PE-O-HS-STD-001-02-E
Revision: 02
Page 2 of 81
2. Regulatory content
2.1
specifies who may identify and authorize hazardous jobs (and any limits to
their authority) and who is responsible for specifying the necessary precautions
communicates clearly to people carrying out the work the exact identity, nature
and extent of the job, the hazards involved, limitations on the extent of the work
and the time during which the work may be carried out.
specifies the precautions to be taken, including safe isolation from potential
risks such as hazardous substances and/or energy sources.
provides a record showing that the nature of the work and needed precautions
have been verified by a competent person.
PE-O-HS-STD-001-02-E
Revision: 02
Page 3 of 81
ensures that all the persons in charge of a site, installation are aware of all
hazardous work being done there, using a suitable display of valid permits (see
Annex 14).
provides a means for coordinating multiple PTW for activities that have the
potential to overlap or conflict with each other.
provides a formal work handover procedure when a PTW is issued for a period
longer than one shift or when permit signatories change (see Annex 14).
ensures that equipment left unserviceable is correctly tagged and identified to
incoming shifts.
provides a procedure for the suspension of work prior to its completion (see
Annex 14).
ensures that details of non-completed work are documented and communicated
to the competent person.
provides a process for change, a determination of when hazards need to be
reassessed and a means for controlled communication of change.
provides a written hand-back procedure to ensure that the equipment/facilities
affected by the PTW are in a safe condition and ready for reinstatement (see
Annex 14).
2.2
EP Asset management
EP Sectors management
Approver
Affected Area Responsible
Performer
Gas test responsible
Fire watch man
Fire brigade
See section 2.11 for details.
2.3
Page 4 of 81
oil/gas wells
areas of an exposed section of flow/pipeline
areas of a drilling rig
EX zones
NOTE : For the EP Hazardous Areas definition and examples see the Standard
Petrom EP FA HA 01 ST : Company Standard for Areas Classification. There, a
classification of existing hazardous areas for the main facilities pertaining to OMV
Petrom can be found. This classification shall be taken in consideration by the
person responsible to identify the hazards, evaluate the risks and put in place the
mitigation measures.
Annex no. 1 shows relevant extracts from the Standard.
Examples of works under a) definition, requiring PTW (the list is not exclusive):
works involving open flame inside a zone of 40 meters radius around
flammable/explosive areas
works producing sparks (incl. static electricity), heat, hot surfaces, ignition
sources
(friction) welding, burning, grinding
needle gunning
pressure testing activity after a work which has affected the integrity of a
system containing pressurised hazardous gases or liquids, to ensure that the
system is safe to be put back into service
b) Works (especially non-routine) which are Hazardous by their nature, even they
are not performed in Hazardous Areas
Examples of works requiring PTW (the list is not exclusive):
electrical works
works inside Confined Spaces
lockout of powered (electrical, mechanical, pressure, flow) systems
PE-O-HS-STD-001-02-E
Revision: 02
Page 5 of 81
complex lifting operations - when a Lifting Plan must be developed (lift greater
than 10 tones, not a single point lift involving two or more lifting/pulling
appliances, lift requiring rollers, restraining anchors or guide frame/structure)
removal of handrails, gratings, hatches and covers or fixed ladders, assembling
/dismantling of scaffoldings or racks
works at height (works carried out at a height greater than 2.0 meters, other
than on walkways, scaffold under certification, or approved access platforms)
works which compromise critical safety systems or which remove them from
service (egg. Emergency Shut Down, Safety, or Power Generator Systems, fire
sand gas detection systems, public address systems, life-saving equipment and
fire fighting equipment)
jobs where two or more individuals or groups need to coordinate activities (egg.
combined or simultaneous operations SIMOPS)
excavation (digging more than 0,70 meters deep)
pressure tests after work which has affected the integrity of an under-pressure
system
diving activities
work at any place on an offshore installation from which any person could fall
into the sea
work involving the use of dangerous substances, including radioactive materials
and explosives
work with asbestos-based materials
roof access
2.4
they are routinely performed and they are fully covered by specific operating
procedures and work instructions which include HSSE matters and eliminate
the cause which can trigger an incident
they do not require open flames inside a zone of 40 meters radius around
flammable/explosive areas
they do not require operations producing ignition sources performed in
technological facilities where flammable or explosive atmosphere can be
present, or in warehouses/other places where flammable/explosive staff is
present
they do not require a Lock-out/Tag-out of any system (however, this
requirement is not applicable to the Minor Maintenance Team members
when a documented routine operation, performed by themselves, requires a
LOTO)
they are not performed on energised systems (systems under pressure,
above or below ambient temperatures or electrically charged)
PE-O-HS-STD-001-02-E
Revision: 02
Page 6 of 81
other works being done nearby cannot affect, in a dangerous way, the work
concerned
work over/work intervention activities where the Permit to Work template is
replaced by the hand over protocol and an approved work program is available
PE-O-HS-STD-001-02-E
Revision: 02
Page 7 of 81
NOTE : A certificate system by itself is not a PERMIT TO WORK and must not be
used to authorize work. A certificate system must be used only in conjunction with
an appropriate Permit to Work.
The gas monitoring is mandatory for all the works with high level of risks related to
gas presence, within classified EX areas, within all confined spaces and any other
situations in which is identified gas presence.
In this case a GAS TESTING RECORD shall be kept and attached to the Permit (see
Annex no. 12)
PE-O-HS-STD-001-02-E
Revision: 02
Page 8 of 81
Identify any other activities that may conflict with the work.
List the preparations required by the Affected Area Responsible and the
Performer.
List any other controls to be put in place by the Affected Area Responsible.
The JSA combines all hazard management information into one document.
JSA can either be created by hand, or by using outputs from the JSA repository
(generic JSAs).
The JSA repository must be created on the Asset level in order to be accessible
by intranet to all employees.
Generic JSA for activities covered by the PTW Standard, which have been created
and archived in the JSA repository, may be made available to all people
concerned (inclusive Contractors) as paper documents. These can be printed off
as standard documents. It is essential that generic JSA are reviewed for each task
before a Permit is authorised.
The generic JSA must have some additional blank lines which can be filled in
by hand (if the case).
If a generic JSA is not available, then one shall be produced manually.
Where Generic JSAs are available for different types of works, these must be
adapted to specific local work conditions.
2.9
In case of tasks which contain both Hot Work and Cold Work, only the HOT
Permit To Work is to be raised, but only if the risks incurred by the cold work
content are the same or less restrictive as the ones required for the Hot Work.
the Permits must have attached the necessary related Certificates (confined
space entry, isolation etc)
the JSA must show the controls required for all the activities
PE-O-HS-STD-001-02-E
Revision: 02
Page 9 of 81
if more than one Permit is used for the same task, the Permits must be crossreferenced
A practical description for the proposed way to use the PTW system in EP can be
found in Annex 14.
2.10
Understand the hazards and threats associated with the workplace/work (What
are the impacts to people, environment or assets? Obtain precise details of the
work to be undertaken. Are there 'process' hazards or hazards associated with the
material being handled involved in the work?)
Assess
Recognise the risks (What are the likelihood to cause harm? Is the risk involved as
low as reasonably practicable - ALARP? Consider the practical difficulties of
carrying out the work, if necessary consulting the discipline specialists
undertaking the work)
Control
Decide upon the barriers and control necessary to manage the risk thus providing
a safe working environment (What is required to prevent the likelihood of causing
harm from carrying out the work being realised? Are there any safer alternatives
either in terms of timing, or the intended method of performance of the work)
Recover
Agree on the recovery measures in the event that controls break down. The
Performer should carry out such assessment (in conjunction with his workforce)
and any other persons whose specialist knowledge may be needed.
Where available the Performer will take advantage of all hazard information in
Part 4 of the Safety Case prepared for the respective facility. This will assist him in
recognising hazards, threats, risks, barriers and precautions needed and response
mechanism should controls breakdown.
PE-O-HS-STD-001-02-E
Revision: 02
Page 10 of 81
Likewise the Approver and the Affected Area Responsible should also undertake
such assessment when the permit is presented to further enhance safety control,
if needed.
2.11 Responsibilities
2.11.1
2.11.2
defines the areas under his responsibility (could be more than one area inside a
Sector boundaries, depending on Sector size) ; this area definition shall assure
that majority of the works performed in different areas will not interfere
defines the Permit Issue Point for each defined area and the way of effective
communication between Permit Issue Points personnel (in the case when works
performed in different areas can interfere)
nominates the Approvers, Affected Area Responsible, Gas Testers and Fire
Watch Men for each defined area and sends the lists with nominated people to
be approved by head of operations ; an alignment with Asset Department Heads
on this matter shall take place for each of the defined areas
makes sure that the people mentioned above are properly trained and certified
makes proposals of jobs to be included in the Exemption list ; an alignment with
Asset Department Heads on this proposal shall take place
informs the people concerned about the works needed to be performed under a
Permit
PE-O-HS-STD-001-02-E
Revision: 02
Page 11 of 81
informs the people concerned about the Permit Issue Point where the Permit
can be approved for a specific job
2.11.4
Page 12 of 81
2.11.6
Performer is responsible for careful planning of work that shall be
undertaken to ensure:
appropriate approvals for the work
all persons in charge of potential affected areas are well aware and all
precautions are taken against possible interaction with other activities
sufficient time is allocated to identify all potential risks, implement necessary
precautions and prepare the workplace
he had received training in the PTW system as applied in that particular location
the workers have received adequate instruction in the PTW system
he assessed the work hazards and controls (JSA)
the permit is posted at the work site in visible place
the work team is briefed on the details of the permit, including any potential
hazard, and on all the precaution taken or to be taken
the taken precautions are maintained throughout the work session
the workers understand that, if the circumstances change, work must be
stopped and advice sought
the work group stays within the limitations set on the permit (physical
boundaries, type of work and PTW validity time)
on completion or suspension of the work the site is left in a safe condition and
the Affected Area Responsible is informed
2.11.7
2.11.8
their employees will follow the requirements of a PTW system, either is the
Contractors or OMV Petroms system, as have been agreed between parties
they are informed of and understand the broad principles of the PTW system for
the locations where their employees are to work
their employees have been given the appropriate training and understand the
operation of the PTW system and their specific responsibilities within it
they monitor the training of their employees
2.11.9 HSSE representative
provides any specialized advice/trainings to the concerned parties as necessary
or required
PE-O-HS-STD-001-02-E
Revision: 02
Page 13 of 81
periodically audits (at least quarterly) the PTW system to ensure that is being
correctly administered
2.11.10 Fire Watch Man must ensure that :
All flammable materials are removed from the work site
Drains remain covered and water sealed
Spark and Welding spatter are contained (use of fire blanket, water spray etc)
Fire fighting equipment is available and ready for immediate use
Alarm is raised if fire or gas emission occur in the work site area
First aid and fire fighting equipment (fire extinguisher, fire blanket etc) is
available and appropriate to the job
2.11.11 Gas Test Responsible Person
can carry out gas tests required during the day.
the results of the Gas Test are to be recorded in the Gas Test Record form,
2.12
except for Confined Space results, which are to be recorded on the Confined
Space Entry Certificate.
gas tests are to be done before work starts, and at the frequency stated on the
Permit. An extra test is required before work re-starts, if the worksite is left
unattended for more than one hour.
in addition to Gas Testing, continuous monitoring may be required. This will
have been specified in Box 3 of the Permit. A Performer may supervise work
for which continuous gas monitoring is required without being appointed as a
Gas Tester. He must, however, have been trained in the use of the gas
detector.
if gas or other hazardous atmosphere is found at any stage, work must stop.
