Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
4, NOVEMBER 2005
1843
I. INTRODUCTION
Manuscript received December 27, 2004; revised June 23, 2005. This work
was supported by the National Science Council of Taiwan under Grant NSC
93-2213-E-022-004. Paper no. TPWRS-00683-2004.
The author is with the Department of Marine Engineering, National Kaohsiung Marine University, Kaohsiung 805, Taiwan, R.O.C. (e-mail: cls@mail.
nkmu.edu.tw).
Digital Object Identifier 10.1109/TPWRS.2005.857921
1844
and
1845
can be calculated
(5)
where
.
is the number of observations of and
is the probability of each observation
.
and
are transferred to proThe information about the
duce two estimates of the line-flow solution variants,
and
, through the power flow model. The
expressed
in (6) to denote the weighting of the concentration located at
) is then used to scale these
(
estimates to take into account the skewness of the probability
distribution of .
(6)
. The value of each
ranges
where
s is unity.
from 0 to 1 and the sum of all
can be obtained from the proposed
The th moment of
method by using
(7)
The standard deviation of the
is computed through
(8)
Fig. 2.
1846
TABLE I
DISTRIBUTIONS OF UNCERTAIN NODAL DATA
TABLE III
STATISTICS OF LOAD FLOW SOLUTION OBTAINED FROM DIFFERENT METHODS
TABLE IV
PERFORMANCE COMPARISONS OF DIFFERENT METHODS
TABLE II
DISTRIBUTIONS OF UNCERTAIN LINE PARAMETERS
Tables III and IV show the test results. Table III shows the
distributions of some of load-flow solution quantities obtained
from different methods. These state variables and output quantities can be considered representative of all the solution quantities so as to determine the accuracy performance of the proposed method. From Table III it can be seen that since nonlinear
power flow equations and no linearizations are used, the errors
introduced in the state variables and line flows can be reduced
with the proposed method. Thus, the load-flow solution distributions obtained from the proposed method are much closer to the
results from the Monte Carlo simulation with 5000 trials than
those obtained from the Monte Carlo simulation with CV of 2%
and the CSA method with 1000 samples and three linearizations.
Table III also shows that since a large number of linearizations
can enhance the computation accuracy of the CSA method, the
result obtained from the CSA method with five linearizations is
more accurate than that from the CAS method with three linearizations and is similar to that obtained form the proposed
method.
Table IV shows the performance comparisons of different
methods. In this test, all probability distributions of the test
system obtained from different methods are used for computing
the performance indices. It can be seen from Table IV that the
proposed method has smaller errors in estimating load-flow
solution distributions and is about 37 times faster than the
Monte Carlo simulation with 733 trials. It can also be found
from Table IV that when considering similar execution time,
the proposed method could have a more accurate result than
that from the CAS method with 1000 samples and three linearizations. The results also indicate that the proposed method
requires less computational effort than the CSA method with
1000 samples and three linearizations when both methods have
1847
10% and 90% confidence levels of line flows are interested, the
estimates of Fig. 5 at 10% and 90% confidence levels for the proposed method are 0.2739 and 0.3634, respectively, as compared
with 0.2790 and 0.3611 obtained from the MCS method. These
and
estimates in Fig. 6 for the proposed method are
and 0.0372 from the MCS
0.0395 as compared with
method. Test results have indicated that the cumulative density
functions obtained from the proposed method are close to the
true load-flow solution distributions. However, in Figs. 5 and 6,
some slight differences near the probabilities of 0.75 and 0.5
can be seen although the general performance is good. The additional tests with three-point and four-point estimate were also
conducted to clarify that. It is shown from the results that the
differences can be reduced when the number of estimate points
increases. From Figs. 5 and 6, and additional test results, it is
concluded that in general the proposed method could have a
fairly good estimate in result of load-flow solution distributions.
However, to obtain better results, a lager number of point estimate could be used in the proposed point estimate method.
Sensitivity analysis is performed to verify the performance
of the proposed method under different numbers of CV of bus
power injections. The smaller value of CV presents operational
or short term planning studies, that the nodal data are well
known. The larger value of CV presents long-term planning
1848
TABLE VI
EFFECTS OF SYSTEM SIZE ON PERFORMANCE OF THE PROPOSED METHOD
TABLE V
SENSITIVITY OF PERFORMANCE OF THE PROPOSED METHOD
COEFFICIENT OF VARIATION OF LINE PARAMETERS
TO
slowly increase as the uncertainty level of line parameters increases. Comparing Fig. 7 to Table V, it is found that the performance of the proposed method is more sensitive to bus power
injections than line parameters, that as expected. The results also
show that the proposed method could flexibly consider different
types of uncertain parameters in the load-flow computations and
accurately estimate the corresponding solution distributions.
To determine the effects of system size on performance of
the proposed method, additional tests using IEEE 30, 57, and
118 bus test systems were conducted. Test results are shown in
Table VI. In the tests, the bus power injections are assumed to
have a normal distribution with CV of 5%. The results are compared with those from the Monte Carlo simulation with 10 000
trials for computation accuracy check. Another Monte Carlo
simulation, that CV of 2% is set to all line-flow quantities to be
estimated, is also performed for computation efficiency comparison. It can be found from Table VI that the convergence time
in the Monte Carlo simulations increases as the size of system
increases. The proposed method is about 37 to 48 times faster
than the Monte Carlo simulations for larger size systems. It has
shown from the results that the proposed method could have a
good result in estimates of load flow solution distributions even
for a large system and its computation performance will not be
degraded with increase of system size.
