Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Management (PPM)
Sudhir M Chadha
(Course of 20 lectures)
Uncertainty
sudhir chadha
Beta distribution
Elapsed time
sudhir chadha
sudhir chadha
sudhir chadha
sudhir chadha
Probability of
Meeting the Deadline
The three simplifying
approximations lead to the
probability duration of the
project being approximated
by a normal distribution.
D = Deadline for the
project;
Number of standard
deviations by which d
exceeds p
= (D - p)/p = 1.
P(T d) = Probability that
the project duration (T)
does not exceed the
deadline (D)
06/10/2015
p (Mean)
sudhir chadha
D (Deadline)
Project Duration
(in weeks)
06/10/2015
sudhir chadha
Project Costs
The following terminology is used for project costs:
Baseline costs. The original planned task, resource, or assignment
costs saved as part of a baseline plan;
Current (or scheduled) costs. The calculated costs of tasks, resources,
and assignments in a project plan. As adjustments are made to the
baseline plan (such as assigning or removing resources) , the
recalculated costs are the current costs. The current cost equals the
actual cost plus the remaining cost per task, resource, or assignment.
Actual costs. The costs that have been incurred for tasks, resources or
assignments. After the project incurs actual costs (typically by tracking
actual work), the current cost equals the actual cost plus the
remaining cost per task, resource, or assignment.
Remaining costs. The difference between the current or scheduled
costs and the actual costs for tasks, resources, or assignments.
06/10/2015
sudhir chadha
11
sudhir chadha
12
Cumulative Project
Costs
The top curve is the
schedule of cumulative
project costs when all
activities begin at their
earliest start times.
The bottom curve is the
schedule of project costs
when all activities begin at
their latest start times.
The areas between the
two curves shows the only
feasible week by week
budget that will not delay
project completion.
5,000,000
4,500,000
4,000,000
3,500,000
Feasible region
for project costs
3,000,000
ET project cost
schedule
2,500,000
LT project cost
schedule
2,000,000
1,500,000
1,000,000
500,000
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43
06/10/2015
sudhir chadha
13
Time-Cost Trade-off
sudhir chadha
15
Crashing
The normal point on the
time-cost graph shows the
time (duration) of an activity
when it is performed in the
normal way.
The crash point shows the
time and cost when the
activity is fully crashed; i.e.,
it is fully expedited with no
cost spared to reduce its
duration as much as
possible.
The options for each
activity are to be at its crash
point, its normal point, or
somewhere on the line
segment between these two
points.
06/10/2015
Crash
Crash cost
Normal
Normal cost
Crash time
Normal time
Activity duration
16
Activity Code
A. Excavate
I. Electrics
B. Foundation
C. Rough wall
D. Roof
L
J
8
Start
0
A
2
B
4
C
10
E
4
F
5
J. Wallboard
K. Flooring
N
K
4
6
Finish
0
M
E. E plumbing
F. I plumbing
G. E siding
H
9
L. I painting
M. E fixtures
N. I fixtures
H. E painting
06/10/2015
sudhir chadha
17
Normal
weeks
Crash
weeks
Normal
Cost
Crash Cost
Max Reduction
in Time
$180,000
$280,000
$100,000
320,000
420,000
50,000
10
620,000
860,000
80,000
260,000
340,000
40,000
410,000
570,000
160,000
180,000
260,000
40,000
900,000
1,020,000
40,000
200,000
380,000
60,000
210,000
270,000
30,000
430,000
490,000
30,000
160,000
200,000
40,000
250,000
350,000
50,000
100,000
200,000
100,000
N
06/10/2015
330,000
sudhir510,000
chadha
60,00018
sudhir chadha
19
ABCEFJKN
ABCEFJLN
ABCIJKN
ABCIJLN
Crash
Cost
ABCDGHM
Activity
to
Crash
40 Weeks
31
43
44
41
42
$30,000
40
31
42
43
40
41
30,000
40
31
41
42
39
40
40,000
40
31
40
41
39
40
40,000
40
31
39
40
39
40
sudhir chadha
20
Linear Programming
Restatement of the problem:
Consider the total cost of the project, including the extra cost of crashing
activities. The problem then is to minimize the total cost, subject to the
constraint that the project duration is less than or equal to the time desired by
the project manager.
06/10/2015
sudhir chadha
21
Conclusions
06/10/2015
sudhir chadha
22