Sei sulla pagina 1di 12

Earthing Calculations

for

Harris 6.6kV Distribution Substation


(Norbert Dentressangle Logistics)
Report Number

ESL0412-R01

Client:
Client Contact:

ENWL
Paul Griffiths

Author:

______________________
David Reed
Engineer

Contact Details:

ERA TECHNOLOGY
T CANOL
CLUN AVENUE
PONTYCLUN
SOUTH WALES
CF72 9AG
Tel:
+44 (0)1443 239503
Fax:
+44 (0)1443 231185
Email: enquiries@era.co.uk

David.Reed@era.co.uk
+44 (0)1443 239503

ERA Technology is a trading name of


Earthing Solutions Ltd

UTILITIES VENDOR DATABASE


Achilles Supplier Number: 061760

RTEMP01 ISSUE 13 17/07/14

3 October 2014

Earthing Calculations Report

Approved By:

Harris 6.6kV Distribution Substation

______________________
Mayur Gaglani
Principal Engineering Consultant

Revision

Date

Prepared

Approved

Notes

17/09/14

DR

MG

Original Issue

03/10/14

DR

MG

Updated fault Levels Provided

B
C
Earthing Solutions Limited 2014
All Rights Reserved
This report and associated drawing(s) (where applicable) have been produced
by Earthing Solutions Ltd and may not be reproduced or distributed outside of the
recipients organisation (either in part or in full) without permission.
If received electronically, the recipient is permitted to make such copies as are
necessary to: view the document on a computer system; comply with a
reasonable corporate computer data protection and back-up policy and
produce one paper copy for personal use.

The calculations contained within this report are based on information supplied
by the client and/or measurements carried out by Earthing Solutions Ltd (unless
otherwise stated). It is the responsibility of the client to ensure that any
rectification or installation work are carried out as per recommendations
contained within this report and associated drawing(s) (where applicable), and in
compliance with the relevant Distribution Network Operator (DNO) policies and
safety documents. Earthing Solutions Ltd shall not be liable for any incidents or
costs incurred due to inaccurate information or incorrect installation.

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page i

3 October 2014

Earthing Calculations Report

Harris 6.6kV Distribution Substation

Contents
Page No.
Summary of Information

Technical Data

Main Report

1.

Introduction

2.

Soil Resistivity

3.

Existing Overall Earth Value

4.

Fault Current Distribution

5.

Earth Potential Rise (EPR)

6.

Touch Voltages

7.

Recommendations

8.

Applicable Standards

Appendix A - Measurement Locations

Appendix B FOP Measurement 2 Data

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page ii

3 October 2014

Earthing Calculations Report

Harris 6.6kV Distribution Substation

Summary of Information
Technical Data
Soil Resistivity Model
Layer

Resistivity (m)

Thickness (m)

630

2.0

28

7.1

15

6.6

167

Earth Resistance
System Elements

Resistance ()

Determination Method

Existing Overall Earthing System

0.112

Measured

Earth Fault Current


Voltage Level (kV)

Total Fault Current (A)

Ground Return Current (A)

6.6

1123

420

Earth Potential Rise


Voltage Level (kV)

EPR (V)

Status

6.6

47

COLD

Overall Classification

COLD

Touch Voltages - Compliance with BS EN 50522 Limits


Voltage Level (kV)

Complies with BS EN 50522 Limits


on Chippings

Complies with BS EN 50522 Limits


on Soil

6.6

YES

YES

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page 1

3 October 2014

Earthing Calculations Report

Harris 6.6kV Distribution Substation

Main Report
1.

Introduction

ENWL have asked for some earthing calculations at Norbert Dentressangle Logistics (SJ 79852
95974) to be carried out. This is required as part of an HSE request. The work carried out is
summarised below.

Carry out soil resistivity soundings using the Wenner Method and derive a representative soil
resistivity model.

Carry out a fall of potential (FOP) earth resistance measurement from the existing main
intake substation (Harris 6.6kV Distribution Substation).

Estimate the ground return current for phase to earth faults at the substation and calculate
the Earth Potential Rise (EPR).

Check that the touch voltages are below BS EN 50522 permitted limits.

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page 2

3 October 2014

2.