The Permit is to be suspended. The Approver must be informed immediately.
he will be responsible for the calibration and certification (through authorized
third party companies) of the devices used for gas testing and detection.
Page 14 of 81
potential hazards associated with the plant/process and with the assigned work;
precautions required before starting work;
knowledge regarding isolation/de-isolation process
details of documentation involved;
specific responsibilities associated with being a task supervisor;
shift handover requirements;
actions to be taken in an emergency situation (including fire fighting and first
aid).
2.13.3 Gas Test Responsible Person
is nominated by APPROVERS (for the initial site testing) and PERFORMER (for
testing during the work period) from their team.
must be trained in gas testing and detection. Gas testing training will be
organized internally in each organizational unit (asset).
2.13.4 Fire Watchman
A fire watchman must be present to monitor the work area, for hot work, e.g.
welding and burning.
The Fire watchman must be suitably trained in the equipment they have to handle
and are responsible for ensuring that:
Suitable fire fighting equipment is available and ready for immediate use.
Flammable materials are cleared away from the worksite.
Drains remain covered.
PE-O-HS-STD-001-02-E
Revision: 02
Page 15 of 81
Sparks and welding spatter are contained (by the use of fire blankets, water
sprays etc)
They are familiar with the location of the nearest fire alarm activation means
and when and how the fire alarm will be raised where a fire or gas release
occurs in the area.
The alarm is raised should there be a fire or gas release in the area.
In complex multi-deck layouts, more than one firewatcher may be required.
A fire watch man may be nominated to monitor the work area while fire and gas
detection system are inhibited/overridden or as required by the Permit Approver
PTW training requirements for the Approvers, Affected Area Responsible and
Performers will include:
legislation and industry recommendation and requirements;
company policy, procedures, work instructions;
responsibilities.
Written examination or suitable assessment is part of the training.
3.
4.
5.
Obsolete regulations
Petrom E&P Standard - HSEQ-RO-06-03-01 Permit to Work System
PE-O-HS-STD-001-02-E
Revision: 02
Page 16 of 81
6.
Certification Standards
SR EN ISO 9001:2008 Quality Management System. Requirements.
7.
Cold Permit to Work is a written document which ensures that any form of
potentially hazardous work involving maintenance, repair, construction or
inspection activities, without hot work, shall be done accordingly with the all HSE
requirements.
Hot Permit to Work is a written document which ensures that any form of work that
involves use of open flame (welding, thermal or oxygen cutting, heating and other
fire or spark producing operations) shall be done accordingly with the all HSE
requirements.
Planned Permit a Permit which has been filled by the Performer, received an unique
number, but not yet authorized by the Approver.
Confined Space Entry Certificate is a written form for any work involving the need
to enter into a confined space in a safe manner.
Confined space is any vat, pit, duct, flue, oven, chimney, silo, reaction vessel,
container, receptacle, underground sewer, shaft, well trench, tunnel, oil storage
tank, pressure vessels or other similar enclosed or partially enclosed structure, if
the space:
is not designed for temporary or permanent occupancy
has a limited, restricted means for entry or exit that makes it physically difficult for a
person to enter or exit the space, and contains, or is likely to contain:
an atmosphere that has a harmful level of any contaminant
an atmosphere that does not have a safe oxygen level or have too much oxygen
process or equipment related hazards
Page 17 of 81
Double Block & Bleed is the isolation of pressurized system through the use of two
closed valve which are in series in a process line/pipeline and a bleed line/vent
between the valves to verify and monitor the pressure holding integrity of the main
shutoff valve.
Blind /Spades : it can be a slip blind between two flanges, a rotational spectacle
blind between two flanges or a bolted blind at the end of a pipe run.
Lock/Lockout : a physical device or barrier (key or combination lock, chain and lock,
isolation blind, etc.) that is used or installed as part of the isolation process to
maintain security of the isolation.
Unique Work Permit Register : a register maintained at the Permit Issue Point for
all work permits issued on daily basis.
Performer (Permit Applicant) : this is a generic title used in this document either
for the person who is appointed to perform the work or the person in charge of
the work team, or the entire work party, as appropriate in the context.
He applies for a Permit and completes the Work Description parts of the Permit,
for approval by the Approver. He is temporarily in charge of the area where the
work is to be performed, during time period when work is performed, without
interfering with the Affected Area responsibilities. He is responsible for ensuring
that he and/or the work team members understand and obey the requirements of
the Permit to Work System and other relevant procedures. He may be employed
by OMV Petrom or a Contractor
Approver is the person who has overall responsibility for the co-ordination of
work, and authorises the Permits affecting his area of responsibility.
A list with nominated people for this position shall be issued by the EP Sectors
management. The list must be sufficiently large, in order to ensure that, at any
time, a nominated person is present and can authorise a Permit. No position titles
will be used!
Page 18 of 81
Residual Hazard are those are still present after the preparation has been done for
safe execution of the job. Additional precautions and special PPE might be
required to control the residual hazards for any activity.
Fire Watchman is the person who monitors the workplace for fire prevention and
fire fighting during hot work, and is appointed by the leader of the working team,
from among the team members.
If the work is to be carried out by just one person, or if none of the team members
is suitable / available, the Approver will appoint someone from location
personnel. He must have basic fire fighting knowledge (use of portable
extinguishers and fire hoses). This knowledge is ensured through specific fire
fighting training provided by a certified trainer.
He must be trained in gas testing and detection. Gas testing training will be
organized internally in each organizational unit (asset).
He will be responsible for the calibration and certification (through authorized
third party companies) of the devices used for gas testing and detection.
His main task : uses the gas test device and STOP the work if the thresholds are
overpassed
7.2
Abbreviations
ALARP - As low as is reasonably practicable
EP
ESD
LEL
PTW
- Permit to Work.
JSA
8.
Page 19 of 81
9.
Annexes
Annex 1
Annex 2
Annex 3
Annex 4
Hot PTW
Annex 5
Cold PTW
Annex 6
PTW Certificates
Annex 7
Annex 8
Annex 9
Annex 10
Annex 11
Radiography Certificate
Annex 12
Annex 13
JSA form
Annex 14
Annex 15
Annex 16
Annex 17
Isolation label
10.
Modified chapters
PE-O-HS-STD-001-02-E
Revision: 02
Page 20 of 81
Regulation Class
Document Class
Standard
Anexa 1
Annex no. 1
All OMV Petrom operating areas have a Hazardous Area Classification. The rules
governing Hot Work depend on the Classification of the area where work is to take
place.
NOTE : For the EP Hazardous Areas definition and examples see the Standard
Petrom EP FA HA 01 ST : Company Standard for Areas Classification. There, a
classification of existing hazardous areas for the main facilities pertaining to OMV
Petrom can be found. This classification shall be taken in consideration by the
person responsible to identify the risks and the mitigation measures.
HAZARDOUS AREA ZONE CLASSIFICATIONS ARE AS FOLLOWS :
1.1.
ZONE 0
ZONE 1
ZONE 2
Hot work is not allowed in Zone 0 or in Zone 1 areas, unless there is no other
means of carrying out essential and/or safety related work.
If all alternatives to Hot Work for carrying out required work in a Zone 0 or Zone 1
area have been considered and ruled out as impractical, then the following action
must be taken:
PE-O-HS-STD-001-02-E
Revision: 02
Page 21 of 81
Regulation Class
Document Class
Standard
Anexa 1
The process system, which resulted in the area being classified as a Zone 0
or Zone 1 area, must be shut down, isolated, depressurised and purged. This
will remove the hazard, which caused the area Zone Classification for the
work period.
A Hot Permit To Work shall then be raised and the work carried out subject
to the necessary special precautions specified on the permit.
RESTRICTIONS ON HOT WORK IN HAZARDOUS AREA ZONE 2
Hot work such as naked flame cutting, welding and grinding must not be carried
out in Zone 2 areas without shutting down and depressurising the adjacent
production facilities.
However, where specifically approved by the person in charge of approval
(Approver in PTW organisation) after consultation with his HSSE Manager at
base, a habitat may be built in order to create an environment within a Zone 2
area, in which Hot Work may be carried out without creating a fire hazard. Before
use, any such habitat must be examined and approved by the Approving
Authority or his delegate.
A Hot Permit To Work shall then be raised and the work carried out subject to the
necessary special precautions specified on the permit.
RESTRICTIONS ON HOT WORK IN NON - HAZARDOUS AREA ZONE
For Hot Work in these areas within 40 m radius surrounding a Zone 2, a Hot
Permit To Work is to be raised, and the work is to be carried out subject to the
necessary precautions, which are to be indicated on the Permit.
Designated hot work areas e.g. welding workshops do not need permits.
