Sei sulla pagina 1di 3

1774 Federal Register / Vol. 71, No.

7 / Wednesday, January 11, 2006 / Notices

comparable CES all employees figure, II. Current Action • Enhance the quality, utility, and
temporary help agency workers, leased Office of Management and Budget clarity of the information to be
workers, independent contractors, and Clearance is being sought for the CES collected; and
other workers not classified elsewhere. Supplemental Form on Temporary • Minimize the burden of the
The BLS plans to re-contact 100 of the Help, Leased, and Other Contracted collection of information on those who
16,000 respondents to verify the quality Work. are to respond, including through the
of the responses received. use of appropriate automated,
III. Desired Focus of Comments electronic, mechanical, or other
Reporting for the CES survey is
The BLS is particularly interested in technological collection techniques or
voluntary under federal law, but is
comments that: other forms of information technology,
mandatory under state law in five
States. The supplemental survey will • Evaluate whether the proposed e.g., permitting electronic submissions
collection of information is necessary of responses.
not be using the State mandatory Type of Review: New Collection.
for the proper performance of the
reporting authority. Agency: Bureau of Labor Statistics.
functions of the agency, including
The BLS may conduct additional whether the information will have Title: CES Supplemental Form on
supplemental surveys in the future, practical utility; Temporary Help, Leased, and Other
depending on the availability of • Evaluate the accuracy of the Contracted Work.
resources and the significance of the agency’s estimate of the burden of the OMB Number: 1220–NEW.
topic. The BLS is requesting approval proposed collection of information, Affected Public: Businesses or other
for collection through December 31, including the validity of the for-profit; Small businesses or
2006. methodology and assumptions used; organizations.

Number of Minutes per Frequency of Annual Annual burden


Form respondents report response responses hours

Supplemental Form on Temporary Help, Leased, and


Other Contracted Work .................................................... 16,000 20 1 16,000 5,333
Response Analysis interviews ............................................. 100 120 1 100 200

Total .............................................................................. 16,100 ........................ ........................ 16,100 5,533

Total Burden Cost (capital/startup): Entergy Nuclear Operations, Inc. (the accident previously evaluated; or (3)
$0. licensee), for operation of the Vermont involve a significant reduction in a
Total Burden Cost (operating/ Yankee Nuclear Power Station (VYNPS) margin of safety. The NRC staff’s
maintenance): $0. located in Windham County, Vermont. analysis of the issue of no significant
Comments submitted in response to The proposed amendment would hazards consideration is presented
this notice will be summarized and/or change the VYNPS operating license to below:
included in the request for Office of increase the maximum authorized
power level from 1593 megawatts First Standard
Management and Budget approval of the
information collection request; they also thermal (MWt) to 1912 MWt. This Does the proposed amendment
will become a matter of public record. change represents an increase of involve a significant increase in the
Signed at Washington, DC, this 3rd day of approximately 20 percent above the probability or consequences of an
January 2006. current maximum authorized power accident previously evaluated?
Kimberley Hill, level. The proposed extended power Response: No.
uprate (EPU) amendment would also As discussed in the licensee’s
Acting Chief, Division of Management
change the VYNPS Technical application dated September 10, 2003,
Systems, Bureau of Labor Statistics.
Specifications (TSs) to provide for the VYNPS EPU analyses, which were
[FR Doc. E6–149 Filed 1–10–06; 8:45 am]
implementing uprated power operation. performed at or above EPU conditions,
BILLING CODE 4510–24–P
Before issuance of the proposed included a review and evaluation of the
license amendment, the Commission structures, systems, and components
will have made findings required by the (SSCs) that could be affected by the
NUCLEAR REGULATORY Atomic Energy Act of 1954, as amended proposed change. The licensee reviewed
COMMISSION (the Act), and the Commission’s plant modifications and revised
regulations. operating parameters, including
[Docket No. 50–271] The Commission has made a operator actions, to confirm acceptable
Entergy Nuclear Vermont Yankee, LLC proposed determination that the performance of plant SSCs under EPU
and Entergy Nuclear Operations, Inc.; amendment request involves no conditions. On this basis, the licensee
Notice of Consideration of Issuance of significant hazards consideration. Under concluded that there is no increase in
Amendment to Facility Operating the Commission’s regulations in Title 10 the probability of accidents previously
License and Proposed No Significant of the Code of Federal Regulations (10 evaluated.
Hazards Consideration Determination CFR), § 50.92, this means that operation Further, as also discussed in the
of the facility in accordance with the licensee’s application, while not being
The U.S. Nuclear Regulatory proposed amendment would not (1) submitted as a risk-informed licensing
rmajette on PROD1PC71 with NOTICES