Earthing Calculations Report

Harris 6.6kV Distribution Substation

Soil Resistivity

Four soil resistivity soundings were carried out on 10th September 2014 using the Wenner Method
and a Megger DET 2/2 instrument. The measurement locations are shown in Appendix A. The
measurement data are shown in Figure 2.1 and Table 2.1 below. The soil resistivity model derived
is shown on the Summary of Information page.

Apparent Resistivity (.m)

1000.0

100.0

SR1
SR2
SR3
SR4
Model

10.0

1.0
1.0

10.0

100.0

Wenner Spacing (m)

Figure 2.1: Soil Resistivity Data and Model Curve


SR1

SR2

SR3

SR4

Wenner
Spacing (m)

Measured
Resistance
()

Apparent
Resistivity
(m)

Measured
Resistance
()

Apparent
Resistivity
(m)

Measured
Resistance
()

Apparent
Resistivity
(m)

Measured
Resistance
()

Apparent
Resistivity
(m)

1.0

19.900

125.04

127.500

801.11

7.480

47.00

7.220

45.36

1.5

14.430

136.00

81.700

770.00

4.640

43.73

3.620

34.12

2.0

9.840

123.65

51.800

650.94

2.520

31.67

2.550

32.04

3.0

5.670

106.88

17.720

334.01

1.329

25.05

1.273

24.00

4.5

3.500

98.96

7.290

206.12

1.057

29.89

0.921

26.04

6.0

1.950

73.51

3.200

120.64

0.837

31.55

0.710

26.77

9.0

0.610

34.49

0.543

30.71

0.525

29.69

0.491

27.77

13.5

0.270

22.90

0.226

19.17

0.352

29.86

0.361

30.62

18.0

0.253

28.61

0.280

31.67

0.281

31.78

27.0

0.080

13.57

0.208

35.29

0.196

33.25

36.0

0.194

43.88

0.161

36.42

54.0

0.288

97.72

0.202

68.54

Table 2.1: Soil Resistivity Data

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page 3

3 October 2014

3.

Earthing Calculations Report

Harris 6.6kV Distribution Substation

Existing Overall Earth Value

An earth resistance measurement was carried out on 10th September 2014 using the fall of
potential method and a Megger DET 2/2 instrument with the remote current electrode located
100m away was carried out from the main intake substation. Due to the short traverse of the test,
a second test was carried out along a different route to verify the results. The measurement data
for the first FOP test route is shown in Figure 3.1 and Table 3.1 below, along with the interpreted
earth resistance in Table 3.2. The measurement data for the second FOP test route is shown in
Appendix B. The measurement routes are shown in Appendix A.
0.600

0.500

Measured Resistance ()

0.400

0.300

0.200

0.100

0.000
0

10

20

30

40

50

60

70

80

90

100

Potential Probe Position (m)

Figure 3.1: Fall of Potential Curve


Distance to Current Probe (m):
Potential Probe Position

100

Measured
Resistance ()

(m)

(% of Distance to
Current Probe)

90

90.0

0.487

80

80.0

0.180

70

70.0

0.129

60

60.0

0.109

50

50.0

0.098

40

40.0

0.085

30

30.0

0.062

20

20.0

0.062

10

10.0

0.052

Table 3.1: Fall of Potential Measurement Data


System Elements

Resistance ()

Interpretation Method

Harris Distribution Substation


Overall Earthing System

0.112

'61.8% Rule'

Table 3.2: Interpreted Measured Resistance

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page 4

3 October 2014

4.

Earthing Calculations Report

Harris 6.6kV Distribution Substation

Fault Current Distribution

4.1 Fault Current


The earth fault level and fault clearance time is 1.123kA and 1s respectively. Based upon this fault
clearance time, the 430V ITU threshold limit is applicable.
The 6.6kV supply arrangement from the source Primary 33/6.6kV substation (Chester Road) is via a
continuous underground cable. For earth faults at the main intake substation, there will be a path
back to source, via the supply cable sheaths and earth electrode connections. Current, which
returns using a metallic route such as the cable sheath, will not contribute significantly to the
consequential EPR at the site. Only the component, which returns through the soil, will do this. The
split of current between the ground and cable sheaths has been calculated using industry
standard routines and the methodology described ENA ER S34.
Table 4.1: Fault Current
6.6kV Fault

5.

