Sei sulla pagina 1di 2

Federal Register / Vol. 71, No.

24 / Monday, February 6, 2006 / Notices 6101

results of this audit will be documented the training and experience credentials facsimile transmission to 301–415–1101
and submitted to the NRC at the end of of the first 10 AU applicants and 25% or by e-mail to hearingdocket@nrc.gov
a two-year period. However, DIGIRAD of any applications received after the and also to the Office of the General
will notify the NRC as soon as first 10. DIGIRAD will audit by Counsel by means of facsimile
practicable after identification of any endeavoring to locate and call transmission to 301–415–3725 or e-mail
discrepancies identified as a result of preceptors as well as Continuing to OGCMailCenter@nrc.gov. If such a
the audit. If no falsifications are Medical Education providers to verify person requests a hearing, that person
uncovered during the two-year period, the information given by the AU shall set forth with particularity the
DIGIRAD will discontinue the practice. applicants. This does not eliminate the manner in which his interest is
4. In addition, DIGIRAD will take requirement that DIGIRAD provide adversely affected by this Order and
other actions to ensure that similar complete and accurate information to shall address the criteria set forth in 10
violations will not recur. These actions the NRC on all AU applicants. The CFR 2.714(d).
will include the Vice President and results of this audit will be documented If a hearing is requested by a person
Corporate Radiation Safety Officer and submitted to the NRC at the end of whose interest is adversely affected, the
preparing and submitting a commentary a two-year period. However, DIGIRAD Commission will issue an Order
to (a) the Journal of Nuclear Medicine, will notify the NRC as soon as designating the time and place of any
(b) the Journal of Nuclear Medicine practicable after identification of any hearing. If a hearing is held, the issue to
Technology, and (c) the Journal of discrepancies identified as a result of be considered at such hearing shall be
Medical Physics to provide an the audit. If no falsifications are whether this Confirmatory Order shall
opportunity for other licensees in the uncovered during the two-year period, be sustained. An answer or a request for
industry to learn from this incident. DIGIRAD will discontinue the practice. a hearing shall not stay the effectiveness
DIGIRAD will advise NRC upon 2. The DIGIRAD Vice President and date of this order.
completion of these items and not later Corporate Radiation Safety Officer will
Dated this 27th day of January 2006.
than one year from the date of this prepare and submit a commentary
agreement. regarding this violation to the Journals For the Nuclear Regulatory Commission.
5. In light of the corrective actions of Nuclear Medicine, Nuclear Medicine Michael Johnson,
that DIGIRAD has taken or has Technology, and Medical Physics to Office of Enforcement.
committed to take as described in Items provide an opportunity for other [FR Doc. E6–1568 Filed 2–3–06; 8:45 am]
2, 3 and 4, the NRC agreed to issue a licensees in the industry to learn from BILLING CODE 7590–01–P
Severity Level III Notice of Violation to this incident.
DIGIRAD (10 CFR 30.9(a)), but to not 3. DIGIRAD will advise NRC upon
issue a Civil Penalty. This action will be completion of these items and not later NUCLEAR REGULATORY
publicly available in ADAMS and on than one year from the date of this COMMISSION
the NRC ‘‘Significant Enforcement agreement. [Docket No. 50–293]
Actions’’ Web site, and the NRC will The Director, Office of Enforcement,
issue a press release announcing this may relax or rescind, in writing, any of Entergy Nuclear Operations, Inc.;
action, as well as the actions DIGIRAD the above conditions upon a showing by Notice of Receipt and Availability of
has taken and committed to take to DIGIRAD of good cause. Application for Renewal of Pilgrim
address the violation. Any person adversely affected by this Nuclear Power Station Facility
6. DIGIRAD agreed to issuance of a Confirmatory Order, other than Operating License No. DPR–35 for an
Confirmatory Order confirming this DIGIRAD, may request a hearing within Additional 20-Year Period
agreement. 20 days of its issuance. Where good
In light of the actions DIGIRAD has cause is shown, consideration will be The U.S. Nuclear Regulatory
taken and agreed to take to correct the given to extending the time to request a Commission (NRC or Commission) has
violation and prevent recurrence, as set hearing. A request for extension of time received an application, dated January
forth in section III above, the NRC has must be made in writing to the Director, 25, 2006, from Entergy Nuclear
concluded that its concerns regarding Office of Enforcement, U.S. Nuclear Operations, Inc., filed pursuant to
the violation can be resolved through Regulatory Commission, Washington, Section 104b (DPR–35) of the Atomic
the NRC’s confirmation of the DC 20555, and must include a statement Energy Act of 1954, as amended, and 10
commitments as outlined in this of good cause for the extension. Any CFR part 54, to renew the operating
Confirmatory Order. request for a hearing shall be submitted license for the Pilgrim Nuclear Power
I find that DIGIRAD’s commitments as to the Secretary, U.S. Nuclear Station. Renewal of the license would
set forth in section III above are Regulatory Commission, ATTN: Chief, authorize the applicant to operate the
acceptable. However, in view of the Rulemaking and Adjudications Staff, facility for an additional 20-year period
foregoing, I have determined that these Washington, DC 20555. Copies of the beyond the period specified in the
commitments shall be confirmed by this hearing request shall also be sent to the current operating license. The current
Confirmatory Order. Based on the above Director, Office of Enforcement, U.S. operating license for the Pilgrim Nuclear
and DIGIRAD’s consent, this Nuclear Regulatory Commission, Power Station (DPR–35) expires on June
Confirmatory Order is immediately Washington, DC 20555, to the Assistant 8, 2012. The Pilgrim Nuclear Power
effective upon issuance. General Counsel for Materials Litigation Station is a Boiling Water Reactor
Accordingly, pursuant to Sections and Enforcement, to the Director of the designed by General Electric. The unit
103, 161b, 161i, 161o, 182, and 186 of Division of Regulatory Improvement is located in Plymouth, MA. The
the Atomic Energy Act of 1954, as Programs at the same address, and to acceptability of the tendered application
rmajette on PROD1PC67 with NOTICES1

