Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Walden (1854)
If you have built castles in the air,
Your work need not be lost;
That is where they should be.
Now put the foundations under them.
FOUNDATION DESIGN
PROCESS
Site characterization
Geology
Stratigraphy
Quantification of relevant geotechnical parameters.
Based on:
In-situ testing
Laboratory testing
Load testing
Coffey Geotechnics
OUTLINE
Investigations
Design
Load tests
Tower foundation performance
Burj Dubai
Foundation design
Load tests
Foundation performance
LOCATION OF DUBAI
PROJECTS
FOUNDATION DESIGN
PROCESS
Based on:
Foundation loadings
Design criteria
Construction issues
Material availability
FOUNDATION DESIGN
PROCESS
Ultimate capacity
Settlement
Differential settlement & tilt
Dynamic behaviour
Earthquake response
Structural strength of foundation elements
Durability
Design Issues
1.
2.
3.
4.
5.
6.
7.
LABORATORY TESTING
Conventional laboratory & field tests
Specialized testing
Effects of repetitive wind loading
Deformation parameters
CNS testing
"
Calcisiltite
Silty Sand
Calcareous Sandstone
Silty Sand
Silty Sand
700
90
500
125
700
125
40
Eu MPa
600
80
400
100
500
100
30
E' MPa
450
200
450
150
200
73
18
2.7
2.0
2.7
1.9
2.3
1.5
0.2
fb MPa
2.7
2.0
2.7
1.9
2.3
1.5
0.1
pu MPa
fs kPa
"
INVESTIGATION PROGRAM
PREDICTION METHODS
Axial Response
Non-Linear boundary element analysis
PIES program
Lateral Response
Non-Linear boundary element analysis
ERCAP program
FOUNDATION TYPES
Towers
Piled raft foundations
Podium
Piles, pile groups
Predicted
Measured
10
20
30
Settlement (mm)
40
LOAD-SETTLEMENT CURVES
FOR PILE P3(H)
30000
25000
20000
15000
10000
Load (kN)
5000 10000 15000 20000 25000 30000
(-0.50)
(-2.00)
(-5.00)
203
0
No. 1 Extensometer
900
Reference beams
Ground anchors
Working platform
(-10.0)
(-16.0)
(-20.0)
(-25.0)
(-30.0)
(-36.0)
Unit 4 - Calcisiltite
(-40.0)
1285
5000
2
0
-2
-4
-6
-8
-10
-12
-14
-16
-18
-20
-22
-24
-26
-28
-30
-32
-34
-36
-38
-40
Predicted
Measured
Measured
0
5 10 15 20
Displacement (mm)
25
175
-5
2.0
Deflection (mm)
4.0
6.0
8.0
10.0
12.0
Measured
Predicted (Load= 150 kN)
1000
2000
3000
4000
5000
6000
LOAD-MOVEMENT CURVES
FOR UPLIFT TEST
-5
Measured
Predicted
50
40
30
20
10
600
Design values
Deduced from P3 (hotel) pile test (compression)
Deduced from P1 (hotel) pile test (tension)
Deduced from P3 (office) pile test (compression)
Deduced from P1 (office) pile test (tension)
100
700
200
125
150
100
75
50
25
0
-10
-1.0 0
2
0
-2
-4
-6
-8
-10
-12
-14
-16
-18
-20
-22
-24
Depth (m)
DESIGN METHODOLOGY
Limit State Approach
Ultimate Limit State:
Static loads
Repetitive wind loads
TOWER FOUNDATION
ANALYSES
GARP program for piled rafts
Ultimate Limit State:
Used both factored & unfactored pile capacities
Many load combinations
ASSESSMENT OF
PREDICTIONS
DYNAMIC FOUNDATION
RESPONSE
Required for seismic & wind response
Dynamic stiffness & damping from dynamic
pile group analysis via Gazetas approach
MATLAB program developed for evaluation
SEISMIC EFFECTS
Liquefaction:
Low very low risk
LOAD COMBINATIONS
Ultimate Limit State:
1.25G + 1.5Q
1.2G + 0.4Q + Wu
0.8G = Wu
G + 0.4Q
Total of 18 load cases per tower
100
10
0
11
15
120
130
130
0
12
0
11
20
25
30
x axis (m)
120
11
0
0
11
35
40
45
120
50
Settlement =
134 mm
Predicted Max.
PREDICTED SETTLEMENT
CONTOURS FOR OFFICE TOWER
130
55
50
45
40
35
30
25
20
15
10
10
0
55
50
45
40
105
10
5
10
15
115
11
5
125
125
115
20
25
30
x axis (m)
115
35
30
25
20
15
10
35
40
105
105
10
5
105
45
50
Predicted Max.
