Sei sulla pagina 1di 2

Federal Register / Vol. 70, No.

126 / Friday, July 1, 2005 / Notices 38237

Total Estimated Annual Burden: 4.3 percent per year since 1990. TVA described for the first solution. As part
16,416 hours. supplies bulk electricity to this area of the second solution, TVA would also
Dated: June 24, 2005. through its Davidson, Pinhook, and upgrade about 75 miles of existing 161-
Craig Hartson,
Wilson 500-kV Substations. As a result kV transmission lines. These
of the rapid population growth, the transmission lines are located in
Acting Reports Clearance Officer, Social
Security Administration.
electrical load for this area has also Davidson, Rutherford, Williamson,
grown rapidly and is expected to exceed Sumner, Wilson, Coffee, Franklin, and
[FR Doc. 05–12980 Filed 6–30–05; 8:45 am]
the capacity of the 500-kV substations Bedford Counties. The upgrade work
BILLING CODE 4191–02–P
serving the area by 2010. Several 161-kV could range from replacing the
transmission lines serving the area from conductors to completely rebuilding the
these substations are also expected to lines.
TENNESSEE VALLEY AUTHORITY become overloaded by 2010. The third potential solution involves
TVA has studied these problems and the expansion of TVA’s existing
Environmental Impact Statement for tentatively concluded that the best Pinhook 500-kV Substation in
Rutherford-Williamson-Davidson method of remedying them is to either southwest Davidson County. The
Power Supply Improvement Project construct a new 500-kV substation or substation would be expanded by
AGENCY: Tennessee Valley Authority. expand an existing 500-kV substation. adding a second bank of 500/161-kV
ACTION: Notice of intent. The solution would also require the transformers. This solution would also
construction and operation of new 500- require the upgrading of about 115 miles
SUMMARY: The Tennessee Valley kV and 161-kV transmission lines and/ of existing 161-kV transmission lines.
Authority (TVA) will prepare an or upgrades to existing transmission These transmission lines are located in
environmental impact statement (EIS) lines. Davidson, Rutherford, Maury,
addressing the proposed construction Williamson, Coffee, Franklin, and
Project Description
and operation of a new or expanded Bedford Counties.
500-kilovolt (kV) substation and TVA has three potential alternative The new 500-kV transmission line
associated transmission line upgrades in solutions. The first would involve the would likely be built using self-
middle Tennessee. The substation construction of a new 500-kV substation supporting, laced steel towers on right-
would be located in Rutherford, in southwest Rutherford County near of-way 175 feet in width. The new 161-
Williamson, or Davidson County. Other Eagleville. The substation would require kV lines would likely be built using self-
project components would be located in an area of at least 50 to 75 acres. Major supporting single-pole or H-frame steel
these counties and in other counties in substation components would include towers on right-of-way 100 feet wide.
middle Tennessee. In the EIS, TVA will four 500/161-kV transformers, two 500- The structure types, right-of-way
evaluate the potential environmental kV breakers, and nine 161-kV breakers. characteristics, and line lengths remain
impacts of the construction, operation, TVA would also add four 500-kV to be determined and could change
and maintenance of the new and breakers to its Maury 500-kV substation when additional information is
upgraded facilities. TVA will use the in north-central Maury County. gathered.
EIS process to obtain public As part of this solution, TVA would Line construction would require
involvement on this proposal. Public also construct and operate a new 500-kV removal of trees within the line right-of-
comment is invited concerning both the transmission line from its Maury 500-kV way as well as any other nearby tall
scope of the EIS and environmental Substation to the new 500-kV trees which would endanger the safe
issues that should be addressed as a part substation. This line would likely be operation of the line. Construction of
of this EIS. about 2725 to 30 miles long and would the 500-kV support structures would
be built on right-of-way purchased by require the excavation of foundations
DATES: Comments on the scope and
TVA in the 1970s for construction of the for each of the tower legs. Support
environmental issues for the EIS must
Hartsville-Maury 500-kV transmission structures for the 161-kV lines would
be postmarked or e-mailed no later than
line. This line was never completed and normally not require separate
August 8, 2005, to ensure consideration.
the portion of the right-of-way proposed foundations and the poles would be
ADDRESSES: Written comments should for the new 500-kV line has remained in embedded in drilled holes. Cranes and
be sent to Charles P. Nicholson, TVA ownership and was never cleared. other heavy equipment would be
Environmental Policy and Planning, Three 161-kV transmission lines are also needed to construct the towers and pull
Tennessee Valley Authority, Mail Stop proposed. One of these, from the new the electrical conductor into place. After
WT 9B, 400 West Summit Hill Drive, 500-kV substation to the Almaville construction, the disturbed areas would
Knoxville, Tennessee 37902–1401. Substation, would be about 7 miles long be restored, and the right-of-way would
Comments may be e-mailed to and built on vacant right-of-way owned be maintained periodically to control
cpnichol@tva.gov. by TVA. A double-circuit line about 12 the growth of tall vegetation that could
FOR FURTHER INFORMATION CONTACT: miles long would be built on new right- endanger the line. A detailed
Hugh S. Barger, Environmental of-way between the new substation and description these activities, as well as
Engineer, Transmission/Power Supply, the Christiana substation. Another line applicable and appropriate
Tennessee Valley Authority, Mail Stop about 2.5 miles long would connect the environmental protection measures, will
MR 4G–C, 1101 Market Street, Murfreesboro-Triune-E. Franklin 161-kV be provided in the EIS.
Chattanooga, Tennessee 37402–2801. transmission line to the new substation. After the completion of scoping, TVA
Telephone (423) 751–3131. E-mail may The proposed transmission lines are will begin detailed studies for siting the
be sent to hsbarger@tva.gov. located in Rutherford, Maury, and substation and routing the transmission
SUPPLEMENTARY INFORMATION: Williamson Counties. lines using maps, aerial photography
The second potential solution and other relevant data. When the
Background involves the construction and operation studies have progressed sufficiently,
The population in Murfreesboro, of a new 500-kV substation in northeast potentially affected landowners will be
Franklin, and surrounding areas of Williamson County near Brentwood. contacted directly, and additional field
Middle Tennessee has grown at a rate of The substation would be similar to that surveys will be conducted.