SUSPENSION OF HOT WORK
Hot Work tasks being undertaken are to be stopped if any of the following
activities are due to take place concurrently adjacent to the hot work:
PE-O-HS-STD-001-02-E
Revision: 02
Page 22 of 81
Regulation Class
Document Class
Standard
Annex 2
Annex no. 2
Conditions
As a general principle, Works that do not require a PTW must meet the following
conditions, all in the same time:
they are routinely performed and they are fully covered by specific operating
procedures and work instructions which include HSSE matters and eliminate the
cause which can trigger an incident
they do not require open flames inside a zone of 40 meters radius around
flammable/explosive areas
they are not performed on energised systems (systems under pressure, above
or below ambient temperatures or electrically charged)
they do not involve complex lifting operations - when a Lifting Plan must be
developed (lift greater than 10 tones, not a single point lift involving two or
more lifting/pulling appliances, lift requiring rollers, restraining anchors or guide
frame/structure)
other works being done nearby cannot affect, in a dangerous way, the work
concerned
PE-O-HS-STD-001-02-E
Revision: 02
Page 23 of 81
Regulation Class
Document Class
Standard
Annex 2
Nipple up/ nipple down BOP (for tubing / sucker rod); Nipple up/ nipple down Xmass Tree (pumping head); Pressure testing BOP, X-mass Tree; Pull out of hole/
run in hole sucker rods; Pull out of hole/ run in hole tubing / drill pipe; Replacing
pump ( P, TP, PCP ); Replacing pump (ESP ); Well cleaning: snd bailer, bailing
,washing; Workover fluids: preparation, transport, storage and control of
parameters; Fishing operations; Milling; Cementing; Swabbing; Casing repair; Side
tracking; Running liner; Packers Operations; Gravel Packing; Slikline Operations
PE-O-HS-STD-001-02-E
Revision: 02
Page 24 of 81
Regulation Class
Document Class
Standard
Annex 2
PE-O-HS-STD-001-02-E
Revision: 02
Page 25 of 81
Hazardous
Areas
0, 1 or 2
Nonhaz
Areas
E
E
E
E
E
E
E
E
E
E
E
E
n/a
n/a
NE
n/a
E
E
NE
E
E
E
E
Telecoms
Visual inspection of all telecom
equipment (no disruption & working
E
E
at heights)
Servicing
and
replacing
of
E
E
equipment
for
individuals
(telephone, radio, fax etc)
Measuring
telecom
equipment
E
E
parameters
without
service
interruption
General
E
E
General plant cleaning
General handling of containers and
E
E
freight
General catering activities (cleaning,
E
E
food preparation)
Works on water/sanitary equipment
E
E
in buildings
NOTE : Where possible, the routine tasks in safe environments shall be covered by
procedures and work instructions and not by permits. This helps reducing the
number of permits in daily use and enables the Affected Area Responsible to
concentrate on tasks that have higher inherent risk potential.
PE-O-HS-STD-001-02-E
Revision: 02
Page 26 of 81
Regulation Class
Document Class
Standard
Annex 3
Annex 3
The purpose of this document is to describe the method for control of Vehicle Entry
and Driving within the hazardous areas in OMV Petrom EP onshore facilities/sites.
1.
General
1.1.
Vehicle entries
Vehicles entering the hazardous area constitute taking potential sources of
ignition into an area where a flammable atmosphere may be present.
A Vehicle Fitness Certificate is mandatory for all vehicle which entry or drive
within the hazardous areas.
Vehicle access to a pig trap area for pipeline pigging operations covered by authorized
procedures and listed in the approved program.
Travel to and from the facility in crew vehicles via the normal marked route to the facility
parking area.
1.2.
This is a written document which ensures that appropriate and competent vehicle
inspection has been carried in order to assess whether the vehicle is fitted to enter
within a hazardous area. The inspection must ensure that the vehicle equipment is in
good condition and any hazard associated with its entry and operability within the
hazardous are controlled through the vehicle inherent safety systems and technical
integrity
The inspection must be carried out by a competent person or authority
The Transport Department Manager is responsible for ensuring a suitable inspection is
carried out for each vehicle. The Transport Department decide on Fitness Certificate
form.
If the inspection results confirm the vehicle fitness for entry and driving within
hazardous areas, a Vehicle Access sticker is to be posted it in a visible place on the
windscreen.
The sticker must clearly show the fitness inspection validity period; the Transport
Department representative will sign and stamp it on the number (bottom row)
representing the current month.
The Vehicle Access sticker model is shown below
PE-O-HS-STD-001-02-E
Revision: 02
Page 27 of 81
Regulation Class
Document Class
Standard
Annex 3
ACCESS VEHICUL
Auto:
Marca
Nr Inmatriculare
10 11
12
A check list for this inspection is provided in this annex. The list is not limitative.
In case of any major repair works following vehicle accidents, or in case of any
changing works of the vehicles initial design, a new fitness inspection must be carried
out.
1.3.
Licenses
Drivers of vehicles shall hold a current driver's license appropriate to the class
of vehicle being driven.
1.4.
2.
2.1
Pre-Entry Requirements
The following shall apply as requirements prior to vehicle entry:
PE-O-HS-STD-001-02-E
Revision: 02
Page 28 of 81
Regulation Class
Document Class
Standard
Annex 3
2.2
2.3
2.4
Vehicle Route
Vehicle movement in the process area of the plant shall be restricted to a
specified route agreed with the driver.
2.5
Escort
An escort of the vehicle may be required, if the Affected Area Responsible will
consider this. The escort shall warn the vehicle driver of specific hazards and to
gas test the access route.
2.6
Parking Locations
Vehicles shall be parked only in places specified. Reverse parking shall be used
at all times.
2.7
Parking Conditions
If a vehicle is to be parked and left unattended, the driver shall ensure that the
vehicle is stopped, the ignition keys are left in the ignition lock and the doors of
the vehicle are left unlocked at all times.
PE-O-HS-STD-001-02-E
Revision: 02
Page 29 of 81
Regulation Class
Document Class
Standard
Annex 3
2.8
The Affected Area Authority shall approve entry in a process area if the following
requirements have been satisfied:
The driver and all passengers are aware of the safety and emergency rules which
apply within the process area
3.
4.
Contractors requirements
The Contractors have to maintain vehicle inherent safety integrity in order to be
allowed to entry in hazardous areas within OMV Petrom EP facilities/sites.
The contractors vehicles which entry in OMV Petrom EP process facilities/sites
must have the same Fitness Certificate presented above, signed and stamped by
the Contractors Responsible person for the current month.
All this annex provisions are applying to all the Contractors vehicle
Checklist for fitness inspection (not limitative)
Review Periodic Inspection Report
Existence of Fitness Certificate, stamped for the current month
Ensure vehicle has passed the required inspection and has the required documents
Check for the permanent or long time presence of Hazardous
Materials/Transportation of Dangerous Goods
Check warning placards and signs, any leaks or spills of hazardous substances,
unsecured cargo, markings and labels.
Check earthing device integrity
Check the availability and operability of fire extinguishers
Check the steering system operability
Check brake system operability
Check the integrity of the chock blocks.
Check head and rear lamps and turn signals for improper colour, operation,
mounting and visibility.
Check windshield wipers for improper operation
Check fuel tank area for any leakage, tank cap proper mounted
Check the exhaust system for integrity, sparks arrester presence and condition
Check condition of air and electrical lines systems (include the battery area).
Check wheels, rims, hubs and tires.
Check integrity of the frame and body
Check condition of all hoses.
Check van and open-top trailer bodies.
Check any oil leaks from engine transmission or differential
PE-O-HS-STD-001-02-E
Revision: 02
Page 30 of 81
Regulation Class
Document Class
Standard
Annex 4
Work order
Location
Date
Time
Zone 1
Non-Haz
Work site
Start
Zone 2
Equipment
Finish
H2S in location
I hav e rev iewed the task and conf irm that the inf ormation in this Application
and in the JSA is adequate and correct
High
Name_________________________
Contractor_________________
Signed
Date
Low
Non
No
natural v entilation
mech. v entilation
drainage
mech. Isolation
electrical isolation
anti ex tools
other blockages
earthing of equipment
gas detection
f ire detection
Gases to be tested f or
Electrical Isolation/De-isolation
Hy drocarbons
Y es
Mechanical Isolation
H 2S
hrs
Conf ined Space Entry
Oxy gen
Excav ation
Other_________
Gas Test Record
Radiography
ENSURE THAT A JSA HAS BEEN PRODUCED AND ATTACHED TO THIS PERMIT AND ALL ITS REQUIREMENTS ARE FULFILLED
I authorise this Permit f or the Work Description abov e and attached JSA, f or the period:
Date:
FROM:
Time:
Date:
TO:
Time:
FROM:
Name: ________________________
Time:
Time:
Signature
Date:
Signature
Position:
5a. VALIDATION
No
I authorise this Permit f or the Work Description abov e and attached JSA
Date:
Time:
Date:
TO:
Time:
Time:
5c. SUSPENSION
5b. ACCEPTANCE
To be signed by the Affected Area Responsible at the start of To be signed by the oncoming Performer whenev er the
each work period
Permit is v alidated and whenev er responsibility passes
f rom one Perf ormer to another.
I conf irm that the conditions at the worksite are saf e f or the
work specif ied. I v alidate the Permit f or the period stated,
prov ided the work party adhere to the permit requirements.
Work must stop if the permit requirements cannot be met.
Validated
Date
From
Time
To
Time
Name
Name
Petrom/
Contractor
Date
Signature
Time
Date
Signature
6. PERMIT CLOSURE
Work complete
Function:___________
Y ES
NO
Remarks:___________________________________________________________________
___________________________________________________________________________
________________________
Work complete
Y ES
NO
Remarks:___________________________________________________________________
___________________________________________________________________________
________________________
(* Delete as appropriate)
Name:___________________ Position: _______________ Signed:______________ Date:________________Time:_____________
PE-O-HS-STD-001-02-E
Revision: 02
Page 31 of 81
Regulation Class
Document Class
Standard
Annex 5
Work order
White - Worksite
Location
Work site
Green - Approver
Equipment
I have review ed the task and I confirm that the information in this
Application and in the JSA is adequate and correct
Name
Contractor
Signed
Detailed Work Description:
Date
Zone 0
Zone 1
Zone 2
H2S in location
High
Low
Insert max ppm
Non-Haz
Non
Time
Start
Finish
NORM Restricted Area
Yes
No
Associated Permits
Certificate Number(s)
Electrical Isolation/De-isolation
Mechanical Isolation
Confined Space Entry
Excavation
Gas Test Record
Radiography
Gases to be tested
for
Hydrocarbons
H2S
Oxygen
Other_________
hrs
Yes
No
ENSURE THAT A JSA HAS BEEN PRODUCED AND ATTACHED TO THIS PERMIT
5a. VALIDATION
Time:
5b. ACCEPTANCE
5c. SUSPENSION
Validated
From
Time
Name
To
Time
6. PERMIT CLOSURE
a) Permit Return by Perform er
Petrom/
Contractor
Date
Work complete
Signature
YES
Time
Date
Signature
NO
Remarks:_______________________________________________________
______________________________________________________________
_________________________________________________
Date: ________________ Time:__________
Name:____________________ Function:___________
Signed:________________
b) Permit Closure by Affected Area Responsible
* Worksite Checked Clear and Safe. (Process Facilities Only)
* Re-instatements/De-isolations Complete.
* Isolations retained under Cert. no. ________________
(* Delete as appropriate)
Work complete
YES
NO
Remarks:_______________________________________________________
______________________________________________________________
_________________________________________________
PE-O-HS-STD-001-02-E
Revision: 02
Page 32 of 81
Regulation Class
Document Class
Standard
Annex 6
Annex no . 6
Certificates in use
Certificates are used in the Permit to Work System to provide additional
authorisation and control for a number of activities.
NOTE : THE PERMIT TO WORK SYSTEM CERTIFICATES ARE NOT PERMITS TO
WORK AND MUST NOT BE USED TO AUTHORISE WORK UNLESS IT iS
ATTACHED TO AN APPROPRIATE PERMIT TO WORK.