Commission (NRC or the Commission) involve a significant increase in the action, the proposed amendment was
is considering issuance of an probability or consequences of an evaluated by the licensee from a risk
amendment to Facility Operating accident previously evaluated; or (2) perspective. Using the NRC guidelines
License No. DPR–28, issued to Entergy create the possibility of a new or established in Regulatory Guide (RG)
Nuclear Vermont Yankee, LLC and different kind of accident from any 1.174, and the calculated results from

VerDate Aug<31>2005 14:20 Jan 10, 2006 Jkt 208001 PO 00000 Frm 00044 Fmt 4703 Sfmt 4703 E:\FR\FM\11JAN1.SGM 11JAN1
Federal Register / Vol. 71, No. 7 / Wednesday, January 11, 2006 / Notices 1775

the VYNPS Level 1 and 2 probabilistic included review of the SSCs that could The NRC staff evaluated the impact of
safety analyses, the best estimate for the be affected by the proposed change. the proposed EPU to assure that
core damage frequency (CDF) increase This review included evaluation of acceptable fuel damage limits are not
due to the proposed EPU is 3.3 E–7 per plant modifications, revised operating exceeded. This included consideration
year (an increase of 4.2 percent over the parameters, changes to operator actions of the VYNPS fuel system design,
pre-EPU CDF of 7.77 E–6 per year). The and procedures, the EPU test program, nuclear system design, thermal and
best estimate for the large early release and changes to the plant TSs. Based on hydraulic design, accident and transient
frequency (LERF) increase due to the this review, the staff concludes that the analyses, and fuel design limits. The
proposed EPU is 1.1 E–7 per year (an proposed amendment would not evaluation included an assessment of
increase of 4.9 percent over the pre-EPU introduce any significantly new or the margin in the associated safety
LERF of 2.23 E–6 per year). The NRC different plant equipment, would not analyses supporting the proposed EPU.
staff concludes, based on review of the significantly impact the manner in The staff’s evaluation found that the
licensee’s risk evaluation and the which the plant is operated, and would licensee’s analysis was acceptable based
acceptance guidelines in RG 1.174, that not have any significant impact on the on use of approved analytical methods
the proposed amendment would not design function or operation of the SCCs and that the licensee had included
involve a significant increase in the involved. The staff’s review did not sufficient margin to account for analysis
probability of an accident previously identify any credible failure and data uncertainty. In addition, the
evaluated. mechanisms, malfunctions, or accident licensee will continue to perform cycle-
The NRC staff’s evaluation of the initiators not already considered in the specific analysis to confirm that fuel
proposed amendment included review VYNPS design and licensing bases. design limits will not be exceeded
of the SSCs that could be affected by the Consequently, the staff concludes that during each cycle. The staff’s evaluation
proposed change. This review included the proposed change would not concluded that the applicable VYNPS
evaluation of plant modifications, introduce any failure mode not licensing basis requirements would
revised operating parameters, changes to previously analyzed. continue to be met following
operator actions and procedures, the Based on the above, the NRC staff implementation of the proposed EPU
EPU test program, and changes to the concludes that the proposed change (e.g., draft General Design Criteria (GDC)
plant TSs. Based on this review, the would not create the possibility of a 6, 7, and 8; and 10 CFR 50.46).
staff concludes that there is reasonable new or different kind of accident from Therefore, the NRC staff concludes that
assurance that the SSCs important to any accident previously evaluated. fuel cladding integrity would be
safety will continue to meet their Third Standard maintained within acceptable limits
intended design basis functions under under the proposed EPU conditions.
EPU conditions. Therefore, the staff Does the proposed amendment
involve a significant reduction in a The NRC staff further evaluated the
concludes that there is no significant impact of the proposed EPU on the
change in the ability of these SSCs to margin of safety?
Response: No. RCPB. The evaluation included an
preclude or mitigate the consequences assessment of overpressure protection;
As discussed in the licensee’s
of accidents. structural integrity of the RCPB piping,
The NRC staff’s evaluation also application, continuing improvements
in analytical techniques based on components, and supports; and
reviewed the impact of the proposed
several decades of boiling-water reactor structural integrity of the reactor vessel.
EPU on the radiological consequences of
safety technology, plant performance With respect to overpressure protection,
design-basis accidents for VYNPS. The
feedback, operating experience, and the staff found that the licensee had
staff’s review concluded that dose
improved fuel and core designs, have used an NRC-approved evaluation
criteria in 10 CFR 50.67, as well as the
resulted in a significant increase in the method, had used the most limiting
applicable acceptance criteria in
design and operating margin between pressurization event, and had
Standard Review Plan Section 15.0.1,
the calculated safety analyses results determined that the peak calculated
would continue to be met at EPU
and the current plant licensing limits. pressure would remain below the
conditions.
The NRC staff concludes, based on The NRC staff’s review found that the American Society of Mechanical
review of the SSCs that could be proposed EPU will reduce some of the Engineers Boiler and Pressure Vessel
affected by the proposed amendment existing design and operational margins. Code (ASME Code) allowable peak
and review of the radiological However, safety margins are considered pressure. With respect to structural
consequences, that the proposed to not be significantly reduced if: (1) integrity of the RCPB piping,
amendment would not involve a Applicable regulatory requirements, components, and supports, the staff
significant increase in the consequences codes and standards or their alternatives found that the licensee had performed
of an accident previously evaluated. approved for use by the NRC, are met, its evaluation using the process and
Based on the above, the NRC staff and (2) if safety analysis acceptance methodology defined in NRC-approved
concludes that the proposed criteria in the licensing basis are met, or topical reports. The staff’s evaluation
amendment would not involve a if proposed revisions to the licensing concluded that RCPB structural integrity
significant increase in the probability or basis provide sufficient margin to would be maintained at EPU conditions.
consequences of an accident previously account for analysis and data With respect to structural integrity of
evaluated. uncertainty. the reactor vessel, the staff found that
Margin of safety is related to the licensee had implemented an
Second Standard confidence in the ability of the fission acceptable reactor vessel materials
Does the proposed amendment create product barriers (i.e., fuel cladding, surveillance program in a previously
the possibility of a new or different kind reactor coolant pressure boundary approved amendment that was based on
rmajette on PROD1PC71 with NOTICES