VerDate jul<14>2003 18:11 Jun 30, 2005 Jkt 205001 PO 00000 Frm 00148 Fmt 4703 Sfmt 4703 E:\FR\FM\01JYN1.SGM 01JYN1
38238 Federal Register / Vol. 70, No. 126 / Friday, July 1, 2005 / Notices

Proposed Issues To Be Addressed this notice is not meant to be exhaustive OFFICE OF THE UNITED STATES
The EIS will contain descriptions of or final. TRADE REPRESENTATIVE
the existing environmental and The scoping process will include both
Andean Trade Preference Act (ATPA),
socioeconomic resources within the area interagency and public scoping. The
as Amended: Notice Regarding the
that would be affected by construction public is invited to submit written
2003 and 2004 Annual Reviews
and operation of the proposed comments or e-mail comments on the
transmission line and upgrades. TVA’s scope of this EIS no later than the date AGENCY: Office of the United States
evaluation of potential environmental given under the DATES section of this Trade Representative.
impacts to these resources will include, notice. ACTION: Notice.
but not necessarily be limited to, the
TVA will conduct a public scoping SUMMARY: In January 2005, the Office of
potential impacts on water quality,
aquatic and terrestrial ecology, meeting on July 11, 2005. This informal the United States Trade Representative
endangered and threatened species, meeting will begin at 4 p.m. and end at (USTR) published a notice specifying
wetlands, aesthetics and visual 8 p.m. (CST). The meeting will be held the results of the preliminary review of
resources, land use, historic and at the Eagleville High School, 500 petitions it received in September 2004
archaeological resources, and Highway 99, Eagleville, Tennessee, in connection with the annual ATPA
socioeconomic resources. The need and Tennessee. review and modifying the schedule for
purpose of the project will be discussed. At the meeting, TVA management and consideration of the remaining
project staff will present overviews of petitions. The January 2005 notice also
Alternatives specified the status of the petitions filed
the proposed transmission line project
The results of evaluating the potential and the EIS process, answer questions, in 2003 that have remained under
environmental impacts and other and solicit comments on the issues that review. The Trade Policy Staff
important issues identified in the Committee has decided to continue the
the public would like addressed in the
scoping process, as well as engineering review of pending petitions.
EIS. These meetings will be publicized
and economic considerations, will be FOR FURTHER INFORMATION CONTACT:
through notices in local newspapers, by
used by TVA in selecting identifying a Bennett M. Harman, Deputy Assistant
TVA press releases, on the TVA Web
preferred alternative. At this time, the U.S. Trade Representative for Latin
site at http://www.tva.gov/environment/
range of alternatives TVA has identified America, at (202) 395–9446.
for detailed evaluation includes no calendar.htm and in letters to local
SUPPLEMENTARY INFORMATION: The ATPA
action and the three alternative elected officials preceding the public
(19 U.S.C. 3201 et seq.), as renewed and
solutions described above. The ability of meetings.
amended by the Andean Trade
energy conversation to meet projected The agencies to be included in the Promotion and Drug Eradication Act of
demands will be addressed. As analyses interagency scoping are U.S. Army 2002 (ATPDEA) in the Trade Act of
proceed, one or more alternatives may Corps of Engineers, U.S. Fish and 2002 (Pub. L. 107–210), provides trade