The Certificates and other associated documents used in the system are:
Mechanical Isolation
Electrical Isolation
Confined Space Entry
Excavation
Gas Test Record
Radiography
Lifting Plans
other significant documents considered by key-persons to be attached to
associated Permits
The Certificates will be issued in two copies
Colours of Certificate copies:
Worksite - WHITE
Permit Issue Point YELLOW
NOTE : For any Certificate a registration number shall be given in the Unique
Work Permits Register and written on the certificate, respectively in the
associated permit.
Box 1 is to be completed by the Performer, giving the details of the job and the
number of the associated Permit.
The Box marked Work Continuing on Permit No is to be used when a Permit
passes its validation period, but work will continue under a new Permit. It allows
the Isolation Certificate to be transferred to a new Permit.
PE-O-HS-STD-001-02-E
Revision: 02
Page 33 of 81
Regulation Class
Document Class
Standard
Annex 6
The Performer is to write here the reason why the isolation is required.
BOX 3 - DETAILS OF ISOLATION
The Affected Area Responsible (or Authorized Electrical Person for electrical
isolations) is to write in Box 3 the details of all isolation points, indicating
whether valves are to be open or closed, and places where spading or
disconnection is required.
Correspondent tags are to be provided together with respective Certificate
BOX 4 ISOLATION
This box is to be used when an isolation is still required after its associated
Permit is Closed.
The EPI ON Section is to be signed to authorise the EPI when a Permit is to be
Closed, with the Isolation remaining.
The EPI OFF Section is to be used when work can continue, and the Isolation
Certificate is to be attached to a new Permit.
The use of the Certificates in the Isolation process is covered below.
PE-O-HS-STD-001-02-E
Revision: 02
Page 34 of 81
Regulation Class
Document Class
Standard
Annex 6
CONTROL OF ISOLATIONS
Electrical/Mechanical Isolation
General:
The electrical/mechanical isolation records (on separate Certificates) is meant to
prevent any danger associated to the electrical and/ or mechanical equipment and
shall be used whenever equipment/ machinery is mechanically switched off/ power
is turned off in order to carry on maintenance and/ or replacement works.
The electrical/ mechanical isolation works must ensure that the isolated
equipment/ machinery cannot start up accidentally. Isolation will be ensured by
locking and labelling. The label will contain the warning: DO NOT OPERATE, the
date, name and forename of the person who performed the isolation and the
number of the isolation Certificate. The label will be posted on the electric panel
where the isolation was done or on the mechanically isolated equipment.
If the electrical/ mechanical isolation of a safety system is needed, it will be
attempted to isolate only the respective part of the system and not the entire
system. In this case, the Approver will decide which the best isolation method is, so
that the system is affected as little as possible.
All Isolation Certificates must be attached to the respective Permit and their
numbers filled in Box 2 of the Permits.
Isolation Requirements
The following requirements apply to all isolations:
Competency
The Approver must ensure that the person nominated to do an Isolation/DeIsolation is competent for the task.
Electrical isolation and de-isolation must be completed ONLY by authorized
electrical persons
Recording
The Affected Area Responsible must record all isolated equipment on the Permit
Location Boards. This is done to ensure that equipment is only isolated or deisolated when it is safe to do so.
Electrical Systems
All electrical isolations are to be done in accordance with OMV Petrom specific
procedures and Romanian legal requirements
PE-O-HS-STD-001-02-E
Revision: 02
Page 35 of 81
Regulation Class
Document Class
Standard
Annex 6
Mechanical Systems
Mechanical Isolations are to be done in accordance with OMV Petrom specific
procedures and Romanian legal requirements
Approval for Isolation
All isolations must be fully described in the Isolation Certificate.
All
documented Isolations are to be authorised by the Approver, who must define
the isolation point and sign the Box 4 of the Mechanical / Electrical Isolation
Certificate. All Isolations are to be approved in accordance with specific valid
OMV Petrom specific procedures and legal requirements
Isolation Process
All mechanical and electrical isolations and de-isolations must be carried out in
compliance with OMV Petrom specific procedures and Romanian legal
requirements
Energy Isolation Principle
Mechanical power covers all machinery that has a direct or indirect source of
power (fluid, electrical, pneumatic) as well having moving parts and stored
energy system that must be immobilised by physical means where possible.
Double block and bleed isolation principle must be used whenever and
wherever is possible
Electrical power isolation covers low voltage (less than 1000 V) electrical
isolations and high voltage (over 1000 V) electrical isolation.
Fluid power also includes the supply of compressed air (gas, liquids and
steam).
PE-O-HS-STD-001-02-E
Revision: 02
Page 36 of 81
Regulation Class
Document Class
Standard
Annex 6
ensure it is left in a safe condition and equipment cannot be re-instated until all
work is properly completed;
- if the PTW is suspended, the status of the work site (eg: mechanical/electrical
isolated, under repairing etc) shall be visible displayed in a suitable location
(eg: control room or other onshore equivalent) and the padlock keys kept in a
secure place to ensure unauthorized access.
All persons authorized to carry out isolation works shall be assessed for their
competence prior assignment and they shall:
be suitably qualified;
have experience on the plant/equipment;
have received specific instructions on the plant, isolation method etc.
Their areas of responsibility shall be clearly defined.
The Performer must inspect work area after all isolations have been
completed and before starting the work.
Isolation
When the isolation has been approved by the Approver, the Performer is to take
the Permit and Isolation Certificate to the Affected Area Responsible or
appropriate Electrical Person, to request isolation.
The Affected Area Responsible (or Electrical Person for electrical isolations) is
then to:
Check the Permit Location Board to ensure that the isolation will not conflict
with any other work.
When satisfied that it is safe to isolate, DO the isolation, tagging and
securing of the valves/switches etc.
NOTE:
The Affected Area Responsible can nominate a competent person to perform
isolation/de-isolation, or, if is specified in his nomination (by the sector chief),
having the necessary competence, he can perform mechanical/electrical
isolation/de-isolation, as appropriate
Prove that the isolation has fully isolated the systems and equipment from
pressure/electricity
If part of the isolation is at a remote location under the control of another
Affected Area Responsible, submit (fax or other suitable communication
means are accepted) a copy of the Isolation Certificate to that location and
obtain a return copy with a signature that the remote isolation is known and
complete.
Sign the Isolation Certificate to confirm that isolation is complete. Then add
the marker and details of the isolation to the Permit Location Board.
PE-O-HS-STD-001-02-E
Revision: 02
Page 37 of 81
Regulation Class
Document Class
Standard
Annex 6
Every valve, spade, switch, breaker etc. used in an isolation must be marked
with a tag label.
The tag label (See Annex no. 17) is to identify the number of the Isolation
Certificate authorising the isolation
Each valve/switch etc. used as part of more than one isolation scheme will have
a tag label for each Isolation Certificate. It is not necessary to fit additional
physical securing for each Isolation Certificate (except if this is required for
electrical isolations by other specific work instructions)
Securing of Isolations
Mechanical
All valves, etc. used as part of an isolation boundary are to be locked and
secured in the required position using a high visibility securing device, e.g.
red/white chain. The purpose of securing the isolation is to prevent valves from
being moved accidentally, and to show everyone in the area that the valve is
being used as part of isolation.
Electrical
All electrical isolations are to be secured where practicable, locked in the 'open'
position with SAFETY PADLOCKS or similar type locking devices
NOTE:
If the electrical apparatus or equipment at the point of isolation is not provided
with suitable means of locking or if SAFETY PADLOCKS cannot be applied, and
the circuit cannot be isolated by the withdrawal of fuses or links, then other
suitable precautions shall be taken to avoid DANGER to person whilst working
on the circuit.
Proving of Isolations
Whenever the isolation is complete, the isolator must prove that the area within
the isolation is fully isolated from pressure/electricity. This can normally be
done by checks at vent valves or by the checks to prove electrical equipment
dead with an APPROVED voltage testing device suitable for the rated voltage of
the circuit. The voltage testing device shall be checked before and after use to
check it is working correctly.
PE-O-HS-STD-001-02-E
Revision: 02
Page 38 of 81
Regulation Class
Document Class
Standard
Annex 6
Check the Permit Location Board to ensure that the removal of the isolation
will not affect the isolation boundary for any other work.
When satisfied that the work is complete and that it is safe to de-isolate, do
the de-isolation (or ask a competent person to do it). If any of the
valves/switches etc. are part of another isolation boundary, the tag for the
current de-isolation is to be removed, but other tags are to be left in place.
The securing device must not be removed until all isolations on the
valve/switch have been removed.
When the isolation has been removed, compare the tags from the
valves/switches with those attached to the Permit/Isolation Certificate to
ensure the De-Isolation is complete. Then remove the marker and
description of the isolation from the Permit Location Board.
Page 39 of 81
Regulation Class
Document Class
Standard
Annex 6
Permit must include a test, and the Permit must be suspended before testing
starts.
When the test is to start, the Affected Area Responsible is to de-isolate, using
the procedure, except that he is not to sign the Permit/Isolation Certificate until
the test is complete and the equipment is finally de-isolated. If a test shows that
more work is needed, and the equipment is to be re-isolated, the Permit is to be
Re-Validated for the work to be done.
This process is not to be used for Hydrostatic or Pneumatic Testing.
Transfer of Isolations between Permits
If a Permit reaches the end of its Validity Period and work is to continue under a
new Permit, the Isolations can be transferred between the two Permits. Box 6b
of the old Permit is to be signed by the Affected Area Responsible to show that
work is not complete.
If the isolation was authorised on a Mechanical Isolation Certificate or Electrical
Isolation Certificate, the number of the new Permit is to be written in the Work
continuing on Permit No. Box on the Certificate. This transfer can only be done
3 times. The Isolation Certificate number is to be written in Box 6b of the old
Permit. The Isolation Certificate is then attached to the new Permit.
Extended Period Isolations
Authorization of EPIs
The procedure for authorising and documenting EPIs is as follows:
a) Any Permits for work related to the isolation are to be Closed by the Affected
Area
Responsible.
The Affected Area Responsible is to sign Box 6b of the Permit and tick the
appropriate box if the work is complete or not, writing the Isolation
Certificate number in the space after Isolation retained under Cert. No.
PE-O-HS-STD-001-02-E
Revision: 02
Page 40 of 81
Regulation Class
Document Class
Standard
Annex 6
A Confined Space Entry Certificate is valid for no more than 1 working shift period. If
the work takes longer than this, a new certificate is to be raised for each new shift. The
first Certificate to be authorised by the Approver, but later ones can be authorised by the
Affected Area Responsible, with all precautions from the previous ones.
A brief description of the use of the Confined Space Entry Certificate is given
below:
BOX 1 APPLICATION
Box 1 is to be completed by the Performer, giving the details of the job and the
number of the Permit for it.