of accident from any accident (RCPB), and containment) to limit the neutron fluence values acceptable for
previously evaluated? level of radiation dose to the public. The VYNPS at EPU conditions. In addition,
Response: No. NRC staff evaluated the impact of the the staff found that the existing
As stated above, the NRC staff’s proposed EPU on the fission product pressure-temperature limit curves
evaluation of the proposed amendment barriers as discussed below. contained in the TSs would remain

VerDate Aug<31>2005 14:20 Jan 10, 2006 Jkt 208001 PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 E:\FR\FM\11JAN1.SGM 11JAN1
1776 Federal Register / Vol. 71, No. 7 / Wednesday, January 11, 2006 / Notices

bounding for EPU conditions. The staff are satisfied. Therefore, the NRC staff October 28 (2 letters), 2003, January 31
also found that the methodology used proposes to determine that the (2 letters), March 4, May 19, July 2, July
by the licensee to evaluate the loads on amendment request involves no 27, July 30, August 12, August 25,
the reactor vessel was consistent with significant hazards consideration. September 14, September 15, September
an NRC-approved methodology and that The Commission is seeking public 23, September 30 (2 letters), October 5,
the maximum stresses and fatigue usage comments on this proposed October 7 (2 letters), December 8, and
factors for EPU conditions would be determination. Any comments received December 9, 2004, and February 24,
within ASME Code allowable limits. within 30 days after the date of March 10, March 24, March 31, April 5,
The staff’s evaluation regarding the publication of this notice will be April 22, June 2, August 1, August 4,
RCPB concluded that the applicable considered in making a final September 10, September 14, September
VYNPS licensing basis requirements determination. 18, September 28, October 17, October
would continue to be met following The Commission previously 21, 2005 (2 letters), October 26, October
implementation of the proposed EPU published a ‘‘Notice of Consideration of 29, November 2, November 22, and
(e.g., draft GDC 9, 33, 34, and 35; 10 Issuance of Amendment to Facility December 2, 2005. Documents may be
CFR 50.60; and 10 CFR part 50, Operating License and Opportunity for examined, and/or copied for a fee, at the
Appendices G and H). Therefore, the a Hearing’’ for the proposed VYNPS NRC’s Public Document Room (PDR),
NRC staff concludes that RCPB EPU amendment in the Federal Register located at One White Flint North, Public
structural integrity would be maintained on July 1, 2004 (69 FR 39976). This File Area O1 F21, 11555 Rockville Pike
under the proposed EPU conditions. Notice provided 60 days for the public (first floor), Rockville, Maryland.
Finally, the NRC staff evaluated the to request a hearing. On August 30, Publicly available records will be
impact of the proposed EPU on the 2004, the Vermont Department of Public accessible electronically from the
containment. The staff found that the Service and the New England Coalition ADAMS Public Electronic Reading
licensee’s analysis used acceptable filed requests for hearing in connection Room on the NRC Web site, http://
calculational methods and conservative with the proposed amendment. By www.nrc.gov/reading-rm/adams.html.
assumptions and that the containment Order dated November 22, 2004, the Persons who do not have access to
pressure and temperature under EPU Atomic Safety and Licensing Board ADAMS or who encounter problems in
conditions would remain below existing (ASLB) granted those hearing requests accessing the documents located in
design limits. The staff also evaluated and by Order dated December 16, 2004, ADAMS should contact the NRC PDR
the licensee’s proposed change to the the ASLB issued its decision to conduct Reference staff at 1–800–397–4209, or