be eliminated due to technical Wildlife Service, Tennessee Department benefits for eligible Andean countries.
infeasibility, unacceptable of Environment and Conservation, the Pursuant to section 3103(d) of the
environmental impacts, or unreasonably Tennessee State Historic Preservation ATPDEA, USTR promulgated
high economic costs. TVA also expects Officer, and other Federal, State, and regulations (15 CFR part 2016) (68 FR
to evaluate multiple sites for the new local agencies, as appropriate. After 43922) regarding the review of
substation. consideration of the scoping comments, eligibility of countries for the benefits of
Scoping Process TVA will further identify alternatives the ATPA, as amended.
and environmental issues to be In a Federal Register notice dated
Scoping, which is integral to the August 17, 2004, USTR initiated the
addressed in the EIS. Following analysis
process for implementing the National 2004 ATPA Annual Review and
Environmental Policy Act (NEPA), is a of the environmental consequences of
announced a deadline of September 15,
procedure that solicits public input to each alternative, TVA will prepare a
2004 for the filing of petitions (69 FR
the EIS process to ensure that: (1) Issues draft EIS for public review and
51138). Several of these petitions
are identified early and properly comment. Notice of availability of the
requested the review of certain practices
studied; (2) issues of little significance draft EIS will be published by the in certain beneficiary developing
do not consume substantial time and Environmental Protection Agency in the countries regarding compliance with the
effort; (3) the draft EIS is thorough and Federal Register. TVA will solicit eligibility criteria set forth in sections
balanced; and (4) delays caused by an written comments on the draft EIS, and 203 (c) and (d) and section 204(b)(6)(B)
inadequate EIS are avoided. TVA’s information about possible public of the ATPA, as amended (19 U.S.C.
NEPA procedures require that the meetings to comment on the draft EIS 3203 (c) and (d); 19 U.S.C.
scoping process commence soon after a will be announced. TVA expects to 3203(b)(6)(B)).
decision has been reached to prepare an release a draft EIS in the fall of 2006 and In a Federal Register notice dated
EIS in order to provide an early and a final EIS in early 2007. January 18, 2005 (70 FR 2921), USTR
open process for determining the scope Dated: June 27, 2005. published the results of the preliminary
and for identifying the significant issues review of these petitions. The TPSC
related to a proposed action. The range Kathryn J. Jackson,
terminated the review of one petition
of alternatives and the issues to be Executive Vice President, River System and modified the date for the
addressed in the draft EIS will be Operations & Environment. announcement of results for both the
determined, in part, from written [FR Doc. 05–13013 Filed 6–30–05; 8:45 am] remaining 2004 petitions and the
comments submitted by mail or e-mail, BILLING CODE 8120–08–P remaining 2003 petitions to on or about
and comments presented orally or in May 31, 2005.
writing at any public meetings. The With respect to the outstanding
preliminary identification of reasonable petitions, the TPSC is modifying the
alternatives and environmental issues in schedule for the review, in accordance

VerDate jul<14>2003 18:11 Jun 30, 2005 Jkt 205001 PO 00000 Frm 00149 Fmt 4703 Sfmt 4703 E:\FR\FM\01JYN1.SGM 01JYN1

Potrebbero piacerti anche