BOX 2 - SAFETY PRECAUTIONS REQUIRED
The Approver check the measures considered by the Performer and he can
add in box Necessary supplementary measures he consider
PE-O-HS-STD-001-02-E
Revision: 02
Page 41 of 81
Regulation Class
Document Class
Standard
Annex 6
Immediately before first entry to the Confined Space each day the Affected Area
Responsible is to test the space for Toxic and Explosive Gases/Vapours and for
Oxygen Concentration. Further testing during the work can be done by any
Authorised Gas Tester.
The Affected Area Responsible must be competent and authorised in order to
perform gas testing, otherwise another authorised person must do it
The results of these tests are to be written in Box 3 of the Certificate.
BOX 4 AUTHORISATION
Once he is satisfied that the Confined Space is safe to enter (check boxes 2 and
3), the Approver/ Affected Area Responsible is to complete Box 4 to define the
period for which the Certificate is valid, and then authorise the entry to proceed.
Digging/Excavation Certificate
The Certificate excavations (digging) shall be used for digging in any location within
or in the vicinity of facilities.
PE-O-HS-STD-001-02-E
Revision: 02
Page 42 of 81
Regulation Class
Document Class
Standard
Annex 7
Certificate No:
Exact Location
Post
Worksite
Permit No.
Contractor/Dept
Equipment
Work Continuing
Signed
Date
on Permit No.
1
2
3
Applied Safety
Padlocks Nos
4. ISOLATION
5. DE-ISOLATION
Name
Name
Signed
Time
Date
Signed
Position
Signed
Position
Time
Date
Time
Name
Date
Signed
Position
Time
Date
Name
Name
Position
Signed
Time
PE-O-HS-STD-001-02-E
Revision: 02
Date
Signed
Page 43 of 81
Position
Time
Date
Regulation Class
Document Class
Standard
Annex 8
Certificate No:
Exact Location
Post
Worksite
Permit No.
Contractor/Dept
Equipment
Work Continuing
Date
on Permit No.
Signed
OPEN
SHUT
SPADE
4. ISOLATION
Name
Position
Time
Name
Date
Signed
Name
Position
Time
Date
Signed
D/CONN
5. DE-ISOLATION
Signed
BLIND
Position
Time
Name
Date
Signed
Position
Time
Date
Name
Name
Signed
Position
Time
PE-O-HS-STD-001-02-E
Revision: 02
Date
Signed
Page 44 of 81
Position
Time
Date
Regulation Class
Document Class
Standard
Annex 9
Num ber:
Date:
WHITE - w orksite ;
YELLOW - Affected Area Responsible (Permit Rack)
Location:..
Function
Worksite:..
Equipment / Space to be entered
Contractor
Signature
to be checked by Affected Area Responsible and/or
Approver)
Required
YES
NO
Checked
The above equipment has been isolated from all source of dangerous liquids, gases and fumes by insertion
of spades or by removing a section of pipew ork and blanking open ends of the circuit
Equipment has been isolated from all sources of electrical and mechanical energy
Isolation Certificates are attached Mechanical
Electrical
Equipment freed of all dangerous materials. All flushing/inert gas purging complete, all liquids drained out
Equipment surrounding area checked and safe from hazards arising from other w ork/operations
Life lines, breathing apparatus and resuscitation equipment available
Adequate access and escape routes are provided
Procedures and rescue plans established and discussed w ith the Performer, personnel entering confined
space and standby personnel
Standby personnel appointed
Name(s):
Natural ventilaton
Mechanical ventilation
Ex equipment
Safety harness
Breathing apparatus w ith external input
Independent Breathing apparatus
Periodic gas testing
Perform er Nam e (in capital letters) _______________________________________ Function __________________________
Signature :
Date :___________________
Hour :_________
Lim its
20-21% VOL
0% LEL for HOT WORK
4% LEL for COLD WORK WITHOUT BA
10% LEL for COLD WORK WEARING BA
10 ppm
Results
%
%
%
%
ppm
I have tested this space for the above gases, w ith the results show n above
Gas Tester Nam e (capital letters) __________________________
Date :______________________
Signature :
Time ___________________
I certify that the above measures and results indicate that the Confined Space is safe for entering and the intervals specified on the Permit
To Work associated w ith this Certificate are covered
This Certificate is valid until:
Date:
Time:
Approver
Name
Signature:
Date :
Time :
Signature:
Date
Time
PE-O-HS-STD-001-02-E
Revision: 02
Page 45 of 81
Regulation Class
Document Class
Standard
Annex 10
Number:
EXCAVATION/DIGGING CERTIFICATE
Date:
WHITE - worksite ;
YELLOW - Affected Area Responsible (Permit Issue Point)
1. DESCRIPTION OF TASK (by Performer)
Location:
Associated work
Name:
..
permits :
Position
Worksite:..
Equipment used:
Contractor
manual Hot Work Permit No:
altele
Signature
Details of excavation/digging: (Limits of excavation/digging to be shown on as-built drawings attached to this
Certificate)
mecanic
Date:
Approv
er
Name
Signature:
Time :
Signature:
Time
PE-O-HS-STD-001-02-E
Revision: 02
Page 46 of 81
Regulation Class
Document Class
Standard
Annex 11
Number:
RADIOGRAPHY CERTIFICATE
Date:
WHITE - worksite ;
YELLOW - Affected Area Responsible (Permit Issue Point)
1. DESCRIPTION OF TASK (by Performer)
Name:
Associated certificates and work permits :
Location:..
Position
Worksite:..
Start time
Date
Time
Contractor
Finish time
Date
Time
Signature
2. EQUIPMENT AND PERSONNEL REQUIREMENTS (to be checked by Permit Approver)
Radiological Safety Responsible: Name
CNCAN License
No
Equipment used
Type
Survey dosimeter
Type
Individual survey dosimeter
Type
Performing personnel
Valid authorizations
For gamma source: radionuclide, activity,date of measurement:
Phone no
Validity
S/N
S/N
S/N
Calibration date
Calibration date
YES
NO
PE-O-HS-STD-001-02-E
Revision: 02
Performer Signature
Date:
Time:
Signature:
Date
Time :
Signature:
Date
Time :
Page 47 of 81
Regulation Class
Document Class
Standard
Annex 12
Date
Associated Permit no
Location
Worksite
Equipment
I request a gas test for the above mentioned equipment or location
Name
Date
Time
Sign
TIME
Gas
Oxygen %
% LEL
%O2
Sign
Lim its
20-21% VOL
H2S
H2S (ppm)
10 ppm
Name
Date
Time
Sign
Time
Sign
Name
PE-O-HS-STD-001-02-E
Revision: 02
Date
Page 48 of 81
Regulation Class
Document Class
Standard
Annex 13
Page
1/1
Doc ref:
Task/Process Assessed:
Revision:
Location:
Date:
Assessment Team:
Approved by:
RESIDUAL RISK
Risk Level
Population
Affected
Risk Level
Loss
Category/
CONTROL MEASURES
List all Current and Planned Control Measures, taking into Account all
Contributing and Escalating Factors
Severity
INITIAL RISK
Severity
Activity
Steps
Hazard Description
and Worst Case
Consequences with
no Barriers or
Recovery Measures
in Place
Likelihood
HAZARD
Likelihood
Operation:
Categories:
Personnel
Automotive
Environment
Assets
Process
Reputation
Security
Performer has to fill in this JSA and Approver or Affected Area Responsible must verify it ; the JSA has to be accepted only if all are convinced that the correct
risk assessment and barriers are in place for the specific activity.
Once Permit to work signed for acceptance, Performer confirms that all the barriers identified in the associated JSA will be in place and applied.
1.5.
The following can be used as a guideline for develop the key sections of the JSA:
Hazard assessment
The actions (for example isolations) that the Affected Area Responsible must
carry out before work can start.
Actions by Performer
The actions that the Performer must carry out, separated into:
Personal Protective Equipment,
Preparation activities
Precautions during the work.
YES
A JSA is required if for any of the following questions where the answer is
PE-O-HS-STD-001-02-E
Revision: 02
Page 49 of 81
Regulation Class
Document Class
Standard
Annex 13
PE-O-HS-STD-001-02-E
Revision: 02
Page 50 of 81
Regulation Class
Document Class
Standard
Annex 14
Annex no. 14
PE-O-HS-STD-001-02-E
Revision: 02
Page 51 of 81
Regulation Class
Document Class
Standard
Annex 14
The number and locations of Permit Issue Points are at his discretion, but must ensure
an appropriate efficiency of running this PTW system within the Sector by : the
effectiveness and easiness of obtaining the PTW forms by any Performer, of obtaining
the necessary approvals at any time, the real possibility of checking the work sites by
the involved persons etc).
It is recommended that display equipment to be provided at each Permit Issue Point.
This equipment consists of a Permit Location and Isolation Board and a Permit Rack.
The person nominated as potential Approver / Affected Area Responsible must ensure
that the Permit and Isolation Displays are kept up to date to show the current work in
the Area he is responsible for.
The information available on the displays at the Permit Issue Points must show :
a.
current maintenance and engineering work in the area, so that conflict between
activities can be avoided
b.
equipment which is isolated, and not available for operational use
c.
isolation boundaries around equipment which is being worked on, which must be
kept secure to avoid damage to equipment and injury to personnel
The Permit Rack is a rack into which Permits and Isolation Certificates can be placed. It
is divided into vertical sections to separate Permits for different sites (areas). These
vertical sections are divided horizontally to separate Permits at each different status, as
follows:
a)
Planned /
Authorised
b)
c)
Validated:
Suspended:
d)
Extended Period
Isolations:
NOTE : In an exceptional case when a Permit Rack cant be used, similar folders
organizers must be used. In this case, the Approvers must ensure an easy access to the
folders of any interested person, for a correct and effective information.
PE-O-HS-STD-001-02-E
Revision: 02
Page 52 of 81
Regulation Class
Document Class
Standard
Annex 14
Original
1st Copy
2nd Copy
WHITE
YELLOW
GREEN
- Worksite Copy
- Permit issue Point (Rack) Copy
- Approvers Copy
An unique registration number will be given in the Unique Work Permits Register
(Annex 15) and written on the permit.
PE-O-HS-STD-001-02-E
Revision: 02
Page 53 of 81
Regulation Class
Document Class
Standard
Annex 14
The Permit form is divided into Boxes which cover the following parts of the life
cycle of the Permit:
Box
No
Function of Box
1*
2*
3*
4a
4b**
5a
5b
5c
6a
6b
APPLICATION
and
Work
Description
Certificates attached to the Permit
Gas Testing Requirements
AUTHORISATION of the Permit
AUTHORISATION of the Permit
VALIDATION of the Permit
ACCEPTANCE of the Permit
SUSPENSION of the Permit
CLOSURE
CLOSURE
Performer
Performer
Performer
Approver
Civil Fire Brigade
Affected
Area
Responsible
Performer
Performer
Performer
Affected
Area
Responsible
*
- Evidences of information filled in these boxes to be checked by Approver, in
case of Hot Works also by Fire Civil Brigade, and approved as suitable by
signing box 4a, respectively 4b for Hot Works
**
- For Hot Work Permit only
For each activity involving hot work, it is mandatory to nominate at least one
competent person as Fire Watchman. He must be aware of his responsibility and know
the obligations he has during hot work operations. He must be trained on basic
knowledge of fire fighting by a certified person or authority
The fire watchman shall have at least one adequate fire-extinguisher (type and capacity
appropriate for the scope of work) and must know the location of the nearest firefighting equipment.