amended, and the Commission’s MSHMC. Because of continuing for docketing, and other matters
regulations in 10 CFR 2.202 and 10 CFR disruptions in delivery of mail to United including an opportunity to request a
part 30 and 35, it is hereby ordered, that States Government offices, it is hearing, will be the subject of
by August 23, 2006: requested that answers and requests for subsequent Federal Register notices.
1. DIGIRAD will audit, for all future hearing be transmitted to the Secretary Copies of the application are available
NRC AU applicants, on a yearly basis, of the Commission either by means of for public inspection at the

VerDate Aug<31>2005 14:55 Feb 03, 2006 Jkt 208001 PO 00000 Frm 00069 Fmt 4703 Sfmt 4703 E:\FR\FM\06FEN1.SGM 06FEN1
6102 Federal Register / Vol. 71, No. 24 / Monday, February 6, 2006 / Notices

Commission’s Public Document Room (DPR–28) expires on March 21, 2012. NUCLEAR REGULATORY
(PDR), located at One White Flint North, The Vermont Yankee Nuclear Power COMMISSION
11555 Rockville Pike (first floor), Station is a Boiling Water Reactor
[Docket No. 030–11789]
Rockville, Maryland 20582 or designed by General Electric. The unit
electronically from the NRC’s is located in Vernon, VT. The Notice of Environmental Assessment
Agencywide Documents Access and acceptability of the tendered application Related to the Issuance of a License
Management System (ADAMS) Public for docketing, and other matters Amendment to Byproduct Material
Electronic Reading Room under including an opportunity to request a License No. 24–00196–07, for
accession number ML060300024. The hearing, will be the subject of Unrestricted Release of a Facility for
ADAMS Public Electronic Reading subsequent Federal Register notices. Saint Louis University, St. Louis, MO
Room is accessible from the NRC’s Web
site at http://www.nrc.gov/reading-rm/ Copies of the application are available AGENCY: Nuclear Regulatory
adams.html. In addition, the application for public inspection at the Commission.
is available at http://www.nrc.gov/ Commission’s Public Document Room ACTION: Issuance of environmental
reactors/operating/licensing/renewal/ (PDR), located at One White Flint North, assessment and Finding of No
applications.html, on the NRC’s Web 11555 Rockville Pike (first floor), Significant Impact for license
page, while the application is under Rockville, Maryland, 20582 or amendment.
review. Persons who do not have access electronically from the NRC’s
to ADAMS or who encounter problems Agencywide Documents Access and FOR FURTHER INFORMATION CONTACT:
in accessing the documents located in Management System (ADAMS) Public George M. McCann, Senior Health
ADAMS should contact the NRC’s PDR Electronic Reading Room under Physicist, Decommissioning Branch,
Reference staff at 1–800–397–4209, accession number ML060300078. The Division of Nuclear Materials Safety,
extension 301–415–4737, or by e-mail to Region III, U.S. Nuclear Regulatory
ADAMS Public Electronic Reading
pdr@nrc.gov. Commission, 2443 Warrenville Road,
Room is accessible from the NRC’s Web
A copy of the license renewal Lisle, Illinois 60532–4352; telephone:
site at http://www.nrc.gov/reading-rm/ (630) 829–9856; or by e-mail at
application for the Pilgrim Nuclear adams.html. In addition, the application
Power Station is also available to local gmm@nrc.gov.
is available at http://www.nrc.gov/
residents near the Pilgrim Nuclear SUPPLEMENTARY INFORMATION: The U.S.
reactors/operating/licensing/renewal/
Power Station at the Plymouth Public applications.html, on the NRC’s Web Nuclear Regulatory Commission (NRC)