Settlement = 138
mm
PREDICTED SETTLEMENT
CONTOURS FOR HOTEL TOWER
11
0
125
y axis (m)
y axis (m)
115
T2
T4
-5.3
T6
-6
T3
-7
-6.2
-6.9
-7
T7
-6.5
-7.3
T5
-7.0
-7.4
T1
-7.4
T8
T9
-7
-6.5
-5.8
-7.2
T10
-8.3
-8
T11
-7
T12
-8.2
T15
T13
-7.9
T14
-6
-7
T16
-8.7
T17
-6.3
-7
-8
-6.0
T18
T19
-8.3
-8
-7.5
T20
-8.0
MEASURED SETTLEMENT
CONTOURS HOTEL TOWER
0.4
0.3
0.2
0.1
0
100
Curve No.
50
Modulus of Soil
between Piles
to Near-Pile Values
20
Modulus of
Layer below
MPa
10
s/d
1.0
5.0
5.0
5.0
1.0
90
90
200
700
700
2
5
3
4
1
2
3
4
5
50
40
30
20
10
1998
7
Time (months)
10 11 12
Predicted
T112
T111
Settlement (mm)
50
40
30
20
10
1998
6
Time (months)
Predicted
Measured
T15
T4
10 11 12
Settlement (mm)
Interaction Factor D
SOME COMMENTS
ORIGINAL
CASE 2
CASE 3
Hotel Tower
CASE 4
CASE 5
160
140
120
80
100
60
40
20
0
Settlement mm
Dubai - 2006
17
Gypsiferous Sandstone
Calcareous Sandstone
Calcarenite
Silty Sand
SIMPLIFIED PROFILE
4.5
Calcareous/Conglomeritic
Conglomeritic Calcisiltite
22.5
Claystone/Siltstone
40
>47
GEOTECHNICAL PEER
REVIEW - SCOPE
30 boreholes
SPT
60 PMT tests in 5 boreholes
6 standpipe piezometers
Geophysics cross-hole tomography
SITE CHARACTERIZATION
LABORATORY TESTING
Advanced tests:
LABORATORY TESTING
Classification (various)
UCS
Point Load Index
Modulus
Chemical
Conventional tests:
90
80
70
60
50
40
30
20
10
0
0
10
20
30
50
60
40
Settlem ent m m
70
80
Analysis
90
Hyder
Coffey
62
45
Settlement mm
(Rigid cap)
p)
56
46
REPUTE
VDISP
72
PIGLET
ABAQUS
Settlement mm
(Flexible cap)
p
66
Load MN
Podium:
Raft:
3.7m thick (tower)
HYDER SETTLEMENT
PREDICTIONS
REPUTE linear
PIGLET - linear
VDISP
100
200
300
400
500
600
700
800
900
Recommended (Hyder)
Original Design
20
-20
-40
-60
-80
-100
-120
COMPARISONS SKIN
FRICTION
RL (DMD)
PIGS
74 mm (maximum)
PREDICTED SETTLEMENT
PROFILE
TP1
TP2
TP3
Stiffness MN/m
TP4
TP5
TP6
At Maximum Load
At Working Load
5000
4000
3000
2000
1000
Measured Time-SettlementWing B
Measured Time-Settlement
Wing A
PREDICTED SETTLEMENT
CONTOURS PIGS ANALYSIS
Hyder
Coffey
16 mm
22 mm
25 mm
Measured
Measured Time-Settlement
Wing C
Feasibility
Detailed Design Serviceability
Optimization
Detailed Design Strength
COMPLETED RAFT
Early 2007
September 2007
CONSTRUCTION PROGRESS
Early 2006
Feasibility Results
Indicated that a raft foundation alone would
have a factor of safety of approximately 10 for
ultimate loading
Settlements would govern. Estimated to be of
the order of 35mm to 60mm
The number of piles would be of the order of
140 as per the foundation design supplied by
contractor. However, piles only 18m long not
35m
Serviceability Case
123 piles (13
less)
Maximum raft
settlement of
44mm
Maximum
differential
settlement of
10mm (1/400)
SAND
D
PEATY CLAY
(SOME SAND)
F-St
SAND
D-VD
DESCRIPTION
14
60
10
60
Av.
SPT
250
80
Su
kPa
37.5
25
90
90
Es
(RAFT)
MPa
2.25
1.5
5.4
0.5
5.4
pu
(RAFT)
MPa
200
50
40
120
20
120
Es
(PILES)
MPa
100
48
60
100
22
100
fs
kPa
10.0
4.1
2.0
9.9
0.7
9.9
fb
MPa
136 piles
founded
on rock
Slab
0.7m
thick
Original Design
25
9.0
SAND WITH
SOME GRAVEL
MD
150
-30
10.0
100
SANDY GRAVEL
2000
-35
2000
-40
M
METASILTSTONE
SW
-25
-20
-15
-10
-5
ASSUMED
BASE OF RAFT
Geotechnical
Model
RL (m)
Patrick Wong
Jeff Forse
Paul Gildea
Bob Lumsdaine
Strath Clarke
Leanne Petersen
Burj Dubai:
Emirates Project:
Paran Moyes
Frances Badelow
John Small
Artique Project
ACKNOWLEDGEMENTS
Frances Badelow
Muliadi Merry
Patrick Wong
Outcomes
CONCLUSIONS