IV. CONCLUSIONS
To obtain adequate information about the adequacy and reliability of a transmission network in the future, system parameter
uncertainties have to be considered in the load-flow study. This
paper proposes a new probabilistic load-flow approach to take
uncertainty of nodal data and line parameters into account in
the load-flow computations and to estimate the corresponding
variations in the solution. Test results have indicated that if the
uncertain parameters considered can be measured or estimated,
the distributions of all state variables and line-flow quantities
can be accurately and efficiently evaluated with the proposed
two-point estimate method through simple numerical computations. However, for better results, a larger number of estimate
point could be used in the proposed method.
The proposed method is tested and verified by comparison
with results from the combined simulation and analytical
1849
APPENDIX
DERIVATION OF THE PROPOSED METHOD
This Appendix shows how to obtain the statistical moments
described in Section II. The derivaof the line-flow solution
and
denote the
tion is similar to that shown in [18]. Let
mean and standard deviation of the bus power injection or line
parameter that is a random variable with probability density
,
. Further, let
denote th moment about
denote the ratio of
to
,
the mean of and
that are expressed as
(A1)
(A2)
where
is equal to zero,
is equal to one,
and
are the coefficient of skewness and coefficient kurtosis of ,
respectively. Using the multivariable Taylor series, the about
the mean of can be expanded as follows:
(A3)
(A4)
where
denotes the expectation.
,
,2, be the th conNow, let
centration of the
and
be the weighting of the concen), where
tration located at (
and
are the unknown constants to be determined. The
and
to approxiproblem is now how to determine the
mate the exact mean of
in (A4) by using the concentrations
and weighted factors of each random variable . In order to
with
for each
achieve this, (A3) is multiplied by
random variable , and summing them up leads to (A5), as
shown at the bottom of the page.
The proposed two-point estimate method uses two concentrations and two weighted factors for each random variable
to match the moments of probability density function of
and to obtain the statistical moments of
. Therefore,
expressed in (A4) by
to approximate the exact mean of
shown in (A5), we can match the first four items of the right
side of (A4) and (A5) (i.e., matching the moments of up to
(A5)
1850
(A6)
(A7)
Equation (A6) is to match the first three moments of the prob,
,
ability density function of . The unknown constants,
, and
, then can be determined based on (A6) and (A7)
and the solutions are as follows:
(A8)
(A9)
where
the coefficient of skewness of
.
that denotes
can be computed as follows:
(A10)
where
.
is the number of observations of and
is the probability of each observation .
and
in (A8) and (A9), it is
Based on the constants
interesting to know that how accurate the proposed method approaches to the exact mean of . Therefore, substituting (A6)
and (A7) into (A5) gives (A11), as shown at the bottom of the
page.
(A12)
Then, substituting (A12) into (A4) gives (A13), as shown at
the bottom of the page.
It can be seen from (A13) that the exact
,
,
can
be
obtained
by
mean
of
in
is a
a third-order approximation. When
third-order polynomial, the proposed method (two-point
with
estimate) gives the exact solution to the mean of
uncertain parameters. Similarly, we can show that the secondcan be approximated by
order moment of
(A14)
The standard deviation of
is then obtained by
(A15)
(A11)
(A13)
REFERENCES
[1] B. Borkowska, Probabilistic load flow, IEEE Trans. Power App. Syst.,
vol. PAS-93, no. 3, pp. 752759, May/Jun. 1974.
[2] J. F. Dopazo, O. A. Klitin, and A. M. Sasson, Stochastic load flows,
IEEE Trans. Power App. Systems, vol. PAS-94, no. 2, pp. 299309,
Mar./Apr. 1975.
[3] R. N. Allan, A. M. L. da Silva, and R. C. Burchett, Evaluation methods
and accuracy in probabilistic load flow solutions, IEEE Trans. Power
App. Syst., vol. PAS-100, no. 5, pp. 25392546, May 1981.
[4] P. Zhang and S. T. Lee, Probabilistic load flow computation using the
method of combined Cumulants and Gram-Charlier expansion, IEEE
Trans. Power Syst., vol. 19, no. 1, pp. 676682, Feb. 2004.
[5] R. N. Allan and A. M. Liete da Silva, Probabilistic load flow using
multilinearizations, Proc. Inst. Elect. Eng. C: Generation, Transmission, Distribution, vol. 128, no. 5, pp. 280287, 1981.
[6] A. P. Sakis Meliopoulos, G. J. Cokkinides, and X. Y. Chao, A new
probabilistic power flow analysis method, IEEE Trans. Power Syst., vol.
5, no. 1, pp. 182190, Feb. 1990.
[7] A. M. Leite da Silva, V. L. Arienti, and R. N. Allan, Probabilistic load
flow considering dependence between input nodal powers, IEEE Trans.
Power App. Syst., vol. PAS-103, no. 6, pp. 15241530, Jun. 1984.
[8] A. M. Leite da Silva and V. L. Arienti, Probabilistic load flow by a
multilinear simulation algorithm, Proc. Inst. Elect. Eng. C: Generation,
Transmission, Distribution, vol. 137, no. 4, pp. 276282, Jul. 1990.
[9] A. M. Leite da Silva, R. N. Allan, S. M. Soares, and V. L. Arienti, Probabilistic load flow considering network outages, Proc. Inst. Elect. Eng.
C: Generation, Transmission, Distribution, vol. 132, no. 3, pp. 139145,
May 1985.
[10] V. Miranda, M. A. Matos, and J. T. Saraiva, Fuzzy load flow- new algorithms incorporating uncertain generation and load representation, in
Proc. 10th Power System Computation Conf., Graz, Austria, 1990, pp.
621627.
1851