Total Fault Current (A)

1123

Proportion of Current following


Ground Return Path (%)

<37.4

Ground Return Current (A)

<420

Earth Potential Rise (EPR)


Table 5.1: Calculated EPR
6.6kV Fault
Ground Return Current (A)

420

Earth Resistance ()

0.112

Earth Potential Rise (V)

47

ITU Voltage Limit (V)

430

Site Classification

COLD

ENWL have confirmed that Chester Road substation is classified as a cold site, so there will be no
transfer potential hazard and therefore Harris Distribution substation will be classified as cold.

6.

Touch Voltages

Assuming that the fault clearance time is 1s, the allowable Touch Voltage limits in accordance
with BS EN 50522 are shown in Table 6.1:
Table 6.1 Maximum Touch Voltages and Compliance with BS EN 50522 Limits
Clearance
Time (s)
1

Limit on Chippings
(V)
298

Limit on Soil
(V)
233

As the maximum calculated EPR (47V) is below the permitted touch voltage limits (233V on soil,
298V on stone chippings), then the distribution substation and the rest of the site can be deemed
safe.

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page 5

3 October 2014

7.

Earthing Calculations Report

Harris 6.6kV Distribution Substation

Recommendations
Action

It is not known if the low earth value at the site is due to the in ground copper installed or the
contribution from the site network. It is recommended that the earthing system of each
distribution substation is reviewed to comply with modern standards in case any of the
substations are inadvertently disconnected from the network, i.e. each substations earthing
system in isolation should provide touch voltage control.
Carry out periodic testing to ensure the low overall earth value is maintained into the future.

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page 6

3 October 2014

8.

Earthing Calculations Report

Harris 6.6kV Distribution Substation

Applicable Standards

ENA Technical Specification 41-24, Guidelines for the Design, Installation, Testing and
Maintenance of Main Earthing Systems in Substations, Issue 1, 1992 (Amended 1999),
published by Energy Networks Association.

ENA Engineering Recommendation S34, A Guide for Assessing the Rise of Earth Potential at
Substation Sites, 1986 (Amended 1986, 1988), published by Energy Networks Association.

ENA Engineering Recommendation S36, Procedure to Identify and Record Hot


Substations, 1988, published by Energy Networks Association.

BS EN 50522 Earthing of Power Installations Exceeding 1kV A.C., 2010, Published by British
Standards Institute.

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page 7

3 October 2014

Earthing Calculations Report

Harris 6.6kV Distribution Substation

Appendix A - Measurement Locations


FOP 2

SR1
FOP 1

SR3

SR4

SR2

Figure A.1: Measurement Locations


Table A.1: Measurement Location Coordinates

Latitude /
Longitude *

Site

FOP 1

FOP 2

SR1

SR2

SR3

SR4

53
27.560'N
2
18.300'W

53
27.655'N
2
18.323'W

53
27.603'N
2
18.160'W

53
27.613'N
2
18.233'W

53
27.511'N
2
18.433'W

53
27.510'N
2
17.932'W

53
27.510'N
2
17.932'W

Note:
*
Refers to main entrance (Site), current probe location (FOP measurement) or centre of traverse (SR
measurement)

Site personnel: Amy Pears, Louise Christopher

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page 8

3 October 2014

Earthing Calculations Report

Harris 6.6kV Distribution Substation

Appendix B FOP Measurement 2 Data

0.500

0.450

0.400

Measured Resistance ()

0.350

0.300

0.250

0.200

0.150

0.100

0.050

0.000
0

10

20

30

40

50

60

70

80

90

100

Potential Probe Position (m)

Distance to Current Probe (m):


Potential Probe Position

100

Measured
Resistance ()

(m)

(% of Distance to
Current Probe)

90

90.0

0.461

80

80.0

0.224

70

70.0

0.185

60

60.0

0.154

50

50.0

0.125

40

40.0

0.098

30

30.0

0.090

20

20.0

0.091

10

10.0

0.079

System Elements

Resistance ()

Interpretation Method

Hill Top Overall Earthing


System

0.160

'61.8% Rule'

Earthing Solutions Ltd

ESL0412-R01 (Rev A)

Page 9

Potrebbero piacerti anche