The fire watchman shall remain at the location of the hot work activity throughout the
works and shall permanently check the adjacent area in order to make sure that the
sparks produced during the works do not produce the ignition of combustible material
and do not affect any other equipment in the area.
If the Performer has no capability to assign this task to a member of the working team,
the Approver must designate one person acting as fire watchman in the area where hot
work activities take place.
PE-O-HS-STD-001-02-E
Revision: 02
Page 54 of 81
PE-O-HS-STD-001-02-E
Revision: 02
4.16.2
4.16.1
Page 55 of 81
4.16.14
4.16.13
Permit
Yes
Work
Finished?
No
4.16.10
Suspend
Permit
Performer
4.16.7 4.16.9
Annex 14
Close
Permit
still
Authorized?
4.16.5
Carry Out
Work
Performer
Standard
Performer /Affected
Area Responsible
No
Yes
Accept
Permit
Re-Validate
Permit
4.16.12
Performer
4.16.5
Accept
Permit
Validate
Permit
4.16.4
Performer
Affected Area
Responsible
Affected Area
Responsible
4.16.4
Prepare
Worksite
Affected Area
Responsible
Document Class
Archive
Permit
Approver
Brief
Work Party
Authorise
Permit
Apply for
Permit
4.16.3
Performer
Approver
Performer
(Permit applicant)
Regulation Class
Regulation Class
Document Class
Standard
Annex 14
4.16.1
4.16.1.1
Departments/Contractors who apply for Permits will obtain the appropriate forms from
Permit Issuing Points.
The Permit is divided into sections, called boxes in this Procedure. Where any box on
a Permit form is not used, it shall have a line drawn through it. Boxes must not be left
blank. Do not write information outside these boxes.
There are a number of tick boxes on the Permit (e.g. Haz Zone 0 ) to indicate area
classification, gas test options etc. These are to be ticked with clear ticks when
required.
Permits must be completed in ball-point pen, to ensure that all copies of the Permit can
be read easily. Pencil must not be used.
NO changes to the wording on a Permit are allowed. If changes are required, a new
Permit must be raised. The only exception is correcting small mistakes, where the
mistake is crossed out and the change initialled by the Performer and Approver.
Additions to the work scope are NOT ALLOWED under any circumstances. If an
addition to the work scope is required, a new Permit is to be raised. It is at the
Approvers discretion whether an additional period of time is required before he
authorises the new Permit and whether the additional work scope requires an
additional site visit.
4.16.1.2
Performer Details
The Performer can be the supervisor, the representative, or the chief of the team doing
the work, or can be the single worker who performs the job. He is the one who pass
through the permit application process.
The Performer will fill in the Boxes 1-3 of the Permit by entering the following
information into the appropriate boxes:
Application and Work Description
In Box 1 of the Permit, write:
the location of the Work (e.g. Compressor Station.), the Worksite (the exact place
in the Facility where the work is to be done; e.g. Compressor no.) and the exact
equipment which is subject of the work (e.g. Inlet valve on cylinder no..). In case
the work is to be done outside the boundaries of a facility (eg: work on pipelines
PE-O-HS-STD-001-02-E
Revision: 02
Page 56 of 81
Regulation Class
Document Class
Standard
Annex 14
between facilities or between well and park, or works at well sites), the Location will
be the name of the facility to whom the worksite belongs, or the downstream facility
performers Name and signature
for Contractors, the name of the Company
the number of the Work Order ; this is very important, as it is used to link the permit
to the daily working schedule
the Hazardous Area Classification of the worksite (advice from the Approver/ Affected
Area Responsible)
whether the work involves working with naturally occurring radioactive materials
(NORM) or in a NORM Restricted Area
whether the work is in an H2S Facility (advice from the Affected Area Responsible) ;
and, if known, the PPM (parts per million) figure of the maximum expected level
the planned time for the work including preparation
whether vehicle access to a Process Facility will be required
the type of the area where the work is to be done
The numbers of any Permits for other parts of the work (in the Associated Permit
Numbers box). This will include any previous Permit for the work.
a precise description of the work to be done, including the equipment to be worked
on and tools to be used
any special equipment to be used, especially if it may introduce a hazard
the appointed fire watchman for the Hot Works ; this person must accept the task by
signing and filling the date and time ; if the Performer cannot appoint one, the
Approver must appoint a competent person
In case of Hot Works, two more sets of information shall be provided:
The Work Description must include enough information to allow Approvers to identify
the hazards involved in the work and the Precautions necessary to control them.
NOTE : General description of the work will not be accepted (eg: Compressor
repair, or Well. roll-out). The description must highlight the direct and effective
intervention over the above mentioned equipment (Check inlet valve on cilinder
no., or Replace coupling between driving engine and centrifugal pump..)
A single Permit must not be used for a sequence of separate equipment where each
equipment will be shut down, worked on and put back into service whilst the other
equipment remain in service. This is to avoid confusion over isolations. The only
exception allowed is work on electrical or electronic systems, such as lighting, which
can be isolated and worked on in sequence.
PE-O-HS-STD-001-02-E
Revision: 02
Page 57 of 81
Regulation Class
Document Class
Standard
Annex 14
NOTE : When a Permit is written for fault finding, it is important that the work
description does not allow the work party to proceed with repair activities without
the risks involved being assessed. The work description shall include:
A description of the fault to be investigated.
A description of the types of fault finding work that may be done.
The point at which work should stop, so that a further Permit for the repair can
be raised.
4.16.1.3
Box 2 Certificates
4.16.1.4
PE-O-HS-STD-001-02-E
Revision: 02
Page 58 of 81
Regulation Class
Document Class
Standard
Annex 14
NOTE : The requests regarding gas testing will be checked by the Approver. The Gas
Test Results will be recorded separate in the Gas Test Record form (for Confined
Space Entry will be recorded in the respective Certificate).
4.16.2 Authorisation and Co-ordination Box 4
4.16.2.1
When Boxes 1-3 of the Permit have been filled in, the Performer is to take the
Permit and Certificates to the appropriate Approver for Authorisation.
NOTE : Approvers require notice of a Permit to allow time to discuss the work
and, for higher risk work, for examination of the worksite. For this reason, a
good work planning is required (it is recommended that the work schedule to
be prepared one day in advance). The Approver may allow shorter notice
periods for essential unplanned work.
Before Authorising the Permit, the Approver must check that:
Page 59 of 81
Regulation Class
Document Class
Standard
Annex 14
For Hot Work Permits, the Approver may consider to examine the worksite, normally
with the Performer, to ensure the work is fully described on the Permit and that all
safety aspects have been considered. For Cold Work Permits the Approver need not
examine the worksite unless he considers this necessary.
Once he is satisfied that the Permit is correctly written for the work, the Approver is to
set an Authorisation period for the Permit and to fill the box 4 (for cold work permits),
respectively 4a (for hot work permits).
The Approver is then to write his name and position, and sign and date Box 4.
In case of Hot Works, the Performer is to take the Permit and Certificates to the
appropriate Civil Fire Brigade for Authorisation. The Authorisation process is identical
as described above.
For Hot Work permits, the Approver will fill and sign box 4a, the Civil Fire Brigade will
fill and sign box 4b. Both authorisations are mandatory.
Once a Permit has been Authorised by the Approver, the only changes that can be
made to it are the addition of new controls to the JSA. These changes are only to be
made by the Approver or the Affected Area Responsible. Deletion of controls is not
allowed. If any changes to controls are made, the Performer is to be informed.
The Performer is then responsible for ensuring that the rest of the work team, or
himself, is fully briefed on the work content, precautions required and the requirements
of the JSA.
NOTE : NO ONE MAY AUTHORISE A PERMIT FOR WORK THAT THEY WILL DO
THEMSELVES
4.16.2.2
The total workload at each location will be reviewed at the daily planning meeting for
the Sector. This shall identify and eliminate any possible conflict situations. However, it
is most important that the Approver looks in detail at the Permit requests for the
following day, and eliminates any safety confliction situation.
Each day the Approver is to review the work for each location for the following day,
using:
Lists from Performers showing which Permits have not been completed and will be
required the following day.
PE-O-HS-STD-001-02-E
Revision: 02
Page 60 of 81
Regulation Class
Document Class
Standard
Annex 14
The Approver is to identify any potential conflicts between activities, and decide which
Permits may be validated for work the following day.
The Approver is to re-check the list of Validated Permits for each location before start
of work on the following day, in that situation when the planning process allows the
preparation of the works and, respectively, the issuing, authorisation and validation in
advance of the respective permits
Hot Work Permits in a Hazardous Area will only be validated if the Affected Area
Responsible will remain at the worksite when work is underway.
There will be a further check for confliction situations by the Affected Area
Responsible, when Permits are validated. (See section 4.16.4)
4.16.3 Briefing of the Performer (work party)
Permits must be Validated by the Affected Area Responsible, before work can start.
Before Validating a Permit, the Affected Area Responsible must carry out a check for
safety conflicts which may occur between activities. To do this he must:
Check that there are no other conflicting activities, which may be operational,
covered by other Permits, or covered by Handover Certificates etc.
When the Affected Area Responsible is sure that the work will not cause a conflict, he
is to convince himself that the worksite is safe for the work. To do this, he must:
Where required, examine the worksite with the Performer to ensure that the
Performer preparations, as required by the JSA, have been completed to make the
worksite safe for work to start.
PE-O-HS-STD-001-02-E
Revision: 02
Page 61 of 81
Regulation Class
Document Class
Standard
Annex 14
If an isolation is required and has not already been completed, do the Isolation,
and complete the Isolation Certificate/Box 2 of the Permit as appropriate.
If a Gas Test is required, do this immediately prior to Validation of the Permit, with
results recorded in Gas Test Record form.
Ensure that the Performer understands the work and the precautions which are
required.
When satisfied that it is safe for work to start, the Affected Area Responsible is to
Validate the Permit.
Hot Work Permits should only be Validated if the Affected Area Responsible will remain
in the area of the work when work is underway.
4.16.5 Acceptance by the Performer - Box 5b
When satisfied that the worksite is safe, the Performer is to sign Box 5b of the Permit in
the presence of the Affected Area Responsible.
NOTE : The Performer cannot be the same person with Affected Area Responsible
The Performer has the right to refuse to sign the Permit Acceptance until he is satisfied
that the worksite is safe.