licensing basis to credit containment a hearing using the procedures in 10 301–415–4737, or send an e-mail to
accident pressure to meet the net CFR part 2, subpart L, ‘‘Informal pdr@nrc.gov.
positive suction head (NPSH) Hearing Procedures for NRC
requirements for the emergency core Adjudications.’’ No additional Dated at Rockville, Maryland, this 5th day
opportunity for hearing is provided in of January 2006.
cooling system pumps. The staff found
that the licensee’s analysis was connection with this notice. For the Nuclear Regulatory Commission.
performed using conservative In accordance with the Commission’s Richard B. Ennis,
assumptions and that the credited regulations in 10 CFR 50.91, if a final Senior Project Manager, Plant Licensing
pressure remains below the containment determination is made that the proposed Branch I–2, Division of Operating Reactor
accident pressure that would be amendment involves no significant Licensing, Office of Nuclear Reactor
available under EPU conditions. The hazards consideration, the Commission Regulation.
staff’s evaluation regarding the may issue the amendment and make it [FR Doc. E6–159 Filed 1–10–06; 8:45 am]
containment concluded that the immediately effective, notwithstanding BILLING CODE 7590–01–P
applicable VYNPS licensing basis submission of adverse comments or a
requirements would continue to be met request for hearing. In that event, any
following implementation of the required hearing would be completed NUCLEAR REGULATORY
proposed EPU (e.g., draft GDC 10, 41, after issuance of the amendment; COMMISSION
49, and 52; and 10 CFR part 50, however, if a final determination is
made that the proposed amendment Radiation Source Protection and
Appendix K). Therefore, the NRC staff
involves a significant hazards Security Task Force; Request for
concludes that containment structural
consideration, the amendment would Public Comment
integrity would be maintained under the
proposed EPU conditions. not be issued prior to completion of the
AGENCY:Nuclear Regulatory
In summary, the NRC staff has hearing.
Written comments may be submitted Commission.
concluded that the structural integrity of
the fission product barriers (i.e., fuel by mail to the Chief, Rules and ACTION: Request for public comment.
cladding, RCPB and containment) Directives Branch, Division of
would be maintained under EPU Administrative Services, Office of SUMMARY: The Nuclear Regulatory
conditions. As such, the proposed Administration, U.S. Nuclear Regulatory Commission (NRC) has established an
amendment would not degrade Commission, Washington, DC 20555– interagency task force to evaluate and
confidence in the ability of the barriers 0001, and should cite the publication make recommendations on the
to limit the level of radiation dose to the date and page number of this Federal protection and security of radiation
public. Register notice. Written comments may sources. The Radiation Source
Based on the above, the NRC staff also be delivered to Room 6D59, Two Protection and Security Task Force
concludes that the proposed change White Flint North, 11545 Rockville (Task Force) is required by the Energy
Pike, Rockville, Maryland, from 7:30 Policy Act of 2005. As part of the Task
rmajette on PROD1PC71 with NOTICES

would not involve a significant


reduction in a margin of safety. a.m. to 4:15 p.m. Federal workdays. Force’s considerations, it is seeking
For further details with respect to the public input on the major issues before
Conclusion proposed action, see the licensee’s the Task Force. To aid in that process,
Based on this review, it appears that application dated September 10, 2003, the NRC is requesting comments on the
the three standards of 10 CFR 50.92(c) as supplemented on October 1, and issues discussed in this notice.

VerDate Aug<31>2005 14:20 Jan 10, 2006 Jkt 208001 PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 E:\FR\FM\11JAN1.SGM 11JAN1

Potrebbero piacerti anche