the leading sets of specialist law reports and the commentaries on selected decisions by the Keating Chambers Editors are always worth studying. The following passage on the recent Technology and Construction Court decision of WW Gear Construction Ltd v McGee Group Ltd [2010] 131 Con LR 63 made eye-catching reading: A well known arbitrator, who must remain nameless, is on record as saying that he had never known a contractors claim fail for want of notice. The commentary went on to make the point that the case comprised just such a failure and that the apparently hard line taken by the court promised others to come if time bars are not observed in claims procedure: the requirement to make a timely application in writing is a precondition to the recovery of loss and/or expense under Clause 4.21. The Contractor simply has no entitlement to recover such loss or expense unless and until it has made such an application (Mr Justice Akenhead). That firm stance was consistent with that taken by the Outer House of Scotlands Court of Session in Education 4 Ayrshire Ltd v South Ayrshire Council [2009] Scot CS CSOH 146, where Lord Glennie observed: The same factors which point to the clause being a condition precedent also point to the need for any notice served in accordance with the clause to comply strictly with its terms. Such an approach would also be consistent with those taken historically in other common law countries; in Canada, for example, in Jack Bradley (Maritimes) Ltd v Modern Construction in 1996 and in Australia in Wormald Engineering Pty Ltd v Resources Conservation Co International in 1988, where Chief Justice Rogers rationalised the upholding of a procedural condition precedent as follows: the regime prescribed will not necessarily work to give complete satisfaction every time. Nonetheless, it is the best machinery that could be devised to accommodate the intended purpose.
Construction Law International Volume 6 Issue 3 October 2011
Those engaging in or advising on
international projects under the FIDIC forms of contract will certainly wish to know if the effect of the time bar in Sub-Clause 20.1 of those forms is as discussed above. That well-known provision, which covers both extension of time and additional payment claims, imposes a 28-day time bar on giving notice, which is made a condition precedent by the words if the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment and the Employer shall be discharged from all liability in connection with the claim. This provision was a significant departure from the procedure under, for example, FIDIC 4th (FIDIC Red Book, 4th ed, 1987), although FIDIC had road-tested a condition precedent time bar in the 1995 Orange Book, where if the Contractor fails to comply with this sub-clause, he shall not be entitled to additional payment. FIDIC 4th had separate procedures for claiming time and more money respectively, Sub-Clause 53.1 (additional payment) had contained a 28day time bar, but the only sanction was in Clause 53.4, whereby failure to comply with the procedure limited the amount to which the contractor was entitled to that considered to be verified by contemporary records. The change to a condition precedent time bar was controversial, perhaps unsurprisingly, among contractors representatives: Why should the Contractor lose his entitlement on such formal grounds? asked the then Head of Legal Services at Skanska International Civil Engineering in the International Construction Law Review 1999; unduly harsh was the verdict of the Chairman of the Conditions of Contract Working Group of the European International Contractors organisation. Part of the objection taken by contractors was that there is no reciprocal time bar for claims by the employer: Sub-Clause 2.5 merely requires that the notice shall be given as soon as practicable after the 21
David Thomas QC
Employer became aware of the event or
circumstances giving rise to the claim. There is a 28-day time limit for employer claims in Sub-Clause 2.5 of the MDB Harmonised Edition of the Red Book, but still no conversion into a condition precedent by the threat of loss of entitlement. This lack of reciprocity may have greater significance than as a cause of disenchantment. German commentators take the view that Sub-Clause 20.1 is disproportionately prejudicial to the contractor and therefore ineffective according to para 9 AGBG. This is not the only jurisdiction where doubts have been expressed over the enforceability of the FIDIC provisions. In 2009, Marwan Sakr of Beirut suggested in the International Construction Law Review that the time-barring clauses may raise controversies under the laws of certain Arab countries, going so far as to suggest that such clauses may be unenforceable under Saudi law. Doubts of a very different sort have, of course, been expressed in some common law jurisdictions, where the shadow of the prevention principle has threatened to produce an unintended consequence of time bar clauses. The so-called Gaymark principle (Gaymark Investments v Waller Construction Group (1999)) in Australia ensured that the employer was denied a claim for liquidated damages because the contractor had failed to meet the notice requirements, thus depriving it of an extension of time for the employers delay. It should be noted that the English courts are not, or not all, convinced by this analysis. Jackson J, as he then was, in
22
Multiplex Constructions (UK) Ltd v Honeywell
Control Systems Ltd (2007), in which this author appeared as leading counsel, expressed his doubts as to whether this represents English law: If Gaymark is good law, then a contractor could disregard with impunity any provision making proper notice a condition precedent. There is perhaps some dissonance, if not irony, in the English courts giving strong endorsements of time bars as conditions precedent at the same time as FIDIC appears to be re-examining its 1999 stance. Under the 2008 Design Build Operate Gold Book, the contractor may be able to escape the severity of Sub-Clause 20.1 by exercising its right to submit to the Dispute Adjudication Board (DAB) any circumstances that it considers justify late submission of the claim. Sub-Clause 20.1 then provides: if the DAB considers that, in all the circumstances, it is fair and reasonable that the late submission be accepted, the DAB shall have the authority to overrule the relevant 28-day limit and, if it so decides, it shall advise the Parties accordingly. While no decision has been made, it is understood that the current FIDIC review of its contracts is at least considering extending this provision to all the Rainbow suite forms. If that were to be the case, time bars would be deprived of some of their bite and the DAB would become a significant arena for disputes as to admissibility of late claims. David Thomas is Queens Counsel at Keating Chambers in London. He has a general commercial practice with considerable expertise in construction and engineering disputes.
Construction Law International Volume 6 Issue 3 October 2011