on
site, to be confirmed by his PM
or send to contractor’s place of
business

17
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 6 Contract Documents

 Cl. 6.1 PD keeps the original


copy, contractor keeps the
duplicate copy
 Cl. 6.2 Contractor submit 8
certified copies, Cl 6.3 2 copies
of drawings, etc, Cl. 6.4 one
copy of contract documents
keep at the site
 Cl. 6.5 On completion
contractor to submit as built
drawings

18
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 7 Sufficiency of Contract
Documents

 Cl. 7.1 Contractor to provide


everything necessary…
 Cl. 7.2 the Articles of
Agreement, the Conditions and
the Appendices shall prevail
over other documents… any
ambiguity/discrepancy to refer
to PD, contractor to rectify at
his own cost

19
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 7 Sufficiency of Contract
Documents

 Cl. 7.3.1 (a) and (b) Documents


are mutually explanatory…
between the Government’s
Requirements and the
Contractor’s Proposal, the
former prevails

20
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 8 Materials, Goods and
Workmanship

 Cl. 8.1 the works shall be in


accordance to the contract
 Cl. 8.4 contractor to carry out
checks and tests
 Cl 8.5 PD may issue
instructions to remove from the
site or rectify any work,
materials… not in accordance
to the contract

21
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 9 Restriction and Procedure
on Use of Imported Materials
and Goods

 Cl. 9.1 Malaysian materials and


goods only
 Cl. 9.2 Imported materials, etc
can only be used if approved
by the Government

22
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 10 Construction Plan,
Equipment, Vehicles and
Machineries

The contractor is responsible and


shall pay all port dues, prepare
and submit all documents and
abide by the requirements of
the relevant authorities, pay all
charges and expenses and
supply a list to the PD

23
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 11 Non-removal of
Materials and Equipment on
Site

Equipment, temporary works,


materials… intended for the
works can only be removed
from the site with the written
consent of the PD

24
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 12 Statutory obligations,
notices, fees and charges

 Cl. 12.1.1 The contractor shall


comply with statutory
requirements
 Cl. 12.2 The Contractor shall
pay/indemnify the Government
against liability of any fees,
charges…

25
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 12 Statutory obligations,
notices, fees and charges

 Cl. 12.1.2 Divergence to be


brought to attention; the
contractor shall propose
amendments (in case of
emergency see Cl. 12.1.3) and
with the PD’s consent carry out
the works at his own cost
(subject to Cl. 12.3)

26
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 12 Statutory obligations,
notices, fees and charges

 Cl. 12.3.1 and 12.3.2 Variation


in the statutory requirements /
conformity with terms of an
authority’s approval after date
of tender leading to amendment
to contractor’s proposal is
treated as an instruction of the
PD affecting a Variation under
Cl. 27.2

27
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 13 Custom Dues and
Taxation

 Cl. 13.1 – 13.3 The contractor


to pay all duties and taxes and
make arrangement for their
employees to pay income tax

28
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 14 Antiquities

 Cl. 14.1 found on the site


becomes the property of the
Government. The contractor
shall not disturb, preserve the
findings, and inform the PD
 Cl. 14.2 PD shall issue
instruction
 Cl. 14.3 Compliance with 14.2
may lead to reimbursement for
loss and or/expense

29
Dr Khairuddin Abdul Rashid

PWD Form DB/T 2002

Conditions of Contract
Clause 15 Copyright, royalties and
patent rights

 Cl. 15.1 The contractor is


responsible for payment of all
royalties or other sums … of
any patented articles, etc in
respect of the works other than
those provided by the PD
 Cl 15.2 Issue on patent that
arises due to PD’s instruction,
the sum added to the contract

30