By signing the Permit the Performer is agreeing to the following:
That the JSA will be complied with, by understanding and applying of the control
measures proposed by himself, but also the acceptance and applying the
supplementary control measures, proposed by the Approver or the Affected Area
Responsible, whichever the Performer is responsible and competent to apply.
NOTE : The control measures for which the Performer is not responsible and/or
competent to apply (egg: electrical isolation, free access-evacuation ways, initial gas
detection etc) must be applied by the Affected Area Responsible and the Performer
must ensure they were applied. All considered measures must be filled in the JSA
and/or the Permit
That the Permit will always be displayed at the worksite when work is in progress.
That no work will be done unless the Affected Area Responsible has validated the
Permit.
PE-O-HS-STD-001-02-E
Revision: 02
Page 62 of 81
Regulation Class
Document Class
Standard
Annex 14
The Performers Permit acceptance signature must appear on both the Worksite and
Permit Rack copies of the Permit. This means that:
When work is in a facility, the Affected Area Responsible shall put the Worksite and
Permit Rack copies (white and yellow) of the Permit together for the Performer to
sign.
Where the worksite is remote from the Permit Issue Point, and a worksite
examination before work starts is required, the Affected Area Responsible is to take
the Worksite and Permit Rack copies (white and yellow) of the Permit to the
worksite where the Performer can sign them.
Where the worksite is remote from the Permit Issue Point, and a worksite
examination before work starts is NOT required, the Performer is to sign the
YELLOW copy of the Permit before leaving the Permit Issue Point, to indicate that
he intends to start work. He is to sign the worksite copy (WHITE) of the Permit at
the worksite, when he is convinced that it is safe for work to start
The Affected Area Responsibles verbal approval is to be obtained before one
Performer hands over responsibility for a Valid Permit to another Performer. The new
Performer is to accept the Permit requirements by signing the next line in box 5b.
When remote sites are involved, the new Performer is to contact the Affected Area
Responsible for verbal approval and sign the worksite copy (white), the Affected Area
Responsible is then to write the name of the new Performer in box 5b of the Permit
Rack copy (yellow).
During the handover briefing, the outgoing Performer shall brief the new Performer on
the topics suggested in Section 4.16.7 (briefing of the work party).
No work can take place under the Permit until:
The Permit has been Validated.
The Performer has signed to accept it.
The Permit is displayed at the Worksite.
4.16.6 Actions after Validation
When the Permit has been signed by both the Affected Area Responsible and
Performer, the top copy (WHITE, worksite) should be given to the Performer, together
with the correspondent copy (WHITE, worksite) of any associated Certificates. The
Performer is responsible for ensuring that the Permit and JSA are placed in a
protective wallet, displayed in a safe position at the Worksite where it can be seen
clearly, and is kept there whilst work is being done.
NOTE : No work is to be done unless a validated Permit is clearly displayed at the
worksite.
Work may now start, following briefing of the workforce (see Section 4.16.7 below).
PE-O-HS-STD-001-02-E
Revision: 02
Page 63 of 81
Regulation Class
Document Class
Standard
Annex 14
The Affected Area Responsible is to place the YELLOW copy of the Permit, together
with all copies of any associated Certificates in the VALIDATED section of the Permit
Rack.
4.16.7 Briefing the Work Party (working team) the Toolbox Talk
Toolbox talks are short briefings given by the Performer to all who are
involved in the work controlled by a permit. These briefings are given before the
work commences and during the work time, as is necessary. The Performer is to
ensure that himself and/or the work team is fully aware of the Work Content and
Precautions to be taken.
Toolbox talks:
PE-O-HS-STD-001-02-E
Revision: 02
Page 64 of 81
Regulation Class
Document Class
Standard
Annex 14
Throughout the work, the Performer is responsible for ensuring that all members of the
work team comply with the requirements of the Permit. The Performer must remain at,
or in close visual contact with the worksite at all times.
Note that the JSA is the most useful tool to ensure work is carried out safely at the
work location. It needs to be applied diligently at every stage of the job.
4.16.9 Gas Test Record
Gas Testing and Monitoring are to be done as required by Box 3 of the Permit.
Any Authorised Gas Tester may carry out gas tests required during the day.
The results of the Gas Test are to be recorded in the Gas Test Record form, except
for Confined Space results, which are to be recorded on the Confined Space
Entry Certificate.
Gas Tests are to be done before work starts, and at the frequency stated on the
Permit. An extra test is required before work re-starts, if the worksite is left
unattended for more than one hour.
In addition to Gas Testing, continuous monitoring may be required. This will
have been specified in Box 3 of the Permit. A Performer may supervise work for
which continuous gas monitoring is required without being licensed as a Gas
Tester. He must, however, have been trained in the use of the gas detector.
If gas or other hazardous atmosphere is found at any stage, work must stop. The
Permit is to be suspended as described in Section 4.16.10, below. The Approver
must be informed immediately.
Page 65 of 81
Regulation Class
Document Class
Standard
Annex 14
Check that the Worksite and equipment affected by the work have been left in a
safe condition.
Sign Box 5c of the WHITE copy of the Permit to confirm that work has been
suspended.
Take the Permit to the Permit Issue Point, sign the YELLOW copy and give it to the
Affected Area Responsible who will keep it there until ready to re-start work.
If work is not complete, but cannot re-start until after the Permit Authorisation period
has expired, the Permit is to be Closed by Affected Area Responsible, by signing it off
in Box 6b - Work Not Completed. Isolations may be retained under the Extended
Period Isolation procedure described in Section 4.18.11.
It is not necessary/mandatory to suspend a Permit before it is Closed.
Once a Permit has been SUSPENDED no work covered by that Permit may be done
until the Permit has been Re-Validated as described in Section 4.16.12, below.
Worksite and Permit Issue Point copies of all suspended Permits are to be kept in the
SUSPENDED section of the Permit Rack.
4.16.10.3 Stoppage and Re-Starting of Work following an Alarm in a Facility
Stopping Work
In the event of an emergency situations, or alarm, at the worksite, all PTW in effect are
to be considered as no longer validated,
All work is to stop immediately in such situations in any facility. Each Performer is to
ensure that his worksites have been left in a safe condition, without endangering the
lives of personnel, and is then to evacuate the site as quickly as possible.
PE-O-HS-STD-001-02-E
Revision: 02
Page 66 of 81
Regulation Class
Document Class
Standard
Annex 14
If the unplanned stoppage of work may cause a dangerous condition, the work party is
to take the emergency actions stated on the JSA.
Re-Starting Work
If the Alarm was not caused by an actual alarm condition, the Affected Area
Responsible may verbally re-authorise each Performer to re-start work once the
all clear signal is given.
Where the Alarm was caused by an actual alarm condition, the Affected
Area Responsible must revalidate all permits. A further Worksite examination is
required if the problem which caused the alarm could have changed conditions
at the worksite.
appropriate, the permit must be closed by the Affected Area Responsible and a
new permit to be issued
4.16.11 Changeover of Personnel
Within a Process Facility, the new Performer must obtain the Affected Area
Responsible verbal approval to change and sign Box 5b of both copies
(WHITE and YELLOW) of the permit.
At remote locations, where he is unable to contact the Affected Area
Responsible, he must sign the worksite copy (WHITE) when he takes over
and the YELLOW copy when he returns to the Permit Issue Point. The
outgoing Performer is not to leave the worksite until he has fully briefed
the new Performer and the new Performer has signed to accept the Permit
in his presence.
PE-O-HS-STD-001-02-E
Revision: 02
Page 67 of 81
Regulation Class
Document Class
Standard
Annex 14
4.16.12
The Work has not been completed, but a new Permit is required.
The Work is to be suspended until a date after the Permit Authorisation Period,
e.g. when spares will be required to repair an item of equipment.
The Work to be done is found to be different from the Work Description on the
Permit - a new Permit must then be obtained for the work.
PE-O-HS-STD-001-02-E
Revision: 02
Page 68 of 81
Regulation Class
Document Class
Standard
Annex 14
Box 6a of the WHITE and YELLOW copies of the Permit is to be signed by the
Performer if the work is complete, to confirm that the work has been properly done.
Box 6a of the WHITE and YELLOW copies of the Permit is to be signed by the
Performer if the work has stopped, but is not complete.
A signature in the box confirms that the worksite has been left in a clean and safe
condition, with all tools and equipment removed.
When Box 6a has been signed, no further work may take place under that Permit.
Box 6b PERMIT CLOSURE BY AFFECTED AREA RESPONSIBLE
Box 6b is to be used where:
the Work is to be suspended until a date after the Permit Authorisation Period.
Where the work is in a Process Facility, the Affected Area Responsible shall do a
Worksite inspection and sign in Box 6b, to ensure the Worksite has been left in a clean
and safe condition.
When he is satisfied that the Worksite has been left in a safe condition the Affected
Area Responsible is to complete and sign Box 6b of the WHITE and YELLOW copies of
the Permit.
Before signing Box 6b, Isolations must be removed or converted to an Extended Period
Isolation.
If the Isolations are removed, the Isolation Certificate must be signed off by the
Affected Area Responsible to confirm that ALL Isolations have been removed.
For Isolations left in place, the Isolation Certificate must be converted to an Extended
Period Isolation (EPI) by completing Box 6 of the Isolation Certificate. The Affected
Area Responsible is to write all the details of the Isolation on the Certificate, and
convert it to an EPI by filling in Box 6 of the Isolation Certificate. The number of the EPI
Isolation Certificate is to be written in Box 6b of the Permit (Isolation retained under
certificate no.)
When Box 6b has been signed, no further work may take place under that Permit.
PE-O-HS-STD-001-02-E
Revision: 02
Page 69 of 81
Regulation Class
Document Class
Standard
Annex 14
On completion of work, the WHITE and YELLOW copies of the permit and any
additional Certificate shall be gathered and returned to the Approver.
The copies must be signed off by the Performer and the Affected Area
Responsible, to indicate completion, subject to worksite inspection.
All other parties involved (eg: those who made aware of the work), shall be
informed about work completion.
The Approver must ensure that Worksite (WHITE) copies of all Closed Permits
and associated documents (JSA, Certificates etc.), all completely signed off, are
kept in an archive file for a period of six months.
Other copies of the documents are to be disposed off.
There is to be a separate file for each month, with the documents sorted by
Closing date.
1. PERMIT PROCESSING PROCEDURE
The following steps summarise the Permit Processing Procedure described in
this Section, together with the use of the Permit Issue Point Facility.
1.
APPLICATION
The
Performer Subject of action:
will:
EXAMINE
Worksite to check work and identify hazards (except for
Cold Work Permit at remote sites with no risk from
overhead lines, buried services etc)
COMPLETE
Performer's parts of the Permit.
COMPLETE
Performer's parts of PTW System Certificates (Isolation,
etc.) and attach to Permit.
