Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Management (PPM)
Sudhir M Chadha
(Course of 20 lectures)
06/10/2015
sudhir chadha
Questions
How should ongoing costs be monitored to try
to keep the project within budget?
Are tasks starting and finishing as planned? If
not, what will be the impact on the projects
finish date?
Are resources spending more or less time than
planned to complete tasks?
Are higher-than-anticipated task costs driving
up the overall cost of the project?
06/10/2015
sudhir chadha
Cost variance is not enough, e.g., if the actual cost is below budget at any
date, is it because the project is under budget (good) or behind schedule
(bad)?
Schedule variance is difficult to measure. For example, if there are many
concurrent tasks, some ahead and others behind schedule, how do we
measure variance? If a project is ahead of schedule could it be that the
easier tasks (out of many similar tasks) have been done first? Or many
non-critical tasks are ahead of schedule while critical ones are delayed?
06/10/2015
sudhir chadha
Work
Performed
Actual
Cost
Budgeted
Cost
Cost Variance
06/10/2015
Work
Scheduled
Budgeted
Cost
Convert to
Money units
Schedule Variance
sudhir chadha
06/10/2015
sudhir chadha
06/10/2015
sudhir chadha
06/10/2015
sudhir chadha
B
0% Cost and
schedule
variance
10
A
5
Variance %
Behind schedule
-10
-5
5
-5
10 Ahead of schedule
C
-10
Over budget
06/10/2015
sudhir chadha
06/10/2015
sudhir chadha
Current date
PV
Cost
Schedule variance
EV
Cost variance
AC
Time
06/10/2015
sudhir chadha
10
10
Senior
Management
threshold
5
Variance %
Behind schedule
-10
-5
CVCV
CVCV
-5
15
5
10
Immediate
Management
threshold
Ahead of
schedule
Variance % -10
Over budget
06/10/2015
sudhir chadha
11
sudhir chadha
12
Tips
The work breakdown structure is critical. Each task must be a discrete task
that meets the following criteria:
It must have defined start and finish dates;
The task must produce a tangible outcome with completion criteria that can
be objectively assessed;
Costs must be assigned to the task.
06/10/2015
sudhir chadha
13