Library, 132 South Street, Plymouth, is considering the issuance of an
page, while the application is under
MA 02360. amendment to NRC Byproduct Materials
review. Persons who do not have access
Dated at Rockville, Maryland, this 31st day License No. 24–00196–07, which is held
to ADAMS or who encounter problems by Saint Louis University (licensee).
of January, 2006. in accessing the documents located in
For the Nuclear Regulatory Commission. The amendment would authorize the
ADAMS should contact the NRC’s PDR unrestricted release of the licensee’s
Frank P. Gillespie, Reference staff at 1–800–397–4209, former Radioactive Waste Storage
Director, Division of License Renewal, Office extension 301–415–4737, or by e-mail to
of Nuclear Reactor Regulation.
Facility, located at 1008 South Spring
pdr@nrc.gov. Avenue, St. Louis, Missouri. The NRC
[FR Doc. E6–1566 Filed 2–3–06; 8:45 am]
A copy of the license renewal has prepared an Environmental
BILLING CODE 7590–01–P
application for the Vermont Yankee Assessment in support of this action in
Nuclear Power Station is also available accordance with the requirements of 10
to local residents near the Vermont CFR part 51. Based on the
NUCLEAR REGULATORY
Yankee Nuclear Power Station at the Environmental Assessment, the NRC
COMMISSION
following four public libraries: Vernon has determined that a Finding of No
[Docket No. 50–271]
Free Library, 567 Governor Hunt Rd, Significant Impact is appropriate. The
Vernon, VT 05354; Brooks Memorial amendment to Saint Louis University’s
Entergy Nuclear Operations, Inc. license will be issued following the
Notice of Receipt and Availability of Library, 224 Main Street, Brattleboro,
VT 05301; Hinsdale Public Library, 122 publication of this Environmental
Application for Renewal of Vermont Assessment and Finding of No
Yankee Nuclear Power Station Facility Brattleboro Rd, Hinsdale, NH 03451;
Significant Impact.
Operating License No. Dpr–28 for an and Dickinson Memorial Library, 115
Additional 20-Year Period Main St, Northfield, MA 01360. I. Environmental Assessment

The U.S. Nuclear Regulatory Dated at Rockville, Maryland, this 31st day Identification of Proposed Action
Commission (NRC or Commission) has of January, 2006. The proposed action would approve
received an application, dated January For the Nuclear Regulatory Commission. St. Louis University’s request to amend
25, 2006, from Entergy Nuclear Frank P. Gillespie, its license and release the licensee’s
Operations, Inc., filed pursuant to Director, Division of License Renewal, Office former waste storage facility for
Section 104b (DPR–28) of the Atomic of Nuclear Reactor Regulation. unrestricted use in accordance with 10
Energy Act of 1954, as amended, and 10 [FR Doc. E6–1567 Filed 2–3–06; 8:45 am] CFR part 20, subpart E. The proposed
CFR part 54, to renew the operating BILLING CODE 7590–01–P
action is in accordance with the Saint
license for the Vermont Yankee Nuclear Louis University’s request to the U.S.
Power Station. Renewal of the license Nuclear Regulatory Commission (NRC)
rmajette on PROD1PC67 with NOTICES1

would authorize the applicant to to amend its NRC Byproduct Material


operate the facility for an additional 20- License by letters dated October 31,
year period beyond the period specified 2005 (ADAMS Accession No.
in the current operating license. The ML060180319), and January 13, 2006
current operating license for the (ADAMS Accession No. ML060170694).
Vermont Yankee Nuclear Power Station Saint Louis University is licensed as an

VerDate Aug<31>2005 14:55 Feb 03, 2006 Jkt 208001 PO 00000 Frm 00070 Fmt 4703 Sfmt 4703 E:\FR\FM\06FEN1.SGM 06FEN1