PRODUCE
JSA and attach it to Permit.
GIVE
Completed documents to Approver.
2. PLANNED PERMITS
The
Approver Subject of action:
will:
CHECK
Performers details and dates proposed for work.
ENTER
The Permit unique number into the Unique Work
Permits Register and mark as Planned
EXAMINE
Worksite with Performer, if required (Hot Work), to
confirm protection and precautions are suitable for the
conditions.
PE-O-HS-STD-001-02-E
Revision: 02
Page 70 of 81
Regulation Class
Document Class
Standard
Annex 14
3. AUTHORISATION
The
Approver Subject of action:
will:
CHECK
Correct certificates are attached.
Permit and Certificate boxes are correctly completed.
If another custodian is affected, if so, to be formally
informed about the scope of work
JSA is correct for the work.
IDENTIFY
If an Isolation is required and nominate competent
person to identify isolation points.
SET
Authorisation period for Permit.
SIGN
Permit and Certificates to Authorise them.
GIVE
Permit and certificate copies to Performer (keep GREEN
copy in file).
CHANGE
Permit status in Unique Work Permits Register to
Authorised, having checked for possible conflicts with
other work.
NOTE : In case of Hot Work, the Civil Fire Brigade will perform the same
authorisation process and will sign the Hot Work Permit in box 4b
4.
PREPARATION
The
will:
BRIEF
5. PREPARATION
The Affected Area Subject of action:
Responsible will:
OBTAIN
Permit and Certificates from Performer, place in the
Authorised section of the Permit Rack.
WRITE
Any isolation details and any other supplementary
control measures on the respective Certificates
CHECK
For any conflict if the isolation or work is done. Do not
allow the isolation or work to proceed if there may be
a safety conflict.
DO/CHECK
The isolation, attaching locks and tags (involve
appropriate isolation authorised persons), other
required measures (gas testing, ventilation, other
custodians notification etc)
RETURN
To the Permit Issue Point.
SIGN
The Certificates for completion and checking.
PLACE
Certificates in the Authorised section of the Permit
Rack with the Permit.
MARK
The isolations done on the location board with correct
colour pegs and labels.
PE-O-HS-STD-001-02-E
Revision: 02
Page 71 of 81
Regulation Class
Document Class
Standard
Annex 14
6. VALIDATION
The Affected Area Subject of action:
Responsible will:
CHECK
All isolations are correctly displayed on location board
and signed up on the certificate.
CHECK
For any conflicting work on the Permit Location Board.
INSPECT
The worksite with the Performer (if required) taking the
Permit, the JSA and the Certificates with him.
PREPARE
Worksite as required by JSA.
CHECK
All preparation controls on the JSA are in place,
initialling each control in the Affected Area
Responsible section of the JSA .
SIGN
The Permit to VALIDATE it.
OBTAIN
Performers signature to ACCEPT the Permit and JSA.
GIVE
The WHITE Permit and WHITE certificate copies to the
Performer to display at the worksite.
RETURN
To the Permit Issue Point.
PLACE
The marker on the location board, at the location
where the work is performed.
PLACE
The YELLOW Permit copy in the VALIDATED section of
the Permit Rack together with YELLOW Certificate
copies.
7. BRIEFING
The
Performer Subject of action:
will:
BRIEF
The work party on the job, the hazards, the
precautions and the actions to take in the event of an
emergency.
PLACE
The WHITE Permit copy, JSA and WHITE Certificate
copies in a protective wallet and display it at a
prominent position at the worksite.
NOTE : THE WORK MAY START AFTER THE PERFORMER HAS FULLY BRIEFED
THE WORK TEAM AND DISPLAYED THE PERMIT
8. SUSPENSION
The
Performer Subject of action:
will:
CHECK
The work site has been left clean and safe.
RETURN
The Permit to the Affected Area Responsible at the
Permit Issue Point.
SIGN
Both copies (White & Yellow) of the Permit in Box 5c.
PE-O-HS-STD-001-02-E
Revision: 02
Page 72 of 81
Regulation Class
Document Class
Standard
Annex 14
9. SUSPENSION
The Affected Area Subject of action:
Responsible will:
CHECK
Performer has signed Permit Box 5c and, for work in
Process Facilities, has left his worksite clean and safe.
PLACE
Both Permit copies in the SUSPENDED section of the
Permit Rack.
REMOVE
The marker from the location board.
NOTE : If the job has not finished, the marker should be put where it can be used for
the same Permit again and not used for another Permit.
THE WORK HAS NOW STOPPED IF WORK IS COMPLETE, GO TO STEP 12.
IF THE WORK IS CONTINUING: PERFORMER WILL RETURN FOR NEXT WORKING
PERIOD, GO TO STEP 10
IF PERFORMER HAS CHANGED, A FULL BRIEFING BY PREVIOUS PERFORMER WILL
BE GIVEN
10. RE-VALIDATION
The Affected Area Subject of action:
Responsible will:
CHECK
Any isolations are still correctly displayed on Permit
Location Board.
CHECK
For conflicting activities on Permit Location Board.
TAKE
Both copies of the Permit and certificates from the
rack.
INSPECT
The worksite with the Performer, if required.
CHECK
Requirements of JSA are still being met.
SIGN
Both copies of the Permit Box 5a to RE-VALIDATE it.
OBTAIN
Performer's signature in Box 5b to ACCEPT the Permit.
GIVE
WHITE Permit copy to the Performer to display at the
worksite with the WHITE Isolation Certificate copy.
RETURN
To the Permit Issue Point.
PLACE
The marker at the location of the worksite, on the
Permit location board.
PLACE
YELLOW Permit copy in the VALIDATED section of the
Permit Rack with YELLOW certificate copies.
PE-O-HS-STD-001-02-E
Revision: 02
Page 73 of 81
Regulation Class
Document Class
Standard
Annex 14
11. BRIEFING
The
Performer Subject of action:
will:
BRIEF
The work party on the job, the hazards, the
precautions and the actions to take in the event of an
emergency.
PLACE
The worksite white copies of the Permit and Certificate
and the JSA in the wallet and display it at a clear
position at the worksite.
WHEN THE JOB IS COMPLETED:
12. CLOSURE
The
Performer Subject of action:
will:
CHECK
That the worksite has been left clean and safe.
RETURN
The Permit to the Affected Area Responsible at the
Issue Point
SIGN
Both copies of the Permit in Box 6a to Cancel it
The Affected Area Subject of action:
Responsible will:
CHECK
Performer has signed the correct Permit Box and left
his worksite clean and safe.
PLACE
Permit copies in the SUSPENDED section of the
Permit Rack
REMOVE
The marker from the location board.
CHECK
That it is safe to de-isolate, if applicable, and that this
will not conflict with other isolations.
OBTAIN
Authorisation to de-isolate, if applicable.
DO THE
De-isolation, returning the Lockout/Tagout devices and
checking the worksite is left clean and safe.
SIGN
Isolation Certificate for de-isolation complete.
REMOVE
Isolation pegs and labels from location board.
SIGN
Permit box 6b to Close it.
RETURN
White and Yellow copies of the Permit and certificates
to the Approver for Archive.
PE-O-HS-STD-001-02-E
Revision: 02
Page 74 of 81
Regulation Class
Document Class
Standard
Annex 14
13. ARCHIVE
The Approver will:
ENTER
RETAIN
NOTE : When required, the Gas Test Record is attached accordingly to the WHITE
copy of the associated Permit. The Gas test Record is issued in only one copy,
permanently kept attached to the WHITE copy of the Permit and archived together
with this.
PE-O-HS-STD-001-02-E
Revision: 02
Page 75 of 81
Regulation Class
Document Class
Standard
Annex 15
Date
of
issue
Permit
(Certificate)
type
PE-O-HS-STD-001-02-E
Revision: 02
Permit
(Certificate)
number
Associated
permit no.
Description
of working
task
Page 76 of 81
Start
time
Permit
close
time
Remarks
Regulation Class
Document Class
Standard
Annex 16
Annex no. 16
Usually, on a OMV Petrom facility, the OMV Petrom EP PTW System will
operate, either the works are performed by OMV Petrom or by a Contractor
The Contractors may operate their own PTW System, if it has been formally
approved by OMV Petrom. Before approval, the Contractors system should be
examined by OMV PETROM to ensure it complies with the checklist below. This
situation must be assessed and decided by the OMV Petrom EP HSSE and set up
throughout Contract terms and/or Bridging documents
Is there a list of work requiring Permit, which complies with the list in the
PTW Standard ?
Does the PTW system apply to the Company and all its sub-contractors?
PTW Standard
Are records of all Authorised and Suspended Permits kept on the worksite?
PE-O-HS-STD-001-02-E
Revision: 02
Page 77 of 81
Regulation Class
Document Class
Standard
Annex 16
Does the procedure state what must be done when an unsafe condition
occurs or an alarm sounds?
Is there a signature to confirm that work is complete, and that the worksite
has been left safe?
Training in PTW
The Drilling Contractors shall comply with the requirements for contractors,
as mentioned above in this Section.
If OMV Petrom PTW System is being used, the OMV PETROM Drilling
Supervisor is to act as the Approver and the Rig Manager as the Affected Area
Responsible.
If the OMV PETROM PTW System is being used, the below list of activities
requiring Permit is to apply in addition to relevant activities from the OMV
PETROM PTW EP Standard.
PE-O-HS-STD-001-02-E
Revision: 02
Page 78 of 81
Regulation Class
Document Class
Standard
Annex 16
Maintenance
Work in those confined spaces where there is a risk from toxic fumes or
oxygen depletion.
Killing well / major work on Xmas Tree while Rig rigging up / down.
Grit blasting.
Cement Unit pressure testing other than cement unit related Rig work.
Any pressure tests not part of current rig work (e.g. Pre-test of BOP / test
manifold / choke manifold.), as per equipment manufacturer
recommendations. A pressure testing procedure must be developed and
agreed with OMV Petrom EP
Page 79 of 81
Regulation Class
Document Class
Standard
Annex 16
Agreeing that the work shall be done on the equipment involved at the
proposed time.
The Permit is to be Authorised OMV PETROM Supervisor, who will act as the
Approver, and validated by the Manager of the RIG.
Work Near The Drilling Location
Where the work is done outside the drilling location, but within 100 metres of
the well, the following shall apply:
PE-O-HS-STD-001-02-E
Revision: 02
Page 80 of 81
Regulation Class
Document Class
Standard
Annex 17
A NU SE OPERA !
DO NOT OPERATE !
ISOLATED EQUIPMENT
Izolat de catre :
Isolated by:
NUME ..
NAME
SEMNATURA
....
SIGNATURE
DATA
DATE
Certificat de izolare nr.
Isolation Certificate no.
PE-O-HS-STD-001-02-E
Revision: 02
Page 81 of 81